SlideShare a Scribd company logo
1 of 11
Running Head; EFFECTIVE PROJECT MANAGEMENT IN
THE FACE OF RISKS 1
EFFECTIVE PROJECT MANAGEMENT IN THE FACE OF
RISKS 2
Effective Project management in the Face of Risks
Name
Institution
The Gantt Chart and the Critical Path
In this week’s Learning Activity, you will be creating and
expanding on the work breakdown structure (WBS) in
ProjectLibre. You will also be adding/updating the Gantt Chart
with predecessors, resources, and costs.
Work Breakdown Structure (WBS)
This week we are continuing in the planning stage of the project
and will be working on tools project managers use to help not
only
plan the project, but to execute, control, and close out the
project
during the rest of the project lifecycle.
The work breakdown structure (WBS) takes the project and
breaks it down into smaller, more manageable pieces (Brenner,
2009). The end-product will be an organized, visual display of
the
main pieces of your project.
The tasks and subtask in the WBS must stand on their own and
be clear to anyone who picks up the document. Project
documents are often forwarded to others who are not intimately
familiar with the project and they need to be able to understand
the tasks.
There are no hard rules on how wide or deep your WBS
structure
should be. However, the subtasks, need to be small enough to
maintain control and visibility and at the same time avoid
excess
bureaucracy.
A WBS of a project to paint a few rooms in a home is provided
in
Figure 1 below. Note the tasks for this project are logically
grouped into several sections.
Figure 1: Work Breakdown Structure to Paint a Room
Gantt Chart
The Gantt chart is a set of horizontal lines that provide a visual
view of the tasks scheduled over time. The Gantt chart is always
paired with the work break down structure (WBS) so the team
can
see the tasks that go with the timeline.
The Gantt chart is also very helpful in seeing the project’s
critical
path and creating a timeline. Visuals from the Gantt chart helps
the team members identify which tasks must be done in
sequence
(for example, buy the paint first before painting the wall) and
which tasks might be done at the same time (for example,
remove
the wallpaper and cover the electrical outlets).
Knowing which tasks can be done simultaneously will allow the
team members to better plan and coordinate resources for the
project.
During this week, you will be adding predecessors to your WBS
and determining when different tasks and subtasks in your
project
should begin. This information will be reflected in your Gantt
chart. You are encouraged to play around with duration and
predecessors to see the impact on Gantt chart, critical path, and
the overall visual.
Figure 2 (below) shows the WBS with the Gantt chart (see blue
horizontal lines) for the painting project. This is a good
example of
what a Gantt chart should look like.
Figure 2: Gantt chart example with key notes
Project Resource
Figure 2 (above) also shows project resources, which you will
be
adding in this week’s learning activity.
In project management, resources are the component needed to
complete a project. Project resources can be people, equipment,
location, funding, and any other necessary asset that is required
to complete a project. Therefore, a lack of resource can be a
constraint to complete a project task.
Project resources should be identified, assessed, and allocated
before a project starts. Resource are added to help ensure
resources are properly scheduled and that no resources are being
double booked or overwhelmed. Poor resource planning can
have
a significant negative consequence on a project, including
delayed delivery, cost overrun, and/or inferior project
deliverable.
See Figure 3 below for a visual of where to add resources in
ProjectLibre.
Figure 3: Adding resources to ProjectLibre
In this week’s learning activity, you will be adding resources
and
costs to your project. See below for where and how to add costs
for the various resources that have been assigned to the project.
Adding costs to resources is a step in figuring out the total costs
of a project.
Many organizations consider internal employee time when
calculating the cost to a project. This is particularly true in
cross-
functional teams (common in projects) where labor resources
come from different departments.
Figure 4: Adding costs to ProjectLibre
Let’s Talk Turkey – Why the Critical Path is so Important
The textbook and your course goes over the critical path, so we
are not going to cover it in detail here, however, the discussion
below will help you bolster your understanding of the critical
path
and what it means to your project and how it will influence
what
you do in the Learning Activity.
Think about Thanksgiving dinner and everything that is cooked
on
that day for the entire family: Turkey, ham, baked potatoes,
sweet
potato, stuffing, greens, rolls, corn bread, gravy, salads, pies
and
more.
Planning a Thanksgiving dinner takes a great deal of
consideration and organization. Project management is no
different!
On Thanksgiving Day, it is NOT feasible to start cooking
everything at the same time nor it is practical to wait till one
dish is
finished before starting the preparation for the next dish.
Logistically, it is also challenging to ensure that every dish is
cooked at the exact the same time (instead you may end up
making the salads and desserts early and reheat other things
before they go on the table).
Applying project management principles to our analogy of
cooking
Thanksgiving meal would include tasks like: write down and
group
the tasks that need to be done (this is your work breakdown
structure), estimating the time to complete each task (task
duration), resources required to complete each task (Joe,
Grandma, the stove, etc.,), and which task(s) must be completed
before starting another task(s) (predecessor).
For Thanksgiving dinner, there are few tasks that will take a
long
time (cooking and thawing the turkey for example), but there
are
plenty of other things that can be done while the bird is thawing
and cooking. Tasks that can be done at the same time are called
parallel tasks.
Figuring out the critical path is the key. The critical path will
tell us
how much time the project will take, when you need to start
thawing and cooking the bird, and what time the dinner will
start.
The following video (Silverman, 2013) provides a good
