The Taco Solar Pumping Station (SPS) combine all the features needed for a closed loop solar
water heating system. Just 5 easy connections to make; 2 for the solar collector(s), 2 for the
storage tank’s heat exchanger and 1 for the expansion tank. The Solar Pumping Station
includes a circulator with an integral variable speed solar control, isolation ball vales, air
elimination, flow meter and a safety group.



                          To Solar
                          Collector                                               Pressure Relief

                                                                                 Pressure Gauge

                                                                                 Expansion Tank
                                                                                     Connection
                                                                          Return Temp Gauge &
                                                                                 Shut-Off Valve
                                                                          Supply Temp Gauge &
                                                                                 Shut-Off Valve

                                                                            Air Eliminator & Vent



                                                                               Circulating Pump
                                                                              With Solar Control
                                                                         Standard 2-Bolt Flange


                                                                       Fill Port Hose Connection


                                                                              Flow Meter in GPM


                                                                   Purge Port Hose Connection


                                                                             Insulated Enclosure

                         To Storage
                                                                  1" Union Connection Tailpiece
                          Tank Heat
                         Exchanger
Component Identification
                                                                                                                                                                              (E) Safety Unit
                                                                                                                                                                The safety unit is CE and TUV approved




                                                                   Supply




                                                                                                     Return
                                                                                                                                                                and protects the installation from over
              Supply           Return
                                                                                                                                                            E   pressurization. It is set to 87 psi (6 bar);
       (A) Shut-off ball valve on the supply                                                                                                                    over this pressure the relief valve will open.
      (thermometer with red ring and scale                                                                           B                                          The unit also comes with a pressure gauge
     30-250°F & 0-120°C) with “Solar” check                                             A
                                                                                                                                                                and a connection for the expansion tank by
                       valve.                                                                                                                                   means of a 3/4" flexible hose kit (included).
           (B) Shut-off ball on the return
      (thermometer with blue ring and scale
     30-250°F & 0-120°C) with “Solar” check
                       valve.

                  Solar Check Valve
      The ball valves of both the supply and the
     return feature an integral flow check (IFC).
       It ensures no gravity flow and low head
     losses. To manually open the check valve,
     such as in the case of draining the system,
           rotate the handle 45° clockwise.

                (C) Circulating Pump                                                                                C
    The circulating pump is a standard variable
    speed Taco 00 Series, 2 bolt flange style.
    The ball valves before and after the
    circulating pump, make it possible to
    service the circulator without draining the
    installation.

                (D) Union Tailpiece                                                                                                                                  (F) Flowmeter
    The 1" unions on the Solar Pumping                                                                                                    The flowmeter allows the installer to regulate the flow rate to
    Station allow direct connections to flexible                                                                                          match the requirements of the installation, by means of a
    stainless steel collector line sets as well as                                            F                                           balancing ball valve. If the balancing valve is closed then
    adaptors to copper pipe. Adaptors (4) for                                                                                             circulation is cut off. Use the upper side fill valve to fill the solar
    ¾” copper pipe are supplied with unit.                                                                                                installation. Use the lower side purge valve for purging the
                                                                                                                                          solar installation.
            Optional Solar Differential
              Temperature Control
                                                        D                                                                                 The convenience of the two valves helps to reduce the filling
            (may be attached or shipped separate)                                                                                         and the purging time. The flow rate is measured and shown by
    Please see manufactures supplied                                                                                                      the sliding cursor inside the flowmeter. The flow rate is read
    instructions for installation and set-up of                                                                                           from lower edge of sliding cursor. This measurement is
    solar differential temperature control.                                                                                               effected by adjusting the balancing valve.


  Directions for use of Flowmeter

                                         Filling




Balancing                                                                   Balancing
  valve                                                                       valve                                                                               Balancing
 closed                                                                       open                                                                                  valve to
                                                            Flow




                                                                                                                              Locking the filling/drain
                                                                                                                                        levers:                  regulate the
                                                                                                                              Remove the lever screw,
                                                                                                                               take off the lever, rotate          flow rate
                                                                                                                              180°and replace it again.                         GPM
                                                                                                                                                                                              Flow rate shown
                                                                                                                                                                                                (in this case
                                                                                                                                                                                                   8 GPM)




