RAC-050
Engineer Training
Feb. 2021
Engineer
Task
Installation
Instrument
Installing
Instrument
Operation
Daily
Maintenance
Repair
Spare parts
Stock
Guided
Instruction
Personnel
Training
Visiting
Maintenance
Preventive
Maintenance
Engineer Task Lists:
Engineer Capability Requirement
Operation
Installation
Principal
Maintenance
Problem
Handling
Engineer
Capability
Engineer Training
Part 1 Instrument Principle
Part 2 Specification of RAC-050
Part 3 Instrument Installing
Part 4 Maintenance
Part 5 Common Troubleshooting
RAC-050 Apperance
After Open the Light-Shield Cover
Normally, when the instrument is working, the cover should be closed in
advance, or else, the test can not go further. For Engineer, you can place the
Magnetic on the cover sensor to disable it. Or you can disconnect the sensor
cable and connect the Pin 1 and Pin3.
Instrument Requirement
 1. Instrument has Inbuilt Main board inside. It doesn’t
need to have PC working with.
 2. Online UPS is Necessary.
 3.RAC-Cleanser and cuvettes should be original from
Rayto, or else, it will have the problem that the Probe
cannot wash totally and bring Carry-over contamination,
and the cuvette is not mixed properly, or even the optical
system cannot work properly.
RAC-Cleanser
RAC-Cleanser (30ml)
Expired Date: 12 Month
Expired Date after open: 30 Day
Storage Temp: 2-35 Celcius
Consumption for Long Rinse and
Test preparation is 200ul
Consumption in testing is Reagent
volume+20ul
Part 1 Instrument Principle
 Principle of light-path
 Electronic circuit principle
 Liquid Path
Plasma
Vacuum Collecting Tube
Coagulation
Testing
Citrate inside,
0.109mol/L
ESR Testing
Citrate inside
Chemistry Testing
No Anti-Coagulant
Hematology Testing
EDTA –K2
Anti-Coagulant
Coagulation Mechanism:
APTT
PT
FIB
Anti-Coagulation Mechanism:
Clotting/Coagulation Method
Scatter Light intersity refects due to the Turbidity Strength. And it’s Linear with
the Testing Material Concentration.
Wavelength: 660nm
No Filter inside, Only
Red Interference Plastic
PT Actual Reaction Curve
X axis: Time(s)*10, 200 means 20s
Y axis: AD, Max Value is 65535
Coagulation Time (S)
PT ratio= PT/Normal
INR= (PT ratio)^(ISI)
DFbg need to calibration with sample
PT% need to do calibration with blood pool
Note: For the Software V2.4e, the DFbg Unit is same with FIB.
Immunologic Method
Light resource is LED and there is 575nm filter in the
Optical System. It will produce yellow light
go through cuvette.
The Turdimitry is more intense, the less light
will transit through the Cuvette.
LED
Photo-
Detector
D-Dimer Reaction Curve
X axis: Time(s)*10, 200 means 20s
Y axis: AD, Max Value is 65535
Reaction Rate
Chromogenic Method
Light resource is LED and there is 405nm filter in the
Optical System.
It’s Purple color in the Reaction cuvette. The
Turdimitry is more intense, the less light
will transit through the Cuvette.
LED
Photo-
Detector
Structure of Light-path
8 Incubation Channels
7 Test Channels
Place for New Cuvettes
Principle of Liquid path
Water Bottle: Postive Pressure, 280+/-30mmHg
Waste Bottle: Negative Pressure
Tube Connection at the Rear
Item Testing Workflow
• Temperature
Stabilized
Add Sample
• Incubate
Add R1
• Mix and Test
Or Incubate
Add R2
Note: If the Sample is need to predilution, the probe will add the
Diluent firstly and then add the Sample, After that, Dispense into
the cuvette and then add R1 and R2.
If sample dilution is not possible to complete in one time, it will
use one Cuvette to diluent the sample. After that, the probe will
add diluent and then add the diluted sample and dispense to the
new cuvette and further add R1 and R2
Test Cycle Time is
30 second
Structure of Hardware
Main Board with
CF card Main Control Board
Motor Driving Board
Temperature
Control Board
Touch
Screen
Driving
Board
Display Driver
Board
Printer Driving
Board
Touch
Screen
LCD Screen
Printer
Head
Input &output System of the instrument
4 Way Pre-Amplify
Board
3 Way Pre-Amplify
Board
Five Pcs
Boards for
Light
Resource
Optical System
Big Driving board
For Catcher
System
Sampling Driving
board
Liquid Detection
Board
Temp-Control System
Mechanic
System
Small Driving
board For
Catcher System
Main board
1. Battery is used to save the BIOS settings.
2. Memory Bank can use the Erase to clean the Pins.
3. CF card is installed on the same side of Memory Bank.
CF Card
 Contains System and Operation Software
Boards on Instrument Rear
Main Control Board
Motor Driving
Board
Temp Control
Board
New Catcher
New Catcher
Old Catcher
Note: To detect the Cuvette, it need to have the reflective sensor.
Liquid Detection Board
Sampling Arm
Probe: Internal Heating
Probe Vertical Anti-Collision
Probe Liquid level detection
Catcher Arm
 Vortex Mixing
 Cuvette
Detection
 3-D movement
Optical Path
Heating
Membrane
Reagent Area
 Reagent Cooling:
<16 celcius
 2 Peltiers
Power Connection
±15V
Temperature
control
board
Industrial
control
board
Motor
drive
board
±15V Switch power
100~240V AC
Filter
5V Switch power 12V Switch power
Power supply port board
24V Switch power
DC 12V DC 24V
DC 5V
Main
control
