The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
- Lost Creek is the company's flagship in-situ recovery uranium facility which began production in 2013 and has exceeded production targets.
- Resources at Lost Creek have increased 250% since 2011 with measured, indicated and inferred resources now totaling over 21 million pounds.
- A preliminary economic assessment outlines potential production of 13.8 million additional pounds over the life of the Lost Creek mine.
- The company's next development project is Shirley Basin, also located in Wyoming.
The document provides an overview of Ur-Energy's Lost Creek ISR uranium facility and 2015 year-end results. Some key points:
- Lost Creek has achieved "steady state" production and delivered its 1,000,000th pound of U3O8 in 2015. Costs have decreased from $21.98/lb in 2013 to $16.27/lb in 2015.
- Resources at Lost Creek and adjacent areas increased by 4.6 million lbs measured/indicated and 1.7 million lbs inferred in 2015.
- A preliminary economic assessment extended the mine life at Lost Creek to 2031 and increased resources by 3.1 million lbs measured/indicated and 1.4 million lbs
The document provides an overview of Ur-Energy's Lost Creek ISR uranium facility and 2015 year-end results. Some key points:
- Lost Creek has achieved "steady state" production and delivered its 1,000,000th pound of U3O8 in 2015. Costs have decreased from $21.98/lb in 2013 to $16.27/lb in 2015.
- Resources at Lost Creek and adjacent areas increased by 4.6 million lbs measured/indicated and 1.7 million lbs inferred in 2015.
- A preliminary economic assessment estimates production of 6.3 million lbs at $14.54/lb operating cost from the Shirley Basin project.
- Multiple sales contracts are
This document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's Lost Creek uranium facility in Wyoming, which began production in 2013 and produced its 1 millionth pound of uranium in 2015. It also mentions Ur-Energy's exploration properties and resource growth. Additionally, it provides background on Ur-Energy's leadership team and board of directors as well as the current state of the uranium market, including supply and demand fundamentals.
The document provides an overview of Ur-Energy's third quarter 2015 results and operations. It discusses steady state production at Lost Creek reaching 1 million pounds of U3O8, an increase in measured resources at Lost Creek, ongoing construction and drilling at Lost Creek and Shirley Basin, and sales of approximately 630,000 pounds of U3O8 in 2015 at an average price of $50.10/lb. Costs per pound continue to decrease and the company expects to release an updated resource estimate and economic analysis in Q4.
This document provides an overview of Ur-Energy Inc.'s 2016 Q2 results. It discusses steady production at the Lost Creek uranium facility, with over 1.86 million pounds produced to date. It also outlines resource growth at Lost Creek through 2015 updates, and plans to advance the Shirley Basin project. Financial details are given on sales, revenues, costs of production, and the company's cash position.
This document provides a summary of Ur-Energy Inc., a uranium mining company. It discusses Ur-Energy's Lost Creek in-situ recovery uranium facility, which began production in 2013 and produced its 1 millionth pound of uranium in 2015. It also mentions Ur-Energy's Shirley Basin project and expansion of resources at Lost Creek. The document contains forward-looking statements and projections regarding future production, costs, and the uranium market. It provides an overview of Ur-Energy's management team, sales agreements, development pipeline, and growth strategy.
This document provides an overview of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy has established steady-state production at its flagship Lost Creek ISR uranium facility in Wyoming and expanded resources through exploration drilling.
- The company's next development project is Shirley Basin in Wyoming, for which a preliminary economic assessment was completed. Permit applications are expected in the fourth quarter of 2015.
- Ur-Energy has a balanced cashflow plan for 2016 secured through an amended loan repayment schedule and scheduled uranium deliveries.
Ur-Energy June 2016 Corporate PresentationBrooke Rock
- Lost Creek ISR uranium facility in Wyoming has been in steady-state production since 2013, producing over 1.73M lbs of U3O8 to date at low costs.
- Resources at the Lost Creek property have increased significantly since 2011 through exploration, totaling over 14.6M lbs of measured and indicated resources currently.
- The Shirley Basin project in Wyoming is the company's next development project, with a positive preliminary economic assessment completed in 2015 and permitting applications underway.
The document provides an overview of Ur-Energy's Lost Creek ISR uranium facility and 2015 year-end results. Some key points:
- Lost Creek has achieved "steady state" production and delivered its 1,000,000th pound of U3O8 in 2015. Costs have decreased from $21.98/lb in 2013 to $16.27/lb in 2015.
- Resources at Lost Creek and adjacent areas increased by 4.6 million lbs measured/indicated and 1.7 million lbs inferred in 2015.
- A preliminary economic assessment extended the mine life at Lost Creek to 2031 and increased resources by 3.1 million lbs measured/indicated and 1.4 million lbs
The document provides an overview of Ur-Energy's Lost Creek ISR uranium facility and 2015 year-end results. Some key points:
- Lost Creek has achieved "steady state" production and delivered its 1,000,000th pound of U3O8 in 2015. Costs have decreased from $21.98/lb in 2013 to $16.27/lb in 2015.
- Resources at Lost Creek and adjacent areas increased by 4.6 million lbs measured/indicated and 1.7 million lbs inferred in 2015.
- A preliminary economic assessment estimates production of 6.3 million lbs at $14.54/lb operating cost from the Shirley Basin project.
- Multiple sales contracts are
This document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's Lost Creek uranium facility in Wyoming, which began production in 2013 and produced its 1 millionth pound of uranium in 2015. It also mentions Ur-Energy's exploration properties and resource growth. Additionally, it provides background on Ur-Energy's leadership team and board of directors as well as the current state of the uranium market, including supply and demand fundamentals.
The document provides an overview of Ur-Energy's third quarter 2015 results and operations. It discusses steady state production at Lost Creek reaching 1 million pounds of U3O8, an increase in measured resources at Lost Creek, ongoing construction and drilling at Lost Creek and Shirley Basin, and sales of approximately 630,000 pounds of U3O8 in 2015 at an average price of $50.10/lb. Costs per pound continue to decrease and the company expects to release an updated resource estimate and economic analysis in Q4.
This document provides an overview of Ur-Energy Inc.'s 2016 Q2 results. It discusses steady production at the Lost Creek uranium facility, with over 1.86 million pounds produced to date. It also outlines resource growth at Lost Creek through 2015 updates, and plans to advance the Shirley Basin project. Financial details are given on sales, revenues, costs of production, and the company's cash position.
This document provides a summary of Ur-Energy Inc., a uranium mining company. It discusses Ur-Energy's Lost Creek in-situ recovery uranium facility, which began production in 2013 and produced its 1 millionth pound of uranium in 2015. It also mentions Ur-Energy's Shirley Basin project and expansion of resources at Lost Creek. The document contains forward-looking statements and projections regarding future production, costs, and the uranium market. It provides an overview of Ur-Energy's management team, sales agreements, development pipeline, and growth strategy.
This document provides an overview of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy has established steady-state production at its flagship Lost Creek ISR uranium facility in Wyoming and expanded resources through exploration drilling.
- The company's next development project is Shirley Basin in Wyoming, for which a preliminary economic assessment was completed. Permit applications are expected in the fourth quarter of 2015.
- Ur-Energy has a balanced cashflow plan for 2016 secured through an amended loan repayment schedule and scheduled uranium deliveries.
Ur-Energy June 2016 Corporate PresentationBrooke Rock
- Lost Creek ISR uranium facility in Wyoming has been in steady-state production since 2013, producing over 1.73M lbs of U3O8 to date at low costs.
- Resources at the Lost Creek property have increased significantly since 2011 through exploration, totaling over 14.6M lbs of measured and indicated resources currently.
- The Shirley Basin project in Wyoming is the company's next development project, with a positive preliminary economic assessment completed in 2015 and permitting applications underway.
UR-Energy Q1 2016 Teleconference and WebcastBrooke Rock
This document summarizes Ur-Energy's 2016 Q1 teleconference and webcast. It discusses Lost Creek's steady production and resource growth. Lost Creek has produced 1.73 million pounds of U3O8 since Q3 2013. Resources have increased by 4.6 million pounds through exploration. Ur-Energy realizes better sales prices through long-term contracts spanning 2013-2021. The document also provides an overview of the Shirley Basin project preliminary economic assessment and regulatory approvals.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and exploration projects. It notes that Lost Creek has achieved steady-state production and delivered its 1 millionth pound of uranium. Resources have increased at Lost Creek and permitting is underway for the Shirley Basin project. The document also provides an overview of the uranium market, including supply and demand fundamentals and the restart of nuclear reactors in Japan.
This presentation discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's Lost Creek uranium production facility, which recently produced its 1 millionth pound of uranium, and discusses plans to develop the Shirley Basin project. The presentation also provides an overview of the current state of the uranium market, including supply and demand fundamentals and the impact of Japan restarting nuclear reactors. Financial information on Ur-Energy's share structure and analysts coverage is also presented.
