SlideShare a Scribd company logo
1 of 35
1
MODELLING AND MANAGING STAKEHOLDER’S
POWER AND INFLUENCE FOR QUALITY
IMPROVEMENT IN CONSTRUCTION PROJECTS
A CASE STUDY AT “JAIPUR METRO”
MODELLING AND MANAGING
STAKEHOLDER’S POWER AND INFLUENCE
FOR QUALITY IMPROVEMENT IN
CONSTRUCTION PROJECTS
A CASE STUDY AT “JAIPUR METRO”
PRESENTED BY:
SHIV KUMAR S.
Assistant Professor
Musaliar College of Engg. & Technology
Owner : Jaipur Metro Rail Corporation Limited (JMRCL)
Client : Delhi Metro Rail Corporation Limited (DMRC)
Type of Project : Design and Build
Scope of Work : Approach Tunnel, Open Ramp Portion and Underground Chandpole Metro
Station by Cut & Cover Method
Original Contract Price : Rs. 101.85 Crore
Revised / assessed Price: Rs. 95.41 Crore
Project Length : 529.476 meter
Revised Project Length : 502 meter
Contract Period : 24 month
Commencement date : 19th November 2010
Intended Completion date : 18th November 2012
Price Adjustment : Yes (Labour, Steel, Cement, Fuel & Machinery/Machine tools)
Liquidated Damages : 0.005% / day for Key dates and 0.05% / day Completion of works, max.10 % of CP.
Defects Liability Period 52 week
Project Salient Features
PACKAGE DESCRIPTION OF
WORK
WORK ALLOTED TO
COMPANIES
C1 Construction of Elevated Way
Duct for approximately 6km
round
DSC Limited
C2 Construction of Four Way
BRTS Corridor extending up to
4.5km, Construction of Way
Duct for 2.5km
ITD-ITD CEM JV
C3 Construction of underground
station at Chandpole
ITD Cementation India
Limited
6
PACKAGE DESCRIPTION OF
WORK
WORK ALLOTED TO
COMPANIES
C4 Construction of the
maintenance yard for vehicles
Prathibha Consitium
C5 Construction of Way Duct of
Two-lane for 2.5 km
ITD-ITD CEM JV
C6 Construction of 6 elevated
stations at Mansarovar,Atish
Market,Ram Nagar,Civil Lines,
Ajmer Pulia,Vivek Vihar
B L Kashyap & Sons
C7 Construction of two Metro
stations- Sindhi camp Bus
stand, and at Railway station
KMV Projects
7
C3 Office
C3 Staff Mess
Jaipur Railway Station
Chandpole
Station
Project
Start Point
Project
End Point
10
INTRODUCTION
• The interactions and interrelationships between stakeholders largely determine the
overall performance of a construction project, and have the crucial responsibility for
delivering a project to successful completion.
• Successful completion of construction projects is dependent on meeting the
expectation of stakeholders throughout the project life cycle.
• The failure of project management teams to address the concerns of construction
project stakeholders has resulted in countless project failures, primarily because
construction stakeholders have the resources and capability to stop construction
projects.
• Thus, it is important to analyze, identify and manage stakeholder interests and
relationships.
11
WHO IS STAKEHOLDER?
 STAKE:
Stake is an interest or a share in an undertaking.
 STAKEHOLDER:
 An individual with a stake.
 Any person, group or organization who can be positively or negatively
impacted by, or cause an impact on, the actions or activities proposed.
 TYPES OF STAKEHOLDERS :
Stakeholders can be divided into internal stakeholders and external stakeholders
• Internal stakeholders being those directly involved in an organization’s decision-
making process (e.g. owners, customers, suppliers, employees)
• External stakeholders being those affected by the organization’s activities in a
significant way (e.g. neighbours, local community, general public, local authorities).
12
STAKEHOLDERS MANAGEMENT
 Analysis of 334 stakeholders involved directly to the project (Internal
stakeholders only).
 73 Stakeholders in company, 261 Stakeholders involved in sub-contractors.
 List of sub-contractors (sub-contract given by the company).
 Soma Construction Limited (7 Engineers, 105 Labours).
 Desai Projects Private Limited (5 Supervisors, 86 Labours).
 Bhoorathnom Construction (P) Ltd (3 Supervisors, 30 Labours).
 Valecha Engineering Limited (3 Supervisors , 22 Labours).
13
STAKEHOLDERS MANAGEMENT
(CONT…)
An important component of stakeholder management is stakeholder analysis.
The study includes:
 A case study at Jaipur Metro C3 Package.