board
Display
port
board
Air
fan
Fuse
Part 2
Instrument Specification
 1. 3 Testing Method
 2. 3. Reagent Mixing around Position A1
 3. LIS Data Transfer
 4. 8 inch Screen with Touch Screen
 5. Reaction Volume: 150-300ul, Vortex Mixing
 6. Laser Printer can installed on the instrument, Built-in
Thermal printer
 7. Optional Function: Sample Barcode Reader, Reagent
Card Reader (RFID).
Part 3 Instrument Installation
 1. Installation Environment
 2. Installation Process
Installation Environment
 Well-ventilated; Free dust as possible around it;
 Prevent from direct exposure to sunlight;
 Prevent it placing around heat source or air one;
 Free from corrosive or flammable gas;
 UPS is necessary;
 Do not be close to brush generator or frequently-switching-on electric
equipment;
 Do not be close to electric equipment sending electromagnetic wave;
 Ambient temperature: 15-30℃, operation temperature fluctuation: less than
+/-2℃/H;
 Ambient humidity: 35%-80%RH, non-condensed;
 This needs to install air conditioner if indoor temperature fails to meet
requirement.
Power supply Requirement:
 Power supply: 220VAC, 50/60Hz, 1000VA, three-core
power supply wire, good grounding;
 Needs independently have grounding wire;
 Neutral-grounding voltage: less than 5V;
 AC power supply must be stable, prohibit sharing in
power supply with high-power electric appliance, stable
power supply should be set at most;
Unpack
 1. Wear glove
 2. Remove the lock from
the box bottom.
Remove the Buffer and Taps
Cut away the Plastic tie
In total it has 5 Plastic tie. After remove the tie, please check
whether the probe arm and catcher arm can move freely.
Connect the Bottles
Switch On and Software Login
1. For User, The password is 888888; For Engineer, the password is h-201
2. Click the Company Logo, and you can see the versions of the software and Main
control board.
Reset all the positions and Then Long Rinse
Note: Long Rinse is necessary for new installation. It make the liquid go
into the instrument.
Check Sensor Status
Please click Open and then you can check all the sensor status.
Part 4 Maintenance
 1. Daily Maintenance
 2. Monthly Maintenance
 3. Yearly Maintenance
Daily Maintenance
 1. Empty the Waste Bottles
 2. After daily test, need to turn off the
instrument and put the reagent back to the
fridge.
Weekly Maintenance
 1. Clean the probe surface with alcohol
 2. Clean Reagent area
 3. Clean the instrument outside surface
with soft cloth, includes the sample Rack
 4. Clean the water bottle
Half Year Maintenance
 1. Grease the Probe arm and Catch Arm
 2. Clean the water bottle filter
 3. Clean the dust on the Fans
Yearly Maintenance
 1. Check whether the fan have abnormal
sound. If yes, please replace it.
 2. Check the optical path. Normally it’s ok
to check every 2 years. LEDs are work
stable.
 3. Check the tube is dirty or not. If yes,
please replace.
Part 5 Adjustment
 1. Probe Position Adjustment
 2. Catcher Position Adjustment
 3. Temperature adjustment
 4. Optical adjustment
Engineering Adjust Interface
Note: The Maintenance Button is enabled when Login Engineer.
The Maintenance interface is mainly used to check the Positions, Check
Movement is correct or not, Parts status, etc.
Probe Adjustment
Debug Area
Position Check
Area
For Dispend and Sample/Reagent Pos., the probe needs to be in the center,
for Vertical position, the probe should touch bottom.
Catcher Position
Air Pos.
 Please Reset probe and catcher arm firstly, then you can choose Air
position for Catcher and click Move XY, then click “Move Z”. In the
next, please choose Air for sampling probe and click Move XY, Click
Move Z and then check whether the probe almost touch the cuvette
bottom.
Optical Path Adjustment
Original Value:
 Low Sensitivity default value: Offset 139, Gain 128.
 Middle Sensitivity default value: Offset 139, Gain 128.
 High Sensitivity default value: Offset 128, Gain 128.
Tools for Optical check
1. Turbidity 100 Better to store in Dark Environment.
2. Turbidity 400 Better to store in Dark Environment
3. Black Cuvette
400 Turbidity Tool:
 CH1-CH5, Low Sensitivit’s AD reference range: 20000±2000.
 Ch6-CH7, Middle Sensitivit’s AD reference range: 30000±3000.
 Ch6-CH7, High Sensitivit’s AD reference range: 55000±10000.
 CH1-CH5, Middle Sensitivit’s AD reference range: 22000±2000.
 CH1-CH5, High Sensitivit’s AD reference range: 55000±5000.
Cuvette with Distilled water
 Ch6-CH7, Low Sensitivit’s AD reference range: 42000±2000.
Use 400 Turbidity Tool and Change Gain value:
100 Turbidity Tool:
Use 100 Turbidity Tool and Change Gain value:
Black Cuvette:
Change Offset value:
AD value: around 400-750
Pressure adjustment
Displayed Pressure: Get into “Temperature” menu and click Open Sensor button. Click
Open liquid pump button. Pay attention to the Liquid Pressure value (Unit is mmHg). We need the
difference between software and air pressure meter less than 10 mmHg. If the value is big, please
click Close liquid pump button and adjust the Gain value. Then test again till it is in the reference
range.
