Risk Event Modeling
Intaver Institute Inc.
303, 6707, Elbow Drive S.W,
Calgary, AB, Canada
Tel: +1 (403) 692-2252
Fax: +1 (403) 459-4533
www.intaver.com
4280 East Tamiami Trail, 302-M,
Naples Florida, 34112, USA
Tel: +1(510) 984 3527
The Project Management Problem
2009 Intaver Institute
Many projects are unsuccessful!
• Budget
• Schedule
• Quality
• Other measures
Projects
consistently
fail to meet:
2009 Intaver Institute 3
Key Project Management Issues
• How to estimate project duration or cost?
• What are the most critical risks and how to handle
them?
• How to measure project performance?
• How to make an informed decision about the
future course of the project?
The Project Management Problem
1/31/2018 2009 Intaver Institute 4
Reasons
• Human psychological limits
• Inadequate training
• Poor processes
• other
The Project Management Problem
2009 Intaver Institute
Risk management key to project success
• Risks are events that can occur during a project
that changes to course of a project
• Risk is key source of project uncertainty and major
root cause of project failure
• Limited ability to forecast and manage project
uncertainty due to risk
The Project Management Problem
2009 Intaver Institute
Chains of unfortunate events
• Risks can form event chains
• A risk occurs and causes another risk to occur,
which causes yet another
• Unexpected result of a series of events derail
projects
• Statistical sampling or Monte Carlo simulations
the best solution for modeling the effect of
related and unrelated project risks
The Project Management Problem
Benefits
2009 Intaver Institute
Understand impact of risk on projects
• Understand project risk and uncertainty in Cost
and Duration
• Identify critical risks and activities
• Model risk handling efforts
• Improved contingency and buffer plans
• Monitoring with risks and uncertainties provides
strong, early signals of impending issues
Uses common PM artifacts
• WBS
• Resources
• Costs
• Risk Register or Risk Lists developed for
qualitative risk management
Risk Event Modeling Workflow
2009 Intaver Institute
Risk Definition
• Risks
– Risks are “events” that have a probability of occurring
during a project
– Risks are identified and assigned to tasks or resources
– Define impact of risks by assigning:
• Chance of occurrence
• Outcome (e.g. delay, increase in cost)
• Result (percentage or fixed value of outcome)
2009 Intaver Institute
What is Monte Carlo
Monte Carlo simulation is a mathematical method used in
risk analysis. Monte Carlo simulations are used to
approximate the distribution of potential results based on
probabilistic inputs.
Monte Carlo Simulations
Input Parameters Output Parameters
Calculation
Engine
Critical Path
Scheduling
Engine
(
)
Task duration
cost, finish time,
etc.
cost, finish time,
etc.
Project duration
Monte Carlo Schedule Analysis
4 5 6321 7 7 82 3 654 1 4 5 632 7
8 9 10 11 12 13 14 15 16
1
2
3
4
5
6
7
Task 1
Task 2
Task 3
Two Approaches to Estimating Probabilities
• The relative frequency approach, where probability equals
the number of occurrences of specific outcome (or event)
divided by the total number of possible outcomes.
• The subjective approach represents an expert’s degree of
belief that a particular outcome will occur.
Two Approaches for Defining Uncertainties
• Distribution-based approach
• Event-based approach
Which Distribution Should Be Used?
Normal Triangual Uniform
Also useful:
• Lognornal
• Beta
Distribution Fitting
Before Eliciting Judgment You Need to Have:
• A clearly defined problem
• An identified list of risks, or a risk breakdown
structure, for the project
• A project schedule
• A clearly defined set of questions you will ask
experts
In addition, your team of experts should be aware of
any personal interest that expert may have regarding
particular issues. It helps to mitigate motivational
biases.
Psychological Factors
• Availability heuristic: people judge the probability of
the occurrence of events by how easily these events
are brought to mind.
• Anchoring heuristic: refers to the human tendency
to remain close to the initial estimate.
• Wishful thinking: when we overestimate the
probabilities of opportunities and underestimate the
probabilities of risks.
Overestimating the Probability of Compound Events
If the probability of a defect in a component is 20% and the
device uses three redundant components, the probability of
the defective device will be (0.2 * 0.2 * 0.2) = 0.008%.
People tend to think this number is much higher.
Ignoring Base-Rate Frequencies
• Historically, the probability that a particular component will
be defective is 1%.
• The component is tested before installation.
• The test showed that the component is defective.
• The test usually successfully identifies defective
components 80% of the time.
• What is the probability that a component is defective?
