The document is a valuation report for a residential flat located at FULL ADDRESS in Mumbai. It provides details of the property such as location, building details, unit details, surrounding locality, valuation methodology and comparable market transactions. It values the 596 sqft 2 BHK flat at Rs. 71,57,000 based on a market rate of Rs. 12500 per sqft for the area. It also provides the ready reckoner rate valuation of Rs. 66,00,000 and notes that the forced sale and distress values would be lower than the estimated market value.
building Site report for 1st year students of B.sc Civil Engineering... this will be helpful in case you have just joined Civil Engineering Class and Your Teacher ask you to prepare a report based on Basic Knowledge.
building Site report for 1st year students of B.sc Civil Engineering... this will be helpful in case you have just joined Civil Engineering Class and Your Teacher ask you to prepare a report based on Basic Knowledge.
CONSTRUCTION OF DISTRICT CONTROL BUILDING, CENTRAL STORE BUILDING & 33/11KV POWER SUBSTATION CONTROL ROOM AT CHAPRA,BIHAR
An Internship Report submitted in partial fulfilment of the
requirements for the degree
of
B.Tech (Civil Engineering)
by
VIJAY KUMAR SINGH
13BCL0001
VIT UNIVERSITY
VELLORE – 632 014, TAMILNADU
Presentation is trying to define the intent , content, methods and scope of arbitration and tendering and its implications for the architectural practice.
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construc...Shrikant Kate
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construction Management _ Final Year (BE) _ Department of Civil Engineering _ TAE _ SPPU _ by Shrikant R. Kate
Labour laws and financial aspects of construction projects Labour laws. studies,
Need and importance of labour laws, study of some important labour laws associated with construction sectorworkmans compensation act 1923
Building and other construction workers act 1996, child labour act, interstate migrant workers act Financial aspects of construction projects.
Capital investments: importance and difficulties, means of finance,
Working capital requirements, project cash flow projections and statements, project balance sheet
Profit loss account statements.
Industrial Training report Civil Engineering.JAPJEETSINGH13
Industrial training report for civil engineering major training final year. All rights to the images, blueprints and content is reserved.
Only available for educational purposes.
professional practice and valuation topic of ppt:-valuationtirath prajapati
Valuation is the technique of estimation or determining the fair price or value of property such as building, a factory, other engineering structures of various types, land etc.
Presentation on building bye laws as per GTU (syllabus) building & town planning.
It is my first presentation on slide share so please give suggestion on given topic or any other requirement.
Thank you.
CONSTRUCTION OF DISTRICT CONTROL BUILDING, CENTRAL STORE BUILDING & 33/11KV POWER SUBSTATION CONTROL ROOM AT CHAPRA,BIHAR
An Internship Report submitted in partial fulfilment of the
requirements for the degree
of
B.Tech (Civil Engineering)
by
VIJAY KUMAR SINGH
13BCL0001
VIT UNIVERSITY
VELLORE – 632 014, TAMILNADU
Presentation is trying to define the intent , content, methods and scope of arbitration and tendering and its implications for the architectural practice.
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construc...Shrikant Kate
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construction Management _ Final Year (BE) _ Department of Civil Engineering _ TAE _ SPPU _ by Shrikant R. Kate
Labour laws and financial aspects of construction projects Labour laws. studies,
Need and importance of labour laws, study of some important labour laws associated with construction sectorworkmans compensation act 1923
Building and other construction workers act 1996, child labour act, interstate migrant workers act Financial aspects of construction projects.
Capital investments: importance and difficulties, means of finance,
Working capital requirements, project cash flow projections and statements, project balance sheet
Profit loss account statements.
Industrial Training report Civil Engineering.JAPJEETSINGH13
Industrial training report for civil engineering major training final year. All rights to the images, blueprints and content is reserved.
Only available for educational purposes.
professional practice and valuation topic of ppt:-valuationtirath prajapati
Valuation is the technique of estimation or determining the fair price or value of property such as building, a factory, other engineering structures of various types, land etc.
