Firesmith’s Testing Pitfalls Checklist 1 November 2014 1 
Common System and Software Testing Pitfalls Checklist 
The following checklist is based on the book Common System and Software Testing Pitfalls by Donald Firesmith. It has been updated with additional testing pitfalls that have been identified since the book’s manuscript was frozen for publication. 
A testing pitfall is defined as a: 
• A human mistake that unnecessarily and unexpectedly causes testing to be: 
– Less effective at uncovering defects 
– Less efficient in terms of time and effort expended 
– More frustrating to perform 
• A bad decision, an incorrect mindset, a wrong action, or failure to act 
• A failure to adequately: 
– Meet a testing challenge 
– Address a testing problem 
• A way to screw up testing 
This checklist is intended for use when: 
• Producing test strategies/plans and related documentations 
• Evaluating contractor proposals 
• Evaluating test strategies/plans and related documentation (quality control) 
• Evaluating as-performed test process (quality assurance) 
• Identifying test-related risks and their mitigation approaches
Firesmith’s Testing Pitfalls Checklist 1 November 2014 2 
1 General Testing Pitfalls 
The following pitfall categories are general and potentially apply to all types of testing: 
1. Test Planning and Scheduling 
2. Stakeholder Involvement and Commitment 
3. Management 
4. Staffing 
5. Process 
6. Pitfall-Related Pitfalls 
7. Test Tools and Environments 
8. Automated Testing 
9. Communication 
10. Testing-as-a-Service (TaaS) 
11. Requirements 
1.1 Test Planning and Scheduling 
Testing Pitfalls 
Observations and Notes 
No Separate Test Planning Documentation (GEN-TPS-1) 
There is no separate testing-specific planning documentation, only incomplete, high-level overviews of testing in the general planning documents. 
 Symptoms  Consequences  Causes  Recommendations 
Incomplete Test Planning (GEN-TPS-2) 
Test planning and its associated documentation are not sufficiently complete for the current point in the system development cycle. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 3 
Test Plans Ignored (GEN-TPS-3) 
The test planning documentation is ignored (that is, it has become “shelfware”) once developed and delivered. 
 Symptoms  Consequences  Causes  Recommendations 
Test-Case Documents as Test Plans (GEN-TPS-4) 
Test-case documents that document specific test cases are mislabeled as test plans. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Schedule (GEN-TPS-5) 
The testing schedule is inadequate to complete proper testing. 
 Symptoms  Consequences  Causes  Recommendations 
Testing at the End (GEN-TPS-6) 
All testing is performed late in the development cycle; there is little or no testing of executable models or unit or integration testing planned or performed during the early and middle stages of the development cycle. 
 Symptoms  Consequences  Causes  Recommendations 
Independent Test Schedule (GEN-TPS-7) 
The test schedule is developed independently of the project master schedule and the schedules of the other development activities. 
 Symptoms  Consequences  Causes  Recommendations 
1.2 Stakeholder Involvement and Commitment 
Testing Pitfalls 
Observations and Notes 
Wrong Testing Mindset (GEN-SIC-1) 
Some testers and testing stakeholders have one or more incorrect 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 4 
beliefs concerning testing. 
Unrealistic Testing Expectations (GEN-SIC-2) 
Testing stakeholders (especially customer representatives and managers) have various unrealistic expectations with regard to testing. 
 Symptoms  Consequences  Causes  Recommendations 
Lack of Stakeholder Commitment to Testing (GEN-SIC-3) 
Stakeholder commitment to the testing effort is inadequate; sufficient resources (for example, people, time in the schedule, tools, or funding) are not allocated the testing effort. 
 Symptoms  Consequences  Causes  Recommendations 
1.3 Management 
Testing Pitfalls 
Observations and Notes 
Inadequate Test Resources (GEN-MGMT-1) 
Management allocates inadequate resources (for example, budget, schedule, staffing, and facilities) to the testing effort. 
 Symptoms  Consequences  Causes  Recommendations 
Inappropriate External Pressures (GEN-MGMT-2) 
Managers and others in positions of authority subject testers to inappropriate external pressures. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test-Related Risk Management (GEN-MGMT-3) 
There are too few test-related risks identified in the project’s official risk repository, and those that are identified have inappropriately low probabilities, low harm severities, and low priorities. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 5 
Inadequate Test Metrics (GEN-MGMT-4) 
Too few test metrics are produced, analyzed, reported, or acted upon, and some of the test metrics that are produced are inappropriate or not very useful. 
 Symptoms  Consequences  Causes  Recommendations 
Inconvenient Test Results Ignored (GEN-MGMT-5) 
Management ignores or treats lightly inconvenient negative test results (especially those with negative ramifications for the schedule, budget, or system quality). 
 Symptoms  Consequences  Causes  Recommendations 
Test Lessons Learned Ignored (GEN-MGMT-6) 
Lessons learned from testing on previous projects are ignored and not placed into practice on the current project. 
 Symptoms  Consequences  Causes  Recommendations 
1.4 Staffing 
Testing Pitfalls 
Observations and Notes 
Lack of Independence (GEN-STF-1) 
The test organization or project test team lack adequate administrative, financial, and technical independence to enable them to withstand inappropriate pressure from the development management to cut corners. 
 Symptoms  Consequences  Causes  Recommendations 
Unclear Testing Responsibilities (GEN-STF-2) 
The testing responsibilities are unclear and do not adequately address which organizations, teams, and people are going to be responsible for and perform the different types of testing. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 6 
Developers Responsible for All Testing (GEN-STF-3) 
Developers are responsible for all of the developmental testing that occurs during system or software development. 
 Symptoms  Consequences  Causes  Recommendations 
Testers Responsible for All Testing (GEN-STF-4) 
Testers are responsible for all of the developmental testing that occurs during system or software development. 
 Symptoms  Consequences  Causes  Recommendations 
Testers Responsible for Quality (GEN-STF-5) 
Testers are (solely) responsible for the quality of the system or software under test. 
 Symptoms  Consequences  Causes  Recommendations 
Users Responsible for Testing (GEN-STF-6) 
The users are responsible for most of the testing, which occurs after the system(s) are operational. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Testing Expertise (GEN-STF-7) 
Some testers, developers, or other testing stakeholders have inadequate testing-related understanding, expertise, experience, or training. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Domain Expertise (GEN-STF-8) 
Testers do not have adequate training, experience, and expertise in the system’s application domain. 
 Symptoms  Consequences  Causes  Recommendations 
Adversarial Relationship (GEN-STF-9) 
A counterproductive adversarial relationship exists between the testers and either management, the developers, or both. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 7 
1.5 Process 
Testing Pitfalls 
Observations and Notes 
No Planned Testing Process (GEN-PRO-1) 
There is no as-planned testing process and all testing (if any) is both ad hoc and completely up to the whims of the individual developers and testers. 
 Symptoms  Consequences  Causes  Recommendations 
Essentially No Testing (GEN-PRO-2) 
Very little if any developmental testing is being performed. 
 Symptoms  Consequences  Causes  Recommendations 
Incomplete Testing (GEN-PRO-3) 
The testers or developers fail to adequately test certain testable behaviors, characteristics, or components of the system or software under test. 
 Symptoms  Consequences  Causes  Recommendations 
Test Process Ignored (GEN-PRO-4) 
The testers, developers, or managers ignore the official documented as-planned test process. 
 Symptoms  Consequences  Causes  Recommendations 
One-Size-Fits-All Testing (GEN-PRO-5) 
All testing is performed the same way, to the same level of rigor, regardless of its criticality. 
 Symptoms  Consequences  Causes  Recommendations 
Sunny Day Testing Only )GEN-PRO-6) 
Testing is largely or totally restricted to verifying that the system does what it should, but does not verify that the system does not do 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 8 
what it should not do. 
Testing and Engineering Process Not Integrated (GEN-PRO-7) 
The testing process is not adequately integrated into the overall system engineering process, but is rather treated as a separate specialty engineering activity with only limited interfaces with the primary engineering activities. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Prioritization (GEN-PRO-8) 
Testing is not adequately prioritized (for example, all types of testing have the same priority). 
 Symptoms  Consequences  Causes  Recommendations 
Test-Type Confusion (GEN-PRO-9) 
Test cases from one type of testing are redundantly repeated as part of another type of testing, even though the testing types have quite different purposes and scopes. 
 Symptoms  Consequences  Causes  Recommendations 
Functionality Testing Overemphasized (GEN-PRO-10) 
There is an overemphasis on testing functionality as opposed to testing quality, data, and interface requirements and testing architectural, design, and implementation constraints. 
 Symptoms  Consequences  Causes  Recommendations 
Black-Box System Testing Overemphasized (GEN-PRO-11) 
There is an overemphasis on black-box system testing for requirements conformance, and there is very little white-box unit and integration testing for the architecture, design, and implementation verification. 
 Symptoms  Consequences  Causes  Recommendations 
Black-Box System Testing Underemphasized (GEN-PRO-12) 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 9 
There is an overemphasis on white-box unit and integration testing, and very little time is spent on black-box system testing to verify conformance to the requirements. 
Test Preconditions Ignored (GEN-PRO-13) 
Test cases do not address preconditions such as the system’s internal mode and states as well as the state(s) of the system’s external environment. 
 Symptoms  Consequences  Causes  Recommendations 
Too Immature for Testing (GEN-PRO-14) 
Products are delivered for testing when they are immature and not ready to be tested. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Data (GEN-PRO-15) 
The test data (including individual test data and sets of test data) lack adequate fidelity to operational data, is incomplete, or is invalid. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Evaluations of Test Assets (GEN-PRO-16) 
The quality of the test assets is not adequately evaluated prior to using them. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Maintenance of Test Assets (GEN-PRO-17) 
Test assets are not properly maintained (that is, adequately updated and iterated) as defects are found and the object under test (OUT) is changed. 
 Symptoms  Consequences  Causes  Recommendations 
Testing as a Phase (GEN-PRO-18) 
Testing is treated as a phase that takes place late in a sequential (also known as waterfall) development cycle instead of as an 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 10 
ongoing activity that takes place continuously in an iterative, incremental, and concurrent (an evolutionary, or agile) development cycle. 
Testers Not Involved Early (GEN-PRO-19) 
Testers are not involved at the beginning of the project, but rather only once an implementation exists to test. 
 Symptoms  Consequences  Causes  Recommendations 
Developmental Testing During Production (GEN-PRO-20) 
Significant system testing is postponed until the system is already in production when fixing defects is much more difficult and expensive. 
 Symptoms  Consequences  Causes  Recommendations 
No Operational Testing (GEN-PRO-21) 
Representative users are not performing any operational testing of the “completed” system under actual operational conditions. 
 Symptoms  Consequences  Causes  Recommendations 
Test Oracles Ignore Nondeterministic Behavior (GEN-PRO-22) 
Testers do not have any criteria for determining when a test has passed when non-deterministic behavior results in intermittent failures and faults. 
 Symptoms  Consequences  Causes  Recommendations 
Testing in Quality (GEN-PRO-23) 
Testing stakeholders rely on testing quality into the system/software under test rather than building quality in from the beginning via all engineering and management activities. 
 Symptoms  Consequences  Causes  Recommendations 
Developers Ignore Testability (GEN-PRO-24) 
