The audit report summarizes the findings of an occupational health and safety management system audit conducted at an organization. Several critical errors were identified across various audit principles, though some areas showed good findings. Recommendations are provided for each error, such as implementing documented procedures for managing hazards, legislative compliance, and ensuring approved codes of practice are followed. While the audit revealed issues, its objectives of evaluating health and safety performance and identifying areas for improvement were achieved. Immediate action is needed to address the most serious errors to ensure legislative compliance and prevent potential harm.