SlideShare a Scribd company logo
Second Report of the
High Level Committee on
Financing Infrastructure
GUJARAT NATIONAL LAW UNIVERSITY
Presented by: Jeel Langadia (16MB03)
Mani Dwivedi (16MB05)
Mayur Jaguwala (16mb07)
Context
• The rapid growth of the economy has placed increasing stress
on physical infrastructure in terms of capacity as well as
efficiency.
• Actual investments for Eleventh plan: Rs. 19 lakh crore
• Estimated investments forTwelfth plan: Rs. 45-50 lakh crore.
• Financing investment of this order required a review of the
existing policies as well as adoption of innovative ways of
financing.
• The High Level Committee on Financing
Infrastructure was thus formed.
Committee’s Objectives forTwelfth FiveYear
Plan
Assess investment in
ten major physical
infrastructure sectors
To suggest ways to
enable the requisite
flows of private
investment
To make recommendations
for government to develop
capital markets for
intermediating long- term
savings for investments
To examine the role of
international capital
flows in infrastructure
financing
To identify any regulatory/
legal impediments
constraining private
investment in
infrastructure
India ranks 85 out of 144
in infrastructure
investment.
India also lags other
countries in project
implementation.
Projects suffers from 20 to
25 per cent time and cost
over-runs.
Delays in projects due to
slow resolution processes.
Trend of Investment
Continued…
The pace of investment has not picked up even during 2013-14 and several bottlenecks and
barriers have continued to persist.
Thus, it was unlikely that theTwelfth Plan projections made earlier would materialise.
Thus, investment projections contained in the Interim Report need to be revised based on
actual investment in the Central sector during 2012-13 and revised estimates (RE) of 2013-14.
The total investment during theTwelfth Plan was now projected at Rs. 30,93,558 crore as
compared to Rs. 27,29,179 crore achieved during the Eleventh Plan at 2011-12 prices
Sectoral Projections
Sector Twelfth Plan
(Projected)
Eleventh Plan Public Sector Private Sector Expected
Growth (2012-
17)
Electricity Rs. 9,08,463
crore
Rs. 7,90,481
crore
Rs. 5,20,127
crore
Rs. 3,88,336 5%
Renewable
Energy
Rs. 1,70,628
crore
Rs. 1,02,004
crore
Rs. 25,652
crore
Rs. 1,44,976
crore
27% (Public)
21% (Private)
Roads &
Bridges
Rs. 5,82,598
crore
- Rs. 4,28,288
crore
Rs. 1,54,310
crore
14% (Public)
10% (Private)
Telecom Rs. 3,23,008
crore
Rs. 4,38,787
crore
Rs. 3,01,747
crore
2%
Railways Rs. 3,39,816
crore
Rs. 2,31,935
crore
Rs. 2,97,054
crore
Rs. 42,762
crore
11%
MRTS Rs. 1,06,866
crore
Rs. 49,184
crore
Rs. 72,304 crore Rs. 34,563
crore
34% (Public)
44%(Private)
Continued…
Sector Twelfth Plan
(Projected)
Eleventh Plan Public Sector Private Sector Expected
Growth (2012-
17)
Irrigation Rs. 2,92,708
crore
Rs. 2,66,375
crore
Rs. 2,92,708
crore
Negligible -
Water Supply
& Sanitation
Rs. 1,49,068
crore
Rs. 1,36,021
crore
Rs. 1,44,636
crore
Rs. 4,431 crore -
Ports Rs. 95,424 crore Rs. 55,347 crore Rs. 20,067 crore Rs. 75,360
crore
30% (Public)
26% (Private)
Airports Rs. 33,629 crore - Rs. 9,191 crore Rs. 24,438 crore 30% (Private)
Storage Rs.
39,948 crore
- Rs. 16,177 crore Rs. 23,771 crore 8% (Public)
40% (Private)
Oil & Gas
Pipelines
Rs. 51,403 crore - Rs. 33,764 crore Rs. 17,638 crore 46% (Public)
60% (Private)
Overarching Recommendations
• A reorientation of programmes and policies was vital for time-bound
delivery of world-class infrastructure.
• Therefore, Committee recommends the constitution of a council to guide
policy formulation with a view of attracting domestic and foreign
investment.
Infrastructure
Development Council
Chairmanship of
Prime Minister
Ministers of Finance
and infrastructure
Ministries and Deputy
Chairman, Planning
Commission
Continued...
Creation of an arbitral architecture
Dedicated to resolution of disputes
Disputes of infrastructure project
Address the role, functions and powers of
regulatory commissions
The manner of selection of regulators
The accountability of regulatory
commissions
Further, due to absence of credible dispute
resolution mechanism resulting in projects
delay and increased costs, Committee
recommends:
The Committee recommends a thorough
review and reform of the regulatory laws and
practices with a view to:
The Committee further recommends that:
The Government may take urgent action to ensure that project authorities honour their respective
contracts and discharge obligations.
The Land AcquisitionAct may be reviewed and suitably amended to cover land acquisition for all
infrastructure projects.
To review and modify lengthy and complex provisions in Land AcquisitionAct in order to ensure
expeditious commencement of the construction of infrastructure projects.
Increase in the tax-free infrastructure bonds.
RBI amended its prudential norms on Advances to Infrastructure Sector under which loans granted will
be classified as secured loan.
Equity
Funding
• Proactive action by Ministries to welcome Foreign Direct Investment (FDI)
• ForeignVenture Capital Investors to be allowed to invest.
• IIFCL's scheme to accelerate investment.
• Government policy reforms to attract larger flows of equity funding.
Refinancing
of Debt
• Setting up infrastructure debt funds (IDFs)
• Pre – payment of bank loan.
• Reinventing IIFCL for a larger role
RESTRUCRING
• NPA
• Debt services
• Bank loan
Particulars Problems Recommendation by
committee
1. Funding of Equity 1. Slowdown in fresh equity
investment due to over
leveraged balance sheet
2. International market also
flushed with liquidity.
1. Open foreign venture capital
to invest in India ‘’ core
investment companies’’.
2. Refinance of debt 1. Banks are deficient in long
term liabilities
2. Risk averse in long term fund.
1. RBI issued guidelines that
ensure debt finance in which risk
based ROI: - higher at
construction
lower at operation period
2. Forms IDFs , (to under take re
finance project loan).
Particulars Problems Recommendation by
committee
3. Restructuring of NPA 1.Viability of project period 20to
30 years but bank expect return
in 12-15 years.They declares
after period as NPA
RBI & department of Financial
Services closely examine special
characteristics on infrastructure
lending for NPA recognition.
4. Restructuring of Debt Services Bank lends upto 12to 15 year ,
and recover principle with
interest.
Payment through ‘’Bullet
Payment’’
5. Restructuring of Bank Loan For restructuring , provisioning is
required for infrastructure loan
by concerned bank.
But bank lends to limited short
period.
NO requirement of provisioning
by banks.
Debt paid before 3 years of
concession period.
Particular Problem Recommendation by committee
6. Development of Bond
Financing
FII’s don’t have trust over
infrastructure bond issued by
companies.
1. IIFCL Provide Guarantee for
specified infrastructure bond
2. IIFCL lends 20% of project cost
to approve projects
3. In order to raise in investment
govt. gives credit rating to
infra companies.to attract
FII’S.S
7. longTerm Finance Large Project finance period 25to
40 years ,
Risk to lender and investor.
1. Floating rate of interest.
2. Bond market creation.
.
• Framework for limited recourse lending:
Recommendation to bank strengthen the project appraisal processes by
knowing : 1. project sponsor have a adequate financial stake
2.The capital cost are reasonable.
3.The revenue Potential of Project is on realistic basis.
External Commercial Borrowing : 1. project can be re finance up to 25%of
project cost but don’t have NPA.
2. Ports & international airport 50% of project cost, with no time limit.
Tax free bond : TO Boost infrastructure Government issued tax free bond upto
30000 cr. to 60,000 cr. During period 2012to 2014.
The Committee recommends that the limit for issuance of such bonds during
the financial year 2014-15 be increased to Rs.1,00,000 crore.
Sectorial Recommendations
for Reviving Investment
Power
• Open Access and competition
• Revisiting the tariff structure
• Public Private Participation (PPP) in distribution
• Debt relief for stranded projects.
COAL SUPPLY
• Operationalise PPP in Coal Mining
• Turn-key implementation of critical railway lines
HIGHWAYS
• Manage aggressive bidding
• Expedite roll-out of PPP projects
• Operationalise the Expressway programme
RAILWAYS
• Restructuring of the Railway Board
• Private investment through PPP
• Financing of viable projects by IRFC
URBAN INFRASTRUCTURE
• AdditionalVGF under JNNURM
• Attract more private investment in MRTS
• Private investment in water supply
IRRIGATION
• Private participation in irrigation
PORTS
• Expedite award of projects
• Deregulation of tariffs
• Reduction in dwell time
• Private participation in inland waterways
AIRPORTS
• Expedite award of Greenfield airports
• Management and Operation of metro airports
• Management and operation of non-metro Airports
• Tariff Regulation
STORAGE
• Creation of modern storage
Conclusion
Devise a time bound
action plan to address
recommendations
Improvement
in roll-out PPP
projects
Monthly monitoring
of the
implementation of
recommendations to
avoid delays