Ur-Energy November 2016 Corporate PresentationBrooke Rock
Ur-Energy provides a summary of its Lost Creek uranium facility and resources. Lost Creek has produced over 2 million pounds of U3O8 through Q3 2016 and continues steady-state production. Resources have increased 250% since 2011 with measured and indicated resources now totaling over 14.6 million pounds. An amended preliminary economic assessment estimates Lost Creek can produce an additional 13.8 million pounds over its lifetime.
- The document discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming.
- It summarizes Ur-Energy's Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with head grades 3-4 times projections.
- It also mentions Ur-Energy's exploration properties, including an upcoming PEA on the Shirley Basin project, and provides an overview of the company's operations and financial position.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's Lost Creek in-situ recovery uranium mine, which began production in 2013, and discusses plans to develop the nearby Shirley Basin project. Production results from Lost Creek are exceeding initial projections due to higher-than-expected uranium grades. The document also notes that long-term uranium sales contracts have been signed to provide revenue through 2021 and that resources have increased through exploration at the Lost Creek property.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming, USA. It summarizes Ur-Energy's Lost Creek uranium production facility and its Shirley Basin development project. It also discusses the state of the global uranium market, including growing nuclear power demand, constrained primary supply, and the need for new producers like Ur-Energy to help fill the gap.
Ur-Energy's August 2017 Corporate PresentationUr-Energy
- Lost Creek ISR uranium facility has been in consistent production for 4 years, capturing over 2.3 million pounds of U3O8. Results show it is a reliable, low-cost producer.
- The company has secured future revenue through term sales agreements totaling over 2.4 million pounds of U3O8 from 2017-2021 at an average price of $50/lb.
- Resources at Lost Creek have increased 250% since 2011 through exploration and development, with measured and indicated resources now totaling over 14.6 million pounds.
This document provides an overview of Ur-Energy Inc. and its uranium production operations. It summarizes Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production in 2013, and its Shirley Basin project. It also discusses the state of the uranium market and supply and demand fundamentals. Finally, it provides production and cost data from Lost Creek's operations that demonstrate it is a reliable, low-cost producer.
- Lost Creek ISR uranium project in Wyoming has been in production since 2013, with production exceeding projections and head grades 3-4 times higher than estimated.
- A 2013 preliminary economic assessment estimated 9.2 million pounds of recoverable uranium over the life of the mine with low production costs and strong economics.
- The company has long term sales contracts in place through 2020 to sell uranium at prices above costs of production, providing revenue stability.
Ur-Energy's November 2017 Corporate PresentationUr-Energy
This document contains forward-looking statements regarding Ur-Energy's ability to maintain production operations at Lost Creek, deliver product on schedule, and further explore and develop projects like Shirley Basin. It also discusses Ur-Energy's recent sales agreements, production levels, and financial results. The document notes that analysts from various firms follow and report on Ur-Energy, and provides context on trends in the nuclear energy and uranium markets.
Ur-Energy Q3 Webcast & Teleconference Power PointBrooke Rock
This document provides an overview and update of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's recent quarterly production results from its Lost Creek ISR uranium facility, discusses its resource growth and future development plans, and outlines its sales contracts and revenue expectations for 2016. The document cautions that certain statements regarding future plans and projections are forward-looking in nature.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and Pathfinder Shirley Basin project. It summarizes Ur-Energy's commercial progress in 2014, including establishing production at Lost Creek and completing sales agreements. It also outlines the company's management team and board of directors as well as the positive long-term fundamentals of the uranium market, including growing nuclear power usage and constrained primary supply. However, the presentation contains forward-looking statements that are subject to risks and uncertainties.
UEX Corporation is a uranium exploration and development company with projects located in the Athabasca Basin of northern Saskatchewan, Canada. It has a portfolio of uranium deposits and exploration projects including 100% ownership of its Eastern Athabasca Projects and a 49.1% interest in Western Athabasca Projects through a joint venture with AREVA. UEX has evolved over 15 years of operations through exploration successes, resource delineations, economic assessments, and joint venture partnerships. The company's strategy is to advance its existing resource assets and conduct innovative exploration with the goal of new discovery as the uranium market improves.
UEX Corporation is a uranium exploration and development company with projects located in the Athabasca Basin of northern Saskatchewan, Canada. It has a portfolio of uranium deposits and exploration projects including 100% ownership of its Eastern Athabasca Projects and a 49.1% interest in Western Athabasca Projects through a joint venture with AREVA. UEX has evolved over 15 years from initial public offering to outlining resources at multiple deposits and conducting preliminary economic assessments and advanced exploration through partnerships and acquisitions. The company aims to increase resources at existing deposits and make new discoveries through innovative exploration programs to create value for shareholders.
UEX Corporation is a uranium exploration and development company with a portfolio of projects located in the Athabasca Basin of northern Saskatchewan, Canada. The company has over 69 million pounds of uranium indicated resources and over 16 million pounds of inferred resources located across its 100% owned Hidden Bay and Shea Creek projects. UEX is also a 49.1% joint venture partner with AREVA on the Western Athabasca Projects. The company's strategy is to advance its projects through exploration and resource growth with the goal of future development when uranium prices improve to support economic extraction.
Ur-Energy July 2016 Corporate PresentationBrooke Rock
- Lost Creek ISR uranium facility in Wyoming has been in steady-state production since 2013, producing over 1.73M lbs of U3O8 to date at low costs.
- Resources at the Lost Creek property have increased significantly since 2011 through exploration, with measured and indicated resources totaling over 14.6M lbs U3O8.
- The company aims to be a "pipeline producer" through developing its projects beyond Lost Creek, with the next project being Shirley Basin in Wyoming.
Ur-Energy August 2016 Corporate Presentation Brooke Rock
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming which began production in 2013 and has produced 1.86M lbs of U3O8 through June 2016. Resource expansion has increased measured, indicated, and inferred resources by 4.6M lbs, 1.7M lbs, and 6.4M lbs respectively since 2015.
- The company has secured long-term sales contracts through 2021 at an average price of $49.81/lb for approximately 3.1M lbs to provide revenue certainty in the current market.
- Ur-Energy is advancing the Shirley Basin project in Wyoming and recently filed permit applications, with the goal of developing additional uranium production centers in
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek uranium production facility in Wyoming and its Shirley Basin project in South Dakota. It also discusses the outlook for the uranium market, noting increasing global nuclear power usage while many primary uranium suppliers have cut production. Ur-Energy believes it is well-positioned to help meet growing US nuclear fuel demand with its domestic uranium production facilities.
Semantik adalah kajian tentang makna pada berbagai tingkatan bahasa seperti morfem, kata, frasa, ayat, dan wacana. Terdapat berbagai teori semantik yang mencoba menjelaskan konsep makna, seperti teori imej, behaviorisme, analisis komponen, dan logika simbolik. Masing-masing teori memiliki kelebihan dan kekurangan dalam penjelasan makna.
The Kessef Group offers mortgage lenders support to close more loans in 10 days or less through their in-house processing, underwriting, and funding. They also help increase revenue through rebates paid when loans fund rather than when sold, and fewer regulations. Kessef additionally aims to help lenders grow their clientele through exclusive leads, marketing support, and builder partnership programs.
UR-Energy Q1 2016 Teleconference and WebcastBrooke Rock
This document summarizes Ur-Energy's 2016 Q1 teleconference and webcast. It discusses Lost Creek's steady production and resource growth. Lost Creek has produced 1.73 million pounds of U3O8 since Q3 2013. Resources have increased by 4.6 million pounds through exploration. Ur-Energy realizes better sales prices through long-term contracts spanning 2013-2021. The document also provides an overview of the Shirley Basin project preliminary economic assessment and regulatory approvals.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and exploration projects. It notes that Lost Creek has achieved steady-state production and delivered its 1 millionth pound of uranium. Resources have increased at Lost Creek and permitting is underway for the Shirley Basin project. The document also provides an overview of the uranium market, including supply and demand fundamentals and the restart of nuclear reactors in Japan.
This presentation discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's Lost Creek uranium production facility, which recently produced its 1 millionth pound of uranium, and discusses plans to develop the Shirley Basin project. The presentation also provides an overview of the current state of the uranium market, including supply and demand fundamentals and the impact of Japan restarting nuclear reactors. Financial information on Ur-Energy's share structure and analysts coverage is also presented.
Ur-Energy November 2016 Corporate PresentationBrooke Rock
Ur-Energy provides a summary of its Lost Creek uranium facility and resources. Lost Creek has produced over 2 million pounds of U3O8 through Q3 2016 and continues steady-state production. Resources have increased 250% since 2011 with measured and indicated resources now totaling over 14.6 million pounds. An amended preliminary economic assessment estimates Lost Creek can produce an additional 13.8 million pounds over its lifetime.
- The document discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming.
- It summarizes Ur-Energy's Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with head grades 3-4 times projections.