Actual Pressure Adjustment:
Click Open Liquid Pump button and connect air pressure meter to WASH connector
which color is blue. Adjust VR501 to make the value of air pressure meter to
280±20mmHg. After adjust PR5, please disconnect the tube of air pressure meter. After
the air releases, please connect air pressure meter and adjust again. Click Close Liquid
Pump after finishing adjustment.
Temperature adjustment
Click “open sensor” and see the displayed temperature. Normally the probe temperature
is around 43 celcius. Reagent Temp. is less than 16 celcius.
TroubleShooting:
 1. Blue Screen
 2. Black Screen
 3. Mechanic Parameter is lost
 4. Common Errors
Blue Screen
How to check whether the system is working ok:
Click “ctrl”+“Alt”+“Del” to ensure whether
the task manager can appear
Possible Reason:
1. System is lost
2. Operation software is corrupted
Note: When the system is working ok, you can see the mouse curse on the
screen after connecting USB mouse.
After turning on the instrument, if you can see the Counting down 3, 2,1, please
click R button several times to recover the system.
Black Screen
 Check the voltage on the LCD interface board
Note: You can disconnect the cable of other
boards, i.e, front board, High voltage board to
locate the problem
Mechanic Parameter Lost
Solution: Copy back the original parameter
file in The software folder.
 1. The Mechanic Parameter is stored in
Sysparam.dat file. When installing the new
instrument, it’s required to backup the
Sysparam.dat for future use.
Note: The USB disk need to kill Virus in
advance.
Common Errors
(001) error alarm for optical coupling reset
for sampling arm X-axis
1
(1) Failure for optical coupling or cluster
(2) Incorrect or in place for optical coupling piece
(3) Cluster for drive board
(4) Aged or broken flat wire
(002) error alarm for optical coupling reset
for sampling arm Y-axis
1
(003)error alarm for optical coupling reset
for sampling arm Z-axis
1
(004) error place for the reagent area for
sampling needle liquid level sensor
2
(1) liquid level test board
(2) Sampling needle
(3) Cluster
(005 or 006) sampling needle fails to test
error existing in liquid level! The place is
at **
5
(1) Lack of reagent or sample
(2) Failure for liquid level test board, replace such
board.
(3) Aged cluster for sampling needle
(4) Broke flat line at X-axis or Y-axis for sampling arm,
replace small or big flat wire
(007) error for impact in sampling needle!
The place is at **
3
(1) J1 port for liquid level test board has two pins
conducted
(2) Failure for micro-switch, replace it
(3) Aged cluster for micro-switch
(4) Broken flat wire at X-axis or Y-axis for
sampling arm
(5) Unreasonable debugging for mechanical arm
place data
(6) Sampling arm fails to move specified position
(7) Painting lubrication oil onto XYZ-axis for
sampling arm
Common Errors
(010)Error for download place data
for sampling arm
1 Error for serial port
(017) error alarm for optical coupling
reset for catcher arm X-axis
1
(1) Failure for optical coupling or cluster
(2) incorrect or in place for optical coupling piece
(3) aged or broken flat wire
(4) Damaged motor drive board
(018) Error alarm for optical coupling
reset for catcher arm Y-axis
1
(1) Failure for optical coupling or cluster
(2) Incorrect or in place for optical coupling piece
(3) aged or broken flat wire
(4) Damaged motor drive board
(019) Error alarm for optical coupling
reset for catcher arm Z-axis
1
(1) Failure for optical coupling or cluster
(2) Incorrect or in place for optical coupling piece
(3) Aged or broken flat wire
(4) Damaged motor drive board
(020) Error for catcher arm cup
failing to detect cuvette! The place is
at **
4
(1) No cuvette exists at make-up place
(2) Some smear exists at reflecting sensor, which affects detection
or damage
(3) Aged or damaged flat wire at X-axis or Y-axis of catcher arm
(4) catcher arm peels out
(5) Failure for drive board
(6) Not vertical reassembly for grab
Common Errors
(024) Error for download place data
for catcher arm
1
(028)Lack of reaction cup 4
(102) Error for communication with
sampling arm
1
(103) Error for communication with
catcher arm
1
(104) Error for communication with
temperature control
1
(105) Abnormal temperature at
reagent area, temperature is **℃
6
(1) Waiting for running machine for less than 20 minutes
(2) Failure for Pletier, replace Pletier
(3) Air fan stops running, resulting in failure for heat radiation.
Replace air fan for cold storage
(4) Failure for temperature sensor
(5) Failure for temperature-control board
How to Claim Problem to Rayto?
 1. Fill the Problem or spare parts Claim
Form with the problem details, including
SN, Photos, Video, software folder, what is
done (if necessary).
 2. Send the claim form to
Support@rayto.com which is available to
all Service Engineers in Rayto.
Collect The problem Record
 1. Each Engineer need to fill in the
problem record after complete the
troubleshooting. For the Maintenance Trip,
there is no need to mentioned.
 2. Please send back to
support@rayto.com every 3 Month.
The end