                               Drain
                                                                      (2) – To starting up the installation:
  (1) – Filling and purging the installation:                          Close the side filling and draining valves and open the balancing valve.                 (3) - Regulate the flow rate using the balancing
  Remove the hose caps from the side filling and                      Remove the hose unions and replace hose caps.                                             valve when circulator is running at full speed.
  draining valves and connect the hose unions.
  Close the balancing valve and open the side filling                 To avoid any unwanted opening of the side valves, it is better to lock                    Note: The flow rate is referenced from the lower
  and draining valves. Use a pump to fill the system                  the levers in the close position, as shown.                                               edge of sliding cursor. (See picture)
  with a quality solar fluid to typically 20-40 psi.
Directions for Venting of Air




                                                                                                                              Supply




                                                                                                                                                   Return
                             Air Vent
  The manual air vent is a device that continually removes air
  that is entrained with the solar fluid. The air rises to the
  upper part of the vent and it can be manually eliminated
  through the special vent connection. Unscrew the knurled
  metal ring lock 360° to vent any captured air.

  This operation should to be done periodically.



Directions for Mounting Module

                                                                             Epp Insulation Box                         Fastening holes on the back fixing plate. Openings on the
                                                           Measurements. 12.1” X 17.0” X 6.6”                           insulation box allow the fastening of pumping station without
                                                           (308 mm X 434 mm X 169 mm)                                   disassembling the unit.
                                                           The enclosure has wiring channels suitable for routing
                        .40"                               of the power supply cable and of the temperature
                                                           sensor cables. A special window allows for reading
                                                           the flow rate without taking off the cover. The back
                                                           plate fastens the unit to the wall or to the storage tank.
                                                    6.3"
    17.0"




                        .40"




                               12.1"

                                                   Back plate to fasten the unit to
                                                   the wall or to the storage tank.
Directions for Mounting Expansion Tank and Bracket



                                                     BRACKET AND CONNECTOR FOR THE EXPANSION TANK
                                                     (A) 3/4” flexible pipe connected to the safety unit of the solar pumping station.
              A                                      (B) Fiber sealing gasket included.
                                                     (C) Connector with double check valve to disconnect the expansion tank in a
                                                     reliable and fast way without any leakage.
                                                     (D) Expansion tank with 3/4” BSP threaded connection. (not included)
                                                     (E) Fixing bracket provided with plugs and screws to fix it to the wall.
                                                     (F) Bottom half of connector (C) that threads on to ¾” BSP expansion tank nipple.
         B                                           Attach the bracket (E) to the wall with the plugs or screws (centre distance 2.2" or
                                                     55 mm). Screw the Connector (F) to the expansion tank. Install the connector (C)       F
                                                     on the fixing bracket using the special groove then lock with the nut. Screw
       C                                             connector (F) into the bottom of connector (C). Screw the flexible pipe from the
                                    E                safety unit (A) to the top of connector (C) with sealing gasket (B) in between.

                                                     REPLACEMENT OF THE EXPANSION TANK
                                                     The connector (C) holds up the expansion tank and allows for quick removal,
                                                     without any leakage. By unscrewing the nut (F) it is possible to disconnect one
                                D                    end of the connector from the expansion tank. The other end of the connector
                                                     stays fixed on the bracket connected to the safety unit. Both the ends have a
                                                     check valve that becomes operative at the time of the disconnection: this
                                                     prevents any leakage both from the expansion tank and from the flexible pipe.
                                                     To put in service again, it is necessary to reconnect the connector by screwing
                                                     the nut (F). In that way the two check valves are opened and the expansion
                                                     tank is again connected to the installation.


                                                    Note: If expansion tank nipple has NPT threads than use
                                                    a hardening type thread sealer like Loctite or SAF-T-LOC.




