IT TOWER, CHANDAKA
SPECIFICATIONS FOR KEY COMPONENTS
CONTENTS
• L O C A T I O N
• S I T E P I C T U R E S
• S I T E P L A N
• Z O N I N G
• A R E A S T A T E M E N T
• F L O O R P L A N
• D E S I G N C O N S I D E R A T I O N S
• A P P R O V A L & D E S I G N
• S T R U C T U R E
• D E S I G N C O N S I D E R A T I O N S
• W A T E R P R O O F I N G
• E L E C T R I C A L
• H V A C
• F I R E F I G H T I N G
• C C T V
• O T H E R K E Y I T E M S
• E X T E R N A L D E V E L O P M E N T W O R K S
LOCATION
Plot area: 2.17 acre
SITE PICTURES
SITE PICTURES
PROPOSAL
SITE PLAN
ABUTTING ROAD
Earthing pit
• Plot Area – 2.17 Acre.
N
85.75M
STILT PARKING
(6 FLOORS,3.6M FLOOR HEIGHT)
OFFICE AREAS
12 FLOORS (4.2 M)
RETAIL, FOOD COURT, CO-WORKING GYM
(4.2M FLOOR HEIGHT)
DATA CENTER (4.6M FLOOR HEIGHT)
ROOF TOP RESTAURANT, CAFE AND
OFFICES
ZONING
BASEMENT PARKING
(3 FLOORS,3.6M FLOOR HEIGHT)
Area Statement
• Proposed Building: 3 B + 6S + 15 Floors
• Basement Parking Area : 3 Basement = 9800
sqmt
• Ground Floor Area: 3220 sqm
• Upper Floor Parking area: 6 Floors = 18300 sq.mt
• Office and Common area : 56088.6 sqm.
• Area Under Parking : 28100 sq.m (50%)
• Car Parking achieved: 602 ECS (518 Cars + 338
Two Wheelers
Total built up: 84188.6 sq.mt
F.A.R: 5.64
Floor Floor Area FAR - BUA
3rd Basement Floor 3634.4 0
2nd Basement Floor 3256.4 0
1st Basement Floor 3256.4 0
Ground/Stilt Floor 3220 627.1
1st Stilt Floor 2976.4 175.3
2nd Stilt Floor 3235 175.3
3rd Stilt Floor 3235 175.3
4th Stilt Floor 3235 175.3
5th Stilt Floor 3235 175.3
Sixth Floor (Data Centre) 3771 3278.4
Seventh Floor (Retail Floor) 3771 3278.4
Eighth Floor 3605 3278.4
Nineth Floor 3605 3278.4
Tenth Floor 3771 3278.4
Eleventh Floor 3605 3278.4
Twelfth Floor 3605 3278.4
Thirteenth Floor 3605 3278.4
Fourteenth Floor 3771 3278.4
Fifteenth Floor 3605 3278.4
Sixteenth Floor 3605 3278.4
Seventeenth Floor 3605 3278.4
Eighteenth Floor 3771 3278.4
Nineteenth Floor 3605 3278.4
Twentieth Floor 3605 2213.8
Total built up 84188.6 49615
Floor heights
FLOOR HEIGHTS - IT TOWER CHANDAKA
S.No. Area Statement Chart Details No of Floor Floor Height (m)
Total Height
(m)
1 Basement - 3
Basement
1 3.6
2 Basement -2 1 3.6
3 Basement -1 1 3.6
4 GF/Stilt Floor
Stilt
Floors
1 3.6 3.6
5 1st Stilt 1 3.6 3.6
6 2nd Stilt 1 3.6 3.6
7 3rd Stilt 1 3.6 3.6
8 4th Stilt 1 3.6 3.6
9 5th Stilt 1 3.6 3.6
9 6th Floor Data Center 1 4.6 4.6
10 7th Floor Retail Floor 1 4.2 4.2
11
8th
, 9th
, 11th
, 12th
, 13th
, 15th
, 16th
,
17th
, 19th
Floor
Working
Floors
9 4.2 37.8
12 1oth, 14th
, 18th
Floor 3 4.2 12.6
14 20th Floor 1 4.2 4.2
TOTAL 24 85.75
FLOOR PLANS – 3 BASEMENTS + 6 STILTS + 15 FLOORS
PROPOSAL GROUND /STILT FLOOR PLAN
GROUND / STILT FLOOR PLAN
Parking Capacity: 36 Cars
PARKING CALCULATION
FLOOR CARS
2
WHEELER
3rd Basement parking 60 36
2nd Basement parking 60 38
1st Basement parking 60 34
Total basement parking 180 108
Ground / stilt parking 36
1st stilt parking 54 46
2nd stilt parking 62 46
3rd stilt parking 62 46
4th stilt parking 62 46
5th stilt parking 62 46
Total Stilt parking 338 230
Total no. of parking
achieved
518 338
SPACE FOR
AMBULANCE AND
EMERGENCY
PARKING
Staircase from basement
terminating at the Ground Floor .
Fire Exit Staircase and Lifts
Service Core
Utility Core
IN
OUT
PROPOSAL CIRCULATION PLAN
CAR MOVEMENT
• SLOPE OF RAMP – 1:12
• TURNING RADIUS OF VEHICLE – 12 M
• UNIDIRECTIONAL MOVEMENT OF VEHICLE
• SEPARATE ENTRY AND EXIT
PROPOSAL - BASEMENT
FIRST BASEMENT PLAN
Parking Capacity: 60 Cars
PARKING CALCULATION
FLOOR CARS
2-
WHEELER
3rd Basement parking 60 36
2nd Basement parking 60 38
1st Basement parking 60 34
Total basement parking 180 108
Ground / stilt parking 36
1st stilt parking 54 46
2nd stilt parking 62 46
3rd stilt parking 62 46
4th stilt parking 62 46
5th stilt parking 62 46
Total Stilt parking 338 230
Total no. of parking
achieved
518 338
Staircase from basement
terminating at the Ground Floor .
Ventilation shafts
continuing in all the three
basement floors
Ventilators in the first
basement at ground level
for Natural Ventilation.
PROPOSAL - BASEMENT
THIRD AND SECOND BASEMENT TYPICAL FLOORPLAN
Parking Capacity : 60 Cars each floor
PARKING CALCULATION
FLOOR CARS
2-
WHEELER
3rd Basement parking 60 36
2nd Basement parking 60 38
1st Basement parking 60 34
Total basement parking 180 108
Ground / stilt parking 36
1st stilt parking 54 46
2nd stilt parking 62 46
3rd stilt parking 62 46
4th stilt parking 62 46
5th stilt parking 62 46
Total Stilt parking 338 230
Total no. of parking
achieved
518 338
Staircase from basement
terminating at the Ground Floor .
PROPOSAL STILT FLOOR PLAN
FIRST STILT FLOOR PLAN
Parking Capacity: 62 Cars
PARKING CALCULATION
FLOOR CARS
2-
WHEELER
3rd Basement parking 60 36
2nd Basement parking 60 38
1st Basement parking 60 34
Total basement parking 180 108
Ground / stilt parking 36
1st stilt parking 54 46
2nd stilt parking 62 46
3rd stilt parking 62 46
4th stilt parking 62 46
5th stilt parking 62 46
Total Stilt parking 338 230
Total no. of parking
achieved