More Related Content

What's hot

Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private PartnershipDeepti Mahajan
 
DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4
Resurgent India
 
FINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIA
FINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIAFINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIA
FINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIA
IAEME Publication
 
Pooled Finance Development Fund
Pooled Finance Development FundPooled Finance Development Fund
Pooled Finance Development Fund
Prasad Thanthratey
 
RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...
RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...
RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...
Rail~Volution
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arunKartikeya Pandey
 
A Basic guide to Infrastructure Business and Financing in India by Netz Capit...
A Basic guide to Infrastructure Business and Financing in India by Netz Capit...A Basic guide to Infrastructure Business and Financing in India by Netz Capit...
A Basic guide to Infrastructure Business and Financing in India by Netz Capit...
atulpkhekade
 
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Lynn Aziz
 
Public infra financing in india
Public infra financing in indiaPublic infra financing in india
Public infra financing in india
Sumeet Sharma PMP
 
Infrastructure financing guide india netz capital
Infrastructure financing guide india netz capitalInfrastructure financing guide india netz capital
Infrastructure financing guide india netz capital
Atul Khekade
 
Road ppt 14 12 15 final
Road ppt 14 12 15 finalRoad ppt 14 12 15 final
Road ppt 14 12 15 final
arpitgoel075
 
The National Treasury, PPP Unit Health Infrastructure Development and Servi...
The National Treasury, PPP Unit   Health Infrastructure Development and Servi...The National Treasury, PPP Unit   Health Infrastructure Development and Servi...
The National Treasury, PPP Unit Health Infrastructure Development and Servi...
Emmanuel Mosoti Machani
 
Mobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS InfrastructureMobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS Infrastructure
Pratish Halady
 
Surface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & IssuesSurface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & Issues
New York Public Transit Association
 
Scheme for Financial Support to Public Private Partnership in Infrastructure
Scheme for Financial Support to Public Private Partnership in InfrastructureScheme for Financial Support to Public Private Partnership in Infrastructure
Scheme for Financial Support to Public Private Partnership in Infrastructure
Our Vibrant Gujarat
 
Experience of GCCIA in developing GCC Regional Electricity Market
Experience of GCCIA in developing GCC Regional Electricity MarketExperience of GCCIA in developing GCC Regional Electricity Market
Experience of GCCIA in developing GCC Regional Electricity Market
Power System Operation
 
CII Policy Watch July 2015
CII Policy Watch July 2015CII Policy Watch July 2015
CII Policy Watch July 2015
Confederation of Indian Industry
 
MAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack SchenendorfMAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack Schenendorf
nssga
 
Gavin Stoddart - Presentation. Vladivostok january 2013 25 01
Gavin Stoddart - Presentation. Vladivostok january 2013 25 01Gavin Stoddart - Presentation. Vladivostok january 2013 25 01
Gavin Stoddart - Presentation. Vladivostok january 2013 25 01
Инесса Бабич
 

What's hot (20)

Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private Partnership
 
FMOC Report
FMOC ReportFMOC Report
FMOC Report
 
DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4
 
FINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIA
FINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIAFINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIA
FINANCIAL VIABILITY OF BOT ROAD PROJECTS IN INDIA
 
Pooled Finance Development Fund
Pooled Finance Development FundPooled Finance Development Fund
Pooled Finance Development Fund
 
RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...
RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...
RV 2014: Show Me the Money- Federal Funding in a Non-Earmark World (Federal F...
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
 
A Basic guide to Infrastructure Business and Financing in India by Netz Capit...
A Basic guide to Infrastructure Business and Financing in India by Netz Capit...A Basic guide to Infrastructure Business and Financing in India by Netz Capit...
A Basic guide to Infrastructure Business and Financing in India by Netz Capit...
 
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
 
Public infra financing in india
Public infra financing in indiaPublic infra financing in india
Public infra financing in india
 
Infrastructure financing guide india netz capital
Infrastructure financing guide india netz capitalInfrastructure financing guide india netz capital
Infrastructure financing guide india netz capital
 
Road ppt 14 12 15 final
Road ppt 14 12 15 finalRoad ppt 14 12 15 final
Road ppt 14 12 15 final
 
The National Treasury, PPP Unit Health Infrastructure Development and Servi...
The National Treasury, PPP Unit   Health Infrastructure Development and Servi...The National Treasury, PPP Unit   Health Infrastructure Development and Servi...
The National Treasury, PPP Unit Health Infrastructure Development and Servi...
 
Mobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS InfrastructureMobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS Infrastructure
 
Surface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & IssuesSurface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & Issues
 
Scheme for Financial Support to Public Private Partnership in Infrastructure
Scheme for Financial Support to Public Private Partnership in InfrastructureScheme for Financial Support to Public Private Partnership in Infrastructure
Scheme for Financial Support to Public Private Partnership in Infrastructure
 
Experience of GCCIA in developing GCC Regional Electricity Market
Experience of GCCIA in developing GCC Regional Electricity MarketExperience of GCCIA in developing GCC Regional Electricity Market
Experience of GCCIA in developing GCC Regional Electricity Market
 
CII Policy Watch July 2015
CII Policy Watch July 2015CII Policy Watch July 2015
CII Policy Watch July 2015
 
MAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack SchenendorfMAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack Schenendorf
 
Gavin Stoddart - Presentation. Vladivostok january 2013 25 01
Gavin Stoddart - Presentation. Vladivostok january 2013 25 01Gavin Stoddart - Presentation. Vladivostok january 2013 25 01
Gavin Stoddart - Presentation. Vladivostok january 2013 25 01
 

Similar to SECOND high level commitie report ON INFRASTRUCTURE PROJECT

Budget FY16-17 : An opportunity to revitalise the infrastructure sector
Budget FY16-17 : An opportunity to revitalise the infrastructure sectorBudget FY16-17 : An opportunity to revitalise the infrastructure sector
Budget FY16-17 : An opportunity to revitalise the infrastructure sector
Zubin Poonawalla
 
Indian budget 2011 2012
Indian budget 2011 2012Indian budget 2011 2012
Indian budget 2011 2012
abhishek mittal
 
Saji sir ready
Saji sir readySaji sir ready
Saji sir readykishanb79
 
Debt restructuring options_adani
Debt restructuring options_adaniDebt restructuring options_adani
Debt restructuring options_adanikalpesh7777
 
Redefining Infrastructure A Pathway For Future
Redefining Infrastructure A Pathway For FutureRedefining Infrastructure A Pathway For Future
Redefining Infrastructure A Pathway For Future
Indus Law
 
Chapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojectsChapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojects
AKSHAYA0000
 
Sectoral Infrastructure Development
Sectoral Infrastructure DevelopmentSectoral Infrastructure Development
Sectoral Infrastructure Development
GAURAV. H .TANDON
 
National monetisation pipeline
National monetisation pipelineNational monetisation pipeline
National monetisation pipeline
Col Mukteshwar Prasad
 
Emerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersEmerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersAnil Kumar Gupta
 
