SlideShare a Scribd company logo
1 of 5
Download to read offline
LAST YEAR OF PEP-II B-FACTORY OPERATION*
J. T. Seeman, SLAC, Menlo Park, CA 94025 USA
Abstract
The PEP-II B-Factory [1] at SLAC (3.1 GeV e+
x 9.0
GeV e-
) operated from 1999 to 2008, delivering
luminosity to the BaBar experiment. The design
luminosity was reached after one and a half years of
operation. In the end PEP-II surpassed by four times its
design luminosity reaching 1.21 x 1034
cm-2
s-1
. It also set
stored beam current records of 2.1 A e-
and 3.2 A e+
.
Continuous injection was implemented with BaBar taking
data. The total delivered luminosity to the BaBar detector
was 557.4 fb-1
spanning five upsilon resonances. PEP-II
was constructed by SLAC, LBNL, and LLNL with help
from BINP, IHEP, the BaBar collaboration, and the US
DOE OHEP.
PEP-II TIMELINE
1987: Particle physicists determine that
asymmetrical beam energies are preferred.
1991: First PEP-II CDR.
1993: Second PEP-II CDR.
1994: Construction started
1997: First HER stored beam 6:30 am June 5.
1998: First LER stored beam 2:49 am July 16.
1998: First collisions 12:05 pm July 23.
1999: BaBar placed on beam line in May.
1999-2008: Collisions for BaBar.
2000: Design luminosity achieved (3x1033
) Oct. 29.
2006: Luminosity 1.2x1034
achieved 8 pm Aug. 17.
2008: PEP-II turned off 23:22 pm April 7.
Table 1 : PEP-II Collision Parameters
*Supported by US DOE contract DE-AC02-76SF00515.
†
seeman@slac.stanford.edu
PEP-II PARAMETERS
In PEP-II the Low Energy Ring (LER) is mounted 0.89 m
above the High Energy Ring (HER) in the 2.2 km tunnel
as shown in Figure 1. The interaction region is shown in
Figure 2 where the beams are collided head on. Figure 3
shows the Be vacuum chamber inside the detector with
the permanent magnet dipoles on either side. The
interface cone angle at the IR between BaBar and PEP-II
was 300 mrad. To bring the beams into collision, LER is
brought down 0.89 m to the HER level and then with
horizontal deviations for both rings the beams are made to
collide as shown in Figure 2. Since both rings have the
same circumference, each bunch in one ring collides with
only one bunch in the other ring. There are small parasitic
collision effects as the bunches separate near the
interaction point but at full currents these only reduce the
luminosity a few percent.
The luminosity in a flat beam collider is given by
where n is the number of bunches, y is the vertical beam-
beam parameter limit, E is the beam energy (GeV), Ib is
the bunch current (A), and y* is the vertical beta function
value at the collision point (cm). This equation holds for
each beam separately. These parameters for PEP-II are
shown in Table 1 with the design and best values. PEP-II
exceeded all design parameters, in particular the
luminosity by a factor of 4 and the integrated luminosity
per day by a factor of 7.
Figure 1 : PEP-II tunnel with LER above the HER.
Parameter
Units Design
April
2008
Best
Gain
Factor
over
Design
I+ mA 2140 3213 x 1.50
I- mA 750 2069 x 2.76
Number
bunches
1658 1732 x 1.04
y* mm 15-25 9-10 x 2.0
Bunch
length
mm 15 10-12 x 1.4
y 0.03
0.05 to
0.065
x 2.0
Luminosity
1034
/cm2
/s
0.3 1.2 x 4.0
Int lumin
per day
pb-1
130 911 x 7.0
*
34
1017.2
y
by EIn
xL =
TUXG01 Proceedings of EPAC08, Genoa, Italy
01 Circular Colliders
946
A02 Lepton Colliders
Figure 2 : PEP-II Interaction Region (IR) with head-on
collisions. There are four permanent magnets within the
BaBar 1.5 T solenoidal field covering +/- 2.5 m.
Figure 3 : IR double-walled Be collision chamber with
nearby water cooling and permanent magnet dipoles.
The high beam currents are supported by large RF
systems consisting of 1.2 MW klystrons at 476 MHz and
high power cavities with HOM absorbing loads. Each
cavity has three loads each with the capability of 10 kW.
A cavity is shown in Figure 4. At peak currents a HER
cavity receives on average 285 kW and the LER cavities
372 kW. The average klystron power was 1.01 MW. An
overhead of about 20% in power was needed to allow the
RF feedback systems to be stable. At high currents there
were about 3 RF trips each day. The longitudinal bunch-
by-bunch (4 nsec) feedback system is shown in Figure 5.
The bunch-by-bunch (4 nsec) transverse feedback system
is shown in Figure 6. Once tuned, these systems were
quite robust. These systems were used to measure and
feedback on beam instabilities (Figure 7). The coupled
bunch instabilities were damped up to the highest current
with some head room but the HER growth rates were
somewhat anomalous being stronger than predicted.
The vacuum systems were extruded copper in the HER
arcs and extruded aluminium with antechambers and
photon-stops in the LER arcs. Both rings had stainless
steel double walled chambers in the straight sections. The
chambers were water cooled continuously over their 2.2
km lengths due to beam heating. From beam-off to beam-
on the vacuum chambers expanded and high power
expansion bellows were needed (Figure 8).
Figure 4 : PEP-II high power copper RF cavity, water
cooled with a 500 kW ceramic window and 3 HOM loads.
Figure 5 : Bunch-by-bunch longitudinal feedback system
with an added low level (woofer) channel.
Figure 6 : Bunch-by-bunch transverse feedback system.
Figure 7 : LER longitudinal feedback damping rates with
total positron current.
Proceedings of EPAC08, Genoa, Italy TUXG01
01 Circular Colliders A02 Lepton Colliders
947
Figure 8 : Ultimate design of the PEP-II high power
expansion bellows module with sliding fingers,
compression (hold down) fingers, beam RF seals at the
ends, and water cooled HOM absorbing tiles.
BEAM-BEAM AND LUMINOSITY
The best location in the tune plane was chosen by the best
beam-beam performance. The best location was obtained
with the horizontal tune just above the half integer ~0.508
and the vertical tune around 0.574. In Figure 9 are shown
simulation luminosity contours on the x-y tune plane
indicating optimal performance near the observed best
location. Considerable but successful work was needed to
correct horizontal beta beat errors at these horizontal
tunes.
The measured luminosity versus the product of the
bunch currents is shown in Figure 10 and the specific
luminosity in Figure 11. The resulting maximum vertical
beam-beam parameters in the two rings were 0.05 to
0.065. At the highest currents with collisions, the HER
current was limited by the LER lifetime and the LER
current by HER generated IR backgrounds in the detector.
In collision an increase in the LER current also increased
its own horizontal beam size, which is not understood.
Figure 9 : Contours of simulated luminosity in the tune
plan. The best fractional tunes were 0.508 horizontally
and 0.574 vertically, generally agreeing with experiment.
Figure 10 : Luminosity versus the product of the bunch
currents. The red and green curves show luminosity in the
By-2 pattern (4 nsec) bunch spacing during routine
operation achieving a luminosity of 1.2 x 1034
. The blue
curve shows the By-4 bunch pattern (8 nsec) scaled to a
By-2 bunch pattern, indicating an increased luminosity
may have been possible in PEP-II with the By-2 pattern.
Figure 11 : Specific luminosity versus the product of the
bunch currents. The specific initially rises because of
dynamic beta effects and then falls due to beam-beam
interaction from both primary and parasitic collisions.
The parasitic beam-beam effect was only a few percent.
The blue points are By-4 pattern scaled to the By-2
pattern.
Continuous (trickle charge) injection was planned for
from the initial design phase of PEP-II. The LER was
accomplished first in November 2003 with BaBar taking