The correct answer is close to 4%, however, most people
would think that answer is a little bit lower than 80%.
Eliciting Probabilities of Events
• Pose a direct question: “What is the probability that the
project will be canceled due to budgetary problems?”
• Ask the experts two opposing questions: (1) “What is the
probability that the project will be canceled?” and (2) “What
is the probability the project will be completed?” The sum of
these two assessments should be 100%.
• Break compound events into simple events and review them
separately.
Probability Wheel
25% No delay of activity
35% 3 day delay of activity
40% 5 day delay of activity
Task Duration
4
8
12
16
20 100%
80%
60%
40%
20%
Frequency
Probability
2 3 4 5 6
(days)
Question: What is the chance that duration
is less than 3 days?
Eliciting Judgment: Probability Method
Eliciting Judgment: Method of Relative Heights
Task Duration
2
4
6
8
10
2 3 4 5 6
50%
40%
30%
20%
10%Frequency
Probability
(days)
Question: How many times the duration
will be between 2 and 3 days?
How Many Trials Are Required?
Huge number of trials (> 1000) usually does not increase
accuracy of analysis
• Incorporate rare events
• Use convergence monitoring
What Is The Chance That a Project Will Be on Time
and Budget?
Analysis of Monte Carlo Results
• Sensitivity and Correlations
• Critical Indices
• Crucial tasks
• Critical Risks
• Probabilistic Calendars
• Deadlines
• Conditional Branching
• Probabilistic Branching
• Chance of Task Existence
Analyze Results
1/31/2018 2009 Intaver Institute 28
• Risk Scores
• Overview with and without risks
• Detailed results of analysis
View results
• Sensitivity
• Crucial Tasks
• Success Rate
• Risk Chart
Identify critical
risks and tasks
• Risk ScoresRisk Matrix
Project Gantt
1/31/2018 2009 Intaver Institute 29
When you have project
schedule and risk
breakdown structure ready
click here to perform Monte
Carlo simulations
Risk Register
Pre-mitigation Probability, Impact,
And Score
1/31/2018 2009 Intaver Institute 30
Result Gantt Chart
1/31/2018 2009 Intaver Institute 31
White bars represent
original project schedule
(no risks)
Blue bars represent
project schedule with
risks
Because of risks, project duration
significantly increased
Results of Risk Analysis
1/31/2018 2009 Intaver Institute 32
Project Summary:
project duration, cost,
and finish time with
and without risks
Results of analysis
for project cost,
finish time, and
duration
Double click on any chart to view detailed information
Detailed Results of Analysis
Move the slider to determine the
chance that project will be within budget
Get detailed
statistical data
Data can be exported
as an image or text
Detailed results can be shown for each tasks
or whole project for cost, duration, start time,
finish time, and income.
Sensitivity
Tornado chart shows risks or other
parameters that have the most
affect on the project schedule
Critical risks need to be
mitigated first
Crucial Tasks
Crucial tasks have the
most affect on the
project schedule
Crucial tasks for project cost and duration
can be different
Success Rate
A task can be canceled if it reaches a task or a project deadline or if it is affected
by risk with a “Cancel task” outcome.
Success rate is calculated
based on number of times
the task is not canceled
Risk Chart
Risk chart show risks, associated with task versus duration or cost
This task has cost
and high risk
These tasks have
balanced risk versus
Cost ratio.
Risk Matrix
Risk matrix shows probability/impact on 5x5 matrix
Double-click on a
risk to view risk
assignments
Risk Probability,
Impact and Score for
the current schedule
Risk Planning
Modeling risk mitigation efforts
•Risk handling strategies
•Transfer
•Mitigate
•Eliminate
•Ignore
•Risk mitigation efforts represent their own costs etc.
which must be accounted for
•Create multiple baselines that model pre and post
mitigation risk handling efforts
•View results of risk handling efforts
•Select project alternative based on criteria (cost,
duration, start and finish time, success rate)
Additional Resources
40
Project Think:
Why Good
Managers
Make Poor
Project
Choices
Project
Decisions: The
Art and Science
Introduction to
Project Risk
Management
and Decision
Project Risk
Analysis Made
Ridiculously
Simple

Risk Event Modeling and Event Chains

  • 1.
    Risk Event Modeling IntaverInstitute Inc. 303, 6707, Elbow Drive S.W, Calgary, AB, Canada Tel: +1 (403) 692-2252 Fax: +1 (403) 459-4533 www.intaver.com 4280 East Tamiami Trail, 302-M, Naples Florida, 34112, USA Tel: +1(510) 984 3527
  • 2.