introduction to the critical path. While the user interface in
ProjectLibre may look different, the concept remains the same.
Silverman, P. (November 28, 2013). Microsoft Project Tutorial
–
Understanding the Critical Path
(Links to an external site.)
[Video file]. Retrieved from https://www.youtube.com/n-
Mw3l42sgw
Paul Silverman
202 subscribers
Microsoft Project Tutorial - Understanding the Critical Path
Watch later
https://www.youtube.com/n-Mw3l42sgw
https://www.youtube.com/n-Mw3l42sgw
https://www.youtube.com/n-Mw3l42sgw
https://www.youtube.com/channel/UCk2A_C750isUuagwvvNf9
HA?feature=embeds_subscribe_title
https://www.youtube.com/watch?v=n-Mw3l42sgw
Share
<div class="player-unavailable"><h1 class="message">An error
occurred.</h1><div
class="submessage"><a
href="http://www.youtube.com/watch?v=n-Mw3l42sgw"
target="_blank">Try watching this video on
www.youtube.com</a>, or enable JavaScript if it is
disabled in your browser.</div></div>
The reason for such a high emphasis on critical path is if any of
the tasks on the critical path are delayed, then it affects the
entire
timeline of the project.
The critical path for Thanksgiving dinner may be this:
1. Menu prep and shopping list
2. Buy the turkey
3. Thaw 20-pound turkey (using the quick method (10 to 12
hours)
4. Bake unstuffed turkey (4.2 to 5 hours)
5. Rest turkey and carve turkey (40 minutes)
6. Reheat food cooked early (20 minutes)
Nothing can start until the menu prep and the turkey has been
purchased /shopping is done. After that the other parts of the
meal can be done while the turkey is thawing, baking, or
resting.
For those of us with only one oven (limited resources) it is
important to include the oven in the list of resources and
schedule
what the oven is doing at any one time appropriately. Managing
the ovens time is key on Thanksgiving. Some dishes may need
to
be baked (like pies and breads) while the turkey is thawing. The
other things can be reallocated to the stove top or rotated in and
out of the oven while the turkey is cooking. For example,
potatoes
for mashed potatoes can be boiled instead of baked. Sweet
potatoes can often be placed in the oven with the turkey.
In this week’s assignment, you will set up your work breakdown
structure with deliverables, subtasks, and associated
dependencies which will allow you to identify your critical
path.
The following video (Bradley, 2015) provides an overview of
how
to set up and use ProjectLibre. This resource may assist you
with
understanding how you will be using ProjectLibre throughout
this
course and with your Time and Cost Estimation Exercise
Interactive learning activity this week.
Bradley, H (July 11, 2015). Learn the basics of ProjetLibre –
Your
quick start to project management with ProjectLibre
(Links to an external site.)
[Video file]. Retrieved from https://youtu.be/oiVnWX-J5Mo
Helen Bradley
45K subscribers
Learn the Basics of ProjectLibre - Your Quick Start to
Project Management with ProjectLibre
Watch later
Share
<div class="player-unavailable"><h1 class="message">An error
occurred.</h1><div
class="submessage"><a
href="http://www.youtube.com/watch?v=oiVnWX-J5Mo"
target="_blank">Try watching this video on
www.youtube.com</a>, or enable JavaScript if it is
disabled in your browser.</div></div>
Stand on its Own
Remember every time you write anything it must stand on its
own.
Meaning the documents must have the information and
background necessary for others to understand them. If others
have to guess what you mean or have to make jumps in logic,
then you have not accomplished your goal.
As a manager or project manager, a lot of your documents will
be
forwarded as is and even someone not familiar with the project
needs to be able to read and understand what your project is
from
the project name, to the project scope, what tasks they need to
do
(the work breakdown structure and WBS dictionary) and what is
https://youtu.be/oiVnWX-J5Mo
https://youtu.be/oiVnWX-J5Mo
https://youtu.be/oiVnWX-J5Mo
https://youtu.be/oiVnWX-J5Mo
https://www.youtube.com/channel/UC31bW-
FYjdc5gsc_Zg77vkA?feature=embeds_subscribe_title
https://www.youtube.com/watch?v=oiVnWX-J5Mo
https://www.youtube.com/watch?v=oiVnWX-J5Mo
going on in the project and what the project manager has done
about it (the milestones, issues, and overall status report).
Since we will be sharing your project and your work in the
classroom writing clearly is also key since the class needs to be
able to understand your project and the work breakdown
structure.
FSBT Project Management Club
Want to learn more about project management and connect with
others? The Forbes School of Business and Technology™
(FSBT) at Ashford University has a Project Management Club.
The FSBT Project Management Club is dedicated to the
personal
and professional growth of its members by sharing and
discussing
methodology, leadership, and career opportunities about project
management. The Project Management Club is open to Ashford
and FSBT students, faculty, staff, alumni, and anyone who has a
strong interest in the area of project management.
The direct URL to join the FSBT Project Management Group is:
https://www.linkedin.com/groups/13536418
(Links to an external site.)
References
Bradley, H. (2015, July 11). Learn the basics of ProjectLibre—
Your quick start to project management with ProjectLibre
(Links to an external site.)
[Video file]. Retrieved from https://youtu.be/oiVnWX-J5Mo
Silverman, Paul (November 28, 2013). Microsoft Project
Tutorial -
Understanding the Critical Path
(Links to an external site.)
[Video file]. Retrieved from
https://www.youtube.com/watch?v=n-
Mw3l42sgw
How to cite this lecture
Milligan, S., Parikh, R. & Ardolino, E.(2019). PRM300: Time
and
Cost Estimations to Project Management
https://www.linkedin.com/groups/13536418
https://www.linkedin.com/groups/13536418
https://youtu.be/oiVnWX-J5Mo
https://youtu.be/oiVnWX-J5Mo
https://youtu.be/oiVnWX-J5Mo
https://youtu.be/oiVnWX-J5Mo
https://www.youtube.com/watch?v=n-Mw3l42sgw
https://www.youtube.com/watch?v=n-Mw3l42sgw
https://www.youtube.com/watch?v=n-Mw3l42sgw
Materials in this lecture are based on the Project Management
Institute, A Guide to the Project Management Body of
Knowledge (PMBOK® Guide) – Sixth Edition, Project
Management Institute, Inc., 2017. Copyright and all rights
reserved. PMBOK® is a registered mark of the Project
Management Institute, Inc.

