SlideShare a Scribd company logo
Weekly Meeting
HR Operations
Report & Review
Week 3
September 2022
One Team One Goal
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Man Power Site
Departement Lok Buntar Ida Manggala Sungai Puting Grand Total
AGM-CPP & Hauling 32 55 1 88
AGM-Dredging & Canal 48 3 51
AGM-Engineering 5 32 1 38
AGM-External Affairs 42 5 47
AGM-Finance 5 1 6
AGM-HRGA 13 8 1 22
AGM-Infrastructure 14 10 1 25
AGM-Learning Institute 1 1
AGM-Lok Buntar Operation 57 2 59
AGM-Marketing & Quality Control 2 3 3 8
AGM-Operations 1 3 4
AGM-Plant & Maintenance 25 36 17 78
AGM-Project Explorasi 4 4
AGM-SHE 7 22 1 30
AGM-Supply Chain 28 12 11 51
AGM-Sungai Puting Operation 64 64
AGM-Terminal & Transhipment 3 3
TOTAL 282 194 103 579
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Turn Over Employee
A. Join Employee
Employee No. Employee Name Work Location Employee Position Join Date
0222210048 Nurul Aida Fitriani Ida Manggala AGM-Land Acquisition Staff 22-Aug-22
0222210051 Cahyo Utomo Putro Ida Manggala AGM-Jr Pit Geology 29-Aug-22
0222210049
Rachma Riskina
Renanda
Ida Manggala AGM-Land Acquisition Staff 31-Aug-22
0222210050 Gilang Adhi Prabowo Ida Manggala AGM-Safety Mining Staff 1-Sep-22
0222210052 Asmauddin Putra Lok Buntar AGM-Purchasing Supervisor 5-Sep-22
0222210053 Afdila Wahyuningsih Lok Buntar
AGM-Community Services
Administration
12-Sep-22
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Turn Over Employee
B. Exit Employee
Employee
No.
Employee Name Work Location Employee Position End Date Ket
0208160010 Tommy Mario Erwindo Ida Manggala AGM - GA Coordinator 27-Aug-22 Resign
0172220517 Muhammad Jaini Lok Buntar AGM-Captain Tug Boat 27-Aug-22 PHK
0172220523 Masyani Lok Buntar AGM-Captain Tug Boat 27-Aug-22 PHK
0172220527 Ahmad Muliani Lok Buntar AGM-Captain Tug Boat 27-Aug-22 PHK
0172220515 Samsuni Riady Lok Buntar AGM-Captain Tug Boat 29-Aug-22 Resign
0162210423 Rano Sabto Wibowo Ida Manggala AGM - RFID Supervisor 7-Sep-22 Resign
0172220521 M. Rahmadiansyah Lok Buntar AGM-Captain Tug Boat 10-Sep-22 PHK
0172220518 Taslim Lok Buntar AGM-Captain Tug Boat 10-Sep-22 PHK
0172220526 Muhammad Ramadani Lok Buntar
AGM-Assistant Captain
Tugboat
17-Sep-22 PHK
0172220525 Mahdinor Lok Buntar
AGM-Assistant Captain
Tugboat
17-Sep-22 PHK
0172220533 Riki Rahman Lok Buntar
AGM-Assistant Captain
Tugboat
17-Sep-22 PHK
0172220522 Maslianor Lok Buntar
AGM-Assistant Captain
Tugboat
17-Sep-22 PHK
0172220516 Rudi Lok Buntar AGM - Captain Tug Boat 17-Sep-22 PHK
0082810238 Emelka Lok Buntar AGM-Finance Staff 26-Sep-22 Resign
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Tenaga Harian Lepas
Department Ida manggala Lok Buntar Sungai Puting Grand Total
AGM-CPP & Hauling 15 15
AGM-Dredging & Canal 1 1
AGM-External Affairs 3 14 17
AGM-HRGA 10 5 16 31
AGM-Infrastructure 7 1 8
AGM-Lok Buntar Operation 3 3
AGM-Marketing 1 2 3 6
AGM-Plant & Maintenance 4 3 6 13
AGM-SHE 10 3 1 14
AGM-Sungai Puting
Operation
10 10
AGM-Supply Chain 4 4
Grand Total 50 36 36 122
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Attendance Ratio
Periode 1 – 19 September 2022
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Attendance Ratio
Periode 1 – 19 September 2022
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Medical Claim
PERIODE Jumlah Klaim Jumlah Rupiah APPROVAL SITE SENT HO APPROVAL HO SENT TO FINANCE
1 – 15 Maret 2022 54 25.517.234 17 Maret 2022 17 Maret 2022 21 Maret 2022 21 Maret 2022
16 – 31 Maret 2022 59 23.478.930 05-Apr-22 05-Apr-22 08-Apr-22 09-Apr-22
1 – 15 April 2022 37 24.172.068 18-Apr-22 18-Apr-22 22-Apr-22 22-Apr-22
16 – 30 April 2022 29 11.294.665 10 Mei 2022 10 Mei 2022 23 Mei 2022 23 Mei 2022
1 – 15 Mei 2022 39 16.230.009 18 Mei 2022 18 Mei 2022 27 Mei 2022 27 Mei 2022
16 – 31 Mei 2022 51 40.022.872 08 Juni 2022 13 Juni 2022 15 Juni 2022 15 Juni 2022
1 – 15 Juni 2022 40 20.801.852 17 Juni 2022 17 Juni 2022 28 Juni 2022 28 Juni 2022
16 – 30 Juni 2022 42 37.758.554 01 Juni 2022 01 Juni 2022 21 Juli 2022 21 Juli 2022
01 – 15 Juli 2022 46 27.452.625 20 Juli 2022 20 Juli 2022 05 Agt 2022 06 Agt 2022
16 – 31 Juli 2022 68 36.313.396 03 Agt 2022 03 Agt 2022 08 Agt 2022 08 Agt 2022
01 – 15 Agustus 2022 42 18.167.007 16 Agt 2022 16 Agt 2022 22 Agt 2022 22 Agt 2022
16 – 31 Agustus 2022 41 26.283.750 04 Sep 2022 04 Sep 2022 09 Sep 2022 09 Sep 2022
01 – 15 September 2022 82 34.795.927 16 Sep 2022 18 Sep 2022
Note : Medical LBCT Masih di HO menunggu persetujuan Pak Ace
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Rekap Tenaga Harian
PERIODE
Jumlah
THL
Jumlah Rupiah
Terima Rekap
Absen
Department
APPROVAL
SITE
SENT HO
APPROVAL
HO
SENT TO
FINANCE
SENT TO
BRI
BRI SENT TO
EMPLOYEE
21 Feb – 20 Mar
2022
116 Rp 269.936.488 22 Maret 22 24 Maret 22 25 Maret 22 31 Maret 22 31 Maret 22 31 Maret 22 01-Apr-22
21 Maret – 20
April 2022
116 Rp 321.689.000 21-Apr-22 22-Apr-22 22-Apr-22 26-Apr-22 26-Apr-22 27-Apr-22 27-Apr-22
21 April – 20 Mei
2022
120 Rp 294.967.300 23 Mei 22 25 Mei 2022 25 Mei 2022 31 Mei 2022
31 Mei 2022
(Sore)
02-Jun-22 02-Jun-22
21 Mei – 20 Juni
2022
121 Rp 351.321.400 21 Juni 2022 23 Juni 2022 23 Juni 2022 28 Juni 2022 29 Juni 2022 29 Juni 2022 29 Juni 2022
21 Jun – 20 Jul
2022
122 Rp 328.435.891 21 Juli 2022 23 Juli 2022 23 Juli 2022 27 Juli 2022 27 Juli 2022 28 Juli 2022 28 Juli 2022
21 Jul – 20 Ags
2022
122 Rp. 341.052.300 21 Ags 2022 22 Ags 2022 22 Ags 2022 30 Ags 2022 31 Ags 2022 31 Ags 2022 31 Ags 2022
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Improvement SS
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Improvement QCC &
QCP
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
No Department Penambahan Baru Replacement Position Open Position Close
1. Engineering 3 1 1 3
2. SHE 6 0 2 4
3. HRGA 1 1 2 0
4. Infrastructure 2 1 2 1
5. Supply Chain 2 2 2 2
6. External Affairs 9 0 3 6
7. CPP Hauling 5 1 5 1
8. Plant & Maintenance 2 2 3 1
9. SPCT 4 0 1 3
10. IR & RM 2 0 1 1
11. Quality Control 0 1 1 0
12. LBCT 3 1 4 0
Total 39 10 27 22
Open Position July &
Agustus
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
HO recruitment
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourchin
g
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 CSR Supervisor
External Affair - CSR /
Comdev HO 1 Supervisor 14-Mar-22 133 Wa Ode 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ
Ana Nurlatifah 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ
Nur Azisya 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ
Faradila Nasri 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 05-Jul-22 12-Jul-22 12-Jul-22 X Withdraw
Dian N 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ
2 Govrel Supervisor External Affair - Govrel HO 1 Supervisor 19-Apr-22 97 Indra 19-Apr-2022 X X X X X X X NQ
3 HRGA Spv HRGA HO 1 Supervisor 27-Mei-22 59 Dony 19-Apr-2022 09-Jul-22 X X X X X X NQ
Herman M 19-Apr-2022 09-Jul-22 X X X X X X NQ
4 Civil Mining Supervisor
Infrastruktur -
Transhipment HO 1 Supervisor 25-Mei-22 61 19-Apr-2022
5 Sr. Civil engineering
Infrastruktur -
Transhipment HO 1 Supervisor 25-Mei-22 61 Mufqi 19-Apr-2022 9 Aug 22 Interview HR
6
Internal Audit
Supervisor
Internal Audit & Risk
Management HO 1 Supervisor 11-Mar-22 136 Michael 19-Apr-2022 22-Jun-22 26-Jun-22 26-Jun-22
Interview Final Yonathan
Laurendy
Yazid 19-Apr-2022
Eka Prasetya 19-Apr-2022
Alfian Fani 19-Apr-2022
Yonathan
Laurendy 19-Apr-2022
Interview Final Yonathan
Laurendy
Febrian Luthfigar 19-Apr-2022 5 Juli 22 6-Jul-22
Nicholas 19-Apr-2022 20 Juli 22 21-Jul-22 Discuss salary expect
Process
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
HO recruitment
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourchin
g
(Tgl
Iklan)
Intervie
w
Psikotest
Intervie
w
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
7 Mine Plan Engineer
Mining Operation -
Engineering HO 1
Supervi
sor 20-Apr-22 96
Dori Apriman
Dhuha 19-Apr-2022
28-Jun-
22 X X X X NQ
M.Riza Fahlevi 19-Apr-2022
Mahmudin 19-Apr-2022
Adi Sulistya 19-Apr-2022
Galang
Budiansyah 19-Apr-2022
Cipta Fakar N 19-Apr-2022 9-Jul-22 15-Jul-22 26-Jul-22 Withdraw
Krisna Hanjar 19-Apr-2022 28-Jul-22 29-Jul-22 28 Juli 22 29 Jul 22 4 Aug 22 Psikotest, salary proposal
Bayu
Widiyartanto 19-Apr-2022 28-Jul-22 29-Jul-22 28 Juli 22 Not recommended
Yuli Yahya 19-Apr-2022 28-Jul-22 29-Jul-22 28 Juli 22 Not recommended
8 Supervisor Maintenance (IM)
Plant &
Maintenance HO 1
Supervi
sor
Approve site 17
Jun 22 19-Apr-2022
9
Safety Transhipment
Supervisor SHE - Transhipment HO 2
Supervi
sor 11-Nov-21 256 Sink 19-Apr-2022 09-Jul-22 X X X X X X NQ
Agus 19-Apr-2022 09-Jul-22 X X X X X X NQ
Donovan 19-Apr-2022 09-Jul-22 X X X X X X NQ
Surya 18-Jun-2022 20-Jul-22 20-Jul-22 Interview final
Gulfrid Baan 18-Jun-2022 20-Jul-22 20-Jul-22 Interview final
10 Purchasing Supervisor
Supply Chain -
Purchasing HO 1
Supervi
sor 21-Apr-22 95 M.Rian Munandar 19-Apr-2022 X X X X X X X Interview User
Ashadika 19-Apr-2022 X X X X X X X
Ali Sabaha
Kurniawan 19-Apr-2022 X X X X X X X
Sriyono 19-Apr-2022 22 Juli 22 X X X X X X
Afdian Eko
Wibowo 19-Apr-2022 22 Juli 22 X X X X X X WD
Dannis Akbar
Kurniawan 19-Apr-2022 22 Juli 22 X X X X X X
Asmauddin Putra 19-Apr-2022 30 Juli 22 1 Agu 22 30 Juli 22 6 Aug 22 2 Aug 22 8 Aug 22 Salary proposal