    The Project ManagementProblem 2009 Intaver Institute Many projects are unsuccessful! • Budget • Schedule • Quality • Other measures Projects consistently fail to meet:
  • 3.
    2009 Intaver Institute3 Key Project Management Issues • How to estimate project duration or cost? • What are the most critical risks and how to handle them? • How to measure project performance? • How to make an informed decision about the future course of the project? The Project Management Problem
  • 4.
    1/31/2018 2009 IntaverInstitute 4 Reasons • Human psychological limits • Inadequate training • Poor processes • other The Project Management Problem
  • 5.
    2009 Intaver Institute Riskmanagement key to project success • Risks are events that can occur during a project that changes to course of a project • Risk is key source of project uncertainty and major root cause of project failure • Limited ability to forecast and manage project uncertainty due to risk The Project Management Problem
  • 6.
    2009 Intaver Institute Chainsof unfortunate events • Risks can form event chains • A risk occurs and causes another risk to occur, which causes yet another • Unexpected result of a series of events derail projects • Statistical sampling or Monte Carlo simulations the best solution for modeling the effect of related and unrelated project risks The Project Management Problem
  • 7.
    Benefits 2009 Intaver Institute Understandimpact of risk on projects • Understand project risk and uncertainty in Cost and Duration • Identify critical risks and activities • Model risk handling efforts • Improved contingency and buffer plans • Monitoring with risks and uncertainties provides strong, early signals of impending issues
  • 8.
    Uses common PMartifacts • WBS • Resources • Costs • Risk Register or Risk Lists developed for qualitative risk management Risk Event Modeling Workflow 2009 Intaver Institute
  • 9.
    Risk Definition • Risks –Risks are “events” that have a probability of occurring during a project – Risks are identified and assigned to tasks or resources – Define impact of risks by assigning: • Chance of occurrence • Outcome (e.g. delay, increase in cost) • Result (percentage or fixed value of outcome) 2009 Intaver Institute
  • 10.
    What is MonteCarlo Monte Carlo simulation is a mathematical method used in risk analysis. Monte Carlo simulations are used to approximate the distribution of potential results based on probabilistic inputs.
  • 11.
    Monte Carlo Simulations InputParameters Output Parameters Calculation Engine Critical Path Scheduling Engine ( ) Task duration cost, finish time, etc. cost, finish time, etc. Project duration
  • 12.
    Monte Carlo ScheduleAnalysis 4 5 6321 7 7 82 3 654 1 4 5 632 7 8 9 10 11 12 13 14 15 16 1 2 3 4 5 6 7 Task 1 Task 2 Task 3
  • 13.
    Two Approaches toEstimating Probabilities • The relative frequency approach, where probability equals the number of occurrences of specific outcome (or event) divided by the total number of possible outcomes. • The subjective approach represents an expert’s degree of belief that a particular outcome will occur.
  • 14.
    Two Approaches forDefining Uncertainties • Distribution-based approach • Event-based approach
  • 15.
    Which Distribution ShouldBe Used? Normal Triangual Uniform Also useful: • Lognornal • Beta
  • 16.
  • 17.
    Before Eliciting JudgmentYou Need to Have: • A clearly defined problem • An identified list of risks, or a risk breakdown structure, for the project • A project schedule • A clearly defined set of questions you will ask experts In addition, your team of experts should be aware of any personal interest that expert may have regarding particular issues. It helps to mitigate motivational biases.
  • 18.
    Psychological Factors • Availabilityheuristic: people judge the probability of the occurrence of events by how easily these events are brought to mind. • Anchoring heuristic: refers to the human tendency to remain close to the initial estimate. • Wishful thinking: when we overestimate the probabilities of opportunities and underestimate the probabilities of risks.
  • 19.
    Overestimating the Probabilityof Compound Events If the probability of a defect in a component is 20% and the device uses three redundant components, the probability of the defective device will be (0.2 * 0.2 * 0.2) = 0.008%. People tend to think this number is much higher.
  • 20.
    Ignoring Base-Rate Frequencies •Historically, the probability that a particular component will be defective is 1%. • The component is tested before installation. • The test showed that the component is defective. • The test usually successfully identifies defective components 80% of the time. • What is the probability that a component is defective? The correct answer is close to 4%, however, most people would think that answer is a little bit lower than 80%.
  • 21.
    Eliciting Probabilities ofEvents • Pose a direct question: “What is the probability that the project will be canceled due to budgetary problems?” • Ask the experts two opposing questions: (1) “What is the probability that the project will be canceled?” and (2) “What is the probability the project will be completed?” The sum of these two assessments should be 100%. • Break compound events into simple events and review them separately.