Presentation on building bye laws as per GTU (syllabus) building & town planning.
It is my first presentation on slide share so please give suggestion on given topic or any other requirement.
Thank you.
ALTA Land Title Survey, ACSM Land Title Survey, National Survey, Commercial Survey, Boundary Survey , Condominium Plats, Subdivision Plats, Flood Elevation Certificates, Topographical Survey, Lot Line Adjustments, Boundary Line Agreements, Site Planning, Site Design, Construction Staking, Survey Consulting, ALTA Consulting, ACSM Consulting, Legal Descriptions, Easements, Subdivision Amendments, Slope Analysis, Volume Calculations, Interior Floorplan Measurements, As-Built Surveys, City Lot Surveys, Claim Surveys, Control Network Engineering, Civil Engineering, Sewer and Water Design, Residential Structure Engineering, Commercial Structure Engineering, Commercial Engineer, Subdivision Design Engineering, Site Plans, Road Design Engineering, Irrigation Systems, Solid Waste and Environmental Services, Site Grading, Storm Water Drainage and Flood Control, Water Supply, Distribution and Treatment, Municipal Infrastructure Design, Land Development Services, Construction Management and Observation, Traffic Analysis, Land Use, Constraint Mapping, Dams and Reservoirs, Groundwater, Zoning Analysis, Zoning Reports, Zoning Letters, Preliminary Land Title Coordination, Final Land Title Coordination, Phase One Environmental Coordination, Phase 1, Environmental Site Assessments, Property Condition Assessments, Seismic Reports, Cost Segregation Studies, Aerial Surveys, Engineering, National Commercial Surveying, Survey Consulting and Coordination, Design Ready Surveys, Easement Surveys, Right-of-Way Surveys, Wind Power and Communication Surveys, Pipeline Surveys, Site Information Reports (SIR), Seminars, Training, CLE Classes, Accident Reconstruction, Property Improvement Survey, Property Boundary Survey, Improvement Location Certificate, Civil Engineering Design, Foundation and Spot Survey, Final Survey, Mortgage and Lot Survey, Right-of-Way, Topographical Survey, Tree Survey, Route Survey, Volumetric Survey, Construction Survey, Legal Description, F.E.M.A. Certificate, Elevation Certificates, FEMA Floodplain Surveys, Global Positioning Systems, Section Corner Restoration, Wireless Tower Sites, Wind Energy Surveying, Transmission Surveying, Section Corner Restoration, Industrial Plant Drawings, Industrial Plant Data Stakeout, AutoCAD Drafting Services
How to Package a Loan Request for Construction, Rehab, and Commercial LoansBeau Eckstein
SFR Ventures Inc. requires that a Financing Request Package accompany all loan requests. The suggested outline included in this packet is very comprehensive and may request information that is not relevant to a particular loan request. This template has been utilized by the principals of SFR Ventures Inc. to effectively raise $400M+ in debt and equity for various real estate investments over the years. This template focuses primarily on residential rehab, construction, and development loans and provides a consistent process for borrowers to streamline the financing process and accelerate the funding timeline to meet the closing deadlines. Timely submission of a completed Financing Request Package can mean funding in as little as 5–7 business days.
Please be advised, SFR Ventures Inc. receives a high volume of loan requests. We aim to review and respond to loan requests within 48 hours of receiving the Financing Request Package. SFR Ventures Inc. requires certain criteria for a loan request to be considered. If the following criteria are not met, your loan request will not be reviewed:
• Borrower must have real estate experience with a proven track record
• Borrower is required to have a minimum of 20% equity into the deal
• The loan-to-value (LTV) may not exceed 70%
About SFR Ventures Inc.
SFR Ventures Inc. seeks to establish long-term relationships with experienced real estate investors, owner operators, developers, and brokers that are built upon trust, client service, and executional efficiency.