518 338
EXPANSION JOINT
PROPOSAL STILT FLOOR PLAN
2ND, 3RD, 4TH, & 5TH STILT TYPICAL FLOOR PLAN
Parking Capacity: 62 Cars each floor
PARKING CALCULATION
FLOOR CARS
2-
WHEELER
3rd Basement parking 60 36
2nd Basement parking 60 38
1st Basement parking 60 34
Total basement parking 180 108
Ground / stilt parking 36
1st stilt parking 54 46
2nd stilt parking 62 46
3rd stilt parking 62 46
4th stilt parking 62 46
5th stilt parking 62 46
Total Stilt parking 338 230
Total no. of parking
achieved
518 338
EXPANSION JOINT
PROPOSAL
SIXTH FLOOR PLAN
6TH FLOOR PLAN (DATA CENTER)
EXPANSION JOINT
PROPOSAL
SEVENTH FLOOR PLAN
7TH FLOOR PLAN – RETAIL FLOOR
Occupant Load – 629 Persons
EXPANSION JOINT
PROPOSAL
TYPICAL
FLOOR PLAN
8TH, 9TH, 11TH, 12TH, 13TH, 15TH, 16TH, 17TH, & 19TH TYPICAL FLOOR PLAN
Occupant Load – 361 Persons
EXPANSION JOINT
PROPOSAL
TYPICAL
FLOOR PLAN
WITH REFUGE
AREA
10TH, 14TH, & 18TH TYPICAL FLOOR PLAN
Occupant Load – 377 Persons
EXPANSION JOINT
PROPOSAL
twentieth
FLOOR PLAN
20TH FLOOR PLAN
Occupant Load – 361 Persons
EXPANSION JOINT
PROPOSAL
fire escape route
4 Fire Towers provided at the 4
corners of the Building at the external
walls, enclosed with a Fireman Lift,
with a Fire Exit at the Ground Floor.
A 7.5 M driveway around the Building
with 9 M turning radius for the easy
movement of Fire Tender.
Terrace kept free from any Services
for evacuation purpose during the
time of Fire.
PROPOSAL
fire escape route
REFUGE AREAS PROVIDED
THROUGHOUT THE BUILDING FOR
EASY EVACUATION.
6th Floor at +22.35 M height
from Ground Level
7th Floor at +26.95 M height
from Ground Level
10th Floor at +39.55 M height
from Ground Level
14th Floor at +56.35 M
height from Ground Level
18th Floor at +73.15 M height
from Ground Level
PROPOSAL
MATERIALS USED IN FACADE
STILT PARKING FLOORING
FREE OF GLAZING , FOR
NATURAL VENTILATION
STRUCTURAL GLAZING
SYSTEM OF DOUBLE-
GLAZING UNIT (DGU)
GLASS, PROPOSED FOR
ALL FLOORS ABOVE THE
STILT FLOORS.
STRUCTURAL FINS OF
ALUMINIUM COATED
PANEL (ACP)
Using passive solar architecture for achieving thermal comfort
through use of structural fins
PROPOSAL
INDICATIVE IMAGES (INTERIOR)
CORRIDORS AND
COMMON SPACES
WITH FALSE CEILING
AND FLOORING
VDF FLOORING WITH
ALL SERVICES IN THE
BASEMENT AND STILT
PARKING FLOORS
OFFICE SPACES
ROOF TOP CAFÉ
PROPOSAL
INDICATIVE IMAGES (INTERIOR)
FOOD COURT AREA
SUPER MARKET
OFFICE LOBBY ACCESS CONTROL LIFT LOBBY
FOOD COURT SKY GARDEN SKY GARDEN
PROPOSAL – Design Considerations
Fifth floor to have Food
Court, GYM, Store
PROPOSAL – Design Considerations
CONCEPT – infrastructure planning through bim
CONCEPT – IBMs
GREEN BUILDING APPROACH
CONCEPT – BMs
CONCEPT – BMs
CONCEPT – BMs
INTELLIGENT PARKING MANAGEMENT SYSTEM
SPECIFICATIONS FOR KEY ITEMS
APPROVAL & DESIGN
Sl No. Scope of work
I
Statutory Approvals - BDA/ BMC, EC, AAI,
WATCO, Any Other
In Bidders Scope
II
Detailed Design Integrated with BIM Modelling
up to LOD 400
In Bidders Scope
SUMMARY OF SOIL STRATA & SBC
STRUCTURE
Description of Items Specification/detail
RCC Framed Structure
Design as per Seismic Zone-III. Pile Foundation, RCC Columns &
Slabs with Column to Column distance of 6mtrs avg.
The Bidder is allowed to optimize the design based on latest
construction technology considering time and cost factor of the
project and approval by IDCO
BASIC COMPONENTS
Sl No. Description of Items Specification/detail
1 Excavated Earth Disposal Upto 10 kilometers
2 RCC Framed Structure
Design as per Seismic Zone-III. Pile Foundation, RCC
Columns & Slabs with Column to Column distance of 6mtrs
avg.
3 Reinforcement Steel Primary Steel
4 Brick Work Fly ash
5 Kota Stone Flooring Service Areas like Panel room & HVAC Room
6 Granite - Flooring & Cladding Staircase, Lift lobby, lift Façade, Refuse Area & Corridors
7 Tile Flooring Vitrified Tiles in Data center & Retail Floor
8 Toilet Tile Wok Vitrified Tiles in Toilets & Washrooms,
Water proofing
Water Proofing Treatment in Project Area
1
Below Foundation of Basements,
Grade Slab, Drains, Sumps,
Trenches, STP, Lift Pits.
HDPE membrane of 1.2 mm thick conforming to IS 16471-2017 - rolled down on
the shuttering /PCC prior to reinforcement casting and pouring the concrete.
The membrane shall consists of a unique HDPE film pressure sensitive adhesive
which allows poured concrete to bond fully with the membrane.
The membrane shall be supplied with one self-adhesive selvedge to provide
sealed laps.
Tensile strength >21 MPa(ASTM 0412),Elongation > 400%, Peel Adhesion to
concrete 880 N/m, Resistance to hydrostatic head > 70 mtr.
2
Basement Retaining Walls, UG
Sump, STP, WTP and Lift Pits in
contact with soil (External)
2mm thick self adhesive, self healing type SBS based membranes minimum
puncture resistance, tensile resistance over 200%,
Elongation over 45% as per IS 16525.T
3
Waterproofing Treatment For
Terrace, Headroom, Open to Sky,
OHT Slab.
Single component pure polyurethane based elastomeric seamless liquid applied
membrane:
ELECTRICAL
Sl No. Description of Items Specification/detail
