SlideShare a Scribd company logo
1
Today’s session will begin shortly
2
10/02/2012 Slide 2
CT Testing:
Theory and Practice
Presented Tom Lawton, TESCO
For TESCO Tuesday
Tuesday, October 27, 2020
3
What We Will Cover
• What are CT’s and PT’s and why do we use them?
• How to read and interpret a transformer face plate
• Why do we test CT’s and PT’s?
• Shop testing
• New Transformers
• Manufacturer’s tests
• Utility tests
• Magnetization effects and demagnetization
• Types of field tests that we will cover in greater depth
in next weeks TESCO Tuesday
4
Self Contained vs. Transformer Rated
1S, 2S, 3S, 4S, 9S, 12S, 16S, 45S, etc., etc.
What’s the Difference?
Different Forms for Different Services and
Applications
5
Self Contained vs. Transformer Rated
Self Contained
(direct)
Transformer Rated
(indirect)
6
Self Contained
Primarily Residential
(1S, 2S, 12S)
Relatively Low Current
Example: 100A
7
Transformer Rated
Primarily Commercial/Industrial
(9S, 16S)
Relatively High Current
Example: 600A
8
What is a CT? a PT?
“A current transformer (CT) is used for
measurement of alternating electric currents.
Current transformers, together with voltage
(or potential) transformers (VT or PT), are
known as instrument transformers. When
current in a circuit is too high to apply directly
to measuring instruments, a current
transformer produces a reduced current
accurately proportional to the current in the
circuit, which can be conveniently connected
to measuring and recording instruments. A
current transformer isolates the measuring
instruments from what may be very high
voltage in the monitored circuit. Current
transformers are commonly used in metering
and protective relays in the electrical power
industry.” - Wikipedia
9
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Current Transformers Conceptual
Representation
Real, with core losses
Ideal. No losses
10
Transformer Rated
Primarily Commercial/Industrial
(9S, 16S)
Relatively High Current
Example: 400A
400:5
5A
11
Example Application
9S Meter Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A5A
12
Faceplate Specifications
Ratio
13
CTs Ratio
For instance, a CT with a 400:5 ratio will
produce 5A on the secondary, when 400A
are applied to the primary.
14
Faceplate Specifications
Thermal
factor
15
CT’s – Functions and Terminology
Thermal Rating factor
A value representing the amount by which the
primary current can be increased without
exceeding the allowable temperature rise.
For instance, a RF of 4.0 at 30° ambient on a
400:5 ratio CT would allow for a primary current
up to 1600A.
16
Faceplate Specifications
Burden
Rating
17
• Manufacturer’s Tests
• Utility Shop Tests
– New Transformers
– Used Transformers
Typical Tests and checks
• Accuracy Testing – this is a Ratio Test
• Accuracy class determination
• Burden Testing
• Polarity checking
• Demagnetize a CT
Shop Testing
Slide 17
18
Burden Rating
The burden range, present in the secondary
circuit, that the manufacturer will guarantee
their CT’s will still accurately function, in
regards to the ratio specification.
19
Burden Testing
Functionality with Burden Present on the
Secondary Loop
ANSI Burden Values
0.1 Ohms
0.2 Ohms
0.5 Ohms
1 Ohms
2 Ohms
4 Ohms
8 Ohms
20
Burden Testing
0.0000
1.0000
2.0000
3.0000
4.0000
5.0000
6.0000
0 2 4 6 8
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
21
CT’s – Functions and Terminology
Accuracy Classifications and Burden
Example: 0.3% @ B0.1, B0.2, B0.5
22
CT’s – Functions and Terminology
Accuracy Classifications and Burden
All CT’s fall within an accuracy class.
IEEE Standards have defined accuracy classes.
23
Polarity Check
The white dot on the transformer indicates
the polarity of the transformer.
24
De-magnetization
CT’s can become magnetized, due to a number of reasons,
including leaving the shorting clip open, near lightning strikes,
and harmonic content.
CT’s can be demagnetized by slowly and smoothly increasing the
secondary resistance until saturation occurs, and then slowly
and smoothly decreasing the secondary resistance.
A resistance that will cause a secondary current reduction of 65%
to 75% will typically put the CT into saturation.
25
• Manufacturer’s Tests
• Utility Shop Tests
– New Transformers
– Used Transformers
Typical Tests and checks
• Accuracy Testing – this is a Ratio Test
• Accuracy class determination
• Burden Testing
• Polarity checking
• Demagnetize a CT
Shop Testing
Slide 25
26
Shop Testing Programs on
Equipment to be used in
Transformer Rated Services
• 100% of all Transformers
– If not possible then sample testing of all and 100% of all those over a certain size for CT’s
and all VT’s (generally not a large volume)
• Transformer testing should include
– Ratio and accuracy testing
– Polarity checking
– Accuracy class determination
• 100% of all transformer rated meters
– If not possible then sample testing of all transformer rated meters and 100% of all those
going into a certain size service and over
27
Types of Field Testing and Site
Verification
Ratio Testing
Burden Testing
Admittance Testing
Polarity and wiring checks
De-magnetization
Meter Site Analyzer
Cat. 6330
28
What we covered
• What are CT’s and PT’s and why do we use them?
• How to read and interpret a transformer face plate
• Why do we test CT’s and PT’s?
• Shop testing
• New Transformers
• Manufacturer’s tests
• Utility tests
• Magnetization effects and demagnetization
• Types of field tests (we will cover in greater depth
in next weeks TESCO Tuesday)
29
Q&A and Upcoming
TESCO Tuesday Presentations
Presentation Date
Ratio, Burden and Admittance 11/3
Lessons Learned from AMI Deployments and Asset
Management Readiness
11/10
Harmonics 11/17
Complete Site Testing 12/1
Electric Vehicle Trends & Calibration of Commercial Chargers 12/8
Streetlights & 5G Metering and Testing 12/15
Sign up: tescometering.com/tescotuesdays
30
Ratio, Burden and Admittance
November 3, 2020 | 11:00 AM Eastern
@tescometering
@TESCO_Metering
TESCO -The Eastern Specialty Company
TESCO -The Eastern Specialty Company

