In December 2015, the UK’s National Audit Office reported that one-third of UK government projects were either unachievable or in-doubt. This would have come as a great surprise to most commentators, in particular that two-thirds of the projects were forecast to be on track! It is not immediately clear from the report on what basis these projects are secure about their on-time delivery. How can a project forecast with confidence that it will deliver on time?
Risk-based Planning and Scheduling, a short course presentation originally prepared for the Bachelor of Science Construction Project Management class, School of Construction, Southern Alberta Institute of Technology, Calgary, Alberta on October 11, 2016.
About the Author/Speaker:
Rufran C. Frago, P. Eng., PMP®, CCP, PMI-RMP®, Author
Senior Planning Specialist, Suncor Energy Inc.
President/Managing Director, RBM&S Inc.
Owner Administrator, E-Touch Up
Wide-range of expertise & specialization in the Manufacturing, Petrochemical, Oleo-chemicals, Oil and Gas, Education & Training Industries for more than 40 years in various roles and capacities. Exposure: Asia, Africa, Middle East and North America.
His expertise includes: Primavera Database Administration, Programs and Project Planning & Scheduling, Qualitative/Quantitative Risk Management, Problem Solving, Project Management, Cost Engineering, Project Control, Construction Management/Coordination, Project Review & Implementation Audit, Estimating, Engineering & Design, Fab/Mod Management, Preventive & Predictive Reliability-Based Maintenance, Operation, Material Selection, Warehousing, EH&S, and Training.
These five types of construction contracts are widely used across the world. Get to about the lump-sum contract, unit-rate contract, cost-plus contract, time & material contract, and target cost contract. All the contract types are explained with their respective example, pros and cons.
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
Check out the 6-time estimation methods for project & activity duration. The approaches are used worldwide and are proven to be effective and powerful.
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
The article aims to explain the types of construction claims and their respective root causes. In the end, the best practices to minimise the claim are explained. A case study on time and cost overrun will detail out what claims arises due to delay.
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
Project management requires a deep understanding of the jargon and terminology for effective implementation of practices. The article presents 20 popular and common terms of project management
Does Better Scheduling Drive Execution Success?Acumen
This white paper outlines the statistics that support the relationship between better schedules and better execution. Based on an ongoing research study conducted by Acumen, this paper is the hard proof of a need for better planning across all industries.
Risk-based Planning and Scheduling, a short course presentation originally prepared for the Bachelor of Science Construction Project Management class, School of Construction, Southern Alberta Institute of Technology, Calgary, Alberta on October 11, 2016.
About the Author/Speaker:
Rufran C. Frago, P. Eng., PMP®, CCP, PMI-RMP®, Author
Senior Planning Specialist, Suncor Energy Inc.
President/Managing Director, RBM&S Inc.
Owner Administrator, E-Touch Up
Wide-range of expertise & specialization in the Manufacturing, Petrochemical, Oleo-chemicals, Oil and Gas, Education & Training Industries for more than 40 years in various roles and capacities. Exposure: Asia, Africa, Middle East and North America.
His expertise includes: Primavera Database Administration, Programs and Project Planning & Scheduling, Qualitative/Quantitative Risk Management, Problem Solving, Project Management, Cost Engineering, Project Control, Construction Management/Coordination, Project Review & Implementation Audit, Estimating, Engineering & Design, Fab/Mod Management, Preventive & Predictive Reliability-Based Maintenance, Operation, Material Selection, Warehousing, EH&S, and Training.
These five types of construction contracts are widely used across the world. Get to about the lump-sum contract, unit-rate contract, cost-plus contract, time & material contract, and target cost contract. All the contract types are explained with their respective example, pros and cons.
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
Check out the 6-time estimation methods for project & activity duration. The approaches are used worldwide and are proven to be effective and powerful.
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
The article aims to explain the types of construction claims and their respective root causes. In the end, the best practices to minimise the claim are explained. A case study on time and cost overrun will detail out what claims arises due to delay.
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
Project management requires a deep understanding of the jargon and terminology for effective implementation of practices. The article presents 20 popular and common terms of project management
Does Better Scheduling Drive Execution Success?Acumen
This white paper outlines the statistics that support the relationship between better schedules and better execution. Based on an ongoing research study conducted by Acumen, this paper is the hard proof of a need for better planning across all industries.
DCMA has enlisted 14-points to assess the project schedule quality. The article explains each of the 14-points in detail and in simple language. Knowledge of these points shall help you to prepare a better and efficient schedule that can be prepared, managed and executed.
The Chunnel Project faced significant cost overruns and delays due to poor cost management throughout its lifecycle. In the inception phase, the initial scope was poorly defined leading to scope creep. In the development phase, lack of proper cost planning and control of scope changes by the Intergovernmental Commission exacerbated costs. In the implementation phase, the use of fixed-price contracts for underground construction caused disputes and claims that increased expenses. Finally, in the closure phase, late modifications in scope delayed completion and reduced returns on investment for stakeholders. Overall, cost overruns ballooned from an initial £4.8 billion estimate to £9.5 billion due to weaknesses in cost planning and control across all project phases.
This document discusses formulas for escalating costs in engineering projects. It defines escalation formulas as mathematical models that estimate how interrelated cost variables change over time based on statistical data and records. The formulas are constituted by terms called monomials that consider the participation or impact of main resources. Each monomial represents a cost component, with coefficients indicating the percentage impact and factors showing the price index growth between the initial date and desired escalation date.
Cost baselines and Cost budget are two terms from Project Cost Management, that could pose a challenge of understanding to many Project Managers.
https://www.mudassiriqbal.net/costbaseline-vs-budget/
For Other PM Concepts, you may visit https://www.mudassiriqbal.net/project-management-terms-and-concepts
Presenting this set of slides with name - Project Schedule PowerPoint Presentation Slides. The stages in this process are Project Schedule,Project Training,Project Plan.