 Analysis of 334 Stakeholders.
 Questionnaire , Interviews , Emailing ,Telephonic conversation etc.
 Attitude, Power, Interest level.
 Datas will be stored for engaging the stakeholders using Project
Stakeholder Organize Deluxe software 3.7.
14
COMPANIES UNDER C3 PACKAGE
 Soma Construction Limited and Valecha Engineering Limited.
 Construction of Diaphram walls.
 Construction of Roof Slab level (Piling done for columns at 12m depths).
 Construction for tunnels (Top-down method).
 Construction of Sidewalks.
 137 Stakeholders are involved.
15
COMPANIES UNDER C3 PACKAGE
 Desai Projects (P) Ltd and Bhoorathnom Construction Company (P)
Ltd.
 Construction of Main Station building.
 Construction of Generator room , Water tank ,Diesel generator room,
ESR room, Electrical Panel room, UPS room( Concrete blocks – 0.25 x
0.25 x 0.15).
 Construction for Ramp (Raft-10m ,1m each working space , 1.2m c/c
shoulder piling).
 124 Stakeholders are involved.
16
PROCEDURES INVOLVED IN THE
STUDY
The main procedures involved in this study are:
Identifying the stakeholders.
 Prioritize the stakeholders.
 Understand the Key stakeholders.
 Managing the stakeholders.
18
IDENTIFYING STAKEHOLDERS
 Identifying stakeholders requires a good deal of research.
 Listing of stakeholders.
19
PRIORITIZE THE STAKEHOLDERS
 Once the list of names has been generated , analyse the list in terms of
power, influence and the extent to which they are affected by the project.
 Questionnaire were prepared seperately for different stakeholders along
with different question codes for getting more accurate result.
 Out of 334 stakeholders, 246 gave response , on the basis of which the
stakeholders are prioritize into four sector table as shown.
 Prioritization Chart has been prepared.
20
High power
Satisfy
Opinion formers. Keep them
satisfied with what is happening and
review your analysis of their
position regularly.
Manage
Key stakeholders who should be fully
engaged through full communication and
consultation.
Low power
Monitor
This group may be ignored if time
and resources are stretched.
Inform
Patients often fall into this category. It may
be helpful to take steps to increase their
influence by organizing them into groups or
taking active consultative work.
Low impact/stake holding High impact/stake holding
21
UNDERSTAND THE KEY
STAKEHOLDERS
 Talk to stakeholders directly.
 Key Stakeholders can be summarized on the Stakeholder map.
 A good way of doing this is by color coding.
 Supporters in green, blockers and critics in red, and others who are
neutral in orange.
22
23
MANAGING THE STAKEHOLDERS
 After identifying all the Key Stakeholders, who are the threats and who are
in favour of the project has to be managed using PROJECT
STAKEHOLDER ORGANIZE DELUXE 3.7 software.
 The identified key stakeholders are entered, organized and managed using
stakeholder organize deluxe software, considering the data’s collected
from the project execution team.
 Project Stakeholder Organize Deluxe 3.7 is simple database management
software that helps us to enter, organize, and manage our project
stakeholders.
24
Examples of stakeholder analysis using Project
Stakeholders Organize Deluxe Software
STAKEHOLDER VIVEK KHARIYA
IDNR 103
COMPANY ITD CEMENTATION INDIA PRIVATE
LIMITED
STATUS Active
POSITION Project Manager
TYPE Organization
CATEGORY ProjectTeam
PHONE1
PHTYPE1
PHONE2
PHTYPE2
EMAIL vivek2000@gmail.com
WEB 25
Examples of stakeholder analysis using Project
Stakeholders Organize Deluxe Software
CONTACT
ADDRESS1 28-C, SECTOR-5
ADDRESS2 CIVIL LANES
CITY JAIPUR
STATEPROV RAJASTHAN
ZIPPOSTAL
COUNTRY INDIA
COMMENTS Good attitude and influence level. Enthusiastic
in work.
HOWTOMANAGE Manage Closely
IMPORTANT
POWERLEVEL1 5-VeryHigh
INTERESTLEVEL1 5-VeryHigh 26
Examples of stakeholder analysis using Project
Stakeholders Organize Deluxe Software
ATTITUDELEVEL1 4-Supporter
POWERLEVEL2 04
INTERESTLEVEL2 04
ATTITUDELEVEL2 04
CUSTOM1
note
EVALUATIONNOTES Fully satisfied in the work
NOTES date note
LOG 16-01-2012 Entry date of details
27
INFERENCE OF THE PROJECT