More Related Content

What's hot

Four Quadrant Metering
Four Quadrant MeteringFour Quadrant Metering
Complete Site Testing
Complete Site TestingComplete Site Testing
Traditional Ratio, Burden, Admittance and Demag Testing – Part I
Traditional Ratio, Burden, Admittance and Demag Testing – Part ITraditional Ratio, Burden, Admittance and Demag Testing – Part I
Traditional Ratio, Burden, Admittance and Demag Testing – Part I
TESCO - The Eastern Specialty Company
 
Certifying DC Electric Vehicle Chargers and AC Level Two Chargers
Certifying DC Electric Vehicle Chargers and AC Level Two ChargersCertifying DC Electric Vehicle Chargers and AC Level Two Chargers
Certifying DC Electric Vehicle Chargers and AC Level Two Chargers
TESCO - The Eastern Specialty Company
 
Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17
TESCO - The Eastern Specialty Company
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
TESCO - The Eastern Specialty Company
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
TESCO - The Eastern Specialty Company
 
BR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-BrochureBR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-Brochure
John Rodrigues (Work)
 
Shunt Calibration For Dummies
Shunt Calibration For DummiesShunt Calibration For Dummies
Shunt Calibration For Dummies
Interface
 
Force Measurement - Best load cell calibration practices
Force Measurement - Best load cell calibration practices Force Measurement - Best load cell calibration practices
Force Measurement - Best load cell calibration practices
Henry Zumbrun
 
Burden Testing, Theory, and Practice
Burden Testing, Theory, and PracticeBurden Testing, Theory, and Practice
Burden Testing, Theory, and Practice
TESCO - The Eastern Specialty Company
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
TESCO - The Eastern Specialty Company
 
Field Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair KitsField Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair Kits
TESCO - The Eastern Specialty Company
 
Procedure On How To Interpret Resistance Reading In An Ohmmeter
Procedure On How To Interpret Resistance Reading In An OhmmeterProcedure On How To Interpret Resistance Reading In An Ohmmeter
Procedure On How To Interpret Resistance Reading In An Ohmmeter
Eddie Abug
 
How to use a digital multimeter
How to use a digital multimeterHow to use a digital multimeter
How to use a digital multimeter
sysya
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instruments
Minka Grdesic
 
Multimeter+basics+step+by+step
Multimeter+basics+step+by+stepMultimeter+basics+step+by+step
Multimeter+basics+step+by+step
CDKTCaoThangBMDTCN
 
Electrical testing equipment clamp meters- Usage, operations and Safety
Electrical testing equipment   clamp meters- Usage, operations and SafetyElectrical testing equipment   clamp meters- Usage, operations and Safety
Electrical testing equipment clamp meters- Usage, operations and Safety
Aniruddha Kulkarni
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Living Online
 