The system or software under test is unnecessarily difficult to test because the developers did not consider testing when designing and 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 11 
implementing the system or software. 
Testing the BackBlob (GEN-PRO-25) 
Testers do not adequately deal with their increasing workload due to an ever increasing backlog of testing work including manual regression testing and the maintenance of automated tests. 
 Symptoms  Consequences  Causes  Recommendations 
Test Assets Not Delivered (GEN-PRO-26) 
The system or software under test is delivered without its associated testing assets that would enable the receiving organization(s) to test new capabilities and perform regression testing after changes. 
 Symptoms  Consequences  Causes  Recommendations 
1.6 Pitfall-Related Pitfalls 
Testing Pitfalls 
Observations and Notes 
Overly Ambitious Process Improvement (GEN-PRP-1) 
The test team is overly ambiguous with regard to improving the testing process by attempting to address too many relevant testing pitfalls at once. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Pitfall Prioritization (GEN-PRP-2) 
Test managers do not adequately prioritize the testing pitfalls (for example by relevance, frequency, severity of negative consequences, and/or risk) when attempting to improve the testing process by better addressing testing pitfalls. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 12 
1.7 Test Tools and Environments 
Testing Pitfalls 
Observations and Notes 
Over-Reliance on Manual Testing (GEN-TTE-1) 
Testers place too much reliance on manual testing such that the majority of testing is performed manually, without adequate support of test tools or test scripts. 
 Symptoms  Consequences  Causes  Recommendations 
Over-Reliance on Testing Tools (GEN-TTE-2) 
Testers and other testing stakeholders place too much reliance on commercial off-the-shelf (COTS) and homegrown testing tools. 
 Symptoms  Consequences  Causes  Recommendations 
Target Platform Difficult to Access (GEN-TTE-3) 
The testers are not prepared to perform adequate testing when the target platform is not designed to enable access for testing. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Environments (GEN-TTE-4) 
There are insufficient test tools, test environments or test beds, and test laboratories or facilities, so adequate testing cannot be performed within the schedule and personnel limitations. 
 Symptoms  Consequences  Causes  Recommendations 
Poor Fidelity of Test Environments (GEN-TTE-5) 
The testers build and use test environments or test beds that have poor fidelity to the operational environment of the system or software under test (SUT), and this causes inconclusive or incorrect test results (false-positive and false-negative test results). 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Environment Quality (GEN-TTE-6) 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 13 
The quality of one or more test environments is inadequate due to an excessive number of defects. 
Test Environments Inadequately Tested (GEN-TTE-7) 
Testers do not test their test environments/beds to eliminate defects that could either prevent the testing of the system or software under test or cause incorrect test results. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Configuration Management (GEN-TTE-8) 
Testing work products (for example, test cases, test scripts, test data, test tools, and test environments) are not under configuration management (CM). 
 Symptoms  Consequences  Causes  Recommendations 
Developers Ignore Testability (GEN-TTE-9) 
It is unnecessarily difficult to develop automated tests because the developers do not consider testing when designing and implementing their system or software. 
 Symptoms  Consequences  Causes  Recommendations 
1.8 Automated Testing 
Testing Pitfalls 
Observations and Notes 
Over-Reliance on Manual Testing (GEN-AUTO-1) 
Testers place too much reliance on manual testing such that the majority of testing is performed manually, without adequate support of test tools or test scripts 
 Symptoms  Consequences  Causes  Recommendations 
Automated Testing Replaces Manual Testing (GEN-AUTO-2) 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 14 
Managers, developers, or testers attempt to replace all manual testing with automated testing. 
Excessive Number of Automated Tests (GEN-AUTO-3) 
The ratio of the amount of automated tests to the amount of deliverable software is too high. 
 Symptoms  Consequences  Causes  Recommendations 
Inappropriate Distribution of Automated Tests (GEN-AUTO-4) 
The distribution of the amount of automated testing among the different levels of testing (such as unit testing, integration testing, system testing, and user interface testing) is inappropriate. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Automated Test Quality (GEN-AUTO-5) 
The automated tests have excessive numbers of defects. 
 Symptoms  Consequences  Causes  Recommendations 
Automated Tests Excessively Complex (GEN-AUTO-6) 
The automated tests are significantly more complex than they need to be. 
 Symptoms  Consequences  Causes  Recommendations 
Automated Tests Not Maintained (GEN-AUTO-7) 
The automated tests are not maintained so that they are no longer trusted or reusable. 
 Symptoms  Consequences  Causes  Recommendations 
Insufficient Resources Invested (GEN-AUTO-8) 
Insufficient resources are allocated to plan for, develop, and maintain automated tests. 
 Symptoms  Consequences  Causes  Recommendations 
Automation Tools Not Appropriate (GEN-AUTO-9) 
The developers and testers select inappropriate tools for supporting 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 15 
automated testing. 
Stakeholders Ignored (GEN-AUTO-10) 
The developers and testers ignore the stakeholders when planning and performing automated testing. 
 Symptoms  Consequences  Causes  Recommendations 
1.9 Communication 
Testing Pitfalls 
Observations and Notes 
Inadequate Architecture and Design Documentation (GEN-COM- 1) 
Architects and designers produce insufficient architecture or design documentation (for example, models and documents) to support white-box (structural) unit and integration testing. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Defect Reports (GEN-COM-2) 
Testers and others create defect reports (also known as bug and trouble reports) that are incomplete, contain incorrect information, or are difficult to read. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Test Documentation (GEN-COM-3) 
Testers create test documentation that is incomplete or contains incorrect information. 
 Symptoms  Consequences  Causes  Recommendations 
Source Documents Not Maintained (GEN-COM-4) 
Developers do not properly maintain the requirements specifications, architecture documents, design documents, and 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 16 
associated models that are needed as inputs to the development of tests. 
Inadequate Communication Concerning Testing (GEN-COM-5) 
Verbal and written communication concerning the testing among testers and other testing stakeholders is inadequate. 
 Symptoms  Consequences  Causes  Recommendations 
Inconsistent Testing Terminology (GEN-COM-6) 
Different testers, developers, managers, and other testing stakeholders often use inconsistent and ambiguous technical jargon so that the same word has different meanings and different words have the same meaning. 
 Symptoms  Consequences  Causes  Recommendations 
1.10 Testing-as-a-Service (TaaS) 
Testing Pitfalls 
Observations and Notes 
Cost-Driven Provider Selection (GEN-TaaS-1) 
Executive or administrative management selects the TaaS provider based solely on minimizing cost. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Oversight (GEN-TaaS-2) 
Project management does not provide adequate oversight of the TaaS provider’s testing effort. 
 Symptoms  Consequences  Causes  Recommendations 
Lack of Outsourcing Expertise (GEN-TaaS-3) 
Project administrative and technical management has insufficient training, expertise, and experience in the outsourcing, especially of 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 17 
testing as a service. 
Inadequate TaaS Contract (GEN-TaaS-4) 
The contract between the development/maintenance organization and the TaaS contractor/vendor does not adequately address the project’s Key Performance Indicators (KPIs), associated Service Level Agreements (SLAs), and the specific metrics by which achievement of the SLAs will be measured. 
 Symptoms  Consequences  Causes  Recommendations 
TaaS Improperly Chosen (GEN-TaaS-5) 
TaaS is selected for the outsourcing of a type of testing for which it is an inappropriate choice. 
 Symptoms  Consequences  Causes  Recommendations 
1.11 Requirements 
Testing Pitfalls 
Observations and Notes 
Tests as Requirements (GEN-REQ-1) 
Developers use black-box system- and subsystem-level tests as a replacement for the associated system and subsystem requirements. 
 Symptoms  Consequences  Causes  Recommendations 
Ambiguous Requirements (GEN-REQ-2) 
Testers misinterpret a great many ambiguous requirements and therefore base their testing on incorrect interpretations of these requirements. 
 Symptoms  Consequences  Causes  Recommendations 
Obsolete Requirements (GEN-REQ-3) 
Testers waste effort and time testing whether the object under test 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 18 
(OUT) correctly implements a great many obsolete requirements. 
Missing Requirements (GEN-REQ-4) 
Testers overlook many undocumented requirements and therefore do not plan for, develop, or run the associated overlooked test cases. 
 Symptoms  Consequences  Causes  Recommendations 
Incomplete Requirements (GEN-REQ-5) 
Testers fail to detect that many requirements are incomplete; therefore, they develop and run correspondingly incomplete or incorrect test cases. 
 Symptoms  Consequences  Causes  Recommendations 
Incorrect Requirements (GEN-REQ-6) 
Testers fail to detect that many requirements are incorrect, and therefore develop and run correspondingly incorrect test cases that produce false-positive and false-negative test results. 
 Symptoms  Consequences  Causes  Recommendations 
Requirements Churn (GEN-REQ-7) 
Testers waste an excessive amount of time and effort developing and running test cases based on many requirements that are not sufficiently stable and that therefore change one or more times prior to delivery. 
 Symptoms  Consequences  Causes  Recommendations 
Improperly Derived Requirements (GEN-REQ-8) 
Testers base their testing on improperly derived requirements, resulting in missing test cases, test cases at the wrong level of abstraction, or incorrect test cases based on cross cutting requirements that are allocated without modification to multiple architectural components. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 19 
Verification Methods Not Adequately Specified (GEN-REQ-9) 
Testers (or other developers) fail to properly specify the verification method(s) for each requirement, thereby causing requirements to be verified using unnecessarily inefficient or ineffective verification method(s). 
 Symptoms  Consequences  Causes  Recommendations 
Lack of Requirements Trace (GEN-REQ-10) 
The testers do not trace the requirements to individual tests or test cases, thereby making it unnecessarily difficult to determine whether the tests are inadequate or excessive. 
 Symptoms  Consequences  Causes  Recommendations 
Titanic Effect of Deferred Requirements (GEN-REQ-11) 
Managers or chief engineers defer numerous requirements from previous blocks or builds to the current block or build after the resources for the current build have been allocated and largely expended. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 20 
2 Test-Type-Specific Testing Pitfalls 
The following pitfall categories are specific to a single type of testing: 
1. Executable Model Testing 
2. Unit Testing 
3. Integration Testing 
4. Specialty Testing 
5. System Testing 
6. User Testing 
7. A/B Testing 
8. Acceptance Testing 
9. SoS Testing 
10. Regression Testing 
2.1 Executable Model Testing 
Testing Pitfalls 
Observations and Notes 
Inadequate Executable Models (TTS-MOD-1) 
Either there are no executable requirements, architectural, or design models or else the models that exist are inadequate to enable associated test cases to be manually or automatically developed. 
 Symptoms  Consequences  Causes  Recommendations 
Executable Models Not Tested (TTS-MOD-2) 
No one (such as testers, requirements engineers, architects, or designers) is testing executable requirements, architectural, or design models to verify whether they conform to the requirements and incorporate any defects. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 21 
2.2 Unit Testing 
Testing Pitfalls 
Observations and Notes 
Testing Does Not Drive Design and Implementation (TTS-UNT-1) 
Software developers and testers do not develop their tests first and then use these tests to drive development of the associated architecture, design, and implementation. 
 Symptoms  Consequences  Causes  Recommendations 