11
Warehouse & Logistic
Suptend Supply Chain HO 1
Supten
d PKB process Rahmadi Rizki 20-Jul-2022 21 Juli 2225 Juli 22 3 Agu 22 Interview SCM & CFO
Process
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
HO recruitment
No Position Department PIC MPP Level Date of PKB
SLA
as
per
toda
y
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes
1 Surveyor Supervisor External Affair - LA HO 1
Supervi
sor
25-Nov-21 162
Rezki
Marahalim
19-Apr-22 19-Apr-22 21-Apr-22 03-Apr-22 06-Apr-22 06-Mei-22 Close
2
Land Acquisition
Supervisor
External Affair - LA HO 1
Supervi
sor
25-Nov-21 164 Heri Supriyanto 19-Apr-22 19-Apr-22 05-Apr-22 08-Apr-22 08-Mei-22 Close
3 FGDP Engineering Mining Operation HO 1 Officer 11-Okt-21 213Dzaky Ilham 19-Apr-22 19-Apr-22 09-Apr-22 12-Apr-22 12-Mei-22 Close
4
Warehouse & Logistic
Superintendent
Supply Chain -
Warehouse
HO 1
Superi
ntende
nt
09-Feb-22 105 Djoli Hendra S 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Apr-22 22-Apr-22 25-Apr-22 25-Mei-22 Close
5
Purchasing
Superintendent
Supply Chain -
Purchasing
HO 1
Superi
ntende
nt
17-Feb-22 104 M Ismail 19-Apr-22 19-Apr-22 29-Apr-22 02-Mei-22 01-Jun-22 Close
6 IT Officer Supply Chain - HO HO 1 Officer 25-Mar-22 82 Aldi 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close
Close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Engineering
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 Surveyor
Mining Operation -
Engineering Site 1
Group
Leader PKB Process Taufik 18-Jun-2022 25-Jul-22 27-Jul-22 X X X X X NQ
Ardy Widi 18-Jun-2022 25-Jul-22 27-Jul-22 27-Jul-22 X X X X NQ
Jhontrado 18-Jun-2022 26-Jul-22 27-Jul-22 X X X X X NQ
Sulaiman Sinaga 18-Jun-2022 26-Jul-22 27-Jul-22 6-Agu-22 10-Agu-22 MCU
No Position Department PIC MPP Level Date of PKB
SLA
as
per
toda
y
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1
Data Processing
Officer
Mining Operation -
Engineering
Site 1 Officer 19-Apr-22 55 Hangger 01-Feb-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 11-Mei-22 14-Mei-22 13-Jun-22 Close
2 Jr. Geotech Engineer
Mining Operation -
Engineering
site 1 Officer 21-Feb-22 114 Zainul Ngatiq 00-Jan-00 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close
3 Jr. Pit Geology
Mining Operation -
Engineering
site 1 Officer 21-Sep-21 302 M Faiq 19-Apr-22 25-Apr-22 25-Apr-22 27-Mei-22 07-Jun-22 23-Jun-22 05-Jul-22 20-Jul-22 Close
4 Jr. Pit Geology
Mining Operation -
Engineering site 1 Officer 21-Sep-21 307 Cahyo 19-Apr-2022 25-Apr-22 25-Apr-22 27-Mei-22 07-Jun-22 23-Jun-22 21-Jul-22 29-Agu-22 CLose
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Road Maintenance
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourch
ing
(Tgl
Iklan)
Intervi
ew
Psikote
st
Intervi
ew
Final
MCU
Salary
Propos
al
Offerin
g
Letter
On
Boardi
ng
Notes
1 Motor Grader Operator Road Maintenance Site 1
Non
Staff 06-Des-21 231 Jarun 19-Apr-2022 28-Jun-22 06-Jul-22 06-Jul-22 07-Jul-22 X X X WD
Bustanul 19-Apr-2022 11-Jul-22 11-Jul-22 11-Jul-22 X X X X NQ User
Trisetiyo 19-Apr-2022 28-Jun-22 06-Jul-22 06-Jul-22 07-Jul-22 23-Jul-22 X X NQ MCU
No Position Department PIC MPP Level Date of PKB
SLA
as
per
toda
y
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes
1
Motor Grader
Operator Road Maintenance Site 1
Non
Staff 06-Des-21 231
Mukhtar
Faulana Hire Internal
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
SHE
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 Safety Group Leader SHE - Mining site 1
Group
Leader 10-Jun-22 45 Zamakh 19-Apr-2022 28-Jun-22 05-Jul-22 19-Jul-22 X X X X NQ
Tommy Mario 18-Jun-2022 28-Jun-22 05-Jul-22 X X X X X NQ
Tommy 18-Jun-2022 28-Jun-22 05-Jul-22 X X X X X NQ
TriJoko M 18-Jun-2022 28-Jun-22 X X X X X X NQ
Tomy Destyan 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 X X X X NQ
Tomy Aprianto 18-Jun-2022 28-Jun-22 X X X X X X NQ
Asyrofi 18-Jun-2022 28-Jun-22 X X X X X X NQ
Rio Martha 18-Jun-2022 28-Jun-22 X X X X X X NQ
Indra Adam 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 29-Jul-22 23-Jul-22 X X Withdraw
2 Safety Group Leader SHE - Transhipment site 1
Group
Leader 13-Jun-22 42
Agung Dwi
Rahmanto 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 X X X X NQ
Rezali Haidir 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 X X X X NQ
Rio Harianto 18-Jun-2022 17-Jun-22 18-Jun-22 21-Jul-22 X X X X NQ
Tesya Ananda
Siregar 18-Jun-2022 17-Jun-22 18-Jun-22 X X X X X NQ
Valentino
Sugiarto 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 X X X X WD
Suharyono 18-Jun-2022 12-Jul-22 12-Jul-22 21-Jul-22 X X X X NQ
No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Note
s
1
Satefy Patrol Group
Leader
SHE - Mining site 1 Officer 23-Agu-21 296 R Prabowo 00-Jan-00 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close
2 Safety Group Leader SHE - Mining site 1
Group
Leader 10-Jun-22 45 Gilang Adhi P 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 22-Jul-22 23-Jul-22 7 Agu 22 1 Sep 22 Close
3
Reclamation &
Revegetation Officer
SHE - Quality and
System
site 1
Group
Leader
11-Mar-22 57 Irwan Pasdar 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Apr-22 26-Apr-22 30-Apr-22 07-Mei-22 Close
4
Monitoring Control
Officer
SHE - Quality and
System
site 1 Officer 09-Feb-22 95 Darintia 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Apr-22 17-Apr-22 25-Apr-22 15-Mei-22 Close
5
Integrated Farming &
DAS
SHE - Quality and
System
Site 1
Group
Leader
25-Apr-22 98 Rennyta 30-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 03-Jun-22 17-Jun-22 05-Jul-22 01-Agu-22 Close
6
Planning
Development Officer
SHE - Quality and
System
Site 1 Officer 12-Mar-22 142 Raudlatul 19-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 21-Mei-22 17-Jun-22 05-Jul-22 01-Agu-22 Close
7
Document Control
Officer
SHE - Quality and
System Site 1 Officer 25-Apr-22 91
Emiliyana
Varida S 30-Apr-2022 18-Mei-22 18-Mei-22 19-Mei-22 30-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 Close
8 Safety Group Leader SHE - Transhipment site 2
Group
Leader 13-Jun-22 42
Catur Ravia
Chandra 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 25-Jun-22 25-Jun-22 12-Jul-22 01-Agu-22 close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
HRGA
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 HR Admin HRGA Site 1 Admin 25-Mei-22 61 Mega 18-Jun-2022 30-Jun-22 02-Jul-22 30-Jun-22 21-Jul-22 MCU, Waiing Decission super user
Nabila 18-Jun-2022 30-Jun-22 02-Jul-22 30-Jun-22 X X X X Hold
Ananda 18-Jun-2022 6-Jul-22 X X X X X X NQ
Process
Close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Infrastructure
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
toda
y
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest Interview Final MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 Doco
Infrastruktur -
Transhipment
Site 1
Group
Leade
r
27-Feb-22 138 Zikri Adham 27-Feb-22 08-Apr-22 18-Mei-22 19-Mei-22 28-Mei-22 12-Jun-22 15-Jun-22 15-Jul-22 Close, internal hire
1 Field Engineer
Infrastruktur -
Transhipment
Site 1
Office
r
25-Mei-22 48
M Abdullah
Rofie
30-Mei-22 01-Jun-22 02-Jun-22 20-Apr-22 15-Jun-22 23-Jun-22 05-Jul-22 12-Jul-22 CLose
2
Civil Mining Group
Leader
Infrastruktur -
Transhipment Site 1
Group
Leade
r 25-Mei-22 61 Rasyid 18-Jun-2022 07-Apr-22 07-Apr-22 20-Apr-22 24-Jun-22 02-Jul-22 12-Jul-22 25-Agu-22 Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourch
ing
(Tgl
Iklan)
Intervi
ew
Psikote
st
Intervi
ew
Final
MCU
Salary
Propos
al
Offerin
g
Letter
On
Boardi
ng
Notes
1
Drafter & Document
Control Infrastruktur Site 1
Group
Leader
PKB On
Process Sourching
2
Civil Transhipment
Group Leader Infrastruktur Site 1
Group
Leader
PKB On
Process Sourching
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Supply Chain
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourch
ing
(Tgl
Iklan)
Intervi
ew
Psikote
st
Intervi
ew
Final
MCU
Salary
Propos
al
Offerin
g
Letter
On
Boardi
ng
Notes
1 IT Programmer Supply Chain - IT Site 1 Officer 19-Apr-22 97 Satrio 19-Apr-2022 18-Mei-22 18-Mei-22 19-Mei-22 25-Mei-22 23-Jun-22 X X
Satrio WD, Sourching
New Kandidat
DanuWinisuda 19-Apr-2022 21-Jul-22 X X X X X X NQ
Syaukani 19-Apr-2022 28 Jul 22 X X X X X X NQ
IGede 19-Apr-2022 28 Jul 22 29 Jul 22 X X X X X NQ
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama
Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 IT Officer Supply Chain - HO HO 1 Officer 25-Mar-22 82 Aldi 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close
2
Purchasing
Superintendent
Supply Chain -
Purchasing
HO 1 Superintendent 17-Feb-22 104 M Ismail 19-Apr-22 19-Apr-22 29-Apr-22 02-Mei-22 01-Jun-22 Close
3
Fuelman Supply Chain Site 1 Non Staff 11-Jul-22 14 Nur Sigit 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 14-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close
4 IT Officer Supply Chain - IT Site 1 Officer 19-Apr-22 87 Miko 19-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 28-Mei-22 12-Jun-22 15-Jun-22 15-Jul-22 Close
5
Fuelman
Supply Chain -
Warehouse
Site 1
Non Staff 11-Jul-22 M.Haykal 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 16-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
External Affair
