SlideShare a Scribd company logo
1 of 64
Download to read offline
Public Presentation
on the Findings of the
Environmental Impact
Assessment for the Proposed
Residential Development at
Coral Springs, Trelawny
Presented by
Environmental Solutions Limited
On behalf of
Gore Developments Limited
September 18, 2012 at the Kettering Baptist Church, Duncans -
Trelawny
Presentation Outline
 Description of the Project
♦ Location
♦ Design of the Development
♦ Amenities
 The EIA Process
♦ Purpose of the EIA
♦ Methodology
♦ TORs
♦ Role of the Consultants
♦ The EIA Team
♦ Work Plan
 The Existing Environment
♦ Physical
♦ Biological
♦ Socio-economic
 Potential Environmental
Impacts
♦ Air quality
♦ Noise
♦ Slopes
♦ Water resources
 Hydrology, drainage and run-
off
 Sewage
♦ Geology
♦ Ecology
♦ Socio-economic
♦ Hazardous materials
♦ Solid waste
 Mitigation Measures
♦ Construction phase
♦ Operation phase
 Cumulative Impacts
 Consideration of Alternatives
Project Site Location
Satellite Imagery of Site
Coral Springs
 Was initially
subdivided in
the 1970s for
380 lots
 39 Titled lots
 26 houses
built in
southern flat
area
Proposed
Development
Layout
• 169 acres (68 Ha)
of land
• 401 two-bedroom
houses with lot
size of 420.5 m2
• Total of 503 lots
• 102 larger service
lots
Typical GDL House
Amenities
 Green spaces
(17.6 Ha)
 Electricity
 Water supply
 Sewage treatment
 Drainage
 Commercial area
including Gas
Station
 Basic School
allocation
Water
Supply
The EIA Process
Purpose
• Describe
project area
and
environmental
conditions,
identify
potential
impacts &
determine
mitigation
measures
Data
• Make use of
available data
where
appropriate
and collate
new data as
necessary
Reporting
• Conduct
assessment
and prepare
report
• Conduct public
hearing for
citizens’
response
Methodology
Multi-disciplinary team used charette style method for data gathering,
analysis and presentation
Data gathering:
- Review of reports and background documents
- Field studies
- Intrusive tests
- Analysis of maps, plans, aerial photos
- Structured interviews
- Laboratory analyses
Team meetings:
Iterative interaction with developer, architects and engineers
Terms of Reference
Approved
by NEPA
(June 19,
2012)
• Internationally accepted TOR
components for Human
Habitation Projects
• Developed between NEPA,
ESL and GDL
• Included in EIA final report
for reference
Role of the Consultants
Collect and analyze all relevant data, information and viewpoints
Systematically identify and examine possible consequences of
proposed development, and potential impacts on the environment
Determine appropriate means to avoid or reduce (mitigate)
impacts to acceptable levels
Utilize objectivity and professional integrity in analyzing and
reporting all findings
Serve as a liaison between developer and regulatory agency
The consultants do not serve as proponents of the project
The EIA Professional Team
Barry Wade, PhD - Team Leader; Environmental Scientist
George Campbell, MSc – Economist
Kimberly Bryan, MSc – Environmental Scientist
Marlon Beale, PhD Candidate – Avifaunal Specialist
Simone Lee, MSc – Terrestrial Ecologist
Roderick Ebanks, MPhil - Archaeologist
GDL Specialist Consultants
Architects
Portico Ltd
Civil and
Structural
Engineers
FCS
Consultants
Ltd
Hydrologist
Brian
Richardson
Geotechnical
Engineers
NHL
Engineers
Ltd
Surveyors
Masters and
Johnson
Work Plan November 2011 to
September 2012
 Client meetings
 Review of documents
 Review of legislation
 Site investigations
 Community surveys
 Water and Air analyses
 Vegetation surveys
 Faunal surveys
 Hydrological/flood
evaluation study
 Data review and analysis
 Analysis of impacts
 Draft report
 Client review
 Final report to NEPA
 Public notices
 Public presentation of
findings
The Existing Environment
Physical Environment
Topography
2 major slopes and
escarpments –
highest point 76 m
More than 50% of site is
low lying – lowest point 7 m
Soils
 6 of 7
boreholes
dug
 BH #6 was
abandoned
 Soil profiles
were created
Soil Profiles
18 samples