Conflict of Interest (TTS-UNT-2) 
Nothing is done to address the following conflict of interest that exists when developers test their own work products: Essentially, they are being asked to demonstrate that their software is defective. 
 Symptoms  Consequences  Causes  Recommendations 
Brittle Test Cases (TTS-UNT-3) 
Unit test cases are too brittle and unnecessarily need to be changed when the unit under test changes. 
 Symptoms  Consequences  Causes  Recommendations 
2.3 Integration Testing 
Testing Pitfalls 
Observations and Notes 
Integration Decreases Testability Ignored (TTS-INT-1) 
Testers fail to take into account that integration encapsulates the individual parts of the whole and the interactions between them, thereby making the internal parts of the integrated whole less 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 22 
observable and less controllable and, therefore, less testable. 
Inadequate Self-Testing (TTS-INT-2) 
Testers fail to take into account that integration encapsulates the individual parts of the whole and the interactions between them, thereby making the internal parts of the integrated whole less observable and less controllable and, therefore, less testable. 
 Symptoms  Consequences  Causes  Recommendations 
Unavailable Components (TTS-INT-3) 
Integration testing must be postponed due to the unavailability of (1) system hardware or software components or (2) test environment components. 
 Symptoms  Consequences  Causes  Recommendations 
System Testing as Integration Testing (TTS-INT-4) 
Testers are actually performing system-level tests of system functionality when they are supposed to be performing integration testing of component interfaces and interactions. 
 Symptoms  Consequences  Causes  Recommendations 
2.4 Specialty Testing 
Testing Pitfalls 
Observations and Notes 
Inadequate Capacity Testing (TTS-SPC-1) 
Testers perform little or no capacity testing (or the capacity testing they do perform is superficial) to determine the degree to which the system or software degrades gracefully as capacity limits are 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 23 
approached, reached, and exceeded. 
Inadequate Concurrency Testing (TTS-SPC-2) 
Testers perform little or no concurrency testing (or the concurrency testing they do perform is superficial) to explicitly uncover the defects that cause the common types of concurrency faults and failures: deadlock, livelock, starvation, priority inversion, race conditions, inconsistent views of shared memory, and unintentional infinite loops. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Configuration Testing (TTS-SPC-3) 
Testers perform little or no configuration testing to determine the degree to which the software under test functions properly when executing on different platform configurations. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Internationalization Testing (TTS-SPC-4) 
Testers perform little or no internationalization testing—or the internationalization testing they do perform is superficial—to determine the degree to which the system is configurable to perform appropriately in multiple countries. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Interface Standards Compliance Testing (TTS-SPC-5) 
Testers perform little or no testing of key interfaces to ensure that they properly comply with associated open interface standards. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Interoperability Testing (TTS-SPC-6) 
Testers perform little or no interoperability testing (or the interoperability testing they do perform is superficial) to determine the degree to which the system successfully interfaces and 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 24 
collaborates with other systems. 
Inadequate Performance Testing (TTS-SPC-7) 
Testers perform little or no performance testing (or the testing they do perform is only superficial) to determine the degree to which the system has adequate levels of the performance quality attributes: event schedualability, jitter, latency, response time, and throughput. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Reliability Testing (TTS-SPC-8) 
Testers perform little or no long-duration reliability testing (also known as stability testing)—or the reliability testing they do perform is superficial (for example, it is not done under operational profiles and is not based on the results of any reliability models)—to determine the degree to which the system continues to function over time without failure. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Robustness Testing (TTS-SPC-9) 
Testers perform little or no robustness testing, or the robustness testing they do perform is superficial (for example, it is not based on the results of any robustness models), to determine the degree to which the system exhibits adequate error, fault, failure, and environmental tolerance. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Safety Testing (TTS-SPC-10) 
Testers perform little or no safety testing, or the safety testing they do perform is superficial (for example, it is not based on the results of a safety or hazard analysis), to determine the degree to which the system is safe from causing or suffering accidental harm. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 25 
Inadequate Security Testing (TTS-SPC-11) 
Testers perform little or no security testing—or the security testing they do perform is superficial (for example, it is not based on the results of a security or threat analysis)—to determine the degree to which the system is secure from causing or suffering malicious harm. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Usability Testing (TTS-SPC-12) 
Testers or usability engineers perform little or no usability testing— or the usability testing they do perform is superficial—to determine the degree to which the system’s human-machine interfaces meet the system’s requirements for usability, manpower, personnel, training, human factors engineering (HFE), and habitability. 
 Symptoms  Consequences  Causes  Recommendations 
2.5 System Testing 
Testing Pitfalls 
Observations and Notes 
Test Hooks Remain (TTS-SYS-1) 
Testers fail to remove temporary test hooks after completing testing, so they remain in the delivered or fielded system. 
 Symptoms  Consequences  Causes  Recommendations 
Lack of Test Hooks (TTS-SYS-2) 
Testers fail to take into account how a lack of test hooks makes it more difficult to test parts of the system hidden via information hiding. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 26 
Inadequate End-to-End Testing (TTS-SYS-3) 
Testers perform inadequate system-level functional testing of a system’s end-to-end support for its missions. 
 Symptoms  Consequences  Causes  Recommendations 
2.6 User Testing 
Testing Pitfalls 
Observations and Notes 
Inadequate User Involvement (TTS-UT-1) 
Too few users representing too few of the different types of users are involved in the performance of user testing and the evaluation of its results. 
 Symptoms  Consequences  Causes  Recommendations 
Unprepared User Representatives (TTS-UT-2) 
The representative user performing user testing are not adequately prepared to effectively and efficiently perform user testing. 
 Symptoms  Consequences  Causes  Recommendations 
User Testing Merely Repeats System Testing (TTS-UT-3) 
User testing is only a repetition of a subsystem of the existing system tests by representative users. 
 Symptoms  Consequences  Causes  Recommendations 
User Testing is Mistaken for Acceptance Testing (TTS-UT-4) 
User testing, often referred as User Acceptance Testing (UAT), is frequently confused with system acceptance testing in spite of their very different goals and descriptions. 
 Symptoms  Consequences  Causes  Recommendations 
Assume Knowledgeable and Careful User (TTS-UT-5) 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 27 
Testers (and developers) mistakenly assume that representative users performing user testing will be careful and as knowledgeable as they are about how the system should work. 
2.7 A/B Testing 
Testing Pitfalls 
Observations and Notes 
Poor Key Performance Indicators (TTS-ABT-1) 
The key performance indicators (KPIs) of the testing do not support business or mission goals. 
 Symptoms  Consequences  Causes  Recommendations 
Misuse of Probability and Statistics (TTS-ABT-2) 
Probability and statistics are misused when interpreting the results of A/B testing. 
 Symptoms  Consequences  Causes  Recommendations 
Confusing Statistical Significance for Business Significance (TTS- ABT-3) 
All statistically significant test results are mistakenly assumed to be sufficiently significant to justify choosing one variant over another, even if the benefits do not justify the associated costs. 
 Symptoms  Consequences  Causes  Recommendations 
Error Source(s) not Controlled (TTS-ABT-4) 
Various sources of error are not controlled during the testing. 
 Symptoms  Consequences  Causes  Recommendations 
System Variant(s) Changed During Test (TTS-ABT-5) 
One or both of the variants of the system or software under test are changed during an A/B test. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 28 
2.8 Acceptance Testing 
Testing Pitfalls 
Observations and Notes 
No Clear System Acceptance Criteria (TTS-AT-1) 
There are no clear system acceptance criteria for use during acceptance testing to determine whether the system is acceptable to the acquiring organization. 
 Symptoms  Consequences  Causes  Recommendations 
2.9 Systems of Systems (SoS) Testing 
Testing Pitfalls 
Observations and Notes 
Inadequate SoS Test Planning (TTS-SoS-1) 
Testers and SoS architects perform an inadequate amount of SoS test planning and fail to appropriately document their plans in SoS- level test planning documentation. 
 Symptoms  Consequences  Causes  Recommendations 
Unclear SoS Testing Responsibilities (TTS-SoS-2) 
Managers or testers fail to clearly define and document the responsibilities for performing end-to-end SoS testing. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Resources for SoS Testing (TTS-SoS-3) 
Management fails to provide adequate resources for system of systems (SoS) testing 
 Symptoms  Consequences  Causes  Recommendations 
SoS Testing Not Properly Scheduled (TTS-SoS-4) 
System of systems testing is not properly scheduled and coordinated 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 29 
with the individual systems’ testing and delivery schedules 
Inadequate SoS Requirements (TTS-SoS-5) 
Many SoS-level requirements are missing, are of poor quality, or are never officially approved or funded. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Support from Individual System Projects (TTS-SoS-6) 
Test support from individual system development or maintenance projects is inadequate to perform system of systems testing. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Defect Tracking Across Projects (TTS-SoS-7) 
Defect tracking across individual system development or maintenance projects is inadequate to support system of systems testing. 
 Symptoms  Consequences  Causes  Recommendations 
Finger-Pointing (TTS-SoS-8) 
Different system development or maintenance projects assign the responsibility for finding and fixing SoS-level defects to other projects. 
 Symptoms  Consequences  Causes  Recommendations 
2.10 Regression Testing 
Testing Pitfalls 
Observations and Notes 
Inadequate Regression Test Automation (TTS-REG-1) 
Testers and developers have automated an insufficient number of tests to enable adequate regression testing. 
 Symptoms  Consequences  Causes  Recommendations
Firesmith’s Testing Pitfalls Checklist 1 November 2014 30 
Regression Testing Not Performed (TTS-REG-2) 
Testers and maintainers perform insufficient regression testing to determine if new defects have been accidentally introduced when changes are made to the system. 
 Symptoms  Consequences  Causes  Recommendations 
Inadequate Scope of Regression Testing (TTS-REG-3) 
The scope of regression testing is insufficiently broad. 
 Symptoms  Consequences  Causes  Recommendations 
Only Low-Level Regression Tests (TTS-REG-4) 
Only low-level (for example, unit-level and possibly integration) regression tests are rerun, so there is no system, acceptance, or operational regression testing and no SoS regression testing. 
 Symptoms  Consequences  Causes  Recommendations 
Test Resources Not Delivered for Maintenance (TTS-REG-5) 
The test resources produced by the development organization are not made available to the maintenance organization to support testing new capabilities and regression testing changes 
 Symptoms  Consequences  Causes  Recommendations 
Only Functional Regression Testing (TTS-REG-6) 
Testers and maintainers only perform regression testing to determine if changes introduce functionality-related defects. 
Inadequate Retesting of Reused Software (TTS-REG-7) 
Developers reuse software without adequately retesting it to ensure that it continues to operate correctly as part of the current system or software. 
 Symptoms  Consequences  Causes  Recommendations