data. The HER continuous injection occured six months
later. See Figure 12 before and Figure 13 after. A 40%
increase in average integrated luminosity was achieved.
OVERALL BEAM PERFORMANCE
PEP-II was operated on five upsilon resonances with
the majority of data on the Y4S as shown in Table 2.
Figure 14 shows the total integrated luminosity of PEP-II
achieving 557.4 fb-1
. The flat regions are maintenance and
installation periods. Figure 15 shows the monthly
integrated luminosity delivered to BaBar by PEP-II. The
period of the last few months was for running on the Y2S,
Y3S, and the energy scan above the Y4S. In Figure 16 is
TUXG01 Proceedings of EPAC08, Genoa, Italy
01 Circular Colliders
948
A02 Lepton Colliders
shown the highest luminosity in each month over the life
of PEP-II. The design luminosity was achieved just over a
year into operations. The luminosity record of PEP-II of
1.2 x 1034
/cm2
/s was achieved in August 2006.
Figure 12 : Luminosity and beam currents for 24 hours
showing the fill-coast mode of PEP-II in early years.
Figure 13 : Continuous injection of both PEP-II beams.
Figure 14 : Total integrated luminosity from 1999 to
2008.
Table 2 : Operation of PEP-II on different upsilon
resonances. The remainder of the total integrated
luminosity not listed of the 557.4 fb-1
was taken as “off
resonance” data near the resonances, together totalling
about 78 fb-1
. Due to the permanent magnet IR
quadrupoles, the LER energy was not changed.
Resonance Data HER Energy
Y2S 14.5 fb-1
8.1 GeV
Y3S 30 fb-1
8.4 GeV
Y4S 433 fb-1
8.97 GeV
Y5S 0.9 fb-1
9.47 GeV
Y6S 0.8 fb-1
9.73 GeV
Figure 15 : Monthly integrated luminosity from 1999 to
2008. The best month was August 2007 with 19.7 fb-1
.
Figure 16 : Peak luminosity in a given month from 1999
to 2008. A peak luminosity of 1.21x1034
/cm2
/s was
achieved.
PEP-II PERFORMANCE
IMPROVEMENTS
All PEP-II components as designed worked to get above
the design luminosity parameters (magnets, RF system,
vacuum system, interaction region, background
mitigation, beam instabilities, bunch-by-bunch feedbacks,
injection, and controls).
Proceedings of EPAC08, Genoa, Italy TUXG01
01 Circular Colliders A02 Lepton Colliders
949
However, to get far above the design up to x 4 design
luminosity and x 7 integrated luminosity per day, several
major upgrades were done [2-13].
A) The electron cloud instability (ECI) in the LER for
e+
needed ~30 gauss solenoids on the straight section
stainless steel vacuum chambers. About 1.8 km of
solenoid was wound. This proved very successful. The
LER Arc chambers with ante-chambers, photon stops and
TiN coatings worked well against ECI as designed. In the
end, ECI did not degrade the peak luminosity.
B) The small (10 cm O.D.) expansion bellows on each
end of the IP Be chamber had to have extra air and water
cooling installed to survive the higher combined beam
currents of over 5 A.
C) The synchrotron and lost particle masking near the
detector was improved as the currents were raised.
D) Seven RF stations were added for a total of 15
stations to handle the highest beam currents in the two
rings (3.2 A x 2.1 A).
E) The feedback kickers were upgraded for both the
longitudinal and transverse systems. The new cavity style
(Frascati) longitudinal kickers worked very well.
F) As the beam currents were increased, the RF
controls were refined with modest upgrades.
G) Higher power vacuum expansion bellows went
through several designs being able to handle ever
increasing HOM powers. See Figure 8 for the best design.
H) Continuous injection needed a lot of careful work to
make it acceptable to BaBar data taking. Both the
accelerator and detector people worked together on
masking, injection control, and diagnostics.
I) The abort gap was reduced from 5% of the
circumference to about 1.6% with an improved abort
kicker pulser.
J) Nearly continuous improvements to the quadrupole
lattices were made. Tuning of the interaction region made
for better beta and dispersion control, detector solenoid
coupling correction, and minimizing vertical emittance.
K) Improved x-y coupling control was needed in the
LER to maximize the luminosity. Permanent magnet
skew quadrupoles were built and installed in very tight
locations.
L) Vertical and horizontal beta-beats in the arcs near
the IR were carefully worked to maximize the luminosity.
M) Simulation codes in 3-D were developed to
understand all the aspects of the beam-beam interaction
and tune shift limits. Good agreement with experiments
was reached in most cases.
N) Every beam abort was studied, categorized, and
analyzed offline. There were on average about 8 beam
aborts per day with about 3 from RF, 3 from unstable
beams, and 2 from detector backgrounds.
ACKNOWLEDGMENTS
The author and the PEP-II team wish to thank the
operations staff, the maintenance crews, the safety teams,
and all other supporting staff at SLAC for their hard work
and efforts. Many thanks go to the US DOE Office of
High Energy Physics for support. The two PEP-II
Machine Advisory Committees helped the project in
many ways. Our colleagues at LBNL, LLNL and Frascati
made many contributions. M. Sullivan, U. Wienands, and
T. Himel were PEP-II Run Coordinators. Y. Cai, Y. Yan,
S. Heifets, and J. Irwin led beam dynamics and lattice
calculations. R. Akre, J. Fox, D. Teytelman, C. Rivetta,
D. Van Winkle, and W. Barry led the feedback efforts. H.
Schwarz, P. McIntosh, and C. Pearson led the high power
RF efforts. R. Humphrey, R. Larsen, and P. Bellomo led
controls and power conversion. F.-J. Decker, G. Yocky,
W. Wittmer, and the operators mastered luminosity
tuning. A. Fisher excelled in beam size measurements. S.
Ecklund led the IR effort. A. Kulikov and R. Iverson
made injection work. W. Kozanecki and M. Weaver
studied backgrounds. S. DeBarger, N. Kurita, S. Metcalfe,
D. Kharakh, and L. Klaisner carried out mechanical
engineering. J. Dorfan was PEP-II project manager and
senior advisor. Many others made strong contributions.
REFERENCES
[1] “PEP-II an Asymmetric B Factory”, Conceptual
Design Report, CALT-68-1869, LBL-PUB-5379,
SLAC-418, UCRL-ID-114055, UC-IIRPA-93-01,
June 1993.
[2] J. Seeman, et. al., “PEP-II at 1.2x1034
/cm2
/s
Luminosity”, PAC 2007, pg. 37.
[3] M. Sullivan, et. al., “Results from a Prototype
Permanent Magnet Dipole-Quadrupole Hybrid for
the PEP-II B-Factory”, PAC 1997, pg. 3330.
[4] J. L. Turner, et. al., “Trickle-charge: a New
Operational Mode for PEP-II”, EPAC 2004, pg. 881.
[5] U. Wienands, et. al., “High-temperature Kicker
Electrodes for High-beam-current Operation of PEP-
II”, EPAC 2004, pg. 2843.
[6] J. D. Fox, et. al., “Development and Testing of a Low
Group-delay Woofer Channel for PEP-II”,
Proceedings of EPAC 2004, pg. 2822.
[7] P. A. McIntosh, et. al., “An Over-damped Cavity
Longitudinal Kicker for the PEP-II LER”, PAC 2003,
pg. 1341.
[8] P. A. McIntosh, et. al., “PEP-II RF System Operation
and Performance”, EPAC 2004, pg. 1087.
[9] U. Wienands, “Vacuum Performance and Beam
Lifetime in the PEP-II Storage Rings”, PAC 2001,
pg. 597.
[10]U. Wienands, et. al., “Tracking Down a Fast
Instability in the PEP-II LER”, EPAC 2006, pg. 658.
[11] M. Sullivan, et. al., “Anomalous High Radiation
Beam Aborts in the PEP-II B-factory”, EPAC 2006,
pg. 652.
[12]A. Novokhatski, et. al., “Modeling of the Sparks in
Q2-bellows of the PEP-II SLAC B-factory”, PAC07,
2007, pg. 658.
[13]A. Novokhatski, et. al., “Damping the High Order
Modes in the Pumping Chamber of the PEP-II Low
Energy Ring”, EPAC 2004, pg. 854.
TUXG01 Proceedings of EPAC08, Genoa, Italy
01 Circular Colliders
950
A02 Lepton Colliders