National monetisation project by Bhawna Bhardwaj
National monetisation project by Bhawna BhardwajNational monetisation project by Bhawna Bhardwaj
National monetisation project by Bhawna Bhardwaj
BhawnaBhardwaj24
 
National monetisation project
National monetisation projectNational monetisation project
National monetisation project
BhawnaBhardwaj24
 
Ecb
Ecb Ecb
Bot(build operate transfr)
Bot(build operate transfr)Bot(build operate transfr)
Bot(build operate transfr)
Kritika Garg
 
SREI Infrastructure Finance Research Report
SREI Infrastructure Finance Research ReportSREI Infrastructure Finance Research Report
SREI Infrastructure Finance Research Report
Peeyush Sahu CAPM®
 
Atma nirbhar bharat full presentation
Atma nirbhar bharat full presentation Atma nirbhar bharat full presentation
Atma nirbhar bharat full presentation
Vikas Barnwal
 
Expectations from Union Budget 2016
Expectations from Union Budget 2016Expectations from Union Budget 2016
Expectations from Union Budget 2016
Abhirup Lahiri
 
Public private partnership in development of road network
Public private partnership in development of road networkPublic private partnership in development of road network
Public private partnership in development of road network
Gokul K Prasad
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
Ankit GAJJAR
 

Similar to SECOND high level commitie report ON INFRASTRUCTURE PROJECT (20)

Budget FY16-17 : An opportunity to revitalise the infrastructure sector
Budget FY16-17 : An opportunity to revitalise the infrastructure sectorBudget FY16-17 : An opportunity to revitalise the infrastructure sector
Budget FY16-17 : An opportunity to revitalise the infrastructure sector
 
Indian budget 2011 2012
Indian budget 2011 2012Indian budget 2011 2012
Indian budget 2011 2012
 
Saji sir ready
Saji sir readySaji sir ready
Saji sir ready
 
Debt restructuring options_adani
Debt restructuring options_adaniDebt restructuring options_adani
Debt restructuring options_adani
 
Redefining Infrastructure A Pathway For Future
Redefining Infrastructure A Pathway For FutureRedefining Infrastructure A Pathway For Future
Redefining Infrastructure A Pathway For Future
 
Chapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojectsChapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojects
 
Sectoral Infrastructure Development
Sectoral Infrastructure DevelopmentSectoral Infrastructure Development
Sectoral Infrastructure Development
 
National monetisation pipeline
National monetisation pipelineNational monetisation pipeline
National monetisation pipeline
 
Emerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersEmerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway Engineers
 
National monetisation project by Bhawna Bhardwaj
National monetisation project by Bhawna BhardwajNational monetisation project by Bhawna Bhardwaj
National monetisation project by Bhawna Bhardwaj
 
National monetisation project
National monetisation projectNational monetisation project
National monetisation project
 
phase 4.pdf
phase 4.pdfphase 4.pdf
phase 4.pdf
 
Ecb
Ecb Ecb
Ecb
 
Bot(build operate transfr)
Bot(build operate transfr)Bot(build operate transfr)
Bot(build operate transfr)
 
SREI Infrastructure Finance Research Report
SREI Infrastructure Finance Research ReportSREI Infrastructure Finance Research Report
SREI Infrastructure Finance Research Report
 
Atma nirbhar bharat full presentation
Atma nirbhar bharat full presentation Atma nirbhar bharat full presentation
Atma nirbhar bharat full presentation
 
Expectations from Union Budget 2016
Expectations from Union Budget 2016Expectations from Union Budget 2016
Expectations from Union Budget 2016
 
Public private partnership in development of road network
Public private partnership in development of road networkPublic private partnership in development of road network
Public private partnership in development of road network
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
 
Iifcl ppt
Iifcl pptIifcl ppt
Iifcl ppt
 

Recently uploaded

Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit CardPoonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
nickysharmasucks
 
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
muslimdavidovich670
 
GeM ppt in railway for presentation on gem
GeM ppt in railway  for presentation on gemGeM ppt in railway  for presentation on gem
GeM ppt in railway for presentation on gem
CwierAsn
 
655264371-checkpoint-science-past-papers-april-2023.pdf
655264371-checkpoint-science-past-papers-april-2023.pdf655264371-checkpoint-science-past-papers-april-2023.pdf
655264371-checkpoint-science-past-papers-april-2023.pdf
morearsh02
 
what is the best method to sell pi coins in 2024
what is the best method to sell pi coins in 2024what is the best method to sell pi coins in 2024
what is the best method to sell pi coins in 2024
DOT TECH
 
234Presentation on Indian Debt Market.ppt
234Presentation on Indian Debt Market.ppt234Presentation on Indian Debt Market.ppt
234Presentation on Indian Debt Market.ppt
PravinPatil144525
 
Webinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont BraunWebinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont Braun
FinTech Belgium
 
What website can I sell pi coins securely.
What website can I sell pi coins securely.What website can I sell pi coins securely.
What website can I sell pi coins securely.
DOT TECH
 
Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...
Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...
Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...
beulahfernandes8
 
what is the future of Pi Network currency.
what is the future of Pi Network currency.what is the future of Pi Network currency.
what is the future of Pi Network currency.
DOT TECH
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
marketing367770
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
DOT TECH
 
Chương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdfChương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdf
va2132004
 
How to get verified on Coinbase Account?_.docx
How to get verified on Coinbase Account?_.docxHow to get verified on Coinbase Account?_.docx
How to get verified on Coinbase Account?_.docx
Buy bitget
 
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdfWhich Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Kezex (KZX)
 