I Internal Electrical Work
i Internal Electrical Work- Complete
Complete Electrical Works in Parking ( 3B+5S =8
Floors), Data Center Floor (1st Floor), Retail Area (2nd
Floor) & Reception area.
ii Internal Electrical Work- Partial
Distribution upto Electrical Panel Room of each Floor
of Core Shell Area. Internal Distribution in Core Shell
Area is not estimated in the Bidder's Scope
II External Electrical Work
Approval, Design and Execution for laying of 33 KV HT
Line, Internal Substation & Complete accessories
ELECTRICAL – LOAD
TOTAL LOAD CALCULATION
S.No Item Description Watt KW
Diversity Load
factor = 0.70
Total KVA
1
Load of fixtures of basement
Floors
175515 175.515 122.8605 170.6
2 Load of fixtures of Stilt Floors 242300 242.3 169.61 235.6
3
Load of fixtures of Commercial
Floors
1327200 1327.2 929.04 1290.3
4 HVAC Load -4000 ton 6002000 6002 4201.4 5835.3
5 Lift - 12 120000 120 84 116.7
6 Pumps 265000 265 185.5 257.6
7 Street light 3.30 0.0033 0.00231 0.0
8 External Electrical 10000 10 7 9.7
TOTAL LOAD CALCULATION 8142018 8142 5699 7916
Substation - 5X2000 KVA
(4working +1Standby)
Transformer capacity.
DG Set capacity is 4 x 2500
KVA (Three running plus one
standby)
HVAC
Sl No. Description of Items Specification/detail Remark
HVAC System - 4000 TR Remarks
i Option 01
Centralized Water Cooled Chiller
System + Cooling Towers
Capital Intensive. Ideal for single user.
Incase of Multiple Users Collection of AMC
charges is cumbersome
ii Option 02
Centralized Cooling Towers +
Decentrailzed Chillers
Lesser Capital Intensive and provide
flexibility to multiple users to design their
own HVAC system with minimal AMC
charges
iii Option 03 VRF for each Floor
Requires areas for installtion of VRF Units at
designated/dedicated areas. Lesser
Capital intensive but provides flexibility to
multiple users.
HVAC - load
S.No. Floor
No of
Floors
Workable/Off
ice/Co-
working Area
(sqm)
Area Details
Recreational
Area (sqm)
Total Area
(sqm)
1 Basement -3 1 0 NA 0
2 Basement -2 1 0 NA 0
3 Basement -1 1 0 NA 0
4 GF/Stilt Floor 1 278 Reception Area 0 278
5 1st Stilt 1 0 NA 0
6 2nd Stilt 1 0 NA 0
7 3rd Stilt 1 0 NA 0
8 4th Stilt 1 0 NA 0
9 1st Floor 1 3245 Data Center 0 3245
10 2nd Floor 1 0
GYM, SUPER
MARKET/ RETAIL,
CAFETERIA/
FOODCOURT
3609 3609
11 3rd & 4th Floors 2 2120
Office and Co-
working Spaces
0 4240
12
5th, 6th, 7th, 9th, 10th,
12th & 13th Floors
7 3609 Office Area 0 25263
13 8th, 11th & 14th Floors 3 3168 Office Area 0 9504
14 15th Floor 1 2443 Office Area 1176 3619
Total Area for Air Conditioning (in sqm) 49758
CALCULATION OF AIR CONDITIONING
Total Area for Chiller
Air Conditioning
Sqm A 49758
Area in Sqft Sqft B = A x 10.76 535396
Hence, Total TR
required for Given
Area is
TR 4000
FIREFIGHTING
Sl No. Description of Items Specification/detail
Fire Fighting & Alarm System
i Fire Fighting & Alarm System - Complete
Complete Fire Fighting Works in Parking ( 3B+5S =8
Floors), Data Center Floor (1st Floor), Retail Area (2nd
Floor) & Reception area. (Sprinklers, hydrants, hose
reel, smoke detector, alarm system, fire extinguishers,
fire panel, pressurized air system in Lift well, lift lobby &
staircase areas.
ii Fire Fighting & Alarm System - Partial
Internal distribution of firefighting system is not included
in the scope of Bidder in core shell areas except
common areas like corridors, lobby, staircases & refuse
areas.
CCTV
Sl No. Description of Items Specification/detail
CCTV SYSTEM
i CCTV SYSTEM - Complete
Complete CCTV Works in Parking ( 3B+5S =8 Floors), Data
Center Floor (1st Floor), Retail Area (2nd Floor) & Reception
area.
ii CCTV SYSTEM - Partial
Internal CCTV system is not included in the scope of Bidder
in core shell areas except common areas like corridors,
lobby, staircases & refuse areas.
OTHER KEY ITEMS
Sl No. Description of Items Specification/detail Remark
1 Solar Sytem
Utilization of 50% terrace area for installing the Solar
Power System.
130 KW
2 Lifts
Passenger Lift - 8 No.s of passenger Lifts (16 Passenger)
Service lift - 2 Nos of Service Lift
Fire lift - 2 Nos
Lift Size
Passenger Lift- 1950 x 2550 mm
Service lift - 3100 x 2200 mm
Fire lift - 1800 x 2400 mm
3 Access Control System Provided in all areas except shell areas
4
IBMS System (Integrated Building
Management System)
Provided in all areas except shell areas
5 Elevation Facade Work
Work includes complete Design, Engineering,
Fabrication,
Supply, installation including testing of materials and
performance, quality control, storage, protection,
transport, final cleaning & handover, maintenance &
guarantees up to the defect notification period for the
entire facade works.
EXETERNAL DEVLOPMENT WORKS
Sl No. Description of Items Specification/detail
SITE DEVELOPMENT WORKS
i Internal Road Cement Concrete (7.5 to 9m wide )
ii Compound Wall
1.8m height (from ground floor) as per elevation
design
iii
Construction and Operation of
Sewerage Treatment Plant
250 KLD including Operation and maintenance
for 10 Years
iv Under Ground water Reservoir 850 KLD
THANK YOU