Please submit your Financing Request Package or any specific questions related to your particular transaction to beau@sfrventures.com
Beau Eckstein
Managing Partner
Direct: 925.852.8261
About Demand and supply of real estate By Nino joseph MihilliNinoJosephMihilli12
There is a wide history on the real estate market. Nearly one-third of America is into real estate investments. The size and measure of the real estate market has made the industry attractive and money-rotate for thousands of investors. Demand and supply are a few elements of the business sector that have affect the business sector greatly. Fundamentally, there are many factors that affect demand and supply of real estate and they include;
Impact of RERA on consumer buying behaviour summer project complete(1)Ajay Singh
As we know real estate (regulation and development) Act 2016 has been passed. Real Estate Regulatory Authority came into this act from May 2017 in Maharashtra
This survey was conducted on a sample size of 201 people who stay in Mumbai and are searching house in Mumbai . The main objective of this survey was to know the consumer buying behavior while buying real estate property. This research has been performed in Mumbai after the implementation of RERA so we can know the impact of RERA on consumer buying behaviour.
Raising Canes in Prime Interstate 10 On/Off Ramp LocationKevin Boeve
Marcus & Millichap is pleased to present for sale a Raising Cane’s located in San Bernardino, California. The property is leased under a 15-year triple-net lease with four, five-year options.
Commercial valuation of property is the prime requirement for investments. Real estate values depend on many elements, such as the present cost of the land, taxation on the lad, the depreciation rates, and others. It is essential that a feasibility analysis be conducted first before the land is invested into. Given this context this report basically attempts to do a feasibility analysis for a property using the Estate Master Feasibility analysis tool. A number of inputs are given based on a case scenario for property. The report attempts to evaluate and critically discusses the real world scenario presented by the Estate master for each of these sets of inputs. A feasibility analysis based on commercial valuation methodology is carried out first, followed by a valuation of the site as is. The residual value is calculated here. The report then calculates the project returns based on the residual values using the Estate Master and in the second part of the report, sensitivity and risks analysis are covered.
Master of Architecture Thesis Healthcare Project management "A Structure Appr...Rohit Digra
Master of Architecture Thesis Healthcare Project management "A Structure Approach" the thesis is based on project management of hospitals in mumbai,well it is all about the reason why many hospitals in mumbai getting delay and how I have overcome it.
Registration council of architecture step by step guide
Note : I have mentioned for submitting original degree to council for registration, it has been withdrawn from the council in their notification dated 30th November 2017,So from now onward you have to not submit your original degree, you have to just send photocopy/xerox of degree.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdfTechSoup
In this webinar you will learn how your organization can access TechSoup's wide variety of product discount and donation programs. From hardware to software, we'll give you a tour of the tools available to help your nonprofit with productivity, collaboration, financial management, donor tracking, security, and more.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
2024.06.01 Introducing a competency framework for languag learning materials ...
Valuation Format
1. VALUATION REPORT
FOR
MR/M/s. etc
OF
RESIDENTIAL – FLAT/COMMERCIAL OFFICE/INDUSTRIAL LAND BUILDING
etc.
AT
FLAT NO.,TH FLOOR,'' WING OF BUILDING NO.1,
(W),MUMBAI – 400067.
BY
,
Architects, Planners, Valuers.
2. 2
VALUATION REPORT
Purpose – Submission to Bank Ltd.
Ref. No.: 17/05049/YES Date:
Branch Name Mumbai Type of case
Valuer’s Name Date of visit
Visiting Engg Name Time of visit
Case Ref. No Date of report
Person contacted for property inspection with contact
details
Client Name & Contact No.
BASIC DETAILS
1 Applicants Name ABC
Name of
Owners
ABC
2 Type of property Residential Flat Current usage Residential Flat
3
Address of property /
Site Address
Address as per
documents
4
Has the valuer done valuation of this property before? If yes, for
whom & when.