More Related Content

Similar to Running Head; EFFECTIVE PROJECT MANAGEMENT IN THE FACE OF RISKS .docx

dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxSunilHotkar2
 
6455922 project-management-teacher-notes
6455922 project-management-teacher-notes6455922 project-management-teacher-notes
6455922 project-management-teacher-notesBhanu Singh
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentationKhem Singh
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxericbrooks84875
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
DB#9 & DB#10.docx· · · · · · · · · DB#9 Cost.docx
DB#9 & DB#10.docx· · · · · · · · · DB#9  Cost.docxDB#9 & DB#10.docx· · · · · · · · · DB#9  Cost.docx
DB#9 & DB#10.docx· · · · · · · · · DB#9 Cost.docxsimonithomas47935
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaDiscover JKUAT
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
Project management teaching
Project management   teachingProject management   teaching
Project management teachingCHIRANJAN SAHA
 
A guide to creating a quality project schedule it-toolkits
A guide to creating a quality project schedule   it-toolkitsA guide to creating a quality project schedule   it-toolkits
A guide to creating a quality project schedule it-toolkitsIT-Toolkits.org
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.pptTecnicoItca
 
CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   bellflower63
 
CMGT 410 NEW Focus Dreams/newtonhelp.com
CMGT 410 NEW Focus Dreams/newtonhelp.comCMGT 410 NEW Focus Dreams/newtonhelp.com
CMGT 410 NEW Focus Dreams/newtonhelp.combellflower110
 

Similar to Running Head; EFFECTIVE PROJECT MANAGEMENT IN THE FACE OF RISKS .docx (20)

dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
 
SEN-22413 - UNIT - V.pptx
SEN-22413 -  UNIT - V.pptxSEN-22413 -  UNIT - V.pptx
SEN-22413 - UNIT - V.pptx
 