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 Comser Administrator External Affair - Comser Site 1 Officer 11-Jun-22 44 Oktaviani 18-Jun-2022 24-Jun-22 24-Jun-22 24-Jun-22 X X X X NQ
Khaliq Adady 18-Jun-2022 24-Jun-22 24-Jun-22 24-Jun-22 26-Jul-22 X X X Unfit
Afdila 18-Jun-2022 30-Jun-22 02-Jul-22 30-Jun-22 29-Jul-22 09-Agu-22 Salary Proposal
2 LA - Negosiator External Affair - LA Site 2 Officer 21-Jun-22 34 Haris 18-Jun-2022 29-Jun-22 30-Jun-22 29-Jun-22 05-Jul-22 23-Jul-22 7 Agu 22 Offering Letter
Oby Dinata 18-Jun-2022 29-Jun-22 30-Jun-22 29-Jun-22 X X X X Withdraw
Hady Susanto 18-Jun-2022 29-Jun-22 14-Jul-22 29-Jun-22 26-Jul-22 23-Jul-22 X X UNFIT
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA as
per
today
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes
1 LA - Senior Admin External Affair - LA Site 1 Officer 10-Jun-22 32 Devi 30-Mei-22 30-Mei-22 30-Mei-22 12-Jun-22 21-Jun-22 23-Jun-22 05-Jul-22 12-Jul-22 Close
2 LLA Officer External Affair - LA Site 1 Officer 21-Jun-22 36 Takdir 30-Mei-22 30-Mei-22 30-Mei-22 12-Jun-22 21-Jun-22 23-Jun-22 05-Jul-22 27-Jul-22 Close
3 LA - Surveyor External Affair - LA Site 2 Officer 21-Jun-22 34 Dimyati 18-Jun-2022 21-Jun-22 21-Jun-22 21-Jun-22 27-Jun-22 02-Jul-22 21-Jul-22 08-Agu-22 Close
4 LA - Senior Admin External Affair - LA Site 2 Officer 10-Jun-22 45 Nurul Aida 30-Mei-22 30-Mei-22 12-Jul-22 12-Jul-22 14-Jul-22 23-Jul-22 7 Agu 22 22-Agus-22 CLose
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
CPP Hauling
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1
Weight Bridge
Operator
Mining Operation -
CPP & Hauling Site 3
Non
Staff 05-Jul-22 20 Nor Ifansyah 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 X X X NQ
Josswa 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 X X X NQ
Isra 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 X X X NQ
M. Fernanda 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 09-Agu-22 Salary proposal
A. Syaiifullah 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 09-Agu-22 Salary proposal
M. Rijani 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 NQ
2 Driver Water Truck
Mining Operation -
CPP & Hauling Site 2
Non
Staff
Belum ada
PKB M. Khatami 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 Review
Agus Melas 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 Review
No Position Department PIC MPP Level Date of PKB
SLA as
per
today
Nama
Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes
1
Hauling Group Leader
(Blok IV)
Mining Operation -
CPP & Hauling
Site 1
Group
Leader
21-Apr-22 71 A Zainuddin 21-Apr-22 12-Mei-22 12-Mei-22 21-Mei-22
22-Mei-
22
29-Mei-22 01-Jun-22 01-Jul-22 Close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Plant & Maintenance
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1
Senior Mechanic A2B
(IM) Plant & Maintenance Site 1 Non Staff 19-Apr-22 97 Teguh Santoso 18-Jun-2022 01-Jul-22 05-Jul-22 01-Jul-22 X X X X WD
Muhammad Rizka Arief 18-Jun-2022 19-Jul-22 19-Jul-22 19-Jul-22 20-Jul-22 X X X NQ
2 Mekanik A2B (SP) Plant & Maintenance Site 1 Non Staff
Approve site
28 jul 22 Wildan 18-Jun-2022
Fahrur Reza 18-Jun-2022
Wahyono 18-Jun-2022
3 PKB Fix Plan (LB Plant & Maintenance Site 1 Non Staff
Approve site
3 agu 22 Rian Hariyadi 18-Jun-2022
No Position Department PIC MPP Level Date of PKB
SLA as
per
today
Nama
Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest Interview Final MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1
Senior Mechanic A2B
(IM) Plant & Maintenance Site 1 Non Staff 19-Apr-22 97 Lutfi Prayogo 18-Jun-2022 01-Jul-22 05-Jul-22 01-Jul-22 25-Jul-22 23-Jul-22 7 Agu 22 8 Agu 22 CLose
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
SPCT
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourchin
g
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 TCT Operation GL
Sungai Putting
Operation Site 1 Officer 19-Apr-22 97 Mawardi 18-Jun-2022 17-Jun-22 22-Jun-22 22-Jun-22 29-Jul-22 X X X NQ
No Position Department PIC MPP Level Date of PKB
SLA
as
per
toda
y
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 Port Officer
Sungai Putting
Operation
Site 1 Officer 22-Apr-22 52 Eginius 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 11-Mei-22 14-Mei-22 13-Jun-22 Close
2 TCT Operation GL
Sungai Putting
Operation
Site 1 Officer 19-Apr-22 58 Hany Sadewa 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 14-Mei-22 17-Mei-22 16-Jun-22 Close
3 TCT Operation GL
Sungai Putting
Operation Site 1 Officer 19-Apr-22 97 Muhammad Arif 18-Jun-2022 17-Jun-22 22-Jun-22 22-Jun-22 25-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
LBCT
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 Excavator Operator
Transhipment - LB
Operation
Site 1
Non
Staff
Belum ada
PKB
Shahrul
Sourching
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
QC
Process
Close
No Position Department PIC MPP Level Date of PKB
SLA
as
per
today
Nama Kandidat
Sourching
(Tgl
Iklan)
Interview
Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On
Boarding
Notes
1 QC Crew Quality Control Site 1
Non
Staff
PKB On
Process Irbani Sourching
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Posisi Close Agustus
No Position Department PIC MPP Level Date of PKB
SLA
as
per
toda
y
Nama Kandidat
Sourching
(Tgl Iklan)
Interview Psikotest
Interview
Final
MCU
Salary
Proposal
Offering
Letter
On Boarding Notes
1 LA - Surveyor External Affair - LA Site 1 Officer 21-Jun-22 34 Dimyati 18-Jun-2022 21-Jun-22 21-Jun-22 21-Jun-22 27-Jun-22 02-Jul-22 21-Jul-22 08-Agu-22 Close
2 LA - Senior Admin External Affair - LA Site 1 Officer 10-Jun-22 45 Nurul Aida 30-Mei-22 30-Mei-22 12-Jul-22 12-Jul-22 14-Jul-22 23-Jul-22 7 Agu 22 22-Agus-22 CLose
3 LLA Officer External Affair - LA Site 1 Officer 21-Jun-22 Fathur Rohman 18-Jun-2022 21-Jun-22 21-Jun-22 21-Jun-22 15-Jul-22 23-Jul-22 7 Agu 22 15-agu-22 Close
4 LLA Officer External Affair - LA Site 1 Officer 21-Jun-22 Rahma Ryzkina Renantha 30-Mei-22 19-Jul-22 19-Jul-22 19-Jul-22 21-Jul-22 23-Jul-22 7 Agu 22 22-Agus-22 Close
5 Civil Mining Group
Leader
Infrastruktur -
Transhipment Site 1
Group
Leader 25-Mei-22 61 Rasyid 18-Jun-2022 07-Apr-22 07-Apr-22 20-Apr-22 24-Jun-22 02-Jul-22 12-Jul-22 25-Agu-22 Close
6
Jr. Pit Geology
Mining Operation -
Engineering site 1 Officer 21-Sep-21 307 Cahyo 19-Apr-2022 25-Apr-22 25-Apr-22 27-Mei-22 07-Jun-22 23-Jun-22 21-Jul-22 29-Agu-22 CLose
7 Senior Mechanic A2B
(IM) Plant & Maintenance Site 1
Non
Staff 19-Apr-22 97 Lutfi Prayogo 18-Jun-2022 01-Jul-22 05-Jul-22 01-Jul-22 25-Jul-22 23-Jul-22 7 Agu 22 8 Agu 22 CLose
8
Safety Group Leader SHE - Mining site 1
Group
Leader 10-Jun-22 45 Gilang Adhi P 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 22-Jul-22 23-Jul-22 7 Agu 22 1 Sep 22 Close
9
Integrated Farming &
DAS
SHE - Quality and
System
Site 1
Group
Leader
25-Apr-22 98 Rennyta 30-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 03-Jun-22 17-Jun-22 05-Jul-22 01-Agu-22 Close
10
Planning
Development Officer
SHE - Quality and
System
Site 1 Officer 12-Mar-22 142 Raudlatul 19-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 21-Mei-22 17-Jun-22 05-Jul-22 01-Agu-22 Close
11 Document Control
Officer
SHE - Quality and
System Site 1 Officer 25-Apr-22 91 Emiliyana Varida S 30-Apr-2022 18-Mei-22 18-Mei-22 19-Mei-22 30-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 Close
12
Safety Group Leader SHE - Transhipment site 1
Group
Leader 13-Jun-22 42 Catur Ravia Chandra 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 25-Jun-22 25-Jun-22 12-Jul-22 01-Agu-22 close
13 SHE Group Leader SHE - Transhipment Site 1 Officer 13-Jun-22 Muhammad Mujahid 18-Jun-2022 12-Jul-22 12-Jul-22 21-Jul-22 22-Jul-22 23-Jul-22 6 agu 22 8 Agu 22 Close
14
TCT Operation GL
Sungai Putting
Operation Site 1 Officer 19-Apr-22 97 Muhammad Arif 18-Jun-2022 17-Jun-22 22-Jun-22 22-Jun-22 25-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 close
15
Fuelman Supply Chain Site 1
Non
Staff 11-Jul-22 14 Nur Sigit 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 14-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close
16
Fuelman
Supply Chain -
Warehouse
Site 1 Non
Staff 11-Jul-22 M.Haykal 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 16-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close
PT. BARAMULTI SUKSES SARANA TBK
PT. ANTANG GUNUNG MERATUS
Promosi Jabatan
No Nama Company Posisi Lama Posisi Baru Mulai Act. Selesai Act
Status
(selesai/lanjut
acting)
Jadwal Presentasi
1 Sulaiman A AGM Transhipment Safety Patrol (LB) SHE Group Leader 1 Maret 2021 31 Mei 2021 Lanjut Acting 6 bulan setelah presentase
2 Raihani AGM Lanjut Acting
3 Muhammad Majeni AGM Kepala Juru Masak GA Group Leader 1 Februari 2021 31 April 2021 Presentasi Agustus W3
4 Saeful Ruslan Hidayat AGM Weightbridge Operator Weightbridge Group Leader Presentasi Agustus W3
5 Sugeng Ariyanto AGM Tolgate Operator Tolgate Group Leader
6 Slamet Bolawi AGM AGM-Excavator Operator (LB) AGM-Excavator Operator (LB) 01 Juli 2021 31 Des 2021
7 Kustani Safran AGM AGM-SHE Jr Supervisor AGM-SHE Supervisor Lulus
8 Taufik AGM AGM-Safety Patrol (SP) AGM-Hauling Group Leader 1 Juli 2022 31 Des 2022
9 Abdul Mukhid AGM AGM-Fix Plan Mekanik (LB) AGM-Fix Plan Group Leader
Created by Irwin Febrian/122
TERIMA KASIH