No
SORROUNDING AND LOCALITY DETAILS
5 Location
Zoning as per Master Plan /
Development plan
Residential
Class of locality (High / Middle Class /
Lower / Negative)
Middle Class
Site (Developed / under-developed) Developed
Proximity from civic amenities / public
transport
1 Km
Nearest Railway Station
Nearest Bus Stop
6 Nearest Landmark
7
Distance from City
Centre
NA
8 Condition and width of approach road : - Good,9 Mt Wide Road
3. 3
PROPERTY DETAILS
9
Brief description of the
property
The subject property is a flat in a S + P + 18 Floor RCC building
known as FULL ADDRESS The surrounding area is
commercial cum residential area. THE DATE OF
AGREEMENT ________,THE PROPERTY IS
FREEHOLD/LEASEHOLD ETC.BEARING CTS NO______
BUILDING HAS _____NO FLOORS,THE BUILDING IS
PREENGINEERED /RCC CONSTRUCTION THE PROPERTY
IS SITITATED _____FLOORS FLAT/SHOP/ROW HOSUE
ETC. FLAT NUMBER THE CARPET AREA/BUILTUP AREA
OF THE FLAT,THE PROPERTY HAS ELECTRIC
CONCEALED,FLOORING FINISHESWIRTE DOWN ETC.
THE AGE OF BUILDING,YEARS OF
CONSTRUCTION,NEAR BY LANDMARKThe market rate in
this area is in range of between Rs. to per Sq ft of BUA.
The rate which is considered for the valuation is Rs. per
Sq.ft of BUA
10 Internal visit done Yes
11 Occupant
Vacant/Occupied
Name of Occupant
Relation with
applicant
Self / Tenant / any other
12 Building details
Property Demarcated Yes / No
Property Identified
through
Residential
Type of structure RCC / Load Bearing
Land/Plot Area NA
No of Blocks/Wings 2 Wings A & B
No of Units per floor 6 Nos per Wing
No. of Floors 18 Floors
No. of Lifts 2 Nos
Amenities -
13 Unit details
Located on Floor No. 8th Floor
No. of rooms / Unit
configuration
2 B.H.K
Remarks on view
from property
14
Present condition of the
property:
Exterior Building in good condition.
Interior Fair condition, well maintained
15 Age of the property 20 Years Residual life 35 Years
4. 4
16 Boundaries North South East West
Actual on site Lobby Open Space Open Space
As per Title document - - - -
Boundaries matching with Sale Deed (Yes / No) -
SANCTION PLAN APPROVAL & OTHER DOCUMENTS DETAILS
17 Sanctioned plans details -
18
Construction
permission /
Commencement
Certificate / OC / BCC
Occupation Certificate
Commencement Certificate:
19 Ownership type Freehold
20
Property documents
verified (Any others)
NA
21
Is the property within
Municipal Limits
MCGM
22
Permissible usage as
per
sanctioned/approved
plan
-
23
Setbacks
As per
plan
As per
Bye- Laws
Actual at
site
Extra
Coverage
deviation
as per
Plan
Extra
Coverage
deviation
as per bye-
laws
Front NA NA 6 M - -
Side 1 (Right NA NA 4.5 M - -
Side2 (Left) NA NA 4.5 M - -
Rear NA NA 6 M - -
Deviations if any
24 Demolition Risk High / Medium / Low / Nil.
25 VALUATION
Area Details
As per Agreement /
Sale Deed
Sft Carpet / BUA /
SBUA
As per Plan Sft Carpet / BUA
As per Measurement Sft Carpet / BUA
A
1
Land + Construction Method (Applicable for Villa / Bunglow / Row House /
Industrial)
Description Area in Sft Rate per Sft Value in Rs.
5. 5
Land area NA
Construction area
(Const rate as per
present condition of the
property)
Value of Land + Construction in Rs. (A1)
A
2
Comparison Method
Built up Area Loading in % -
Saleable area - Rate per Sft 12,500/- Sq.Ft
Value of property as per comparison method (A2)
B Value of Amenities if applicable
a) No of car parks Rate per car parking Value of car park
2 Nos
b) Other charges in Rs. (Lump Sum) -
Total Amenities charges (B) -
Total Fair Market Value of the property: - A1 or
A2 + B
Rs.