 On the basis of the detailed study conducted on the stakeholders engaged
under C3 Package of construction of underground station at Chandpole of
Jaipur Metro, it has been concluded that out of 334 stakeholders only 246
gave their responses (ie,73.65%) and it was observed that 116 of them had
a positive temperament while 83 were neutral which can also be visioned
has a positive outlook to the project.
 47 out of 246 were blockers and had various issues which could be
resolved by the company.
 The overall inference is that 199 (116+83) out of 246 is approximately
81% is definitely positive and hence the project can be deemed as a
success.
28
CONCLUSION
 The pros and cons of this project was that it is an almost-perfect analysis of
employee satisfaction of any company and is beneficial in overall administration
of the same.
 This study must be carried out so as to tackle various employee related problems
and to ensure utmost stakeholder satisfaction.
 On the contrary, this study has a major disadvantage ie, it is very time
consuming. If it was to be conducted on the entire project it would have been a
humongous if not an impossible task.
29
SAMPLE QUESTIONNAIRES FOR
ANALYSIS
Q.1. What is your total experience in this field?
less than 5 years
5 to 10 years
more than 10 years
Q.2. For how many years are you working with Company?
Less than 2 years
2-5 years
5-10 years
Q.3. Do you think that you have work load?
Yes No
Q.4. Is the superior friendly to you?
Yes No
Q.5. Do you think that your work is carried out properly?
Yes No
Q.6. Do you think that your labours are working according to your directions and control?
Yes No
30
SAMPLE QUESTIONNAIRES FOR
ANALYSIS
Q.7. Are you satisfied with the company’s submission of drawings at proper time?
Yes No
Q.8. Is there any lag in the work ?
Yes No
Q.9. Do you think that the manpower and equipment provided to you is sufficient to finish the task?
Yes No
Q.10. How many labours have been supervised by you?
Upto 10
between 10 to 30
between 30 to 50
Q.11. Do you think that the present state of work can be improved ?
Yes No
31
SAMPLE QUESTIONNAIRES FOR
ANALYSIS
Q.12. Which factor according to you is the best for improving the state of work?
improving the pay scale of supervisor
giving supervisors more power
conducting seminar to improve quality
Q.13. What is the working hour for you?
8 hours
8-10 hours
more than 10 hours
Q.14. Are you provided with the facility of overtime?
Yes No
Q.15. How many casual leaves are allotted to you monthly?
less than 2
2-3 days
3-4 days
None
32
SAMPLE QUESTIONNAIRES FOR
ANALYSIS
Q.16. According to you ,Is there any thing the company can do to improve your work satisfaction
level?
Yes No
Q.17. If yes, the change has to be made in which field ?
Work incentive
Better inter-relation with higher officials
Better working condition
Opportunity for growth
Q.18. According to you , the working environment for you is :
Good
Poor
Satisfactory
Q.19.Do you think that the co-workers are doing their work properly?
Yes No
Q.20. Do you think that any decision made by you is appreciated by company?
Yes No
33
REFERENCES
• Freeman, R.E. (1984) Strategic Management: A Stakeholder Approach, Pitman
Publishing Inc., Boston .
• Freeman, R.E. (1999) Divergent stakeholder theory. Academy of Management Review.
• Olander, S. (2006) External stakeholder analysis in construction project management,
Doctoral thesis, Department of Construction Management, Lund University, Lund.
• Vinten, G.(2000) The stakeholder manager. Management Decision, 28(6), 377-83.
• Gibson, K (2000) The moral basis of stakeholder theory. Journal of Business Ethics,
26(3), 245-257.
• Friedman, A.L. and Miles, S. (2006) Stakeholders: Theory and Practice, Oxford
University Press, Oxford.
• Newcombe, R.(2003) From client to project stakeholders: a stakeholder mapping
approach. Construction Management and Economics, 21, 841-8.
• Cleland, D.J. (1995) Project Management Strategic Design and Implementation,
McGraw-Hill, Singapore.
• Morris, P.W.G. (1994) The Management of Projects: A New Model, Thomas Telford,
London.
34
35