- It also mentions Ur-Energy's exploration properties, including an upcoming PEA on the Shirley Basin project, and provides an overview of the company's operations and financial position.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's Lost Creek in-situ recovery uranium mine, which began production in 2013, and discusses plans to develop the nearby Shirley Basin project. Production results from Lost Creek are exceeding initial projections due to higher-than-expected uranium grades. The document also notes that long-term uranium sales contracts have been signed to provide revenue through 2021 and that resources have increased through exploration at the Lost Creek property.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming, USA. It summarizes Ur-Energy's Lost Creek uranium production facility and its Shirley Basin development project. It also discusses the state of the global uranium market, including growing nuclear power demand, constrained primary supply, and the need for new producers like Ur-Energy to help fill the gap.
Ur-Energy's August 2017 Corporate PresentationUr-Energy
- Lost Creek ISR uranium facility has been in consistent production for 4 years, capturing over 2.3 million pounds of U3O8. Results show it is a reliable, low-cost producer.
- The company has secured future revenue through term sales agreements totaling over 2.4 million pounds of U3O8 from 2017-2021 at an average price of $50/lb.
- Resources at Lost Creek have increased 250% since 2011 through exploration and development, with measured and indicated resources now totaling over 14.6 million pounds.
This document provides an overview of Ur-Energy Inc. and its uranium production operations. It summarizes Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production in 2013, and its Shirley Basin project. It also discusses the state of the uranium market and supply and demand fundamentals. Finally, it provides production and cost data from Lost Creek's operations that demonstrate it is a reliable, low-cost producer.
- Lost Creek ISR uranium project in Wyoming has been in production since 2013, with production exceeding projections and head grades 3-4 times higher than estimated.
- A 2013 preliminary economic assessment estimated 9.2 million pounds of recoverable uranium over the life of the mine with low production costs and strong economics.
- The company has long term sales contracts in place through 2020 to sell uranium at prices above costs of production, providing revenue stability.
Ur-Energy's November 2017 Corporate PresentationUr-Energy
This document contains forward-looking statements regarding Ur-Energy's ability to maintain production operations at Lost Creek, deliver product on schedule, and further explore and develop projects like Shirley Basin. It also discusses Ur-Energy's recent sales agreements, production levels, and financial results. The document notes that analysts from various firms follow and report on Ur-Energy, and provides context on trends in the nuclear energy and uranium markets.
Ur-Energy Q3 Webcast & Teleconference Power PointBrooke Rock
This document provides an overview and update of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's recent quarterly production results from its Lost Creek ISR uranium facility, discusses its resource growth and future development plans, and outlines its sales contracts and revenue expectations for 2016. The document cautions that certain statements regarding future plans and projections are forward-looking in nature.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and Pathfinder Shirley Basin project. It summarizes Ur-Energy's commercial progress in 2014, including establishing production at Lost Creek and completing sales agreements. It also outlines the company's management team and board of directors as well as the positive long-term fundamentals of the uranium market, including growing nuclear power usage and constrained primary supply. However, the presentation contains forward-looking statements that are subject to risks and uncertainties.
UEX Corporation is a uranium exploration and development company with projects located in the Athabasca Basin of northern Saskatchewan, Canada. It has a portfolio of uranium deposits and exploration projects including 100% ownership of its Eastern Athabasca Projects and a 49.1% interest in Western Athabasca Projects through a joint venture with AREVA. UEX has evolved over 15 years of operations through exploration successes, resource delineations, economic assessments, and joint venture partnerships. The company's strategy is to advance its existing resource assets and conduct innovative exploration with the goal of new discovery as the uranium market improves.
UEX Corporation is a uranium exploration and development company with projects located in the Athabasca Basin of northern Saskatchewan, Canada. It has a portfolio of uranium deposits and exploration projects including 100% ownership of its Eastern Athabasca Projects and a 49.1% interest in Western Athabasca Projects through a joint venture with AREVA. UEX has evolved over 15 years from initial public offering to outlining resources at multiple deposits and conducting preliminary economic assessments and advanced exploration through partnerships and acquisitions. The company aims to increase resources at existing deposits and make new discoveries through innovative exploration programs to create value for shareholders.
UEX Corporation is a uranium exploration and development company with a portfolio of projects located in the Athabasca Basin of northern Saskatchewan, Canada. The company has over 69 million pounds of uranium indicated resources and over 16 million pounds of inferred resources located across its 100% owned Hidden Bay and Shea Creek projects. UEX is also a 49.1% joint venture partner with AREVA on the Western Athabasca Projects. The company's strategy is to advance its projects through exploration and resource growth with the goal of future development when uranium prices improve to support economic extraction.
Ur-Energy July 2016 Corporate PresentationBrooke Rock
- Lost Creek ISR uranium facility in Wyoming has been in steady-state production since 2013, producing over 1.73M lbs of U3O8 to date at low costs.
- Resources at the Lost Creek property have increased significantly since 2011 through exploration, with measured and indicated resources totaling over 14.6M lbs U3O8.
- The company aims to be a "pipeline producer" through developing its projects beyond Lost Creek, with the next project being Shirley Basin in Wyoming.
Ur-Energy August 2016 Corporate Presentation Brooke Rock
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming which began production in 2013 and has produced 1.86M lbs of U3O8 through June 2016. Resource expansion has increased measured, indicated, and inferred resources by 4.6M lbs, 1.7M lbs, and 6.4M lbs respectively since 2015.
- The company has secured long-term sales contracts through 2021 at an average price of $49.81/lb for approximately 3.1M lbs to provide revenue certainty in the current market.
- Ur-Energy is advancing the Shirley Basin project in Wyoming and recently filed permit applications, with the goal of developing additional uranium production centers in
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek uranium production facility in Wyoming and its Shirley Basin project in South Dakota. It also discusses the outlook for the uranium market, noting increasing global nuclear power usage while many primary uranium suppliers have cut production. Ur-Energy believes it is well-positioned to help meet growing US nuclear fuel demand with its domestic uranium production facilities.
Semantik adalah kajian tentang makna pada berbagai tingkatan bahasa seperti morfem, kata, frasa, ayat, dan wacana. Terdapat berbagai teori semantik yang mencoba menjelaskan konsep makna, seperti teori imej, behaviorisme, analisis komponen, dan logika simbolik. Masing-masing teori memiliki kelebihan dan kekurangan dalam penjelasan makna.
The Kessef Group offers mortgage lenders support to close more loans in 10 days or less through their in-house processing, underwriting, and funding. They also help increase revenue through rebates paid when loans fund rather than when sold, and fewer regulations. Kessef additionally aims to help lenders grow their clientele through exclusive leads, marketing support, and builder partnership programs.
Science involves various types of writing including keeping a science notebook. A science notebook contains everything done in class like bell ringers, vocabulary, notes, labs and more. Labs require the most writing and include writing the purpose, predictions, materials, procedures, data collection, analysis and conclusions. Beyond labs, science notebooks provide many opportunities for creative writing like poems, posters and games.
Morumotto provides a visual authentication solution that uses images to authenticate users, eliminating the need for passwords that are often reused or insecurely stored. It allows for single sign-on across multiple sites using one-time passwords generated for each login without plugins. The service will be launching publicly in a few weeks and offers multi-factor authentication including secure password resets and phishing protection.
The document discusses the benefits of exercise for mental health. Regular physical activity can help reduce anxiety and depression and improve mood and cognitive functioning. Exercise causes chemical changes in the brain that may help protect against mental illness and improve symptoms.
This two-day training event focused on social services contracts and grants. On day one, attendees would learn how to write successful performance-based proposals, including identifying funding sources, understanding requirements, and avoiding common mistakes. They would also learn tips for enhanced funding and making proposals more relevant. On day two, the training would cover navigating the audit process for contracts and grants, including conducting risk assessments, understanding requirements, and preparing for audits. Attendees would acquire knowledge on effectively implementing performance-based contracting and forming relationships with funders. The event aimed to provide nonprofit leaders with strategies for obtaining and managing contracts and grants.
Mobile marketing in Latin America is growing rapidly due to increasing smartphone and mobile internet usage. However, three myths are holding back its growth: that Latin Americans are not receptive to mobile ads; that feature phones are not important; and that most mobile transactions occur offline. The document dispels these myths with data showing Latin Americans' openness to mobile ads, the continued dominance of feature phones, and examples of successful mobile campaigns including sponsored services. It argues marketers need a "mobile first" approach and should test mobile strategies now to benefit from the fast growth of this region's mobile sector.
El documento describe los esfuerzos para rediseñar los programas académicos en el Instituto de Bellas Artes e implementar las Tecnologías de la Información y la Comunicación (TIC). Actualmente, el instituto cuenta con recursos tecnológicos básicos como internet de alta velocidad y computadores, pero se necesita mejorar la capacitación de docentes, aumentar los recursos educativos digitales, y rediseñar los programas de estudio para integrar mejor las TIC. El objetivo general es formar estudiantes con habilidades TIC
Analytical Investments Trading System Presentationpjgabrielli
The document describes a quantitative trading system developed by Dr. Nick Tishchenko that provides automated signals for long and short trades across stocks, ETFs, and futures. The system uses algorithms to identify trending sectors and stocks on various timeframes and automatically sets trade entry and exit points as well as dynamic stops. Backtests show the system generated profits from 72-79% of trades and strong annual returns across various indexes from 1998-2009. The system is now being offered to subscribers for real-time trade signals and portfolio management.