More Related Content

Similar to RAC-050 Engineer Training V1.0e-202202.ppt

Autel Powerscan PS100 User Manual
Autel Powerscan PS100 User ManualAutel Powerscan PS100 User Manual
Autel Powerscan PS100 User Manual
obddeal
 
EMPTY BOTTLE INSPECTION MACHINE
EMPTY BOTTLE INSPECTION MACHINEEMPTY BOTTLE INSPECTION MACHINE
EMPTY BOTTLE INSPECTION MACHINE
NIKHIL KRISHNA
 
Requirements_and_Testing_Diagram_Process2
Requirements_and_Testing_Diagram_Process2Requirements_and_Testing_Diagram_Process2
Requirements_and_Testing_Diagram_Process2
Bob Moreno
 
1104B Training Materials--B level--V4.1.pptx
1104B Training Materials--B level--V4.1.pptx1104B Training Materials--B level--V4.1.pptx
1104B Training Materials--B level--V4.1.pptx
ArnoldoFelix3
 

Similar to RAC-050 Engineer Training V1.0e-202202.ppt (20)

Hướng dẫn sử dụng Testo 435-3
Hướng dẫn sử dụng Testo 435-3Hướng dẫn sử dụng Testo 435-3
Hướng dẫn sử dụng Testo 435-3
 
Hướng dẫn sử dụng testo 435-3
Hướng dẫn sử dụng  testo 435-3 Hướng dẫn sử dụng  testo 435-3
Hướng dẫn sử dụng testo 435-3
 
DSC
DSCDSC
DSC
 
Oxygen analyser
Oxygen analyserOxygen analyser
Oxygen analyser
 
Maa sharda pharmacy college ayodhya SOP
Maa sharda pharmacy college ayodhya SOPMaa sharda pharmacy college ayodhya SOP
Maa sharda pharmacy college ayodhya SOP
 
Autel Powerscan PS100 User Manual
Autel Powerscan PS100 User ManualAutel Powerscan PS100 User Manual
Autel Powerscan PS100 User Manual
 