More Related Content

What's hot

Construction of cc_road
Construction of cc_roadConstruction of cc_road
Construction of cc_road
Madhu Choudhary
 
Water safety plan bangladesh
Water safety plan bangladeshWater safety plan bangladesh
Water safety plan bangladesh
Asian Paint Bangladesh Ltd
 
Highway Alignment
Highway Alignment Highway Alignment
Highway Alignment
RAMPRASAD KUMAWAT
 
Highway planning
Highway planningHighway planning
Highway planning
AKANSHA GURELE
 
Distresses in the pavement
Distresses in the pavementDistresses in the pavement
Distresses in the pavement
Bhavya Jaiswal
 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdf
Er. Bam Bhandari
 
Global positioning system_Surveying, Civil Engineering
Global positioning system_Surveying, Civil EngineeringGlobal positioning system_Surveying, Civil Engineering
Global positioning system_Surveying, Civil Engineering
A Makwana
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
RAMPRASAD KUMAWAT
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
Mylene Delmoro
 
Drone survey
Drone surveyDrone survey
Drone survey
ShramikMane1
 
Highway route location
Highway route locationHighway route location
Highway route location
wrya hade
 
GPS surveying/DIGITAL SURVEYING
GPS  surveying/DIGITAL SURVEYINGGPS  surveying/DIGITAL SURVEYING
GPS surveying/DIGITAL SURVEYING
Avinash Kumar Gupta
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
Tashfique Chowdhury
 
chapter19. Terrestrial and Close-Range Photogrammetry.pdf
chapter19. Terrestrial and Close-Range Photogrammetry.pdfchapter19. Terrestrial and Close-Range Photogrammetry.pdf
chapter19. Terrestrial and Close-Range Photogrammetry.pdf
ssuser3f7a17
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
reemajadwani
 
Total station Surveying
Total station SurveyingTotal station Surveying
Total station Surveying
Kiran M
 
Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & Pavements
Aaqib Iqbal
 
River training works lecture
River training works lectureRiver training works lecture
River training works lecture
sarhad university peshawer
 
Traffic control devices
Traffic control devicesTraffic control devices
Traffic control devices
Abhishek Kansara
 
Drawing And Report
Drawing And Report Drawing And Report
Drawing And Report
RAMPRASAD KUMAWAT
 

What's hot (20)

Construction of cc_road
Construction of cc_roadConstruction of cc_road
Construction of cc_road
 
Water safety plan bangladesh
Water safety plan bangladeshWater safety plan bangladesh
Water safety plan bangladesh
 
Highway Alignment
Highway Alignment Highway Alignment
Highway Alignment
 
Highway planning
Highway planningHighway planning
Highway planning
 
Distresses in the pavement
Distresses in the pavementDistresses in the pavement
Distresses in the pavement
 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdf
 
Global positioning system_Surveying, Civil Engineering
Global positioning system_Surveying, Civil EngineeringGlobal positioning system_Surveying, Civil Engineering
Global positioning system_Surveying, Civil Engineering
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Drone survey
Drone surveyDrone survey
Drone survey
 
Highway route location
Highway route locationHighway route location
Highway route location
 
GPS surveying/DIGITAL SURVEYING
GPS  surveying/DIGITAL SURVEYINGGPS  surveying/DIGITAL SURVEYING
GPS surveying/DIGITAL SURVEYING
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
chapter19. Terrestrial and Close-Range Photogrammetry.pdf
chapter19. Terrestrial and Close-Range Photogrammetry.pdfchapter19. Terrestrial and Close-Range Photogrammetry.pdf
chapter19. Terrestrial and Close-Range Photogrammetry.pdf
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
 
Total station Surveying
Total station SurveyingTotal station Surveying
Total station Surveying
 
Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & Pavements
 
River training works lecture
River training works lectureRiver training works lecture
River training works lecture
 
Traffic control devices
Traffic control devicesTraffic control devices
Traffic control devices
 
Drawing And Report
Drawing And Report Drawing And Report
Drawing And Report
 

Similar to Report HRGA Meeting Report Sep 2022 W3.pptx

Report HRGA Meeting Report Ops Mei 2022 W2.pptx
Report HRGA Meeting Report Ops Mei 2022 W2.pptxReport HRGA Meeting Report Ops Mei 2022 W2.pptx
Report HRGA Meeting Report Ops Mei 2022 W2.pptx
NazarFahrizal1
 
Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)
Das A. K.
 
Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)
Das A. K.
 
Rajasthan DSM Penalty August 2018
Rajasthan DSM Penalty August 2018Rajasthan DSM Penalty August 2018
Rajasthan DSM Penalty August 2018
Das A. K.
 
Ppt 8 12 2006
Ppt 8 12 2006Ppt 8 12 2006
Ppt 8 12 2006
widibaskoro
 
Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)  Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)
Das A. K.
 

Similar to Report HRGA Meeting Report Sep 2022 W3.pptx (6)

Report HRGA Meeting Report Ops Mei 2022 W2.pptx
Report HRGA Meeting Report Ops Mei 2022 W2.pptxReport HRGA Meeting Report Ops Mei 2022 W2.pptx
Report HRGA Meeting Report Ops Mei 2022 W2.pptx
 
Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for June 2018 (uploaded on 1st May 2019)
 
Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for September 2018 (uploaded on 1st May 2019)
 
Rajasthan DSM Penalty August 2018
Rajasthan DSM Penalty August 2018Rajasthan DSM Penalty August 2018
Rajasthan DSM Penalty August 2018
 
Ppt 8 12 2006
Ppt 8 12 2006Ppt 8 12 2006
Ppt 8 12 2006
 
Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)  Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)
Revised Rajasthan DSM Penalty for July 2018 (uploaded on 1st May 2019)
 

Recently uploaded

Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Satta Matka Dpboss Kalyan Matka Results
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
Freelance
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
obriengroupinc04
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
Rbc Rbcua
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
valvereliz227
 
DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...
DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...
DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...
essorprof62
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
Cambridge Product Management Network
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
irhcs
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
pavelborek
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
advik4387
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
CIOWomenMagazine
 
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium PresentationKirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip
 
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
ISONIKELtd
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
Eternity Paralegal Services
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 

Recently uploaded (20)

Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
 
DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...
DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...
DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KALYAN FIX JO...
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
 
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium PresentationKirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
 