were tested -
average
Compressive
Strength of
1640 psi
Compact to v.
dense Gravelly
Sands
(weathered
limestone) +
Clays
Geology
 Mm – Montpelier Limestone Formation
 Solid red lines show geological faults
 Rocks classified as Medium hard limestone
Hydrology and Drainage
Site drainage controlled by central
sinkhole/pond
Sinkhole lip is clearly demarked at
the 15 m (50 ft.) contour
All drainage lines discharge into
the sinkhole
Centre Northern end
Overflow of the high water
mark
Eastern section
Natural Drainage
Features
Sinkhole drains an area of
approximately 315 hectares
65% of the
property
drains to
sinkhole;
35%
northwards
North Coast
Highway
separates
the
southern
catchment
(the Dry
Valley side)
from the
Coral
Springs
sinkhole
Flows from
south are
channeled
via a
culvert
beneath the
highway to
the
sinkhole
100 Year Flood Plain (17.48 m)
Pond
Water Quality
Drain leading
to sinkhole
monitored
from southern
Dry Valley
property
High BOD and
iron values in
the drain after
passing existing
houses
Sinkhole/pond
acts as a sink
for
contaminants
Natural Hazards
Flooding
• Known to
occur at
the lowest
elevations
on site
Hurricanes
• Like rest of
Jamaica
the site is
prone to
hurricane
impacts
and climate
variability
Landslides
• No
historical
evidence of
landslides
Earthquakes
• Fault line
traverses
site
• Jamaica
located in
active zone
Pollution
• No known
incidences
of pollution
in a 5 Km
zone
Biological Environment
 Four key Habitats:
Domestic Cultivated Zone
Bougainvillea
Mango
Papaya
Ackee
Orange
Closed/Thick Dry Limestone
Forests
Dense shrub
and herb
species in
lower half of
the forest:
Red
Birch
Burnwood Bullhoof Guango Logwood
Open Dry
Limestone
Forests
Less dense upper canopy
and more lower scattered
shrub presence:
• Red Birch
• Burnwood
• Bullhoof
• Guango
• Logwood
Riverine
Vegetation
Bamboo
Sweetsop
Breadfruit
Birds
38 bird
species
13 endemics (e.g.
Jamaican Tody, White
Chinned Thrush, and
Jamaican Lizard Cuckoo)
3 endemic sub-species
12 resident species
8 (winter) migrant species
(e.g. Osprey, American
Redstart and Black
Throated Blue Warbler)
Other Fauna
14 butterfly species (two endemics)
“Croaking lizard”
Bats
Termites
Lampyrid Fireflies
Jamaican Slider Turtle (observed in pond)
Socio-Economic
Environment
♦ Tourism Developments
♦ Heritage Attractions
♦ Falmouth Deep Water Terminal
♦ Housing Developments
 Florence Hall and Stone brook
The Communities of
Interest are:
Falmouth: Parish capital and
main commercial centre;
population 8,188
• Coral Springs – existing
residential estate
• Duncans
• Stewart Castle
• Carey Park and Refuge
• Retreat Heights
Community Opinion on Project
Approval rating for the project
General concerns about the project?
Benefits of the project?
Environmental fears of the project?
Social Infrastructure
Mainly centred in Falmouth
Utilities:
Water
Electricity
Telecommunications
Public
Health
Facilities
Education:
William Knibb
and Holland
High
Waste
Management
Fire
Brigade
Transportation
Heritage
Possible storm
water structure
leading into the
sinkhole/pond
Pack stone wall
around the
north western
section of pond
Very few visible
remnants
above ground
Heritage
Eastern (left) and
western (right)
pack stone
boundary walls
Concrete square
wall structure:
cattle watering
facility?
Potential Environmental
Impacts
Occurrence
of impacts:
• Construction Phase (Site Preparation and
Construction)
• Operations
Classification
of Impacts:
• Positive or negative
• Direct or indirect
• Short or long term
• Reversible or irreversible
• Cumulative
Potential Impacts
Air
quality:
•Increased dust during
construction activities
Noise:
•Will be elevated during
construction hours
Potential Impacts:
Slopes
•Clearance of
vegetation on steep
slopes
•Grading/cutting and
filling of slopes
Potential Impacts: Drainage and
Hydrology
Blasting
Changes
geometry of
sinkholes
features causing
blockages in
outflow pathways
Erosion
Eroded sediments
can clog the
sinkhole
Encroachment of
sinkhole rim
Reduce storage
volume for storm
water runoff
FLOODING