Measurement & Instrumentation (BE)
Measurement & Instrumentation (BE)Measurement & Instrumentation (BE)
Measurement & Instrumentation (BE)
PRABHAHARAN429
 

What's hot (20)

Four Quadrant Metering
Four Quadrant MeteringFour Quadrant Metering
Four Quadrant Metering
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
Traditional Ratio, Burden, Admittance and Demag Testing – Part I
Traditional Ratio, Burden, Admittance and Demag Testing – Part ITraditional Ratio, Burden, Admittance and Demag Testing – Part I
Traditional Ratio, Burden, Admittance and Demag Testing – Part I
 
Certifying DC Electric Vehicle Chargers and AC Level Two Chargers
Certifying DC Electric Vehicle Chargers and AC Level Two ChargersCertifying DC Electric Vehicle Chargers and AC Level Two Chargers
Certifying DC Electric Vehicle Chargers and AC Level Two Chargers
 
Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
 
BR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-BrochureBR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-Brochure
 
Shunt Calibration For Dummies
Shunt Calibration For DummiesShunt Calibration For Dummies
Shunt Calibration For Dummies
 
Force Measurement - Best load cell calibration practices
Force Measurement - Best load cell calibration practices Force Measurement - Best load cell calibration practices
Force Measurement - Best load cell calibration practices
 
Burden Testing, Theory, and Practice
Burden Testing, Theory, and PracticeBurden Testing, Theory, and Practice
Burden Testing, Theory, and Practice
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
 
Field Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair KitsField Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair Kits
 
Procedure On How To Interpret Resistance Reading In An Ohmmeter
Procedure On How To Interpret Resistance Reading In An OhmmeterProcedure On How To Interpret Resistance Reading In An Ohmmeter
Procedure On How To Interpret Resistance Reading In An Ohmmeter
 
How to use a digital multimeter
How to use a digital multimeterHow to use a digital multimeter
How to use a digital multimeter
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instruments
 
Multimeter+basics+step+by+step
Multimeter+basics+step+by+stepMultimeter+basics+step+by+step
Multimeter+basics+step+by+step
 
Electrical testing equipment clamp meters- Usage, operations and Safety
Electrical testing equipment   clamp meters- Usage, operations and SafetyElectrical testing equipment   clamp meters- Usage, operations and Safety
Electrical testing equipment clamp meters- Usage, operations and Safety
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
 
Measurement & Instrumentation (BE)
Measurement & Instrumentation (BE)Measurement & Instrumentation (BE)
Measurement & Instrumentation (BE)
 

Similar to TESCO Tuesday: CT Testing: Theory and Practice

CT Testing: Theory and Practice
CT Testing: Theory and PracticeCT Testing: Theory and Practice
CT Testing: Theory and Practice
TESCO - The Eastern Specialty Company
 
CT Testing: Theory and Practice
CT Testing: Theory and PracticeCT Testing: Theory and Practice
CT Testing: Theory and Practice
TESCO - The Eastern Specialty Company
 
Ratio, Burden, and Admittance Testing
Ratio, Burden, and Admittance TestingRatio, Burden, and Admittance Testing
Ratio, Burden, and Admittance Testing
TESCO - The Eastern Specialty Company
 
Ratio, Burden, Admittance Testing
Ratio, Burden, Admittance TestingRatio, Burden, Admittance Testing
Ratio, Burden, Admittance Testing
TESCO - The Eastern Specialty Company
 
Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO - The Eastern Specialty Company
 
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and AdmittanceNebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
TESCO - The Eastern Specialty Company
 
CT Testing - Theory and Practice.pptx
CT Testing - Theory and Practice.pptxCT Testing - Theory and Practice.pptx
CT Testing - Theory and Practice.pptx
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
TESCO - The Eastern Specialty Company
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
TESCO - The Eastern Specialty Company
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
TESCO - The Eastern Specialty Company
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
TESCO - The Eastern Specialty Company
 
Introduction to Instrument Transformers
Introduction to Instrument TransformersIntroduction to Instrument Transformers
Introduction to Instrument Transformers
TESCO - The Eastern Specialty Company
 
Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
TESCO - The Eastern Specialty Company
 