                           LIMITED WARRANTY STATEMENT
                                                                                                                                  TACO OFFERS THIS WARRANTY IN LIEU
Taco, Inc. will repair or replace without             Any Taco product or part not installed or                                   OF ALL OTHER EXPRESS WARRANTIES.
charge (at the company’s option) any product          operated in conformity with Taco instructions                               ANY WARRANTY IMPLIED BY LAW
or part which is proven defective under               or which has been subject to misuse,                                        INCLUDING WARRANTIES OF
normal use within one (1) year from the date          misapplication, the addition of petroleum-                                  MERCHANTABILITY OR FITNESS IS IN
of start-up or one (1) year and six (6) months        based fluids or certain chemical additives to                               EFFECT ONLY FOR THE DURATION OF
from date of shipment (whichever occurs               the systems, or other abuse, will not be                                    THE EXPRESS WARRANTY SET FORTH
first). Taco, Inc. will repair or replace without     covered by this warranty. If in doubt as to                                 IN THE FIRST PARAGRAPH ABOVE. THE
charge (at the company’s option) any Taco             whether a particular substance is suitable for                              ABOVE WARRANTIES ARE IN LIEU OF
“00” Series circulator cartridge that is proven       use with a Taco product or part, or for any                                 ALL OTHER WARRANTIES, EXPRESS OR
defective under normal use within three (3)           application restrictions, consult the applicable                            STATUTORY, OR ANY OTHER
years from the date of start-up or three (3)          Taco instruction sheets or contact Taco at                                  WARRANTY OBLIGATION ON THE PART
years and six (6) months from date of                 [401-942-8000].                                                             OF TACO. TACO WILL NOT BE LIABLE
shipment (whichever occurs first). In order to        Taco reserves the right to provide                                          FOR ANY SPECIAL, INCIDENTAL,
obtain service under this warranty, it is the         replacement products and parts which are                                    INDIRECT OR CONSEQUENTIAL
responsibility of the purchaser to promptly           substantially similar in design and functionally                            DAMAGES RESULTING FROM THE USE
notify the local Taco stocking distributor or         equivalent to the defective product or part.                                OF ITS PRODUCTS OR ANY INCIDENTAL
Taco in writing and promptly deliver the              Taco reserves the right to make changes in                                  COSTS OF REMOVING OR REPLACING
subject product or part, delivery prepaid, to         details of design, construction, or                                         DEFECTIVE PRODUCTS.
the stocking distributor. For assistance on           arrangement of materials of its products                                    This warranty gives the purchaser specific
warranty returns, the purchaser may either            without notification.                                                       rights, and the purchaser may have other
contact the local Taco stocking distributor or                                                                                    rights which vary from state to state. Some
Taco. If the subject product or part contains                                                                                     states do not allow limitations on how long
no defect as covered in this warranty, the                                                                                        an implied warranty lasts or on the exclusion
purchaser will be billed for parts and labor                                                                                      of incidental or consequential damages, so
charges in effect at time of factory                                                                                              these limitations or exclusions may not apply
examination and repair.                                                                                                           to you.




Solar MADE EASY.                                                                                                                                                Printed in USA

TACO, INC., 1160 Cranston Street, Cranston, RI 02920 Telephone: (401) 942-8000 FAX: (401) 942-2360.                                                             Copyright 2009
TACO (Canada), Ltd., 8450 Lawson Road, Unit #3, Milton, Ontario L9T 0J8. Telephone: (905) 564-9422. FAX: (905) 564-9436.                                         TACO, Inc.
Visit our web site at: http://www.taco-hvac.com

More Related Content

What's hot

GE Frame 9E Gas Turbine Nandipur Power Project
GE  Frame 9E Gas Turbine Nandipur Power ProjectGE  Frame 9E Gas Turbine Nandipur Power Project
GE Frame 9E Gas Turbine Nandipur Power ProjectZohaib Asif
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineRAVI PAL SINGH
 
Boiler doc 08 control application
Boiler doc 08   control applicationBoiler doc 08   control application
Boiler doc 08 control applicationMars Tsani
 
High performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoHigh performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoIllinois ASHRAE
 
Boiler
BoilerBoiler
Boileravik
 
ABB Power Curcuit Braker
ABB Power Curcuit BrakerABB Power Curcuit Braker
ABB Power Curcuit BrakerOleg Volkov
 
Fire pump controllers
Fire pump controllersFire pump controllers
Fire pump controllersmichaeljmack
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPSManohar Tatwawadi
 
Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Ray Beebe
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Boiler Feed Water Control
Boiler Feed Water ControlBoiler Feed Water Control
Boiler Feed Water Controlno suhaila
 

What's hot (17)

GE Frame 9E Gas Turbine Nandipur Power Project
GE  Frame 9E Gas Turbine Nandipur Power ProjectGE  Frame 9E Gas Turbine Nandipur Power Project
GE Frame 9E Gas Turbine Nandipur Power Project
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
Thermal Management of Transformers
Thermal Management of TransformersThermal Management of Transformers
Thermal Management of Transformers
 
Boiler doc 08 control application
Boiler doc 08   control applicationBoiler doc 08   control application
Boiler doc 08 control application
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Roy hubbard
Roy hubbardRoy hubbard
Roy hubbard
 
High performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoHigh performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicago
 