More Related Content

What's hot

A simple high capability c+ l broad bandwidth erbium doped fiber source
A simple high capability c+ l broad bandwidth erbium doped fiber sourceA simple high capability c+ l broad bandwidth erbium doped fiber source
A simple high capability c+ l broad bandwidth erbium doped fiber sourceNaku Technology Co,. Ltd
 
PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS
PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS
PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS jantjournal
 
Rare earth doped fibers
Rare earth doped fibersRare earth doped fibers
Rare earth doped fibersPritesh Desai
 
The effect of copper conversion plates on low-Z target image quality
The effect of copper conversion plates on low-Z target image qualityThe effect of copper conversion plates on low-Z target image quality
The effect of copper conversion plates on low-Z target image qualityDavid Parsons
 
A181 brain equivalent plastic
A181 brain equivalent plasticA181 brain equivalent plastic
A181 brain equivalent plastickent.riley
 
Seminar on uv spectroscopy
Seminar on uv spectroscopy Seminar on uv spectroscopy
Seminar on uv spectroscopy hameed momin
 
Design of Reconfigurable Microstrip Patch Antenna for WLAN Application
Design of Reconfigurable Microstrip Patch Antenna for WLAN ApplicationDesign of Reconfigurable Microstrip Patch Antenna for WLAN Application
Design of Reconfigurable Microstrip Patch Antenna for WLAN ApplicationEditor IJMTER
 
Study of multiple antennas with defected ground slot for low-band LTE applica...
Study of multiple antennas with defected ground slot for low-band LTE applica...Study of multiple antennas with defected ground slot for low-band LTE applica...
Study of multiple antennas with defected ground slot for low-band LTE applica...journalBEEI
 