BYD SWOT Analysis and In-Depth Insights 2024.pptx
BYD SWOT Analysis and In-Depth Insights 2024.pptxBYD SWOT Analysis and In-Depth Insights 2024.pptx
BYD SWOT Analysis and In-Depth Insights 2024.pptx
mikemetalprod
 
Introduction to Value Added Tax System.ppt
Introduction to Value Added Tax System.pptIntroduction to Value Added Tax System.ppt
Introduction to Value Added Tax System.ppt
VishnuVenugopal84
 
Introduction to Indian Financial System ()
Introduction to Indian Financial System ()Introduction to Indian Financial System ()
Introduction to Indian Financial System ()
Avanish Goel
 
PF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptxPF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptx
GunjanSharma28848
 
Commercial Bank Economic Capsule - May 2024
Commercial Bank Economic Capsule - May 2024Commercial Bank Economic Capsule - May 2024
Commercial Bank Economic Capsule - May 2024
Commercial Bank of Ceylon PLC
 

Recently uploaded (20)

Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit CardPoonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
 
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
 
GeM ppt in railway for presentation on gem
GeM ppt in railway  for presentation on gemGeM ppt in railway  for presentation on gem
GeM ppt in railway for presentation on gem
 
655264371-checkpoint-science-past-papers-april-2023.pdf
655264371-checkpoint-science-past-papers-april-2023.pdf655264371-checkpoint-science-past-papers-april-2023.pdf
655264371-checkpoint-science-past-papers-april-2023.pdf
 
what is the best method to sell pi coins in 2024
what is the best method to sell pi coins in 2024what is the best method to sell pi coins in 2024
what is the best method to sell pi coins in 2024
 
234Presentation on Indian Debt Market.ppt
234Presentation on Indian Debt Market.ppt234Presentation on Indian Debt Market.ppt
234Presentation on Indian Debt Market.ppt
 
Webinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont BraunWebinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont Braun
 
What website can I sell pi coins securely.
What website can I sell pi coins securely.What website can I sell pi coins securely.
What website can I sell pi coins securely.
 
Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...
Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...
Exploring Abhay Bhutada’s Views After Poonawalla Fincorp’s Collaboration With...
 
what is the future of Pi Network currency.
what is the future of Pi Network currency.what is the future of Pi Network currency.
what is the future of Pi Network currency.
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
 
Chương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdfChương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdf
 
How to get verified on Coinbase Account?_.docx
How to get verified on Coinbase Account?_.docxHow to get verified on Coinbase Account?_.docx
How to get verified on Coinbase Account?_.docx
 
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdfWhich Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
 
BYD SWOT Analysis and In-Depth Insights 2024.pptx
BYD SWOT Analysis and In-Depth Insights 2024.pptxBYD SWOT Analysis and In-Depth Insights 2024.pptx
BYD SWOT Analysis and In-Depth Insights 2024.pptx
 
Introduction to Value Added Tax System.ppt
Introduction to Value Added Tax System.pptIntroduction to Value Added Tax System.ppt
Introduction to Value Added Tax System.ppt
 
Introduction to Indian Financial System ()
Introduction to Indian Financial System ()Introduction to Indian Financial System ()
Introduction to Indian Financial System ()
 
PF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptxPF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptx
 
Commercial Bank Economic Capsule - May 2024
Commercial Bank Economic Capsule - May 2024Commercial Bank Economic Capsule - May 2024
Commercial Bank Economic Capsule - May 2024
 