  • 22.
    Probability Wheel 25% Nodelay of activity 35% 3 day delay of activity 40% 5 day delay of activity
  • 23.
    Task Duration 4 8 12 16 20 100% 80% 60% 40% 20% Frequency Probability 23 4 5 6 (days) Question: What is the chance that duration is less than 3 days? Eliciting Judgment: Probability Method
  • 24.
    Eliciting Judgment: Methodof Relative Heights Task Duration 2 4 6 8 10 2 3 4 5 6 50% 40% 30% 20% 10%Frequency Probability (days) Question: How many times the duration will be between 2 and 3 days?
  • 25.
    How Many TrialsAre Required? Huge number of trials (> 1000) usually does not increase accuracy of analysis • Incorporate rare events • Use convergence monitoring
  • 26.
    What Is TheChance That a Project Will Be on Time and Budget?
  • 27.
    Analysis of MonteCarlo Results • Sensitivity and Correlations • Critical Indices • Crucial tasks • Critical Risks • Probabilistic Calendars • Deadlines • Conditional Branching • Probabilistic Branching • Chance of Task Existence
  • 28.
    Analyze Results 1/31/2018 2009Intaver Institute 28 • Risk Scores • Overview with and without risks • Detailed results of analysis View results • Sensitivity • Crucial Tasks • Success Rate • Risk Chart Identify critical risks and tasks • Risk ScoresRisk Matrix
  • 29.
    Project Gantt 1/31/2018 2009Intaver Institute 29 When you have project schedule and risk breakdown structure ready click here to perform Monte Carlo simulations
  • 30.
    Risk Register Pre-mitigation Probability,Impact, And Score 1/31/2018 2009 Intaver Institute 30
  • 31.
    Result Gantt Chart 1/31/20182009 Intaver Institute 31 White bars represent original project schedule (no risks) Blue bars represent project schedule with risks Because of risks, project duration significantly increased
  • 32.
    Results of RiskAnalysis 1/31/2018 2009 Intaver Institute 32 Project Summary: project duration, cost, and finish time with and without risks Results of analysis for project cost, finish time, and duration Double click on any chart to view detailed information
  • 33.
    Detailed Results ofAnalysis Move the slider to determine the chance that project will be within budget Get detailed statistical data Data can be exported as an image or text Detailed results can be shown for each tasks or whole project for cost, duration, start time, finish time, and income.
  • 34.
    Sensitivity Tornado chart showsrisks or other parameters that have the most affect on the project schedule Critical risks need to be mitigated first
  • 35.
    Crucial Tasks Crucial taskshave the most affect on the project schedule Crucial tasks for project cost and duration can be different
  • 36.
    Success Rate A taskcan be canceled if it reaches a task or a project deadline or if it is affected by risk with a “Cancel task” outcome. Success rate is calculated based on number of times the task is not canceled
  • 37.
    Risk Chart Risk chartshow risks, associated with task versus duration or cost This task has cost and high risk These tasks have balanced risk versus Cost ratio.
  • 38.
    Risk Matrix Risk matrixshows probability/impact on 5x5 matrix Double-click on a risk to view risk assignments Risk Probability, Impact and Score for the current schedule
  • 39.
    Risk Planning Modeling riskmitigation efforts •Risk handling strategies •Transfer •Mitigate •Eliminate •Ignore •Risk mitigation efforts represent their own costs etc. which must be accounted for •Create multiple baselines that model pre and post mitigation risk handling efforts •View results of risk handling efforts •Select project alternative based on criteria (cost, duration, start and finish time, success rate)
  • 40.
    Additional Resources 40 Project Think: WhyGood Managers Make Poor Project Choices Project Decisions: The Art and Science Introduction to Project Risk Management and Decision Project Risk Analysis Made Ridiculously Simple

Editor's Notes

  • #9 Why is this easy
  • #31 Risk register is central point of entry into risk analysis and management system Shows calculated project risk scores – ranks and identifies critical project risks. Add two screen shots. Risk Register Risk Assignment Add slide with Risk Mitigation Waterfall diagram with descriptive names
  • #32 Change to put calculated results in the Result Gantt chart
  • #34 Detailed results show certainty levels or the chance that a project parameter will be a certain value. Allows you to see the values e.g. managing at 75% certainty as well as setting buffers or contingencies.
  • #37 Calculates the success rates of tasks or project based upon deadlines or constraints