Power Services India Risk Assessment
Location:
GSECL – Sikka TPS , Jamngar-
Gujarat.
Unit: FGD Unit #2 and #3 Assessment No / Rev: GE/GSECL/RA/01
System / Activity:
Soil testing work
Date of Assessment: 02-10-2023
Consequence Rating
(C)
Stages in Risk Assessment: - 1 2 3 4 5 Legend:
⮚ Assess risks using guidelines below (Risk = L x C)
⮚ Attempt to reduce risk to as low a value as possible by applying
additional controls / actions - even if the initial assessment falls into the
“white” zone
⮚ Re-assess risks
⮚ Sign form to confirm all controls and actions shall be implemented
Likelihood Rating
(L)
1 1 2 3 4 5 Tolerable Risk
2 2 4 6 8 10
3 3 6 9 12 15
Tolerable with additional controls
implemented
4 4 8 12 16 20
5 5 10 15 20 25 Intolerable risk – seek advice
Health & Safety Risk Assessment Guidelines
Rating Likelihood of Occurrence (L) Consequence(s) (C)
1
Highly Unlikely – Unforeseeable, very short
exposure time
Minor accident – Minor injury - No Lost Time Accident (LTA)
2
Unlikely – Not reasonably foreseeable, short
exposure time
Injury requiring first aid treatment – Able to continue working - No LTA
3
Possible – May occur if control measures
insufficiently robust
Major injury / disability – Results in lasting effect, some disability, cannot immediately return to work – LTA
4 Likely – Foreseeable, prolonged exposure Permanent Consequences – Disability that requires a change in job – LTA
5 Almost Certain – Foreseeable, Imminent danger Potential Fatality
Environmental Risk Assessment Guidelines
Rating Likelihood of Occurrence (L) Consequence(s) (C)
1
Highly Unlikely – Unforeseeable, very short
exposure time
No Noticeable Impact – Negligible disturbance to the ecosystem. No local criticism. Well within legal requirements
2
Unlikely – Not reasonably foreseeable, short
exposure time
Minor Impact – Short-term disturbance to the ecosystem. Some local criticism. Within legal requirements
Power Services India Risk Assessment
3
Possible – May occur if control measures
insufficiently robust
Medium Impact – Medium-term disturbance to the ecosystem if exposure persists. Local / Third Party criticism / adverse
publicity. Complies with legal requirements
4 Likely – Foreseeable, prolonged exposure Major Impact – Long-term damage to the ecosystem. Outside legal requirements
5 Almost Certain – Foreseeable, Imminent danger
Catastrophic Impact – Irreparable damage to the ecological system. Political criticism / adverse publicity / prosecution.
Significantly outside legal requirements.
Power Services India Risk Assessment
Hierarchy to follow for Control 1- Elimination (E) 2- Substitution (S) 3- Engineering Control (EC) 4- Administrative Control (AC) 5- Use of PPE (PPEs)
Assessment No: 001
Hazards Identified
(include the exposed groups) L
(1-5)
C
(1-5)
Risk
(LxC)
Actions / Extra Controls
L
(1-5)
C
(1-5)
Residu
al Risk
(LxC)
Action
Implemented
(Sign / Date)
Task & Hazard Identification Existing Controls
Task: Material Mobilization
Hazards:
✔ Unsafe, Non Standard,
unauthorized & Non
inspected material
✔ Working with & use of
material
● List of material record
maintain
● Pre Outage checklist to be
filled signed and submitted
● All relevant test certificate to
be submitted at site for cross
verification
● Inspection of material and its
record
4 3 12
● PoWRA
● List of approved material
● Records of test
certificated
● Inspection at site
1 1 1
Daily site EHS
inspections,
daily &
weekly EHS
meetings,
training,
motivation
programmes
are carrying
out by EHS
officer to
control the
hazards.
Power Services India Risk Assessment
Assessment No: 001
Hazards Identified
(include the exposed groups) L
(1-5)
C
(1-5)
Risk
(LxC)
Actions / Extra Controls
L
(1-5)
C
(1-5)
Residu
al Risk
(LxC)
Action
Implemented
(Sign / Date)
Task & Hazard Identification Existing Controls
Task: Material Loading,
Unloading & shifting
Hazards:
✔ Unsafe Rigging
Methodology
✔ Incompetent manpower
Deployment
✔ Damaged Lifting
machines and
accessories
✔ Lifting tools & tackle
failure
● PTW
● All relevant test certificate to
be submitted
● Chain Pulley block and Trolley
available
● Lift plan availability
● Adequate supervision
● Competent manpower or
rigger
2 1 2
● Conduct TBT daily
● PoWRA
● Skill Matrix – Form 61
● Adequate supervision
● Visual, Signage’s and
Display of guidelines
● Daily visual inspection of
lifting tools & tackles
● PPE Like helmet, safety
shoes, hand gloves
1 1 1
Daily site EHS
inspections,
daily &
weekly EHS
meetings,
training,
motivation
programmes
are carrying
out by EHS
officer to
control the
hazards.