The document discusses the history and concepts of Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT), which are network analysis techniques used for project management. CPM was developed by DuPont in the 1950s for chemical plant projects, while PERT was developed by the US Navy for the Polaris missile program. Both techniques use network diagrams of activities and their dependencies to analyze the critical path and schedule of a project. CPM uses deterministic activity times while PERT uses probabilistic times to account for uncertainty. The techniques help answer questions about project completion dates, schedules, budgets, and how to finish early.
The document discusses the differences between contract management and project management. It provides details on:
1) Project management focuses on managing a project to completion on time and on budget, while contract management focuses on managing agreements between parties to meet objectives.
2) Key differences include project management involving multiple entities working on one project, while contract management involves binding two or more separate entities.
3) Estimation techniques used in project management include effort estimation, cost estimation, and resource estimation to align project constraints like scope, time, cost, quality, resources, and risk.
The document summarizes the key steps a project manager would take to address issues with cost and time estimates for a project to develop a low-cost color laser printer. The project manager would first clarify priorities with senior management using a priority matrix. They would then schedule a meeting to explain the priority matrix and get permission to increase costs if needed. The project manager would also consider outsourcing technology or producing in-house to potentially reduce costs. Next, they would get detailed cost and time estimates from multiple estimators to assess risks. Finally, the project manager would do a break-even analysis and get feedback from the project team on the revised plan before continuing or abandoning the project.
Management of risk affects the success and financial viability of a project. Internal risks, which are generally within the control of a construction organisation, are cost and schedule overrun. External risks include market conditions, government policy and natural disasters.
This article describes the management of internal risks through integrated schedule and cost analysis as these are areas that can be managed effectively by a construction organisation with minimal set up cost.
The types of project referred to in this article can either be design-and-build or build-only projects. Other forms of procurement such as Build-Operate-Transfer (BOT) will attract different risks which are not considered herein.
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
The document discusses estimating costs for construction projects in fragile and transitional contexts using the three-point estimating technique. It explains that the technique uses optimistic, most likely, and pessimistic estimates to define a cost range and improve accuracy. As an example, the document applies the technique to estimate costs for a basic education project in Sudan. It calculates optimistic, most likely, and pessimistic cost scenarios accounting for risks like instability and variables like inflation. The final cost estimate of $157,192 is close to the most likely amount, demonstrating how the simple three-point technique can reliably estimate costs while considering the uncertainties of fragile contexts.
The document discusses capital project lifecycle management in the oil and gas industry. It notes that managing major capital projects is critical given economic conditions and stakeholder demands for return on investment. The best way to manage projects is to take a holistic, stage-gate approach considering the entire lifecycle from planning through decommissioning. Some common pitfalls projects face between concept and commissioning include ineffective cost management, schedule delays, finance and credit risk, lack of urgency, and unclear roles and responsibilities, especially in joint ventures. Managing risks up front by considering the full lifecycle during planning can help projects achieve their goals.
The CPM (Critical Path Method) model is a deterministic approach used for project planning and scheduling. It involves identifying all tasks, determining their duration and sequence, and analyzing which path has no float or slack time between tasks. This critical path determines the minimum time needed to complete the project. The CPM makes assumptions that the critical path will not change, activity times are independent and known, and the project completion time is normally distributed. The key steps of CPM include specifying activities, establishing sequences, building a network diagram, estimating activity times, identifying the critical path, and updating the critical path diagram. The overall goal of CPM is to complete the project in the shortest time possible through techniques like fast tracking and crashing the critical
The CPM (Critical Path Method) model is a deterministic approach used for comparatively risk-free projects that involves developing a network diagram and identifying the critical path. There are four main assumptions of CPM: 1) the critical path does not change, 2) project completion time is normally distributed, 3) activity times are statistically independent, and 4) activity times are deterministic. The key steps of CPM include activity specification, establishing activity sequence, developing a network diagram, estimating activity times, identifying the critical path, and updating the critical path diagram. The major objective of CPM is to complete the project in the shortest time possible through techniques like fast tracking and crashing the critical path.
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
This document summarizes and compares two capital projects, Case A and Case B, in terms of their risk management approaches. Case A took a single point estimate approach which resulted in fixed contingency amounts, while Case B took a range analysis workshop approach to identify and quantify risks. Case B developed cost and schedule ranges and analyzed key risk drivers, allowing them to model outcomes more accurately. Best practice for risk analysis involves taking a risk-driven, integrated cost-schedule approach to understand contingency needs and prioritize top risks.
Delivering programs with less capability than promised, while exceeding the cost and planned durations, distorts decision making, contributes to increasing cost growth to other programs, undermines the Federal government’s credibility with taxpayers and contributes to the public’s negative support for these programs.
Many reasons have been hypothesized and documented for cost and schedule growth. The authors review some of these reasons, and propose that government and contractors use the historical variability of the past programs to establish cost and schedule estimates at the outset and periodically update these estimates with up-to-date risks, to increase the probability of program success. For this to happen, the authors recommend changes to estimating, acquisition and contracting processes.
Cure for cost and schedule growth (submitted)Glen Alleman
This document discusses ways to reduce unanticipated cost and schedule growth on public programs. It recommends that programs establish initial cost and schedule estimates based on the variability seen on historical similar programs, and budget programs at a 70% probability of meeting cost and schedule targets. This would involve developing activity-based estimates adjusted for past program issues, and getting contractor input on meeting targets. The document argues this approach could help control unanticipated growth if estimates are set high enough based on historical data.
Delay Analysis - Correcting for Programme ErrorsDavid Greig
Should a programme containing errors be corrected prior to undertaking delay analysis?