More Related Content

What's hot

ISTQB, ISEB Lecture Notes- 2
ISTQB, ISEB Lecture Notes- 2ISTQB, ISEB Lecture Notes- 2
ISTQB, ISEB Lecture Notes- 2onsoftwaretest
 
ISTQB, ISEB Lecture Notes- 4
ISTQB, ISEB Lecture Notes- 4ISTQB, ISEB Lecture Notes- 4
ISTQB, ISEB Lecture Notes- 4onsoftwaretest
 
Software Testing - Test management - Mazenet Solution
Software Testing - Test management - Mazenet SolutionSoftware Testing - Test management - Mazenet Solution
Software Testing - Test management - Mazenet SolutionMazenetsolution
 
Static testing techniques
Static testing techniquesStatic testing techniques
Static testing techniquesMazenetsolution
 
Introduction to ISTQB & ISEB Certifications
Introduction to ISTQB & ISEB CertificationsIntroduction to ISTQB & ISEB Certifications
Introduction to ISTQB & ISEB CertificationsYogindernath Gupta
 
ISTQB / ISEB Foundation Exam Practice
ISTQB / ISEB Foundation Exam PracticeISTQB / ISEB Foundation Exam Practice
ISTQB / ISEB Foundation Exam PracticeYogindernath Gupta
 
Iseb, ISTQB Static Testing
Iseb, ISTQB Static TestingIseb, ISTQB Static Testing
Iseb, ISTQB Static Testingonsoftwaretest
 
ISTQB Foundation Level Certification - Intruduction
ISTQB Foundation Level Certification - IntruductionISTQB Foundation Level Certification - Intruduction
ISTQB Foundation Level Certification - IntruductionQA Guards
 
Software Testing Process
Software Testing ProcessSoftware Testing Process
Software Testing Processguest1f2740
 
Free-ebook-rex-black advanced-software-testing
Free-ebook-rex-black advanced-software-testingFree-ebook-rex-black advanced-software-testing
Free-ebook-rex-black advanced-software-testingQualister
 
ISTQB / ISEB Foundation Exam Practice - 4
ISTQB / ISEB Foundation Exam Practice - 4ISTQB / ISEB Foundation Exam Practice - 4
ISTQB / ISEB Foundation Exam Practice - 4Yogindernath Gupta
 
ISTQB, ISEB Lecture Notes
ISTQB, ISEB Lecture NotesISTQB, ISEB Lecture Notes
ISTQB, ISEB Lecture Notesonsoftwaretest
 
Manage Testing by Dependencies—Not Activities
Manage Testing by Dependencies—Not ActivitiesManage Testing by Dependencies—Not Activities
Manage Testing by Dependencies—Not ActivitiesTechWell
 

What's hot (20)

ISTQB, ISEB Lecture Notes- 2
ISTQB, ISEB Lecture Notes- 2ISTQB, ISEB Lecture Notes- 2
ISTQB, ISEB Lecture Notes- 2
 
ISTQB, ISEB Lecture Notes- 4
ISTQB, ISEB Lecture Notes- 4ISTQB, ISEB Lecture Notes- 4
ISTQB, ISEB Lecture Notes- 4
 
Istqb chapter 5
Istqb chapter 5Istqb chapter 5
Istqb chapter 5
 
Software Testing - Test management - Mazenet Solution
Software Testing - Test management - Mazenet SolutionSoftware Testing - Test management - Mazenet Solution
Software Testing - Test management - Mazenet Solution
 
Static testing techniques
Static testing techniquesStatic testing techniques
Static testing techniques
 
Introduction to ISTQB & ISEB Certifications
Introduction to ISTQB & ISEB CertificationsIntroduction to ISTQB & ISEB Certifications
Introduction to ISTQB & ISEB Certifications
 
ISTQB / ISEB Foundation Exam Practice
ISTQB / ISEB Foundation Exam PracticeISTQB / ISEB Foundation Exam Practice
ISTQB / ISEB Foundation Exam Practice
 
Iseb, ISTQB Static Testing
Iseb, ISTQB Static TestingIseb, ISTQB Static Testing
Iseb, ISTQB Static Testing
 
ISTQB Foundation Level Certification - Intruduction
ISTQB Foundation Level Certification - IntruductionISTQB Foundation Level Certification - Intruduction
ISTQB Foundation Level Certification - Intruduction
 
Istqb foundation level day 1
Istqb foundation level   day 1Istqb foundation level   day 1
Istqb foundation level day 1
 
Software Testing
Software TestingSoftware Testing
Software Testing
 
Software Testing Process
Software Testing ProcessSoftware Testing Process
Software Testing Process
 
Software Testing 4/5
Software Testing 4/5Software Testing 4/5
Software Testing 4/5
 
Free-ebook-rex-black advanced-software-testing
Free-ebook-rex-black advanced-software-testingFree-ebook-rex-black advanced-software-testing
Free-ebook-rex-black advanced-software-testing
 
ISTQB / ISEB Foundation Exam Practice - 4
ISTQB / ISEB Foundation Exam Practice - 4ISTQB / ISEB Foundation Exam Practice - 4
ISTQB / ISEB Foundation Exam Practice - 4
 
Static Testing
Static TestingStatic Testing
Static Testing
 
Static testing
Static testingStatic testing
Static testing
 
ISTQB, ISEB Lecture Notes
ISTQB, ISEB Lecture NotesISTQB, ISEB Lecture Notes
ISTQB, ISEB Lecture Notes
 
Manage Testing by Dependencies—Not Activities
Manage Testing by Dependencies—Not ActivitiesManage Testing by Dependencies—Not Activities
Manage Testing by Dependencies—Not Activities
 
Static Testing
Static Testing Static Testing
Static Testing
 

Similar to Common System and Software Testing Pitfalls Checklist - 2014

Common testing pitfalls er-2014 - 2014-10-27
Common testing pitfalls   er-2014 - 2014-10-27Common testing pitfalls   er-2014 - 2014-10-27
Common testing pitfalls er-2014 - 2014-10-27Donald Firesmith
 
Test management
Test managementTest management
Test managementOana Feidi
 
ISTQB / ISEB Foundation Exam Practice - 5
ISTQB / ISEB Foundation Exam Practice - 5ISTQB / ISEB Foundation Exam Practice - 5
ISTQB / ISEB Foundation Exam Practice - 5Yogindernath Gupta
 
Test Management introduction
Test Management introductionTest Management introduction
Test Management introductionOana Feidi
 
ISTQBCH foundation level chapter 01 fundamentals of testing
ISTQBCH foundation level chapter 01 fundamentals of testingISTQBCH foundation level chapter 01 fundamentals of testing
ISTQBCH foundation level chapter 01 fundamentals of testingKhalilSalhi5
 
Fundamentals of Software Testing
Fundamentals of Software TestingFundamentals of Software Testing
Fundamentals of Software TestingSagar Joshi
 
Software Engineering (Testing Activities, Management, and Automation)
Software Engineering (Testing Activities, Management, and Automation)Software Engineering (Testing Activities, Management, and Automation)
Software Engineering (Testing Activities, Management, and Automation)ShudipPal
 
Fundamentals of testing
Fundamentals of testingFundamentals of testing
Fundamentals of testingBugRaptors
 
1)Testing-Fundamentals_L_D.pptx
1)Testing-Fundamentals_L_D.pptx1)Testing-Fundamentals_L_D.pptx
1)Testing-Fundamentals_L_D.pptxgianggiang114
 
Common Testing Problems – Pitfalls to Prevent and Mitigate
Common Testing Problems – Pitfalls to Prevent and MitigateCommon Testing Problems – Pitfalls to Prevent and Mitigate
Common Testing Problems – Pitfalls to Prevent and MitigateDonald Firesmith
 
Bab 1 Fundamentals Of Testing
Bab 1 Fundamentals Of TestingBab 1 Fundamentals Of Testing
Bab 1 Fundamentals Of Testinglolayoriva
 
ISTQB - What's testing
ISTQB - What's testingISTQB - What's testing
ISTQB - What's testingHoangThiHien1
 