Font
FontFont
Font
 
Edwards Signaling E-PD Installation Manual
Edwards Signaling E-PD Installation ManualEdwards Signaling E-PD Installation Manual
Edwards Signaling E-PD Installation Manual
 
E 8-personal
E 8-personalE 8-personal
E 8-personal
 
Manual de operación y mantenimiento concentrador de oxigeno jay-5
Manual de operación y mantenimiento concentrador de oxigeno jay-5Manual de operación y mantenimiento concentrador de oxigeno jay-5
Manual de operación y mantenimiento concentrador de oxigeno jay-5
 
EMPTY BOTTLE INSPECTION MACHINE
EMPTY BOTTLE INSPECTION MACHINEEMPTY BOTTLE INSPECTION MACHINE
EMPTY BOTTLE INSPECTION MACHINE
 
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptxQUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
 
SOLDERING TQ.pptx
SOLDERING TQ.pptxSOLDERING TQ.pptx
SOLDERING TQ.pptx
 
ORP Sensor Troubleshooting Guide
ORP Sensor Troubleshooting GuideORP Sensor Troubleshooting Guide
ORP Sensor Troubleshooting Guide
 
Hướng dẫn sử dụng máy đo đa năng Testo 550 KIT
Hướng dẫn sử dụng máy đo đa năng Testo 550 KIT Hướng dẫn sử dụng máy đo đa năng Testo 550 KIT
Hướng dẫn sử dụng máy đo đa năng Testo 550 KIT
 
Hướng dẫn sử dụng testo 550
Hướng dẫn sử dụng testo 550Hướng dẫn sử dụng testo 550
Hướng dẫn sử dụng testo 550
 
Jay 5 bw
Jay 5 bwJay 5 bw
Jay 5 bw
 
Requirements_and_Testing_Diagram_Process2
Requirements_and_Testing_Diagram_Process2Requirements_and_Testing_Diagram_Process2
Requirements_and_Testing_Diagram_Process2
 
1104B Training Materials--B level--V4.1.pptx
1104B Training Materials--B level--V4.1.pptx1104B Training Materials--B level--V4.1.pptx
1104B Training Materials--B level--V4.1.pptx
 
Qualification of Analytical Equipments
Qualification of Analytical EquipmentsQualification of Analytical Equipments
Qualification of Analytical Equipments
 

Recently uploaded

Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Recently uploaded (20)

HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 

RAC-050 Engineer Training V1.0e-202202.ppt

  • 1. 深圳雷杜生命科学股份有限公司 RAYTO LIFE AND ANALYTICAL SCIENCES CO.,LTD. Your Reliable Partner In Lab Diagnostics RAC-050 Engineer Training Feb. 2021
  • 4. Engineer Training Part 1 Instrument Principle Part 2 Specification of RAC-050 Part 3 Instrument Installing Part 4 Maintenance Part 5 Common Troubleshooting
  • 6.
  • 7. After Open the Light-Shield Cover Normally, when the instrument is working, the cover should be closed in advance, or else, the test can not go further. For Engineer, you can place the Magnetic on the cover sensor to disable it. Or you can disconnect the sensor cable and connect the Pin 1 and Pin3.
  • 8. Instrument Requirement  1. Instrument has Inbuilt Main board inside. It doesn’t need to have PC working with.  2. Online UPS is Necessary.  3.RAC-Cleanser and cuvettes should be original from Rayto, or else, it will have the problem that the Probe cannot wash totally and bring Carry-over contamination, and the cuvette is not mixed properly, or even the optical system cannot work properly.
  • 9. RAC-Cleanser RAC-Cleanser (30ml) Expired Date: 12 Month Expired Date after open: 30 Day Storage Temp: 2-35 Celcius Consumption for Long Rinse and Test preparation is 200ul Consumption in testing is Reagent volume+20ul
  • 10. Part 1 Instrument Principle  Principle of light-path  Electronic circuit principle  Liquid Path
  • 12. Vacuum Collecting Tube Coagulation Testing Citrate inside, 0.109mol/L ESR Testing Citrate inside Chemistry Testing No Anti-Coagulant Hematology Testing EDTA –K2 Anti-Coagulant
  • 14.
  • 16. Clotting/Coagulation Method Scatter Light intersity refects due to the Turbidity Strength. And it’s Linear with the Testing Material Concentration. Wavelength: 660nm No Filter inside, Only Red Interference Plastic
  • 17. PT Actual Reaction Curve X axis: Time(s)*10, 200 means 20s Y axis: AD, Max Value is 65535 Coagulation Time (S)
  • 18. PT ratio= PT/Normal INR= (PT ratio)^(ISI) DFbg need to calibration with sample PT% need to do calibration with blood pool Note: For the Software V2.4e, the DFbg Unit is same with FIB.
  • 19. Immunologic Method Light resource is LED and there is 575nm filter in the Optical System. It will produce yellow light go through cuvette. The Turdimitry is more intense, the less light will transit through the Cuvette. LED Photo- Detector
  • 20. D-Dimer Reaction Curve X axis: Time(s)*10, 200 means 20s Y axis: AD, Max Value is 65535 Reaction Rate
  • 21. Chromogenic Method Light resource is LED and there is 405nm filter in the Optical System. It’s Purple color in the Reaction cuvette. The Turdimitry is more intense, the less light will transit through the Cuvette. LED Photo- Detector
  • 22. Structure of Light-path 8 Incubation Channels 7 Test Channels
  • 23.
  • 24.
  • 25. Place for New Cuvettes
  • 26. Principle of Liquid path Water Bottle: Postive Pressure, 280+/-30mmHg Waste Bottle: Negative Pressure
  • 27.
  • 28.
  • 29. Tube Connection at the Rear
  • 30. Item Testing Workflow • Temperature Stabilized Add Sample • Incubate Add R1 • Mix and Test Or Incubate Add R2 Note: If the Sample is need to predilution, the probe will add the Diluent firstly and then add the Sample, After that, Dispense into the cuvette and then add R1 and R2. If sample dilution is not possible to complete in one time, it will use one Cuvette to diluent the sample. After that, the probe will add diluent and then add the diluted sample and dispense to the new cuvette and further add R1 and R2 Test Cycle Time is 30 second
  • 31. Structure of Hardware Main Board with CF card Main Control Board Motor Driving Board Temperature Control Board Touch Screen Driving Board Display Driver Board Printer Driving Board Touch Screen LCD Screen Printer Head Input &output System of the instrument 4 Way Pre-Amplify Board 3 Way Pre-Amplify Board Five Pcs Boards for Light Resource Optical System Big Driving board For Catcher System Sampling Driving board Liquid Detection Board Temp-Control System Mechanic System Small Driving board For Catcher System
  • 32. Main board 1. Battery is used to save the BIOS settings. 2. Memory Bank can use the Erase to clean the Pins. 3. CF card is installed on the same side of Memory Bank.
  • 33. CF Card  Contains System and Operation Software
  • 34.
  • 35. Boards on Instrument Rear Main Control Board Motor Driving Board Temp Control Board
  • 36. New Catcher New Catcher Old Catcher Note: To detect the Cuvette, it need to have the reflective sensor.
  • 38. Sampling Arm Probe: Internal Heating Probe Vertical Anti-Collision Probe Liquid level detection
  • 39. Catcher Arm  Vortex Mixing  Cuvette Detection  3-D movement
  • 41. Reagent Area  Reagent Cooling: <16 celcius  2 Peltiers
  • 42.
  • 43. Power Connection ±15V Temperature control board Industrial control board Motor drive board ±15V Switch power 100~240V AC Filter 5V Switch power 12V Switch power Power supply port board 24V Switch power DC 12V DC 24V DC 5V Main control board Display port board Air fan Fuse