How and when should any corrections be made? Or perhaps, not at all!
These are some of the questions the delay analyst might face when considering a contractor's programme which contains errors.
The document introduces the Time, Quality, Money (TQM) approach to project management, which involves balancing the three competing demands of time, quality, and money. It discusses tools for planning, carrying out, and monitoring projects according to the TQM approach. These include critical path analysis, defining clear scope, regular communication, Gantt charts, budgets, and performance indicators.
Delay Analysis - Correcting for Programme ErrorsDavid Greig
Should a programme containing errors be corrected prior to undertaking delay analysis?
How and when should any corrections be made? Or perhaps, not at all!
These are some of the questions the delay analyst might face when considering a contractor's programme which contains errors.
Project success through excellence in procurement and contract managementCatherine Bendell
This document provides an overview of a guide on project success through excellent contract management. It discusses why procurement and contract management are important for project managers. Modern developments include a greater emphasis on outcomes, benefits and whole life costs. The project lifecycle has expanded to include operation and termination. There is an increasing need for collaboration between organizations. Selection criteria now include organizational culture and capabilities. Contracts aim to align motivations and define how parties will work together. The seven-stage procurement and contract management model is presented, along with things project managers should consistently do well.
This document provides an overview of a presentation on project success through excellent contract management. It discusses why procurement and contract management are important for project managers. It outlines the agenda which will cover modern developments in these areas, a seven stage procurement and contract management model, and things project managers should consistently do well. It also defines procurement and discusses how the definition and understanding of procurement has expanded with developments like considering outcomes, benefits, whole lifecycles, and the need for collaboration in complex projects.
This document discusses cost and schedule overruns that are common in publicly-funded programs. It proposes establishing cost and schedule estimates based on the historical variability of similar past programs, and updating estimates periodically with risks, to increase the probability of on-target program delivery. Specific changes are recommended to how initial estimates are created and agreed upon, including developing activity-based estimates adjusted for issues on past programs. Programs should be budgeted at a 70% probability of meeting cost and schedule targets using this joint confidence level approach. This involves changes to estimating, acquisition, and contracting processes.
DCMA has enlisted 14-points to assess the project schedule quality. The article explains each of the 14-points in detail and in simple language. Knowledge of these points shall help you to prepare a better and efficient schedule that can be prepared, managed and executed.
The Chunnel Project faced significant cost overruns and delays due to poor cost management throughout its lifecycle. In the inception phase, the initial scope was poorly defined leading to scope creep. In the development phase, lack of proper cost planning and control of scope changes by the Intergovernmental Commission exacerbated costs. In the implementation phase, the use of fixed-price contracts for underground construction caused disputes and claims that increased expenses. Finally, in the closure phase, late modifications in scope delayed completion and reduced returns on investment for stakeholders. Overall, cost overruns ballooned from an initial £4.8 billion estimate to £9.5 billion due to weaknesses in cost planning and control across all project phases.
This document discusses formulas for escalating costs in engineering projects. It defines escalation formulas as mathematical models that estimate how interrelated cost variables change over time based on statistical data and records. The formulas are constituted by terms called monomials that consider the participation or impact of main resources. Each monomial represents a cost component, with coefficients indicating the percentage impact and factors showing the price index growth between the initial date and desired escalation date.
Cost baselines and Cost budget are two terms from Project Cost Management, that could pose a challenge of understanding to many Project Managers.
https://www.mudassiriqbal.net/costbaseline-vs-budget/
For Other PM Concepts, you may visit https://www.mudassiriqbal.net/project-management-terms-and-concepts
Presenting this set of slides with name - Project Schedule PowerPoint Presentation Slides. The stages in this process are Project Schedule,Project Training,Project Plan.
The document discusses the history and concepts of Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT), which are network analysis techniques used for project management. CPM was developed by DuPont in the 1950s for chemical plant projects, while PERT was developed by the US Navy for the Polaris missile program. Both techniques use network diagrams of activities and their dependencies to analyze the critical path and schedule of a project. CPM uses deterministic activity times while PERT uses probabilistic times to account for uncertainty. The techniques help answer questions about project completion dates, schedules, budgets, and how to finish early.
The document discusses the differences between contract management and project management. It provides details on:
1) Project management focuses on managing a project to completion on time and on budget, while contract management focuses on managing agreements between parties to meet objectives.
2) Key differences include project management involving multiple entities working on one project, while contract management involves binding two or more separate entities.
3) Estimation techniques used in project management include effort estimation, cost estimation, and resource estimation to align project constraints like scope, time, cost, quality, resources, and risk.
The document summarizes the key steps a project manager would take to address issues with cost and time estimates for a project to develop a low-cost color laser printer. The project manager would first clarify priorities with senior management using a priority matrix. They would then schedule a meeting to explain the priority matrix and get permission to increase costs if needed. The project manager would also consider outsourcing technology or producing in-house to potentially reduce costs. Next, they would get detailed cost and time estimates from multiple estimators to assess risks. Finally, the project manager would do a break-even analysis and get feedback from the project team on the revised plan before continuing or abandoning the project.
Management of risk affects the success and financial viability of a project. Internal risks, which are generally within the control of a construction organisation, are cost and schedule overrun. External risks include market conditions, government policy and natural disasters.
This article describes the management of internal risks through integrated schedule and cost analysis as these are areas that can be managed effectively by a construction organisation with minimal set up cost.
The types of project referred to in this article can either be design-and-build or build-only projects. Other forms of procurement such as Build-Operate-Transfer (BOT) will attract different risks which are not considered herein.