This document discusses the importance of estate planning and having a will. It notes that without a will, assets will be distributed according to intestacy laws, which can lead to family feuds. Dying without a proper estate plan can result in over 90% of an estate's value being lost to taxes, debts, and administrative fees. The document recommends speaking to a financial advisor to create an estate plan through tools like a will, trust, or corporate will in order to ensure one's assets are distributed as desired and protected for loved ones.
The document outlines the agenda for a social media marketing workshop. The agenda includes introductions, sessions on social media strategic planning, Twitter, Hootsuite, Facebook, and a wrap-up. It also lists the credentials of the workshop presenter, who has experience with online marketing since 1994 and major brands. The document then covers what social media is, why businesses should care about it, examples of social media usage statistics, and an overview of Twitter.
A real estate investment opportunity is offered for a 3 bedroom house in Toronto, Ontario. The opportunity seeks a cash partner to invest 95% of the funds needed, which is $66,453. In return, the cash partner would receive 65% of the profits from renting the property, estimated between $22,000 to $41,000. Key details provided include property features, pictures, tenant profile, and potential financial returns.
The document provides an overview of social media strategy and social advertising. It discusses measuring the social landscape, developing a social media strategy with content, engagement, management and measurement. It also covers social advertising including defining goals, budgets, targeting audiences and creating landing pages. Remarketing is discussed as well as resources for social media marketing.
IAB Europe Ad Ex2010 Online Adspend study IAB México
The European online advertising market grew 15.4% in 2010 to €17.7 billion, outperforming total ad markets. Display advertising saw the largest surge, growing 21.1% to €5.8 billion as it benefited from innovations in mobile, video, and social formats. Search grew 15.6% to €7.9 billion. Classifieds & Directories increased 7.5% to €3.9 billion. Emerging markets saw the highest growth rates while many established markets grew above the European average, demonstrating the continued strength and potential of digital advertising.
This article spotlights a collaborative partnership approach to develop and garner support for Healthy and Smart, a HIV/AIDS prevention curriculum strategy. Focus is purposely placed on an action research methodology based in theory and evidence. The programmatic method is incremental and encompasses a transdisciplinary and culturally appropriate approach. In particular, our method instigates effective social change and public policy by forming collaborative partnerships. The essence of collaborative partnerships with key public policy and administrative actors is its alignment with a nation’s social development policy position. Critical to the development of a comprehensive action research approach is investing time to explore each social factor fully. Healthy and Smart HIV/AIDS Prevention Program for Youth exemplifies a participatory program development model for public managers.
Building codes and regulations provide minimum standards for building construction and safety. They address requirements for materials, building systems, fire resistance, means of egress, occupancy loads and more. Various codes apply to different aspects of construction, such as the International Building Code, International Residential Code, and National Fire Protection Association codes. Buildings are also subject to zoning ordinances and legal requirements regarding accessibility and worker safety. It is the responsibility of architects and designers to understand and comply with all applicable codes and regulations to ensure building safety.
The document summarizes a report on global consumer confidence in the second quarter of 2014. Some key findings include:
- Global consumer confidence increased slightly to an index of 97, the highest since 2007, driven by gains in North America and parts of Europe.
- Optimism about job prospects reached 50% globally for the first time since 2007, though outlook varied regionally.
- Confidence increased in the US and Canada in North America and parts of Europe like Italy, but declined in Japan and some emerging markets.
Ur-Energy is an advanced pre-production junior mining company focused on developing low-cost uranium production properties in the United States. Its objectives are low-cost US uranium production, resource growth through exploration and strategic opportunities. It has an advanced project called Lost Creek in Wyoming that is in the regulatory process and expects to be cash-flow positive. Ur-Energy aims to expand resources and be a low-cost uranium production center in the US market, where domestic production is a fraction of domestic demand.
Ur-Energy April 2016 Corporate PresentationUr-Energy
The document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
- Lost Creek is the company's flagship ISR uranium facility which began production in 2013 and has exceeded production targets, demonstrating it is a reliable, low-cost operation.
- Resources at Lost Creek have increased 250% since 2011 with measured, indicated, and inferred resources now totaling over 14 million pounds.
- A preliminary economic assessment outlines potential to produce over 13 million additional pounds at Lost Creek with low production costs.
- The company has long-term sales contracts in place to deliver over 3 million pounds of uranium through 2021, providing revenue certainty.
Ur-Energy May 2016 Corporate PresentationBrooke Rock
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
1) Ur-Energy has established a reliable, low-cost uranium production center at its Lost Creek ISR facility in Wyoming and has expanded resources through exploration.
2) The company is advancing its Shirley Basin project and completing permitting to become its next uranium development.
3) Ur-Energy has a strong technical team with over 180 years of combined uranium production experience in ISR operations.
Ur-Energy December 2016 Corporate PresentationBrooke Rock
This document provides an overview and summary of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming and is developing the Shirley Basin project.
- Lost Creek has steadily produced over 2 million pounds of uranium since 2013 and resource expansion continues.
- The company aims to realize better sales prices through long-term sales agreements and reduce exposure to volatile markets.
- Ur-Energy has a strong technical team with over 180 years of combined uranium production experience in ISR operations.
Ur-Energy September 2016 Corporate PresentationBrooke Rock
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming which began production in 2013 and has produced 1.86M lbs of U3O8 through June 2016.
- Resources at Lost Creek have increased 250% since 2011 with measured and indicated resources now totaling 14.6M lbs and inferred resources at 6.4M lbs.
- A preliminary economic assessment estimates Lost Creek can produce an additional 13.8M lbs over its lifetime at the lowest quartile production costs in the industry.
Ur-Energy October 2016 Corporate Presentation Brooke Rock
- Ur-Energy operates the Lost Creek uranium facility in Wyoming and is developing the Shirley Basin project. Lost Creek has steadily produced 1.86 million pounds of uranium since 2013 and provides reliable, low-cost production. Resource expansion has increased reserves by 4.6 million pounds at Lost Creek.
- Global nuclear power demand is projected to increase 35% by 2030, driving increased uranium consumption. However, production cuts by major producers Kazatomprom and Cameco may limit supply.
- Ur-Energy aims to realize higher uranium sales prices through long-term sales agreements and develop the Shirley Basin project, while maintaining steady production at Lost Creek.
Ur energy's january 2017 corporate presentationUr-Energy
This document provides an overview and summary of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming and is advancing the Shirley Basin project.
- Lost Creek has reliably produced over 2 million pounds of uranium since 2013 and resource expansion continues.
- The company aims to realize better uranium sales prices through long-term sales agreements.
- Global nuclear power capacity and uranium demand are projected to significantly increase in the coming years, driven by countries like China and Russia. Major producers have announced reductions in supply.
Ur Energy's February 2017 Corporate PresentationUr-Energy
This presentation discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
- Ur-Energy has established a reliable, low-cost uranium production center at its Lost Creek ISR facility in Wyoming and continues to expand resources through exploration.
- The company is pursuing development of its Shirley Basin project in Wyoming.
- Global demand for uranium is expected to increase in the coming years due to projected growth in nuclear power generation worldwide. However, production cuts by major producers may limit supply.
- Ur-Energy aims to realize better uranium sales prices through long-term sales agreements and has an experienced technical and management team.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013. It also mentions their next development project at Shirley Basin and provides details on Ur-Energy's management team, board of directors, the outlook for nuclear power and uranium demand, and Ur-Energy's position in the US uranium market. The document contains forward-looking statements and projections that are subject to risks and uncertainties.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's Shirley Basin project, acquired in 2013, which has 8.8 million pounds of high-grade uranium resources. The document outlines Ur-Energy's management team, long term sales contracts through 2019, and the positive long term outlook for nuclear and uranium demand.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013 and has exceeded production targets with head grades 3-4 times projections. It also discusses the Shirley Basin project acquired in 2013, which has an initial resource estimate of 8.8 million pounds from a technical report. Overall, the document outlines Ur-Energy's progress in establishing itself as a reliable uranium producer through operational successes at Lost Creek.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
- Lost Creek is the company's flagship uranium production facility which began production in 2013 and is exceeding production targets with head grades 3-4 times projected levels.
- The Shirley Basin project in Wyoming was acquired in 2013 and a preliminary economic assessment was completed in January 2015, estimating 8.8 million pounds of uranium resources.
- Long term sales contracts through 2019 provide future revenue while market conditions remain uncertain. 514,000 pounds were sold in 2014 at an average price of $51.10 per pound.
Ur-Energy's June 2017 Corporate PresentationUr-Energy
This document provides an overview and summary of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy has steadily produced uranium from its Lost Creek ISR facility in Wyoming since 2013 and has expanded resources through exploration.
- The company is pursuing development of its Shirley Basin project in Wyoming.
- Long-term fundamentals for uranium demand remain positive due to expected growth in nuclear power globally. However, production cuts by major producers may tighten supply in the near-term.