  • 44. Part 2 Instrument Specification  1. 3 Testing Method  2. 3. Reagent Mixing around Position A1  3. LIS Data Transfer  4. 8 inch Screen with Touch Screen  5. Reaction Volume: 150-300ul, Vortex Mixing  6. Laser Printer can installed on the instrument, Built-in Thermal printer  7. Optional Function: Sample Barcode Reader, Reagent Card Reader (RFID).
  • 45. Part 3 Instrument Installation  1. Installation Environment  2. Installation Process
  • 46. Installation Environment  Well-ventilated; Free dust as possible around it;  Prevent from direct exposure to sunlight;  Prevent it placing around heat source or air one;  Free from corrosive or flammable gas;  UPS is necessary;  Do not be close to brush generator or frequently-switching-on electric equipment;  Do not be close to electric equipment sending electromagnetic wave;  Ambient temperature: 15-30℃, operation temperature fluctuation: less than +/-2℃/H;  Ambient humidity: 35%-80%RH, non-condensed;  This needs to install air conditioner if indoor temperature fails to meet requirement.
  • 47. Power supply Requirement:  Power supply: 220VAC, 50/60Hz, 1000VA, three-core power supply wire, good grounding;  Needs independently have grounding wire;  Neutral-grounding voltage: less than 5V;  AC power supply must be stable, prohibit sharing in power supply with high-power electric appliance, stable power supply should be set at most;
  • 48. Unpack  1. Wear glove  2. Remove the lock from the box bottom.
  • 49. Remove the Buffer and Taps
  • 50. Cut away the Plastic tie In total it has 5 Plastic tie. After remove the tie, please check whether the probe arm and catcher arm can move freely.
  • 52. Switch On and Software Login 1. For User, The password is 888888; For Engineer, the password is h-201 2. Click the Company Logo, and you can see the versions of the software and Main control board.
  • 53. Reset all the positions and Then Long Rinse Note: Long Rinse is necessary for new installation. It make the liquid go into the instrument.
  • 54. Check Sensor Status Please click Open and then you can check all the sensor status.
  • 55. Part 4 Maintenance  1. Daily Maintenance  2. Monthly Maintenance  3. Yearly Maintenance
  • 56. Daily Maintenance  1. Empty the Waste Bottles  2. After daily test, need to turn off the instrument and put the reagent back to the fridge.
  • 57. Weekly Maintenance  1. Clean the probe surface with alcohol  2. Clean Reagent area  3. Clean the instrument outside surface with soft cloth, includes the sample Rack  4. Clean the water bottle
  • 58. Half Year Maintenance  1. Grease the Probe arm and Catch Arm  2. Clean the water bottle filter  3. Clean the dust on the Fans
  • 59. Yearly Maintenance  1. Check whether the fan have abnormal sound. If yes, please replace it.  2. Check the optical path. Normally it’s ok to check every 2 years. LEDs are work stable.  3. Check the tube is dirty or not. If yes, please replace.
  • 60. Part 5 Adjustment  1. Probe Position Adjustment  2. Catcher Position Adjustment  3. Temperature adjustment  4. Optical adjustment
  • 61. Engineering Adjust Interface Note: The Maintenance Button is enabled when Login Engineer. The Maintenance interface is mainly used to check the Positions, Check Movement is correct or not, Parts status, etc.
  • 62. Probe Adjustment Debug Area Position Check Area For Dispend and Sample/Reagent Pos., the probe needs to be in the center, for Vertical position, the probe should touch bottom.
  • 63.
  • 65. Air Pos.  Please Reset probe and catcher arm firstly, then you can choose Air position for Catcher and click Move XY, then click “Move Z”. In the next, please choose Air for sampling probe and click Move XY, Click Move Z and then check whether the probe almost touch the cuvette bottom.
  • 66.
  • 67. Optical Path Adjustment Original Value:  Low Sensitivity default value: Offset 139, Gain 128.  Middle Sensitivity default value: Offset 139, Gain 128.  High Sensitivity default value: Offset 128, Gain 128.
  • 68. Tools for Optical check 1. Turbidity 100 Better to store in Dark Environment. 2. Turbidity 400 Better to store in Dark Environment 3. Black Cuvette
  • 69. 400 Turbidity Tool:  CH1-CH5, Low Sensitivit’s AD reference range: 20000±2000.  Ch6-CH7, Middle Sensitivit’s AD reference range: 30000±3000.  Ch6-CH7, High Sensitivit’s AD reference range: 55000±10000.  CH1-CH5, Middle Sensitivit’s AD reference range: 22000±2000.  CH1-CH5, High Sensitivit’s AD reference range: 55000±5000. Cuvette with Distilled water  Ch6-CH7, Low Sensitivit’s AD reference range: 42000±2000. Use 400 Turbidity Tool and Change Gain value: 100 Turbidity Tool: Use 100 Turbidity Tool and Change Gain value: Black Cuvette: Change Offset value: AD value: around 400-750
  • 70. Pressure adjustment Displayed Pressure: Get into “Temperature” menu and click Open Sensor button. Click Open liquid pump button. Pay attention to the Liquid Pressure value (Unit is mmHg). We need the difference between software and air pressure meter less than 10 mmHg. If the value is big, please click Close liquid pump button and adjust the Gain value. Then test again till it is in the reference range. Actual Pressure Adjustment: Click Open Liquid Pump button and connect air pressure meter to WASH connector which color is blue. Adjust VR501 to make the value of air pressure meter to 280±20mmHg. After adjust PR5, please disconnect the tube of air pressure meter. After the air releases, please connect air pressure meter and adjust again. Click Close Liquid Pump after finishing adjustment.