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
The document discusses estimating costs for construction projects in fragile and transitional contexts using the three-point estimating technique. It explains that the technique uses optimistic, most likely, and pessimistic estimates to define a cost range and improve accuracy. As an example, the document applies the technique to estimate costs for a basic education project in Sudan. It calculates optimistic, most likely, and pessimistic cost scenarios accounting for risks like instability and variables like inflation. The final cost estimate of $157,192 is close to the most likely amount, demonstrating how the simple three-point technique can reliably estimate costs while considering the uncertainties of fragile contexts.
The document discusses capital project lifecycle management in the oil and gas industry. It notes that managing major capital projects is critical given economic conditions and stakeholder demands for return on investment. The best way to manage projects is to take a holistic, stage-gate approach considering the entire lifecycle from planning through decommissioning. Some common pitfalls projects face between concept and commissioning include ineffective cost management, schedule delays, finance and credit risk, lack of urgency, and unclear roles and responsibilities, especially in joint ventures. Managing risks up front by considering the full lifecycle during planning can help projects achieve their goals.
The CPM (Critical Path Method) model is a deterministic approach used for project planning and scheduling. It involves identifying all tasks, determining their duration and sequence, and analyzing which path has no float or slack time between tasks. This critical path determines the minimum time needed to complete the project. The CPM makes assumptions that the critical path will not change, activity times are independent and known, and the project completion time is normally distributed. The key steps of CPM include specifying activities, establishing sequences, building a network diagram, estimating activity times, identifying the critical path, and updating the critical path diagram. The overall goal of CPM is to complete the project in the shortest time possible through techniques like fast tracking and crashing the critical
The CPM (Critical Path Method) model is a deterministic approach used for comparatively risk-free projects that involves developing a network diagram and identifying the critical path. There are four main assumptions of CPM: 1) the critical path does not change, 2) project completion time is normally distributed, 3) activity times are statistically independent, and 4) activity times are deterministic. The key steps of CPM include activity specification, establishing activity sequence, developing a network diagram, estimating activity times, identifying the critical path, and updating the critical path diagram. The major objective of CPM is to complete the project in the shortest time possible through techniques like fast tracking and crashing the critical path.
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
This document summarizes and compares two capital projects, Case A and Case B, in terms of their risk management approaches. Case A took a single point estimate approach which resulted in fixed contingency amounts, while Case B took a range analysis workshop approach to identify and quantify risks. Case B developed cost and schedule ranges and analyzed key risk drivers, allowing them to model outcomes more accurately. Best practice for risk analysis involves taking a risk-driven, integrated cost-schedule approach to understand contingency needs and prioritize top risks.
Delivering programs with less capability than promised, while exceeding the cost and planned durations, distorts decision making, contributes to increasing cost growth to other programs, undermines the Federal government’s credibility with taxpayers and contributes to the public’s negative support for these programs.
Many reasons have been hypothesized and documented for cost and schedule growth. The authors review some of these reasons, and propose that government and contractors use the historical variability of the past programs to establish cost and schedule estimates at the outset and periodically update these estimates with up-to-date risks, to increase the probability of program success. For this to happen, the authors recommend changes to estimating, acquisition and contracting processes.
Cure for cost and schedule growth (submitted)Glen Alleman
This document discusses ways to reduce unanticipated cost and schedule growth on public programs. It recommends that programs establish initial cost and schedule estimates based on the variability seen on historical similar programs, and budget programs at a 70% probability of meeting cost and schedule targets. This would involve developing activity-based estimates adjusted for past program issues, and getting contractor input on meeting targets. The document argues this approach could help control unanticipated growth if estimates are set high enough based on historical data.
Delay Analysis - Correcting for Programme ErrorsDavid Greig
Should a programme containing errors be corrected prior to undertaking delay analysis?
How and when should any corrections be made? Or perhaps, not at all!
These are some of the questions the delay analyst might face when considering a contractor's programme which contains errors.
The document introduces the Time, Quality, Money (TQM) approach to project management, which involves balancing the three competing demands of time, quality, and money. It discusses tools for planning, carrying out, and monitoring projects according to the TQM approach. These include critical path analysis, defining clear scope, regular communication, Gantt charts, budgets, and performance indicators.
Delay Analysis - Correcting for Programme ErrorsDavid Greig
Should a programme containing errors be corrected prior to undertaking delay analysis?
How and when should any corrections be made? Or perhaps, not at all!
These are some of the questions the delay analyst might face when considering a contractor's programme which contains errors.
Project success through excellence in procurement and contract managementCatherine Bendell
This document provides an overview of a guide on project success through excellent contract management. It discusses why procurement and contract management are important for project managers. Modern developments include a greater emphasis on outcomes, benefits and whole life costs. The project lifecycle has expanded to include operation and termination. There is an increasing need for collaboration between organizations. Selection criteria now include organizational culture and capabilities. Contracts aim to align motivations and define how parties will work together. The seven-stage procurement and contract management model is presented, along with things project managers should consistently do well.
This document provides an overview of a presentation on project success through excellent contract management. It discusses why procurement and contract management are important for project managers. It outlines the agenda which will cover modern developments in these areas, a seven stage procurement and contract management model, and things project managers should consistently do well. It also defines procurement and discusses how the definition and understanding of procurement has expanded with developments like considering outcomes, benefits, whole lifecycles, and the need for collaboration in complex projects.
This document discusses cost and schedule overruns that are common in publicly-funded programs. It proposes establishing cost and schedule estimates based on the historical variability of similar past programs, and updating estimates periodically with risks, to increase the probability of on-target program delivery. Specific changes are recommended to how initial estimates are created and agreed upon, including developing activity-based estimates adjusted for issues on past programs. Programs should be budgeted at a 70% probability of meeting cost and schedule targets using this joint confidence level approach. This involves changes to estimating, acquisition, and contracting processes.