6455922 project-management-teacher-notes
6455922 project-management-teacher-notes6455922 project-management-teacher-notes
6455922 project-management-teacher-notes
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentation
 
Lab exercise 6
Lab exercise 6Lab exercise 6
Lab exercise 6
 
Project time
Project timeProject time
Project time
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
DB#9 & DB#10.docx· · · · · · · · · DB#9 Cost.docx
DB#9 & DB#10.docx· · · · · · · · · DB#9  Cost.docxDB#9 & DB#10.docx· · · · · · · · · DB#9  Cost.docx
DB#9 & DB#10.docx· · · · · · · · · DB#9 Cost.docx
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Communication 1
Communication 1Communication 1
Communication 1
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
 
A guide to creating a quality project schedule it-toolkits
A guide to creating a quality project schedule   it-toolkitsA guide to creating a quality project schedule   it-toolkits
A guide to creating a quality project schedule it-toolkits
 
Managing Small Projects Introduction
Managing Small Projects   IntroductionManaging Small Projects   Introduction
Managing Small Projects Introduction
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   
 
CMGT 410 NEW Focus Dreams/newtonhelp.com
CMGT 410 NEW Focus Dreams/newtonhelp.comCMGT 410 NEW Focus Dreams/newtonhelp.com
CMGT 410 NEW Focus Dreams/newtonhelp.com
 

More from jeffsrosalyn

Problem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docx
Problem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docxProblem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docx
Problem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docxjeffsrosalyn
 
Problem 8-2B(a) Journalize the transactions, including explanation.docx
Problem 8-2B(a) Journalize the transactions, including explanation.docxProblem 8-2B(a) Journalize the transactions, including explanation.docx
Problem 8-2B(a) Journalize the transactions, including explanation.docxjeffsrosalyn
 
Problem 14-4AFinancial information for Ernie Bishop Company is pre.docx
Problem 14-4AFinancial information for Ernie Bishop Company is pre.docxProblem 14-4AFinancial information for Ernie Bishop Company is pre.docx
Problem 14-4AFinancial information for Ernie Bishop Company is pre.docxjeffsrosalyn
 
Problem and solution essay  about the difficulties of speaking Engli.docx
Problem and solution essay  about the difficulties of speaking Engli.docxProblem and solution essay  about the difficulties of speaking Engli.docx
Problem and solution essay  about the difficulties of speaking Engli.docxjeffsrosalyn
 
problem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docx
problem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docxproblem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docx
problem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docxjeffsrosalyn
 
Problem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docx
Problem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docxProblem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docx
Problem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docxjeffsrosalyn
 
Problem 1-4A (Part Level Submission)Matt Stiner started a delivery.docx
Problem 1-4A (Part Level Submission)Matt Stiner started a delivery.docxProblem 1-4A (Part Level Submission)Matt Stiner started a delivery.docx
Problem 1-4A (Part Level Submission)Matt Stiner started a delivery.docxjeffsrosalyn
 
PROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docxPROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docxjeffsrosalyn
 
Problem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docx
Problem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docxProblem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docx
Problem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docxjeffsrosalyn
 
Problem 13-6AIrwin Corporation has been authorized to issue 20,80.docx
Problem 13-6AIrwin Corporation has been authorized to issue 20,80.docxProblem 13-6AIrwin Corporation has been authorized to issue 20,80.docx
Problem 13-6AIrwin Corporation has been authorized to issue 20,80.docxjeffsrosalyn
 
Problem 1-2A (Part Level Submission)On August 31, the balance sh.docx
Problem 1-2A (Part Level Submission)On August 31, the balance sh.docxProblem 1-2A (Part Level Submission)On August 31, the balance sh.docx
Problem 1-2A (Part Level Submission)On August 31, the balance sh.docxjeffsrosalyn
 
Problem 1-2A (Part Level Submission)On August 31, the balance shee.docx
Problem 1-2A (Part Level Submission)On August 31, the balance shee.docxProblem 1-2A (Part Level Submission)On August 31, the balance shee.docx
Problem 1-2A (Part Level Submission)On August 31, the balance shee.docxjeffsrosalyn
 
Prior to posting in this discussion, completeThe Parking Garage.docx
Prior to posting in this discussion, completeThe Parking Garage.docxPrior to posting in this discussion, completeThe Parking Garage.docx
Prior to posting in this discussion, completeThe Parking Garage.docxjeffsrosalyn
 