More Related Content

Similar to Shiv - STAKEHOLDERS PRESENTATION FINAL REVIEW.ppt

Project initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder managementProject initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder managementRudreshSamant
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction IndustryGirish Singh
 
Project Development Phases and Project Life Cycle.pptx
Project Development Phases and Project Life Cycle.pptxProject Development Phases and Project Life Cycle.pptx
Project Development Phases and Project Life Cycle.pptxJohnChristopherRegui2
 
Innovative project management practices for large power sector projects.
Innovative project management  practices for large power sector projects.Innovative project management  practices for large power sector projects.
Innovative project management practices for large power sector projects.sanjeeev bahadur, m.tech,mba
 
Retrospective: Three Years of Grid Programs @ ARPA-E
Retrospective: Three Years of Grid Programs @ ARPA-ERetrospective: Three Years of Grid Programs @ ARPA-E
Retrospective: Three Years of Grid Programs @ ARPA-EJosh Gould
 
PM-1 Overview.ppt
PM-1 Overview.pptPM-1 Overview.ppt
PM-1 Overview.pptnatisil1
 
The challenge of wicked problems in airlines engineering ahmad arafat
The challenge of wicked problems in airlines engineering   ahmad arafatThe challenge of wicked problems in airlines engineering   ahmad arafat
The challenge of wicked problems in airlines engineering ahmad arafatAhmad Arafat
 
SDLC & Project Team roles_in practice
SDLC & Project Team roles_in practiceSDLC & Project Team roles_in practice
SDLC & Project Team roles_in practicebizpresenter
 
Value engineering in residential house construction
Value engineering in residential house constructionValue engineering in residential house construction
Value engineering in residential house constructionIAEME Publication
 
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONVALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONIAEME Publication
 
project implementation chapter Five.ppt
project implementation   chapter Five.pptproject implementation   chapter Five.ppt
project implementation chapter Five.pptselam49
 
10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder ManagementSanjay Rajpoot
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1Aconex
 
What Is Oracle Primavera Unifier
What Is Oracle Primavera UnifierWhat Is Oracle Primavera Unifier
What Is Oracle Primavera UnifierJessica Tanner
 

Similar to Shiv - STAKEHOLDERS PRESENTATION FINAL REVIEW.ppt (20)

Project initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder managementProject initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder management
 
PM_lecture.pdf
PM_lecture.pdfPM_lecture.pdf
PM_lecture.pdf
 
Pm lecture
Pm lecturePm lecture
Pm lecture
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction Industry
 
IPD-Whitepaper_2018-2.pdf
IPD-Whitepaper_2018-2.pdfIPD-Whitepaper_2018-2.pdf
IPD-Whitepaper_2018-2.pdf
 
PMC2
PMC2PMC2
PMC2
 
Project Development Phases and Project Life Cycle.pptx
Project Development Phases and Project Life Cycle.pptxProject Development Phases and Project Life Cycle.pptx
Project Development Phases and Project Life Cycle.pptx
 
Project Stakeholder Management
Project Stakeholder ManagementProject Stakeholder Management
Project Stakeholder Management
 
Innovative project management practices for large power sector projects.
Innovative project management  practices for large power sector projects.Innovative project management  practices for large power sector projects.
Innovative project management practices for large power sector projects.
 
Retrospective: Three Years of Grid Programs @ ARPA-E
Retrospective: Three Years of Grid Programs @ ARPA-ERetrospective: Three Years of Grid Programs @ ARPA-E
Retrospective: Three Years of Grid Programs @ ARPA-E
 
PM-1 Overview.ppt
PM-1 Overview.pptPM-1 Overview.ppt
PM-1 Overview.ppt
 
The challenge of wicked problems in airlines engineering ahmad arafat
The challenge of wicked problems in airlines engineering   ahmad arafatThe challenge of wicked problems in airlines engineering   ahmad arafat
The challenge of wicked problems in airlines engineering ahmad arafat
 
SDLC & Project Team roles_in practice
SDLC & Project Team roles_in practiceSDLC & Project Team roles_in practice
SDLC & Project Team roles_in practice
 
Value engineering in residential house construction
Value engineering in residential house constructionValue engineering in residential house construction
Value engineering in residential house construction
 
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONVALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
 
project implementation chapter Five.ppt
project implementation   chapter Five.pptproject implementation   chapter Five.ppt
project implementation chapter Five.ppt
 