The document discusses project monitoring and control. It describes the plan-monitor-control cycle as an ongoing process of planning work, checking progress, comparing to plans, taking corrective actions if needed, and re-planning. Key items to monitor and control are time, cost, and scope. An effective monitoring system requires designing mechanisms to gather and report data on project performance. Routine reports keep stakeholders informed, while exception reports document changes or problems. Earned value analysis compares actual costs to planned costs and progress to evaluate performance.
How To Develop A Project Management PlanOrangescrum
For project managers, a successful outcome is always preceded by a well-prepared project management plan. A lot of effort is put into planning which helps you prepare a better Project Management Plan.
This paper explores using a theoretical S-curve equation to forecast total project duration based on past physical progress data. It presents three case studies applying the method: 1) A petrochemical plant where actual progress of 37.6% in 23 months was used to fit a curve predicting completion in 46 months, close to later reported progress. 2) An oil & gas unit where early and later data fits predicted completion accurately. 3) A civil works project where initial and additional data again closely matched the predicted curve. The method provides a simple tool to forecast duration when detailed schedule data is unavailable.
This document discusses techniques for evaluating projects under uncertainty, including sensitivity analysis, switching values, and probability distributions of outcomes. Sensitivity analysis systematically tests how changes to estimates impact a project's worth. Probability distributions collapse uncertain outcomes into point estimates but lack variance data. Direct or simulated calculations of probability distributions provide a full picture of outcome likelihoods when events are independent.
The document discusses Project Evaluation Review Technique (PERT), a project management tool used to analyze tasks, time required, and critical paths. It describes various project management methodologies like PRINCE2, Agile, and Critical Path Method (CPM) that are suited for different types of projects. Finally, it discusses setting up an organizational structure and quality management process for a project.
Discover timeless style with the 2022 Vintage Roman Numerals Men's Ring. Crafted from premium stainless steel, this 6mm wide ring embodies elegance and durability. Perfect as a gift, it seamlessly blends classic Roman numeral detailing with modern sophistication, making it an ideal accessory for any occasion.
https://rb.gy/usj1a2
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfthesiliconleaders
In the recent edition, The 10 Most Influential Leaders Guiding Corporate Evolution, 2024, The Silicon Leaders magazine gladly features Dejan Štancer, President of the Global Chamber of Business Leaders (GCBL), along with other leaders.
Understanding User Needs and Satisfying ThemAggregage
https://www.productmanagementtoday.com/frs/26903918/understanding-user-needs-and-satisfying-them
We know we want to create products which our customers find to be valuable. Whether we label it as customer-centric or product-led depends on how long we've been doing product management. There are three challenges we face when doing this. The obvious challenge is figuring out what our users need; the non-obvious challenges are in creating a shared understanding of those needs and in sensing if what we're doing is meeting those needs.
In this webinar, we won't focus on the research methods for discovering user-needs. We will focus on synthesis of the needs we discover, communication and alignment tools, and how we operationalize addressing those needs.
Industry expert Scott Sehlhorst will:
• Introduce a taxonomy for user goals with real world examples
• Present the Onion Diagram, a tool for contextualizing task-level goals
• Illustrate how customer journey maps capture activity-level and task-level goals
• Demonstrate the best approach to selection and prioritization of user-goals to address
• Highlight the crucial benchmarks, observable changes, in ensuring fulfillment of customer needs
Structural Design Process: Step-by-Step Guide for BuildingsChandresh Chudasama
The structural design process is explained: Follow our step-by-step guide to understand building design intricacies and ensure structural integrity. Learn how to build wonderful buildings with the help of our detailed information. Learn how to create structures with durability and reliability and also gain insights on ways of managing structures.
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesHolger Mueller
Holger Mueller of Constellation Research shares his key takeaways from SAP's Sapphire confernece, held in Orlando, June 3rd till 5th 2024, in the Orange Convention Center.
Building Your Employer Brand with Social MediaLuanWise
Presented at The Global HR Summit, 6th June 2024
In this keynote, Luan Wise will provide invaluable insights to elevate your employer brand on social media platforms including LinkedIn, Facebook, Instagram, X (formerly Twitter) and TikTok. You'll learn how compelling content can authentically showcase your company culture, values, and employee experiences to support your talent acquisition and retention objectives. Additionally, you'll understand the power of employee advocacy to amplify reach and engagement – helping to position your organization as an employer of choice in today's competitive talent landscape.
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
SATTA MATKA SATTA FAST RESULT KALYAN TOP MATKA RESULT KALYAN SATTA MATKA FAST RESULT MILAN RATAN RAJDHANI MAIN BAZAR MATKA FAST TIPS RESULT MATKA CHART JODI CHART PANEL CHART FREE FIX GAME SATTAMATKA ! MATKA MOBI SATTA 143 spboss.in TOP NO1 RESULT FULL RATE MATKA ONLINE GAME PLAY BY APP SPBOSS
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...my Pandit
Explore the fascinating world of the Gemini Zodiac Sign. Discover the unique personality traits, key dates, and horoscope insights of Gemini individuals. Learn how their sociable, communicative nature and boundless curiosity make them the dynamic explorers of the zodiac. Dive into the duality of the Gemini sign and understand their intellectual and adventurous spirit.
B2B payments are rapidly changing. Find out the 5 key questions you need to be asking yourself to be sure you are mastering B2B payments today. Learn more at www.BlueSnap.com.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.AnnySerafinaLove
This letter, written by Kellen Harkins, Course Director at Full Sail University, commends Anny Love's exemplary performance in the Video Sharing Platforms class. It highlights her dedication, willingness to challenge herself, and exceptional skills in production, editing, and marketing across various video platforms like YouTube, TikTok, and Instagram.
Industrial Tech SW: Category Renewal and CreationChristian Dahlen
Every industrial revolution has created a new set of categories and a new set of players.