Michael Ludden L3Report2016
Michael Ludden L3Report2016Michael Ludden L3Report2016
Michael Ludden L3Report2016Michael Ludden
 
ResearchStatement2016_v2
ResearchStatement2016_v2ResearchStatement2016_v2
ResearchStatement2016_v2Feng-Kuo Hsu
 

What's hot (13)

A simple high capability c+ l broad bandwidth erbium doped fiber source
A simple high capability c+ l broad bandwidth erbium doped fiber sourceA simple high capability c+ l broad bandwidth erbium doped fiber source
A simple high capability c+ l broad bandwidth erbium doped fiber source
 
PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS
PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS
PLANAR ACS FED DUAL BAND ANTENNA WITH DGS FOR WIRELESS APPLICATIONS
 
Rare earth doped fibers
Rare earth doped fibersRare earth doped fibers
Rare earth doped fibers
 
The effect of copper conversion plates on low-Z target image quality
The effect of copper conversion plates on low-Z target image qualityThe effect of copper conversion plates on low-Z target image quality
The effect of copper conversion plates on low-Z target image quality
 
Erbium-Doped Fiber Amplifier (EDFA)
Erbium-Doped Fiber Amplifier (EDFA)Erbium-Doped Fiber Amplifier (EDFA)
Erbium-Doped Fiber Amplifier (EDFA)
 
A181 brain equivalent plastic
A181 brain equivalent plasticA181 brain equivalent plastic
A181 brain equivalent plastic
 
Seminar on uv spectroscopy
Seminar on uv spectroscopy Seminar on uv spectroscopy
Seminar on uv spectroscopy
 
Raman Ampli
Raman AmpliRaman Ampli
Raman Ampli
 
Aieee model paper
Aieee  model paperAieee  model paper
Aieee model paper
 
Design of Reconfigurable Microstrip Patch Antenna for WLAN Application
Design of Reconfigurable Microstrip Patch Antenna for WLAN ApplicationDesign of Reconfigurable Microstrip Patch Antenna for WLAN Application
Design of Reconfigurable Microstrip Patch Antenna for WLAN Application
 
Study of multiple antennas with defected ground slot for low-band LTE applica...
Study of multiple antennas with defected ground slot for low-band LTE applica...Study of multiple antennas with defected ground slot for low-band LTE applica...
Study of multiple antennas with defected ground slot for low-band LTE applica...
 
Michael Ludden L3Report2016
Michael Ludden L3Report2016Michael Ludden L3Report2016
Michael Ludden L3Report2016
 
ResearchStatement2016_v2
ResearchStatement2016_v2ResearchStatement2016_v2
ResearchStatement2016_v2
 

Viewers also liked

Carrera solidaria haiti
Carrera solidaria haitiCarrera solidaria haiti
Carrera solidaria haitiBto Ruiz
 
Your Airline Here - LS Business Cases 26102016
Your Airline Here - LS Business Cases 26102016Your Airline Here - LS Business Cases 26102016
Your Airline Here - LS Business Cases 26102016Ramón Luis Pizarro Romero
 
평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방
평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방
평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방dasom0041
 
Artigo livro digital_multimidia
Artigo livro digital_multimidiaArtigo livro digital_multimidia
Artigo livro digital_multimidiaFernando Zornitta
 
Hendrik Snyman CV 2016
Hendrik Snyman CV 2016Hendrik Snyman CV 2016
Hendrik Snyman CV 2016Hendrik Snyman
 
6 c relatório ae 2p
6 c relatório ae 2p6 c relatório ae 2p
6 c relatório ae 2panabregieira
 
Así trabajamos
Así trabajamos Así trabajamos
Así trabajamos cristy011
 
Uusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisut
Uusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisutUusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisut
Uusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisutSenaatti-kiinteistöt
 
AssemblyDrawingPreacherCurl
AssemblyDrawingPreacherCurlAssemblyDrawingPreacherCurl
AssemblyDrawingPreacherCurlPatrick Barroso
 
Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016
Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016
Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016Ramón Luis Pizarro Romero
 
20150423 配布資料(学生アンケート中間報告)
20150423 配布資料(学生アンケート中間報告)20150423 配布資料(学生アンケート中間報告)
20150423 配布資料(学生アンケート中間報告)UT_Semester
 
The Agency Response, Digiday WTF VR, May 11th, 2016
The Agency Response, Digiday WTF VR, May 11th, 2016The Agency Response, Digiday WTF VR, May 11th, 2016
The Agency Response, Digiday WTF VR, May 11th, 2016Digiday
 
UX Alive Conference speaker is Sophie Kleber (Huge) presentations
UX Alive Conference speaker is Sophie Kleber (Huge) presentationsUX Alive Conference speaker is Sophie Kleber (Huge) presentations
UX Alive Conference speaker is Sophie Kleber (Huge) presentationsUX Alive Conference
 
Didactica de orledys martinez
Didactica de orledys martinezDidactica de orledys martinez
Didactica de orledys martinezorledys martinez
 
Congestion Charge - polskie uwarunkowania prawne
Congestion Charge - polskie uwarunkowania prawneCongestion Charge - polskie uwarunkowania prawne
Congestion Charge - polskie uwarunkowania prawneAneta Wrobel
 

Viewers also liked (17)

Carrera solidaria haiti
Carrera solidaria haitiCarrera solidaria haiti
Carrera solidaria haiti
 
Your Airline Here - LS Business Cases 26102016
Your Airline Here - LS Business Cases 26102016Your Airline Here - LS Business Cases 26102016
Your Airline Here - LS Business Cases 26102016
 
평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방
평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방
평촌오피.부평오피≒다솜넷≒분당오피걸.부평오피방
 
Artigo livro digital_multimidia
Artigo livro digital_multimidiaArtigo livro digital_multimidia
Artigo livro digital_multimidia
 
Hendrik Snyman CV 2016
Hendrik Snyman CV 2016Hendrik Snyman CV 2016
Hendrik Snyman CV 2016
 
6 c relatório ae 2p
6 c relatório ae 2p6 c relatório ae 2p
6 c relatório ae 2p
 
Presentazione istituzionale
Presentazione istituzionalePresentazione istituzionale
Presentazione istituzionale
 