Task: Material Stacking and
storage
Hazards:
✔ Unorganized manner of
storing
✔ Wear and tear of
material
● Designated area for storing
material
● Adequate shelf
● Marking and identification
2 1 2
● Conduct TBT daily
● PoWRA
● PPE like helmet, safety
shoes, hand gloves, nose
mask and full body
harness
1 1 1
Daily site EHS
inspections,
daily &
weekly EHS
meetings,
training,
motivation
programmes
are carrying
out by EHS
officer to
control the
hazards.
Power Services India Risk Assessment
Assessment No: 001
Hazards Identified
(include the exposed groups) L
(1-5)
C
(1-5)
Risk
(LxC)
Actions / Extra Controls
L
(1-5)
C
(1-5)
Residu
al Risk
(LxC)
Action
Implemented
(Sign / Date)
Task & Hazard Identification Existing Controls
Task: Soil Tesing ( Drilling
Method).
Hazards:
✔ Fall of object
✔ Falling hazard
✔ Failure of lifting
accessories.
✔ Lifting tools & tackle
failure
✔ Falling of person &
material.
✔ Cut injury.
✔ solar radiation, dust
and noise.
✔ Toxic Gases.
● PTW.
● All lifting tools/machine must
be certified.
● Ensure hands, feet and loose
clothing are kept clear from
moving parts of the drill.
● Isolate the hazard.
4 3 12
● Conduct TBT daily
● Use of tray for stack of
tools
● PoWRA
● PPE like helmet, safety
shoes, hand gloves, nose
mask and full body
harness
1 1 1
Daily site EHS
inspections,
daily &
weekly EHS
meetings,
training,
motivation
programmes
are carrying
out by EHS
officer to
control the
hazards.
Task: Machining activities
Hazards:
✔ Sharp Edge contacts
✔ Metal particle fall in eye
✔ Assembly of fixtures
falling
✔ Miss-handling of tools
● Protection cover at sharp edge
area
● Grinding guards
● Competent person for
assembly of fixtures
● Good tools available for
cutting & drilling
3 4 12
● Conduct TBT daily
● PoWRA
● Adequate supervision
● PPE Like helmet, safety
shoes, cut resistance
hand gloves, safety
goggle
1 1 1
Daily site EHS
inspections,
daily &
weekly EHS
meetings,
training,
motivation
programmes
are carrying
out by EHS
officer to
control the
hazards.
Power Services India Risk Assessment
Prepared By: Print: Sign: Date:
Reviewed By: Print: Sign: Date:
Approved By: Print: Sign Date:

Risk assessment-Soil Testing GSECL-FGD # 02 , #3..docx

  • 1.
    Power Services IndiaRisk Assessment Location: GSECL – Sikka TPS , Jamngar- Gujarat. Unit: FGD Unit #2 and #3 Assessment No / Rev: GE/GSECL/RA/01 System / Activity: Soil testing work Date of Assessment: 02-10-2023 Consequence Rating (C) Stages in Risk Assessment: - 1 2 3 4 5 Legend: ⮚ Assess risks using guidelines below (Risk = L x C) ⮚ Attempt to reduce risk to as low a value as possible by applying additional controls / actions - even if the initial assessment falls into the “white” zone ⮚ Re-assess risks ⮚ Sign form to confirm all controls and actions shall be implemented Likelihood Rating (L) 1 1 2 3 4 5 Tolerable Risk 2 2 4 6 8 10 3 3 6 9 12 15 Tolerable with additional controls implemented 4 4 8 12 16 20 5 5 10 15 20 25 Intolerable risk – seek advice Health & Safety Risk Assessment Guidelines Rating Likelihood of Occurrence (L) Consequence(s) (C) 1 Highly Unlikely – Unforeseeable, very short exposure time Minor accident – Minor injury - No Lost Time Accident (LTA) 2 Unlikely – Not reasonably foreseeable, short exposure time Injury requiring first aid treatment – Able to continue working - No LTA 3 Possible – May occur if control measures insufficiently robust Major injury / disability – Results in lasting effect, some disability, cannot immediately return to work – LTA 4 Likely – Foreseeable, prolonged exposure Permanent Consequences – Disability that requires a change in job – LTA 5 Almost Certain – Foreseeable, Imminent danger Potential Fatality Environmental Risk Assessment Guidelines Rating Likelihood of Occurrence (L) Consequence(s) (C) 1 Highly Unlikely – Unforeseeable, very short exposure time No Noticeable Impact – Negligible disturbance to the ecosystem. No local criticism. Well within legal requirements 2 Unlikely – Not reasonably foreseeable, short exposure time Minor Impact – Short-term disturbance to the ecosystem. Some local criticism. Within legal requirements
  • 2.