More Related Content

Similar to IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA

Be presentation rev
Be presentation revBe presentation rev
Be presentation rev
Yong Sy
 
An industrial training report
An industrial training reportAn industrial training report
An industrial training report
borokinni
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
Edel Fox
 
Brouches of Jaypee Green
Brouches of Jaypee GreenBrouches of Jaypee Green
Brouches of Jaypee Green
Rakesh Agarwal
 
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Apex Realty Solutions
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 

Similar to IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA (20)

Ascent 456 Floorplans Download. Sales hotline 6100 9300
Ascent 456 Floorplans Download. Sales hotline 6100 9300Ascent 456 Floorplans Download. Sales hotline 6100 9300
Ascent 456 Floorplans Download. Sales hotline 6100 9300
 
Sun Optima
Sun OptimaSun Optima
Sun Optima
 
Time Square West 8-22-14
Time Square West 8-22-14Time Square West 8-22-14
Time Square West 8-22-14
 
f7
f7f7
f7
 
BE presentation slides
BE presentation slidesBE presentation slides
BE presentation slides
 
Be presentation rev
Be presentation revBe presentation rev
Be presentation rev
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics Presentation
 
An industrial training report
An industrial training reportAn industrial training report
An industrial training report
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
Brouches of Jaypee Green
Brouches of Jaypee GreenBrouches of Jaypee Green
Brouches of Jaypee Green
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
 
Nirmal US Open Apartment, Mulund
Nirmal US Open Apartment, MulundNirmal US Open Apartment, Mulund
Nirmal US Open Apartment, Mulund
 
SHRI Radha Skygardens Brochure - Home with a view
SHRI Radha Skygardens Brochure - Home with a viewSHRI Radha Skygardens Brochure - Home with a view
SHRI Radha Skygardens Brochure - Home with a view
 
ILD Trade Centre in Gurgaon
ILD Trade Centre in GurgaonILD Trade Centre in Gurgaon
ILD Trade Centre in Gurgaon
 
Public Housing Summary
Public Housing SummaryPublic Housing Summary
Public Housing Summary
 
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
 
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
Curo One Serviced suites Apartments 12% Assured Returns New Chandigarh@921688...
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Setting BI for ultimate performance for Site
Setting BI for ultimate performance for SiteSetting BI for ultimate performance for Site
Setting BI for ultimate performance for Site
 

Recently uploaded

NON-COMMUNICABLE DISEASES.pptx...........
NON-COMMUNICABLE DISEASES.pptx...........NON-COMMUNICABLE DISEASES.pptx...........
NON-COMMUNICABLE DISEASES.pptx...........
CydeizelMercado1
 
obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...
obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...
obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...
yulianti213969
 
Sun day thang 4 sun life team trung dai
Sun day thang 4 sun life team trung daiSun day thang 4 sun life team trung dai
Sun day thang 4 sun life team trung dai
GiangTra20
 
Captain america painting competition -- 13
Captain america painting competition -- 13Captain america painting competition -- 13
Captain america painting competition -- 13
Su Yan-Jen
 
一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样
一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样
一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样
aqwaz
 
OBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGI
OBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGIOBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGI
OBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGI
Obat Cytotec
 
obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...
obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...
obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...
yulianti213969
 

Recently uploaded (20)

Neighborhood Guide To Atlanta’s Awe-Inspiring Art Galleries
Neighborhood Guide To Atlanta’s Awe-Inspiring Art GalleriesNeighborhood Guide To Atlanta’s Awe-Inspiring Art Galleries
Neighborhood Guide To Atlanta’s Awe-Inspiring Art Galleries
 
Young & Hot ℂall Girls Surat Dumas Road 8849756361 WhatsApp Number Best Rates...
Young & Hot ℂall Girls Surat Dumas Road 8849756361 WhatsApp Number Best Rates...Young & Hot ℂall Girls Surat Dumas Road 8849756361 WhatsApp Number Best Rates...
Young & Hot ℂall Girls Surat Dumas Road 8849756361 WhatsApp Number Best Rates...
 