SECOND high level commitie report ON INFRASTRUCTURE PROJECT

  • 1. Second Report of the High Level Committee on Financing Infrastructure GUJARAT NATIONAL LAW UNIVERSITY Presented by: Jeel Langadia (16MB03) Mani Dwivedi (16MB05) Mayur Jaguwala (16mb07)
  • 2. Context • The rapid growth of the economy has placed increasing stress on physical infrastructure in terms of capacity as well as efficiency. • Actual investments for Eleventh plan: Rs. 19 lakh crore • Estimated investments forTwelfth plan: Rs. 45-50 lakh crore. • Financing investment of this order required a review of the existing policies as well as adoption of innovative ways of financing. • The High Level Committee on Financing Infrastructure was thus formed.
  • 3. Committee’s Objectives forTwelfth FiveYear Plan Assess investment in ten major physical infrastructure sectors To suggest ways to enable the requisite flows of private investment To make recommendations for government to develop capital markets for intermediating long- term savings for investments To examine the role of international capital flows in infrastructure financing To identify any regulatory/ legal impediments constraining private investment in infrastructure
  • 4. India ranks 85 out of 144 in infrastructure investment. India also lags other countries in project implementation. Projects suffers from 20 to 25 per cent time and cost over-runs. Delays in projects due to slow resolution processes.
  • 6. Continued… The pace of investment has not picked up even during 2013-14 and several bottlenecks and barriers have continued to persist. Thus, it was unlikely that theTwelfth Plan projections made earlier would materialise. Thus, investment projections contained in the Interim Report need to be revised based on actual investment in the Central sector during 2012-13 and revised estimates (RE) of 2013-14. The total investment during theTwelfth Plan was now projected at Rs. 30,93,558 crore as compared to Rs. 27,29,179 crore achieved during the Eleventh Plan at 2011-12 prices
  • 7. Sectoral Projections Sector Twelfth Plan (Projected) Eleventh Plan Public Sector Private Sector Expected Growth (2012- 17) Electricity Rs. 9,08,463 crore Rs. 7,90,481 crore Rs. 5,20,127 crore Rs. 3,88,336 5% Renewable Energy Rs. 1,70,628 crore Rs. 1,02,004 crore Rs. 25,652 crore Rs. 1,44,976 crore 27% (Public) 21% (Private) Roads & Bridges Rs. 5,82,598 crore - Rs. 4,28,288 crore Rs. 1,54,310 crore 14% (Public) 10% (Private) Telecom Rs. 3,23,008 crore Rs. 4,38,787 crore Rs. 3,01,747 crore 2% Railways Rs. 3,39,816 crore Rs. 2,31,935 crore Rs. 2,97,054 crore Rs. 42,762 crore 11% MRTS Rs. 1,06,866 crore Rs. 49,184 crore Rs. 72,304 crore Rs. 34,563 crore 34% (Public) 44%(Private)
  • 8. Continued… Sector Twelfth Plan (Projected) Eleventh Plan Public Sector Private Sector Expected Growth (2012- 17) Irrigation Rs. 2,92,708 crore Rs. 2,66,375 crore Rs. 2,92,708 crore Negligible - Water Supply & Sanitation Rs. 1,49,068 crore Rs. 1,36,021 crore Rs. 1,44,636 crore Rs. 4,431 crore - Ports Rs. 95,424 crore Rs. 55,347 crore Rs. 20,067 crore Rs. 75,360 crore 30% (Public) 26% (Private) Airports Rs. 33,629 crore - Rs. 9,191 crore Rs. 24,438 crore 30% (Private) Storage Rs. 39,948 crore - Rs. 16,177 crore Rs. 23,771 crore 8% (Public) 40% (Private) Oil & Gas Pipelines Rs. 51,403 crore - Rs. 33,764 crore Rs. 17,638 crore 46% (Public) 60% (Private)
  • 9. Overarching Recommendations • A reorientation of programmes and policies was vital for time-bound delivery of world-class infrastructure. • Therefore, Committee recommends the constitution of a council to guide policy formulation with a view of attracting domestic and foreign investment. Infrastructure Development Council Chairmanship of Prime Minister Ministers of Finance and infrastructure Ministries and Deputy Chairman, Planning Commission
  • 10. Continued... Creation of an arbitral architecture Dedicated to resolution of disputes Disputes of infrastructure project Address the role, functions and powers of regulatory commissions The manner of selection of regulators The accountability of regulatory commissions Further, due to absence of credible dispute resolution mechanism resulting in projects delay and increased costs, Committee recommends: The Committee recommends a thorough review and reform of the regulatory laws and practices with a view to:
  • 11. The Committee further recommends that: The Government may take urgent action to ensure that project authorities honour their respective contracts and discharge obligations. The Land AcquisitionAct may be reviewed and suitably amended to cover land acquisition for all infrastructure projects. To review and modify lengthy and complex provisions in Land AcquisitionAct in order to ensure expeditious commencement of the construction of infrastructure projects. Increase in the tax-free infrastructure bonds. RBI amended its prudential norms on Advances to Infrastructure Sector under which loans granted will be classified as secured loan.
  • 12. Equity Funding • Proactive action by Ministries to welcome Foreign Direct Investment (FDI) • ForeignVenture Capital Investors to be allowed to invest. • IIFCL's scheme to accelerate investment. • Government policy reforms to attract larger flows of equity funding. Refinancing of Debt • Setting up infrastructure debt funds (IDFs) • Pre – payment of bank loan. • Reinventing IIFCL for a larger role RESTRUCRING • NPA • Debt services • Bank loan
  • 13. Particulars Problems Recommendation by committee 1. Funding of Equity 1. Slowdown in fresh equity investment due to over leveraged balance sheet 2. International market also flushed with liquidity. 1. Open foreign venture capital to invest in India ‘’ core investment companies’’. 2. Refinance of debt 1. Banks are deficient in long term liabilities 2. Risk averse in long term fund. 1. RBI issued guidelines that ensure debt finance in which risk based ROI: - higher at construction lower at operation period 2. Forms IDFs , (to under take re finance project loan).
  • 14. Particulars Problems Recommendation by committee 3. Restructuring of NPA 1.Viability of project period 20to 30 years but bank expect return in 12-15 years.They declares after period as NPA RBI & department of Financial Services closely examine special characteristics on infrastructure lending for NPA recognition. 4. Restructuring of Debt Services Bank lends upto 12to 15 year , and recover principle with interest. Payment through ‘’Bullet Payment’’ 5. Restructuring of Bank Loan For restructuring , provisioning is required for infrastructure loan by concerned bank. But bank lends to limited short period. NO requirement of provisioning by banks. Debt paid before 3 years of concession period.
  • 15. Particular Problem Recommendation by committee 6. Development of Bond Financing FII’s don’t have trust over infrastructure bond issued by companies. 1. IIFCL Provide Guarantee for specified infrastructure bond 2. IIFCL lends 20% of project cost to approve projects 3. In order to raise in investment govt. gives credit rating to infra companies.to attract FII’S.S 7. longTerm Finance Large Project finance period 25to 40 years , Risk to lender and investor. 1. Floating rate of interest. 2. Bond market creation.
  • 16. . • Framework for limited recourse lending: Recommendation to bank strengthen the project appraisal processes by knowing : 1. project sponsor have a adequate financial stake 2.The capital cost are reasonable. 3.The revenue Potential of Project is on realistic basis. External Commercial Borrowing : 1. project can be re finance up to 25%of project cost but don’t have NPA. 2. Ports & international airport 50% of project cost, with no time limit. Tax free bond : TO Boost infrastructure Government issued tax free bond upto 30000 cr. to 60,000 cr. During period 2012to 2014. The Committee recommends that the limit for issuance of such bonds during the financial year 2014-15 be increased to Rs.1,00,000 crore.
  • 18. Power • Open Access and competition • Revisiting the tariff structure • Public Private Participation (PPP) in distribution • Debt relief for stranded projects. COAL SUPPLY • Operationalise PPP in Coal Mining • Turn-key implementation of critical railway lines HIGHWAYS • Manage aggressive bidding • Expedite roll-out of PPP projects • Operationalise the Expressway programme
  • 19.
  • 20. RAILWAYS • Restructuring of the Railway Board • Private investment through PPP • Financing of viable projects by IRFC URBAN INFRASTRUCTURE • AdditionalVGF under JNNURM • Attract more private investment in MRTS • Private investment in water supply IRRIGATION • Private participation in irrigation
  • 21. PORTS • Expedite award of projects • Deregulation of tariffs • Reduction in dwell time • Private participation in inland waterways AIRPORTS • Expedite award of Greenfield airports • Management and Operation of metro airports • Management and operation of non-metro Airports • Tariff Regulation STORAGE • Creation of modern storage
  • 22. Conclusion Devise a time bound action plan to address recommendations Improvement in roll-out PPP projects Monthly monitoring of the implementation of recommendations to avoid delays