Water Quality
Run off from site activities and stockpiles
Waste waters from washing of vehicles
Wastewater from construction site sanitary
facilities
Improper and inadequate sewage disposal
facilities
Fuel and chemical storage
Potential Impacts:
Potential Impacts: Ecology
Inevitable
removal of
~ 150 Ha of
vegetation
Loss of
habitats
Fragmentation
of habitats
Impact on
faunal
species
e.g. loss
of bird
nesting
sites
Socio-economic Impacts:
Employment
Traffic
Solid Waste
• Local construction
work force
• Heavy vehicles
entering and leaving
the property
• construction debris,
vegetation, and solid
waste from the
construction
camp/site
Carrying Capacity
• NWC able to supply projected 595
m3/day of water without affecting
the overall water supply
Water
supply
• Facilities already overwhelmed
Solid
waste
• Facilities already severely
overwhelmed
Health
care
Mitigation Measures: Air
Quality
Phased vegetation
clearance
• To create
buffers to filter
out dust
• Minimize
chances of
erosion
Wetting exposed
surfaces
• Especially
during dry
periods during
construction
Safety gears
• Construction
crews should
be provided
with
appropriate
gears for
protection
Mitigation Measures: Slopes
No removal of
vegetation on
escarpments
Roads and parking
areas designed to
minimize excessive
erosion
Fills to be properly
stabilized and cuts
supported by
retaining walls or
other appropriate
structures
 SA#1 to SA# 5 (54.3
ha) flows to the pond
in a series of storm
sewer and covered U
drains
 SA#6 to SA# 8 (flow
north from site) have
three exit points to
meet natural channels
in wide open U drains
 SA#9 to SA# 14
(50.5 ha) flow into
the existing channels
via several drains
Drainage, Hydrology
and Flood Mitigation
Sub-catchment 1-14
Drainage, Hydrology and Flood
Mitigation
Storage capacity and
infiltration potential
of sinkhole to be
increased
Hard brown clay to
be removed and
filled with compacted
gravel and crushed
limestone (13.5 m -
14.2 m contour)
Post development
flood elevation will
not exceed pre
development flood
elevation
Designed to
reduce
flooding by
0.78 m for 100
year storm
Sinkhole Protection: No-Fill
Zone
No construction, vegetation removal/modification, stockpiling or
storage of any kind should be allowed in this (14 m contour line)
Water Quality: Sewage Treatment
Septic tank on each lot
Lift Stations
Four “Reed Beds” (Constructed Wetland)
Three Chlorination Chambers
Reed Bed Cross Section
Example of Reed Beds –
GDL Florence Hall
Development
Ecology
• Preserve
contiguous areas
of vegetation
Minimize
fragmentation
• Create open
spaces for
recreation and
sports
Green space
allocation • Re-introduce
endemic plants
into landscape
Landscaping
Waste Management
A warning sign should
be erected in the
vicinity of the
pond/sinkhole
Garbage collection
should be adequately
facilitated by regular
collection
Heritage
Features such as
the packed stone
walls should be
preserved and
integrated into
the development
During site
clearance JNHT
should be present
to ensure that any
sub-surface
structures
encountered are
preserved
Restoration of the Florence Hall
Great House
October 2007
August 2012
Colonial era
Cumulative Impacts
Increased urbanization of the Coral Springs area due to the
housing development and open commercial area
Increase in noise and dust during construction
Increased traffic during construction and increased
ingress/egress to highway during operation
Improved housing stock – local residents and
overseas investment (Diaspora)
Increased use of drainage basin and sinkhole could
minimize future development options
Ecology – loss of natural habitat and impact on existing
aesthetics
ALTERNATIVES
Sewage
Treatment
• The developer
may consider
allowing existing
Coral Springs
residents to
connect to the
central sewage
system.
Private
Forestry for
slopes
• E.g. as a Forest
Reserve) under
the Forestry
Division’s
Private Forestry
Programme
No Build
Alternative
• No additional
houses to meet
demand
• No drainage
improvements
THANK YOU!
QUESTIONS AND ANSWERS

More Related Content

Similar to Public Presentation on the Findings of the Environmental Impact Assessment pdf

LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1Theodore McNeal
 
Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...
Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...
Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...AnnArborSPARK
 
Impact of desalination plant
Impact of desalination plantImpact of desalination plant
Impact of desalination plantLincy Jancy
 
REMOTE SENSING AND GIS
REMOTE SENSING AND GISREMOTE SENSING AND GIS
REMOTE SENSING AND GISTEAM AGRI
 
Introduction to disposal part 1 landfill
Introduction to disposal part 1 landfillIntroduction to disposal part 1 landfill
Introduction to disposal part 1 landfillRehab O. Abdel Rahman
 
Environmental pollution and climate change
Environmental pollution and climate changeEnvironmental pollution and climate change
Environmental pollution and climate changeAnil Thapa Kazi
 
introductiontoenvironmentalchemistry-190927053238.pptx
introductiontoenvironmentalchemistry-190927053238.pptxintroductiontoenvironmentalchemistry-190927053238.pptx
introductiontoenvironmentalchemistry-190927053238.pptxhabtamugeremew499
 
Air water-sound-and-Land-pollution and its remedial approach
Air water-sound-and-Land-pollution and its remedial approachAir water-sound-and-Land-pollution and its remedial approach
Air water-sound-and-Land-pollution and its remedial approachIslamic University of Bangladesh
 
Philadelphia Water Department, Green City Clean Waters Program
Philadelphia Water Department, Green City Clean Waters ProgramPhiladelphia Water Department, Green City Clean Waters Program
Philadelphia Water Department, Green City Clean Waters ProgramNew Jersey Future
 
Environmental Pollution.pptx
Environmental Pollution.pptxEnvironmental Pollution.pptx
Environmental Pollution.pptxLohithKumar919628
 
Introduction to environmental chemistry
Introduction to environmental chemistryIntroduction to environmental chemistry
Introduction to environmental chemistrygeetha T
 
Site selection and site planning
Site selection and site planningSite selection and site planning
Site selection and site planningHiba Abbas
 

Similar to Public Presentation on the Findings of the Environmental Impact Assessment pdf (20)

LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...
Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...
Michigan Energy Forum - November 7, 2013 - Balancing Energy and Environmental...
 
Birch Bay Watershed Characterization
Birch Bay Watershed CharacterizationBirch Bay Watershed Characterization
Birch Bay Watershed Characterization
 
EIA & EIV
EIA & EIVEIA & EIV
EIA & EIV
 
Impact of desalination plant
Impact of desalination plantImpact of desalination plant
Impact of desalination plant
 
UCOWR2016_ShresthaP
UCOWR2016_ShresthaPUCOWR2016_ShresthaP
UCOWR2016_ShresthaP
 
REMOTE SENSING AND GIS
REMOTE SENSING AND GISREMOTE SENSING AND GIS
REMOTE SENSING AND GIS
 
Scert final
Scert finalScert final
Scert final
 
Introduction to disposal part 1 landfill
Introduction to disposal part 1 landfillIntroduction to disposal part 1 landfill
Introduction to disposal part 1 landfill
 
Environmental pollution and climate change
Environmental pollution and climate changeEnvironmental pollution and climate change
Environmental pollution and climate change
 
introductiontoenvironmentalchemistry-190927053238.pptx
introductiontoenvironmentalchemistry-190927053238.pptxintroductiontoenvironmentalchemistry-190927053238.pptx
introductiontoenvironmentalchemistry-190927053238.pptx
 
Air water-sound-and-Land-pollution and its remedial approach
Air water-sound-and-Land-pollution and its remedial approachAir water-sound-and-Land-pollution and its remedial approach
Air water-sound-and-Land-pollution and its remedial approach
 