NON-COMMUNICABLE DISEASES.pptx...........
NON-COMMUNICABLE DISEASES.pptx...........NON-COMMUNICABLE DISEASES.pptx...........
NON-COMMUNICABLE DISEASES.pptx...........
 
Young & Hot ℂall Girls Olpad 8849756361 WhatsApp Number Best Rates of Surat ℂ...
Young & Hot ℂall Girls Olpad 8849756361 WhatsApp Number Best Rates of Surat ℂ...Young & Hot ℂall Girls Olpad 8849756361 WhatsApp Number Best Rates of Surat ℂ...
Young & Hot ℂall Girls Olpad 8849756361 WhatsApp Number Best Rates of Surat ℂ...
 
Green Lantern the Animated Series Practice Boards by Phoebe Holmes.pdf
Green Lantern the Animated Series Practice Boards by Phoebe Holmes.pdfGreen Lantern the Animated Series Practice Boards by Phoebe Holmes.pdf
Green Lantern the Animated Series Practice Boards by Phoebe Holmes.pdf
 
VIP ℂall Girls Rustampura 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Se...
VIP ℂall Girls Rustampura 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Se...VIP ℂall Girls Rustampura 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Se...
VIP ℂall Girls Rustampura 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Se...
 
Museum Quality__Published in PrintAction.pdf
Museum Quality__Published in PrintAction.pdfMuseum Quality__Published in PrintAction.pdf
Museum Quality__Published in PrintAction.pdf
 
Young & Hot ℂall Girls Kamrej 8849756361 WhatsApp Number Best Rates of Surat ...
Young & Hot ℂall Girls Kamrej 8849756361 WhatsApp Number Best Rates of Surat ...Young & Hot ℂall Girls Kamrej 8849756361 WhatsApp Number Best Rates of Surat ...
Young & Hot ℂall Girls Kamrej 8849756361 WhatsApp Number Best Rates of Surat ...
 
obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...
obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...
obat aborsi klaten wa 081336238223 jual obat aborsi cytotec asli di klaten54-...
 
Sun day thang 4 sun life team trung dai
Sun day thang 4 sun life team trung daiSun day thang 4 sun life team trung dai
Sun day thang 4 sun life team trung dai
 
Young & Hot ℂall Girls Pandesara 8849756361 WhatsApp Number Best Rates of Sur...
Young & Hot ℂall Girls Pandesara 8849756361 WhatsApp Number Best Rates of Sur...Young & Hot ℂall Girls Pandesara 8849756361 WhatsApp Number Best Rates of Sur...
Young & Hot ℂall Girls Pandesara 8849756361 WhatsApp Number Best Rates of Sur...
 
Captain america painting competition -- 13
Captain america painting competition -- 13Captain america painting competition -- 13
Captain america painting competition -- 13
 
Young & Hot ℂall Girls Khodiyar Nagar 8849756361 WhatsApp Number Best Rates o...
Young & Hot ℂall Girls Khodiyar Nagar 8849756361 WhatsApp Number Best Rates o...Young & Hot ℂall Girls Khodiyar Nagar 8849756361 WhatsApp Number Best Rates o...
Young & Hot ℂall Girls Khodiyar Nagar 8849756361 WhatsApp Number Best Rates o...
 
My scariest moment presentation-part one
My scariest moment presentation-part oneMy scariest moment presentation-part one
My scariest moment presentation-part one
 
一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样
一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样
一比一原版(MQU毕业证书)麦考瑞大学毕业证成绩单原件一模一样
 
OBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGI
OBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGIOBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGI
OBAT ABORSI BANYUWANGI 087776558899 💊 OBAT PENGGUGUR KANDUNGAN BANYNYUWANGI
 
obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...
obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...
obat aborsi wonogiri wa 081336238223 jual obat aborsi cytotec asli di wonogir...
 
Seven Bungalows Esℂorts Serviℂe Available 24x7 Hire Now, WhatsApp No 99304962...
Seven Bungalows Esℂorts Serviℂe Available 24x7 Hire Now, WhatsApp No 99304962...Seven Bungalows Esℂorts Serviℂe Available 24x7 Hire Now, WhatsApp No 99304962...
Seven Bungalows Esℂorts Serviℂe Available 24x7 Hire Now, WhatsApp No 99304962...
 
DeFeliceKitley_Resume_BFAVCDGraduated2024
DeFeliceKitley_Resume_BFAVCDGraduated2024DeFeliceKitley_Resume_BFAVCDGraduated2024
DeFeliceKitley_Resume_BFAVCDGraduated2024
 
VIP ℂall Girls Surat 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Serviℂe...
VIP ℂall Girls Surat 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Serviℂe...VIP ℂall Girls Surat 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Serviℂe...
VIP ℂall Girls Surat 8527049040 WhatsApp AnyTime Best Surat ℂall Girl Serviℂe...
 

IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA

  • 2. CONTENTS • L O C A T I O N • S I T E P I C T U R E S • S I T E P L A N • Z O N I N G • A R E A S T A T E M E N T • F L O O R P L A N • D E S I G N C O N S I D E R A T I O N S • A P P R O V A L & D E S I G N • S T R U C T U R E • D E S I G N C O N S I D E R A T I O N S • W A T E R P R O O F I N G • E L E C T R I C A L • H V A C • F I R E F I G H T I N G • C C T V • O T H E R K E Y I T E M S • E X T E R N A L D E V E L O P M E N T W O R K S
  • 6. PROPOSAL SITE PLAN ABUTTING ROAD Earthing pit • Plot Area – 2.17 Acre. N
  • 7. 85.75M STILT PARKING (6 FLOORS,3.6M FLOOR HEIGHT) OFFICE AREAS 12 FLOORS (4.2 M) RETAIL, FOOD COURT, CO-WORKING GYM (4.2M FLOOR HEIGHT) DATA CENTER (4.6M FLOOR HEIGHT) ROOF TOP RESTAURANT, CAFE AND OFFICES ZONING BASEMENT PARKING (3 FLOORS,3.6M FLOOR HEIGHT)
  • 8. Area Statement • Proposed Building: 3 B + 6S + 15 Floors • Basement Parking Area : 3 Basement = 9800 sqmt • Ground Floor Area: 3220 sqm • Upper Floor Parking area: 6 Floors = 18300 sq.mt • Office and Common area : 56088.6 sqm. • Area Under Parking : 28100 sq.m (50%) • Car Parking achieved: 602 ECS (518 Cars + 338 Two Wheelers Total built up: 84188.6 sq.mt F.A.R: 5.64 Floor Floor Area FAR - BUA 3rd Basement Floor 3634.4 0 2nd Basement Floor 3256.4 0 1st Basement Floor 3256.4 0 Ground/Stilt Floor 3220 627.1 1st Stilt Floor 2976.4 175.3 2nd Stilt Floor 3235 175.3 3rd Stilt Floor 3235 175.3 4th Stilt Floor 3235 175.3 5th Stilt Floor 3235 175.3 Sixth Floor (Data Centre) 3771 3278.4 Seventh Floor (Retail Floor) 3771 3278.4 Eighth Floor 3605 3278.4 Nineth Floor 3605 3278.4 Tenth Floor 3771 3278.4 Eleventh Floor 3605 3278.4 Twelfth Floor 3605 3278.4 Thirteenth Floor 3605 3278.4 Fourteenth Floor 3771 3278.4 Fifteenth Floor 3605 3278.4 Sixteenth Floor 3605 3278.4 Seventeenth Floor 3605 3278.4 Eighteenth Floor 3771 3278.4 Nineteenth Floor 3605 3278.4 Twentieth Floor 3605 2213.8 Total built up 84188.6 49615
  • 9. Floor heights FLOOR HEIGHTS - IT TOWER CHANDAKA S.No. Area Statement Chart Details No of Floor Floor Height (m) Total Height (m) 1 Basement - 3 Basement 1 3.6 2 Basement -2 1 3.6 3 Basement -1 1 3.6 4 GF/Stilt Floor Stilt Floors 1 3.6 3.6 5 1st Stilt 1 3.6 3.6 6 2nd Stilt 1 3.6 3.6 7 3rd Stilt 1 3.6 3.6 8 4th Stilt 1 3.6 3.6 9 5th Stilt 1 3.6 3.6 9 6th Floor Data Center 1 4.6 4.6 10 7th Floor Retail Floor 1 4.2 4.2 11 8th , 9th , 11th , 12th , 13th , 15th , 16th , 17th , 19th Floor Working Floors 9 4.2 37.8 12 1oth, 14th , 18th Floor 3 4.2 12.6 14 20th Floor 1 4.2 4.2 TOTAL 24 85.75
  • 10. FLOOR PLANS – 3 BASEMENTS + 6 STILTS + 15 FLOORS
  • 11. PROPOSAL GROUND /STILT FLOOR PLAN GROUND / STILT FLOOR PLAN Parking Capacity: 36 Cars PARKING CALCULATION FLOOR CARS 2 WHEELER 3rd Basement parking 60 36 2nd Basement parking 60 38 1st Basement parking 60 34 Total basement parking 180 108 Ground / stilt parking 36 1st stilt parking 54 46 2nd stilt parking 62 46 3rd stilt parking 62 46 4th stilt parking 62 46 5th stilt parking 62 46 Total Stilt parking 338 230 Total no. of parking achieved 518 338 SPACE FOR AMBULANCE AND EMERGENCY PARKING Staircase from basement terminating at the Ground Floor . Fire Exit Staircase and Lifts Service Core Utility Core
  • 12. IN OUT PROPOSAL CIRCULATION PLAN CAR MOVEMENT • SLOPE OF RAMP – 1:12 • TURNING RADIUS OF VEHICLE – 12 M • UNIDIRECTIONAL MOVEMENT OF VEHICLE • SEPARATE ENTRY AND EXIT
  • 13. PROPOSAL - BASEMENT FIRST BASEMENT PLAN Parking Capacity: 60 Cars PARKING CALCULATION FLOOR CARS 2- WHEELER 3rd Basement parking 60 36 2nd Basement parking 60 38 1st Basement parking 60 34 Total basement parking 180 108 Ground / stilt parking 36 1st stilt parking 54 46 2nd stilt parking 62 46 3rd stilt parking 62 46 4th stilt parking 62 46 5th stilt parking 62 46 Total Stilt parking 338 230 Total no. of parking achieved 518 338 Staircase from basement terminating at the Ground Floor . Ventilation shafts continuing in all the three basement floors Ventilators in the first basement at ground level for Natural Ventilation.
  • 14. PROPOSAL - BASEMENT THIRD AND SECOND BASEMENT TYPICAL FLOORPLAN Parking Capacity : 60 Cars each floor PARKING CALCULATION FLOOR CARS 2- WHEELER 3rd Basement parking 60 36 2nd Basement parking 60 38 1st Basement parking 60 34 Total basement parking 180 108 Ground / stilt parking 36 1st stilt parking 54 46 2nd stilt parking 62 46 3rd stilt parking 62 46 4th stilt parking 62 46 5th stilt parking 62 46 Total Stilt parking 338 230 Total no. of parking achieved 518 338 Staircase from basement terminating at the Ground Floor .
  • 15. PROPOSAL STILT FLOOR PLAN FIRST STILT FLOOR PLAN Parking Capacity: 62 Cars PARKING CALCULATION FLOOR CARS 2- WHEELER 3rd Basement parking 60 36 2nd Basement parking 60 38 1st Basement parking 60 34 Total basement parking 180 108 Ground / stilt parking 36 1st stilt parking 54 46 2nd stilt parking 62 46 3rd stilt parking 62 46 4th stilt parking 62 46 5th stilt parking 62 46 Total Stilt parking 338 230 Total no. of parking achieved 518 338 EXPANSION JOINT