10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder Management
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
What Is Oracle Primavera Unifier
What Is Oracle Primavera UnifierWhat Is Oracle Primavera Unifier
What Is Oracle Primavera Unifier
 
ICT 4109.pdf
ICT 4109.pdfICT 4109.pdf
ICT 4109.pdf
 

Recently uploaded

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 

Recently uploaded (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 

Shiv - STAKEHOLDERS PRESENTATION FINAL REVIEW.ppt

  • 1. 1 MODELLING AND MANAGING STAKEHOLDER’S POWER AND INFLUENCE FOR QUALITY IMPROVEMENT IN CONSTRUCTION PROJECTS A CASE STUDY AT “JAIPUR METRO”
  • 2. MODELLING AND MANAGING STAKEHOLDER’S POWER AND INFLUENCE FOR QUALITY IMPROVEMENT IN CONSTRUCTION PROJECTS A CASE STUDY AT “JAIPUR METRO” PRESENTED BY: SHIV KUMAR S. Assistant Professor Musaliar College of Engg. & Technology
  • 3.
  • 4. Owner : Jaipur Metro Rail Corporation Limited (JMRCL) Client : Delhi Metro Rail Corporation Limited (DMRC) Type of Project : Design and Build Scope of Work : Approach Tunnel, Open Ramp Portion and Underground Chandpole Metro Station by Cut & Cover Method Original Contract Price : Rs. 101.85 Crore Revised / assessed Price: Rs. 95.41 Crore Project Length : 529.476 meter Revised Project Length : 502 meter Contract Period : 24 month Commencement date : 19th November 2010 Intended Completion date : 18th November 2012 Price Adjustment : Yes (Labour, Steel, Cement, Fuel & Machinery/Machine tools) Liquidated Damages : 0.005% / day for Key dates and 0.05% / day Completion of works, max.10 % of CP. Defects Liability Period 52 week Project Salient Features
  • 5.
  • 6. PACKAGE DESCRIPTION OF WORK WORK ALLOTED TO COMPANIES C1 Construction of Elevated Way Duct for approximately 6km round DSC Limited C2 Construction of Four Way BRTS Corridor extending up to 4.5km, Construction of Way Duct for 2.5km ITD-ITD CEM JV C3 Construction of underground station at Chandpole ITD Cementation India Limited 6
  • 7. PACKAGE DESCRIPTION OF WORK WORK ALLOTED TO COMPANIES C4 Construction of the maintenance yard for vehicles Prathibha Consitium C5 Construction of Way Duct of Two-lane for 2.5 km ITD-ITD CEM JV C6 Construction of 6 elevated stations at Mansarovar,Atish Market,Ram Nagar,Civil Lines, Ajmer Pulia,Vivek Vihar B L Kashyap & Sons C7 Construction of two Metro stations- Sindhi camp Bus stand, and at Railway station KMV Projects 7
  • 8.
  • 9. C3 Office C3 Staff Mess Jaipur Railway Station Chandpole Station
  • 11. INTRODUCTION • The interactions and interrelationships between stakeholders largely determine the overall performance of a construction project, and have the crucial responsibility for delivering a project to successful completion. • Successful completion of construction projects is dependent on meeting the expectation of stakeholders throughout the project life cycle. • The failure of project management teams to address the concerns of construction project stakeholders has resulted in countless project failures, primarily because construction stakeholders have the resources and capability to stop construction projects. • Thus, it is important to analyze, identify and manage stakeholder interests and relationships. 11
  • 12. WHO IS STAKEHOLDER?  STAKE: Stake is an interest or a share in an undertaking.  STAKEHOLDER:  An individual with a stake.  Any person, group or organization who can be positively or negatively impacted by, or cause an impact on, the actions or activities proposed.  TYPES OF STAKEHOLDERS : Stakeholders can be divided into internal stakeholders and external stakeholders • Internal stakeholders being those directly involved in an organization’s decision- making process (e.g. owners, customers, suppliers, employees) • External stakeholders being those affected by the organization’s activities in a significant way (e.g. neighbours, local community, general public, local authorities). 12
  • 13. STAKEHOLDERS MANAGEMENT  Analysis of 334 stakeholders involved directly to the project (Internal stakeholders only).  73 Stakeholders in company, 261 Stakeholders involved in sub-contractors.  List of sub-contractors (sub-contract given by the company).  Soma Construction Limited (7 Engineers, 105 Labours).  Desai Projects Private Limited (5 Supervisors, 86 Labours).  Bhoorathnom Construction (P) Ltd (3 Supervisors, 30 Labours).  Valecha Engineering Limited (3 Supervisors , 22 Labours). 13
