- Ur-Energy has begun production at its Lost Creek ISR uranium facility in Wyoming, with first sales occurring in December 2013.
- A preliminary economic assessment updated Lost Creek resources to 13.5 million pounds and projected strong economics over the life of the mine.
- The company acquired additional projects in Wyoming through the purchase of Pathfinder Mines in December 2013, with the Shirley Basin project expected to be the next development.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with projects located in Wyoming. Key points include:
- Ur-Energy has begun production at its Lost Creek ISR uranium facility in Wyoming and expects to produce approximately 1 million pounds of uranium in 2014.
- The company recently acquired additional uranium properties in Wyoming through the purchase of Pathfinder Mines, including the Shirley Basin project which is projected to be the company's next production center.
- A preliminary economic assessment updated Lost Creek's resources to 9.2 million pounds recoverable and demonstrated strong economics for the project, with estimated production costs in the lowest industry quartile.
- Ur-Energy aims to
The document discusses Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production activities in 2013. It achieved first sales and revenue in December 2013, and has exceeded production targets and guidance. The document also mentions Ur-Energy's acquisition of the Pathfinder Mines Shirley Basin project in 2013, which has over 8 million pounds of uranium resources and is planned to begin production in 2017. Finally, the document provides an overview of Ur-Energy's marketing strategy of long-term sales contracts securing future revenue through 2019.
This document discusses Ur-Energy Inc., a uranium mining company. It summarizes that Ur-Energy has begun production at its Lost Creek in-situ recovery uranium facility in Wyoming, with first sales occurring in late 2013. It also notes that Ur-Energy recently acquired additional uranium properties in Wyoming and will be pursuing permitting and resource estimates for those projects. The document contains forward-looking statements about Ur-Energy's plans and production estimates that are subject to various risks and uncertainties.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It discusses Ur-Energy's Lost Creek uranium production facility, which began production in 2013. The document also notes Ur-Energy's acquisition of the Pathfinder Shirley Basin project in 2013 and its plans to develop that project. Additionally, the document contains forward-looking statements about Ur-Energy's projections and timelines.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and Pathfinder Shirley Basin project. It notes that Lost Creek has begun production activities and sales, and is moving toward steady-state production. It also discusses advancing permitting at Shirley Basin. The presentation provides an overview of Ur-Energy's share structure, analyst coverage, management team, the outlook for the uranium market, and Ur-Energy's contracts which de-risk the company in an uncertain market.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It discusses Ur-Energy's Lost Creek ISR uranium project, which commenced production in 2013 and is exceeding production targets. The presentation also summarizes Ur-Energy's acquisition of the Shirley Basin project in Wyoming, which has an initial resource estimate of 8.8 million pounds of uranium. Overall, the presentation outlines Ur-Energy's strategy of developing low-cost ISR uranium projects in the United States to capitalize on domestic uranium demand that is not being met by domestic production.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
1) Ur-Energy has begun production at its Lost Creek ISR uranium mine in Wyoming, with production exceeding initial projections.
2) The company acquired the Shirley Basin project in Wyoming, which is projected to be its next production center with permitting underway.
3) Ur-Energy has secured long-term uranium sales contracts through 2019 to provide revenue despite current uranium market volatility.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with its primary operating asset being the Lost Creek in-situ recovery uranium project in Wyoming. Key points include:
1) Lost Creek began production in 2013 and is ramping up towards steady-state levels, with production exceeding initial projections.
2) Additional resources were identified in 2013 at Lost Creek and at the Shirley Basin project acquired in late 2013, which could become the next production center.
3) Long-term sales contracts through 2019 provide revenue certainty in an uncertain market, with over 1 million pounds committed at an average price above $50/lb.
4) Preliminary economic analysis shows Lost Creek has
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with projects located in Wyoming. Key points include:
- Ur-Energy has begun production at its Lost Creek ISR uranium facility in Wyoming and expects to produce approximately 1 million pounds of uranium in 2014.
- The company recently acquired additional uranium properties in Wyoming through the purchase of Pathfinder Mines, including the Shirley Basin project which is projected to be the company's next production center.
- A preliminary economic assessment updated Lost Creek's resources to 9.2 million pounds recoverable and demonstrated strong economics for the project, with estimated production costs in the lowest industry quartile.
- Ur-Energy aims to
The document discusses Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production activities in 2013. It achieved first sales and revenue in December 2013, and has exceeded production targets and guidance. The document also mentions Ur-Energy's acquisition of the Pathfinder Mines Shirley Basin project in 2013, which has over 8 million pounds of uranium resources and is planned to begin production in 2017. Finally, the document provides an overview of Ur-Energy's marketing strategy of long-term sales contracts securing future revenue through 2019.
This document discusses Ur-Energy Inc., a uranium mining company. It summarizes that Ur-Energy has begun production at its Lost Creek in-situ recovery uranium facility in Wyoming, with first sales occurring in late 2013. It also notes that Ur-Energy recently acquired additional uranium properties in Wyoming and will be pursuing permitting and resource estimates for those projects. The document contains forward-looking statements about Ur-Energy's plans and production estimates that are subject to various risks and uncertainties.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It discusses Ur-Energy's Lost Creek uranium production facility, which began production in 2013. The document also notes Ur-Energy's acquisition of the Pathfinder Shirley Basin project in 2013 and its plans to develop that project. Additionally, the document contains forward-looking statements about Ur-Energy's projections and timelines.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and Pathfinder Shirley Basin project. It notes that Lost Creek has begun production activities and sales, and is moving toward steady-state production. It also discusses advancing permitting at Shirley Basin. The presentation provides an overview of Ur-Energy's share structure, analyst coverage, management team, the outlook for the uranium market, and Ur-Energy's contracts which de-risk the company in an uncertain market.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It discusses Ur-Energy's Lost Creek ISR uranium project, which commenced production in 2013 and is exceeding production targets. The presentation also summarizes Ur-Energy's acquisition of the Shirley Basin project in Wyoming, which has an initial resource estimate of 8.8 million pounds of uranium. Overall, the presentation outlines Ur-Energy's strategy of developing low-cost ISR uranium projects in the United States to capitalize on domestic uranium demand that is not being met by domestic production.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
1) Ur-Energy has begun production at its Lost Creek ISR uranium mine in Wyoming, with production exceeding initial projections.
2) The company acquired the Shirley Basin project in Wyoming, which is projected to be its next production center with permitting underway.
3) Ur-Energy has secured long-term uranium sales contracts through 2019 to provide revenue despite current uranium market volatility.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with its primary operating asset being the Lost Creek in-situ recovery uranium project in Wyoming. Key points include:
1) Lost Creek began production in 2013 and is ramping up towards steady-state levels, with production exceeding initial projections.
2) Additional resources were identified in 2013 at Lost Creek and at the Shirley Basin project acquired in late 2013, which could become the next production center.
3) Long-term sales contracts through 2019 provide revenue certainty in an uncertain market, with over 1 million pounds committed at an average price above $50/lb.
4) Preliminary economic analysis shows Lost Creek has
Ur-Energy provides a presentation on its operations and projects. It has begun production at its Lost Creek in-situ recovery uranium facility, with production exceeding initial projections. It also acquired the Pathfinder-Shirley Basin project in 2013, which has over 8 million pounds of uranium resources indicated for potential production in 2017. The presentation discusses Ur-Energy's contracts securing future uranium sales, low cost structure, and experienced management team, positioning it to benefit from increasing global nuclear energy demand.
Ur-Energy provides a presentation on their uranium production operations and market outlook. They have begun production at their Lost Creek ISR facility in Wyoming and are moving toward steady-state operations. They also acquired the Shirley Basin project and are permitting it for future development. The uranium market fundamentals are positive long term due to growing nuclear power usage and constrained primary supply, positioning Ur-Energy well to help meet US demand with their domestic production.
Ur-Energy's March 2017 Corporate PresentationUr-Energy
The document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming and development projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek project in Wyoming, which began production in 2013 and has produced over 2 million pounds of uranium through 2016. It also discusses Ur-Energy's Shirley Basin project in Wyoming, which has over 8.8 million pounds of resources identified. The document contains forward-looking statements about Ur-Energy's projects and the uranium market, and notes various risks and uncertainties involved.
Ur-Energy's June 2017 Corporate PresentationUr-Energy
This document provides an overview and summary of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy has steadily produced uranium from its Lost Creek ISR facility in Wyoming since 2013 and has expanded resources through exploration.
- The company is pursuing development of its Shirley Basin project in Wyoming.
- Long-term fundamentals for uranium demand remain positive due to expected growth in nuclear power globally. However, production cuts by major producers may tighten supply in the near-term.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
- Lost Creek is the company's flagship uranium production facility which began production in 2013 and is exceeding production targets with head grades 3-4 times projected levels.
- The Shirley Basin project in Wyoming was acquired in 2013 and a preliminary economic assessment was completed in January 2015, estimating 8.8 million pounds of uranium resources.
- Long term sales contracts through 2019 provide future revenue while market conditions remain uncertain. 514,000 pounds were sold in 2014 at an average price of $51.10 per pound.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013. It also mentions their next development project at Shirley Basin and provides details on Ur-Energy's management team, board of directors, the outlook for nuclear power and uranium demand, and Ur-Energy's position in the US uranium market. The document contains forward-looking statements and projections that are subject to risks and uncertainties.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013 and has exceeded production targets with head grades 3-4 times projections. It also discusses the Shirley Basin project acquired in 2013, which has an initial resource estimate of 8.8 million pounds from a technical report. Overall, the document outlines Ur-Energy's progress in establishing itself as a reliable uranium producer through operational successes at Lost Creek.
This document provides a disclaimer and overview of Ur-Energy Inc., a uranium mining company. It summarizes that Ur-Energy has begun production at its Lost Creek facility in Wyoming, exceeding expectations. It has also agreed to acquire Pathfinder Mines Corporation to expand its resources. Ur-Energy has a strong management team with extensive uranium industry experience and its stock is traded on the NYSE MKT and TSX exchanges. The document outlines that nuclear energy demand is growing as more reactors are planned worldwide. However, global uranium supply is constrained as high capital costs pose challenges for developing new mines.
Ur-Energy Q3 Webcast & Teleconference Power PointBrooke Rock
This document provides an overview and update of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's recent quarterly production results from its Lost Creek ISR uranium facility, discusses its resource growth and future development plans, and outlines its sales contracts and revenue expectations for 2016. The document cautions that certain statements regarding future plans and projections are forward-looking in nature.
The document is a presentation by Ur-Energy Inc. that provides an overview and disclaimer about the company. It summarizes that Ur-Energy has commenced production at its Lost Creek uranium facility in Wyoming, exceeding expectations. It is also expanding resources through acquisitions and exploration. Ur-Energy has secured revenue through long-term sales agreements and closed on $34 million in financing. The presentation provides details on Ur-Energy's market position, analyst coverage, management team, and the outlook for growing nuclear fuel demand and a changing global supply picture.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek uranium production facility in Wyoming and its Shirley Basin project in South Dakota. It also discusses the outlook for the uranium market, noting increasing global nuclear power usage while many primary uranium suppliers have cut production. Ur-Energy believes it is well-positioned to help meet growing US nuclear fuel demand with its domestic uranium production facilities.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
Ure corporate presentation final (final) 20140301Urenergy
The document is a presentation by Ur-Energy Inc. discussing its business operations and outlook. It summarizes that Ur-Energy has begun production at its Lost Creek in-situ recovery uranium facility in Wyoming, with first sales occurring in late 2013. It expects to ramp production up to 1 million pounds of uranium in 2014. It also recently acquired new uranium projects in Wyoming through the purchase of Pathfinder Mines Corporation. The presentation provides an overview of Ur-Energy's management and projects, and the outlook for growing demand in the nuclear power and uranium industries.
Ur Energy's February 2017 Corporate PresentationUr-Energy
This presentation discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
- Ur-Energy has established a reliable, low-cost uranium production center at its Lost Creek ISR facility in Wyoming and continues to expand resources through exploration.
- The company is pursuing development of its Shirley Basin project in Wyoming.
- Global demand for uranium is expected to increase in the coming years due to projected growth in nuclear power generation worldwide. However, production cuts by major producers may limit supply.
- Ur-Energy aims to realize better uranium sales prices through long-term sales agreements and has an experienced technical and management team.
Ur-Energy provides a presentation summarizing its business and operations. It discusses its Lost Creek in-situ recovery uranium mining project in Wyoming, which began production in late 2013. It also describes its agreement to acquire Pathfinder Mines Corporation, which holds additional uranium projects and assets. The presentation provides an overview of Ur-Energy's strategy, management team, and positioning in the uranium market.
The document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's operations, including its Lost Creek in-situ recovery uranium facility which began production in 2013. It also discusses Ur-Energy's acquisition of Pathfinder Mines Corporation and its uranium projects. The document contains forward-looking statements and disclaimers around the risks and uncertainties inherent in the uranium mining industry.
Ur-Energy's November 2017 Corporate PresentationUr-Energy
This document contains forward-looking statements regarding Ur-Energy's ability to maintain production operations at Lost Creek, deliver product on schedule, and further explore and develop projects like Shirley Basin. It also discusses Ur-Energy's recent sales agreements, production levels, and financial results. The document notes that analysts from various firms follow and report on Ur-Energy, and provides context on trends in the nuclear energy and uranium markets.
This corporate presentation from Ur-Energy provides information about the company and its projects. Ur-Energy is an advanced pre-production uranium company focused on developing its flagship Lost Creek project in Wyoming. Key objectives include bringing Lost Creek into production in 2013, expanding resources through exploration and acquisitions, and securing revenue through long-term sales agreements. Lost Creek has fully approved permits and is under construction, with initial production anticipated in the second half of 2013. Ur-Energy also has agreements to acquire additional projects from Pathfinder Mines Corporation that will provide future production centers.
This document provides an overview of Ur-Energy Inc. and its uranium production operations. It summarizes Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production in 2013, and its Shirley Basin project. It also discusses the state of the uranium market and supply and demand fundamentals. Finally, it provides production and cost data from Lost Creek's operations that demonstrate it is a reliable, low-cost producer.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's Shirley Basin project, acquired in 2013, which has 8.8 million pounds of high-grade uranium resources. The document outlines Ur-Energy's management team, long term sales contracts through 2019, and the positive long term outlook for nuclear and uranium demand.
Ur-Energy provides a presentation on its operations and projects. It has begun production at its Lost Creek in-situ recovery uranium facility, with production exceeding initial projections. It also acquired the Pathfinder-Shirley Basin project in 2013, which has over 8 million pounds of uranium resources indicated for potential production in 2017. The presentation discusses Ur-Energy's contracts securing future uranium sales, low cost structure, and experienced management team, positioning it to benefit from increasing global nuclear energy demand.
Ur-Energy provides a presentation on their uranium production operations and market outlook. They have begun production at their Lost Creek ISR facility in Wyoming and are moving toward steady-state operations. They also acquired the Shirley Basin project and are permitting it for future development. The uranium market fundamentals are positive long term due to growing nuclear power usage and constrained primary supply, positioning Ur-Energy well to help meet US demand with their domestic production.
Ur-Energy's March 2017 Corporate PresentationUr-Energy
The document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming and development projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek project in Wyoming, which began production in 2013 and has produced over 2 million pounds of uranium through 2016. It also discusses Ur-Energy's Shirley Basin project in Wyoming, which has over 8.8 million pounds of resources identified. The document contains forward-looking statements about Ur-Energy's projects and the uranium market, and notes various risks and uncertainties involved.
Ur-Energy's June 2017 Corporate PresentationUr-Energy
This document provides an overview and summary of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy has steadily produced uranium from its Lost Creek ISR facility in Wyoming since 2013 and has expanded resources through exploration.
- The company is pursuing development of its Shirley Basin project in Wyoming.
- Long-term fundamentals for uranium demand remain positive due to expected growth in nuclear power globally. However, production cuts by major producers may tighten supply in the near-term.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
- Lost Creek is the company's flagship uranium production facility which began production in 2013 and is exceeding production targets with head grades 3-4 times projected levels.
- The Shirley Basin project in Wyoming was acquired in 2013 and a preliminary economic assessment was completed in January 2015, estimating 8.8 million pounds of uranium resources.
- Long term sales contracts through 2019 provide future revenue while market conditions remain uncertain. 514,000 pounds were sold in 2014 at an average price of $51.10 per pound.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013. It also mentions their next development project at Shirley Basin and provides details on Ur-Energy's management team, board of directors, the outlook for nuclear power and uranium demand, and Ur-Energy's position in the US uranium market. The document contains forward-looking statements and projections that are subject to risks and uncertainties.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013 and has exceeded production targets with head grades 3-4 times projections. It also discusses the Shirley Basin project acquired in 2013, which has an initial resource estimate of 8.8 million pounds from a technical report. Overall, the document outlines Ur-Energy's progress in establishing itself as a reliable uranium producer through operational successes at Lost Creek.
This document provides a disclaimer and overview of Ur-Energy Inc., a uranium mining company. It summarizes that Ur-Energy has begun production at its Lost Creek facility in Wyoming, exceeding expectations. It has also agreed to acquire Pathfinder Mines Corporation to expand its resources. Ur-Energy has a strong management team with extensive uranium industry experience and its stock is traded on the NYSE MKT and TSX exchanges. The document outlines that nuclear energy demand is growing as more reactors are planned worldwide. However, global uranium supply is constrained as high capital costs pose challenges for developing new mines.
Ur-Energy Q3 Webcast & Teleconference Power PointBrooke Rock
This document provides an overview and update of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's recent quarterly production results from its Lost Creek ISR uranium facility, discusses its resource growth and future development plans, and outlines its sales contracts and revenue expectations for 2016. The document cautions that certain statements regarding future plans and projections are forward-looking in nature.
The document is a presentation by Ur-Energy Inc. that provides an overview and disclaimer about the company. It summarizes that Ur-Energy has commenced production at its Lost Creek uranium facility in Wyoming, exceeding expectations. It is also expanding resources through acquisitions and exploration. Ur-Energy has secured revenue through long-term sales agreements and closed on $34 million in financing. The presentation provides details on Ur-Energy's market position, analyst coverage, management team, and the outlook for growing nuclear fuel demand and a changing global supply picture.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
This document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming and South Dakota. It summarizes Ur-Energy's flagship Lost Creek uranium production facility in Wyoming and its Shirley Basin project in South Dakota. It also discusses the outlook for the uranium market, noting increasing global nuclear power usage while many primary uranium suppliers have cut production. Ur-Energy believes it is well-positioned to help meet growing US nuclear fuel demand with its domestic uranium production facilities.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's flagship Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's next development project at Shirley Basin, acquired in 2013, which has 8.8 million pounds of resources identified in a preliminary economic assessment. The document contains forward-looking statements regarding Ur-Energy's projections and timelines.
Ure corporate presentation final (final) 20140301Urenergy
The document is a presentation by Ur-Energy Inc. discussing its business operations and outlook. It summarizes that Ur-Energy has begun production at its Lost Creek in-situ recovery uranium facility in Wyoming, with first sales occurring in late 2013. It expects to ramp production up to 1 million pounds of uranium in 2014. It also recently acquired new uranium projects in Wyoming through the purchase of Pathfinder Mines Corporation. The presentation provides an overview of Ur-Energy's management and projects, and the outlook for growing demand in the nuclear power and uranium industries.
Ur Energy's February 2017 Corporate PresentationUr-Energy
This presentation discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
- Ur-Energy has established a reliable, low-cost uranium production center at its Lost Creek ISR facility in Wyoming and continues to expand resources through exploration.
- The company is pursuing development of its Shirley Basin project in Wyoming.
- Global demand for uranium is expected to increase in the coming years due to projected growth in nuclear power generation worldwide. However, production cuts by major producers may limit supply.
- Ur-Energy aims to realize better uranium sales prices through long-term sales agreements and has an experienced technical and management team.
Ur-Energy provides a presentation summarizing its business and operations. It discusses its Lost Creek in-situ recovery uranium mining project in Wyoming, which began production in late 2013. It also describes its agreement to acquire Pathfinder Mines Corporation, which holds additional uranium projects and assets. The presentation provides an overview of Ur-Energy's strategy, management team, and positioning in the uranium market.
The document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's operations, including its Lost Creek in-situ recovery uranium facility which began production in 2013. It also discusses Ur-Energy's acquisition of Pathfinder Mines Corporation and its uranium projects. The document contains forward-looking statements and disclaimers around the risks and uncertainties inherent in the uranium mining industry.
Ur-Energy's November 2017 Corporate PresentationUr-Energy
This document contains forward-looking statements regarding Ur-Energy's ability to maintain production operations at Lost Creek, deliver product on schedule, and further explore and develop projects like Shirley Basin. It also discusses Ur-Energy's recent sales agreements, production levels, and financial results. The document notes that analysts from various firms follow and report on Ur-Energy, and provides context on trends in the nuclear energy and uranium markets.
This corporate presentation from Ur-Energy provides information about the company and its projects. Ur-Energy is an advanced pre-production uranium company focused on developing its flagship Lost Creek project in Wyoming. Key objectives include bringing Lost Creek into production in 2013, expanding resources through exploration and acquisitions, and securing revenue through long-term sales agreements. Lost Creek has fully approved permits and is under construction, with initial production anticipated in the second half of 2013. Ur-Energy also has agreements to acquire additional projects from Pathfinder Mines Corporation that will provide future production centers.
This document provides an overview of Ur-Energy Inc. and its uranium production operations. It summarizes Ur-Energy's Lost Creek uranium production facility in Wyoming, which began production in 2013, and its Shirley Basin project. It also discusses the state of the uranium market and supply and demand fundamentals. Finally, it provides production and cost data from Lost Creek's operations that demonstrate it is a reliable, low-cost producer.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. It summarizes Ur-Energy's flagship Lost Creek in-situ recovery uranium project, which began production in 2013 and has exceeded production targets with higher than expected head grades. It also discusses Ur-Energy's Shirley Basin project, acquired in 2013, which has 8.8 million pounds of high-grade uranium resources. The document outlines Ur-Energy's management team, long term sales contracts through 2019, and the positive long term outlook for nuclear and uranium demand.
- The document is the transcript from a Ur-Energy teleconference and webcast that discusses the company's Lost Creek uranium production facility and Pathfinder-Shirley Basin development project.
- Lost Creek has exceeded production targets with head grades 3-4 times higher than projected, and the facility has successfully captured over 500,000 pounds of uranium between 2013-2014.
- An updated preliminary economic assessment estimates 9.2 million pounds of uranium can be recovered from Lost Creek over its lifetime at a low cash operating cost of $21.61 per pound.
BPI Build-HD is a dietary supplement that claims to help build muscle mass and strength. It contains several ingredients that some research suggests may help with muscle growth like creatine, beta-alanine, and vitamin D. However, more research is still needed to determine the effectiveness of this particular product for muscle building.
Dog-eat-dog 03 - Ergonomie - Sweep zone et GestaltDogstudio
Les Dog-eat-Dog sont des présentations informels organisés par Dogstudio tous les vendredi à Namur.
Ce Dog-eat-dog propose de présenter la théorie de Gestalt dans l'ergonomie Web.
Les Dog-eat-Dog sont des présentations informels organisés par Dogstudio tous les vendredi à Namur.
L'idée est de présenter en 10-15 min un sujet afin d'améliorer la web-attitude de tout un chacun.
Ouvert à tous bien évidement !
This presentation discusses Ur-Energy's Lost Creek uranium production facility and Pathfinder Shirley Basin project. It summarizes Ur-Energy's commercial progress in 2014, including establishing production at Lost Creek and completing sales agreements. It also outlines the company's management team and board of directors as well as the positive long-term fundamentals of the uranium market, including growing nuclear power usage and constrained primary supply. However, the presentation contains forward-looking statements that are subject to risks and uncertainties.
This document provides a summary of Ur-Energy Inc., a uranium mining company. It discusses Ur-Energy's Lost Creek in-situ recovery uranium facility, which began production in 2013 and produced its 1 millionth pound of uranium in 2015. It also mentions Ur-Energy's Shirley Basin project and expansion of resources at Lost Creek. The document contains forward-looking statements and projections regarding future production, costs, and the uranium market. It provides an overview of Ur-Energy's management team, sales agreements, development pipeline, and growth strategy.