GW
GW GW
GW
 
Planetary Boundaries
Planetary BoundariesPlanetary Boundaries
Planetary Boundaries
 
khanababa
khanababa khanababa
khanababa
 
Philadelphia Water Department, Green City Clean Waters Program
Philadelphia Water Department, Green City Clean Waters ProgramPhiladelphia Water Department, Green City Clean Waters Program
Philadelphia Water Department, Green City Clean Waters Program
 
Environmental Pollution.pptx
Environmental Pollution.pptxEnvironmental Pollution.pptx
Environmental Pollution.pptx
 
Introduction to environmental chemistry
Introduction to environmental chemistryIntroduction to environmental chemistry
Introduction to environmental chemistry
 
Lid Intro Nw
Lid Intro NwLid Intro Nw
Lid Intro Nw
 
Site selection and site planning
Site selection and site planningSite selection and site planning
Site selection and site planning
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

Public Presentation on the Findings of the Environmental Impact Assessment pdf

  • 1. Public Presentation on the Findings of the Environmental Impact Assessment for the Proposed Residential Development at Coral Springs, Trelawny Presented by Environmental Solutions Limited On behalf of Gore Developments Limited September 18, 2012 at the Kettering Baptist Church, Duncans - Trelawny
  • 2. Presentation Outline  Description of the Project ♦ Location ♦ Design of the Development ♦ Amenities  The EIA Process ♦ Purpose of the EIA ♦ Methodology ♦ TORs ♦ Role of the Consultants ♦ The EIA Team ♦ Work Plan  The Existing Environment ♦ Physical ♦ Biological ♦ Socio-economic  Potential Environmental Impacts ♦ Air quality ♦ Noise ♦ Slopes ♦ Water resources  Hydrology, drainage and run- off  Sewage ♦ Geology ♦ Ecology ♦ Socio-economic ♦ Hazardous materials ♦ Solid waste  Mitigation Measures ♦ Construction phase ♦ Operation phase  Cumulative Impacts  Consideration of Alternatives
  • 4. Satellite Imagery of Site Coral Springs  Was initially subdivided in the 1970s for 380 lots  39 Titled lots  26 houses built in southern flat area
  • 5. Proposed Development Layout • 169 acres (68 Ha) of land • 401 two-bedroom houses with lot size of 420.5 m2 • Total of 503 lots • 102 larger service lots
  • 7. Amenities  Green spaces (17.6 Ha)  Electricity  Water supply  Sewage treatment  Drainage  Commercial area including Gas Station  Basic School allocation
  • 9. The EIA Process Purpose • Describe project area and environmental conditions, identify potential impacts & determine mitigation measures Data • Make use of available data where appropriate and collate new data as necessary Reporting • Conduct assessment and prepare report • Conduct public hearing for citizens’ response
  • 10. Methodology Multi-disciplinary team used charette style method for data gathering, analysis and presentation Data gathering: - Review of reports and background documents - Field studies - Intrusive tests - Analysis of maps, plans, aerial photos - Structured interviews - Laboratory analyses Team meetings: Iterative interaction with developer, architects and engineers
  • 11. Terms of Reference Approved by NEPA (June 19, 2012) • Internationally accepted TOR components for Human Habitation Projects • Developed between NEPA, ESL and GDL • Included in EIA final report for reference
  • 12. Role of the Consultants Collect and analyze all relevant data, information and viewpoints Systematically identify and examine possible consequences of proposed development, and potential impacts on the environment Determine appropriate means to avoid or reduce (mitigate) impacts to acceptable levels Utilize objectivity and professional integrity in analyzing and reporting all findings Serve as a liaison between developer and regulatory agency The consultants do not serve as proponents of the project
  • 13. The EIA Professional Team Barry Wade, PhD - Team Leader; Environmental Scientist George Campbell, MSc – Economist Kimberly Bryan, MSc – Environmental Scientist Marlon Beale, PhD Candidate – Avifaunal Specialist Simone Lee, MSc – Terrestrial Ecologist Roderick Ebanks, MPhil - Archaeologist
  • 14. GDL Specialist Consultants Architects Portico Ltd Civil and Structural Engineers FCS Consultants Ltd Hydrologist Brian Richardson Geotechnical Engineers NHL Engineers Ltd Surveyors Masters and Johnson