Boiler
BoilerBoiler
Boiler
 
ABB Power Curcuit Braker
ABB Power Curcuit BrakerABB Power Curcuit Braker
ABB Power Curcuit Braker
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Fire pump controllers
Fire pump controllersFire pump controllers
Fire pump controllers
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Air receiver tank
Air receiver tankAir receiver tank
Air receiver tank
 
Integrated control valve, sensors, actuator, and controller
Integrated control valve, sensors, actuator, and controllerIntegrated control valve, sensors, actuator, and controller
Integrated control valve, sensors, actuator, and controller
 
Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Boiler Feed Water Control
Boiler Feed Water ControlBoiler Feed Water Control
Boiler Feed Water Control
 

Viewers also liked

Qs basements
Qs basementsQs basements
Qs basementskiakaha
 
Walls Not Connected Foundations
Walls Not Connected FoundationsWalls Not Connected Foundations
Walls Not Connected Foundationskiakaha
 
Killing Sacred Cows
Killing Sacred CowsKilling Sacred Cows
Killing Sacred Cowskiakaha
 
The Auditorium Suspended Cieling Has No Siesmic Bracing
The Auditorium Suspended Cieling Has No Siesmic BracingThe Auditorium Suspended Cieling Has No Siesmic Bracing
The Auditorium Suspended Cieling Has No Siesmic Bracingkiakaha
 
Temple View Urban Design Guide
Temple View Urban Design GuideTemple View Urban Design Guide
Temple View Urban Design Guidekiakaha
 
My fathers statement to the commissioners in new zealand
My fathers statement to the commissioners in new zealandMy fathers statement to the commissioners in new zealand
My fathers statement to the commissioners in new zealandkiakaha
 
Peter Witehira Submission / Ngapuhi 2013
Peter Witehira Submission / Ngapuhi 2013Peter Witehira Submission / Ngapuhi 2013
Peter Witehira Submission / Ngapuhi 2013kiakaha
 
Letter to Elder Clayton_Temple View New Zealand
Letter to Elder Clayton_Temple View New ZealandLetter to Elder Clayton_Temple View New Zealand
Letter to Elder Clayton_Temple View New Zealandkiakaha
 
Notes from the field_We're the One
Notes from the field_We're the OneNotes from the field_We're the One
Notes from the field_We're the Onekiakaha
 

Viewers also liked (9)

Qs basements
Qs basementsQs basements
Qs basements
 
Walls Not Connected Foundations
Walls Not Connected FoundationsWalls Not Connected Foundations
Walls Not Connected Foundations
 
Killing Sacred Cows
Killing Sacred CowsKilling Sacred Cows
Killing Sacred Cows
 
The Auditorium Suspended Cieling Has No Siesmic Bracing
The Auditorium Suspended Cieling Has No Siesmic BracingThe Auditorium Suspended Cieling Has No Siesmic Bracing
The Auditorium Suspended Cieling Has No Siesmic Bracing
 
Temple View Urban Design Guide
Temple View Urban Design GuideTemple View Urban Design Guide
Temple View Urban Design Guide
 
My fathers statement to the commissioners in new zealand
My fathers statement to the commissioners in new zealandMy fathers statement to the commissioners in new zealand
My fathers statement to the commissioners in new zealand
 
Peter Witehira Submission / Ngapuhi 2013
Peter Witehira Submission / Ngapuhi 2013Peter Witehira Submission / Ngapuhi 2013
Peter Witehira Submission / Ngapuhi 2013
 
Letter to Elder Clayton_Temple View New Zealand
Letter to Elder Clayton_Temple View New ZealandLetter to Elder Clayton_Temple View New Zealand
Letter to Elder Clayton_Temple View New Zealand
 
Notes from the field_We're the One
Notes from the field_We're the OneNotes from the field_We're the One
Notes from the field_We're the One
 

Similar to S P S Instruction Sheet

Pump Station Submittals
Pump Station SubmittalsPump Station Submittals
Pump Station Submittalskiakaha
 
Solar Pumping Station 100 79
Solar Pumping Station 100 79Solar Pumping Station 100 79
Solar Pumping Station 100 79kiakaha
 
Solar Pumping Station 100 79
Solar Pumping Station 100 79Solar Pumping Station 100 79
Solar Pumping Station 100 79kiakaha
 
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing ValvesSunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing ValvesSunMaxx Solar
 
Hot water flow controller function description
Hot water flow controller function descriptionHot water flow controller function description
Hot water flow controller function descriptionADEWALE ADEOYE
 
