SlideShare a Scribd company logo
Slides Transcription
Slide 1
NON-RESIDENTIAL BUILDING: CONSTRUCTION MANAGEMENT
Slide 2
 The presentation is about efficient construction management practice and methodologies
to be utilized in the undertaking of a construction project
 The project undertaken, is the construction of an industrial building in Albury, New South
Wales
 Construction was executed as per the client's specifications and NCC codes and standards
 The ultimate aim of the team is to deliver the project to the client at minimal costs
 The two methods were the parametric method and the square foot method which produced
relatively different cost projections for the project,
Slide 3
 The proposed construction is to on irregular piece of land in Albury, New South Wales
(NSW)
 The project is to be developed for the construction of a warehouse and a retail showroom
for the storage of bulky goods for sale
 The aim of the project to develop the various tasks needed in executing the project plan to
its completion
 Our main objective is to deliver the project within the time schedule, and maximizing on
the quality of fit-outs and finishes while minimizing on cost
 Planning was through effective construction management practices
 Desired construction was obtained as per the schedule & at a minimum cost
Slide 4
 The main of the project is to integrate construction management principles in the
construction of the proposed Albury industrial warehouse project
 Our client task the team to develop and effective construction plan with the least
construction cost
 Therefore the aim was to highlight all construction processes while assigning each stage a
reasonable and manageable budget
 the objective was to deliver project within the shortest period available as client not more
than 12 months for the construction
 Due to efficient construction management plans, the project was scheduled to take 8
months to completions
Slide 5
 civil works is the initial on-site activity to be considered on the construction site
 it is mandatory to do a soil engineering test, which is to be carried out by a geotechnical
engineer
 According to the site classification done by Civil Test Albury Wodonga,
 it was found out that the site is generally flat with a good surface drainage
 From the overall investigation done in accordance with AS 2870-2011, the site was
classified as class H1
 Civil work activities include
 Excavation- for this project will not be complex considering the simple design of the
warehouse and set out
 Site planning - The primary reason for planning our site is to maximize on the working
environment and ensure safe construction throughout the project delivery
 Ground water control - . Building new kerb inlet pit is important including other new storm
water drainage.
Slide 6
 Civil works activities are necessitated through use of different tools, equipment and
machines
 Some of the machines to be used in the civil works include
 Excavators - They are the most common earth moving vehicles that were used to dig an
move earth. They perform various tasks such as breaking holes and digging trenches
 Loaders - are heavy materials that move side to side or load materials
 Skid steer loaders - Are small, engine-powered machines that have lift arms.
 Cranes/forklifts – used to lift construction materials, load and offload materials on site
Slide 7
 Footing and foundation systems follows after preliminary earthworks.
 It involves digging of foundations and setting of footing systems with sufficient strength
to support the entire structural loads (both dead and live loads)
 Activities involved include
 Geotechnical soil condition analysis – from tests, site was classified under H1 site
 This limits the wall lintel to be at min 300mm and piers at min 600mm below existing
surface level
 Pad footing of 600 by 600 mm was proposed for columns and concrete of 25MPa grade to
be used on columns
 Strip foundations proved best fit for construction and location for the project
 Strip foundation of 450x550mm running at the perimeter is proposed
 The table shows the specification for concrete for foundation and footing activities
Slide 8
 The proposed wall system for the construction of the warehouse is a tilt slab system. The
reason why this system has been chosen is because of its ability to speed up the construction
process and its low cost
 Factors for selecting tilt lab system is that is has reduced labour, short time of construction,
can accommodate large amount of people on site and require less equipment to execute
 Tilt up process is to be considered in pouring wet concrete into the slabs
 Sandwich walls selected for mezzanine construction
 The typical dimensions of the wall panels are:
 Widths: 1.2m - 4.5m
 Heights: 3m – 12m
 Thicknesses: 110mm – 500mm
 The parapet wall will be made of a coping finish at the top of quality material or a rail that
is 900mm high