    Power Services IndiaRisk Assessment 3 Possible – May occur if control measures insufficiently robust Medium Impact – Medium-term disturbance to the ecosystem if exposure persists. Local / Third Party criticism / adverse publicity. Complies with legal requirements 4 Likely – Foreseeable, prolonged exposure Major Impact – Long-term damage to the ecosystem. Outside legal requirements 5 Almost Certain – Foreseeable, Imminent danger Catastrophic Impact – Irreparable damage to the ecological system. Political criticism / adverse publicity / prosecution. Significantly outside legal requirements.
  • 3.
    Power Services IndiaRisk Assessment Hierarchy to follow for Control 1- Elimination (E) 2- Substitution (S) 3- Engineering Control (EC) 4- Administrative Control (AC) 5- Use of PPE (PPEs) Assessment No: 001 Hazards Identified (include the exposed groups) L (1-5) C (1-5) Risk (LxC) Actions / Extra Controls L (1-5) C (1-5) Residu al Risk (LxC) Action Implemented (Sign / Date) Task & Hazard Identification Existing Controls Task: Material Mobilization Hazards: ✔ Unsafe, Non Standard, unauthorized & Non inspected material ✔ Working with & use of material ● List of material record maintain ● Pre Outage checklist to be filled signed and submitted ● All relevant test certificate to be submitted at site for cross verification ● Inspection of material and its record 4 3 12 ● PoWRA ● List of approved material ● Records of test certificated ● Inspection at site 1 1 1 Daily site EHS inspections, daily & weekly EHS meetings, training, motivation programmes are carrying out by EHS officer to control the hazards.
  • 4.
    Power Services IndiaRisk Assessment Assessment No: 001 Hazards Identified (include the exposed groups) L (1-5) C (1-5) Risk (LxC) Actions / Extra Controls L (1-5) C (1-5) Residu al Risk (LxC) Action Implemented (Sign / Date) Task & Hazard Identification Existing Controls Task: Material Loading, Unloading & shifting Hazards: ✔ Unsafe Rigging Methodology ✔ Incompetent manpower Deployment ✔ Damaged Lifting machines and accessories ✔ Lifting tools & tackle failure ● PTW ● All relevant test certificate to be submitted ● Chain Pulley block and Trolley available ● Lift plan availability ● Adequate supervision ● Competent manpower or rigger 2 1 2 ● Conduct TBT daily ● PoWRA ● Skill Matrix – Form 61 ● Adequate supervision ● Visual, Signage’s and Display of guidelines ● Daily visual inspection of lifting tools & tackles ● PPE Like helmet, safety shoes, hand gloves 1 1 1 Daily site EHS inspections, daily & weekly EHS meetings, training, motivation programmes are carrying out by EHS officer to control the hazards. Task: Material Stacking and storage Hazards: ✔ Unorganized manner of storing ✔ Wear and tear of material ● Designated area for storing material ● Adequate shelf ● Marking and identification 2 1 2 ● Conduct TBT daily ● PoWRA ● PPE like helmet, safety shoes, hand gloves, nose mask and full body harness 1 1 1 Daily site EHS inspections, daily & weekly EHS meetings, training, motivation programmes are carrying out by EHS officer to control the hazards.
  • 5.
    Power Services IndiaRisk Assessment Assessment No: 001 Hazards Identified (include the exposed groups) L (1-5) C (1-5) Risk (LxC) Actions / Extra Controls L (1-5) C (1-5) Residu al Risk (LxC) Action Implemented (Sign / Date) Task & Hazard Identification Existing Controls Task: Soil Tesing ( Drilling Method). Hazards: ✔ Fall of object ✔ Falling hazard ✔ Failure of lifting accessories. ✔ Lifting tools & tackle failure ✔ Falling of person & material. ✔ Cut injury. ✔ solar radiation, dust and noise. ✔ Toxic Gases. ● PTW. ● All lifting tools/machine must be certified. ● Ensure hands, feet and loose clothing are kept clear from moving parts of the drill. ● Isolate the hazard. 4 3 12 ● Conduct TBT daily ● Use of tray for stack of tools ● PoWRA ● PPE like helmet, safety shoes, hand gloves, nose mask and full body harness 1 1 1 Daily site EHS inspections, daily & weekly EHS meetings, training, motivation programmes are carrying out by EHS officer to control the hazards. Task: Machining activities Hazards: ✔ Sharp Edge contacts ✔ Metal particle fall in eye ✔ Assembly of fixtures falling ✔ Miss-handling of tools ● Protection cover at sharp edge area ● Grinding guards ● Competent person for assembly of fixtures ● Good tools available for cutting & drilling 3 4 12 ● Conduct TBT daily ● PoWRA ● Adequate supervision ● PPE Like helmet, safety shoes, cut resistance hand gloves, safety goggle 1 1 1 Daily site EHS inspections, daily & weekly EHS meetings, training, motivation programmes are carrying out by EHS officer to control the hazards.
  • 6.
    Power Services IndiaRisk Assessment Prepared By: Print: Sign: Date: Reviewed By: Print: Sign: Date: Approved By: Print: Sign Date: