SlideShare a Scribd company logo
TYPES OF BUILDING CONTRACT
• Lump-sum Contract
• Cost Plus Fixed Fee Contract
• Cost Plus Bid Bid Fee Contract
• Guaranteed Maximum Contract
• Negotiated Contract
• Unit-price Contract
• Design Build
• Turn Key Contracts
Lump-sum Contract
• Traditional method of Contract.
• The contractor offers to do the whole work for a total
stipulated sum of money as shown in drawings and
described by specification.
• It is more suitable for works which contractor have
prior construction experience.
• This is considered when tender process will tend to be
slower and preparing a tender may be more expensive
for the contractor.
Lump-sum Contract(Contd.)
Advantages
• Owner is aware of the cost of the project before the
project construction starts.
• Project scope and limits are defined prior to the start
of construction.
• Contractual relation between all parties, owner and
Engineer are clearly defined.
• Best price for work obtained through competitive
process with cost of work established and agreed
upon.
Lump-sum Contract(Contd.)
Disadvantages
• The lack of time flexibility in this method may result in
delayed project implementation.
• Highly skilled Architect or Engineer is needed.
• Difficult to implement revisions or change in the work
on the later stage of the work.
Cost Plus fixed fee Contract
•All Cost for the work according to the specification is
reimbursed by the owner to the contractor.
•Contractor is paid a fixed sum which represents the profit
•The variation on the lump-sum fee is percentage fee
wherein fees is established by percentage of total cost
incurred by the contractor.
•Usually it is fixed as a sum.
Cost Plus Bid fee Contract
•Owner invites proposal from qualified contractor
in terms of past experience, performance , etc.
•All Cost for the work according to the
specification is reimbursed by the owner to the
contractor.
•The bid fee is calculated on the basis of project
scope.
Guaranteed Maximum Contract
•The contractor agrees to perform work within a
price ceiling. This is the maximum guaranteed
price.
•If the ceiling is exceeded, without change in scope
then the excess cost is borne by the contractor.
•If the work is accomplished under the ceiling then
the owner pays no more than the actual cost and
the profit is shared between the contractor and
the owner.
•This method gives greater flexibility for the owner
Negotiated Contract
The preselected contractors are invited upon on
the basis of
• Capability of the past experience in the specific
area
• Availability of the personnel to accomplish the
work in the specified time frame
• Bid (Estimate) Price
• Proposed method for compensation including
amount of fee.
Negotiated Contract (Contd.)
•The owner is then negotiating with the contract
including method of payment for the work, Bid,
etc.
•On the basis of circumstances it can be
competitive or non-competitive.
Unit Price Contract
•Based on the estimated quantities of the items
involved in the work.
•The cost per unit item is given by the contractor
and the estimated quantities of items are given by
the owner.
•The total cost of work can only be calculated only
measurement is made
after the completion of the work because
on the basis of work
actually done.
Unit Price Contract (Contd.)
•The contractor is obliged to perform the work
actually required in the field at his quoted price
only.
•If the estimated quantity is exceeds, then there
should be increase in unit price , therefore it is
difficult to forecast the project cost.
Design Build
•It is a method to deliver a project in which the design and
construction services are contracted by a single entity
known as the design–builder or design–build contractor
•design–build relies on a single point of responsibility
contract and is used to minimize risks for the project
owner and to reduce the delivery schedule by
overlapping the design phase and construction phase of a
project.
•Contractor will be responsible for all of the work on the
project, regardless of the nature of the fault
Turn-key contracts
•A type of project that is constructed so that it could be
sold to any buyer as a completed product.
•This is contrasted with build to order, where the
constructor builds an item to the buyer's exact
specifications, or when an incomplete product is sold
with the assumption that the buyer would complete it.

More Related Content

Similar to types-170309142854.pptx

Types of contracts
Types of contractsTypes of contracts
Types of contracts
Tulsi Pokhrel
 
Construction contract
Construction contract Construction contract
Construction contract
Rakshith Reddy
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
Anil Kumar(6)
 
Negotiated contracts
Negotiated contractsNegotiated contracts
Negotiated contracts
SHUBHAM SINGH
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
fritzlejarso
 
3. Contract Pricing.pdf
3. Contract Pricing.pdf3. Contract Pricing.pdf
3. Contract Pricing.pdf
MohammedAlQudsi2
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
kohwenqi
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
Association for Project Management
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
R.R.G.S Bandara
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
Mohib Ullah
 
Contract costing
Contract costingContract costing
Contract costing
Prince Sagoo
 
Types of contract
Types of contractTypes of contract
Types of contract
HarshalNarkhede7
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
arpantripathi2
 
3 Type of contracts.pdf
3 Type of contracts.pdf3 Type of contracts.pdf
3 Type of contracts.pdf
ThanoonQasem
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
mianmohsinmumtazshb
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
Kunal Kacholiya
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
Touqeer1
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
mayuray
 

Similar to types-170309142854.pptx (20)

Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Construction contract
Construction contract Construction contract
Construction contract
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Negotiated contracts
Negotiated contractsNegotiated contracts
Negotiated contracts
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
3. Contract Pricing.pdf
3. Contract Pricing.pdf3. Contract Pricing.pdf
3. Contract Pricing.pdf
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
 
Contract costing
Contract costingContract costing
Contract costing
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
3 Type of contracts.pdf
3 Type of contracts.pdf3 Type of contracts.pdf
3 Type of contracts.pdf
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 

Recently uploaded

一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANE
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANEEASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANE
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANE
Febless Hernane
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
7sd8fier
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
LORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLO
LORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLOLORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLO
LORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLO
lorraineandreiamcidl
 
Moldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo espMoldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo esp
Hess9
 
Technoblade The Legacy of a Minecraft Legend.
Technoblade The Legacy of a Minecraft Legend.Technoblade The Legacy of a Minecraft Legend.
Technoblade The Legacy of a Minecraft Legend.
Techno Merch
 
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With DesignsGame Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
184804
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
Storytelling For The Web: Integrate Storytelling in your Design Process
Storytelling For The Web: Integrate Storytelling in your Design ProcessStorytelling For The Web: Integrate Storytelling in your Design Process
Storytelling For The Web: Integrate Storytelling in your Design Process
Chiara Aliotta
 
Connect Conference 2022: Passive House - Economic and Environmental Solution...
Connect Conference 2022: Passive House -  Economic and Environmental Solution...Connect Conference 2022: Passive House -  Economic and Environmental Solution...
Connect Conference 2022: Passive House - Economic and Environmental Solution...
TE Studio
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
taqyed
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
smpc3nvg
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
aaryangarg12
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
M. A. Architect
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
PDF SubmissionDigital Marketing Institute in Noida
PDF SubmissionDigital Marketing Institute in NoidaPDF SubmissionDigital Marketing Institute in Noida
PDF SubmissionDigital Marketing Institute in Noida
PoojaSaini954651
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Mansi Shah
 

Recently uploaded (20)

一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANE
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANEEASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANE
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANE
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
LORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLO
LORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLOLORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLO
LORRAINE ANDREI_LEQUIGAN_HOW TO USE TRELLO
 
Moldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo espMoldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo esp
 
Technoblade The Legacy of a Minecraft Legend.
Technoblade The Legacy of a Minecraft Legend.Technoblade The Legacy of a Minecraft Legend.
Technoblade The Legacy of a Minecraft Legend.
 
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With DesignsGame Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
Storytelling For The Web: Integrate Storytelling in your Design Process
Storytelling For The Web: Integrate Storytelling in your Design ProcessStorytelling For The Web: Integrate Storytelling in your Design Process
Storytelling For The Web: Integrate Storytelling in your Design Process
 
Connect Conference 2022: Passive House - Economic and Environmental Solution...
Connect Conference 2022: Passive House -  Economic and Environmental Solution...Connect Conference 2022: Passive House -  Economic and Environmental Solution...
Connect Conference 2022: Passive House - Economic and Environmental Solution...
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
PDF SubmissionDigital Marketing Institute in Noida
PDF SubmissionDigital Marketing Institute in NoidaPDF SubmissionDigital Marketing Institute in Noida
PDF SubmissionDigital Marketing Institute in Noida
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
 

types-170309142854.pptx

  • 1. TYPES OF BUILDING CONTRACT • Lump-sum Contract • Cost Plus Fixed Fee Contract • Cost Plus Bid Bid Fee Contract • Guaranteed Maximum Contract • Negotiated Contract • Unit-price Contract • Design Build • Turn Key Contracts
  • 2. Lump-sum Contract • Traditional method of Contract. • The contractor offers to do the whole work for a total stipulated sum of money as shown in drawings and described by specification. • It is more suitable for works which contractor have prior construction experience. • This is considered when tender process will tend to be slower and preparing a tender may be more expensive for the contractor.
  • 3. Lump-sum Contract(Contd.) Advantages • Owner is aware of the cost of the project before the project construction starts. • Project scope and limits are defined prior to the start of construction. • Contractual relation between all parties, owner and Engineer are clearly defined. • Best price for work obtained through competitive process with cost of work established and agreed upon.
  • 4. Lump-sum Contract(Contd.) Disadvantages • The lack of time flexibility in this method may result in delayed project implementation. • Highly skilled Architect or Engineer is needed. • Difficult to implement revisions or change in the work on the later stage of the work.
  • 5. Cost Plus fixed fee Contract •All Cost for the work according to the specification is reimbursed by the owner to the contractor. •Contractor is paid a fixed sum which represents the profit •The variation on the lump-sum fee is percentage fee wherein fees is established by percentage of total cost incurred by the contractor. •Usually it is fixed as a sum.
  • 6. Cost Plus Bid fee Contract •Owner invites proposal from qualified contractor in terms of past experience, performance , etc. •All Cost for the work according to the specification is reimbursed by the owner to the contractor. •The bid fee is calculated on the basis of project scope.
  • 7. Guaranteed Maximum Contract •The contractor agrees to perform work within a price ceiling. This is the maximum guaranteed price. •If the ceiling is exceeded, without change in scope then the excess cost is borne by the contractor. •If the work is accomplished under the ceiling then the owner pays no more than the actual cost and the profit is shared between the contractor and the owner. •This method gives greater flexibility for the owner
  • 8. Negotiated Contract The preselected contractors are invited upon on the basis of • Capability of the past experience in the specific area • Availability of the personnel to accomplish the work in the specified time frame • Bid (Estimate) Price • Proposed method for compensation including amount of fee.
  • 9. Negotiated Contract (Contd.) •The owner is then negotiating with the contract including method of payment for the work, Bid, etc. •On the basis of circumstances it can be competitive or non-competitive.
  • 10. Unit Price Contract •Based on the estimated quantities of the items involved in the work. •The cost per unit item is given by the contractor and the estimated quantities of items are given by the owner. •The total cost of work can only be calculated only measurement is made after the completion of the work because on the basis of work actually done.
  • 11. Unit Price Contract (Contd.) •The contractor is obliged to perform the work actually required in the field at his quoted price only. •If the estimated quantity is exceeds, then there should be increase in unit price , therefore it is difficult to forecast the project cost.
  • 12. Design Build •It is a method to deliver a project in which the design and construction services are contracted by a single entity known as the design–builder or design–build contractor •design–build relies on a single point of responsibility contract and is used to minimize risks for the project owner and to reduce the delivery schedule by overlapping the design phase and construction phase of a project. •Contractor will be responsible for all of the work on the project, regardless of the nature of the fault
  • 13. Turn-key contracts •A type of project that is constructed so that it could be sold to any buyer as a completed product. •This is contrasted with build to order, where the constructor builds an item to the buyer's exact specifications, or when an incomplete product is sold with the assumption that the buyer would complete it.