Editor's Notes

  1. POWER Open Access and competition - SERCs should only fix the wheeling charge and open access surcharge in accordance with the Tariff Policy notified by the Central Government. - 75 per cent of the Centre's discretionary allocation comprising 15 per cent of CPSUs' available for direct sale by CPSUs to open access consumers. – Introduction of competition in the market – reduce the monopoly in the market. – open access in place, generating companies will be able to produce more electricity at market prices and sell directly to bulk consumers at mutually negotiated prices. Revisiting the tariff structure - consumer tariffs be rationalised and graded according to capacity to pay. The smaller households may be charged a lower tariff , high income households, commercial consumers and industries should be gradually moved to market-based pricing where these consumers may be enabled to choose from among competing supplies of electricity. Public Private Participation (PPP) in distribution – framework should be adopted by the States for cities and larger towns in the first instance. The Central Government may provide Viability Gap Funding and other support for this purpose. Debt relief for stranded projects - Large volumes of private investment are under stress because of short supply of coal and gas. - Due to this production reduces and the normal loss increase like fixed cost, like salary etc. large number of power projects are likely to become non-performing assets (NPAs), if some relief is not provided by way of restructuring or rescheduling of their loans. COAL SUPPLY Operationalise PPP in Coal Mining - With the addition of ~65 GW of incremental coal based capacity in Twelfth Plan, a short fall of 100-120 MTPA of coal is expected. It is also unsustainable from the perspective of managing the current account deficit. The Government had constituted an Inter- Ministerial Group (IMG) for finalising a Model Concession Agreement (MCA) for enabling PPP in coal mining. MCA after extensive consultations with experts and stakeholders. Under this model, the coal mine as well the coal will remain in the ownership of the public sector, while the private partner will receive a mining charge on the coal mined. The sale of such coal will be undertaken by the public entity which grants the PPP concession Agreement. Existing mines of CIL, which are yet to be explored, may also be transferred to the new company. Turn-key implementation of critical railway Line - Ib Valley in Odisha, North Karanpura in Jharkhand and Mand-Raigarh in Chhattisgarhenvisage major coal production during the Twelfth Plan and beyond. Accordingly, three critical railway line projects namely Tori- Shivpuri-Kathautia in Jharkhand, Bhupdeopur- Korba-Dharamjai in Chhattisgarh and Barpali- Jharsuguda in Odisha have been taken up for implantation. HIGHWAYS Manage aggressive bidding - The international best practice is to prequalify and shortlist 3 to 5 bidders for the final stage of bidding. This is necessary because the final round of bidding for PPP/EPC (turnkey) projects requires significant investment in time and resources for submission of competitive bids. In USA, a Federal law prescribes a ceiling of 5 shortlisted bidders for the final round of bidding in such projects. - practice of shortlisting of bidders which was initially adopted in the PPP model framework, but was later put in abeyance, may be restored, especially for the highway sector. Expedite roll-out of PPP projects - During the year 2013-14, NHAI has awarded just 1215 km consisting of two PPP projects against a target of 9,000 km. In the previous year also, only 1,116 km were awarded against a target of 9,500 km. The Committee recommends that NHAI should draw up a month-wise plan to award 5,000 km in 2014-15 and 10,000 km in 2015-16. This will be possible only if NHAI is able to undertake a sustained roll-out of projects which are financially viable and bankable, given the expected toll revenues. Operationalise the Expressway programme – promote expressway infrastructure more and more. Revision of Total Project Cost - the weighted average inflation in key commodities (bitumen, steel, labour) used in highway construction has been much higher than the WPI. The Committee recommends that keeping in view the principle of cost neutralization as embodied in the MCA, the TPC may be revised based on a formula that captures inflation of key cost drivers of road construction.
  2. RAILWAYS Turnaround of Indian Railways - facing serious problems such as inadequate investment, diminishing efficiency, falling safety standards and declining share in freight and passenger traffic. Restructuring of the Railway Board - Railway Board on commercial lines to enable investments and growth in the railways which otherwise seems sluggish. The Committee also recommends creation of a post of Member (PPP) in railways board who would be responsible for project conceptualisation, development and processing of all PPP projects to facilitate their speedy sanction by the Government and award of concessions. Private investment through PPP - private investment which constitutes about 5 per cent of its total investment. (i) Modernisation of Railway stations, Elevated suburban corridors in Mumbai, Development of new freight corridors, Development of logistics parks, Port connectivity projects, and Manufacturing of diesel and electric engines, coaches and wagons. Financing of viable projects by IRFC - the IRFC has somehow limited its mandate to leasing of rolling stock to the Railways whereas it should serve the broader objectives for which it was created. Some of the projects that should qualify for IRFC financing include viable electrification and signalling schemes, railway lines etc. The Committee recommends that Railway Ministry should formulate viable project proposals and award them on a turnkey basis to be financed by IRFC. URBAN INFRASTRUCTURE Additional VGF under JNNURM – JNNURM