Similar to Common System and Software Testing Pitfalls Checklist - 2014 (20)

Common testing pitfalls er-2014 - 2014-10-27
Common testing pitfalls   er-2014 - 2014-10-27Common testing pitfalls   er-2014 - 2014-10-27
Common testing pitfalls er-2014 - 2014-10-27
 
Ch14
Ch14Ch14
Ch14
 
Test management
Test managementTest management
Test management
 
ISTQB / ISEB Foundation Exam Practice - 5
ISTQB / ISEB Foundation Exam Practice - 5ISTQB / ISEB Foundation Exam Practice - 5
ISTQB / ISEB Foundation Exam Practice - 5
 
Test Management introduction
Test Management introductionTest Management introduction
Test Management introduction
 
CTFL chapter 05
CTFL chapter 05CTFL chapter 05
CTFL chapter 05
 
Fundamentals of Testing Section 1/6
Fundamentals of Testing   Section 1/6Fundamentals of Testing   Section 1/6
Fundamentals of Testing Section 1/6
 
ISTQBCH foundation level chapter 01 fundamentals of testing
ISTQBCH foundation level chapter 01 fundamentals of testingISTQBCH foundation level chapter 01 fundamentals of testing
ISTQBCH foundation level chapter 01 fundamentals of testing
 
Fundamentals of Software Testing
Fundamentals of Software TestingFundamentals of Software Testing
Fundamentals of Software Testing
 
Fundamental test process
Fundamental test processFundamental test process
Fundamental test process
 
Test Management
Test ManagementTest Management
Test Management
 
Software Engineering (Testing Activities, Management, and Automation)
Software Engineering (Testing Activities, Management, and Automation)Software Engineering (Testing Activities, Management, and Automation)
Software Engineering (Testing Activities, Management, and Automation)
 
Fundamentals of testing
Fundamentals of testingFundamentals of testing
Fundamentals of testing
 
Test management
Test managementTest management
Test management
 
1)Testing-Fundamentals_L_D.pptx
1)Testing-Fundamentals_L_D.pptx1)Testing-Fundamentals_L_D.pptx
1)Testing-Fundamentals_L_D.pptx
 
Common Testing Problems – Pitfalls to Prevent and Mitigate
Common Testing Problems – Pitfalls to Prevent and MitigateCommon Testing Problems – Pitfalls to Prevent and Mitigate
Common Testing Problems – Pitfalls to Prevent and Mitigate
 
Bab 1 Fundamentals Of Testing
Bab 1 Fundamentals Of TestingBab 1 Fundamentals Of Testing
Bab 1 Fundamentals Of Testing
 
TMMi Implementation Guideline
TMMi Implementation GuidelineTMMi Implementation Guideline
TMMi Implementation Guideline
 
ISTQB - What's testing
ISTQB - What's testingISTQB - What's testing
ISTQB - What's testing
 
Ieee829mtp
Ieee829mtpIeee829mtp
Ieee829mtp
 

Recently uploaded

EY_Graph Database Powered Sustainability
EY_Graph Database Powered SustainabilityEY_Graph Database Powered Sustainability
EY_Graph Database Powered SustainabilityNeo4j
 
Hand gesture recognition PROJECT PPT.pptx
Hand gesture recognition PROJECT PPT.pptxHand gesture recognition PROJECT PPT.pptx
Hand gesture recognition PROJECT PPT.pptxbodapatigopi8531
 
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsUnveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsAlberto González Trastoy
 
HR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comHR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comFatema Valibhai
 
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...stazi3110
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...kellynguyen01
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providermohitmore19
 
Introduction to Decentralized Applications (dApps)
Introduction to Decentralized Applications (dApps)Introduction to Decentralized Applications (dApps)
Introduction to Decentralized Applications (dApps)Intelisync
 
Asset Management Software - Infographic
Asset Management Software - InfographicAsset Management Software - Infographic
Asset Management Software - InfographicHr365.us smith
 
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...soniya singh
 
Optimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVOptimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVshikhaohhpro
 
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdfLearn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdfkalichargn70th171
 
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideBuilding Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideChristina Lin
 
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...gurkirankumar98700
 
The Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdf
The Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdfThe Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdf
The Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdfkalichargn70th171
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software DevelopersVinodh Ram
 
Unit 1.1 Excite Part 1, class 9, cbse...
Unit 1.1 Excite Part 1, class 9, cbse...Unit 1.1 Excite Part 1, class 9, cbse...
Unit 1.1 Excite Part 1, class 9, cbse...aditisharan08
 
Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)OPEN KNOWLEDGE GmbH
 

Recently uploaded (20)

EY_Graph Database Powered Sustainability
EY_Graph Database Powered SustainabilityEY_Graph Database Powered Sustainability
EY_Graph Database Powered Sustainability
 
Hand gesture recognition PROJECT PPT.pptx
Hand gesture recognition PROJECT PPT.pptxHand gesture recognition PROJECT PPT.pptx
Hand gesture recognition PROJECT PPT.pptx
 
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsUnveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
 
HR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comHR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.com
 
Exploring iOS App Development: Simplifying the Process
Exploring iOS App Development: Simplifying the ProcessExploring iOS App Development: Simplifying the Process
Exploring iOS App Development: Simplifying the Process
 
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service provider
 
Introduction to Decentralized Applications (dApps)
Introduction to Decentralized Applications (dApps)Introduction to Decentralized Applications (dApps)
Introduction to Decentralized Applications (dApps)
 
Asset Management Software - Infographic
Asset Management Software - InfographicAsset Management Software - Infographic
Asset Management Software - Infographic
 
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
 
Optimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVOptimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTV
 
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdfLearn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
 
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideBuilding Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
 
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
 
The Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdf
The Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdfThe Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdf
The Essentials of Digital Experience Monitoring_ A Comprehensive Guide.pdf
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software Developers
 
Unit 1.1 Excite Part 1, class 9, cbse...
Unit 1.1 Excite Part 1, class 9, cbse...Unit 1.1 Excite Part 1, class 9, cbse...
Unit 1.1 Excite Part 1, class 9, cbse...
 
Call Girls In Mukherjee Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...
Call Girls In Mukherjee Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...Call Girls In Mukherjee Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...
Call Girls In Mukherjee Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...
 
Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)
 