Ur-Energy's March 2017 Corporate PresentationUr-Energy
The document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming and development projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek project in Wyoming, which began production in 2013 and has produced over 2 million pounds of uranium through 2016. It also discusses Ur-Energy's Shirley Basin project in Wyoming, which has over 8.8 million pounds of resources identified. The document contains forward-looking statements about Ur-Energy's projects and the uranium market, and notes various risks and uncertainties involved.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It discusses Ur-Energy's Lost Creek uranium production facility, which began production in 2013. The document also notes Ur-Energy's acquisition of the Pathfinder Shirley Basin project in 2013 and its plans to develop that project. Additionally, the document contains forward-looking statements about Ur-Energy's projections and timelines.
The document discusses Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production activities in 2013. It achieved first sales and revenue in December 2013, and has exceeded production targets and guidance. The document also mentions Ur-Energy's acquisition of the Pathfinder Mines Shirley Basin project in 2013, which has over 8 million pounds of uranium resources and is planned to begin production in 2017. Finally, the document provides an overview of Ur-Energy's marketing strategy of long-term sales contracts securing future revenue through 2019.
Ur-Energy provides a presentation on their uranium production operations and market outlook. They have begun production at their Lost Creek ISR facility in Wyoming and are moving toward steady-state operations. They also acquired the Shirley Basin project and are permitting it for future development. The uranium market fundamentals are positive long term due to growing nuclear power usage and constrained primary supply, positioning Ur-Energy well to help meet US demand with their domestic production.
- Ur-Energy has begun production at its Lost Creek ISR uranium facility in Wyoming, with first sales occurring in December 2013.
- A preliminary economic assessment updated Lost Creek resources to 13.5 million pounds and projected strong economics over the life of the mine.
- The company acquired additional projects in Wyoming through the purchase of Pathfinder Mines in December 2013, with the Shirley Basin project expected to be the next development.
Ur-Energy provides a presentation on its operations and projects. It has begun production at its Lost Creek in-situ recovery uranium facility, with production exceeding initial projections. It also acquired the Pathfinder-Shirley Basin project in 2013, which has over 8 million pounds of uranium resources indicated for potential production in 2017. The presentation discusses Ur-Energy's contracts securing future uranium sales, low cost structure, and experienced management team, positioning it to benefit from increasing global nuclear energy demand.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and Pathfinder Shirley Basin project. It notes that Lost Creek has begun production activities and sales, and is moving toward steady-state production. It also discusses advancing permitting at Shirley Basin. The presentation provides an overview of Ur-Energy's share structure, analyst coverage, management team, the outlook for the uranium market, and Ur-Energy's contracts which de-risk the company in an uncertain market.
Similar to Ur-Energy March 2016 Corporate Presentation (20)
The document provides an overview of Ur-Energy's second quarter 2015 results and operations. It summarizes production and sales figures, discusses operational improvements at Lost Creek that have lowered costs, and outlines plans to increase resources at Lost Creek and Shirley Basin. Upcoming milestones include resource updates for both properties and continuing development at MU2.
The document provides an overview of Ur-Energy's second quarter 2015 results. It summarizes production levels and costs, revenues, resource estimates for the Lost Creek property, and development status for Lost Creek and Shirley Basin. It also discusses the company's cash position, sales contracts, cost reduction efforts, and CEO search. Production levels increased over the previous year while costs decreased. Resource estimates for Lost Creek were also increased.
Ur-Energy provides a summary of its operations and projects. It discusses the successful start of production at its Lost Creek facility, with production rates exceeding targets. It also describes its agreement to acquire Pathfinder Mines Corporation, which would provide its next production center. The acquisition includes the Shirley Basin and Lucky Mc projects and exploration data. Ur-Energy believes these projects and additional exploration targets could significantly expand its uranium resources.
Ur-Energy provides a summary of its operations, including:
1) Lost Creek has begun production operations and is fully staffed.
2) A definitive agreement was signed to acquire Pathfinder Mines Corporation, which holds the next potential production center and includes the Shirley Basin and Lucky Mc projects.
3) Long term sales contracts have been secured with four US utilities to provide a revenue stream through 2019 and de-risk the company in an uncertain market.
- Ur-Energy is an advanced uranium exploration and development company with its fully licensed and constructed Lost Creek project in Wyoming set to begin production in Q3 2013.
- The company has secured long-term uranium sales contracts and is fully funded to begin production at Lost Creek.
- Ur-Energy also has a definitive agreement to acquire Pathfinder Mines Corporation which holds additional uranium resources in Wyoming that will provide future production centers for the company.
- Ur-Energy is an advanced uranium mining company with its fully licensed and construction-ready Lost Creek project in Wyoming.
- Lost Creek is projected to begin first production in Q3 2013 and have an 8-10 year mine life at low operating costs of $16.12/lb.
- The company is also acquiring Pathfinder Mines Corporation, which holds additional uranium projects and infrastructure to support future production.
- Ur-Energy has secured long-term uranium sales agreements and is well positioned to supply the US market given low domestic production.
- The document provides an overview of Ur-Energy Inc., a uranium exploration and development company.
- Ur-Energy is developing its Lost Creek project in Wyoming, with first production forecast for Q3 2013, and has signed an agreement to acquire Pathfinder Mines Corporation which holds its next potential production center.
- The company has secured project financing and long-term uranium sales agreements to support development of the Lost Creek project while reducing exposure to volatile market prices.
Ur-Energy provides a summary of a document discussing its advanced Lost Creek uranium project in Wyoming. The summary notes that construction has begun at Lost Creek with first production expected in the second half of 2013. It also mentions that Ur-Energy has signed an agreement to acquire Pathfinder Mines Corporation, which holds the Shirley Basin and Lucky Mc uranium projects and could provide Ur-Energy's next production center.
The document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's advanced Lost Creek project in Wyoming, which is expected to begin production in the second half of 2013. It also notes Ur-Energy's plans to expand resources through acquisitions and exploration. Finally, it provides details on Ur-Energy's market position, including its share capital, cash position, analyst coverage, and experienced management team.
The document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's advanced Lost Creek project in Wyoming, which is expected to begin production in the second half of 2013. It also notes Ur-Energy's plans to expand resources through acquisitions and exploration. Finally, it provides details on Ur-Energy's market position, including its cash reserves, analyst coverage, and experienced management team.
The document provides an overview of Ur-Energy Inc., an advanced uranium exploration and development company with their primary project being the Lost Creek in-situ recovery uranium project in Wyoming, discusses their plans to commence production in the second half of 2013, and cautions that the document contains forward-looking statements and projections that are inherently uncertain and subject to significant risks and uncertainties.
This corporate presentation from Ur-Energy provides information about the company and its projects. Ur-Energy is an advanced pre-production uranium company focused on developing its flagship Lost Creek project in Wyoming. Key objectives include bringing Lost Creek into production in 2013, expanding resources through exploration and acquisitions, and securing revenue through long-term sales agreements. Lost Creek has fully approved permits and is under construction, with initial production anticipated in the second half of 2013. Ur-Energy also has agreements to acquire additional projects from Pathfinder Mines Corporation that will provide future production centers.
Ur-Energy is an advanced pre-production junior mining company focused on developing low-cost uranium production properties in the United States. Its objectives are Lost Creek Development, resource growth, and strategic opportunities. It is currently constructing its flagship Lost Creek ISR uranium project in Wyoming, with first production expected in the second half of 2013. The company is also expanding its resources through the planned acquisition of Pathfinder Mines Corporation, which holds Ur-Energy's next potential production center and extensive exploration assets. Ur-Energy has an experienced management team with over 150 years of combined uranium production experience and is well positioned to help meet the growing demand for nuclear fuel in the United States and globally.
The corporate presentation provides an overview of Ur-Energy, an advanced pre-production junior mining company focused on developing low-cost uranium production properties in the United States. Key points include:
- Ur-Energy's flagship property is the Lost Creek ISR uranium project in Wyoming, which is fully licensed and under construction with first production anticipated in mid-2013.
- The presentation provides details on Ur-Energy's experienced management team, growing resources at Lost Creek, favorable economics from preliminary analyses, and marketing strategy to sell uranium production.
- Ur-Energy also intends to expand resources through the planned acquisition of Pathfinder Mines Corporation and continued exploration at Lost Creek and other US-based projects.
Ur-Energy is an advanced pre-production junior mining company focused on developing its Lost Creek uranium project in Wyoming. The company's objectives are to bring Lost Creek into production by mid-2013, expand resources through acquisitions and exploration, and secure revenue through long-term sales agreements. Ur-Energy has a strong balance sheet with $29 million in cash as of September 2012 and is followed by several analysts. The experienced management team is led by CEO Wayne Heili and includes a board with expertise in geology, mining finance, and engineering.