  • 14. STAKEHOLDERS MANAGEMENT (CONT…) An important component of stakeholder management is stakeholder analysis. The study includes:  A case study at Jaipur Metro C3 Package.  Analysis of 334 Stakeholders.  Questionnaire , Interviews , Emailing ,Telephonic conversation etc.  Attitude, Power, Interest level.  Datas will be stored for engaging the stakeholders using Project Stakeholder Organize Deluxe software 3.7. 14
  • 15. COMPANIES UNDER C3 PACKAGE  Soma Construction Limited and Valecha Engineering Limited.  Construction of Diaphram walls.  Construction of Roof Slab level (Piling done for columns at 12m depths).  Construction for tunnels (Top-down method).  Construction of Sidewalks.  137 Stakeholders are involved. 15
  • 16. COMPANIES UNDER C3 PACKAGE  Desai Projects (P) Ltd and Bhoorathnom Construction Company (P) Ltd.  Construction of Main Station building.  Construction of Generator room , Water tank ,Diesel generator room, ESR room, Electrical Panel room, UPS room( Concrete blocks – 0.25 x 0.25 x 0.15).  Construction for Ramp (Raft-10m ,1m each working space , 1.2m c/c shoulder piling).  124 Stakeholders are involved. 16
  • 17.
  • 18. PROCEDURES INVOLVED IN THE STUDY The main procedures involved in this study are: Identifying the stakeholders.  Prioritize the stakeholders.  Understand the Key stakeholders.  Managing the stakeholders. 18
  • 19. IDENTIFYING STAKEHOLDERS  Identifying stakeholders requires a good deal of research.  Listing of stakeholders. 19
  • 20. PRIORITIZE THE STAKEHOLDERS  Once the list of names has been generated , analyse the list in terms of power, influence and the extent to which they are affected by the project.  Questionnaire were prepared seperately for different stakeholders along with different question codes for getting more accurate result.  Out of 334 stakeholders, 246 gave response , on the basis of which the stakeholders are prioritize into four sector table as shown.  Prioritization Chart has been prepared. 20
  • 21. High power Satisfy Opinion formers. Keep them satisfied with what is happening and review your analysis of their position regularly. Manage Key stakeholders who should be fully engaged through full communication and consultation. Low power Monitor This group may be ignored if time and resources are stretched. Inform Patients often fall into this category. It may be helpful to take steps to increase their influence by organizing them into groups or taking active consultative work. Low impact/stake holding High impact/stake holding 21
  • 22. UNDERSTAND THE KEY STAKEHOLDERS  Talk to stakeholders directly.  Key Stakeholders can be summarized on the Stakeholder map.  A good way of doing this is by color coding.  Supporters in green, blockers and critics in red, and others who are neutral in orange. 22
  • 23. 23
  • 24. MANAGING THE STAKEHOLDERS  After identifying all the Key Stakeholders, who are the threats and who are in favour of the project has to be managed using PROJECT STAKEHOLDER ORGANIZE DELUXE 3.7 software.  The identified key stakeholders are entered, organized and managed using stakeholder organize deluxe software, considering the data’s collected from the project execution team.  Project Stakeholder Organize Deluxe 3.7 is simple database management software that helps us to enter, organize, and manage our project stakeholders. 24
  • 25. Examples of stakeholder analysis using Project Stakeholders Organize Deluxe Software STAKEHOLDER VIVEK KHARIYA IDNR 103 COMPANY ITD CEMENTATION INDIA PRIVATE LIMITED STATUS Active POSITION Project Manager TYPE Organization CATEGORY ProjectTeam PHONE1 PHTYPE1 PHONE2 PHTYPE2 EMAIL vivek2000@gmail.com WEB 25
  • 26. Examples of stakeholder analysis using Project Stakeholders Organize Deluxe Software CONTACT ADDRESS1 28-C, SECTOR-5 ADDRESS2 CIVIL LANES CITY JAIPUR STATEPROV RAJASTHAN ZIPPOSTAL COUNTRY INDIA COMMENTS Good attitude and influence level. Enthusiastic in work. HOWTOMANAGE Manage Closely IMPORTANT POWERLEVEL1 5-VeryHigh INTERESTLEVEL1 5-VeryHigh 26
  • 27. Examples of stakeholder analysis using Project Stakeholders Organize Deluxe Software ATTITUDELEVEL1 4-Supporter POWERLEVEL2 04 INTERESTLEVEL2 04 ATTITUDELEVEL2 04 CUSTOM1 note EVALUATIONNOTES Fully satisfied in the work NOTES date note LOG 16-01-2012 Entry date of details 27