Common System and Software Testing Pitfalls Checklist - 2014

  • 1. Firesmith’s Testing Pitfalls Checklist 1 November 2014 1 Common System and Software Testing Pitfalls Checklist The following checklist is based on the book Common System and Software Testing Pitfalls by Donald Firesmith. It has been updated with additional testing pitfalls that have been identified since the book’s manuscript was frozen for publication. A testing pitfall is defined as a: • A human mistake that unnecessarily and unexpectedly causes testing to be: – Less effective at uncovering defects – Less efficient in terms of time and effort expended – More frustrating to perform • A bad decision, an incorrect mindset, a wrong action, or failure to act • A failure to adequately: – Meet a testing challenge – Address a testing problem • A way to screw up testing This checklist is intended for use when: • Producing test strategies/plans and related documentations • Evaluating contractor proposals • Evaluating test strategies/plans and related documentation (quality control) • Evaluating as-performed test process (quality assurance) • Identifying test-related risks and their mitigation approaches
  • 2. Firesmith’s Testing Pitfalls Checklist 1 November 2014 2 1 General Testing Pitfalls The following pitfall categories are general and potentially apply to all types of testing: 1. Test Planning and Scheduling 2. Stakeholder Involvement and Commitment 3. Management 4. Staffing 5. Process 6. Pitfall-Related Pitfalls 7. Test Tools and Environments 8. Automated Testing 9. Communication 10. Testing-as-a-Service (TaaS) 11. Requirements 1.1 Test Planning and Scheduling Testing Pitfalls Observations and Notes No Separate Test Planning Documentation (GEN-TPS-1) There is no separate testing-specific planning documentation, only incomplete, high-level overviews of testing in the general planning documents. Symptoms Consequences Causes Recommendations Incomplete Test Planning (GEN-TPS-2) Test planning and its associated documentation are not sufficiently complete for the current point in the system development cycle. Symptoms Consequences Causes Recommendations
  • 3. Firesmith’s Testing Pitfalls Checklist 1 November 2014 3 Test Plans Ignored (GEN-TPS-3) The test planning documentation is ignored (that is, it has become “shelfware”) once developed and delivered. Symptoms Consequences Causes Recommendations Test-Case Documents as Test Plans (GEN-TPS-4) Test-case documents that document specific test cases are mislabeled as test plans. Symptoms Consequences Causes Recommendations Inadequate Test Schedule (GEN-TPS-5) The testing schedule is inadequate to complete proper testing. Symptoms Consequences Causes Recommendations Testing at the End (GEN-TPS-6) All testing is performed late in the development cycle; there is little or no testing of executable models or unit or integration testing planned or performed during the early and middle stages of the development cycle. Symptoms Consequences Causes Recommendations Independent Test Schedule (GEN-TPS-7) The test schedule is developed independently of the project master schedule and the schedules of the other development activities. Symptoms Consequences Causes Recommendations 1.2 Stakeholder Involvement and Commitment Testing Pitfalls Observations and Notes Wrong Testing Mindset (GEN-SIC-1) Some testers and testing stakeholders have one or more incorrect Symptoms Consequences Causes Recommendations
  • 4. Firesmith’s Testing Pitfalls Checklist 1 November 2014 4 beliefs concerning testing. Unrealistic Testing Expectations (GEN-SIC-2) Testing stakeholders (especially customer representatives and managers) have various unrealistic expectations with regard to testing. Symptoms Consequences Causes Recommendations Lack of Stakeholder Commitment to Testing (GEN-SIC-3) Stakeholder commitment to the testing effort is inadequate; sufficient resources (for example, people, time in the schedule, tools, or funding) are not allocated the testing effort. Symptoms Consequences Causes Recommendations 1.3 Management Testing Pitfalls Observations and Notes Inadequate Test Resources (GEN-MGMT-1) Management allocates inadequate resources (for example, budget, schedule, staffing, and facilities) to the testing effort. Symptoms Consequences Causes Recommendations Inappropriate External Pressures (GEN-MGMT-2) Managers and others in positions of authority subject testers to inappropriate external pressures. Symptoms Consequences Causes Recommendations Inadequate Test-Related Risk Management (GEN-MGMT-3) There are too few test-related risks identified in the project’s official risk repository, and those that are identified have inappropriately low probabilities, low harm severities, and low priorities. Symptoms Consequences Causes Recommendations
  • 5. Firesmith’s Testing Pitfalls Checklist 1 November 2014 5 Inadequate Test Metrics (GEN-MGMT-4) Too few test metrics are produced, analyzed, reported, or acted upon, and some of the test metrics that are produced are inappropriate or not very useful. Symptoms Consequences Causes Recommendations Inconvenient Test Results Ignored (GEN-MGMT-5) Management ignores or treats lightly inconvenient negative test results (especially those with negative ramifications for the schedule, budget, or system quality). Symptoms Consequences Causes Recommendations Test Lessons Learned Ignored (GEN-MGMT-6) Lessons learned from testing on previous projects are ignored and not placed into practice on the current project. Symptoms Consequences Causes Recommendations 1.4 Staffing Testing Pitfalls Observations and Notes Lack of Independence (GEN-STF-1) The test organization or project test team lack adequate administrative, financial, and technical independence to enable them to withstand inappropriate pressure from the development management to cut corners. Symptoms Consequences Causes Recommendations Unclear Testing Responsibilities (GEN-STF-2) The testing responsibilities are unclear and do not adequately address which organizations, teams, and people are going to be responsible for and perform the different types of testing. Symptoms Consequences Causes Recommendations
  • 6. Firesmith’s Testing Pitfalls Checklist 1 November 2014 6 Developers Responsible for All Testing (GEN-STF-3) Developers are responsible for all of the developmental testing that occurs during system or software development. Symptoms Consequences Causes Recommendations Testers Responsible for All Testing (GEN-STF-4) Testers are responsible for all of the developmental testing that occurs during system or software development. Symptoms Consequences Causes Recommendations Testers Responsible for Quality (GEN-STF-5) Testers are (solely) responsible for the quality of the system or software under test. Symptoms Consequences Causes Recommendations Users Responsible for Testing (GEN-STF-6) The users are responsible for most of the testing, which occurs after the system(s) are operational. Symptoms Consequences Causes Recommendations Inadequate Testing Expertise (GEN-STF-7) Some testers, developers, or other testing stakeholders have inadequate testing-related understanding, expertise, experience, or training. Symptoms Consequences Causes Recommendations Inadequate Domain Expertise (GEN-STF-8) Testers do not have adequate training, experience, and expertise in the system’s application domain. Symptoms Consequences Causes Recommendations Adversarial Relationship (GEN-STF-9) A counterproductive adversarial relationship exists between the testers and either management, the developers, or both. Symptoms Consequences Causes Recommendations
  • 7. Firesmith’s Testing Pitfalls Checklist 1 November 2014 7 1.5 Process Testing Pitfalls Observations and Notes No Planned Testing Process (GEN-PRO-1) There is no as-planned testing process and all testing (if any) is both ad hoc and completely up to the whims of the individual developers and testers. Symptoms Consequences Causes Recommendations Essentially No Testing (GEN-PRO-2) Very little if any developmental testing is being performed. Symptoms Consequences Causes Recommendations Incomplete Testing (GEN-PRO-3) The testers or developers fail to adequately test certain testable behaviors, characteristics, or components of the system or software under test. Symptoms Consequences Causes Recommendations Test Process Ignored (GEN-PRO-4) The testers, developers, or managers ignore the official documented as-planned test process. Symptoms Consequences Causes Recommendations One-Size-Fits-All Testing (GEN-PRO-5) All testing is performed the same way, to the same level of rigor, regardless of its criticality. Symptoms Consequences Causes Recommendations Sunny Day Testing Only )GEN-PRO-6) Testing is largely or totally restricted to verifying that the system does what it should, but does not verify that the system does not do Symptoms Consequences Causes Recommendations
  • 8. Firesmith’s Testing Pitfalls Checklist 1 November 2014 8 what it should not do. Testing and Engineering Process Not Integrated (GEN-PRO-7) The testing process is not adequately integrated into the overall system engineering process, but is rather treated as a separate specialty engineering activity with only limited interfaces with the primary engineering activities. Symptoms Consequences Causes Recommendations Inadequate Test Prioritization (GEN-PRO-8) Testing is not adequately prioritized (for example, all types of testing have the same priority). Symptoms Consequences Causes Recommendations Test-Type Confusion (GEN-PRO-9) Test cases from one type of testing are redundantly repeated as part of another type of testing, even though the testing types have quite different purposes and scopes. Symptoms Consequences Causes Recommendations Functionality Testing Overemphasized (GEN-PRO-10) There is an overemphasis on testing functionality as opposed to testing quality, data, and interface requirements and testing architectural, design, and implementation constraints. Symptoms Consequences Causes Recommendations Black-Box System Testing Overemphasized (GEN-PRO-11) There is an overemphasis on black-box system testing for requirements conformance, and there is very little white-box unit and integration testing for the architecture, design, and implementation verification. Symptoms Consequences Causes Recommendations Black-Box System Testing Underemphasized (GEN-PRO-12) Symptoms Consequences Causes Recommendations
  • 9. Firesmith’s Testing Pitfalls Checklist 1 November 2014 9 There is an overemphasis on white-box unit and integration testing, and very little time is spent on black-box system testing to verify conformance to the requirements. Test Preconditions Ignored (GEN-PRO-13) Test cases do not address preconditions such as the system’s internal mode and states as well as the state(s) of the system’s external environment. Symptoms Consequences Causes Recommendations Too Immature for Testing (GEN-PRO-14) Products are delivered for testing when they are immature and not ready to be tested. Symptoms Consequences Causes Recommendations Inadequate Test Data (GEN-PRO-15) The test data (including individual test data and sets of test data) lack adequate fidelity to operational data, is incomplete, or is invalid. Symptoms Consequences Causes Recommendations Inadequate Evaluations of Test Assets (GEN-PRO-16) The quality of the test assets is not adequately evaluated prior to using them. Symptoms Consequences Causes Recommendations Inadequate Maintenance of Test Assets (GEN-PRO-17) Test assets are not properly maintained (that is, adequately updated and iterated) as defects are found and the object under test (OUT) is changed. Symptoms Consequences Causes Recommendations Testing as a Phase (GEN-PRO-18) Testing is treated as a phase that takes place late in a sequential (also known as waterfall) development cycle instead of as an Symptoms Consequences Causes Recommendations
  • 10. Firesmith’s Testing Pitfalls Checklist 1 November 2014 10 ongoing activity that takes place continuously in an iterative, incremental, and concurrent (an evolutionary, or agile) development cycle. Testers Not Involved Early (GEN-PRO-19) Testers are not involved at the beginning of the project, but rather only once an implementation exists to test. Symptoms Consequences Causes Recommendations Developmental Testing During Production (GEN-PRO-20) Significant system testing is postponed until the system is already in production when fixing defects is much more difficult and expensive. Symptoms Consequences Causes Recommendations No Operational Testing (GEN-PRO-21) Representative users are not performing any operational testing of the “completed” system under actual operational conditions. Symptoms Consequences Causes Recommendations Test Oracles Ignore Nondeterministic Behavior (GEN-PRO-22) Testers do not have any criteria for determining when a test has passed when non-deterministic behavior results in intermittent failures and faults. Symptoms Consequences Causes Recommendations Testing in Quality (GEN-PRO-23) Testing stakeholders rely on testing quality into the system/software under test rather than building quality in from the beginning via all engineering and management activities. Symptoms Consequences Causes Recommendations Developers Ignore Testability (GEN-PRO-24) The system or software under test is unnecessarily difficult to test because the developers did not consider testing when designing and Symptoms Consequences Causes Recommendations