Prior to engaging in this discussion, read Chapters 10 and 11 in y.docx
Prior to engaging in this discussion, read Chapters 10 and 11 in y.docxPrior to engaging in this discussion, read Chapters 10 and 11 in y.docx
Prior to engaging in this discussion, read Chapters 10 and 11 in y.docxjeffsrosalyn
 
Privacy in a Technological AgePrivacy protection is a hot top.docx
Privacy in a Technological AgePrivacy protection is a hot top.docxPrivacy in a Technological AgePrivacy protection is a hot top.docx
Privacy in a Technological AgePrivacy protection is a hot top.docxjeffsrosalyn
 
Privacy Introduction Does the technology today Pene.docx
Privacy Introduction Does the technology today Pene.docxPrivacy Introduction Does the technology today Pene.docx
Privacy Introduction Does the technology today Pene.docxjeffsrosalyn
 
Prisoner rights in America are based largely on the provisions of th.docx
Prisoner rights in America are based largely on the provisions of th.docxPrisoner rights in America are based largely on the provisions of th.docx
Prisoner rights in America are based largely on the provisions of th.docxjeffsrosalyn
 
Principles of Supply and Demanda brief example of supply and deman.docx
Principles of Supply and Demanda brief example of supply and deman.docxPrinciples of Supply and Demanda brief example of supply and deman.docx
Principles of Supply and Demanda brief example of supply and deman.docxjeffsrosalyn
 
Primary Task Response Within the Discussion Board area, write 300.docx
Primary Task Response Within the Discussion Board area, write 300.docxPrimary Task Response Within the Discussion Board area, write 300.docx
Primary Task Response Within the Discussion Board area, write 300.docxjeffsrosalyn
 
Pretend you are a British government official during the time leadin.docx
Pretend you are a British government official during the time leadin.docxPretend you are a British government official during the time leadin.docx
Pretend you are a British government official during the time leadin.docxjeffsrosalyn
 

More from jeffsrosalyn (20)

Problem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docx
Problem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docxProblem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docx
Problem 7.  Dollars for WaitingJeffrey Swift has been a messenger.docx
 
Problem 8-2B(a) Journalize the transactions, including explanation.docx
Problem 8-2B(a) Journalize the transactions, including explanation.docxProblem 8-2B(a) Journalize the transactions, including explanation.docx
Problem 8-2B(a) Journalize the transactions, including explanation.docx
 
Problem 14-4AFinancial information for Ernie Bishop Company is pre.docx
Problem 14-4AFinancial information for Ernie Bishop Company is pre.docxProblem 14-4AFinancial information for Ernie Bishop Company is pre.docx
Problem 14-4AFinancial information for Ernie Bishop Company is pre.docx
 
Problem and solution essay  about the difficulties of speaking Engli.docx
Problem and solution essay  about the difficulties of speaking Engli.docxProblem and solution essay  about the difficulties of speaking Engli.docx
Problem and solution essay  about the difficulties of speaking Engli.docx
 
problem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docx
problem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docxproblem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docx
problem 8-6 (LO 4) Worksheet, direct and indirect holding, interco.docx
 
Problem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docx
Problem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docxProblem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docx
Problem 4-5ADevine Brown opened Devine’s Carpet Cleaners on March .docx
 
Problem 1-4A (Part Level Submission)Matt Stiner started a delivery.docx
Problem 1-4A (Part Level Submission)Matt Stiner started a delivery.docxProblem 1-4A (Part Level Submission)Matt Stiner started a delivery.docx
Problem 1-4A (Part Level Submission)Matt Stiner started a delivery.docx
 
PROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docxPROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income stat.docx
 
Problem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docx
Problem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docxProblem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docx
Problem 12-9ACondensed financial data of Odgers Inc. follow.ODGE.docx
 
Problem 13-6AIrwin Corporation has been authorized to issue 20,80.docx
Problem 13-6AIrwin Corporation has been authorized to issue 20,80.docxProblem 13-6AIrwin Corporation has been authorized to issue 20,80.docx
Problem 13-6AIrwin Corporation has been authorized to issue 20,80.docx
 
Problem 1-2A (Part Level Submission)On August 31, the balance sh.docx
Problem 1-2A (Part Level Submission)On August 31, the balance sh.docxProblem 1-2A (Part Level Submission)On August 31, the balance sh.docx
Problem 1-2A (Part Level Submission)On August 31, the balance sh.docx
 