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 

Report HRGA Meeting Report Sep 2022 W3.pptx

  • 1. Weekly Meeting HR Operations Report & Review Week 3 September 2022 One Team One Goal
  • 2. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Man Power Site Departement Lok Buntar Ida Manggala Sungai Puting Grand Total AGM-CPP & Hauling 32 55 1 88 AGM-Dredging & Canal 48 3 51 AGM-Engineering 5 32 1 38 AGM-External Affairs 42 5 47 AGM-Finance 5 1 6 AGM-HRGA 13 8 1 22 AGM-Infrastructure 14 10 1 25 AGM-Learning Institute 1 1 AGM-Lok Buntar Operation 57 2 59 AGM-Marketing & Quality Control 2 3 3 8 AGM-Operations 1 3 4 AGM-Plant & Maintenance 25 36 17 78 AGM-Project Explorasi 4 4 AGM-SHE 7 22 1 30 AGM-Supply Chain 28 12 11 51 AGM-Sungai Puting Operation 64 64 AGM-Terminal & Transhipment 3 3 TOTAL 282 194 103 579
  • 3. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Turn Over Employee A. Join Employee Employee No. Employee Name Work Location Employee Position Join Date 0222210048 Nurul Aida Fitriani Ida Manggala AGM-Land Acquisition Staff 22-Aug-22 0222210051 Cahyo Utomo Putro Ida Manggala AGM-Jr Pit Geology 29-Aug-22 0222210049 Rachma Riskina Renanda Ida Manggala AGM-Land Acquisition Staff 31-Aug-22 0222210050 Gilang Adhi Prabowo Ida Manggala AGM-Safety Mining Staff 1-Sep-22 0222210052 Asmauddin Putra Lok Buntar AGM-Purchasing Supervisor 5-Sep-22 0222210053 Afdila Wahyuningsih Lok Buntar AGM-Community Services Administration 12-Sep-22
  • 4. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Turn Over Employee B. Exit Employee Employee No. Employee Name Work Location Employee Position End Date Ket 0208160010 Tommy Mario Erwindo Ida Manggala AGM - GA Coordinator 27-Aug-22 Resign 0172220517 Muhammad Jaini Lok Buntar AGM-Captain Tug Boat 27-Aug-22 PHK 0172220523 Masyani Lok Buntar AGM-Captain Tug Boat 27-Aug-22 PHK 0172220527 Ahmad Muliani Lok Buntar AGM-Captain Tug Boat 27-Aug-22 PHK 0172220515 Samsuni Riady Lok Buntar AGM-Captain Tug Boat 29-Aug-22 Resign 0162210423 Rano Sabto Wibowo Ida Manggala AGM - RFID Supervisor 7-Sep-22 Resign 0172220521 M. Rahmadiansyah Lok Buntar AGM-Captain Tug Boat 10-Sep-22 PHK 0172220518 Taslim Lok Buntar AGM-Captain Tug Boat 10-Sep-22 PHK 0172220526 Muhammad Ramadani Lok Buntar AGM-Assistant Captain Tugboat 17-Sep-22 PHK 0172220525 Mahdinor Lok Buntar AGM-Assistant Captain Tugboat 17-Sep-22 PHK 0172220533 Riki Rahman Lok Buntar AGM-Assistant Captain Tugboat 17-Sep-22 PHK 0172220522 Maslianor Lok Buntar AGM-Assistant Captain Tugboat 17-Sep-22 PHK 0172220516 Rudi Lok Buntar AGM - Captain Tug Boat 17-Sep-22 PHK 0082810238 Emelka Lok Buntar AGM-Finance Staff 26-Sep-22 Resign
  • 5. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Tenaga Harian Lepas Department Ida manggala Lok Buntar Sungai Puting Grand Total AGM-CPP & Hauling 15 15 AGM-Dredging & Canal 1 1 AGM-External Affairs 3 14 17 AGM-HRGA 10 5 16 31 AGM-Infrastructure 7 1 8 AGM-Lok Buntar Operation 3 3 AGM-Marketing 1 2 3 6 AGM-Plant & Maintenance 4 3 6 13 AGM-SHE 10 3 1 14 AGM-Sungai Puting Operation 10 10 AGM-Supply Chain 4 4 Grand Total 50 36 36 122
  • 6. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Attendance Ratio Periode 1 – 19 September 2022
  • 7. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Attendance Ratio Periode 1 – 19 September 2022
  • 8. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Medical Claim PERIODE Jumlah Klaim Jumlah Rupiah APPROVAL SITE SENT HO APPROVAL HO SENT TO FINANCE 1 – 15 Maret 2022 54 25.517.234 17 Maret 2022 17 Maret 2022 21 Maret 2022 21 Maret 2022 16 – 31 Maret 2022 59 23.478.930 05-Apr-22 05-Apr-22 08-Apr-22 09-Apr-22 1 – 15 April 2022 37 24.172.068 18-Apr-22 18-Apr-22 22-Apr-22 22-Apr-22 16 – 30 April 2022 29 11.294.665 10 Mei 2022 10 Mei 2022 23 Mei 2022 23 Mei 2022 1 – 15 Mei 2022 39 16.230.009 18 Mei 2022 18 Mei 2022 27 Mei 2022 27 Mei 2022 16 – 31 Mei 2022 51 40.022.872 08 Juni 2022 13 Juni 2022 15 Juni 2022 15 Juni 2022 1 – 15 Juni 2022 40 20.801.852 17 Juni 2022 17 Juni 2022 28 Juni 2022 28 Juni 2022 16 – 30 Juni 2022 42 37.758.554 01 Juni 2022 01 Juni 2022 21 Juli 2022 21 Juli 2022 01 – 15 Juli 2022 46 27.452.625 20 Juli 2022 20 Juli 2022 05 Agt 2022 06 Agt 2022 16 – 31 Juli 2022 68 36.313.396 03 Agt 2022 03 Agt 2022 08 Agt 2022 08 Agt 2022 01 – 15 Agustus 2022 42 18.167.007 16 Agt 2022 16 Agt 2022 22 Agt 2022 22 Agt 2022 16 – 31 Agustus 2022 41 26.283.750 04 Sep 2022 04 Sep 2022 09 Sep 2022 09 Sep 2022 01 – 15 September 2022 82 34.795.927 16 Sep 2022 18 Sep 2022 Note : Medical LBCT Masih di HO menunggu persetujuan Pak Ace
  • 9. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Rekap Tenaga Harian PERIODE Jumlah THL Jumlah Rupiah Terima Rekap Absen Department APPROVAL SITE SENT HO APPROVAL HO SENT TO FINANCE SENT TO BRI BRI SENT TO EMPLOYEE 21 Feb – 20 Mar 2022 116 Rp 269.936.488 22 Maret 22 24 Maret 22 25 Maret 22 31 Maret 22 31 Maret 22 31 Maret 22 01-Apr-22 21 Maret – 20 April 2022 116 Rp 321.689.000 21-Apr-22 22-Apr-22 22-Apr-22 26-Apr-22 26-Apr-22 27-Apr-22 27-Apr-22 21 April – 20 Mei 2022 120 Rp 294.967.300 23 Mei 22 25 Mei 2022 25 Mei 2022 31 Mei 2022 31 Mei 2022 (Sore) 02-Jun-22 02-Jun-22 21 Mei – 20 Juni 2022 121 Rp 351.321.400 21 Juni 2022 23 Juni 2022 23 Juni 2022 28 Juni 2022 29 Juni 2022 29 Juni 2022 29 Juni 2022 21 Jun – 20 Jul 2022 122 Rp 328.435.891 21 Juli 2022 23 Juli 2022 23 Juli 2022 27 Juli 2022 27 Juli 2022 28 Juli 2022 28 Juli 2022 21 Jul – 20 Ags 2022 122 Rp. 341.052.300 21 Ags 2022 22 Ags 2022 22 Ags 2022 30 Ags 2022 31 Ags 2022 31 Ags 2022 31 Ags 2022
  • 10. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Improvement SS
  • 11. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Improvement QCC & QCP
  • 12. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS No Department Penambahan Baru Replacement Position Open Position Close 1. Engineering 3 1 1 3 2. SHE 6 0 2 4 3. HRGA 1 1 2 0 4. Infrastructure 2 1 2 1 5. Supply Chain 2 2 2 2 6. External Affairs 9 0 3 6 7. CPP Hauling 5 1 5 1 8. Plant & Maintenance 2 2 3 1 9. SPCT 4 0 1 3 10. IR & RM 2 0 1 1 11. Quality Control 0 1 1 0 12. LBCT 3 1 4 0 Total 39 10 27 22 Open Position July & Agustus
  • 13. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS HO recruitment No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourchin g (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 CSR Supervisor External Affair - CSR / Comdev HO 1 Supervisor 14-Mar-22 133 Wa Ode 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ Ana Nurlatifah 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ Nur Azisya 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ Faradila Nasri 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 05-Jul-22 12-Jul-22 12-Jul-22 X Withdraw Dian N 19-Apr-2022 26-Jun-22 26-Jun-22 04-Jul-22 X X X X NQ 2 Govrel Supervisor External Affair - Govrel HO 1 Supervisor 19-Apr-22 97 Indra 19-Apr-2022 X X X X X X X NQ 3 HRGA Spv HRGA HO 1 Supervisor 27-Mei-22 59 Dony 19-Apr-2022 09-Jul-22 X X X X X X NQ Herman M 19-Apr-2022 09-Jul-22 X X X X X X NQ 4 Civil Mining Supervisor Infrastruktur - Transhipment HO 1 Supervisor 25-Mei-22 61 19-Apr-2022 5 Sr. Civil engineering Infrastruktur - Transhipment HO 1 Supervisor 25-Mei-22 61 Mufqi 19-Apr-2022 9 Aug 22 Interview HR 6 Internal Audit Supervisor Internal Audit & Risk Management HO 1 Supervisor 11-Mar-22 136 Michael 19-Apr-2022 22-Jun-22 26-Jun-22 26-Jun-22 Interview Final Yonathan Laurendy Yazid 19-Apr-2022 Eka Prasetya 19-Apr-2022 Alfian Fani 19-Apr-2022 Yonathan Laurendy 19-Apr-2022 Interview Final Yonathan Laurendy Febrian Luthfigar 19-Apr-2022 5 Juli 22 6-Jul-22 Nicholas 19-Apr-2022 20 Juli 22 21-Jul-22 Discuss salary expect Process
  • 14. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS HO recruitment No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourchin g (Tgl Iklan) Intervie w Psikotest Intervie w Final MCU Salary Proposal Offering Letter On Boarding Notes 7 Mine Plan Engineer Mining Operation - Engineering HO 1 Supervi sor 20-Apr-22 96 Dori Apriman Dhuha 19-Apr-2022 28-Jun- 22 X X X X NQ M.Riza Fahlevi 19-Apr-2022 Mahmudin 19-Apr-2022 Adi Sulistya 19-Apr-2022 Galang Budiansyah 19-Apr-2022 Cipta Fakar N 19-Apr-2022 9-Jul-22 15-Jul-22 26-Jul-22 Withdraw Krisna Hanjar 19-Apr-2022 28-Jul-22 29-Jul-22 28 Juli 22 29 Jul 22 4 Aug 22 Psikotest, salary proposal Bayu Widiyartanto 19-Apr-2022 28-Jul-22 29-Jul-22 28 Juli 22 Not recommended Yuli Yahya 19-Apr-2022 28-Jul-22 29-Jul-22 28 Juli 22 Not recommended 8 Supervisor Maintenance (IM) Plant & Maintenance HO 1 Supervi sor Approve site 17 Jun 22 19-Apr-2022 9 Safety Transhipment Supervisor SHE - Transhipment HO 2 Supervi sor 11-Nov-21 256 Sink 19-Apr-2022 09-Jul-22 X X X X X X NQ Agus 19-Apr-2022 09-Jul-22 X X X X X X NQ Donovan 19-Apr-2022 09-Jul-22 X X X X X X NQ Surya 18-Jun-2022 20-Jul-22 20-Jul-22 Interview final Gulfrid Baan 18-Jun-2022 20-Jul-22 20-Jul-22 Interview final 10 Purchasing Supervisor Supply Chain - Purchasing HO 1 Supervi sor 21-Apr-22 95 M.Rian Munandar 19-Apr-2022 X X X X X X X Interview User Ashadika 19-Apr-2022 X X X X X X X Ali Sabaha Kurniawan 19-Apr-2022 X X X X X X X Sriyono 19-Apr-2022 22 Juli 22 X X X X X X Afdian Eko Wibowo 19-Apr-2022 22 Juli 22 X X X X X X WD Dannis Akbar Kurniawan 19-Apr-2022 22 Juli 22 X X X X X X Asmauddin Putra 19-Apr-2022 30 Juli 22 1 Agu 22 30 Juli 22 6 Aug 22 2 Aug 22 8 Aug 22 Salary proposal 11 Warehouse & Logistic Suptend Supply Chain HO 1 Supten d PKB process Rahmadi Rizki 20-Jul-2022 21 Juli 2225 Juli 22 3 Agu 22 Interview SCM & CFO Process