This document provides an overview of Ur-Energy Inc., a uranium mining company. It summarizes Ur-Energy's Lost Creek uranium facility in Wyoming, which began production in 2013 and produced its 1 millionth pound of uranium in 2015. It also mentions Ur-Energy's exploration properties and resource growth. Additionally, it provides background on Ur-Energy's leadership team and board of directors as well as the current state of the uranium market, including supply and demand fundamentals.
This document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's Lost Creek in-situ recovery uranium mine, which began production in 2013, and discusses plans to develop the nearby Shirley Basin project. Production results from Lost Creek are exceeding initial projections due to higher-than-expected uranium grades. The document also notes that long-term uranium sales contracts have been signed to provide revenue through 2021 and that resources have increased through exploration at the Lost Creek property.
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming, USA. It summarizes Ur-Energy's Lost Creek uranium production facility and its Shirley Basin development project. It also discusses the state of the global uranium market, including growing nuclear power demand, constrained primary supply, and the need for new producers like Ur-Energy to help fill the gap.
- Lost Creek ISR uranium project in Wyoming has been in production since 2013, with production exceeding projections and head grades 3-4 times higher than estimated.
- A 2013 preliminary economic assessment estimated 9.2 million pounds of recoverable uranium over the life of the mine with low production costs and strong economics.
- The company has long term sales contracts in place through 2020 to sell uranium at prices above costs of production, providing revenue stability.
This presentation discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming. It summarizes Ur-Energy's Lost Creek uranium production facility, which recently produced its 1 millionth pound of uranium, and discusses plans to develop the Shirley Basin project. The presentation also provides an overview of the current state of the uranium market, including supply and demand fundamentals and the impact of Japan restarting nuclear reactors. Financial information on Ur-Energy's share structure and analysts coverage is also presented.
- The document discusses Ur-Energy Inc., a uranium mining company with operations in Wyoming.
- It summarizes Ur-Energy's Lost Creek uranium production facility, which began production in 2013 and has exceeded production targets with head grades 3-4 times projections.
- It also mentions Ur-Energy's exploration properties, including an upcoming PEA on the Shirley Basin project, and provides an overview of the company's operations and financial position.
This document provides an overview of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy has established steady-state production at its flagship Lost Creek ISR uranium facility in Wyoming and expanded resources through exploration drilling.
- The company's next development project is Shirley Basin in Wyoming, for which a preliminary economic assessment was completed. Permit applications are expected in the fourth quarter of 2015.
- Ur-Energy has a balanced cashflow plan for 2016 secured through an amended loan repayment schedule and scheduled uranium deliveries.
This presentation discusses Ur-Energy's Lost Creek uranium production facility and exploration projects. It notes that Lost Creek has achieved steady-state production and delivered its 1 millionth pound of uranium. Resources have increased at Lost Creek and permitting is underway for the Shirley Basin project. The document also provides an overview of the uranium market, including supply and demand fundamentals and the restart of nuclear reactors in Japan.
Ur-Energy May 2016 Corporate PresentationBrooke Rock
This presentation provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
1) Ur-Energy has established a reliable, low-cost uranium production center at its Lost Creek ISR facility in Wyoming and has expanded resources through exploration.
2) The company is advancing its Shirley Basin project and completing permitting to become its next uranium development.
3) Ur-Energy has a strong technical team with over 180 years of combined uranium production experience in ISR operations.
The document provides an overview of Ur-Energy Inc., a uranium mining company with projects in Wyoming. Key points include:
- Lost Creek is the company's flagship in-situ recovery uranium facility which began production in 2013 and has exceeded production targets.
- Resources at Lost Creek have increased 250% since 2011 with measured, indicated and inferred resources now totaling over 21 million pounds.
- A preliminary economic assessment outlines potential production of 13.8 million additional pounds over the life of the Lost Creek mine.
- The company's next development project is Shirley Basin, also located in Wyoming.
Ur-Energy July 2016 Corporate PresentationBrooke Rock
- Lost Creek ISR uranium facility in Wyoming has been in steady-state production since 2013, producing over 1.73M lbs of U3O8 to date at low costs.
- Resources at the Lost Creek property have increased significantly since 2011 through exploration, with measured and indicated resources totaling over 14.6M lbs U3O8.
- The company aims to be a "pipeline producer" through developing its projects beyond Lost Creek, with the next project being Shirley Basin in Wyoming.
Ur-Energy June 2016 Corporate PresentationBrooke Rock
- Lost Creek ISR uranium facility in Wyoming has been in steady-state production since 2013, producing over 1.73M lbs of U3O8 to date at low costs.
- Resources at the Lost Creek property have increased significantly since 2011 through exploration, totaling over 14.6M lbs of measured and indicated resources currently.
- The Shirley Basin project in Wyoming is the company's next development project, with a positive preliminary economic assessment completed in 2015 and permitting applications underway.
Ur-Energy April 2016 Corporate PresentationUr-Energy
The document provides an overview of Ur-Energy Inc., a uranium mining company with operations in Wyoming. Key points include:
- Lost Creek is the company's flagship ISR uranium facility which began production in 2013 and has exceeded production targets, demonstrating it is a reliable, low-cost operation.
- Resources at Lost Creek have increased 250% since 2011 with measured, indicated, and inferred resources now totaling over 14 million pounds.
- A preliminary economic assessment outlines potential to produce over 13 million additional pounds at Lost Creek with low production costs.
- The company has long-term sales contracts in place to deliver over 3 million pounds of uranium through 2021, providing revenue certainty.
Ur-Energy November 2016 Corporate PresentationBrooke Rock
Ur-Energy provides a summary of its Lost Creek uranium facility and resources. Lost Creek has produced over 2 million pounds of U3O8 through Q3 2016 and continues steady-state production. Resources have increased 250% since 2011 with measured and indicated resources now totaling over 14.6 million pounds. An amended preliminary economic assessment estimates Lost Creek can produce an additional 13.8 million pounds over its lifetime.
Ur-Energy December 2016 Corporate PresentationBrooke Rock
This document provides an overview and summary of Ur-Energy Inc., a uranium mining company. Key points include:
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming and is developing the Shirley Basin project.