Así trabajamos
Así trabajamos Así trabajamos
Así trabajamos
 
Uusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisut
Uusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisutUusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisut
Uusi tapa tehdä töitä - Palveluja tukevat joustavat ratkaisut
 
AssemblyDrawingPreacherCurl
AssemblyDrawingPreacherCurlAssemblyDrawingPreacherCurl
AssemblyDrawingPreacherCurl
 
Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016
Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016
Ciencia de Datos para Directivos y Ejecutivos RLPR - HAV 08092016
 
20150423 配布資料(学生アンケート中間報告)
20150423 配布資料(学生アンケート中間報告)20150423 配布資料(学生アンケート中間報告)
20150423 配布資料(学生アンケート中間報告)
 
PistonAssembly
PistonAssemblyPistonAssembly
PistonAssembly
 
The Agency Response, Digiday WTF VR, May 11th, 2016
The Agency Response, Digiday WTF VR, May 11th, 2016The Agency Response, Digiday WTF VR, May 11th, 2016
The Agency Response, Digiday WTF VR, May 11th, 2016
 
UX Alive Conference speaker is Sophie Kleber (Huge) presentations
UX Alive Conference speaker is Sophie Kleber (Huge) presentationsUX Alive Conference speaker is Sophie Kleber (Huge) presentations
UX Alive Conference speaker is Sophie Kleber (Huge) presentations
 
Didactica de orledys martinez
Didactica de orledys martinezDidactica de orledys martinez
Didactica de orledys martinez
 
Congestion Charge - polskie uwarunkowania prawne
Congestion Charge - polskie uwarunkowania prawneCongestion Charge - polskie uwarunkowania prawne
Congestion Charge - polskie uwarunkowania prawne
 

Similar to SLAC last year of PEP-II B-Factory

Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...researchinventy
 
Communication Engineering LED and LASER Sources.ppt
Communication Engineering LED and LASER Sources.pptCommunication Engineering LED and LASER Sources.ppt
Communication Engineering LED and LASER Sources.pptMdYekraRahman1
 
The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...
The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...
The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...IJECEIAES
 
Reflectance and photoluminescence characterization of BexZn1
Reflectance and photoluminescence characterization of BexZn1Reflectance and photoluminescence characterization of BexZn1
Reflectance and photoluminescence characterization of BexZn1Oleg Maksimov
 
Optical control of resonant light transmission for an atom-cavity system_Arij...
Optical control of resonant light transmission for an atom-cavity system_Arij...Optical control of resonant light transmission for an atom-cavity system_Arij...
Optical control of resonant light transmission for an atom-cavity system_Arij...Arijit Sharma
 
Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...
Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...
Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...IOSR Journals
 
Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...
Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...
Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...IOSR Journals
 
Advances in energy harvesting methods
Advances in energy harvesting methodsAdvances in energy harvesting methods
Advances in energy harvesting methodsSpringer
 
Andrea Rossi - S.Focardi Paper
Andrea Rossi - S.Focardi PaperAndrea Rossi - S.Focardi Paper
Andrea Rossi - S.Focardi Paperandrea-rossi
 

Similar to SLAC last year of PEP-II B-Factory (20)

Seeman1 (1).ppt
Seeman1 (1).pptSeeman1 (1).ppt
Seeman1 (1).ppt
 
Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...
 
wep153
wep153wep153
wep153
 
Communication Engineering LED and LASER Sources.ppt
Communication Engineering LED and LASER Sources.pptCommunication Engineering LED and LASER Sources.ppt
Communication Engineering LED and LASER Sources.ppt
 
The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...
The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...
The Effects of Nano Fillers on Space Charge Distribution in Cross-Linked Poly...
 
Reflectance and photoluminescence characterization of BexZn1
Reflectance and photoluminescence characterization of BexZn1Reflectance and photoluminescence characterization of BexZn1
Reflectance and photoluminescence characterization of BexZn1
 
Optical control of resonant light transmission for an atom-cavity system_Arij...
Optical control of resonant light transmission for an atom-cavity system_Arij...Optical control of resonant light transmission for an atom-cavity system_Arij...
Optical control of resonant light transmission for an atom-cavity system_Arij...
 
Final Paper
Final PaperFinal Paper
Final Paper
 
Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...
Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...
Design, Electrostatic and Eigen Frequency Analysis of Fixed–Fixed Beam MEMS R...
 
Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...
Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...
Design, Electrostatic and Eigen Frequency Analysis of Fixed– Fixed Beam MEMS ...
 
Ferro2016
Ferro2016Ferro2016
Ferro2016
 
IAC-15.B2.5.1_paper
IAC-15.B2.5.1_paperIAC-15.B2.5.1_paper
IAC-15.B2.5.1_paper
 
Advances in energy harvesting methods
Advances in energy harvesting methodsAdvances in energy harvesting methods
Advances in energy harvesting methods
 
3 p8 1518
3 p8 15183 p8 1518
3 p8 1518
 
A05620105
A05620105A05620105
A05620105
 
Application and Comparison Between the Conventional Methods and PSO Method fo...
Application and Comparison Between the Conventional Methods and PSO Method fo...Application and Comparison Between the Conventional Methods and PSO Method fo...
Application and Comparison Between the Conventional Methods and PSO Method fo...
 