Forced Sale Value / Distress Value Rs.
Ready Reckoner rate / Circle rate Rs.
Approx. Rentals in case of 100% complete
property
Rs.
Insurance value / Re-construction cost Rs.
26 Market Comparable
a
)
Property Details
Value Rs.
Date of
Transaction
-
b) Property Details
Value Rs.
Date of
Transaction
-
27 Stage of Construction
Details of stage of
construction
NA
%age Progress - %age Reco -
28 Remarks
Negative Remarks Positive Remarks
Nil Flat is in good condition.
6. 6
29 Latitude: Longitude:
Location Sketch: Attached (GOOGLE EARTH)
Property Sketch: Please refer Annexure I (AUTOCAD/HAND SKETCH)
Property Photographs: Minimum 4 photographs (2 external and 2 internal)
Declaration:
I/We hereby declare that:
1. Our representative physically inspected the property.
2. We have no direct/indirect interest in the property valued.
3. Report is prepared based on the information furnished to us or documents submitted or
shown to us by the client.
4. The fair market value indicated in the report is an opinion of the value prevailing on the
date of the said report and is based on market feedback on values of similar properties.
5. The client is free to obtain other independent opinions on the same. The fair market value of
such properties/localities may increase or decrease depending on the future market
conditions and scenarios.
6. This report does not certify of confirm any ownership or title of the property that has been
valued. The ownership papers/sale deeds may please be verified at your end to ascertain
the right title & area.
7. The services provided by ________________ to the Client will be limited to their use. The
Report should not be used for any other purpose.
8. The Report will reflect matters, as they currently exist. Changes may materially affect the
information contained in the Report.
9. It should be noted that report would be based upon the facts and evidence available at the
date of assessment. Periodical review of the same may be required. Changes in socio-
economic, economic policy and political conditions could result in a substantially different
situation than those presented at the stated effective date ___________assumes no
responsibility for changes in such external conditions.
10. We do not possess legal expertise and hence recommend you to take opinion of legal expert
in order to ensure that there are no elements, restriction or charges contained which are
likely to have detrimental effect upon the value or marketability of property.
11. In the preparation of the Report, we have relied on the following information:
a. Information provided to us by the client and its affiliates and subsidiaries and third
parties;
b. Other relevant information provided to us by the Client and its affiliates and
subsidiaries at request;
7. 7
c. Other relevant information available to us or publicly available.
For M/s.______________
B.Arch.
Architects, Planner, Govt. Regd. Valuer.
Date:
Place: Mumbai
Stamps & Signature
8. Property
Builtup Area
(Sqft)
RR Rate
(Rs/ per Sq
mt)
Formula rr
rate -
construction
cost X
depreciation
RR Value (Rs.)
builtup
area/10.764 X
rr rate
RR Value Say
Rs.
Flat 596 119200 66,00,074 66,00,000
Value As per Market Rate
Property
Builtup Area
( in Sqft)
Market rate
(Rs/ per Sq.ft.)
Amount (Rs.)
area X market
rate
Dep (Rs.) Age/
Life 20/55
area x
construction
cost x residual
value 0.9 x
age/life
FMV (Rs.)
amount -
depreciation
Say FMV
RSV
(5% less)
DSV ( 15% less
than FMV)
Flat 596 12500 74,50,000 2,92,582 71,57,418 71,57,000
Car Parking 3,00,000
74,57,000
ANNEXURE II
63,38,45070,84,150
Value As per RR Rate
M/s.
The RR Rate for flat is Rs. 1,24,700/- per Sq.mt. Cost of construction is taking for valuation of Rs. 27,500/- per Sq.mt. for RCC structure. Depreciation
is taking 20% on Cost of construction based on age of building as per the RR guideline rules.
Address