Air Conditioning Energy Conservation System
Air Conditioning Energy Conservation SystemAir Conditioning Energy Conservation System
Air Conditioning Energy Conservation SystemEnergySavings
 
Project Report - Spring 2014
Project Report - Spring 2014Project Report - Spring 2014
Project Report - Spring 2014Garret Stec
 
Control Valves .pdf
Control Valves .pdfControl Valves .pdf
Control Valves .pdfmarcos849547
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing SystemSalil Vaidya
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfHariomgupta90
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
78679939 dvc6000manualinstrucciones
78679939 dvc6000manualinstrucciones78679939 dvc6000manualinstrucciones
78679939 dvc6000manualinstruccionesMowaten Masry
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSatish Pydimarla
 

Similar to S P S Instruction Sheet (20)

Pump Station Submittals
Pump Station SubmittalsPump Station Submittals
Pump Station Submittals
 
Solar Pumping Station 100 79
Solar Pumping Station 100 79Solar Pumping Station 100 79
Solar Pumping Station 100 79
 
Solar Pumping Station 100 79
Solar Pumping Station 100 79Solar Pumping Station 100 79
Solar Pumping Station 100 79
 
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing ValvesSunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
 
Hot water flow controller function description
Hot water flow controller function descriptionHot water flow controller function description
Hot water flow controller function description
 
Air Conditioning Energy Conservation System
Air Conditioning Energy Conservation SystemAir Conditioning Energy Conservation System
Air Conditioning Energy Conservation System
 
1760 1750 control valves
1760 1750 control valves1760 1750 control valves
1760 1750 control valves
 
F001
F001F001
F001
 
Project Report - Spring 2014
Project Report - Spring 2014Project Report - Spring 2014
Project Report - Spring 2014
 
Transformers
TransformersTransformers
Transformers
 
Control Valve.pdf
Control Valve.pdfControl Valve.pdf
Control Valve.pdf
 
Control Valves .pdf
Control Valves .pdfControl Valves .pdf
Control Valves .pdf
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
Electrostatic Precipitator
Electrostatic Precipitator Electrostatic Precipitator
Electrostatic Precipitator
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdf
 
Transformer
TransformerTransformer
Transformer
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
78679939 dvc6000manualinstrucciones
78679939 dvc6000manualinstrucciones78679939 dvc6000manualinstrucciones
78679939 dvc6000manualinstrucciones
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
mn03010.pdf
mn03010.pdfmn03010.pdf
mn03010.pdf
 

More from kiakaha

Statement of meshweyla kusheyla harata alexander macdonald
Statement of meshweyla kusheyla harata alexander macdonaldStatement of meshweyla kusheyla harata alexander macdonald
Statement of meshweyla kusheyla harata alexander macdonaldkiakaha
 
Statement of kena alexander
Statement of kena alexanderStatement of kena alexander
Statement of kena alexanderkiakaha
 
Statement of Rakaipaka O Puriri-Ahmu
Statement of Rakaipaka O Puriri-AhmuStatement of Rakaipaka O Puriri-Ahmu
Statement of Rakaipaka O Puriri-Ahmukiakaha
 
Liz Witehira Submission 2013
Liz Witehira Submission 2013Liz Witehira Submission 2013
Liz Witehira Submission 2013kiakaha
 
Patent application / Solar Fins
Patent application / Solar FinsPatent application / Solar Fins
Patent application / Solar Finskiakaha
 
Roots tech sponsor and exhibitor kit_2014
Roots tech sponsor and exhibitor kit_2014Roots tech sponsor and exhibitor kit_2014
Roots tech sponsor and exhibitor kit_2014kiakaha
 
Appendix 6 visual assessment reports - urban design assessment - mansergh g...
Appendix 6   visual assessment reports - urban design assessment - mansergh g...Appendix 6   visual assessment reports - urban design assessment - mansergh g...
Appendix 6 visual assessment reports - urban design assessment - mansergh g...kiakaha
 
IworX linecard
IworX linecardIworX linecard
IworX linecardkiakaha
 
IworX web brochure
IworX web brochureIworX web brochure
IworX web brochurekiakaha
 
O remember
O rememberO remember
O rememberkiakaha
 
Letter of financial support
Letter of financial supportLetter of financial support
Letter of financial supportkiakaha
 
Remember and perish not
Remember and perish notRemember and perish not
Remember and perish notkiakaha
 