emphasises the need for harnessing private investment for financing urban infrastructure projects, the Government has not yet spelt out any mechanism or scheme under which private investment can be incentivised. - The only financial incentive currently being provided for PPP projects in urban infrastructure is a capital grant of up to 20 per cent of the capital cost under the ongoing Viability Gap Funding (VGF) Scheme. VGF grants under the extant VGF Scheme should also be eligible for a matching grant of 20 per cent under the JNNURM. This would imply that the Central Government would provide up to 40 per cent of capital grant for financing PPP projects in urban infrastructure. In addition, the State Governments may be required to provide capital grants or subordinated interest-free debt of up to 20 per cent of project cost for further improving the viability and bankability of such PPP projects. Attract more private investment in MRTS - The success Second Report of the High Level Committee of PPP mode in attracting private capital has already been demonstrated in the Hyderabad and Mumbai MRTS projects though some difficulties seem to have arisen in implementation of both these projects - with adequate cross-subsidisation from real estate so that the available budgetary resources can be better leveraged for a larger MRTS programme. The Committee also recommends that a VGF grant of 20 per cent of the total project cost should be provided out of JNNURM funds (in addition to the 20 per cent presently available under the extant VGF scheme) to improve the financial viability of PPP projects in this sector. Private investment in water supply - There is a need to encourage private participation in upgrading and modernising urban water supply and sanitation. PPP approach, nor are they able to rationalise the user charges and ensure supply of quality drinking water. PPP should be made an integral part of the strategy for water supply and sanitation projects under the JNNURM. The Committee also recommends that a VGF grant of 20 per cent of the total project cost should be provided out of JNNURM funds (in addition to the 20 per cent presently available under the extant VGF scheme) to improve the financial viability of PPP projects in this sector. IRRIGATION Private participation in irrigation - The model of USA where about 98 per cent of the dams have been built by the private sector could be explored in India through some pilot projects. Since part of the water from these dams would be allocated for industrial and urban purposes, user charges could be calibrated to improve viability. The Government could also provide the requisite grants to bridge the gap in financial viability of such projects. Sprinkler and drip irrigation improve water use efficiency very significantly. Development of clusters of sprinkler/drip irrigation could be undertaken through PPP to provide a boost to growth in food production and farmers' income. The Committee, therefore, recommends the adoption of PPP mode for financing medium and micro irrigation schemes.
  3. PORTS Expedite award of projects - As against the target of 512 MMT, capacity addition in major ports during the Eleventh Plan was only 185 MMT. The non major ports in the state sector performed relatively better by adding 257 MMT against the target of 347 MMT. The poor performance of major ports was due to award of only 20 PPP projects against a target of 49 projects during the Eleventh Plan. Deregulation of tariffs - The existing method of fixing tariffs by TAMP is contrary to international best practice and leads to various anomalies. – Reduction in dwell time - there is a need to modernise the technology and processes to bring dwell time at par with international standards. The Committee recommends that the Government should announce a time bound action plan for reduction in dwell time. Capital dredging. - Several Indian ports suffer from low drafts which prevent entry of large modern vessels. The Committee recommends that the Ministry of Shipping should accelerate the pace of capital dredging and where the project size is large, private participation may also be explored along with the provision of VGF, where necessary. Private participation in inland waterways - private participation in the development and operation of inland waterways. The Government should finalise and adopt the regulatory and contractual framework to enable PPP projects in financing, construction and operation of inland waterways. AIRPORTS Expedite award of Greenfield airports - The Committee recommends that the three greenfield airports at Navi Mumbai, Goa and Chandigarh, which have been identified for development through PPP, may be awarded within six months. Management and Operation of metro airports - Management and operation of non-metro - airports Many of these airports would also require further investments. The Committee recommends that the development and operation of both airside and city side facilities at the 10 non-metro airports in Jaipur, Lucknow, Amritsar, Bhubaneswar, Guwhati, Coimbatore, Varanasi, Gaya, Udaipur, and Tuticorin, may be undertaken through PPP. Tariff Regulation - Airports Economic Regulatory Authority (AERA) may be advised by the Central Government to establish a regulatory framework that ensures economic and competitive costs, as distinct from 'cost plus' tariffs. For this purpose, AERA may adopt international best practices and also draw from the experience in other infrastructure sectors in India. STORAGE – Creation of modern storage - Shortage of modern storage capacity has caused a significant loss of food grains. Sole reliance on FCI as well as the absence of a viable model has hampered the creation of modern storage capacity. The Committee recommends that the programme for creating 2 MT of Silo storage through PPP may be implemented expeditiously through FCI as well as the State Governments within agreed timelines to be announced by the Government.