- Lost Creek has steadily produced over 2 million pounds of uranium since 2013 and resource expansion continues.
- The company aims to realize better sales prices through long-term sales agreements and reduce exposure to volatile markets.
- Ur-Energy has a strong technical team with over 180 years of combined uranium production experience in ISR operations.
Ur-Energy August 2016 Corporate Presentation Brooke Rock
- Ur-Energy operates the Lost Creek in-situ recovery uranium facility in Wyoming which began production in 2013 and has produced 1.86M lbs of U3O8 through June 2016. Resource expansion has increased measured, indicated, and inferred resources by 4.6M lbs, 1.7M lbs, and 6.4M lbs respectively since 2015.
- The company has secured long-term sales contracts through 2021 at an average price of $49.81/lb for approximately 3.1M lbs to provide revenue certainty in the current market.
- Ur-Energy is advancing the Shirley Basin project in Wyoming and recently filed permit applications, with the goal of developing additional uranium production centers in
Similar to Ure corporate presentation 20140411 (final) (18)
UnityNet World Environment Day Abraham Project 2024 Press ReleaseLHelferty
June 12, 2024 UnityNet International (#UNI) World Environment Day Abraham Project 2024 Press Release from Markham / Mississauga, Ontario in the, Greater Tkaronto Bioregion, Canada in the North American Great Lakes Watersheds of North America (Turtle Island).
Methanex is the world's largest producer and supplier of methanol. We create value through our leadership in the global production, marketing and delivery of methanol to customers. View our latest Investor Presentation for more details.
Cleades Robinson, a respected leader in Philadelphia's police force, is known for his diplomatic and tactful approach, fostering a strong community rapport.
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfSOFTTECHHUB
The world of blockchain and decentralized technologies is about to witness a groundbreaking event. ZKsync, the pioneering Ethereum Layer 2 network, has announced the highly anticipated airdrop of its native token, ZK. This move marks a significant milestone in the protocol's journey, empowering the community to take the reins and shape the future of this revolutionary ecosystem.
2. NYSE MKT: URG • TSX: URE
This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur in the future. Such
statements include without limitation the Company’s timeframe for events culminating in the completion of commissioning and ramp up of production at Lost Creek; timing of
making product deliveries; the technical and economic viability of Lost Creek (including the production and cost projections contained in the preliminary economic analysis of the
Lost Creek Property); the ability to complete additional favorable uranium sales agreements and ability to reduce exposure to volatile market; the potential of exploration targets
throughout the Lost Creek Property (including the ability to expand resources); the further exploration, development and permitting of exploration and development projects
including at PMC projects; the long term effects on the uranium market of events in Japan in 2011 including supply and demand projections; and whether a re-rating of the
Company will occur with production ramp up. These statements are based on current expectations that, while considered reasonable by management at this time, inherently
involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Numerous factors could cause actual events to differ materially from
those in the forward-looking statements. Factors that could cause such differences, without limiting the generality of the following, include: risks inherent in exploration activities;
volatility and sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of exploration competition; the ability to raise funds through
private or public equity financings; imprecision in resource and reserve estimates; environmental and safety risks including increased regulatory burdens; unexpected geological
or hydrological conditions; a possible deterioration in political support for nuclear energy; changes in government regulations and policies, including trade laws and policies;
demand for nuclear power; weather and other natural phenomena; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; and
other exploration, development, operating, financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking statements
are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this presentation. Ur-Energy Inc. disclaims any intention or obligation
to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise.
Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and, accordingly, the estimates and
assumptions underlying the projections are inherently highly uncertain, based on events that have not taken place, and are subject to significant economic, financial, regulatory,
competitive and other uncertainties and contingencies beyond the control of Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a
number of significant risk factors, there can be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly
materially, from those projected.
The attention of investors is drawn to the Risk Factors set out in the Company's Annual Report on Form 10-K, dated March 3, 2014, which is filed with the U.S. Securities and
Exchange Commission on EDGAR (http://www.sec.gov/edgar.shtml) and the regulatory authorities in Canada on SEDAR (www.sedar.com).
Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the terms "measured", "indicated"
and "inferred" mineral resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities
and Exchange Commission does not recognize these terms. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources
will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically
or legally minable.
John Cooper, Ur-Energy Project Geologist, P.Geo., SME Registered Member and Qualified Person as defined by National Instrument 43-101, reviewed and approved
the technical information contained in this presentation.
Disclaimer
2
3. NYSE MKT: URG • TSX: URE
Lost Creek ISR - The World’s Newest Uranium
Production Facility
Initiated production activities in August 2013
First product sales and revenue in December 2013
Expanded resources with December 2013 PEA
High production grade exceeds expectations
Pathfinder - Shirley Basin, our Next Development
Completed acquisition in December 2013
Commencing permitting activities in 2014
Resource Technical Report in 2014
Ur-Energy at a Glance
3
Realizing better sales prices through long term sales agreements
Capital intensive year occurred in 2013 to build and start Lost Creek
Closed US$34 million Wyoming Industrial Development Revenue Bond
Commercial banking relationship established with RMBAH
Listed on the Russell 3000 Index
See Disclaimer re Forward-looking Statements and Projections (slide 2)
4. NYSE MKT: URG • TSX: URE
Share Capital & Cash Position
As of 2/28/14
Shares Outstanding 128.11M
Stock Options & RSUs 8.68M
Warrants 8.37M
Fully Diluted 145.16M
Market Cap (4/11/14) US$179.22M
Cash (12/31/13) US$1.6M
Cash per Share (12/31/13) ~US$0.01
Share Price (4/10/14) US$1.50
52 Week Range US$.74 - $1.99
Avg. Daily Volume ~1,957,400
(3-mo URG & URE 4/11/14)
Member of S&P/TSX SmallCap Index
Geographical Distribution as of 6/30/13
United States ~53%
Canada ~23%
Other ~24%
Ur-Energy’s Market Position
4
NYSE MKT: URG
TSX: URE
5. NYSE MKT: URG • TSX: URE
Ur-Energy Inc. is followed by the analysts listed above. This list, including the firms and individual analysts at these firms, is subject to change at
any time without notice. Please note that any opinions, estimates, forecasts, conclusions or recommendations regarding Ur-Energy Inc.
performance made by these analysts are theirs alone and do not represent opinions, estimates, forecasts, conclusions, recommendations or
predictions of Ur-Energy Inc. or its management. Ur-Energy Inc. does not by its reference above or in any other manner imply its endorsement
of or concurrence with such information, conclusions or recommendations.