O remember
O rememberO remember
O rememberkiakaha
 
Jeremy Johnson FTC Charges Dec 21, 2010
Jeremy Johnson FTC Charges Dec 21, 2010Jeremy Johnson FTC Charges Dec 21, 2010
Jeremy Johnson FTC Charges Dec 21, 2010kiakaha
 
Fbo rfp st george city feb 2009
Fbo rfp st george city feb 2009Fbo rfp st george city feb 2009
Fbo rfp st george city feb 2009kiakaha
 
Quick tips windows and doors
Quick tips windows and doorsQuick tips windows and doors
Quick tips windows and doorskiakaha
 
Quick tips walls
Quick tips wallsQuick tips walls
Quick tips wallskiakaha
 
Quick tips project properties
Quick tips project propertiesQuick tips project properties
Quick tips project propertieskiakaha
 
The value proposition for solar hot water heating in california
The value proposition for solar hot water heating in californiaThe value proposition for solar hot water heating in california
The value proposition for solar hot water heating in californiakiakaha
 
CSI program handbookdecember2009_v2
CSI program handbookdecember2009_v2CSI program handbookdecember2009_v2
CSI program handbookdecember2009_v2kiakaha
 

More from kiakaha (20)

Statement of meshweyla kusheyla harata alexander macdonald
Statement of meshweyla kusheyla harata alexander macdonaldStatement of meshweyla kusheyla harata alexander macdonald
Statement of meshweyla kusheyla harata alexander macdonald
 
Statement of kena alexander
Statement of kena alexanderStatement of kena alexander
Statement of kena alexander
 
Statement of Rakaipaka O Puriri-Ahmu
Statement of Rakaipaka O Puriri-AhmuStatement of Rakaipaka O Puriri-Ahmu
Statement of Rakaipaka O Puriri-Ahmu
 
Liz Witehira Submission 2013
Liz Witehira Submission 2013Liz Witehira Submission 2013
Liz Witehira Submission 2013
 
Patent application / Solar Fins
Patent application / Solar FinsPatent application / Solar Fins
Patent application / Solar Fins
 
Roots tech sponsor and exhibitor kit_2014
Roots tech sponsor and exhibitor kit_2014Roots tech sponsor and exhibitor kit_2014
Roots tech sponsor and exhibitor kit_2014
 
Appendix 6 visual assessment reports - urban design assessment - mansergh g...
Appendix 6   visual assessment reports - urban design assessment - mansergh g...Appendix 6   visual assessment reports - urban design assessment - mansergh g...
Appendix 6 visual assessment reports - urban design assessment - mansergh g...
 
IworX linecard
IworX linecardIworX linecard
IworX linecard
 
IworX web brochure
IworX web brochureIworX web brochure
IworX web brochure
 
O remember
O rememberO remember
O remember
 
Letter of financial support
Letter of financial supportLetter of financial support
Letter of financial support
 
Remember and perish not
Remember and perish notRemember and perish not
Remember and perish not
 
O remember
O rememberO remember
O remember
 
Jeremy Johnson FTC Charges Dec 21, 2010
Jeremy Johnson FTC Charges Dec 21, 2010Jeremy Johnson FTC Charges Dec 21, 2010
Jeremy Johnson FTC Charges Dec 21, 2010
 
Fbo rfp st george city feb 2009
Fbo rfp st george city feb 2009Fbo rfp st george city feb 2009
Fbo rfp st george city feb 2009
 
Quick tips windows and doors
Quick tips windows and doorsQuick tips windows and doors
Quick tips windows and doors
 
Quick tips walls
Quick tips wallsQuick tips walls
Quick tips walls
 
Quick tips project properties
Quick tips project propertiesQuick tips project properties
Quick tips project properties
 
The value proposition for solar hot water heating in california
The value proposition for solar hot water heating in californiaThe value proposition for solar hot water heating in california
The value proposition for solar hot water heating in california
 
CSI program handbookdecember2009_v2
CSI program handbookdecember2009_v2CSI program handbookdecember2009_v2
CSI program handbookdecember2009_v2
 

Recently uploaded

Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 

Recently uploaded (20)

Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 

S P S Instruction Sheet

  • 1. The Taco Solar Pumping Station (SPS) combine all the features needed for a closed loop solar water heating system. Just 5 easy connections to make; 2 for the solar collector(s), 2 for the storage tank’s heat exchanger and 1 for the expansion tank. The Solar Pumping Station includes a circulator with an integral variable speed solar control, isolation ball vales, air elimination, flow meter and a safety group. To Solar Collector Pressure Relief Pressure Gauge Expansion Tank Connection Return Temp Gauge & Shut-Off Valve Supply Temp Gauge & Shut-Off Valve Air Eliminator & Vent Circulating Pump With Solar Control Standard 2-Bolt Flange Fill Port Hose Connection Flow Meter in GPM Purge Port Hose Connection Insulated Enclosure To Storage 1" Union Connection Tailpiece Tank Heat Exchanger
  • 2. Component Identification (E) Safety Unit The safety unit is CE and TUV approved Supply Return and protects the installation from over Supply Return E pressurization. It is set to 87 psi (6 bar); (A) Shut-off ball valve on the supply over this pressure the relief valve will open. (thermometer with red ring and scale B The unit also comes with a pressure gauge 30-250°F & 0-120°C) with “Solar” check A and a connection for the expansion tank by valve. means of a 3/4" flexible hose kit (included). (B) Shut-off ball on the return (thermometer with blue ring and scale 30-250°F & 0-120°C) with “Solar” check valve. Solar Check Valve The ball valves of both the supply and the return feature an integral flow check (IFC). It ensures no gravity flow and low head losses. To manually open the check valve, such as in the case of draining the system, rotate the handle 45° clockwise. (C) Circulating Pump C The circulating pump is a standard variable speed Taco 00 Series, 2 bolt flange style. The ball valves before and after the circulating pump, make it possible to service the circulator without draining the installation. (D) Union Tailpiece (F) Flowmeter The 1" unions on the Solar Pumping The flowmeter allows the installer to regulate the flow rate to Station allow direct connections to flexible match the requirements of the installation, by means of a stainless steel collector line sets as well as F balancing ball valve. If the balancing valve is closed then adaptors to copper pipe. Adaptors (4) for circulation is cut off. Use the upper side fill valve to fill the solar ¾” copper pipe are supplied with unit. installation. Use the lower side purge valve for purging the solar installation. Optional Solar Differential Temperature Control D The convenience of the two valves helps to reduce the filling (may be attached or shipped separate) and the purging time. The flow rate is measured and shown by Please see manufactures supplied the sliding cursor inside the flowmeter. The flow rate is read instructions for installation and set-up of from lower edge of sliding cursor. This measurement is solar differential temperature control. effected by adjusting the balancing valve. Directions for use of Flowmeter Filling Balancing Balancing valve valve Balancing closed open valve to Flow Locking the filling/drain levers: regulate the Remove the lever screw, take off the lever, rotate flow rate 180°and replace it again. GPM Flow rate shown (in this case 8 GPM) Drain (2) – To starting up the installation: (1) – Filling and purging the installation: Close the side filling and draining valves and open the balancing valve. (3) - Regulate the flow rate using the balancing Remove the hose caps from the side filling and Remove the hose unions and replace hose caps. valve when circulator is running at full speed. draining valves and connect the hose unions. Close the balancing valve and open the side filling To avoid any unwanted opening of the side valves, it is better to lock Note: The flow rate is referenced from the lower and draining valves. Use a pump to fill the system the levers in the close position, as shown. edge of sliding cursor. (See picture) with a quality solar fluid to typically 20-40 psi.
  • 3. Directions for Venting of Air Supply Return Air Vent The manual air vent is a device that continually removes air that is entrained with the solar fluid. The air rises to the upper part of the vent and it can be manually eliminated through the special vent connection. Unscrew the knurled metal ring lock 360° to vent any captured air. This operation should to be done periodically. Directions for Mounting Module Epp Insulation Box Fastening holes on the back fixing plate. Openings on the Measurements. 12.1” X 17.0” X 6.6” insulation box allow the fastening of pumping station without (308 mm X 434 mm X 169 mm) disassembling the unit. The enclosure has wiring channels suitable for routing .40" of the power supply cable and of the temperature sensor cables. A special window allows for reading the flow rate without taking off the cover. The back plate fastens the unit to the wall or to the storage tank. 6.3" 17.0" .40" 12.1" Back plate to fasten the unit to the wall or to the storage tank.