Roger L. Smith, Chief Financial Officer (CPA, CA)
Non-Executive Directors
James M. Franklin, Chairman (Geologist)
W. William Boberg (Mining Engineer)
Kathy E. Walker (Lawyer)
Gary C. Huber (Geologist)
Thomas Parker (Mining Executive)
Steven M. Hatten (Mining Executive)
Technical Staff
John W. Cash, Vice President Regulatory Affairs & Exploration (Geologist)
John Cooper, Project Geologist (Geologist)
Catherine Bull,
Ur-Energy is an advanced pre-production junior mining company focused on developing its flagship Lost Creek uranium project located in Wyoming, USA. The company recently began construction at Lost Creek and expects first production in mid-2013. Ur-Energy has also grown resources at Lost Creek through acquisitions and exploration and aims to further expand through additional strategic opportunities.
Ur-Energy is developing its flagship Lost Creek uranium project in Wyoming. It recently received final permits and began construction in October 2012, with first production expected in mid-2013. The project has low projected operating costs and significant resources that could support production for 8-10 years. Ur-Energy also continues exploring and acquiring additional uranium properties in the region.
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
The Evolution and Impact of OTT Platforms: A Deep Dive into the Future of Ent...ABHILASH DUTTA
This presentation provides a thorough examination of Over-the-Top (OTT) platforms, focusing on their development and substantial influence on the entertainment industry, with a particular emphasis on the Indian market.We begin with an introduction to OTT platforms, defining them as streaming services that deliver content directly over the internet, bypassing traditional broadcast channels. These platforms offer a variety of content, including movies, TV shows, and original productions, allowing users to access content on-demand across multiple devices.The historical context covers the early days of streaming, starting with Netflix's inception in 1997 as a DVD rental service and its transition to streaming in 2007. The presentation also highlights India's television journey, from the launch of Doordarshan in 1959 to the introduction of Direct-to-Home (DTH) satellite television in 2000, which expanded viewing choices and set the stage for the rise of OTT platforms like Big Flix, Ditto TV, Sony LIV, Hotstar, and Netflix. The business models of OTT platforms are explored in detail. Subscription Video on Demand (SVOD) models, exemplified by Netflix and Amazon Prime Video, offer unlimited content access for a monthly fee. Transactional Video on Demand (TVOD) models, like iTunes and Sky Box Office, allow users to pay for individual pieces of content. Advertising-Based Video on Demand (AVOD) models, such as YouTube and Facebook Watch, provide free content supported by advertisements. Hybrid models combine elements of SVOD and AVOD, offering flexibility to cater to diverse audience preferences.
Content acquisition strategies are also discussed, highlighting the dual approach of purchasing broadcasting rights for existing films and TV shows and investing in original content production. This section underscores the importance of a robust content library in attracting and retaining subscribers.The presentation addresses the challenges faced by OTT platforms, including the unpredictability of content acquisition and audience preferences. It emphasizes the difficulty of balancing content investment with returns in a competitive market, the high costs associated with marketing, and the need for continuous innovation and adaptation to stay relevant.
The impact of OTT platforms on the Bollywood film industry is significant. The competition for viewers has led to a decrease in cinema ticket sales, affecting the revenue of Bollywood films that traditionally rely on theatrical releases. Additionally, OTT platforms now pay less for film rights due to the uncertain success of films in cinemas.
Looking ahead, the future of OTT in India appears promising. The market is expected to grow by 20% annually, reaching a value of ₹1200 billion by the end of the decade. The increasing availability of affordable smartphones and internet access will drive this growth, making OTT platforms a primary source of entertainment for many viewers.
Navigating the world of forex trading can be challenging, especially for beginners. To help you make an informed decision, we have comprehensively compared the best forex brokers in India for 2024. This article, reviewed by Top Forex Brokers Review, will cover featured award winners, the best forex brokers, featured offers, the best copy trading platforms, the best forex brokers for beginners, the best MetaTrader brokers, and recently updated reviews. We will focus on FP Markets, Black Bull, EightCap, IC Markets, and Octa.
Company Valuation webinar series - Tuesday, 4 June 2024FelixPerez547899
This session provided an update as to the latest valuation data in the UK and then delved into a discussion on the upcoming election and the impacts on valuation. We finished, as always with a Q&A
Industrial Tech SW: Category Renewal and CreationChristian Dahlen
Every industrial revolution has created a new set of categories and a new set of players.
Multiple new technologies have emerged, but Samsara and C3.ai are only two companies which have gone public so far.
Manufacturing startups constitute the largest pipeline share of unicorns and IPO candidates in the SF Bay Area, and software startups dominate in Germany.
Building Your Employer Brand with Social MediaLuanWise
Presented at The Global HR Summit, 6th June 2024
In this keynote, Luan Wise will provide invaluable insights to elevate your employer brand on social media platforms including LinkedIn, Facebook, Instagram, X (formerly Twitter) and TikTok. You'll learn how compelling content can authentically showcase your company culture, values, and employee experiences to support your talent acquisition and retention objectives. Additionally, you'll understand the power of employee advocacy to amplify reach and engagement – helping to position your organization as an employer of choice in today's competitive talent landscape.
How MJ Global Leads the Packaging Industry.pdfMJ Global
MJ Global's success in staying ahead of the curve in the packaging industry is a testament to its dedication to innovation, sustainability, and customer-centricity. By embracing technological advancements, leading in eco-friendly solutions, collaborating with industry leaders, and adapting to evolving consumer preferences, MJ Global continues to set new standards in the packaging sector.
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfthesiliconleaders
In the recent edition, The 10 Most Influential Leaders Guiding Corporate Evolution, 2024, The Silicon Leaders magazine gladly features Dejan Štancer, President of the Global Chamber of Business Leaders (GCBL), along with other leaders.
SATTA MATKA SATTA FAST RESULT KALYAN TOP MATKA RESULT KALYAN SATTA MATKA FAST RESULT MILAN RATAN RAJDHANI MAIN BAZAR MATKA FAST TIPS RESULT MATKA CHART JODI CHART PANEL CHART FREE FIX GAME SATTAMATKA ! MATKA MOBI SATTA 143 spboss.in TOP NO1 RESULT FULL RATE MATKA ONLINE GAME PLAY BY APP SPBOSS
Structural Design Process: Step-by-Step Guide for BuildingsChandresh Chudasama
The structural design process is explained: Follow our step-by-step guide to understand building design intricacies and ensure structural integrity. Learn how to build wonderful buildings with the help of our detailed information. Learn how to create structures with durability and reliability and also gain insights on ways of managing structures.
Discover timeless style with the 2022 Vintage Roman Numerals Men's Ring. Crafted from premium stainless steel, this 6mm wide ring embodies elegance and durability. Perfect as a gift, it seamlessly blends classic Roman numeral detailing with modern sophistication, making it an ideal accessory for any occasion.
https://rb.gy/usj1a2
3 Simple Steps To Buy Verified Payoneer Account In 2024SEOSMMEARTH
Buy Verified Payoneer Account: Quick and Secure Way to Receive Payments
Buy Verified Payoneer Account With 100% secure documents, [ USA, UK, CA ]. Are you looking for a reliable and safe way to receive payments online? Then you need buy verified Payoneer account ! Payoneer is a global payment platform that allows businesses and individuals to send and receive money in over 200 countries.
If You Want To More Information just Contact Now:
Skype: SEOSMMEARTH
Telegram: @seosmmearth
Gmail: seosmmearth@gmail.com
2. NYSE MKT: URG • TSX: URE
This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur in the future. Such statements include
without limitation the Company’s ability to maintain steady-state operations; timing of making product deliveries; the technical and economic viability of Lost Creek (including the production and
cost projections contained in the preliminary economic analysis of the Lost Creek Property); whether higher-than-expected headgrades will continue to be realized throughout Lost Creek; the
ability to complete additional favorable uranium sales agreements and ability to reduce exposure to volatile market; the potential of exploration targets throughout the Lost Creek Property
(including the continuing ability to expand resources); the further exploration, development and permitting of Company projects, including at Shirley Basin; the technical and economic viability
of Shirley Basin (including the production and cost projections contained in the preliminary economic analysis of the Shirley Basin project); completion of (and timing for) regulatory approvals
and other development at Shirley Basin; and the long term effects on the uranium market of events in Japan in 2011 including supply and demand projections; and whether a re-rating of the
Company will occur with establishment of production credentials. These statements are based on current expectations that, while considered reasonable by management at this time,
inherently involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Numerous factors could cause actual events to differ materially from those
in the forward-looking statements. Factors that could cause such differences, without limiting the generality of the following, include: risks inherent in exploration activities; volatility and
sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of exploration competition; the ability to raise funds through private or public equity
financings; imprecision in resource and reserve estimates; environmental and safety risks including increased regulatory burdens; unexpected geological or hydrological conditions; a possible
deterioration in political support for nuclear energy; changes in government regulations and policies, including trade laws and policies; demand for nuclear power; weather and other natural
phenomena; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; and other exploration, development, operating, financial market and
regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking statements are reasonable, undue reliance should not be placed on these statements,
which only apply as of the date of this presentation. Ur-Energy Inc. disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new
information, future events or otherwise.
Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and, accordingly, the estimates and assumptions
underlying the projections are inherently highly uncertain, based on events that have not taken place, and are subject to significant economic, financial, regulatory, competitive and other
uncertainties and contingencies beyond the control of Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors,
there can be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially, from those projected.