  • 15. Work Plan November 2011 to September 2012  Client meetings  Review of documents  Review of legislation  Site investigations  Community surveys  Water and Air analyses  Vegetation surveys  Faunal surveys  Hydrological/flood evaluation study  Data review and analysis  Analysis of impacts  Draft report  Client review  Final report to NEPA  Public notices  Public presentation of findings
  • 18. Topography 2 major slopes and escarpments – highest point 76 m More than 50% of site is low lying – lowest point 7 m
  • 19. Soils  6 of 7 boreholes dug  BH #6 was abandoned  Soil profiles were created
  • 20. Soil Profiles 18 samples were tested - average Compressive Strength of 1640 psi Compact to v. dense Gravelly Sands (weathered limestone) + Clays
  • 21. Geology  Mm – Montpelier Limestone Formation  Solid red lines show geological faults  Rocks classified as Medium hard limestone
  • 22. Hydrology and Drainage Site drainage controlled by central sinkhole/pond Sinkhole lip is clearly demarked at the 15 m (50 ft.) contour All drainage lines discharge into the sinkhole
  • 23. Centre Northern end Overflow of the high water mark Eastern section
  • 24. Natural Drainage Features Sinkhole drains an area of approximately 315 hectares 65% of the property drains to sinkhole; 35% northwards North Coast Highway separates the southern catchment (the Dry Valley side) from the Coral Springs sinkhole Flows from south are channeled via a culvert beneath the highway to the sinkhole
  • 25. 100 Year Flood Plain (17.48 m) Pond
  • 26. Water Quality Drain leading to sinkhole monitored from southern Dry Valley property High BOD and iron values in the drain after passing existing houses Sinkhole/pond acts as a sink for contaminants
  • 27. Natural Hazards Flooding • Known to occur at the lowest elevations on site Hurricanes • Like rest of Jamaica the site is prone to hurricane impacts and climate variability Landslides • No historical evidence of landslides Earthquakes • Fault line traverses site • Jamaica located in active zone Pollution • No known incidences of pollution in a 5 Km zone
  • 30. Closed/Thick Dry Limestone Forests Dense shrub and herb species in lower half of the forest: Red Birch Burnwood Bullhoof Guango Logwood
  • 31. Open Dry Limestone Forests Less dense upper canopy and more lower scattered shrub presence: • Red Birch • Burnwood • Bullhoof • Guango • Logwood
  • 33. Birds 38 bird species 13 endemics (e.g. Jamaican Tody, White Chinned Thrush, and Jamaican Lizard Cuckoo) 3 endemic sub-species 12 resident species 8 (winter) migrant species (e.g. Osprey, American Redstart and Black Throated Blue Warbler)
  • 34. Other Fauna 14 butterfly species (two endemics) “Croaking lizard” Bats Termites Lampyrid Fireflies Jamaican Slider Turtle (observed in pond)
  • 35. Socio-Economic Environment ♦ Tourism Developments ♦ Heritage Attractions ♦ Falmouth Deep Water Terminal ♦ Housing Developments  Florence Hall and Stone brook
  • 36. The Communities of Interest are: Falmouth: Parish capital and main commercial centre; population 8,188 • Coral Springs – existing residential estate • Duncans • Stewart Castle • Carey Park and Refuge • Retreat Heights
  • 37. Community Opinion on Project Approval rating for the project General concerns about the project? Benefits of the project? Environmental fears of the project?
  • 38. Social Infrastructure Mainly centred in Falmouth Utilities: Water Electricity Telecommunications Public Health Facilities Education: William Knibb and Holland High Waste Management Fire Brigade Transportation
  • 39. Heritage Possible storm water structure leading into the sinkhole/pond Pack stone wall around the north western section of pond Very few visible remnants above ground
  • 40. Heritage Eastern (left) and western (right) pack stone boundary walls Concrete square wall structure: cattle watering facility?
  • 41. Potential Environmental Impacts Occurrence of impacts: • Construction Phase (Site Preparation and Construction) • Operations Classification of Impacts: • Positive or negative • Direct or indirect • Short or long term • Reversible or irreversible • Cumulative
  • 42. Potential Impacts Air quality: •Increased dust during construction activities Noise: •Will be elevated during construction hours
  • 43. Potential Impacts: Slopes •Clearance of vegetation on steep slopes •Grading/cutting and filling of slopes