  • 15. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS HO recruitment No Position Department PIC MPP Level Date of PKB SLA as per toda y Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Surveyor Supervisor External Affair - LA HO 1 Supervi sor 25-Nov-21 162 Rezki Marahalim 19-Apr-22 19-Apr-22 21-Apr-22 03-Apr-22 06-Apr-22 06-Mei-22 Close 2 Land Acquisition Supervisor External Affair - LA HO 1 Supervi sor 25-Nov-21 164 Heri Supriyanto 19-Apr-22 19-Apr-22 05-Apr-22 08-Apr-22 08-Mei-22 Close 3 FGDP Engineering Mining Operation HO 1 Officer 11-Okt-21 213Dzaky Ilham 19-Apr-22 19-Apr-22 09-Apr-22 12-Apr-22 12-Mei-22 Close 4 Warehouse & Logistic Superintendent Supply Chain - Warehouse HO 1 Superi ntende nt 09-Feb-22 105 Djoli Hendra S 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Apr-22 22-Apr-22 25-Apr-22 25-Mei-22 Close 5 Purchasing Superintendent Supply Chain - Purchasing HO 1 Superi ntende nt 17-Feb-22 104 M Ismail 19-Apr-22 19-Apr-22 29-Apr-22 02-Mei-22 01-Jun-22 Close 6 IT Officer Supply Chain - HO HO 1 Officer 25-Mar-22 82 Aldi 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close Close
  • 16. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Engineering Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Surveyor Mining Operation - Engineering Site 1 Group Leader PKB Process Taufik 18-Jun-2022 25-Jul-22 27-Jul-22 X X X X X NQ Ardy Widi 18-Jun-2022 25-Jul-22 27-Jul-22 27-Jul-22 X X X X NQ Jhontrado 18-Jun-2022 26-Jul-22 27-Jul-22 X X X X X NQ Sulaiman Sinaga 18-Jun-2022 26-Jul-22 27-Jul-22 6-Agu-22 10-Agu-22 MCU No Position Department PIC MPP Level Date of PKB SLA as per toda y Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Data Processing Officer Mining Operation - Engineering Site 1 Officer 19-Apr-22 55 Hangger 01-Feb-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 11-Mei-22 14-Mei-22 13-Jun-22 Close 2 Jr. Geotech Engineer Mining Operation - Engineering site 1 Officer 21-Feb-22 114 Zainul Ngatiq 00-Jan-00 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close 3 Jr. Pit Geology Mining Operation - Engineering site 1 Officer 21-Sep-21 302 M Faiq 19-Apr-22 25-Apr-22 25-Apr-22 27-Mei-22 07-Jun-22 23-Jun-22 05-Jul-22 20-Jul-22 Close 4 Jr. Pit Geology Mining Operation - Engineering site 1 Officer 21-Sep-21 307 Cahyo 19-Apr-2022 25-Apr-22 25-Apr-22 27-Mei-22 07-Jun-22 23-Jun-22 21-Jul-22 29-Agu-22 CLose
  • 17. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Road Maintenance Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourch ing (Tgl Iklan) Intervi ew Psikote st Intervi ew Final MCU Salary Propos al Offerin g Letter On Boardi ng Notes 1 Motor Grader Operator Road Maintenance Site 1 Non Staff 06-Des-21 231 Jarun 19-Apr-2022 28-Jun-22 06-Jul-22 06-Jul-22 07-Jul-22 X X X WD Bustanul 19-Apr-2022 11-Jul-22 11-Jul-22 11-Jul-22 X X X X NQ User Trisetiyo 19-Apr-2022 28-Jun-22 06-Jul-22 06-Jul-22 07-Jul-22 23-Jul-22 X X NQ MCU No Position Department PIC MPP Level Date of PKB SLA as per toda y Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Motor Grader Operator Road Maintenance Site 1 Non Staff 06-Des-21 231 Mukhtar Faulana Hire Internal
  • 18. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS SHE Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Safety Group Leader SHE - Mining site 1 Group Leader 10-Jun-22 45 Zamakh 19-Apr-2022 28-Jun-22 05-Jul-22 19-Jul-22 X X X X NQ Tommy Mario 18-Jun-2022 28-Jun-22 05-Jul-22 X X X X X NQ Tommy 18-Jun-2022 28-Jun-22 05-Jul-22 X X X X X NQ TriJoko M 18-Jun-2022 28-Jun-22 X X X X X X NQ Tomy Destyan 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 X X X X NQ Tomy Aprianto 18-Jun-2022 28-Jun-22 X X X X X X NQ Asyrofi 18-Jun-2022 28-Jun-22 X X X X X X NQ Rio Martha 18-Jun-2022 28-Jun-22 X X X X X X NQ Indra Adam 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 29-Jul-22 23-Jul-22 X X Withdraw 2 Safety Group Leader SHE - Transhipment site 1 Group Leader 13-Jun-22 42 Agung Dwi Rahmanto 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 X X X X NQ Rezali Haidir 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 X X X X NQ Rio Harianto 18-Jun-2022 17-Jun-22 18-Jun-22 21-Jul-22 X X X X NQ Tesya Ananda Siregar 18-Jun-2022 17-Jun-22 18-Jun-22 X X X X X NQ Valentino Sugiarto 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 X X X X WD Suharyono 18-Jun-2022 12-Jul-22 12-Jul-22 21-Jul-22 X X X X NQ No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Note s 1 Satefy Patrol Group Leader SHE - Mining site 1 Officer 23-Agu-21 296 R Prabowo 00-Jan-00 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close 2 Safety Group Leader SHE - Mining site 1 Group Leader 10-Jun-22 45 Gilang Adhi P 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 22-Jul-22 23-Jul-22 7 Agu 22 1 Sep 22 Close 3 Reclamation & Revegetation Officer SHE - Quality and System site 1 Group Leader 11-Mar-22 57 Irwan Pasdar 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Apr-22 26-Apr-22 30-Apr-22 07-Mei-22 Close 4 Monitoring Control Officer SHE - Quality and System site 1 Officer 09-Feb-22 95 Darintia 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Apr-22 17-Apr-22 25-Apr-22 15-Mei-22 Close 5 Integrated Farming & DAS SHE - Quality and System Site 1 Group Leader 25-Apr-22 98 Rennyta 30-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 03-Jun-22 17-Jun-22 05-Jul-22 01-Agu-22 Close 6 Planning Development Officer SHE - Quality and System Site 1 Officer 12-Mar-22 142 Raudlatul 19-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 21-Mei-22 17-Jun-22 05-Jul-22 01-Agu-22 Close 7 Document Control Officer SHE - Quality and System Site 1 Officer 25-Apr-22 91 Emiliyana Varida S 30-Apr-2022 18-Mei-22 18-Mei-22 19-Mei-22 30-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 Close 8 Safety Group Leader SHE - Transhipment site 2 Group Leader 13-Jun-22 42 Catur Ravia Chandra 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 25-Jun-22 25-Jun-22 12-Jul-22 01-Agu-22 close
  • 19. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS HRGA No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 HR Admin HRGA Site 1 Admin 25-Mei-22 61 Mega 18-Jun-2022 30-Jun-22 02-Jul-22 30-Jun-22 21-Jul-22 MCU, Waiing Decission super user Nabila 18-Jun-2022 30-Jun-22 02-Jul-22 30-Jun-22 X X X X Hold Ananda 18-Jun-2022 6-Jul-22 X X X X X X NQ Process Close
  • 20. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Infrastructure Process Close No Position Department PIC MPP Level Date of PKB SLA as per toda y Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Doco Infrastruktur - Transhipment Site 1 Group Leade r 27-Feb-22 138 Zikri Adham 27-Feb-22 08-Apr-22 18-Mei-22 19-Mei-22 28-Mei-22 12-Jun-22 15-Jun-22 15-Jul-22 Close, internal hire 1 Field Engineer Infrastruktur - Transhipment Site 1 Office r 25-Mei-22 48 M Abdullah Rofie 30-Mei-22 01-Jun-22 02-Jun-22 20-Apr-22 15-Jun-22 23-Jun-22 05-Jul-22 12-Jul-22 CLose 2 Civil Mining Group Leader Infrastruktur - Transhipment Site 1 Group Leade r 25-Mei-22 61 Rasyid 18-Jun-2022 07-Apr-22 07-Apr-22 20-Apr-22 24-Jun-22 02-Jul-22 12-Jul-22 25-Agu-22 Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourch ing (Tgl Iklan) Intervi ew Psikote st Intervi ew Final MCU Salary Propos al Offerin g Letter On Boardi ng Notes 1 Drafter & Document Control Infrastruktur Site 1 Group Leader PKB On Process Sourching 2 Civil Transhipment Group Leader Infrastruktur Site 1 Group Leader PKB On Process Sourching
  • 21. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Supply Chain Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourch ing (Tgl Iklan) Intervi ew Psikote st Intervi ew Final MCU Salary Propos al Offerin g Letter On Boardi ng Notes 1 IT Programmer Supply Chain - IT Site 1 Officer 19-Apr-22 97 Satrio 19-Apr-2022 18-Mei-22 18-Mei-22 19-Mei-22 25-Mei-22 23-Jun-22 X X Satrio WD, Sourching New Kandidat DanuWinisuda 19-Apr-2022 21-Jul-22 X X X X X X NQ Syaukani 19-Apr-2022 28 Jul 22 X X X X X X NQ IGede 19-Apr-2022 28 Jul 22 29 Jul 22 X X X X X NQ No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 IT Officer Supply Chain - HO HO 1 Officer 25-Mar-22 82 Aldi 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 13-Mei-22 16-Mei-22 15-Jun-22 Close 2 Purchasing Superintendent Supply Chain - Purchasing HO 1 Superintendent 17-Feb-22 104 M Ismail 19-Apr-22 19-Apr-22 29-Apr-22 02-Mei-22 01-Jun-22 Close 3 Fuelman Supply Chain Site 1 Non Staff 11-Jul-22 14 Nur Sigit 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 14-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close 4 IT Officer Supply Chain - IT Site 1 Officer 19-Apr-22 87 Miko 19-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 28-Mei-22 12-Jun-22 15-Jun-22 15-Jul-22 Close 5 Fuelman Supply Chain - Warehouse Site 1 Non Staff 11-Jul-22 M.Haykal 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 16-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close
