Question 13 (1 point) Which of the following statements is False? a Program management does not focus on project interdependencies within the project b A project may or may not be a part of a program but a program will always have projects A portfolio refers to the projects, programs, sub- portfolios and operations as a group to achieve strategic objectives Some of the projects undertaken by an organization may not belong to any program but every project is a part of portfolio Question 14 (1 point) Which of the following is NOT an example of value in terms of project outcomes? a Promotion of project team members as the result of a successful project delivery b Enabling the changes to needed to facilitate organizationai transition and/or growth Making posicive contnbutions to societal or environmental issues d Sustaining benefits from previous projects or existing business operations Question 15 (f point) Which of the following Eusiness Decision Criteria subtracts the project costs from the project benefits and then divides by the project costs? a Payback Period b ROI Weighted Scoring Model NPV.