Multiple new technologies have emerged, but Samsara and C3.ai are only two companies which have gone public so far.
Manufacturing startups constitute the largest pipeline share of unicorns and IPO candidates in the SF Bay Area, and software startups dominate in Germany.
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
The Programme Certainty Paradox
1. The Programme Certainty Paradox
Page 1 of 4August 2016
Introduction
In December 20151
, the UK’s National
Audit Office reported that one-third
of UK government projects were
either unachievable or in-doubt.
This would have come as a great
surprise to most commentators,
in particular that two-thirds of the
projects were forecast to be on track!
It is not immediately clear from the
report on what basis these projects
are secure about their on-time
delivery. How can a project forecast
with confidence that it will deliver on
time?
Need for Certainty
Economically the world is smaller,
as regional and local economies
become ever increasingly dependent
on cross-border trade. International
competition that flows from this
globalised economy has significantly
affected the construction industry,
introducing further challenges
that affect both employers and
contractors.
Tocompeteinternationally,employers
need to realise their projects’ benefits
in shorter timescales. At the same
time, a project’s viability is ever more
dependent on world commodity
prices and the globalised movement
of capital.
Contractors are equally affected;
reduced project timescales and the
increased influence of international
contractors in local markets have
intensified pressure on dwindling
profit margins2
.
Due to globalisation, the boundary
between a project’s success and
failure has diminished, which makes
the cost of project overruns even
more expensive. Consequently,
employers and contractors desire
certainty; in particular, to know that
their project will be delivered on time
and to budget.
Paradox
Paradoxically, the path to certainty
is found in uncertainty. This is
particularly true for the timely
completion of projects, where
achievement is premised on an
assumed future performance.
Basis of Project Time
Prior to any examination on how
to achieve certainty3
that a project
will complete on-time; it is prudent
to reflect on the manner in which
project time is evaluated, managed
and monitored. In particular, the
programmes the parties rely on to
make time-related decisions.
Most standard conditions of contract
require the contractor to prepare a
contract programme. This should
demonstrate how it will perform the
works in order to complete by the
contracted completion date.
The contract programme consists of
activities with set durations that are
logically linked to form a network.
As-long-as the total duration of the
longest path through this network
is less than or equal to the time
required for the project; the parties
are usually satisfied the programme
will deliver the project on time.
That viewpoint is overly simplistic
given the programme’s proper
context: it is a forecast, based on
an assumption that these future
activities will be performed in the
sequence and times planned. In the
same way budgets are projections of
future financial expenditure, contract
programmes are estimates of future
performance.
Prospective programmes (including
contract programmes) are time
models on which the project’s
decision-making process is founded.
These include (but are not limited to):
• Cost and budget forecasting;
• Resource management;
• Interface management with
subcontractors and other
parties;
• Change management;
• Risk management;
• Site and logistics management;
and
• Procurement considerations,
including material delivery to
site.
As the programme is a model
based on future events, its value is
directly proportional to its quality
— the results of any programme
interrogation, necessary for a
decision-making process, will only be
as robust as the model used. Rubbish
in will result in rubbish out!
Programme Quality
It is clearly imperative that the
programme model should be as
reliable as practicable, but how is this
achieved?
Assistance is provided in the form
of Schedule Metrics — a series
of objective benchmarks, against
which a programme’s quality can be
measured.
1
United Kingdom National Audit Office, ‘Delivering major projects in government: a briefing for the Committee of Public Accounts’, January
2016.
2
Construction News’ Annual CN100 survey, reported in September 2015.
3
Insofar as it is practicable to achieve.
2. These benchmarks promote quality
through a series of criteria that the
programme is expected to achieve or
better. These include:
• Minimal, if any, use of hard
constraints, such as ‘finish on’ or
‘start on’ dates;
• Preference for Finish-to-Start
logic relationships over other
available logic types;
• Restriction on activities’
durations, for example to less
than one reporting cycle;
• Limited reliance on artificial
constraints such as lags between
activities;
• Use of appropriate calendars for
activities;
• Prohibition on the use of negative
lags; and
• Limited activities with high float
durations.
Schedule Metrics’ benchmarks are
particularly concerned with the
programme’s logic structure and
the development of the longest-
path. This makes them an invaluable
tool when considering whether a
programme is suitable for risk or
delay analysis purposes.
In terms of prospective programmes,
Schedule Metrics should be
considered as best practice guidelines
to assist planners build and maintain
the project’s programme.
Clearly, Schedule Metrics are an
invaluable tool that should form part
of every programme’s development,
although, they have limitations.
Significantly, they cannot talk to the
planned intentions themselves: they
cannot assess whether the plan is, in
fact, buildable.
Generally, it is for the contractor to
determine the sequence in which
it proposes to perform the works.
These intentions should be clearly
represented in the programme. Too
often the plan is put together in
isolation, without input from those
who will deliver it. It becomes merely
a reporting tool, devoid of value.
For the programme to accurately
model the planned intentions, it must
be prepared collaboratively, with buy-
in from the project’s site team.
A Tool to Manage Uncertainty
A collaboratively built and
benchmarked programme will be
more robust. Nevertheless, this
in itself does not provide certainty
that the contracted completion date
will be achieved, as shown in the
programme.
Preparation of a contract or
prospective programme may,
therefore, seem futile. That is not
the case. Instead, these forward
looking programmes need to be given
a more appropriate context. Rather
than seeking to attain certainty, they
should be considered as tools to
manage uncertainty.
Moreover, a robust programme
gives confidence that it is a suitable
model to assess uncertainty and
give authoritative results. This
is important because, as stated
earlier, the path to certainty lies in
understanding uncertainty.
What is Uncertainty?
It is relevant at this juncture to set-
out what is meant by uncertainty.