  • 22. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS External Affair No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Comser Administrator External Affair - Comser Site 1 Officer 11-Jun-22 44 Oktaviani 18-Jun-2022 24-Jun-22 24-Jun-22 24-Jun-22 X X X X NQ Khaliq Adady 18-Jun-2022 24-Jun-22 24-Jun-22 24-Jun-22 26-Jul-22 X X X Unfit Afdila 18-Jun-2022 30-Jun-22 02-Jul-22 30-Jun-22 29-Jul-22 09-Agu-22 Salary Proposal 2 LA - Negosiator External Affair - LA Site 2 Officer 21-Jun-22 34 Haris 18-Jun-2022 29-Jun-22 30-Jun-22 29-Jun-22 05-Jul-22 23-Jul-22 7 Agu 22 Offering Letter Oby Dinata 18-Jun-2022 29-Jun-22 30-Jun-22 29-Jun-22 X X X X Withdraw Hady Susanto 18-Jun-2022 29-Jun-22 14-Jul-22 29-Jun-22 26-Jul-22 23-Jul-22 X X UNFIT Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 LA - Senior Admin External Affair - LA Site 1 Officer 10-Jun-22 32 Devi 30-Mei-22 30-Mei-22 30-Mei-22 12-Jun-22 21-Jun-22 23-Jun-22 05-Jul-22 12-Jul-22 Close 2 LLA Officer External Affair - LA Site 1 Officer 21-Jun-22 36 Takdir 30-Mei-22 30-Mei-22 30-Mei-22 12-Jun-22 21-Jun-22 23-Jun-22 05-Jul-22 27-Jul-22 Close 3 LA - Surveyor External Affair - LA Site 2 Officer 21-Jun-22 34 Dimyati 18-Jun-2022 21-Jun-22 21-Jun-22 21-Jun-22 27-Jun-22 02-Jul-22 21-Jul-22 08-Agu-22 Close 4 LA - Senior Admin External Affair - LA Site 2 Officer 10-Jun-22 45 Nurul Aida 30-Mei-22 30-Mei-22 12-Jul-22 12-Jul-22 14-Jul-22 23-Jul-22 7 Agu 22 22-Agus-22 CLose
  • 23. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS CPP Hauling Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Weight Bridge Operator Mining Operation - CPP & Hauling Site 3 Non Staff 05-Jul-22 20 Nor Ifansyah 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 X X X NQ Josswa 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 X X X NQ Isra 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 X X X NQ M. Fernanda 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 09-Agu-22 Salary proposal A. Syaiifullah 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 09-Agu-22 Salary proposal M. Rijani 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 NQ 2 Driver Water Truck Mining Operation - CPP & Hauling Site 2 Non Staff Belum ada PKB M. Khatami 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 Review Agus Melas 19-Apr-2022 21-Jun-22 21-Jun-22 12-Jul-22 29-Jul-22 Review No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Hauling Group Leader (Blok IV) Mining Operation - CPP & Hauling Site 1 Group Leader 21-Apr-22 71 A Zainuddin 21-Apr-22 12-Mei-22 12-Mei-22 21-Mei-22 22-Mei- 22 29-Mei-22 01-Jun-22 01-Jul-22 Close
  • 24. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Plant & Maintenance Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Senior Mechanic A2B (IM) Plant & Maintenance Site 1 Non Staff 19-Apr-22 97 Teguh Santoso 18-Jun-2022 01-Jul-22 05-Jul-22 01-Jul-22 X X X X WD Muhammad Rizka Arief 18-Jun-2022 19-Jul-22 19-Jul-22 19-Jul-22 20-Jul-22 X X X NQ 2 Mekanik A2B (SP) Plant & Maintenance Site 1 Non Staff Approve site 28 jul 22 Wildan 18-Jun-2022 Fahrur Reza 18-Jun-2022 Wahyono 18-Jun-2022 3 PKB Fix Plan (LB Plant & Maintenance Site 1 Non Staff Approve site 3 agu 22 Rian Hariyadi 18-Jun-2022 No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Senior Mechanic A2B (IM) Plant & Maintenance Site 1 Non Staff 19-Apr-22 97 Lutfi Prayogo 18-Jun-2022 01-Jul-22 05-Jul-22 01-Jul-22 25-Jul-22 23-Jul-22 7 Agu 22 8 Agu 22 CLose
  • 25. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS SPCT Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourchin g (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 TCT Operation GL Sungai Putting Operation Site 1 Officer 19-Apr-22 97 Mawardi 18-Jun-2022 17-Jun-22 22-Jun-22 22-Jun-22 29-Jul-22 X X X NQ No Position Department PIC MPP Level Date of PKB SLA as per toda y Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Port Officer Sungai Putting Operation Site 1 Officer 22-Apr-22 52 Eginius 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 11-Mei-22 14-Mei-22 13-Jun-22 Close 2 TCT Operation GL Sungai Putting Operation Site 1 Officer 19-Apr-22 58 Hany Sadewa 19-Apr-22 19-Apr-22 21-Apr-22 22-Apr-22 24-Mei-22 14-Mei-22 17-Mei-22 16-Jun-22 Close 3 TCT Operation GL Sungai Putting Operation Site 1 Officer 19-Apr-22 97 Muhammad Arif 18-Jun-2022 17-Jun-22 22-Jun-22 22-Jun-22 25-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 close
  • 26. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS LBCT Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 Excavator Operator Transhipment - LB Operation Site 1 Non Staff Belum ada PKB Shahrul Sourching
  • 27. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS QC Process Close No Position Department PIC MPP Level Date of PKB SLA as per today Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 QC Crew Quality Control Site 1 Non Staff PKB On Process Irbani Sourching
  • 28. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Posisi Close Agustus No Position Department PIC MPP Level Date of PKB SLA as per toda y Nama Kandidat Sourching (Tgl Iklan) Interview Psikotest Interview Final MCU Salary Proposal Offering Letter On Boarding Notes 1 LA - Surveyor External Affair - LA Site 1 Officer 21-Jun-22 34 Dimyati 18-Jun-2022 21-Jun-22 21-Jun-22 21-Jun-22 27-Jun-22 02-Jul-22 21-Jul-22 08-Agu-22 Close 2 LA - Senior Admin External Affair - LA Site 1 Officer 10-Jun-22 45 Nurul Aida 30-Mei-22 30-Mei-22 12-Jul-22 12-Jul-22 14-Jul-22 23-Jul-22 7 Agu 22 22-Agus-22 CLose 3 LLA Officer External Affair - LA Site 1 Officer 21-Jun-22 Fathur Rohman 18-Jun-2022 21-Jun-22 21-Jun-22 21-Jun-22 15-Jul-22 23-Jul-22 7 Agu 22 15-agu-22 Close 4 LLA Officer External Affair - LA Site 1 Officer 21-Jun-22 Rahma Ryzkina Renantha 30-Mei-22 19-Jul-22 19-Jul-22 19-Jul-22 21-Jul-22 23-Jul-22 7 Agu 22 22-Agus-22 Close 5 Civil Mining Group Leader Infrastruktur - Transhipment Site 1 Group Leader 25-Mei-22 61 Rasyid 18-Jun-2022 07-Apr-22 07-Apr-22 20-Apr-22 24-Jun-22 02-Jul-22 12-Jul-22 25-Agu-22 Close 6 Jr. Pit Geology Mining Operation - Engineering site 1 Officer 21-Sep-21 307 Cahyo 19-Apr-2022 25-Apr-22 25-Apr-22 27-Mei-22 07-Jun-22 23-Jun-22 21-Jul-22 29-Agu-22 CLose 7 Senior Mechanic A2B (IM) Plant & Maintenance Site 1 Non Staff 19-Apr-22 97 Lutfi Prayogo 18-Jun-2022 01-Jul-22 05-Jul-22 01-Jul-22 25-Jul-22 23-Jul-22 7 Agu 22 8 Agu 22 CLose 8 Safety Group Leader SHE - Mining site 1 Group Leader 10-Jun-22 45 Gilang Adhi P 18-Jun-2022 28-Jun-22 05-Jul-22 19-Jul-22 22-Jul-22 23-Jul-22 7 Agu 22 1 Sep 22 Close 9 Integrated Farming & DAS SHE - Quality and System Site 1 Group Leader 25-Apr-22 98 Rennyta 30-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 03-Jun-22 17-Jun-22 05-Jul-22 01-Agu-22 Close 10 Planning Development Officer SHE - Quality and System Site 1 Officer 12-Mar-22 142 Raudlatul 19-Apr-22 18-Mei-22 18-Mei-22 19-Mei-22 21-Mei-22 17-Jun-22 05-Jul-22 01-Agu-22 Close 11 Document Control Officer SHE - Quality and System Site 1 Officer 25-Apr-22 91 Emiliyana Varida S 30-Apr-2022 18-Mei-22 18-Mei-22 19-Mei-22 30-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 Close 12 Safety Group Leader SHE - Transhipment site 1 Group Leader 13-Jun-22 42 Catur Ravia Chandra 18-Jun-2022 17-Jun-22 18-Jun-22 24-Jun-22 25-Jun-22 25-Jun-22 12-Jul-22 01-Agu-22 close 13 SHE Group Leader SHE - Transhipment Site 1 Officer 13-Jun-22 Muhammad Mujahid 18-Jun-2022 12-Jul-22 12-Jul-22 21-Jul-22 22-Jul-22 23-Jul-22 6 agu 22 8 Agu 22 Close 14 TCT Operation GL Sungai Putting Operation Site 1 Officer 19-Apr-22 97 Muhammad Arif 18-Jun-2022 17-Jun-22 22-Jun-22 22-Jun-22 25-Jun-22 02-Jul-22 12-Jul-22 01-Agu-22 close 15 Fuelman Supply Chain Site 1 Non Staff 11-Jul-22 14 Nur Sigit 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 14-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close 16 Fuelman Supply Chain - Warehouse Site 1 Non Staff 11-Jul-22 M.Haykal 19-Apr-2022 05-Jul-22 12-Jul-22 12-Jul-22 16-Jul-22 19-Jul-22 22-Jul-22 01-Agu-22 Close
  • 29. PT. BARAMULTI SUKSES SARANA TBK PT. ANTANG GUNUNG MERATUS Promosi Jabatan No Nama Company Posisi Lama Posisi Baru Mulai Act. Selesai Act Status (selesai/lanjut acting) Jadwal Presentasi 1 Sulaiman A AGM Transhipment Safety Patrol (LB) SHE Group Leader 1 Maret 2021 31 Mei 2021 Lanjut Acting 6 bulan setelah presentase 2 Raihani AGM Lanjut Acting 3 Muhammad Majeni AGM Kepala Juru Masak GA Group Leader 1 Februari 2021 31 April 2021 Presentasi Agustus W3 4 Saeful Ruslan Hidayat AGM Weightbridge Operator Weightbridge Group Leader Presentasi Agustus W3 5 Sugeng Ariyanto AGM Tolgate Operator Tolgate Group Leader 6 Slamet Bolawi AGM AGM-Excavator Operator (LB) AGM-Excavator Operator (LB) 01 Juli 2021 31 Des 2021 7 Kustani Safran AGM AGM-SHE Jr Supervisor AGM-SHE Supervisor Lulus 8 Taufik AGM AGM-Safety Patrol (SP) AGM-Hauling Group Leader 1 Juli 2022 31 Des 2022 9 Abdul Mukhid AGM AGM-Fix Plan Mekanik (LB) AGM-Fix Plan Group Leader
  • 30. Created by Irwin Febrian/122 TERIMA KASIH