United States
H.C. Wainwright Jeff Wright (New York, NY) 1.212.365.0545
Roth Capital Partners Joseph Reagor (Newport Beach, CA) 1.949.720.7106
Analyst Coverage
5
Canada
Cantor Fitzgerald Rob Chang (Toronto, ON) 1.416.849.5008
Dundee Securities David Talbot (Toronto, ON) 1.416.350.3082
Haywood Securities Colin Healey (Vancouver, BC) 1.604.697.7400
L.B. Securities Chris Chang (Toronto, ON) 1.416.865.5798
Raymond James David Sadowski (Vancouver, BC) 1.604.659.8255
6. NYSE MKT: URG • TSX: URE
Board of Directors
Executive Directors
Wayne W. Heili, President & Chief Executive Officer (Metallurgical Engineer)
Jeffrey T. Klenda,* Board Chairman, Executive Director (Mining Finance)
Non-Executive Directors
W. William Boberg,* Former President & CEO (Professional Geologist)
James M. Franklin,* Chair-Technical Committee (Professional Geologist)
Paul Macdonell,* Chair-Compensation and Corp. Governance & Nominating Committees
(Private Mediator)
Thomas H. Parker, Chair-Audit Committee (Professional Engineer)
Officers
Roger L. Smith, Chief Financial Officer & Chief Administrative Officer (CPA & MBA)
Steven M. Hatten, VP Operations (Mining Engineer)
John W. Cash, VP Regulatory Affairs (Geologist & Geophysicist)
James A. Bonner, VP of Geology (Professional Geologist)
Penne A. Goplerud, Corporate Secretary & General Counsel (JD)
* Founding Directors
Experienced Management Team
6
7. NYSE MKT: URG • TSX: URE
Highly experienced technical and management team
160 years of direct uranium production experience
ISR operations experience – Nebraska, Texas, Wyoming & Kazakhstan
Industry Leading Professionals
7
8. NYSE MKT: URG • TSX: URE
435 operable reactors world wide
with 374 GWe capacity
66 New Nuclear Reactors under
construction in 13 countries
160 planned
319 proposed
Nuclear Fuel Demand is Growing
8
Renewed prospect of restarting Japan’s reactor fleet (projected first half of 2014)
In 2012 world nuclear industry consumption was ~180 million lbs. and
production was only ~152 million lbs.
*Source: UxC Uranium Market Outlook
See Disclaimer re Forward-looking Statements and Projections (slide 2)
9. NYSE MKT: URG • TSX: URE
HEU secondary supply concluded in 2013
Provided 24 Mlbs/yr equivalent for past 20 years
Large scale production uneconomical at current prices
Rossing – reduced production rates (6.0 Mlbs/yr)
Ranger – shut down indefinitely (5.0 Mlbs/yr)
Paladin – Kayelekera production halted (3.0 Mlbs/yr)
Key supply deferrals
BHP Billiton – Olympic Dam expansion
Cameco – Kintyre
Areva – Trekkopje and Imouraren
Many more
Current uranium pricing cannot sustain high cost producers
New Global Supply Is In Decline
9
See Disclaimer re Forward-looking Statements and Projections (slide 2)
10. NYSE MKT: URG • TSX: URE
US demand is not met by US production
US domestic production ~ 4M lbs of uranium/yr1
US utilities consume ~55M lbs of uranium/yr1
URG 2014 estimate of ~1M lbs, ~20% of US market share
Ur-Energy is well positioned to capitalize on this opportunity
1 U.S. Energy Information Administration
The US Uranium Market
10
See Disclaimer re Forward-looking Statements and Projections (slide 2)
11. NYSE MKT: URG • TSX: URE
Exclusive representation by Jim Cornell of NuCore Energy, LLC in
negotiations of off-take purchase agreement
Focused on the United States
nuclear utilities market
Six long term contracts spanning
2013-2019 timeframe
De-risking by securing future
revenue stream in an uncertain
market
Long term pricing that supports
production plans for Lost Creek
Sound Marketing Strategy
11
See Disclaimer re Forward-looking Statements and Projections (slide 2)
12. NYSE MKT: URG • TSX: URE
Ur-Energy is a “Pipeline Producer”
Identify and develop resources holding
substantial potential for economic
production
Not just looking at “Pounds in the Ground”
Ur-Energy’s Strategic Position
12
Management team with a proven
record of funding and developing new
mining projects
US marketing and sales strategy
Objective to grow into mid-tier producer
See Disclaimer re Forward-looking Statements and Projections (slide 2)
14. NYSE MKT: URG • TSX: URE
In-Situ Recovery (ISR) Uranium Mining
14
Environmentally sound production method
Well understood by Wyoming state regulators
Cost effective, low capital costs
15. NYSE MKT: URG • TSX: URE
Exploration targets within the Lost Creek
Project and adjoining projects provide
potential of additional resources U3O8
Lost Creek Project – 4,254 permit acres
Adjoining projects – ~38,000 acresMany of these exploration targets remain conceptual in nature.
There has been insufficient exploration to define mineral resource
estimates at all such exploration targets. It is uncertain if further
exploration will result in the additional target areas being
delineated as further mineral resource.