Slide 9
 These figures shows images of tilt up walling system, suspended floor systems, tile roofing
and suspended staircases for the proposed industrial building
Slide 10
 Secondary construction entails; project cost estimation, time planning, project
specifications, procurement, project delivery and handover among other aspects
 Budget
 The warehouse and retail showroom project in Albury consist of four different construction
areas. Therefore, this means that the cost of constructing this whole development must be
calculated separately for each development due to the different rates of material, labour
and quantity as directed in Rawlinson's guide 2017.
 The different developments in this project include:
 Warehouse offices for employees occupation
 Industrial warehouse
 Partially underground parking
 open parking areas
 Overall estimate budget is at $2,845,609.00
Slide 11
 The project is to completed under 12 month period, therefore it is important to effectively
plan and start by time-consuming activities first
 The project site in Albury requires demolition and excavation works before the major
project is undertaken by the contractor.
 There is an old structure within the confines of the site boundary that requires demolition
prior to the excavation works.
 These are the most time- consuming elements of the project as they are cost and labour
intensive
 The allocated time frame for the completion of the entire project is 8 months between
15/09/2021 and 28/3/22
 The table schedule elaborate more about activities with respective days
Slide 12
 Project construction is divided into; substructure constructions, installation of amenities,
fitting and finishes, and landscaping
 Subfloors ( Reinforcement and pouring of concrete) to take place concurrently with enough
labour and equipment’s. (15 days).
 Excavation of site, then a hardcore layer is laid and compacted, reinforcement cages are
laid and concrete
 Subfloor columns take 5 days
 Load bearing walls to transfer the roof and top floor loads to the foundations therefore a
material with high compressive strength will be required
 Amenities; include waterproofing, tilling and Plumbing Components installations
 Fitting and finishes include flooring, carpeting, painting and electrical fittings
 Landscaping - Done to connect the building to the landscape and create a microclimate
Slide 13
 The use of the building specifications enables the contractors to follow the construction
methods recommended by the clients
 The installation design also has to follow the requirements set by the AS 2159
 Project type: non residential building
 Site: Albury, New South Wales
 Construction period: 8 months
 Budget: $2,845,609.00
 Building: Industrial/commercial structures
 4 retail showrooms
 Warehouse
 Retail shops and office units
 Car park basement
Slide 14
 The physical model of a design project is like a prototype scale created to give the
constrution team and the developer a replica of what is to be constructed
 The proliferation of Computer Aided Design (CAD) software have enabled the creation of
more complex models by providing a virtual environment.
 The model created for this project encapsulates the industrial environment achieved
through the use of a number of tools and techniques.
Slide 15
 The industrial development in the city of Albury is set to take nine months to utilize both
methods of design and construct contractual construction.
 These methods save on time, leading to a shorter duration of time involved in the building.
 The budget involved in the structure is based on the estimates of the GFA and is estimated
to be around $2.8 million; this consists of the value of engineering techniques incorporated
according to clients' specifications
 It is suspected that the geographical location of Albury may have adverse effects on the
availability and the arrival time of the raw materials;
 Therefore, the builders have to adapt using a design and construct contract based on the
problems experienced in the construction process.
Slide 16
Reference list
Slide 17
Reference list

More Related Content

Similar to Slides Transcription.docx

Ici j sern unit employer brief v2 (1)
Ici j sern unit employer brief v2 (1)Ici j sern unit employer brief v2 (1)
Ici j sern unit employer brief v2 (1)
Macy Khor
 
ICI Project Brief
ICI Project BriefICI Project Brief
ICI Project Brief
J-Sern Phua
 
Ici j sern unit employer brief v2
Ici j sern unit employer brief v2Ici j sern unit employer brief v2
Ici j sern unit employer brief v2
Arthur Wilson
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final Project
Allen Green
 
Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Site%20 installation %20final_20070219
Site%20 installation %20final_20070219
Quang Nguyễn
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures Ltd
Sk Md Nayar
 
CV.2016
CV.2016CV.2016
CV.2016
Mamdouh Attia
 
CV
CVCV
Capital Gate Abu Dhabhi - Case Study
Capital Gate Abu Dhabhi - Case Study Capital Gate Abu Dhabhi - Case Study
Capital Gate Abu Dhabhi - Case Study
Jeesmon Babu
 
BUILDING REFURBISHMENT for industry bb.pdf
BUILDING REFURBISHMENT for industry bb.pdfBUILDING REFURBISHMENT for industry bb.pdf
BUILDING REFURBISHMENT for industry bb.pdf
aZrieyajizzz
 
CV-R.B.Guinir Jr.(01-15-17)
CV-R.B.Guinir Jr.(01-15-17)CV-R.B.Guinir Jr.(01-15-17)
CV-R.B.Guinir Jr.(01-15-17)
Rogelio Jr Guinir
 
Implementation of a high performace clusther for a university
Implementation of a high performace clusther for a universityImplementation of a high performace clusther for a university
Implementation of a high performace clusther for a university
SharyuMahale
 
Innovation technique in construction
Innovation technique in constructionInnovation technique in construction
Innovation technique in construction
School of Planning and Architecture, new delhi
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
SiharaGallage
 