Problem 1-2A (Part Level Submission)On August 31, the balance shee.docx
Problem 1-2A (Part Level Submission)On August 31, the balance shee.docxProblem 1-2A (Part Level Submission)On August 31, the balance shee.docx
Problem 1-2A (Part Level Submission)On August 31, the balance shee.docx
 
Prior to posting in this discussion, completeThe Parking Garage.docx
Prior to posting in this discussion, completeThe Parking Garage.docxPrior to posting in this discussion, completeThe Parking Garage.docx
Prior to posting in this discussion, completeThe Parking Garage.docx
 
Prior to engaging in this discussion, read Chapters 10 and 11 in y.docx
Prior to engaging in this discussion, read Chapters 10 and 11 in y.docxPrior to engaging in this discussion, read Chapters 10 and 11 in y.docx
Prior to engaging in this discussion, read Chapters 10 and 11 in y.docx
 
Privacy in a Technological AgePrivacy protection is a hot top.docx
Privacy in a Technological AgePrivacy protection is a hot top.docxPrivacy in a Technological AgePrivacy protection is a hot top.docx
Privacy in a Technological AgePrivacy protection is a hot top.docx
 
Privacy Introduction Does the technology today Pene.docx
Privacy Introduction Does the technology today Pene.docxPrivacy Introduction Does the technology today Pene.docx
Privacy Introduction Does the technology today Pene.docx
 
Prisoner rights in America are based largely on the provisions of th.docx
Prisoner rights in America are based largely on the provisions of th.docxPrisoner rights in America are based largely on the provisions of th.docx
Prisoner rights in America are based largely on the provisions of th.docx
 
Principles of Supply and Demanda brief example of supply and deman.docx
Principles of Supply and Demanda brief example of supply and deman.docxPrinciples of Supply and Demanda brief example of supply and deman.docx
Principles of Supply and Demanda brief example of supply and deman.docx
 
Primary Task Response Within the Discussion Board area, write 300.docx
Primary Task Response Within the Discussion Board area, write 300.docxPrimary Task Response Within the Discussion Board area, write 300.docx
Primary Task Response Within the Discussion Board area, write 300.docx
 
Pretend you are a British government official during the time leadin.docx
Pretend you are a British government official during the time leadin.docxPretend you are a British government official during the time leadin.docx
Pretend you are a British government official during the time leadin.docx
 

Recently uploaded

DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 

Recently uploaded (20)

OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 

Running Head; EFFECTIVE PROJECT MANAGEMENT IN THE FACE OF RISKS .docx

  • 1. Running Head; EFFECTIVE PROJECT MANAGEMENT IN THE FACE OF RISKS 1 EFFECTIVE PROJECT MANAGEMENT IN THE FACE OF RISKS 2 Effective Project management in the Face of Risks Name Institution The Gantt Chart and the Critical Path In this week’s Learning Activity, you will be creating and expanding on the work breakdown structure (WBS) in ProjectLibre. You will also be adding/updating the Gantt Chart with predecessors, resources, and costs. Work Breakdown Structure (WBS) This week we are continuing in the planning stage of the project and will be working on tools project managers use to help not only plan the project, but to execute, control, and close out the project during the rest of the project lifecycle. The work breakdown structure (WBS) takes the project and breaks it down into smaller, more manageable pieces (Brenner,
  • 2. 2009). The end-product will be an organized, visual display of the main pieces of your project. The tasks and subtask in the WBS must stand on their own and be clear to anyone who picks up the document. Project documents are often forwarded to others who are not intimately familiar with the project and they need to be able to understand the tasks. There are no hard rules on how wide or deep your WBS structure should be. However, the subtasks, need to be small enough to maintain control and visibility and at the same time avoid excess bureaucracy. A WBS of a project to paint a few rooms in a home is provided in Figure 1 below. Note the tasks for this project are logically grouped into several sections. Figure 1: Work Breakdown Structure to Paint a Room Gantt Chart The Gantt chart is a set of horizontal lines that provide a visual view of the tasks scheduled over time. The Gantt chart is always paired with the work break down structure (WBS) so the team can see the tasks that go with the timeline. The Gantt chart is also very helpful in seeing the project’s critical path and creating a timeline. Visuals from the Gantt chart helps the team members identify which tasks must be done in sequence
  • 3. (for example, buy the paint first before painting the wall) and which tasks might be done at the same time (for example, remove the wallpaper and cover the electrical outlets). Knowing which tasks can be done simultaneously will allow the team members to better plan and coordinate resources for the project. During this week, you will be adding predecessors to your WBS and determining when different tasks and subtasks in your project should begin. This information will be reflected in your Gantt chart. You are encouraged to play around with duration and predecessors to see the impact on Gantt chart, critical path, and the overall visual. Figure 2 (below) shows the WBS with the Gantt chart (see blue horizontal lines) for the painting project. This is a good example of what a Gantt chart should look like. Figure 2: Gantt chart example with key notes Project Resource Figure 2 (above) also shows project resources, which you will be adding in this week’s learning activity. In project management, resources are the component needed to complete a project. Project resources can be people, equipment, location, funding, and any other necessary asset that is required to complete a project. Therefore, a lack of resource can be a constraint to complete a project task. Project resources should be identified, assessed, and allocated before a project starts. Resource are added to help ensure resources are properly scheduled and that no resources are being double booked or overwhelmed. Poor resource planning can
  • 4. have a significant negative consequence on a project, including delayed delivery, cost overrun, and/or inferior project deliverable. See Figure 3 below for a visual of where to add resources in ProjectLibre. Figure 3: Adding resources to ProjectLibre In this week’s learning activity, you will be adding resources and costs to your project. See below for where and how to add costs for the various resources that have been assigned to the project. Adding costs to resources is a step in figuring out the total costs of a project. Many organizations consider internal employee time when calculating the cost to a project. This is particularly true in cross- functional teams (common in projects) where labor resources come from different departments. Figure 4: Adding costs to ProjectLibre Let’s Talk Turkey – Why the Critical Path is so Important The textbook and your course goes over the critical path, so we are not going to cover it in detail here, however, the discussion below will help you bolster your understanding of the critical path and what it means to your project and how it will influence what you do in the Learning Activity. Think about Thanksgiving dinner and everything that is cooked on that day for the entire family: Turkey, ham, baked potatoes, sweet
  • 5. potato, stuffing, greens, rolls, corn bread, gravy, salads, pies and more. Planning a Thanksgiving dinner takes a great deal of consideration and organization. Project management is no different! On Thanksgiving Day, it is NOT feasible to start cooking everything at the same time nor it is practical to wait till one dish is finished before starting the preparation for the next dish. Logistically, it is also challenging to ensure that every dish is cooked at the exact the same time (instead you may end up making the salads and desserts early and reheat other things before they go on the table). Applying project management principles to our analogy of cooking Thanksgiving meal would include tasks like: write down and group the tasks that need to be done (this is your work breakdown structure), estimating the time to complete each task (task duration), resources required to complete each task (Joe, Grandma, the stove, etc.,), and which task(s) must be completed before starting another task(s) (predecessor). For Thanksgiving dinner, there are few tasks that will take a long time (cooking and thawing the turkey for example), but there are plenty of other things that can be done while the bird is thawing and cooking. Tasks that can be done at the same time are called parallel tasks. Figuring out the critical path is the key. The critical path will tell us how much time the project will take, when you need to start