Resource Update for the NI 43-101 Preliminary Economic Assessment
of the Lost Creek Property (December 30, 2013)
Measured: 4.85 Mlbs eU3O8 (in 4.29 Mt @ 0.057%)
Indicated: 3.80 Mlbs eU3O8 (in 4.04 Mt @ 0.048%)
Inferred: 4.74 Mlbs eU3O8 (in 4.72 Mt @ 0.051%)
* Based on grade cutoff of 0.02% eU3O8 and a GT cutoff of 0.3
The Lost Creek Property
15
See Disclaimer re Forward-looking Statements and Projections (slide 2)
16. NYSE MKT: URG • TSX: URE
Lost Creek Production Status
Finished Yellowcake Product
16
Mine Unit 1
Ion Exchange Vessels for Uranium Recovery
A Construction and Operational Success
Operations commenced in August 2013
Commissioned all production circuits in 2013
Surpassing production targets
Peak production grade 2X-3X PEA projections
>80,000 pounds recovered in January 2014
2014 objective – approximately 1.0 million pounds
17. NYSE MKT: URG • TSX: URE
Interior of Header House
Lost Creek Processing Plant
Lost Creek In Operation
17
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Twin Yellowcake Dryers
2013 uranium production
190K pounds recovered
131K pounds finished product
$21.98/lb. cash cost
First revenues from operations, December 2013
$5.7 million
Sale of 90K pounds at $62.92/lb.
18. NYSE MKT: URG • TSX: URE
December 30, 2013 PEA* updates resources and economic analysis
Estimates 9.2 million pounds recoverable over life of mine
Lost Creek Project Economics
Gross Revenues of US$588M LOM
Net Cash flow US$319M
Internal rate of return (IRR) at 74.5%
Lowest quartile Uranium Production Costs
Estimates direct operating costs at US $11.54/lb.
Cash Operating Cost including sustaining development US$21.61/lb.
LOM Project Cost including initial capital and reclamation US$29.13/lb.
Capital requirement of US$49M
US$46.5 initial capital completed prior to PEA effective date
*Preliminary Economic Assessment of the Lost Creek Property, Sweetwater County, Wyoming prepared by TREC Inc. – December 30, 2013
(posted on SEDAR and EDGAR).
Cautionary Statement: This PEA is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the
economic considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this PEA is based on
both site-specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery at this level
will be achieved.
Preliminary Economic Assessment
18
See Disclaimer re Forward-looking Statements and Projections (slide 2)
19. NYSE MKT: URG • TSX: URE
Purchase closed in December 2013
Deal Terms
Cash: ~US$6.6M
Conditional Royalty (5%)
Based on future uranium
spot market pricing
Capped maximum value
PMC Shirley Basin projected as
Ur-Energy’s next production center
Pathfinder Mines Acquisition
19
See Disclaimer re Forward-looking Statements and Projections (slide 2)
20. NYSE MKT: URG • TSX: URE
Shirley Basin
Licensing and development planning to be
initiated this year for 2017 production
Historic estimate of resources: >10 Mlbs
U3O8*, subject to conversion to NI 43-101
compliant
Shallow, high grade roll front deposit:
average 0.21% U3O8; ISR amenable
mineralization
Resources located on patented mining
claims
Lucky Mc – Gas Hills
Historic estimate of resources: 4.7 Mlbs
U3O8*
Strategic opportunities with nearby
developers
*Ur-Energy is not treating the historic reports as current mineral resources or mineral reserves, because a Qualified Person has not yet conducted
sufficient work to classify the estimates as such. Shirley Basin resource estimate is based on a krigged GT layer model conducted in 2010,
employing various cut offs. Lucky Mc resource estimate is based on a 1996 polygonal method estimation.
Pathfinder Projects
20
See Disclaimer re Forward-looking Statements and Projections (slide 2)
21. NYSE MKT: URG • TSX: URE
ISR by-product disposal facility
Revenue generating asset
Fully licensed for operation
Multiple disposal agreements in place
Scarce asset – 1 of 4 commercial facilities of this type in the US
Historical US uranium exploration database
Hundreds of project descriptions located in twenty-three states
More than 15,000 drill logs; technical and economic evaluations
Strong addition to Ur-Energy’s existing project database
Pathfinder Assets
21
See Disclaimer re Forward-looking Statements and Projections (slide 2)
22. NYSE MKT: URG • TSX: URE
M&I resource average GT of
1.1 (17.2 ft @ 0.065% U3O8)
Shallow: 240 feet deep
Over 3,700 drill holes define
deposit
(Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR)
Can be licensed with NRC as amendment to Lost Creek license
NI 43-101 Resource, July 2006
Measured & Indicated: 12.2 Mlbs eU3O8
(in 9.4 Mt @ 0.065%)
Inferred: 1.8 Mlbs eU3O8
(in1.6 Mt @ 0.055%)
Lost Soldier
22
See Disclaimer re Forward-looking Statements and Projections (slide 2)
23. NYSE MKT: URG • TSX: URE
Growth oriented technical & management team
Proven record of developing projects through to production
Low-cost uranium production center at Lost Creek
Production rates exceeding technical expectations
Development (not exploration) project pipeline
Pathfinder – Shirley Basin
Multiple long-term uranium sales agreements
Reducing Company exposure to volatile marketplace
Cash flowing project to secure financial picture
Continued re-rating likely as Ur-Energy proves production credentials
Ur-Energy – Right Now!
23
See Disclaimer re Forward-looking Statements and Projections (slide 2)
24. NYSE MKT: URG • TSX: URE
1. Advance Lost Creek to nameplate production
Ramping up production rates
Expand NI 43-101 compliant resources through drilling programs
2. Pathfinder Mines
Transition to operating and regulatory activities
Bring resources to NI 43-101 compliance
3. Corporate finance – positive cash position
Lost Creek production revenues
Leader in innovative finance actions
4. Growth in production profile
Expand Lost Creek Property resources
New initiatives
2014 Objectives & News Flow
24
See Disclaimer re Forward-looking Statements and Projections (slide 2)
25. NYSE MKT: URG • TSX: URE
For more information, please contact:
Wayne Heili, President, Chief Executive Officer & Director
Jeff Klenda, Board Chairman & Executive Director
Rich Boberg, Director of Investor and Public Relations
Charisse Heser, Manager of Investor and Public Relations
By Mail:
Ur-Energy Corporate Office
10758 W. Centennial Rd., Suite 200
Littleton, CO 80127 USA
By Phone:
Office 720.981.4588
Toll-Free 866.981.4588
Fax 720.981.5643
By E-mail:
wayne.heili@ur-energy.com
jeff.klenda@ur-energy.com
rich.boberg@ur-energy.com
charisse.heser@ur-energy.com
Ur-Energy–The Right People. The Right Projects. Right Now!
25