Appendices
AppendicesAppendices
Ahmed Mohamed Maher Shafik
Ahmed Mohamed Maher ShafikAhmed Mohamed Maher Shafik
Ahmed Mohamed Maher Shafik
Ahmed Shafik
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional Construction
IRJET Journal
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
Siddique Pasha
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
Wael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp Letters
Waell Azmy
 

Similar to Slides Transcription.docx (20)

Ici j sern unit employer brief v2 (1)
Ici j sern unit employer brief v2 (1)Ici j sern unit employer brief v2 (1)
Ici j sern unit employer brief v2 (1)
 
ICI Project Brief
ICI Project BriefICI Project Brief
ICI Project Brief
 
Ici j sern unit employer brief v2
Ici j sern unit employer brief v2Ici j sern unit employer brief v2
Ici j sern unit employer brief v2
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final Project
 
Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Site%20 installation %20final_20070219
Site%20 installation %20final_20070219
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures Ltd
 
CV.2016
CV.2016CV.2016
CV.2016
 
CV
CVCV
CV
 
Capital Gate Abu Dhabhi - Case Study
Capital Gate Abu Dhabhi - Case Study Capital Gate Abu Dhabhi - Case Study
Capital Gate Abu Dhabhi - Case Study
 
BUILDING REFURBISHMENT for industry bb.pdf
BUILDING REFURBISHMENT for industry bb.pdfBUILDING REFURBISHMENT for industry bb.pdf
BUILDING REFURBISHMENT for industry bb.pdf
 
CV-R.B.Guinir Jr.(01-15-17)
CV-R.B.Guinir Jr.(01-15-17)CV-R.B.Guinir Jr.(01-15-17)
CV-R.B.Guinir Jr.(01-15-17)
 
Implementation of a high performace clusther for a university
Implementation of a high performace clusther for a universityImplementation of a high performace clusther for a university
Implementation of a high performace clusther for a university
 
Innovation technique in construction
Innovation technique in constructionInnovation technique in construction
Innovation technique in construction
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
 
Appendices
AppendicesAppendices
Appendices
 
Ahmed Mohamed Maher Shafik
Ahmed Mohamed Maher ShafikAhmed Mohamed Maher Shafik
Ahmed Mohamed Maher Shafik
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional Construction
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Wael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp Letters
 

Recently uploaded

Sources of Revenue for State Government - Prof Oyedokun.pptx
Sources of Revenue for State Government - Prof Oyedokun.pptxSources of Revenue for State Government - Prof Oyedokun.pptx
Sources of Revenue for State Government - Prof Oyedokun.pptx
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
Financial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptxFinancial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptx
Writo-Finance
 
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
5spllj1l
 
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
mayaclinic18
 
Eco-Innovations and Firm Heterogeneity. Evidence from Italian Family and Nonf...
Eco-Innovations and Firm Heterogeneity.Evidence from Italian Family and Nonf...Eco-Innovations and Firm Heterogeneity.Evidence from Italian Family and Nonf...
Eco-Innovations and Firm Heterogeneity. Evidence from Italian Family and Nonf...
University of Calabria
 
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
obyzuk
 
Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...
Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...
Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...
Vighnesh Shashtri
 
Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...
Labour Market Information Council | Conseil de l’information sur le marché du travail
 
快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样
快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样
快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样
rlo9fxi
 
Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...
Labour Market Information Council | Conseil de l’information sur le marché du travail
 
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptxOAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
hiddenlevers
 
What's a worker’s market? Job quality and labour market tightness
What's a worker’s market? Job quality and labour market tightnessWhat's a worker’s market? Job quality and labour market tightness
What's a worker’s market? Job quality and labour market tightness
Labour Market Information Council | Conseil de l’information sur le marché du travail
 
Instant Issue Debit Cards
Instant Issue Debit CardsInstant Issue Debit Cards
Instant Issue Debit Cards
egoetzinger
 
Donald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptxDonald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptx
SerdarHudaykuliyew
 
1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf
Neal Brewster
 
DEMAND AND SUPPLY.docx Notes for Economics
DEMAND AND SUPPLY.docx Notes for EconomicsDEMAND AND SUPPLY.docx Notes for Economics
DEMAND AND SUPPLY.docx Notes for Economics
Opanga1
 
G20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summitG20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summit
rohitsaxena882511
 
Role of Information Technology in Revenue - Prof Oyedokun.pptx
Role of Information Technology in Revenue  - Prof Oyedokun.pptxRole of Information Technology in Revenue  - Prof Oyedokun.pptx
Role of Information Technology in Revenue - Prof Oyedokun.pptx
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt FinancingHow Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
Vighnesh Shashtri
 