  • 11. Firesmith’s Testing Pitfalls Checklist 1 November 2014 11 implementing the system or software. Testing the BackBlob (GEN-PRO-25) Testers do not adequately deal with their increasing workload due to an ever increasing backlog of testing work including manual regression testing and the maintenance of automated tests. Symptoms Consequences Causes Recommendations Test Assets Not Delivered (GEN-PRO-26) The system or software under test is delivered without its associated testing assets that would enable the receiving organization(s) to test new capabilities and perform regression testing after changes. Symptoms Consequences Causes Recommendations 1.6 Pitfall-Related Pitfalls Testing Pitfalls Observations and Notes Overly Ambitious Process Improvement (GEN-PRP-1) The test team is overly ambiguous with regard to improving the testing process by attempting to address too many relevant testing pitfalls at once. Symptoms Consequences Causes Recommendations Inadequate Pitfall Prioritization (GEN-PRP-2) Test managers do not adequately prioritize the testing pitfalls (for example by relevance, frequency, severity of negative consequences, and/or risk) when attempting to improve the testing process by better addressing testing pitfalls. Symptoms Consequences Causes Recommendations
  • 12. Firesmith’s Testing Pitfalls Checklist 1 November 2014 12 1.7 Test Tools and Environments Testing Pitfalls Observations and Notes Over-Reliance on Manual Testing (GEN-TTE-1) Testers place too much reliance on manual testing such that the majority of testing is performed manually, without adequate support of test tools or test scripts. Symptoms Consequences Causes Recommendations Over-Reliance on Testing Tools (GEN-TTE-2) Testers and other testing stakeholders place too much reliance on commercial off-the-shelf (COTS) and homegrown testing tools. Symptoms Consequences Causes Recommendations Target Platform Difficult to Access (GEN-TTE-3) The testers are not prepared to perform adequate testing when the target platform is not designed to enable access for testing. Symptoms Consequences Causes Recommendations Inadequate Test Environments (GEN-TTE-4) There are insufficient test tools, test environments or test beds, and test laboratories or facilities, so adequate testing cannot be performed within the schedule and personnel limitations. Symptoms Consequences Causes Recommendations Poor Fidelity of Test Environments (GEN-TTE-5) The testers build and use test environments or test beds that have poor fidelity to the operational environment of the system or software under test (SUT), and this causes inconclusive or incorrect test results (false-positive and false-negative test results). Symptoms Consequences Causes Recommendations Inadequate Test Environment Quality (GEN-TTE-6) Symptoms Consequences Causes Recommendations
  • 13. Firesmith’s Testing Pitfalls Checklist 1 November 2014 13 The quality of one or more test environments is inadequate due to an excessive number of defects. Test Environments Inadequately Tested (GEN-TTE-7) Testers do not test their test environments/beds to eliminate defects that could either prevent the testing of the system or software under test or cause incorrect test results. Symptoms Consequences Causes Recommendations Inadequate Test Configuration Management (GEN-TTE-8) Testing work products (for example, test cases, test scripts, test data, test tools, and test environments) are not under configuration management (CM). Symptoms Consequences Causes Recommendations Developers Ignore Testability (GEN-TTE-9) It is unnecessarily difficult to develop automated tests because the developers do not consider testing when designing and implementing their system or software. Symptoms Consequences Causes Recommendations 1.8 Automated Testing Testing Pitfalls Observations and Notes Over-Reliance on Manual Testing (GEN-AUTO-1) Testers place too much reliance on manual testing such that the majority of testing is performed manually, without adequate support of test tools or test scripts Symptoms Consequences Causes Recommendations Automated Testing Replaces Manual Testing (GEN-AUTO-2) Symptoms Consequences Causes Recommendations
  • 14. Firesmith’s Testing Pitfalls Checklist 1 November 2014 14 Managers, developers, or testers attempt to replace all manual testing with automated testing. Excessive Number of Automated Tests (GEN-AUTO-3) The ratio of the amount of automated tests to the amount of deliverable software is too high. Symptoms Consequences Causes Recommendations Inappropriate Distribution of Automated Tests (GEN-AUTO-4) The distribution of the amount of automated testing among the different levels of testing (such as unit testing, integration testing, system testing, and user interface testing) is inappropriate. Symptoms Consequences Causes Recommendations Inadequate Automated Test Quality (GEN-AUTO-5) The automated tests have excessive numbers of defects. Symptoms Consequences Causes Recommendations Automated Tests Excessively Complex (GEN-AUTO-6) The automated tests are significantly more complex than they need to be. Symptoms Consequences Causes Recommendations Automated Tests Not Maintained (GEN-AUTO-7) The automated tests are not maintained so that they are no longer trusted or reusable. Symptoms Consequences Causes Recommendations Insufficient Resources Invested (GEN-AUTO-8) Insufficient resources are allocated to plan for, develop, and maintain automated tests. Symptoms Consequences Causes Recommendations Automation Tools Not Appropriate (GEN-AUTO-9) The developers and testers select inappropriate tools for supporting Symptoms Consequences Causes Recommendations
  • 15. Firesmith’s Testing Pitfalls Checklist 1 November 2014 15 automated testing. Stakeholders Ignored (GEN-AUTO-10) The developers and testers ignore the stakeholders when planning and performing automated testing. Symptoms Consequences Causes Recommendations 1.9 Communication Testing Pitfalls Observations and Notes Inadequate Architecture and Design Documentation (GEN-COM- 1) Architects and designers produce insufficient architecture or design documentation (for example, models and documents) to support white-box (structural) unit and integration testing. Symptoms Consequences Causes Recommendations Inadequate Defect Reports (GEN-COM-2) Testers and others create defect reports (also known as bug and trouble reports) that are incomplete, contain incorrect information, or are difficult to read. Symptoms Consequences Causes Recommendations Inadequate Test Documentation (GEN-COM-3) Testers create test documentation that is incomplete or contains incorrect information. Symptoms Consequences Causes Recommendations Source Documents Not Maintained (GEN-COM-4) Developers do not properly maintain the requirements specifications, architecture documents, design documents, and Symptoms Consequences Causes Recommendations
  • 16. Firesmith’s Testing Pitfalls Checklist 1 November 2014 16 associated models that are needed as inputs to the development of tests. Inadequate Communication Concerning Testing (GEN-COM-5) Verbal and written communication concerning the testing among testers and other testing stakeholders is inadequate. Symptoms Consequences Causes Recommendations Inconsistent Testing Terminology (GEN-COM-6) Different testers, developers, managers, and other testing stakeholders often use inconsistent and ambiguous technical jargon so that the same word has different meanings and different words have the same meaning. Symptoms Consequences Causes Recommendations 1.10 Testing-as-a-Service (TaaS) Testing Pitfalls Observations and Notes Cost-Driven Provider Selection (GEN-TaaS-1) Executive or administrative management selects the TaaS provider based solely on minimizing cost. Symptoms Consequences Causes Recommendations Inadequate Oversight (GEN-TaaS-2) Project management does not provide adequate oversight of the TaaS provider’s testing effort. Symptoms Consequences Causes Recommendations Lack of Outsourcing Expertise (GEN-TaaS-3) Project administrative and technical management has insufficient training, expertise, and experience in the outsourcing, especially of Symptoms Consequences Causes Recommendations
  • 17. Firesmith’s Testing Pitfalls Checklist 1 November 2014 17 testing as a service. Inadequate TaaS Contract (GEN-TaaS-4) The contract between the development/maintenance organization and the TaaS contractor/vendor does not adequately address the project’s Key Performance Indicators (KPIs), associated Service Level Agreements (SLAs), and the specific metrics by which achievement of the SLAs will be measured. Symptoms Consequences Causes Recommendations TaaS Improperly Chosen (GEN-TaaS-5) TaaS is selected for the outsourcing of a type of testing for which it is an inappropriate choice. Symptoms Consequences Causes Recommendations 1.11 Requirements Testing Pitfalls Observations and Notes Tests as Requirements (GEN-REQ-1) Developers use black-box system- and subsystem-level tests as a replacement for the associated system and subsystem requirements. Symptoms Consequences Causes Recommendations Ambiguous Requirements (GEN-REQ-2) Testers misinterpret a great many ambiguous requirements and therefore base their testing on incorrect interpretations of these requirements. Symptoms Consequences Causes Recommendations Obsolete Requirements (GEN-REQ-3) Testers waste effort and time testing whether the object under test Symptoms Consequences Causes Recommendations
  • 18. Firesmith’s Testing Pitfalls Checklist 1 November 2014 18 (OUT) correctly implements a great many obsolete requirements. Missing Requirements (GEN-REQ-4) Testers overlook many undocumented requirements and therefore do not plan for, develop, or run the associated overlooked test cases. Symptoms Consequences Causes Recommendations Incomplete Requirements (GEN-REQ-5) Testers fail to detect that many requirements are incomplete; therefore, they develop and run correspondingly incomplete or incorrect test cases. Symptoms Consequences Causes Recommendations Incorrect Requirements (GEN-REQ-6) Testers fail to detect that many requirements are incorrect, and therefore develop and run correspondingly incorrect test cases that produce false-positive and false-negative test results. Symptoms Consequences Causes Recommendations Requirements Churn (GEN-REQ-7) Testers waste an excessive amount of time and effort developing and running test cases based on many requirements that are not sufficiently stable and that therefore change one or more times prior to delivery. Symptoms Consequences Causes Recommendations Improperly Derived Requirements (GEN-REQ-8) Testers base their testing on improperly derived requirements, resulting in missing test cases, test cases at the wrong level of abstraction, or incorrect test cases based on cross cutting requirements that are allocated without modification to multiple architectural components. Symptoms Consequences Causes Recommendations
  • 19. Firesmith’s Testing Pitfalls Checklist 1 November 2014 19 Verification Methods Not Adequately Specified (GEN-REQ-9) Testers (or other developers) fail to properly specify the verification method(s) for each requirement, thereby causing requirements to be verified using unnecessarily inefficient or ineffective verification method(s). Symptoms Consequences Causes Recommendations Lack of Requirements Trace (GEN-REQ-10) The testers do not trace the requirements to individual tests or test cases, thereby making it unnecessarily difficult to determine whether the tests are inadequate or excessive. Symptoms Consequences Causes Recommendations Titanic Effect of Deferred Requirements (GEN-REQ-11) Managers or chief engineers defer numerous requirements from previous blocks or builds to the current block or build after the resources for the current build have been allocated and largely expended. Symptoms Consequences Causes Recommendations
  • 20. Firesmith’s Testing Pitfalls Checklist 1 November 2014 20 2 Test-Type-Specific Testing Pitfalls The following pitfall categories are specific to a single type of testing: 1. Executable Model Testing 2. Unit Testing 3. Integration Testing 4. Specialty Testing 5. System Testing 6. User Testing 7. A/B Testing 8. Acceptance Testing 9. SoS Testing 10. Regression Testing 2.1 Executable Model Testing Testing Pitfalls Observations and Notes Inadequate Executable Models (TTS-MOD-1) Either there are no executable requirements, architectural, or design models or else the models that exist are inadequate to enable associated test cases to be manually or automatically developed. Symptoms Consequences Causes Recommendations Executable Models Not Tested (TTS-MOD-2) No one (such as testers, requirements engineers, architects, or designers) is testing executable requirements, architectural, or design models to verify whether they conform to the requirements and incorporate any defects. Symptoms Consequences Causes Recommendations