  • 28. INFERENCE OF THE PROJECT  On the basis of the detailed study conducted on the stakeholders engaged under C3 Package of construction of underground station at Chandpole of Jaipur Metro, it has been concluded that out of 334 stakeholders only 246 gave their responses (ie,73.65%) and it was observed that 116 of them had a positive temperament while 83 were neutral which can also be visioned has a positive outlook to the project.  47 out of 246 were blockers and had various issues which could be resolved by the company.  The overall inference is that 199 (116+83) out of 246 is approximately 81% is definitely positive and hence the project can be deemed as a success. 28
  • 29. CONCLUSION  The pros and cons of this project was that it is an almost-perfect analysis of employee satisfaction of any company and is beneficial in overall administration of the same.  This study must be carried out so as to tackle various employee related problems and to ensure utmost stakeholder satisfaction.  On the contrary, this study has a major disadvantage ie, it is very time consuming. If it was to be conducted on the entire project it would have been a humongous if not an impossible task. 29
  • 30. SAMPLE QUESTIONNAIRES FOR ANALYSIS Q.1. What is your total experience in this field? less than 5 years 5 to 10 years more than 10 years Q.2. For how many years are you working with Company? Less than 2 years 2-5 years 5-10 years Q.3. Do you think that you have work load? Yes No Q.4. Is the superior friendly to you? Yes No Q.5. Do you think that your work is carried out properly? Yes No Q.6. Do you think that your labours are working according to your directions and control? Yes No 30
  • 31. SAMPLE QUESTIONNAIRES FOR ANALYSIS Q.7. Are you satisfied with the company’s submission of drawings at proper time? Yes No Q.8. Is there any lag in the work ? Yes No Q.9. Do you think that the manpower and equipment provided to you is sufficient to finish the task? Yes No Q.10. How many labours have been supervised by you? Upto 10 between 10 to 30 between 30 to 50 Q.11. Do you think that the present state of work can be improved ? Yes No 31
  • 32. SAMPLE QUESTIONNAIRES FOR ANALYSIS Q.12. Which factor according to you is the best for improving the state of work? improving the pay scale of supervisor giving supervisors more power conducting seminar to improve quality Q.13. What is the working hour for you? 8 hours 8-10 hours more than 10 hours Q.14. Are you provided with the facility of overtime? Yes No Q.15. How many casual leaves are allotted to you monthly? less than 2 2-3 days 3-4 days None 32
  • 33. SAMPLE QUESTIONNAIRES FOR ANALYSIS Q.16. According to you ,Is there any thing the company can do to improve your work satisfaction level? Yes No Q.17. If yes, the change has to be made in which field ? Work incentive Better inter-relation with higher officials Better working condition Opportunity for growth Q.18. According to you , the working environment for you is : Good Poor Satisfactory Q.19.Do you think that the co-workers are doing their work properly? Yes No Q.20. Do you think that any decision made by you is appreciated by company? Yes No 33
  • 34. REFERENCES • Freeman, R.E. (1984) Strategic Management: A Stakeholder Approach, Pitman Publishing Inc., Boston . • Freeman, R.E. (1999) Divergent stakeholder theory. Academy of Management Review. • Olander, S. (2006) External stakeholder analysis in construction project management, Doctoral thesis, Department of Construction Management, Lund University, Lund. • Vinten, G.(2000) The stakeholder manager. Management Decision, 28(6), 377-83. • Gibson, K (2000) The moral basis of stakeholder theory. Journal of Business Ethics, 26(3), 245-257. • Friedman, A.L. and Miles, S. (2006) Stakeholders: Theory and Practice, Oxford University Press, Oxford. • Newcombe, R.(2003) From client to project stakeholders: a stakeholder mapping approach. Construction Management and Economics, 21, 841-8. • Cleland, D.J. (1995) Project Management Strategic Design and Implementation, McGraw-Hill, Singapore. • Morris, P.W.G. (1994) The Management of Projects: A New Model, Thomas Telford, London. 34
  • 35. 35