Load Cell Lunch and Learn Presented by Interface
Load Cell Lunch and Learn Presented by InterfaceLoad Cell Lunch and Learn Presented by Interface
Load Cell Lunch and Learn Presented by Interface
Interface
 
ECNE - Spring 2017 CT Theory and Practice
ECNE - Spring 2017 CT Theory and PracticeECNE - Spring 2017 CT Theory and Practice
ECNE - Spring 2017 CT Theory and Practice
TESCO - The Eastern Specialty Company
 
Complete Site Testing
Complete Site TestingComplete Site Testing
CT Burden Testing
CT Burden TestingCT Burden Testing

Similar to TESCO Tuesday: CT Testing: Theory and Practice (20)

CT Testing: Theory and Practice
CT Testing: Theory and PracticeCT Testing: Theory and Practice
CT Testing: Theory and Practice
 
CT Testing: Theory and Practice
CT Testing: Theory and PracticeCT Testing: Theory and Practice
CT Testing: Theory and Practice
 
Ratio, Burden, and Admittance Testing
Ratio, Burden, and Admittance TestingRatio, Burden, and Admittance Testing
Ratio, Burden, and Admittance Testing
 
Ratio, Burden, Admittance Testing
Ratio, Burden, Admittance TestingRatio, Burden, Admittance Testing
Ratio, Burden, Admittance Testing
 
Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
 
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and AdmittanceNebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
 
CT Testing - Theory and Practice.pptx
CT Testing - Theory and Practice.pptxCT Testing - Theory and Practice.pptx
CT Testing - Theory and Practice.pptx
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
 
Introduction to Instrument Transformers
Introduction to Instrument TransformersIntroduction to Instrument Transformers
Introduction to Instrument Transformers
 
Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
 
Load Cell Lunch and Learn Presented by Interface
Load Cell Lunch and Learn Presented by InterfaceLoad Cell Lunch and Learn Presented by Interface
Load Cell Lunch and Learn Presented by Interface
 
ECNE - Spring 2017 CT Theory and Practice
ECNE - Spring 2017 CT Theory and PracticeECNE - Spring 2017 CT Theory and Practice
ECNE - Spring 2017 CT Theory and Practice
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
CT Burden Testing
CT Burden TestingCT Burden Testing
CT Burden Testing
 

Recently uploaded

Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
SOFTTECHHUB
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
TIPNGVN2
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
Safe Software
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
Kumud Singh
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
DianaGray10
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
Zilliz
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
mikeeftimakis1
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Vladimir Iglovikov, Ph.D.
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
Daiki Mogmet Ito
 

Recently uploaded (20)

Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
 

TESCO Tuesday: CT Testing: Theory and Practice

  • 1. 1 Today’s session will begin shortly
  • 2. 2 10/02/2012 Slide 2 CT Testing: Theory and Practice Presented Tom Lawton, TESCO For TESCO Tuesday Tuesday, October 27, 2020
  • 3. 3 What We Will Cover • What are CT’s and PT’s and why do we use them? • How to read and interpret a transformer face plate • Why do we test CT’s and PT’s? • Shop testing • New Transformers • Manufacturer’s tests • Utility tests • Magnetization effects and demagnetization • Types of field tests that we will cover in greater depth in next weeks TESCO Tuesday
  • 4. 4 Self Contained vs. Transformer Rated 1S, 2S, 3S, 4S, 9S, 12S, 16S, 45S, etc., etc. What’s the Difference? Different Forms for Different Services and Applications
  • 5. 5 Self Contained vs. Transformer Rated Self Contained (direct) Transformer Rated (indirect)
  • 6. 6 Self Contained Primarily Residential (1S, 2S, 12S) Relatively Low Current Example: 100A
  • 7. 7 Transformer Rated Primarily Commercial/Industrial (9S, 16S) Relatively High Current Example: 600A
  • 8. 8 What is a CT? a PT? “A current transformer (CT) is used for measurement of alternating electric currents. Current transformers, together with voltage (or potential) transformers (VT or PT), are known as instrument transformers. When current in a circuit is too high to apply directly to measuring instruments, a current transformer produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments. A current transformer isolates the measuring instruments from what may be very high voltage in the monitored circuit. Current transformers are commonly used in metering and protective relays in the electrical power industry.” - Wikipedia
  • 9. 9 Fundamentals of Polyphase Field Meter Testing and Site Verification Current Transformers Conceptual Representation Real, with core losses Ideal. No losses
  • 10. 10 Transformer Rated Primarily Commercial/Industrial (9S, 16S) Relatively High Current Example: 400A 400:5 5A
  • 11. 11 Example Application 9S Meter Installation 5A PHASE A SOURCE PHASE C PHASE B LOAD 400A 400A 400A 5A5A
  • 13. 13 CTs Ratio For instance, a CT with a 400:5 ratio will produce 5A on the secondary, when 400A are applied to the primary.
  • 15. 15 CT’s – Functions and Terminology Thermal Rating factor A value representing the amount by which the primary current can be increased without exceeding the allowable temperature rise. For instance, a RF of 4.0 at 30° ambient on a 400:5 ratio CT would allow for a primary current up to 1600A.
  • 17. 17 • Manufacturer’s Tests • Utility Shop Tests – New Transformers – Used Transformers Typical Tests and checks • Accuracy Testing – this is a Ratio Test • Accuracy class determination • Burden Testing • Polarity checking • Demagnetize a CT Shop Testing Slide 17
  • 18. 18 Burden Rating The burden range, present in the secondary circuit, that the manufacturer will guarantee their CT’s will still accurately function, in regards to the ratio specification.
  • 19. 19 Burden Testing Functionality with Burden Present on the Secondary Loop ANSI Burden Values 0.1 Ohms 0.2 Ohms 0.5 Ohms 1 Ohms 2 Ohms 4 Ohms 8 Ohms
  • 20. 20 Burden Testing 0.0000 1.0000 2.0000 3.0000 4.0000 5.0000 6.0000 0 2 4 6 8 0.3% @ B0.1, B0.2, B0.5 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A – 0.015 = 4.985A Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000
  • 21. 21 CT’s – Functions and Terminology Accuracy Classifications and Burden Example: 0.3% @ B0.1, B0.2, B0.5
  • 22. 22 CT’s – Functions and Terminology Accuracy Classifications and Burden All CT’s fall within an accuracy class. IEEE Standards have defined accuracy classes.
  • 23. 23 Polarity Check The white dot on the transformer indicates the polarity of the transformer.
  • 24. 24 De-magnetization CT’s can become magnetized, due to a number of reasons, including leaving the shorting clip open, near lightning strikes, and harmonic content. CT’s can be demagnetized by slowly and smoothly increasing the secondary resistance until saturation occurs, and then slowly and smoothly decreasing the secondary resistance. A resistance that will cause a secondary current reduction of 65% to 75% will typically put the CT into saturation.
  • 25. 25 • Manufacturer’s Tests • Utility Shop Tests – New Transformers – Used Transformers Typical Tests and checks • Accuracy Testing – this is a Ratio Test • Accuracy class determination • Burden Testing • Polarity checking • Demagnetize a CT Shop Testing Slide 25
  • 26. 26 Shop Testing Programs on Equipment to be used in Transformer Rated Services • 100% of all Transformers – If not possible then sample testing of all and 100% of all those over a certain size for CT’s and all VT’s (generally not a large volume) • Transformer testing should include – Ratio and accuracy testing – Polarity checking – Accuracy class determination • 100% of all transformer rated meters – If not possible then sample testing of all transformer rated meters and 100% of all those going into a certain size service and over
  • 27. 27 Types of Field Testing and Site Verification Ratio Testing Burden Testing Admittance Testing Polarity and wiring checks De-magnetization Meter Site Analyzer Cat. 6330
  • 28. 28 What we covered • What are CT’s and PT’s and why do we use them? • How to read and interpret a transformer face plate • Why do we test CT’s and PT’s? • Shop testing • New Transformers • Manufacturer’s tests • Utility tests • Magnetization effects and demagnetization • Types of field tests (we will cover in greater depth in next weeks TESCO Tuesday)
  • 29. 29 Q&A and Upcoming TESCO Tuesday Presentations Presentation Date Ratio, Burden and Admittance 11/3 Lessons Learned from AMI Deployments and Asset Management Readiness 11/10 Harmonics 11/17 Complete Site Testing 12/1 Electric Vehicle Trends & Calibration of Commercial Chargers 12/8 Streetlights & 5G Metering and Testing 12/15 Sign up: tescometering.com/tescotuesdays
  • 30. 30 Ratio, Burden and Admittance November 3, 2020 | 11:00 AM Eastern @tescometering @TESCO_Metering TESCO -The Eastern Specialty Company TESCO -The Eastern Specialty Company