Rossi focardi paper (1)
Rossi focardi paper (1)Rossi focardi paper (1)
Rossi focardi paper (1)
 
Andrea Rossi - S.Focardi Paper
Andrea Rossi - S.Focardi PaperAndrea Rossi - S.Focardi Paper
Andrea Rossi - S.Focardi Paper
 
36.12122507 (1)
36.12122507 (1)36.12122507 (1)
36.12122507 (1)
 
36.12122507
36.1212250736.12122507
36.12122507
 

More from John D. Gracia

Account Roadmap Summary
Account Roadmap SummaryAccount Roadmap Summary
Account Roadmap SummaryJohn D. Gracia
 
SI engagement guidelines 4of5
SI engagement guidelines 4of5SI engagement guidelines 4of5
SI engagement guidelines 4of5John D. Gracia
 
SI engagement guidelines 5of5
SI engagement guidelines 5of5SI engagement guidelines 5of5
SI engagement guidelines 5of5John D. Gracia
 
SI engagement guidelines 3of5
SI engagement guidelines 3of5SI engagement guidelines 3of5
SI engagement guidelines 3of5John D. Gracia
 
SI engagement guidelines 2of5
SI engagement guidelines 2of5SI engagement guidelines 2of5
SI engagement guidelines 2of5John D. Gracia
 
SI engagement guidelines 1of5
SI engagement guidelines 1of5SI engagement guidelines 1of5
SI engagement guidelines 1of5John D. Gracia
 
sextupole magnet assembly
sextupole magnet assemblysextupole magnet assembly
sextupole magnet assemblyJohn D. Gracia
 
sextupole core design paper 2of2
sextupole core design paper 2of2sextupole core design paper 2of2
sextupole core design paper 2of2John D. Gracia
 
sextupole core design paper 1of2
sextupole core design paper 1of2sextupole core design paper 1of2
sextupole core design paper 1of2John D. Gracia
 

More from John D. Gracia (9)

Account Roadmap Summary
Account Roadmap SummaryAccount Roadmap Summary
Account Roadmap Summary
 
SI engagement guidelines 4of5
SI engagement guidelines 4of5SI engagement guidelines 4of5
SI engagement guidelines 4of5
 
SI engagement guidelines 5of5
SI engagement guidelines 5of5SI engagement guidelines 5of5
SI engagement guidelines 5of5
 
SI engagement guidelines 3of5
SI engagement guidelines 3of5SI engagement guidelines 3of5
SI engagement guidelines 3of5
 
SI engagement guidelines 2of5
SI engagement guidelines 2of5SI engagement guidelines 2of5
SI engagement guidelines 2of5
 
SI engagement guidelines 1of5
SI engagement guidelines 1of5SI engagement guidelines 1of5
SI engagement guidelines 1of5
 
sextupole magnet assembly
sextupole magnet assemblysextupole magnet assembly
sextupole magnet assembly
 
sextupole core design paper 2of2
sextupole core design paper 2of2sextupole core design paper 2of2
sextupole core design paper 2of2
 
sextupole core design paper 1of2
sextupole core design paper 1of2sextupole core design paper 1of2
sextupole core design paper 1of2
 