  • 71. Temperature adjustment Click “open sensor” and see the displayed temperature. Normally the probe temperature is around 43 celcius. Reagent Temp. is less than 16 celcius.
  • 72. TroubleShooting:  1. Blue Screen  2. Black Screen  3. Mechanic Parameter is lost  4. Common Errors
  • 73. Blue Screen How to check whether the system is working ok: Click “ctrl”+“Alt”+“Del” to ensure whether the task manager can appear Possible Reason: 1. System is lost 2. Operation software is corrupted Note: When the system is working ok, you can see the mouse curse on the screen after connecting USB mouse. After turning on the instrument, if you can see the Counting down 3, 2,1, please click R button several times to recover the system.
  • 74. Black Screen  Check the voltage on the LCD interface board Note: You can disconnect the cable of other boards, i.e, front board, High voltage board to locate the problem
  • 75. Mechanic Parameter Lost Solution: Copy back the original parameter file in The software folder.  1. The Mechanic Parameter is stored in Sysparam.dat file. When installing the new instrument, it’s required to backup the Sysparam.dat for future use. Note: The USB disk need to kill Virus in advance.
  • 76. Common Errors (001) error alarm for optical coupling reset for sampling arm X-axis 1 (1) Failure for optical coupling or cluster (2) Incorrect or in place for optical coupling piece (3) Cluster for drive board (4) Aged or broken flat wire (002) error alarm for optical coupling reset for sampling arm Y-axis 1 (003)error alarm for optical coupling reset for sampling arm Z-axis 1 (004) error place for the reagent area for sampling needle liquid level sensor 2 (1) liquid level test board (2) Sampling needle (3) Cluster (005 or 006) sampling needle fails to test error existing in liquid level! The place is at ** 5 (1) Lack of reagent or sample (2) Failure for liquid level test board, replace such board. (3) Aged cluster for sampling needle (4) Broke flat line at X-axis or Y-axis for sampling arm, replace small or big flat wire (007) error for impact in sampling needle! The place is at ** 3 (1) J1 port for liquid level test board has two pins conducted (2) Failure for micro-switch, replace it (3) Aged cluster for micro-switch (4) Broken flat wire at X-axis or Y-axis for sampling arm (5) Unreasonable debugging for mechanical arm place data (6) Sampling arm fails to move specified position (7) Painting lubrication oil onto XYZ-axis for sampling arm
  • 77. Common Errors (010)Error for download place data for sampling arm 1 Error for serial port (017) error alarm for optical coupling reset for catcher arm X-axis 1 (1) Failure for optical coupling or cluster (2) incorrect or in place for optical coupling piece (3) aged or broken flat wire (4) Damaged motor drive board (018) Error alarm for optical coupling reset for catcher arm Y-axis 1 (1) Failure for optical coupling or cluster (2) Incorrect or in place for optical coupling piece (3) aged or broken flat wire (4) Damaged motor drive board (019) Error alarm for optical coupling reset for catcher arm Z-axis 1 (1) Failure for optical coupling or cluster (2) Incorrect or in place for optical coupling piece (3) Aged or broken flat wire (4) Damaged motor drive board (020) Error for catcher arm cup failing to detect cuvette! The place is at ** 4 (1) No cuvette exists at make-up place (2) Some smear exists at reflecting sensor, which affects detection or damage (3) Aged or damaged flat wire at X-axis or Y-axis of catcher arm (4) catcher arm peels out (5) Failure for drive board (6) Not vertical reassembly for grab
  • 78. Common Errors (024) Error for download place data for catcher arm 1 (028)Lack of reaction cup 4 (102) Error for communication with sampling arm 1 (103) Error for communication with catcher arm 1 (104) Error for communication with temperature control 1 (105) Abnormal temperature at reagent area, temperature is **℃ 6 (1) Waiting for running machine for less than 20 minutes (2) Failure for Pletier, replace Pletier (3) Air fan stops running, resulting in failure for heat radiation. Replace air fan for cold storage (4) Failure for temperature sensor (5) Failure for temperature-control board
  • 79. How to Claim Problem to Rayto?  1. Fill the Problem or spare parts Claim Form with the problem details, including SN, Photos, Video, software folder, what is done (if necessary).  2. Send the claim form to Support@rayto.com which is available to all Service Engineers in Rayto.
  • 80. Collect The problem Record  1. Each Engineer need to fill in the problem record after complete the troubleshooting. For the Maintenance Trip, there is no need to mentioned.  2. Please send back to support@rayto.com every 3 Month.