The attention of investors is drawn to the Risk Factors set out in the Company's Annual Report on Form 10-K, filed February 26, 2016, which is filed with the U.S. Securities and Exchange
Commission on EDGAR (http://www.sec.gov/edgar.shtml) and the regulatory authorities in Canada on SEDAR (www.sedar.com).
Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the terms "measured", "indicated" and "inferred"
mineral resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission
does not recognize these terms. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral
reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally minable.
James A Bonner, Ur-Energy Vice President, Geology, P.Geo., SME Registered Member and Qualified Person as defined by National Instrument 43-101, reviewed and approved
the technical information contained in this presentation.
2
3. NYSE MKT: URG • TSX: URE 3
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Lost Creek ISR Uranium Facility
Initiated Production 3Q 2013
• Produced 1.63M pounds of U308 2Q 2015
• State of the art flagship project
• Results demonstrate that Lost Creek is a
reliable, low cost production center – “steady
state” production
Resource Growth – Two 2015 Updates
• Lost Creek Property net increase of 4.6 million lbs. Measured & Indicated resource
• Resources from exploration drilling: 139,000lbs Measured & Indicated; 498,000lbs
Inferred
Realizing better sales prices through long term sales agreements
Pathfinder - Shirley Basin, our Next Development
• PEA Completed in January 2015
• Application for permit to mine filed 4Q 2015; work on other applications underway
4. NYSE MKT: URG • TSX: URE 4
Share Capital & Cash Position
As of 12/31/2015
Shares Outstanding 130.2M
Stock Options & RSUs 11.1M
Warrants 8.2M
Fully Diluted 149.5M
Shares outstanding (2/25/16) 143.3M
Cash (2/25/2016) US$6.8M
Market Cap (2/29/2016) US$63.18M
Share Price (3/11/2016) US$0.52
52 Week Range US$0.44 - $1.07
Avg. Daily Volume ~433,000
(3-mo URG & URE 3/3/2016)
Member of S&P/TSX SmallCap Index
Geographical Distribution as of 6/30/15
United States ~65%
Canada ~19%
Other ~16%
NYSE MKT: URG
TSX: URE
5. NYSE MKT: URG • TSX: URE
Ur-Energy Inc. is followed by the analysts listed above. This list, including the firms and individual analysts at these firms, is subject to
change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or recommendations regarding Ur-Energy
Inc. performance made by these analysts are theirs alone and do not represent opinions, estimates, forecasts, conclusions,
recommendations or predictions of Ur-Energy Inc. or its management. Ur-Energy Inc. does not by its reference above or in any other manner
imply its endorsement of or concurrence with such information, conclusions or recommendations.
5
United States
H.C. Wainwright Heiko Ihle (New York, NY) 1.212.356.0510
Roth Capital Partners Joseph Reagor (Newport Beach, CA) 1.949.720.7106
Canada
Cantor Fitzgerald Rob Chang (Toronto, ON) 1.416.849.5008
Dundee Securities David Talbot (Toronto, ON) 1.416.350.3082
Haywood Securities Colin Healey (Vancouver, BC) 1.604.697.7400
L.B. Securities Chris Chang (Toronto, ON) 1.416.865.5798
Raymond James David Sadowski (Vancouver, BC) 1.604.659.8255
6. NYSE MKT: URG • TSX: URE
Board of Directors
Executive Director
Jeffrey T. Klenda,* Chairman and Executive Director (Mining Finance)
Non-Executive Directors
W. William Boberg,* Former President & CEO (Professional Geologist)
James M. Franklin,* Chair-Technical Committee (Professional Geologist)
Paul Macdonell,* Chair-Compensation and Corp. Governance & Nominating Committees
(Private Mediator)
Thomas H. Parker, Lead Director, Chair-Audit Committee (Professional Engineer)
Gary C. Huber, Director (Professional Geologist; Mining Executive)
Officers
Roger L. Smith, Chief Financial Officer & Chief Administrative Officer (CPA & MBA)
Steven M. Hatten, VP Operations (Mining Engineer)
John W. Cash, VP Regulatory Affairs (Geologist & Geophysicist)
James A. Bonner, VP of Geology (Professional Geologist)
Penne A. Goplerud, Corporate Secretary & General Counsel (JD)
* Founding Directors
6
7. NYSE MKT: URG • TSX: URE
Highly experienced technical and management team
~180 years of direct uranium production experience
• ISR operations experience – Nebraska, Texas & Wyoming
7
8. NYSE MKT: URG • TSX: URE
439 operable reactors world wide
with 382 GWe capacity
64 New Nuclear Reactors under
construction in 14 countries
• 90 net new reactors by 2022
• 159 planned
• 329 proposed
8
*Source: UxC Uranium Market Outlook
Japan’s reactor fleet: Sendai 1 began full operations September 10, 2015
Sendai 2 began full operations November 17, 2015
Takahama 3 restarted on January 29, 2016
Takahama 4 restarted on February 26, 2016
In 2014, world nuclear industry consumption was ~171 million lbs and
production was only ~145 million lbs
See Disclaimer re Forward-looking Statements and Projections (slide 2)
*Sources: Nuclear Energy Institute; World Nuclear Association
9. NYSE MKT: URG • TSX: URE
HEU secondary supply concluded in 2013
• Provided 24 Mlbs/yr equivalent for past 20 years
Large scale production uneconomical at current prices
• Rossing – reduced production rates (6.0 Mlbs/yr)
• Paladin – Kayelekera production halted (3.0 Mlbs/yr)
Key supply deferrals
• BHP Billiton – Olympic Dam expansion
• Cameco – Kintyre and Millennium
• Areva – Trekkopje and Imouraren
• Swakop Uranium – Husab
• Many more
Current uranium pricing cannot sustain high cost producers
• US shutdowns – production rates falling
9
See Disclaimer re Forward-looking Statements and Projections (slide 2)
10. NYSE MKT: URG • TSX: URE
US demand is not met by US production
• US domestic production ~3.3M lbs of uranium/yr1
• US utilities consume ~46.5M lbs of uranium/yr1
Ur-Energy is well positioned to capitalize on this opportunity
10
See Disclaimer re Forward-looking Statements and Projections (slide 2)
1U.S. Energy Information Administration 2014
Uranium originating in Kazakhstan, Russia and Uzbekistan accounted for
39% of the 53 million pounds purchased by US utilities
Production
Falling
11. NYSE MKT: URG • TSX: URE
Multiple long-term contracts spanning
2013-2021 timeframe, post Fukushima
• ~3.1M lbs committed 2016 – 2021
(avg. price $49.81/lb)
De-risking by securing future revenue
stream in an uncertain market
• 2015: 630,000 lbs U3O8 at avg. price of
$49.42/lb - $31.1M gross revenues
• 2016: 662,000 lbs U3O8 at avg. price of
$47.58/lb - $31.5M gross revenues
• Spot sales supplementing
11
Exclusive representation by Jim Cornell of NuCore Energy, LLC in
negotiations of off-take purchase agreements
See Disclaimer re Forward-looking Statements and Projections (slide 2)
12. NYSE MKT: URG • TSX: URE
Environmentally sound production method
Well understood by Wyoming state regulators
Cost effective, low capital costs
Governor signed bill to become an “Agreement State”
12
13. NYSE MKT: URG • TSX: URE 13
Ur-Energy is a “Pipeline Producer”
• Target larger and scalable project
• Not just “Pounds in the Ground”
• Following the “Smith Ranch” model
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Wyoming
~42,000 acres
14. NYSE MKT: URG • TSX: URE 14
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Measured: 9.39 Mlbs eU3O8 (in 9.74 Mt @ 0.048%)1
Indicated: 5.22 Mlbs eU3O8 (in 5.94 Mt @ 0.044%)
Inferred: 6.44 Mlbs eU3O8 (in 7.37 Mt @ 0.044%)
Based on grade cutoff of 0.02% eU3O8 and GT cutoffs of 0.2 and 0.3
1Measured resources not reduced by the 1,358,000 lbs. produced from MU1
*Amended Preliminary Economic Assessment for the Lost Creek Property,
Sweetwater County, Wyoming, February 8, 2016. (filed on SEDAR)
Increase in Resources Fukishima to Date . . . . . . . . . . .250%
March 2011 February 2012 April 2012 December 2013 June 2015 February 2016
5,230,000 5,765,300
8,348,200 8,655,000
11,084,000
14,609,000
780,000
2,017,800
2,869,100
4,740,000 5,040,000
6,439,000
Resources
Lost Creek Resource Growth 2011-2016
Measured & Indicated Inferred
15. NYSE MKT: URG • TSX: URE
Estimates additional 13.8 million pounds recoverable over life of mine
(1.4 M pounds produced as of 9/30/15)
Project Economics
• Gross future sales of US$919 M
• Net pre-tax cash flow US$511 M
Lowest quartile Uranium Production Costs
• Life of mine operating costs at US$14.58/lb.