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFiTdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
nimaruinazawa258
 

Recently uploaded (20)

Sources of Revenue for State Government - Prof Oyedokun.pptx
Sources of Revenue for State Government - Prof Oyedokun.pptxSources of Revenue for State Government - Prof Oyedokun.pptx
Sources of Revenue for State Government - Prof Oyedokun.pptx
 
Financial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptxFinancial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptx
 
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
 
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
 
Eco-Innovations and Firm Heterogeneity. Evidence from Italian Family and Nonf...
Eco-Innovations and Firm Heterogeneity.Evidence from Italian Family and Nonf...Eco-Innovations and Firm Heterogeneity.Evidence from Italian Family and Nonf...
Eco-Innovations and Firm Heterogeneity. Evidence from Italian Family and Nonf...
 
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
 
Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...
Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...
Abhay Bhutada Leads Poonawalla Fincorp To Record Low NPA And Unprecedented Gr...
 
Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...
 
快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样
快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样
快速制作美国迈阿密大学牛津分校毕业证文凭证书英文原版一模一样
 
Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...
 
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptxOAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
 
What's a worker’s market? Job quality and labour market tightness
What's a worker’s market? Job quality and labour market tightnessWhat's a worker’s market? Job quality and labour market tightness
What's a worker’s market? Job quality and labour market tightness
 
Instant Issue Debit Cards
Instant Issue Debit CardsInstant Issue Debit Cards
Instant Issue Debit Cards
 
Donald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptxDonald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptx
 
1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf
 
DEMAND AND SUPPLY.docx Notes for Economics
DEMAND AND SUPPLY.docx Notes for EconomicsDEMAND AND SUPPLY.docx Notes for Economics
DEMAND AND SUPPLY.docx Notes for Economics
 
G20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summitG20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summit
 
Role of Information Technology in Revenue - Prof Oyedokun.pptx
Role of Information Technology in Revenue  - Prof Oyedokun.pptxRole of Information Technology in Revenue  - Prof Oyedokun.pptx
Role of Information Technology in Revenue - Prof Oyedokun.pptx
 
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt FinancingHow Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
 
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFiTdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
 