Uncertainty in the programme sense
is not impossibility or improbability
— it is not unbound and infinite.
Rather, it should be considered as
a range within which uncontrolled
effects may occur. The more limited
the number of potential results that
can be observed, the greater the
perceived level of certainty.
Historic data can be used to set these
boundaries with a satisfactory degree
of confidence. The available results
reduce as the project progresses,
such that certainty is greater at the
end of the works than the beginning.
Duration Uncertainty
Inthesearchforprogrammecertainty,
the first uncertainty to consider is
‘Duration Uncertainty’.
A prospective programme suffers
a significant flaw: it assumes
the duration of a future event is
determinable. On the contrary, it
cannot be stated with any certainty
that a future activity will take the
duration allocated. If the duration
of each activity within the network
cannot be determined; little
confidence can be derived that the
contracted completion date will be
achieved.
It may be impossible to forecast an
activity’s exact duration; however,
historic data can identify the
maximum and minimum time it has
previously taken. From this factual
data, a statistical likelihood for each
duration can be calculated. This can
then be extrapolated to derive the
most likely duration.
Thereby, an activity’s duration is
better expressed as a distribution
between three ranges: the minimum,
most likely and maximum duration
(see Figures 1 and 2).
Page 2 of 4August 2016
The Programme Certainty Paradox
Figure 1 – Historic data can be graphically presented to identify the minimum, most
likely and maximum durations similar activities have historically taken.
3. Page 3 of 4August 2016
The Programme Certainty Paradox
The uncertainty of an activity’s
duration now has boundaries.
Given that each activity’s duration
can be expressed as a range, it
is necessary to assess how these
variable durations may combine to
affect the contracted completion
when they are applied across a
programme (see Figure 3).
Statistical analysis tools, such as a
Monte Carlo Simulation, use over
a thousand ‘what-if’ scenarios to
determine the probabilistic value of
an outcome. This principle can be
employed to assess a programme’s
likely finish date and compare it
against the contracted completion
obligations.
Each ‘what-if’ scenario uses a
duration from the activities’ range
and reviews how they combine to
affect the completion date. When
this is repeated over a thousand
times, it becomes possible to give a
confidence rating for each potential
completion date.
From this assessment, the parties can
assess whether they are comfortable
that the contracted completion date
is likely to be achieved.
However, that is not the end of the
story.
External Factors
The previous steps discussed concern
uncertainty inherent within the
programme. However, there are
external factors that may affect the
project’s timings (both positively as-
well-as negatively) that are not within
the parties’ full control. These risks
andopportunitiesshouldbemanaged
by the parties through a project-wide
risk management strategy.
The core element to this strategy
is to understand the effect various
risks and opportunities have on the
projects’ timings – both before and
after a risk or opportunity is treated.
Arguably the most reliable method
to assess these impacts is to run
a Quantitative Schedule Risk
Analysis (QSRA). This method finds
particular favour in the Oil and
Gas industry, where it has been
successfully used for many years.
A QSRA requires the parties to
collect quantitative data, for each
risk or opportunity. Specifically, a
probabilistic likelihood that it will
occur and, in that event, the effect it
may have in terms of both time and
cost.
Previous projects and published
benchmark data are good sources for
this quantitative information.
Nevertheless, as the QSRA is a
modelled form of analysis, particular
care should be taken to validate this
data prior to incorporation into the
assessment.
Once this quantitative data has been
verified;theriskoropportunitycanbe
attached to the effected programme
activity(ies). Thereafter, statistical
analysis tools can model, amongst
other things, their likely effect on the
contracted completion date.
In assessing the effect on the
completion date; the QSRA provides
two key results (see Figure 4):
• The probabilistic likelihood
that the contracted time for
completion will be achieved; and
• A probabilistic value for each of
the risk determined completion
dates.
In addition, a QSRA can identify the
programme activities that are most
likely to appear on the programme’s
longest path (see Figure 5).
This is particularly valuable as it
allows the project’s management
to focus on those activities that are
statistically most likely to influence
on-time completion.
Benefits for Employers
For an employer the benefits from
programme certainty go beyond
merely knowing when their project
may be realised.
Early risk modelling, especially as
part of the feasibility study, can
identify risks to be transferred to the
contractor and those that must be
managed by the employer. This can
be used to inform an appropriate
contract strategy to best treat these
threats.
Schedule risk techniques allow
the employer to interrogate the
contractor’s tender and contract
programmes. In-so-doing, not only
will it satisfy itself that the contractor
can deliver as promised; it can
use this information to build more
robust cash-flow forecasts and risk
contingency allocation.
Figure 3 – The programme is a network of activities, each with
a range of possible durations.
Figure 2 – The range of an Activity’s
duration should be considered as a
variable, derived from the historic data
(see Figure 1).
4. During the works the employer
should, collaborate with the
contractor to execute a project risk
management strategy with regular
schedule risk up-dates. This on-
going effort promotes early risk
identification and more effective risk
treatment. Resultantly, the project
is significantly more likely to be
delivered on-time and to budget.
For employers, programme certainty
may not be limited to the likely
completion date — especially
for projects made-up by multiple
contract packages. In that case, it is
equally important to have the same
confidence level for the interface
points between contractors. This
sameconceptapplies when managing
multiple interrelated projects as part
of a portfolio.
Benefits for Contractors
As noted earlier, the programme is
integral to the contractor’s decision-
making processes and is a crucial tool
for the management of the works.
With ever tighter project timescales,
theabilitytomakeaccurateandtimely
decisions has become imperative.
This decision-making is significantly
enhanced by schedule risk analysis,
as they are founded on and tested
against more robust information. As
a result, the contractor can manage
the works by exception — that is,
focusing efforts where they will be
most effective. For example, through
schedule risk analysis the contractor
can better identify those activities
that are probabilistically most likely
to be on the longest path and most
sensitive to delay. Management and
resource efforts can be concentrated
on these activities to significantly
reduce the likelihood of delay and
the potential imposition of liquidated
damages.