SLAC last year of PEP-II B-Factory

  • 1. LAST YEAR OF PEP-II B-FACTORY OPERATION* J. T. Seeman, SLAC, Menlo Park, CA 94025 USA Abstract The PEP-II B-Factory [1] at SLAC (3.1 GeV e+ x 9.0 GeV e- ) operated from 1999 to 2008, delivering luminosity to the BaBar experiment. The design luminosity was reached after one and a half years of operation. In the end PEP-II surpassed by four times its design luminosity reaching 1.21 x 1034 cm-2 s-1 . It also set stored beam current records of 2.1 A e- and 3.2 A e+ . Continuous injection was implemented with BaBar taking data. The total delivered luminosity to the BaBar detector was 557.4 fb-1 spanning five upsilon resonances. PEP-II was constructed by SLAC, LBNL, and LLNL with help from BINP, IHEP, the BaBar collaboration, and the US DOE OHEP. PEP-II TIMELINE 1987: Particle physicists determine that asymmetrical beam energies are preferred. 1991: First PEP-II CDR. 1993: Second PEP-II CDR. 1994: Construction started 1997: First HER stored beam 6:30 am June 5. 1998: First LER stored beam 2:49 am July 16. 1998: First collisions 12:05 pm July 23. 1999: BaBar placed on beam line in May. 1999-2008: Collisions for BaBar. 2000: Design luminosity achieved (3x1033 ) Oct. 29. 2006: Luminosity 1.2x1034 achieved 8 pm Aug. 17. 2008: PEP-II turned off 23:22 pm April 7. Table 1 : PEP-II Collision Parameters *Supported by US DOE contract DE-AC02-76SF00515. † seeman@slac.stanford.edu PEP-II PARAMETERS In PEP-II the Low Energy Ring (LER) is mounted 0.89 m above the High Energy Ring (HER) in the 2.2 km tunnel as shown in Figure 1. The interaction region is shown in Figure 2 where the beams are collided head on. Figure 3 shows the Be vacuum chamber inside the detector with the permanent magnet dipoles on either side. The interface cone angle at the IR between BaBar and PEP-II was 300 mrad. To bring the beams into collision, LER is brought down 0.89 m to the HER level and then with horizontal deviations for both rings the beams are made to collide as shown in Figure 2. Since both rings have the same circumference, each bunch in one ring collides with only one bunch in the other ring. There are small parasitic collision effects as the bunches separate near the interaction point but at full currents these only reduce the luminosity a few percent. The luminosity in a flat beam collider is given by where n is the number of bunches, y is the vertical beam- beam parameter limit, E is the beam energy (GeV), Ib is the bunch current (A), and y* is the vertical beta function value at the collision point (cm). This equation holds for each beam separately. These parameters for PEP-II are shown in Table 1 with the design and best values. PEP-II exceeded all design parameters, in particular the luminosity by a factor of 4 and the integrated luminosity per day by a factor of 7. Figure 1 : PEP-II tunnel with LER above the HER. Parameter Units Design April 2008 Best Gain Factor over Design I+ mA 2140 3213 x 1.50 I- mA 750 2069 x 2.76 Number bunches 1658 1732 x 1.04 y* mm 15-25 9-10 x 2.0 Bunch length mm 15 10-12 x 1.4 y 0.03 0.05 to 0.065 x 2.0 Luminosity 1034 /cm2 /s 0.3 1.2 x 4.0 Int lumin per day pb-1 130 911 x 7.0 * 34 1017.2 y by EIn xL = TUXG01 Proceedings of EPAC08, Genoa, Italy 01 Circular Colliders 946 A02 Lepton Colliders
  • 2. Figure 2 : PEP-II Interaction Region (IR) with head-on collisions. There are four permanent magnets within the BaBar 1.5 T solenoidal field covering +/- 2.5 m. Figure 3 : IR double-walled Be collision chamber with nearby water cooling and permanent magnet dipoles. The high beam currents are supported by large RF systems consisting of 1.2 MW klystrons at 476 MHz and high power cavities with HOM absorbing loads. Each cavity has three loads each with the capability of 10 kW. A cavity is shown in Figure 4. At peak currents a HER cavity receives on average 285 kW and the LER cavities 372 kW. The average klystron power was 1.01 MW. An overhead of about 20% in power was needed to allow the RF feedback systems to be stable. At high currents there were about 3 RF trips each day. The longitudinal bunch- by-bunch (4 nsec) feedback system is shown in Figure 5. The bunch-by-bunch (4 nsec) transverse feedback system is shown in Figure 6. Once tuned, these systems were quite robust. These systems were used to measure and feedback on beam instabilities (Figure 7). The coupled bunch instabilities were damped up to the highest current with some head room but the HER growth rates were somewhat anomalous being stronger than predicted. The vacuum systems were extruded copper in the HER arcs and extruded aluminium with antechambers and photon-stops in the LER arcs. Both rings had stainless steel double walled chambers in the straight sections. The chambers were water cooled continuously over their 2.2 km lengths due to beam heating. From beam-off to beam- on the vacuum chambers expanded and high power expansion bellows were needed (Figure 8). Figure 4 : PEP-II high power copper RF cavity, water cooled with a 500 kW ceramic window and 3 HOM loads. Figure 5 : Bunch-by-bunch longitudinal feedback system with an added low level (woofer) channel. Figure 6 : Bunch-by-bunch transverse feedback system. Figure 7 : LER longitudinal feedback damping rates with total positron current. Proceedings of EPAC08, Genoa, Italy TUXG01 01 Circular Colliders A02 Lepton Colliders 947
  • 3. Figure 8 : Ultimate design of the PEP-II high power expansion bellows module with sliding fingers, compression (hold down) fingers, beam RF seals at the ends, and water cooled HOM absorbing tiles. BEAM-BEAM AND LUMINOSITY The best location in the tune plane was chosen by the best beam-beam performance. The best location was obtained with the horizontal tune just above the half integer ~0.508 and the vertical tune around 0.574. In Figure 9 are shown simulation luminosity contours on the x-y tune plane indicating optimal performance near the observed best location. Considerable but successful work was needed to correct horizontal beta beat errors at these horizontal tunes. The measured luminosity versus the product of the bunch currents is shown in Figure 10 and the specific luminosity in Figure 11. The resulting maximum vertical beam-beam parameters in the two rings were 0.05 to 0.065. At the highest currents with collisions, the HER current was limited by the LER lifetime and the LER current by HER generated IR backgrounds in the detector. In collision an increase in the LER current also increased its own horizontal beam size, which is not understood. Figure 9 : Contours of simulated luminosity in the tune plan. The best fractional tunes were 0.508 horizontally and 0.574 vertically, generally agreeing with experiment. Figure 10 : Luminosity versus the product of the bunch currents. The red and green curves show luminosity in the By-2 pattern (4 nsec) bunch spacing during routine operation achieving a luminosity of 1.2 x 1034 . The blue curve shows the By-4 bunch pattern (8 nsec) scaled to a By-2 bunch pattern, indicating an increased luminosity may have been possible in PEP-II with the By-2 pattern. Figure 11 : Specific luminosity versus the product of the bunch currents. The specific initially rises because of dynamic beta effects and then falls due to beam-beam interaction from both primary and parasitic collisions. The parasitic beam-beam effect was only a few percent. The blue points are By-4 pattern scaled to the By-2 pattern. Continuous (trickle charge) injection was planned for from the initial design phase of PEP-II. The LER was accomplished first in November 2003 with BaBar taking data. The HER continuous injection occured six months later. See Figure 12 before and Figure 13 after. A 40% increase in average integrated luminosity was achieved. OVERALL BEAM PERFORMANCE PEP-II was operated on five upsilon resonances with the majority of data on the Y4S as shown in Table 2. Figure 14 shows the total integrated luminosity of PEP-II achieving 557.4 fb-1 . The flat regions are maintenance and installation periods. Figure 15 shows the monthly integrated luminosity delivered to BaBar by PEP-II. The period of the last few months was for running on the Y2S, Y3S, and the energy scan above the Y4S. In Figure 16 is TUXG01 Proceedings of EPAC08, Genoa, Italy 01 Circular Colliders 948 A02 Lepton Colliders