  • 21. Firesmith’s Testing Pitfalls Checklist 1 November 2014 21 2.2 Unit Testing Testing Pitfalls Observations and Notes Testing Does Not Drive Design and Implementation (TTS-UNT-1) Software developers and testers do not develop their tests first and then use these tests to drive development of the associated architecture, design, and implementation. Symptoms Consequences Causes Recommendations Conflict of Interest (TTS-UNT-2) Nothing is done to address the following conflict of interest that exists when developers test their own work products: Essentially, they are being asked to demonstrate that their software is defective. Symptoms Consequences Causes Recommendations Brittle Test Cases (TTS-UNT-3) Unit test cases are too brittle and unnecessarily need to be changed when the unit under test changes. Symptoms Consequences Causes Recommendations 2.3 Integration Testing Testing Pitfalls Observations and Notes Integration Decreases Testability Ignored (TTS-INT-1) Testers fail to take into account that integration encapsulates the individual parts of the whole and the interactions between them, thereby making the internal parts of the integrated whole less Symptoms Consequences Causes Recommendations
  • 22. Firesmith’s Testing Pitfalls Checklist 1 November 2014 22 observable and less controllable and, therefore, less testable. Inadequate Self-Testing (TTS-INT-2) Testers fail to take into account that integration encapsulates the individual parts of the whole and the interactions between them, thereby making the internal parts of the integrated whole less observable and less controllable and, therefore, less testable. Symptoms Consequences Causes Recommendations Unavailable Components (TTS-INT-3) Integration testing must be postponed due to the unavailability of (1) system hardware or software components or (2) test environment components. Symptoms Consequences Causes Recommendations System Testing as Integration Testing (TTS-INT-4) Testers are actually performing system-level tests of system functionality when they are supposed to be performing integration testing of component interfaces and interactions. Symptoms Consequences Causes Recommendations 2.4 Specialty Testing Testing Pitfalls Observations and Notes Inadequate Capacity Testing (TTS-SPC-1) Testers perform little or no capacity testing (or the capacity testing they do perform is superficial) to determine the degree to which the system or software degrades gracefully as capacity limits are Symptoms Consequences Causes Recommendations
  • 23. Firesmith’s Testing Pitfalls Checklist 1 November 2014 23 approached, reached, and exceeded. Inadequate Concurrency Testing (TTS-SPC-2) Testers perform little or no concurrency testing (or the concurrency testing they do perform is superficial) to explicitly uncover the defects that cause the common types of concurrency faults and failures: deadlock, livelock, starvation, priority inversion, race conditions, inconsistent views of shared memory, and unintentional infinite loops. Symptoms Consequences Causes Recommendations Inadequate Configuration Testing (TTS-SPC-3) Testers perform little or no configuration testing to determine the degree to which the software under test functions properly when executing on different platform configurations. Symptoms Consequences Causes Recommendations Inadequate Internationalization Testing (TTS-SPC-4) Testers perform little or no internationalization testing—or the internationalization testing they do perform is superficial—to determine the degree to which the system is configurable to perform appropriately in multiple countries. Symptoms Consequences Causes Recommendations Inadequate Interface Standards Compliance Testing (TTS-SPC-5) Testers perform little or no testing of key interfaces to ensure that they properly comply with associated open interface standards. Symptoms Consequences Causes Recommendations Inadequate Interoperability Testing (TTS-SPC-6) Testers perform little or no interoperability testing (or the interoperability testing they do perform is superficial) to determine the degree to which the system successfully interfaces and Symptoms Consequences Causes Recommendations
  • 24. Firesmith’s Testing Pitfalls Checklist 1 November 2014 24 collaborates with other systems. Inadequate Performance Testing (TTS-SPC-7) Testers perform little or no performance testing (or the testing they do perform is only superficial) to determine the degree to which the system has adequate levels of the performance quality attributes: event schedualability, jitter, latency, response time, and throughput. Symptoms Consequences Causes Recommendations Inadequate Reliability Testing (TTS-SPC-8) Testers perform little or no long-duration reliability testing (also known as stability testing)—or the reliability testing they do perform is superficial (for example, it is not done under operational profiles and is not based on the results of any reliability models)—to determine the degree to which the system continues to function over time without failure. Symptoms Consequences Causes Recommendations Inadequate Robustness Testing (TTS-SPC-9) Testers perform little or no robustness testing, or the robustness testing they do perform is superficial (for example, it is not based on the results of any robustness models), to determine the degree to which the system exhibits adequate error, fault, failure, and environmental tolerance. Symptoms Consequences Causes Recommendations Inadequate Safety Testing (TTS-SPC-10) Testers perform little or no safety testing, or the safety testing they do perform is superficial (for example, it is not based on the results of a safety or hazard analysis), to determine the degree to which the system is safe from causing or suffering accidental harm. Symptoms Consequences Causes Recommendations
  • 25. Firesmith’s Testing Pitfalls Checklist 1 November 2014 25 Inadequate Security Testing (TTS-SPC-11) Testers perform little or no security testing—or the security testing they do perform is superficial (for example, it is not based on the results of a security or threat analysis)—to determine the degree to which the system is secure from causing or suffering malicious harm. Symptoms Consequences Causes Recommendations Inadequate Usability Testing (TTS-SPC-12) Testers or usability engineers perform little or no usability testing— or the usability testing they do perform is superficial—to determine the degree to which the system’s human-machine interfaces meet the system’s requirements for usability, manpower, personnel, training, human factors engineering (HFE), and habitability. Symptoms Consequences Causes Recommendations 2.5 System Testing Testing Pitfalls Observations and Notes Test Hooks Remain (TTS-SYS-1) Testers fail to remove temporary test hooks after completing testing, so they remain in the delivered or fielded system. Symptoms Consequences Causes Recommendations Lack of Test Hooks (TTS-SYS-2) Testers fail to take into account how a lack of test hooks makes it more difficult to test parts of the system hidden via information hiding. Symptoms Consequences Causes Recommendations
  • 26. Firesmith’s Testing Pitfalls Checklist 1 November 2014 26 Inadequate End-to-End Testing (TTS-SYS-3) Testers perform inadequate system-level functional testing of a system’s end-to-end support for its missions. Symptoms Consequences Causes Recommendations 2.6 User Testing Testing Pitfalls Observations and Notes Inadequate User Involvement (TTS-UT-1) Too few users representing too few of the different types of users are involved in the performance of user testing and the evaluation of its results. Symptoms Consequences Causes Recommendations Unprepared User Representatives (TTS-UT-2) The representative user performing user testing are not adequately prepared to effectively and efficiently perform user testing. Symptoms Consequences Causes Recommendations User Testing Merely Repeats System Testing (TTS-UT-3) User testing is only a repetition of a subsystem of the existing system tests by representative users. Symptoms Consequences Causes Recommendations User Testing is Mistaken for Acceptance Testing (TTS-UT-4) User testing, often referred as User Acceptance Testing (UAT), is frequently confused with system acceptance testing in spite of their very different goals and descriptions. Symptoms Consequences Causes Recommendations Assume Knowledgeable and Careful User (TTS-UT-5) Symptoms Consequences Causes Recommendations
  • 27. Firesmith’s Testing Pitfalls Checklist 1 November 2014 27 Testers (and developers) mistakenly assume that representative users performing user testing will be careful and as knowledgeable as they are about how the system should work. 2.7 A/B Testing Testing Pitfalls Observations and Notes Poor Key Performance Indicators (TTS-ABT-1) The key performance indicators (KPIs) of the testing do not support business or mission goals. Symptoms Consequences Causes Recommendations Misuse of Probability and Statistics (TTS-ABT-2) Probability and statistics are misused when interpreting the results of A/B testing. Symptoms Consequences Causes Recommendations Confusing Statistical Significance for Business Significance (TTS- ABT-3) All statistically significant test results are mistakenly assumed to be sufficiently significant to justify choosing one variant over another, even if the benefits do not justify the associated costs. Symptoms Consequences Causes Recommendations Error Source(s) not Controlled (TTS-ABT-4) Various sources of error are not controlled during the testing. Symptoms Consequences Causes Recommendations System Variant(s) Changed During Test (TTS-ABT-5) One or both of the variants of the system or software under test are changed during an A/B test. Symptoms Consequences Causes Recommendations
  • 28. Firesmith’s Testing Pitfalls Checklist 1 November 2014 28 2.8 Acceptance Testing Testing Pitfalls Observations and Notes No Clear System Acceptance Criteria (TTS-AT-1) There are no clear system acceptance criteria for use during acceptance testing to determine whether the system is acceptable to the acquiring organization. Symptoms Consequences Causes Recommendations 2.9 Systems of Systems (SoS) Testing Testing Pitfalls Observations and Notes Inadequate SoS Test Planning (TTS-SoS-1) Testers and SoS architects perform an inadequate amount of SoS test planning and fail to appropriately document their plans in SoS- level test planning documentation. Symptoms Consequences Causes Recommendations Unclear SoS Testing Responsibilities (TTS-SoS-2) Managers or testers fail to clearly define and document the responsibilities for performing end-to-end SoS testing. Symptoms Consequences Causes Recommendations Inadequate Resources for SoS Testing (TTS-SoS-3) Management fails to provide adequate resources for system of systems (SoS) testing Symptoms Consequences Causes Recommendations SoS Testing Not Properly Scheduled (TTS-SoS-4) System of systems testing is not properly scheduled and coordinated Symptoms Consequences Causes Recommendations
  • 29. Firesmith’s Testing Pitfalls Checklist 1 November 2014 29 with the individual systems’ testing and delivery schedules Inadequate SoS Requirements (TTS-SoS-5) Many SoS-level requirements are missing, are of poor quality, or are never officially approved or funded. Symptoms Consequences Causes Recommendations Inadequate Support from Individual System Projects (TTS-SoS-6) Test support from individual system development or maintenance projects is inadequate to perform system of systems testing. Symptoms Consequences Causes Recommendations Inadequate Defect Tracking Across Projects (TTS-SoS-7) Defect tracking across individual system development or maintenance projects is inadequate to support system of systems testing. Symptoms Consequences Causes Recommendations Finger-Pointing (TTS-SoS-8) Different system development or maintenance projects assign the responsibility for finding and fixing SoS-level defects to other projects. Symptoms Consequences Causes Recommendations 2.10 Regression Testing Testing Pitfalls Observations and Notes Inadequate Regression Test Automation (TTS-REG-1) Testers and developers have automated an insufficient number of tests to enable adequate regression testing. Symptoms Consequences Causes Recommendations
  • 30. Firesmith’s Testing Pitfalls Checklist 1 November 2014 30 Regression Testing Not Performed (TTS-REG-2) Testers and maintainers perform insufficient regression testing to determine if new defects have been accidentally introduced when changes are made to the system. Symptoms Consequences Causes Recommendations Inadequate Scope of Regression Testing (TTS-REG-3) The scope of regression testing is insufficiently broad. Symptoms Consequences Causes Recommendations Only Low-Level Regression Tests (TTS-REG-4) Only low-level (for example, unit-level and possibly integration) regression tests are rerun, so there is no system, acceptance, or operational regression testing and no SoS regression testing. Symptoms Consequences Causes Recommendations Test Resources Not Delivered for Maintenance (TTS-REG-5) The test resources produced by the development organization are not made available to the maintenance organization to support testing new capabilities and regression testing changes Symptoms Consequences Causes Recommendations Only Functional Regression Testing (TTS-REG-6) Testers and maintainers only perform regression testing to determine if changes introduce functionality-related defects. Inadequate Retesting of Reused Software (TTS-REG-7) Developers reuse software without adequately retesting it to ensure that it continues to operate correctly as part of the current system or software. Symptoms Consequences Causes Recommendations