An on-going risk management
strategy allows the contractor to
identify risks and opportunities that
are most likely to affect these longest
path activities. In-so-doing, efforts
can be more effectively employed to
minimise the effects of these risks,
whilst maximising opportunities.
Like the employer, the contractor
is normally required to manage the
interface with various subcontractors.
To effectively manage this, the
contractor must be certain that the
interface dates can be met and, in the
event that they cannot, undertake
appropriate mitigation measures.
Enhanced programme certainty
provides contractors with an earlier
warning that these interface dates
are at risk, allowing for earlier and
potentially more effective and less
expensive intervention.
August 2016
The Programme Certainty Paradox
Page 4 of 4
Figure 5 – The analysis registers the percentage of times an activity appears on the
longest path across all the ‘What-if?’ scenarios.
Figure 4 – The analysis registers the completion date observed in each ‘What-if?’
scenario. These can be graphically represented and probabilistic values derived. In
this example, the contracted completion date was 11 December 2015, which was only
achieved 15% of the time. Whereas, there is an 80% chance that the project will
complete by 17 December 2015.
5. The Programme Certainty Paradox
Schedule risk techniques also assist
the contractor to overcome project
delay. Events and their affects are
identified earlier so that they can be
treated more effectively, often with
reduced cost impacts. Furthermore,
clear identification of the probabilistic
longest path allows for more effective
recovery measures using ‘programme
crashing’ (or similar) techniques.
Time-Cost Integration
Time and money are not necessarily
linked. However, the programme can
facilitate greater cost certainty.
An activity represents work to be
done and, therefore, has a cost. This
may include (but is not limited to) the
cost for labour, plant and material
necessary to perform the activity.
A cash-flow forecast can be derived
from attaching these costs to their
relevant programme activities. The
resultant model expresses how cost
will be incurred over the project’s
duration.
Like the programme, this cash-flow
is dynamic and influenced by risks
and opportunities. This can be in the
form of additional costs (or savings)
that result from the risk event itself
or more simply the shifting of the
expenditure profile to mirror the
event’s effect on the programme.
The cost associated with risk and
opportunity can be further assessed
throughaQCRAprocess. Theresultant
probabilistic Cost-to-Complete (‘CTC’)
considers:
• The probabilistic cost effect of
identified risks and opportunities;
• A cash-flow forecast, adjusted to
account for an activity’s duration
uncertainty;
• Themostlikelyprojectcompletion
date and, therefore, its total
duration; and
• The project’s cost sensitivity in
response to change.
Conclusion
Managing the project’s programme
and subsequent up-dates is pivotal
to on-time delivery. However,
prospective programmes model a
single outcome, based on a series
of variable future events (such as
an activity’s actual duration). They
cannot give certainty that the project
will complete on or before the
contracted completion date.
Various techniques narrow this
uncertainty to a range of outcomes.
Therefore, the project’s management
can focus its efforts and decision-
making on the tasks that will achieve
the best outcome, directly benefiting
the project and its on-time delivery.
Otherwise, prospective programmes
remain antithetical Cassandran
prophecies: people blindly believe
their foresight, except those who
prepared them.
However, with minimal investment
the programme can become a
powerful tool to manage the
uncertainty that can prevent the
project’s achievement. As a result,
the project is significantly more
likely to be achieved on-time and to
budget. n
This article is written by Lee Baker,
Director, Hill International, Inc.
Lee is responsible for the Forensic
Delay Group in the Asia region. Lee
is a delay analyst with over 12 years’
industry experience, who specialises in
time-related matters and programme
risk management. He has been
appointed to prepare expert reports
and regularly advises clients on
dispute avoidance and resolution. Lee
has extensive international experience
of high value mega-projects, across
a wide-range of industry sectors.
These include Power Generation,
Aviation, Rail, High-rise buildings
and Prestige Retail and Commercial
developments. Lee prepares and
presents courses for the RICS and his
recent speaking engagements include:
FIDIC Asia Pacific Conference, Annual
Construction Risk Management
Conference, PMI (Singapore Branch)
Symposium and the YSIAC Advocacy
Roadshow.
Disclaimer: This article does not constitute
advice, legal or otherwise, and is provided only
as general commentary. Appropriate professional
advice should always be obtained before taking or
refraining from taking any action in relation to such
information and/or the application of applicable
law. This article and the materials contained in it are
provided on the basis that all liability for any loss or
damage, whether direct or indirect, arising out of
or in connection with any use or reliance upon this
article is excluded to the fullest extent permitted by
law.
Page 4 of 4August 2016
Hill International, with over 4,600
professionals in 100 offices worldwide,
provides programme management,
project management, construction
management, construction claims and
other consulting services primarily
to the buildings, transportation,
environmental, energy and industrial
markets. As a pioneer of the
construction claims industry, we have
a thorough understanding of what can
go wrong on a construction project or
programme as we have helped avoid
or resolve problems in almost every
market sector for nearly four decades.
Our approach to project management
is to minimise risk from the earliest
stages of a project and to provide our
clients with independent and objective
guidance from concept through
completion.
To date, Hill Construction Consultancy
Group has participated in over 50,000
disputes valued in excess of US$100
billion. Our Project Management Group
has participated in over 10,000 project
assignments with a total construction
value of over US$500 billion.
Published by :
Hill Construction Consultancy Pte Ltd.
331 North Bridge Road . #20-03 Odeon
Towers Singapore 188720.
T: +65 6338 2455 | F: +65 6339 8568
E: advicesg@hillintl.com
W: www.hillintl.com