  • 16. PROPOSAL STILT FLOOR PLAN 2ND, 3RD, 4TH, & 5TH STILT TYPICAL FLOOR PLAN Parking Capacity: 62 Cars each floor PARKING CALCULATION FLOOR CARS 2- WHEELER 3rd Basement parking 60 36 2nd Basement parking 60 38 1st Basement parking 60 34 Total basement parking 180 108 Ground / stilt parking 36 1st stilt parking 54 46 2nd stilt parking 62 46 3rd stilt parking 62 46 4th stilt parking 62 46 5th stilt parking 62 46 Total Stilt parking 338 230 Total no. of parking achieved 518 338 EXPANSION JOINT
  • 17. PROPOSAL SIXTH FLOOR PLAN 6TH FLOOR PLAN (DATA CENTER) EXPANSION JOINT
  • 18. PROPOSAL SEVENTH FLOOR PLAN 7TH FLOOR PLAN – RETAIL FLOOR Occupant Load – 629 Persons EXPANSION JOINT
  • 19. PROPOSAL TYPICAL FLOOR PLAN 8TH, 9TH, 11TH, 12TH, 13TH, 15TH, 16TH, 17TH, & 19TH TYPICAL FLOOR PLAN Occupant Load – 361 Persons EXPANSION JOINT
  • 20. PROPOSAL TYPICAL FLOOR PLAN WITH REFUGE AREA 10TH, 14TH, & 18TH TYPICAL FLOOR PLAN Occupant Load – 377 Persons EXPANSION JOINT
  • 21. PROPOSAL twentieth FLOOR PLAN 20TH FLOOR PLAN Occupant Load – 361 Persons EXPANSION JOINT
  • 22. PROPOSAL fire escape route 4 Fire Towers provided at the 4 corners of the Building at the external walls, enclosed with a Fireman Lift, with a Fire Exit at the Ground Floor. A 7.5 M driveway around the Building with 9 M turning radius for the easy movement of Fire Tender. Terrace kept free from any Services for evacuation purpose during the time of Fire.
  • 23. PROPOSAL fire escape route REFUGE AREAS PROVIDED THROUGHOUT THE BUILDING FOR EASY EVACUATION. 6th Floor at +22.35 M height from Ground Level 7th Floor at +26.95 M height from Ground Level 10th Floor at +39.55 M height from Ground Level 14th Floor at +56.35 M height from Ground Level 18th Floor at +73.15 M height from Ground Level
  • 24. PROPOSAL MATERIALS USED IN FACADE STILT PARKING FLOORING FREE OF GLAZING , FOR NATURAL VENTILATION STRUCTURAL GLAZING SYSTEM OF DOUBLE- GLAZING UNIT (DGU) GLASS, PROPOSED FOR ALL FLOORS ABOVE THE STILT FLOORS. STRUCTURAL FINS OF ALUMINIUM COATED PANEL (ACP) Using passive solar architecture for achieving thermal comfort through use of structural fins
  • 25. PROPOSAL INDICATIVE IMAGES (INTERIOR) CORRIDORS AND COMMON SPACES WITH FALSE CEILING AND FLOORING VDF FLOORING WITH ALL SERVICES IN THE BASEMENT AND STILT PARKING FLOORS OFFICE SPACES ROOF TOP CAFÉ
  • 27.
  • 28. OFFICE LOBBY ACCESS CONTROL LIFT LOBBY FOOD COURT SKY GARDEN SKY GARDEN
  • 29.
  • 30. PROPOSAL – Design Considerations
  • 31. Fifth floor to have Food Court, GYM, Store PROPOSAL – Design Considerations
  • 32. CONCEPT – infrastructure planning through bim
  • 40. APPROVAL & DESIGN Sl No. Scope of work I Statutory Approvals - BDA/ BMC, EC, AAI, WATCO, Any Other In Bidders Scope II Detailed Design Integrated with BIM Modelling up to LOD 400 In Bidders Scope
  • 41. SUMMARY OF SOIL STRATA & SBC
  • 42. STRUCTURE Description of Items Specification/detail RCC Framed Structure Design as per Seismic Zone-III. Pile Foundation, RCC Columns & Slabs with Column to Column distance of 6mtrs avg. The Bidder is allowed to optimize the design based on latest construction technology considering time and cost factor of the project and approval by IDCO
  • 43. BASIC COMPONENTS Sl No. Description of Items Specification/detail 1 Excavated Earth Disposal Upto 10 kilometers 2 RCC Framed Structure Design as per Seismic Zone-III. Pile Foundation, RCC Columns & Slabs with Column to Column distance of 6mtrs avg. 3 Reinforcement Steel Primary Steel 4 Brick Work Fly ash 5 Kota Stone Flooring Service Areas like Panel room & HVAC Room 6 Granite - Flooring & Cladding Staircase, Lift lobby, lift Façade, Refuse Area & Corridors 7 Tile Flooring Vitrified Tiles in Data center & Retail Floor 8 Toilet Tile Wok Vitrified Tiles in Toilets & Washrooms,
  • 44. Water proofing Water Proofing Treatment in Project Area 1 Below Foundation of Basements, Grade Slab, Drains, Sumps, Trenches, STP, Lift Pits. HDPE membrane of 1.2 mm thick conforming to IS 16471-2017 - rolled down on the shuttering /PCC prior to reinforcement casting and pouring the concrete. The membrane shall consists of a unique HDPE film pressure sensitive adhesive which allows poured concrete to bond fully with the membrane. The membrane shall be supplied with one self-adhesive selvedge to provide sealed laps. Tensile strength >21 MPa(ASTM 0412),Elongation > 400%, Peel Adhesion to concrete 880 N/m, Resistance to hydrostatic head > 70 mtr. 2 Basement Retaining Walls, UG Sump, STP, WTP and Lift Pits in contact with soil (External) 2mm thick self adhesive, self healing type SBS based membranes minimum puncture resistance, tensile resistance over 200%, Elongation over 45% as per IS 16525.T 3 Waterproofing Treatment For Terrace, Headroom, Open to Sky, OHT Slab. Single component pure polyurethane based elastomeric seamless liquid applied membrane:
  • 45. ELECTRICAL Sl No. Description of Items Specification/detail I Internal Electrical Work i Internal Electrical Work- Complete Complete Electrical Works in Parking ( 3B+5S =8 Floors), Data Center Floor (1st Floor), Retail Area (2nd Floor) & Reception area. ii Internal Electrical Work- Partial Distribution upto Electrical Panel Room of each Floor of Core Shell Area. Internal Distribution in Core Shell Area is not estimated in the Bidder's Scope II External Electrical Work Approval, Design and Execution for laying of 33 KV HT Line, Internal Substation & Complete accessories
  • 46. ELECTRICAL – LOAD TOTAL LOAD CALCULATION S.No Item Description Watt KW Diversity Load factor = 0.70 Total KVA 1 Load of fixtures of basement Floors 175515 175.515 122.8605 170.6 2 Load of fixtures of Stilt Floors 242300 242.3 169.61 235.6 3 Load of fixtures of Commercial Floors 1327200 1327.2 929.04 1290.3 4 HVAC Load -4000 ton 6002000 6002 4201.4 5835.3 5 Lift - 12 120000 120 84 116.7 6 Pumps 265000 265 185.5 257.6 7 Street light 3.30 0.0033 0.00231 0.0 8 External Electrical 10000 10 7 9.7 TOTAL LOAD CALCULATION 8142018 8142 5699 7916 Substation - 5X2000 KVA (4working +1Standby) Transformer capacity. DG Set capacity is 4 x 2500 KVA (Three running plus one standby)
  • 47. HVAC Sl No. Description of Items Specification/detail Remark HVAC System - 4000 TR Remarks i Option 01 Centralized Water Cooled Chiller System + Cooling Towers Capital Intensive. Ideal for single user. Incase of Multiple Users Collection of AMC charges is cumbersome ii Option 02 Centralized Cooling Towers + Decentrailzed Chillers Lesser Capital Intensive and provide flexibility to multiple users to design their own HVAC system with minimal AMC charges iii Option 03 VRF for each Floor Requires areas for installtion of VRF Units at designated/dedicated areas. Lesser Capital intensive but provides flexibility to multiple users.
  • 48. HVAC - load S.No. Floor No of Floors Workable/Off ice/Co- working Area (sqm) Area Details Recreational Area (sqm) Total Area (sqm) 1 Basement -3 1 0 NA 0 2 Basement -2 1 0 NA 0 3 Basement -1 1 0 NA 0 4 GF/Stilt Floor 1 278 Reception Area 0 278 5 1st Stilt 1 0 NA 0 6 2nd Stilt 1 0 NA 0 7 3rd Stilt 1 0 NA 0 8 4th Stilt 1 0 NA 0 9 1st Floor 1 3245 Data Center 0 3245 10 2nd Floor 1 0 GYM, SUPER MARKET/ RETAIL, CAFETERIA/ FOODCOURT 3609 3609 11 3rd & 4th Floors 2 2120 Office and Co- working Spaces 0 4240 12 5th, 6th, 7th, 9th, 10th, 12th & 13th Floors 7 3609 Office Area 0 25263 13 8th, 11th & 14th Floors 3 3168 Office Area 0 9504 14 15th Floor 1 2443 Office Area 1176 3619 Total Area for Air Conditioning (in sqm) 49758 CALCULATION OF AIR CONDITIONING Total Area for Chiller Air Conditioning Sqm A 49758 Area in Sqft Sqft B = A x 10.76 535396 Hence, Total TR required for Given Area is TR 4000
  • 49. FIREFIGHTING Sl No. Description of Items Specification/detail Fire Fighting & Alarm System i Fire Fighting & Alarm System - Complete Complete Fire Fighting Works in Parking ( 3B+5S =8 Floors), Data Center Floor (1st Floor), Retail Area (2nd Floor) & Reception area. (Sprinklers, hydrants, hose reel, smoke detector, alarm system, fire extinguishers, fire panel, pressurized air system in Lift well, lift lobby & staircase areas. ii Fire Fighting & Alarm System - Partial Internal distribution of firefighting system is not included in the scope of Bidder in core shell areas except common areas like corridors, lobby, staircases & refuse areas.
  • 50. CCTV Sl No. Description of Items Specification/detail CCTV SYSTEM i CCTV SYSTEM - Complete Complete CCTV Works in Parking ( 3B+5S =8 Floors), Data Center Floor (1st Floor), Retail Area (2nd Floor) & Reception area. ii CCTV SYSTEM - Partial Internal CCTV system is not included in the scope of Bidder in core shell areas except common areas like corridors, lobby, staircases & refuse areas.
  • 51. OTHER KEY ITEMS Sl No. Description of Items Specification/detail Remark 1 Solar Sytem Utilization of 50% terrace area for installing the Solar Power System. 130 KW 2 Lifts Passenger Lift - 8 No.s of passenger Lifts (16 Passenger) Service lift - 2 Nos of Service Lift Fire lift - 2 Nos Lift Size Passenger Lift- 1950 x 2550 mm Service lift - 3100 x 2200 mm Fire lift - 1800 x 2400 mm 3 Access Control System Provided in all areas except shell areas 4 IBMS System (Integrated Building Management System) Provided in all areas except shell areas 5 Elevation Facade Work Work includes complete Design, Engineering, Fabrication, Supply, installation including testing of materials and performance, quality control, storage, protection, transport, final cleaning & handover, maintenance & guarantees up to the defect notification period for the entire facade works.
  • 52. EXETERNAL DEVLOPMENT WORKS Sl No. Description of Items Specification/detail SITE DEVELOPMENT WORKS i Internal Road Cement Concrete (7.5 to 9m wide ) ii Compound Wall 1.8m height (from ground floor) as per elevation design iii Construction and Operation of Sewerage Treatment Plant 250 KLD including Operation and maintenance for 10 Years iv Under Ground water Reservoir 850 KLD