  • 4. Directions for Mounting Expansion Tank and Bracket BRACKET AND CONNECTOR FOR THE EXPANSION TANK (A) 3/4” flexible pipe connected to the safety unit of the solar pumping station. A (B) Fiber sealing gasket included. (C) Connector with double check valve to disconnect the expansion tank in a reliable and fast way without any leakage. (D) Expansion tank with 3/4” BSP threaded connection. (not included) (E) Fixing bracket provided with plugs and screws to fix it to the wall. (F) Bottom half of connector (C) that threads on to ¾” BSP expansion tank nipple. B Attach the bracket (E) to the wall with the plugs or screws (centre distance 2.2" or 55 mm). Screw the Connector (F) to the expansion tank. Install the connector (C) F on the fixing bracket using the special groove then lock with the nut. Screw C connector (F) into the bottom of connector (C). Screw the flexible pipe from the E safety unit (A) to the top of connector (C) with sealing gasket (B) in between. REPLACEMENT OF THE EXPANSION TANK The connector (C) holds up the expansion tank and allows for quick removal, without any leakage. By unscrewing the nut (F) it is possible to disconnect one D end of the connector from the expansion tank. The other end of the connector stays fixed on the bracket connected to the safety unit. Both the ends have a check valve that becomes operative at the time of the disconnection: this prevents any leakage both from the expansion tank and from the flexible pipe. To put in service again, it is necessary to reconnect the connector by screwing the nut (F). In that way the two check valves are opened and the expansion tank is again connected to the installation. Note: If expansion tank nipple has NPT threads than use a hardening type thread sealer like Loctite or SAF-T-LOC. LIMITED WARRANTY STATEMENT TACO OFFERS THIS WARRANTY IN LIEU Taco, Inc. will repair or replace without Any Taco product or part not installed or OF ALL OTHER EXPRESS WARRANTIES. charge (at the company’s option) any product operated in conformity with Taco instructions ANY WARRANTY IMPLIED BY LAW or part which is proven defective under or which has been subject to misuse, INCLUDING WARRANTIES OF normal use within one (1) year from the date misapplication, the addition of petroleum- MERCHANTABILITY OR FITNESS IS IN of start-up or one (1) year and six (6) months based fluids or certain chemical additives to EFFECT ONLY FOR THE DURATION OF from date of shipment (whichever occurs the systems, or other abuse, will not be THE EXPRESS WARRANTY SET FORTH first). Taco, Inc. will repair or replace without covered by this warranty. If in doubt as to IN THE FIRST PARAGRAPH ABOVE. THE charge (at the company’s option) any Taco whether a particular substance is suitable for ABOVE WARRANTIES ARE IN LIEU OF “00” Series circulator cartridge that is proven use with a Taco product or part, or for any ALL OTHER WARRANTIES, EXPRESS OR defective under normal use within three (3) application restrictions, consult the applicable STATUTORY, OR ANY OTHER years from the date of start-up or three (3) Taco instruction sheets or contact Taco at WARRANTY OBLIGATION ON THE PART years and six (6) months from date of [401-942-8000]. OF TACO. TACO WILL NOT BE LIABLE shipment (whichever occurs first). In order to Taco reserves the right to provide FOR ANY SPECIAL, INCIDENTAL, obtain service under this warranty, it is the replacement products and parts which are INDIRECT OR CONSEQUENTIAL responsibility of the purchaser to promptly substantially similar in design and functionally DAMAGES RESULTING FROM THE USE notify the local Taco stocking distributor or equivalent to the defective product or part. OF ITS PRODUCTS OR ANY INCIDENTAL Taco in writing and promptly deliver the Taco reserves the right to make changes in COSTS OF REMOVING OR REPLACING subject product or part, delivery prepaid, to details of design, construction, or DEFECTIVE PRODUCTS. the stocking distributor. For assistance on arrangement of materials of its products This warranty gives the purchaser specific warranty returns, the purchaser may either without notification. rights, and the purchaser may have other contact the local Taco stocking distributor or rights which vary from state to state. Some Taco. If the subject product or part contains states do not allow limitations on how long no defect as covered in this warranty, the an implied warranty lasts or on the exclusion purchaser will be billed for parts and labor of incidental or consequential damages, so charges in effect at time of factory these limitations or exclusions may not apply examination and repair. to you. Solar MADE EASY. Printed in USA TACO, INC., 1160 Cranston Street, Cranston, RI 02920 Telephone: (401) 942-8000 FAX: (401) 942-2360. Copyright 2009 TACO (Canada), Ltd., 8450 Lawson Road, Unit #3, Milton, Ontario L9T 0J8. Telephone: (905) 564-9422. FAX: (905) 564-9436. TACO, Inc. Visit our web site at: http://www.taco-hvac.com