• Total pre-tax cost at US$29.29/lb.
• Average annual production of 0.86 M pounds U3O8 at 37.4 mg/l
15
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Cautionary statement: This Amended Preliminary Economic Assessment is preliminary in nature, and includes inferred mineral resources that are considered too speculative
geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mineral resources that are not mineral reserves
do not have demonstrated economic viability. There is increased risk and uncertainty to commencing and conducting production without established mineral reserves that may
result in economic and technical failure which may adversely impact future profitability. The estimated mineral recovery used in this Amended Preliminary Economic Assessment
is based on recovery data from wellfield operations to date, as well as Ur-Energy personnel and industry experience at similar facilities. There can be no assurance that
recovery at this level will be achieved.
*Amended Preliminary Economic Assessment for the Lost Creek Property, Sweetwater County, Wyoming prepared by TREC Inc. – February 8, 2016 (posted on SEDAR).
Lost Creek Processing Plant
16. NYSE MKT: URG • TSX: URE 16
A Construction and Operational Success
Operations commenced and all production circuits commissioned
in 2013
Surpassing production targets
• Peak production grade 3X-4X 2013 pre-operational projections
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Mine Unit 1
Finished Yellowcake Product
Interior of Header House
0
50
100
150
200
250
Pre-Ops
Proj
Q4 2013 Q1 2014 Q2 2014 Q3 2014 Q4 2014 Q1 2015 Q2 2015 Q3 2015 Q4 2015
42
211
179
152
135
123
110 108
86 85
PPM
Lost Creek Head Grades vs. Projection
17. NYSE MKT: URG • TSX: URE 17
2013 Q4 2014 YTD 2015 Q1 2015 Q2 2015 Q3 2015 Q4 2015 YTD
141K lbs
captured
596K lbs
captured
192K lbs
captured
207K lbs
captured
172K lbs
captured
212K lbs
captured
784K lbs
captured
131K lbs
drummed
548K lbs
drummed
177K lbs
drummed
184K lbs
drummed
177K lbs
drummed
189K lbs
drummed
727K lbs
drummed
$21.98/lb
cash cost*
$19.73/lb
cash cost*
$18.86/lb
cash cost*
$16.15/lb
cash cost*
$15.19/lb
cash cost*
$15.42/lb
cash cost*
$16.27/lb
cash cost*
Uranium production
December
2013
2014 YTD 2015 Q1 2015 Q2 2015 Q3 2015 Q4 2015 YTD
$5.7 million $26.5 million $7.4 million $18.2 million $8.5 million $7.8 million $42.0 million
90K lbs at
$62.92/lb sold
518K lbs at
$51.22/lb sold
146K lbs at
$50.55/lb sold
404K lbs at
$45.08/lb sold
150K lbs at
$56.39/lb sold
225K lbs at
$34.47/lb sold
925K lbs at
$45.20/lb sold
Revenues from operations
Falling Costs Year on Year Down 17.5%
*Excludes severance and ad valorem taxes, which for 2014 averaged $2.48 per pound and for 2015 averaged $3.14 per pound
18. NYSE MKT: URG • TSX: URE
Purchase closed in December 2013
On patented mining claims – we own the ground
8.8 million pounds, shallow, high grade roll front deposit
ISR amenable mineralization
Baseline data gathering was completed in 2015. Application for a permit to mine was
submitted in December 2015. Work on other applications is underway.
18
See Disclaimer re Forward-looking Statements and Projections (slide 2)
1. Sum of Measured and Indicated tons and pounds may not add to the reported total due to rounding.
2. Based on grade cutoff of 0.02 percent eU3O8 and a grade x thickness cutoff of 0.25 GT.
3. Measured and Indicated Mineral Resources as defined in Section 1.2 of NI 43-101 (the CIM Definition Standards (CIM
Council, 2014)).
4. All reported resources occur below the historic pre-mining static water table.
RESOURCE
AREA
MEASURED INDICATED
AVG GRADE
% eU3O8
SHORT TONS
(X 1000)
POUNDS
(X 1000)
AVG GRADE
% eU3O8
SHORT
TONS
(X 1000)
POUNDS
(X 1000)
FAB
TREND
0.280 1,172 6,574 0.119 456 1,081
AREA 5 0.243 195 947 0.115 93 214
TOTAL 0.275 1,367 7,521 0.118 549 1,295
MEASURED & INDICATED 0.230 1,915 8,816
Mineral Resource Estimate Summary July 2014
*Preliminary Economic Assessment Shirley Basin Uranium Project, Carbon County, Wyoming prepared by Western Water Consultants, Inc.,
d/b/a WWC Engineering – January 27, 2015 (posted on SEDAR).
19. NYSE MKT: URG • TSX: URE
January 27, 2015 PEA*
Estimates 6.3 million pounds will be produced from the Project
Project Economics
• Gross revenues of US$230.1M LOM
• Net cash flow US$215.9M
• Internal rate of return (IRR) at 117.0%
Uranium Production Costs
• Estimates direct operating costs at US$14.54/lb.
• Total cost of production including severance taxes and operational and capital
spending is estimated at US$31.26/lb.
Capital requirement of US$30.6M (with nominal annual budgets until buildout)
19
See Disclaimer re Forward-looking Statements and Projections (slide 2)
*Preliminary Economic Assessment Shirley Basin Uranium Project, Carbon County, Wyoming prepared by Western Water Consultants, Inc., d/b/a WWC Engineering – January
27, 2015 (posted on SEDAR).
Cautionary Statement: This Preliminary Economic Assessment is preliminary in nature and includes mineral resources. Mineral resources that are not mineral reserves do not have
demonstrated economic viability. There is increased risk and uncertainty to commencing production without established mineral reserves that may result in economic and technical
failure which may adversely impact future profitability. The estimated mineral recovery used in this Preliminary Economic Assessment is based on site-specific laboratory recovery
data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery of mineral resources at this level will be achieved. There is no
certainty that the preliminary economic assessment will be realized.
20. NYSE MKT: URG • TSX: URE
Lucky Mc – Gas Hills
• Historic estimate of resources: 4.7 Mlbs U3O8*
• Strategic opportunities with nearby developers
ISR by-product disposal facility
• Revenue generating asset
• Fully licensed for operation
• Multiple disposal agreements in place
• Scarce asset – 1 of 4 commercial facilities of this type in the US
Historical US uranium exploration database
• Hundreds of project descriptions located in twenty-three states
• More than 15,000 drill logs; technical and economic evaluations
• Strong addition to Ur-Energy’s existing project database
20
See Disclaimer re Forward-looking Statements and Projections (slide 2)
*Ur-Energy is not treating the historic reports as current mineral resources or mineral reserves, because a Qualified Person has not yet conducted sufficient
work to classify the estimates as such. Lucky Mc resource estimate is based on an internal 1996 PMC polygonal method estimation.
21. NYSE MKT: URG • TSX: URE
M&I resource average GT of
1.1 (17.2 ft @ 0.065% U3O8)
Shallow: 240 feet deep
Over 3,700 drill holes define deposit
21
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NI 43-101 Resource, July 2006
Measured & Indicated: 12.2 Mlbs eU3O8
(in 9.4 Mt @ 0.065%)
Inferred: 1.8 Mlbs eU3O8
(in1.6 Mt @ 0.055%)
Can be licensed with NRC as amendment to Lost Creek license
(Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR)
Lost Soldier Property
22. NYSE MKT: URG • TSX: URE
Proven track record of bringing projects to production
• Low-cost uranium production center at Lost Creek
• Top producing new project in the US
Growth oriented technical & management team
Development (not exploration) project pipeline
Shirley Basin
Lost Soldier
Multiple long-term uranium sales agreements
• Reducing Company exposure to volatile marketplace
• Agreements through 2021
22
See Disclaimer re Forward-looking Statements and Projections (slide 2)
23. NYSE MKT: URG • TSX: URE
1. Advancing Lost Creek production
• Maintain “steady state” production
• Efficient cost management of mining operations
2. Demonstrate growth in production profile
• Expand Lost Creek Property resources – June 2015 Technical Report
• Further update to Lost Creek resources – December 7, 2015
• NI 43-101 PEA filed – February 8, 2016
• New Initiatives
3. Pathfinder Mines – Shirley Basin
• Transition to operating and regulatory activities
• Resources NI 43-101 compliant
• NI 43-101 PEA completed January 2015
4. Corporate finance – positive cash position
• Low-cost Lost Creek production + growing inventories = financing alternatives
23
See Disclaimer re Forward-looking Statements and Projections (slide 2)
24. NYSE MKT: URG • TSX: URE
For more information, please contact:
Jeff Klenda, Chairman & Executive Director
Rich Boberg, Senior Director of Investor and Public Relations
By Mail:
Ur-Energy Corporate Office
10758 W. Centennial Rd., Suite 200
Littleton, CO 80127 USA
By Phone:
Office 720.981.4588
Toll-Free 866.981.4588
Fax 720.981.5643
By E-mail:
jeff.klenda@ur-energy.com
rich.boberg@ur-energy.com
24