Slides Transcription.docx

  • 1. Slides Transcription Slide 1 NON-RESIDENTIAL BUILDING: CONSTRUCTION MANAGEMENT Slide 2  The presentation is about efficient construction management practice and methodologies to be utilized in the undertaking of a construction project  The project undertaken, is the construction of an industrial building in Albury, New South Wales  Construction was executed as per the client's specifications and NCC codes and standards  The ultimate aim of the team is to deliver the project to the client at minimal costs  The two methods were the parametric method and the square foot method which produced relatively different cost projections for the project, Slide 3  The proposed construction is to on irregular piece of land in Albury, New South Wales (NSW)  The project is to be developed for the construction of a warehouse and a retail showroom for the storage of bulky goods for sale  The aim of the project to develop the various tasks needed in executing the project plan to its completion  Our main objective is to deliver the project within the time schedule, and maximizing on the quality of fit-outs and finishes while minimizing on cost  Planning was through effective construction management practices  Desired construction was obtained as per the schedule & at a minimum cost
  • 2. Slide 4  The main of the project is to integrate construction management principles in the construction of the proposed Albury industrial warehouse project  Our client task the team to develop and effective construction plan with the least construction cost  Therefore the aim was to highlight all construction processes while assigning each stage a reasonable and manageable budget  the objective was to deliver project within the shortest period available as client not more than 12 months for the construction  Due to efficient construction management plans, the project was scheduled to take 8 months to completions Slide 5  civil works is the initial on-site activity to be considered on the construction site  it is mandatory to do a soil engineering test, which is to be carried out by a geotechnical engineer  According to the site classification done by Civil Test Albury Wodonga,  it was found out that the site is generally flat with a good surface drainage  From the overall investigation done in accordance with AS 2870-2011, the site was classified as class H1  Civil work activities include  Excavation- for this project will not be complex considering the simple design of the warehouse and set out
  • 3.  Site planning - The primary reason for planning our site is to maximize on the working environment and ensure safe construction throughout the project delivery  Ground water control - . Building new kerb inlet pit is important including other new storm water drainage. Slide 6  Civil works activities are necessitated through use of different tools, equipment and machines  Some of the machines to be used in the civil works include  Excavators - They are the most common earth moving vehicles that were used to dig an move earth. They perform various tasks such as breaking holes and digging trenches  Loaders - are heavy materials that move side to side or load materials  Skid steer loaders - Are small, engine-powered machines that have lift arms.  Cranes/forklifts – used to lift construction materials, load and offload materials on site Slide 7  Footing and foundation systems follows after preliminary earthworks.  It involves digging of foundations and setting of footing systems with sufficient strength to support the entire structural loads (both dead and live loads)  Activities involved include  Geotechnical soil condition analysis – from tests, site was classified under H1 site  This limits the wall lintel to be at min 300mm and piers at min 600mm below existing surface level  Pad footing of 600 by 600 mm was proposed for columns and concrete of 25MPa grade to be used on columns
  • 4.  Strip foundations proved best fit for construction and location for the project  Strip foundation of 450x550mm running at the perimeter is proposed  The table shows the specification for concrete for foundation and footing activities Slide 8  The proposed wall system for the construction of the warehouse is a tilt slab system. The reason why this system has been chosen is because of its ability to speed up the construction process and its low cost  Factors for selecting tilt lab system is that is has reduced labour, short time of construction, can accommodate large amount of people on site and require less equipment to execute  Tilt up process is to be considered in pouring wet concrete into the slabs  Sandwich walls selected for mezzanine construction  The typical dimensions of the wall panels are:  Widths: 1.2m - 4.5m  Heights: 3m – 12m  Thicknesses: 110mm – 500mm  The parapet wall will be made of a coping finish at the top of quality material or a rail that is 900mm high  Slide 9  These figures shows images of tilt up walling system, suspended floor systems, tile roofing and suspended staircases for the proposed industrial building Slide 10
  • 5.  Secondary construction entails; project cost estimation, time planning, project specifications, procurement, project delivery and handover among other aspects  Budget  The warehouse and retail showroom project in Albury consist of four different construction areas. Therefore, this means that the cost of constructing this whole development must be calculated separately for each development due to the different rates of material, labour and quantity as directed in Rawlinson's guide 2017.  The different developments in this project include:  Warehouse offices for employees occupation  Industrial warehouse  Partially underground parking  open parking areas  Overall estimate budget is at $2,845,609.00 Slide 11  The project is to completed under 12 month period, therefore it is important to effectively plan and start by time-consuming activities first  The project site in Albury requires demolition and excavation works before the major project is undertaken by the contractor.  There is an old structure within the confines of the site boundary that requires demolition prior to the excavation works.  These are the most time- consuming elements of the project as they are cost and labour intensive
  • 6.  The allocated time frame for the completion of the entire project is 8 months between 15/09/2021 and 28/3/22  The table schedule elaborate more about activities with respective days Slide 12  Project construction is divided into; substructure constructions, installation of amenities, fitting and finishes, and landscaping  Subfloors ( Reinforcement and pouring of concrete) to take place concurrently with enough labour and equipment’s. (15 days).  Excavation of site, then a hardcore layer is laid and compacted, reinforcement cages are laid and concrete  Subfloor columns take 5 days  Load bearing walls to transfer the roof and top floor loads to the foundations therefore a material with high compressive strength will be required  Amenities; include waterproofing, tilling and Plumbing Components installations  Fitting and finishes include flooring, carpeting, painting and electrical fittings  Landscaping - Done to connect the building to the landscape and create a microclimate Slide 13  The use of the building specifications enables the contractors to follow the construction methods recommended by the clients  The installation design also has to follow the requirements set by the AS 2159  Project type: non residential building  Site: Albury, New South Wales
  • 7.  Construction period: 8 months  Budget: $2,845,609.00  Building: Industrial/commercial structures  4 retail showrooms  Warehouse  Retail shops and office units  Car park basement Slide 14  The physical model of a design project is like a prototype scale created to give the constrution team and the developer a replica of what is to be constructed  The proliferation of Computer Aided Design (CAD) software have enabled the creation of more complex models by providing a virtual environment.  The model created for this project encapsulates the industrial environment achieved through the use of a number of tools and techniques. Slide 15  The industrial development in the city of Albury is set to take nine months to utilize both methods of design and construct contractual construction.  These methods save on time, leading to a shorter duration of time involved in the building.  The budget involved in the structure is based on the estimates of the GFA and is estimated to be around $2.8 million; this consists of the value of engineering techniques incorporated according to clients' specifications
  • 8.  It is suspected that the geographical location of Albury may have adverse effects on the availability and the arrival time of the raw materials;  Therefore, the builders have to adapt using a design and construct contract based on the problems experienced in the construction process. Slide 16 Reference list Slide 17 Reference list