20. Free end
Rigid connection
We need to calculate the required penetration
depth to make the bottom connection totally
fixed and prevent any rotation about it.
22. (C) in the undrained condition is bigger than it in the drained condition, so the critical is to use it in the
drained condition
The load is function in the height, so it’s a first-degree equation … the S.F.D is a second-degree equation,
and B.M.D is a third-degree equation
27. 10.18
2.21d^2
4.76d
14.28d
9.18d^2
125
19.5 m
Z
Any factor fn. (d) let it fn. (Z) and recalculate as following to get the point of the max. B.M
𝐹𝑥 = 𝑧𝑒𝑟𝑜
⇒ 10.18 + 125 + 4.76𝑍 + 2.21𝑍2 + 125 + 50𝑍 = 9.18𝑍2 + 14.28𝑍
⇒ −6.97𝑍2 + 40.47𝑍 + 135.1 = 𝑍𝑒𝑟𝑜
∴ 𝑍 = 8.17𝑚
Point of zero shear (max. B.M) shall be below the dredge line
28. ∴ 𝑀max = −2.35 8.17 3 + 20.24 8.17 2 + 135.18(8.17) + 218.52 = 1392.4𝐾𝑁. 𝑚
Design the shoring system in the following cases …
SPW and fs = 140:160 MPa Sx = Mmax / fs … and get section from tables
Diaphragm wall Get d from C1 = 3.5 and then get As
Piles
Design as circular columns, but in the case
of secant piles design the RC pile only
In the case of the piles .. Multiply moment x spacing to get the acting moment / pile
30. We use this system if the depth of excavation is very high, which will cause high lateral deformations for the
wall system if it behaves as cantilever system
The reasons which may push me to use another system instead of the cantilever system are …
1- Very deep excavation height.
2- Very high lateral loads (soil – surcharge – ground water - ……).
3- The cantilever system develops large B.M & needs very big penetration depth.
31. The anchored system may be divided to
Anchored-free system Anchored-fixed system
Free = 1.2d Fixed = 1.44d
34. To get the reaction on the anchor, multiply the reaction on
the spacing between them
35. Example
G.W.T
Sand
Silty Clay
𝛾 = 18𝐾 Τ
𝑁 𝑚3
∅ = 34𝑜
𝛾 = 19𝐾 Τ
𝑁 𝑚3
𝐶𝑢 = 30𝐾𝑃𝑎
𝐶′ = 5𝐾𝑃𝑎
∅′ = 20𝑜
2 m
3 m
For the same previous example … determine the max. B.M if it’s anchored-
free system
d
38. To get the point of zero shear, calculate σ 𝑭𝑨 above the dredge line,
and you will get case of the followings …
1- If active force > FA … Point of zero shear is above
the dredge line.
2- Otherwise .. It’ll be below the dredge line
44. X
H
There are two points of zero shear, above and below the dredge line
… so there are two points of max. B.M for the system
45. Example
G.W.T
Sand
Silty Clay
𝛾 = 18𝐾 Τ
𝑁 𝑚3
∅ = 34𝑜
𝛾 = 19𝐾 Τ
𝑁 𝑚3
𝐶𝑢 = 30𝐾𝑃𝑎
𝐶′ = 5𝐾𝑃𝑎
∅′ = 20𝑜
2 m
3 m
For the same previous example … determine the max. B.M if it’s anchored-fixed
system, and the point of zero moment is below the dredge line by 0.5 m
D
0.5 m
50. For The Max. B.M
FOR THE UPPER PART
To get the point of zero shear, calculate σ 𝑭𝑨 above the dredge line, and you will get case of the followings …
1- If active force > FA … Point of zero shear is above
the dredge line.
2- Otherwise .. It’ll be below the dredge line
Active = 125 + 10.18 =135.18 KN > Fa = 83.16 KN …. The point of zero shear is above the dredge line