  • 4. shown the highest luminosity in each month over the life of PEP-II. The design luminosity was achieved just over a year into operations. The luminosity record of PEP-II of 1.2 x 1034 /cm2 /s was achieved in August 2006. Figure 12 : Luminosity and beam currents for 24 hours showing the fill-coast mode of PEP-II in early years. Figure 13 : Continuous injection of both PEP-II beams. Figure 14 : Total integrated luminosity from 1999 to 2008. Table 2 : Operation of PEP-II on different upsilon resonances. The remainder of the total integrated luminosity not listed of the 557.4 fb-1 was taken as “off resonance” data near the resonances, together totalling about 78 fb-1 . Due to the permanent magnet IR quadrupoles, the LER energy was not changed. Resonance Data HER Energy Y2S 14.5 fb-1 8.1 GeV Y3S 30 fb-1 8.4 GeV Y4S 433 fb-1 8.97 GeV Y5S 0.9 fb-1 9.47 GeV Y6S 0.8 fb-1 9.73 GeV Figure 15 : Monthly integrated luminosity from 1999 to 2008. The best month was August 2007 with 19.7 fb-1 . Figure 16 : Peak luminosity in a given month from 1999 to 2008. A peak luminosity of 1.21x1034 /cm2 /s was achieved. PEP-II PERFORMANCE IMPROVEMENTS All PEP-II components as designed worked to get above the design luminosity parameters (magnets, RF system, vacuum system, interaction region, background mitigation, beam instabilities, bunch-by-bunch feedbacks, injection, and controls). Proceedings of EPAC08, Genoa, Italy TUXG01 01 Circular Colliders A02 Lepton Colliders 949
  • 5. However, to get far above the design up to x 4 design luminosity and x 7 integrated luminosity per day, several major upgrades were done [2-13]. A) The electron cloud instability (ECI) in the LER for e+ needed ~30 gauss solenoids on the straight section stainless steel vacuum chambers. About 1.8 km of solenoid was wound. This proved very successful. The LER Arc chambers with ante-chambers, photon stops and TiN coatings worked well against ECI as designed. In the end, ECI did not degrade the peak luminosity. B) The small (10 cm O.D.) expansion bellows on each end of the IP Be chamber had to have extra air and water cooling installed to survive the higher combined beam currents of over 5 A. C) The synchrotron and lost particle masking near the detector was improved as the currents were raised. D) Seven RF stations were added for a total of 15 stations to handle the highest beam currents in the two rings (3.2 A x 2.1 A). E) The feedback kickers were upgraded for both the longitudinal and transverse systems. The new cavity style (Frascati) longitudinal kickers worked very well. F) As the beam currents were increased, the RF controls were refined with modest upgrades. G) Higher power vacuum expansion bellows went through several designs being able to handle ever increasing HOM powers. See Figure 8 for the best design. H) Continuous injection needed a lot of careful work to make it acceptable to BaBar data taking. Both the accelerator and detector people worked together on masking, injection control, and diagnostics. I) The abort gap was reduced from 5% of the circumference to about 1.6% with an improved abort kicker pulser. J) Nearly continuous improvements to the quadrupole lattices were made. Tuning of the interaction region made for better beta and dispersion control, detector solenoid coupling correction, and minimizing vertical emittance. K) Improved x-y coupling control was needed in the LER to maximize the luminosity. Permanent magnet skew quadrupoles were built and installed in very tight locations. L) Vertical and horizontal beta-beats in the arcs near the IR were carefully worked to maximize the luminosity. M) Simulation codes in 3-D were developed to understand all the aspects of the beam-beam interaction and tune shift limits. Good agreement with experiments was reached in most cases. N) Every beam abort was studied, categorized, and analyzed offline. There were on average about 8 beam aborts per day with about 3 from RF, 3 from unstable beams, and 2 from detector backgrounds. ACKNOWLEDGMENTS The author and the PEP-II team wish to thank the operations staff, the maintenance crews, the safety teams, and all other supporting staff at SLAC for their hard work and efforts. Many thanks go to the US DOE Office of High Energy Physics for support. The two PEP-II Machine Advisory Committees helped the project in many ways. Our colleagues at LBNL, LLNL and Frascati made many contributions. M. Sullivan, U. Wienands, and T. Himel were PEP-II Run Coordinators. Y. Cai, Y. Yan, S. Heifets, and J. Irwin led beam dynamics and lattice calculations. R. Akre, J. Fox, D. Teytelman, C. Rivetta, D. Van Winkle, and W. Barry led the feedback efforts. H. Schwarz, P. McIntosh, and C. Pearson led the high power RF efforts. R. Humphrey, R. Larsen, and P. Bellomo led controls and power conversion. F.-J. Decker, G. Yocky, W. Wittmer, and the operators mastered luminosity tuning. A. Fisher excelled in beam size measurements. S. Ecklund led the IR effort. A. Kulikov and R. Iverson made injection work. W. Kozanecki and M. Weaver studied backgrounds. S. DeBarger, N. Kurita, S. Metcalfe, D. Kharakh, and L. Klaisner carried out mechanical engineering. J. Dorfan was PEP-II project manager and senior advisor. Many others made strong contributions. REFERENCES [1] “PEP-II an Asymmetric B Factory”, Conceptual Design Report, CALT-68-1869, LBL-PUB-5379, SLAC-418, UCRL-ID-114055, UC-IIRPA-93-01, June 1993. [2] J. Seeman, et. al., “PEP-II at 1.2x1034 /cm2 /s Luminosity”, PAC 2007, pg. 37. [3] M. Sullivan, et. al., “Results from a Prototype Permanent Magnet Dipole-Quadrupole Hybrid for the PEP-II B-Factory”, PAC 1997, pg. 3330. [4] J. L. Turner, et. al., “Trickle-charge: a New Operational Mode for PEP-II”, EPAC 2004, pg. 881. [5] U. Wienands, et. al., “High-temperature Kicker Electrodes for High-beam-current Operation of PEP- II”, EPAC 2004, pg. 2843. [6] J. D. Fox, et. al., “Development and Testing of a Low Group-delay Woofer Channel for PEP-II”, Proceedings of EPAC 2004, pg. 2822. [7] P. A. McIntosh, et. al., “An Over-damped Cavity Longitudinal Kicker for the PEP-II LER”, PAC 2003, pg. 1341. [8] P. A. McIntosh, et. al., “PEP-II RF System Operation and Performance”, EPAC 2004, pg. 1087. [9] U. Wienands, “Vacuum Performance and Beam Lifetime in the PEP-II Storage Rings”, PAC 2001, pg. 597. [10]U. Wienands, et. al., “Tracking Down a Fast Instability in the PEP-II LER”, EPAC 2006, pg. 658. [11] M. Sullivan, et. al., “Anomalous High Radiation Beam Aborts in the PEP-II B-factory”, EPAC 2006, pg. 652. [12]A. Novokhatski, et. al., “Modeling of the Sparks in Q2-bellows of the PEP-II SLAC B-factory”, PAC07, 2007, pg. 658. [13]A. Novokhatski, et. al., “Damping the High Order Modes in the Pumping Chamber of the PEP-II Low Energy Ring”, EPAC 2004, pg. 854. TUXG01 Proceedings of EPAC08, Genoa, Italy 01 Circular Colliders 950 A02 Lepton Colliders