  • 44. Potential Impacts: Drainage and Hydrology Blasting Changes geometry of sinkholes features causing blockages in outflow pathways Erosion Eroded sediments can clog the sinkhole Encroachment of sinkhole rim Reduce storage volume for storm water runoff FLOODING
  • 45. Water Quality Run off from site activities and stockpiles Waste waters from washing of vehicles Wastewater from construction site sanitary facilities Improper and inadequate sewage disposal facilities Fuel and chemical storage
  • 47. Potential Impacts: Ecology Inevitable removal of ~ 150 Ha of vegetation Loss of habitats Fragmentation of habitats Impact on faunal species e.g. loss of bird nesting sites
  • 48. Socio-economic Impacts: Employment Traffic Solid Waste • Local construction work force • Heavy vehicles entering and leaving the property • construction debris, vegetation, and solid waste from the construction camp/site
  • 49. Carrying Capacity • NWC able to supply projected 595 m3/day of water without affecting the overall water supply Water supply • Facilities already overwhelmed Solid waste • Facilities already severely overwhelmed Health care
  • 50. Mitigation Measures: Air Quality Phased vegetation clearance • To create buffers to filter out dust • Minimize chances of erosion Wetting exposed surfaces • Especially during dry periods during construction Safety gears • Construction crews should be provided with appropriate gears for protection
  • 51. Mitigation Measures: Slopes No removal of vegetation on escarpments Roads and parking areas designed to minimize excessive erosion Fills to be properly stabilized and cuts supported by retaining walls or other appropriate structures
  • 52.  SA#1 to SA# 5 (54.3 ha) flows to the pond in a series of storm sewer and covered U drains  SA#6 to SA# 8 (flow north from site) have three exit points to meet natural channels in wide open U drains  SA#9 to SA# 14 (50.5 ha) flow into the existing channels via several drains Drainage, Hydrology and Flood Mitigation Sub-catchment 1-14
  • 53. Drainage, Hydrology and Flood Mitigation Storage capacity and infiltration potential of sinkhole to be increased Hard brown clay to be removed and filled with compacted gravel and crushed limestone (13.5 m - 14.2 m contour) Post development flood elevation will not exceed pre development flood elevation Designed to reduce flooding by 0.78 m for 100 year storm
  • 54. Sinkhole Protection: No-Fill Zone No construction, vegetation removal/modification, stockpiling or storage of any kind should be allowed in this (14 m contour line)
  • 55. Water Quality: Sewage Treatment Septic tank on each lot Lift Stations Four “Reed Beds” (Constructed Wetland) Three Chlorination Chambers
  • 56. Reed Bed Cross Section
  • 57. Example of Reed Beds – GDL Florence Hall Development
  • 58. Ecology • Preserve contiguous areas of vegetation Minimize fragmentation • Create open spaces for recreation and sports Green space allocation • Re-introduce endemic plants into landscape Landscaping
  • 59. Waste Management A warning sign should be erected in the vicinity of the pond/sinkhole Garbage collection should be adequately facilitated by regular collection
  • 60. Heritage Features such as the packed stone walls should be preserved and integrated into the development During site clearance JNHT should be present to ensure that any sub-surface structures encountered are preserved
  • 61. Restoration of the Florence Hall Great House October 2007 August 2012 Colonial era
  • 62. Cumulative Impacts Increased urbanization of the Coral Springs area due to the housing development and open commercial area Increase in noise and dust during construction Increased traffic during construction and increased ingress/egress to highway during operation Improved housing stock – local residents and overseas investment (Diaspora) Increased use of drainage basin and sinkhole could minimize future development options Ecology – loss of natural habitat and impact on existing aesthetics
  • 63. ALTERNATIVES Sewage Treatment • The developer may consider allowing existing Coral Springs residents to connect to the central sewage system. Private Forestry for slopes • E.g. as a Forest Reserve) under the Forestry Division’s Private Forestry Programme No Build Alternative • No additional houses to meet demand • No drainage improvements