  • 6. thawing and cooking the bird, and what time the dinner will start. The following video (Silverman, 2013) provides a good introduction to the critical path. While the user interface in ProjectLibre may look different, the concept remains the same. Silverman, P. (November 28, 2013). Microsoft Project Tutorial – Understanding the Critical Path (Links to an external site.) [Video file]. Retrieved from https://www.youtube.com/n- Mw3l42sgw Paul Silverman 202 subscribers Microsoft Project Tutorial - Understanding the Critical Path Watch later https://www.youtube.com/n-Mw3l42sgw https://www.youtube.com/n-Mw3l42sgw https://www.youtube.com/n-Mw3l42sgw https://www.youtube.com/channel/UCk2A_C750isUuagwvvNf9 HA?feature=embeds_subscribe_title https://www.youtube.com/watch?v=n-Mw3l42sgw Share <div class="player-unavailable"><h1 class="message">An error occurred.</h1><div class="submessage"><a href="http://www.youtube.com/watch?v=n-Mw3l42sgw" target="_blank">Try watching this video on www.youtube.com</a>, or enable JavaScript if it is disabled in your browser.</div></div> The reason for such a high emphasis on critical path is if any of
  • 7. the tasks on the critical path are delayed, then it affects the entire timeline of the project. The critical path for Thanksgiving dinner may be this: 1. Menu prep and shopping list 2. Buy the turkey 3. Thaw 20-pound turkey (using the quick method (10 to 12 hours) 4. Bake unstuffed turkey (4.2 to 5 hours) 5. Rest turkey and carve turkey (40 minutes) 6. Reheat food cooked early (20 minutes) Nothing can start until the menu prep and the turkey has been purchased /shopping is done. After that the other parts of the meal can be done while the turkey is thawing, baking, or resting. For those of us with only one oven (limited resources) it is important to include the oven in the list of resources and schedule what the oven is doing at any one time appropriately. Managing the ovens time is key on Thanksgiving. Some dishes may need to be baked (like pies and breads) while the turkey is thawing. The other things can be reallocated to the stove top or rotated in and out of the oven while the turkey is cooking. For example, potatoes for mashed potatoes can be boiled instead of baked. Sweet potatoes can often be placed in the oven with the turkey. In this week’s assignment, you will set up your work breakdown structure with deliverables, subtasks, and associated dependencies which will allow you to identify your critical path. The following video (Bradley, 2015) provides an overview of how to set up and use ProjectLibre. This resource may assist you with
  • 8. understanding how you will be using ProjectLibre throughout this course and with your Time and Cost Estimation Exercise Interactive learning activity this week. Bradley, H (July 11, 2015). Learn the basics of ProjetLibre – Your quick start to project management with ProjectLibre (Links to an external site.) [Video file]. Retrieved from https://youtu.be/oiVnWX-J5Mo Helen Bradley 45K subscribers Learn the Basics of ProjectLibre - Your Quick Start to Project Management with ProjectLibre Watch later Share <div class="player-unavailable"><h1 class="message">An error occurred.</h1><div class="submessage"><a href="http://www.youtube.com/watch?v=oiVnWX-J5Mo" target="_blank">Try watching this video on www.youtube.com</a>, or enable JavaScript if it is disabled in your browser.</div></div> Stand on its Own Remember every time you write anything it must stand on its own. Meaning the documents must have the information and background necessary for others to understand them. If others have to guess what you mean or have to make jumps in logic, then you have not accomplished your goal. As a manager or project manager, a lot of your documents will
  • 9. be forwarded as is and even someone not familiar with the project needs to be able to read and understand what your project is from the project name, to the project scope, what tasks they need to do (the work breakdown structure and WBS dictionary) and what is https://youtu.be/oiVnWX-J5Mo https://youtu.be/oiVnWX-J5Mo https://youtu.be/oiVnWX-J5Mo https://youtu.be/oiVnWX-J5Mo https://www.youtube.com/channel/UC31bW- FYjdc5gsc_Zg77vkA?feature=embeds_subscribe_title https://www.youtube.com/watch?v=oiVnWX-J5Mo https://www.youtube.com/watch?v=oiVnWX-J5Mo going on in the project and what the project manager has done about it (the milestones, issues, and overall status report). Since we will be sharing your project and your work in the classroom writing clearly is also key since the class needs to be able to understand your project and the work breakdown structure. FSBT Project Management Club Want to learn more about project management and connect with others? The Forbes School of Business and Technology™ (FSBT) at Ashford University has a Project Management Club. The FSBT Project Management Club is dedicated to the personal and professional growth of its members by sharing and discussing methodology, leadership, and career opportunities about project management. The Project Management Club is open to Ashford and FSBT students, faculty, staff, alumni, and anyone who has a strong interest in the area of project management.
  • 10. The direct URL to join the FSBT Project Management Group is: https://www.linkedin.com/groups/13536418 (Links to an external site.) References Bradley, H. (2015, July 11). Learn the basics of ProjectLibre— Your quick start to project management with ProjectLibre (Links to an external site.) [Video file]. Retrieved from https://youtu.be/oiVnWX-J5Mo Silverman, Paul (November 28, 2013). Microsoft Project Tutorial - Understanding the Critical Path (Links to an external site.) [Video file]. Retrieved from https://www.youtube.com/watch?v=n- Mw3l42sgw How to cite this lecture Milligan, S., Parikh, R. & Ardolino, E.(2019). PRM300: Time and Cost Estimations to Project Management https://www.linkedin.com/groups/13536418 https://www.linkedin.com/groups/13536418 https://youtu.be/oiVnWX-J5Mo https://youtu.be/oiVnWX-J5Mo https://youtu.be/oiVnWX-J5Mo https://youtu.be/oiVnWX-J5Mo https://www.youtube.com/watch?v=n-Mw3l42sgw https://www.youtube.com/watch?v=n-Mw3l42sgw https://www.youtube.com/watch?v=n-Mw3l42sgw
  • 11. Materials in this lecture are based on the Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved. PMBOK® is a registered mark of the Project Management Institute, Inc.