SlideShare a Scribd company logo
Proposed radical changes in,“The Arbitration & Conciliation Act, 1996”
Preface
The Law Commission vide its Report No. 246 has proposed various amendments to the Arbitration and
Conciliation Act 1996. The Hon’ble President of India promulgated THE ARBITRATION AND CONCILIATION
(AMENDMENT) ORDINANCE, 2015 on 23rd October, 2015. Considering the eagerness of the Govt. to reduce
fruitless litigation, instill confidence in foreign investors, the proposed amendment to the Arbitration and
Conciliation Act promulgated as an ordinance as the parliament was not in session.
The proposed amendments to the said Act will bring major revolution to the Arbitration process (procedural as
well as statutory) deviating from the existing act in many aspects. There is bound to be frequent discussions at
various forums i.e. by Legal experts and Institutions through seminars, papers and Lectures etc. for reaching
the consensus. However, the Law shall take a clear shape only after the various judgments in the litigation
consequent to the introduction of the amendments to the Act while the Institutions/Legal Society etc. have to be
in readiness to cope up with the changing environment.
The main objective of the amendment to the Act are namely, expediting of the arbitration cases delayed
inordinately, limiting the cost of arbitration (although debatable), discouragement to frivolous claims,
independent/impartial arbitrators, encouragement to Institutional Arbitration, making India friendly arbitration
seat to stop flying of cases to Singapore and other countries, diluting the stringent Conditions of Contract ,
jurisdiction of arbitrator, challenge of award and various other aspects. The salient amendments with their
objective and consequences, the deviation from the existing Act and its effect on the existing Arbitration process
and the various concerns are as follows:
1. Time bound Arbitration (avoidance of delays)
Hitherto, there was no time limit for the Arbitrators to expedite the arbitration process. Now it will be mandatory
for the arbitrator to make a disclosure of their ability to devote sufficient time to complete the arbitration
proceedings and publish the award expeditiously. (24 months for arbitration proceedings and 3 months for
publication of award). The arbitral tribunal has also been empowered to impose costs for frequent and
unnecessary adjournments in the light of Salem Advocate Bar Association case.
Moreover, the fee being fixed on the basis of amount of claim, the arbitrators shall not unnecessarily prolong the
arbitration to continue their meter inordinately. The arbitrators can now decide when the fee is chargeable to
them. The fixed fee implies that the arbitrators shall be paid on contract basis instead of daily basis and hence
an incentive for them to expedite the case.
The Law Commission Report provides that an application challenging the award, be endeavored to be disposed
of expeditiously and in any event within a period of 1 year from the date of service of notice. The Law Commission
Report also seeks to deal with each issue in a systematic and analytical manner. Separately, the Law
Commission Report also recommends that specialized and dedicated arbitration benches be constituted (as
done in the Delhi High Court). It is also provided that such an application (appointment of arbitrator u/s 11) be
endeavored to be disposed of expeditiously, and requires the Court to make an endeavor to dispose of the
matter within 60 days from the service of notice on the opposite party.
The above changes shall discipline the arbitrators and the parties to expedite the whole process and to take the
arbitration sincerely. The amendment doesn’t specify the action/remedy if the process is not completed within
24 months i.e. the mandate of the tribunal shall be terminated or the parties can agree to extend the time period.
2. Fees & Costs
Supreme Court in one of its judgment observed that the cost of arbitration can be high if the arbitral tribunal
consists of retired Judges and many a times exceeding the amount of dispute. Hence, the amendment specifies
the model fee schedule for guidance. The prescribed fees are not mandatory and applicable only in the case of,
fee not fixed by the parties. It is apprehended that the arbitral tribunal shall henceforth fix the fee as per the
model fee taking it as a moral support and it would be quite embarrassing for either of the parties to contest the
fee fixed by the arbitral tribunal. This introduction will not in any way lead to the reduction of fees by retired
judges but instead cause the fee of the Non retired Judges arbitrators increase abnormally e.g. if the total claim
of Claims and Counter claims is Rs.40.0 crore (say), the cost of arbitration as per model fee structure shall be
approx. Rs.30.0 lakhs. In some cases, the arbitrator may simply decide in 2 to 3 hearings that the tribunal has
no jurisdiction due to limitation or accord and satisfaction. Sometimes, the cost of claims may be quite high but
the issue may not be so complex to require many hearings for adjudication but the fee has been kept uniform.
There has to be some connection of fee with the number of hearings and the amount of claim.
The model fee prescribed by the Law commission is as follows:
Sum in Dispute (Rs.) Model Fees (Indicative)
Upto Rs. 5,00,000/- Rs. 45,000/-
Above Rs. 5,00,000/- and upto Rs. 20,00,000/- Rs. 45,000/- + 3.5% of the claim amount over
and above Rs. 5,00,000/-
Above Rs. 20,00,000/- and upto Rs.
1,00,00,000/-
Rs. 97,500/- + 3% of the claim amount over
and above Rs. 20,00,000/-
Above Rs. 1,00,00,000/- and upto Rs.
10,00,00,000/-
Rs. 3,37,500/- + 1% of the claim amount over
and above Rs. 1,00,00,000/-
Above Rs. 10,00,00,000/- and upto Rs.
20,00,00,000/-
Rs. 12,37,500/- + 0.75% of the claim amount
over and above Rs. 1,00,00,000/-
Above Rs. 20,00,00,000/- Rs. 19,87,500/- + 0. 5% of the claim amount
over and above Rs. 20,00,00,000/- with a
ceiling of Rs. 30,00,000/-
* In the event, the arbitrator to be appointed is a Sole Arbitrator, he shall be entitled to an additional amount of
25% on the fee payable as per the table set out above.
It would be advisable to fix the fee of the arbitrators while drafting the arbitration agreement so that there is
check on unusual high fee in view of the subject to clause still existing in the proposed amended Act. Even if
one of the parties has the right to appoint the arbitrator, the fees must be fixed in the arbitration agreement so
that in the eventuality of appointment of arbitrators by the High Court, the fees remain unchanged.
A new sub-section, ”Regime for costs” has been introduced for cost payable by one party to another, though not
mandatory, but recommendatory since it is the liberal attitude of the tribunals of not awarding costs. This leads
to frivolous points being raised in appeals or frivolous appeals being filed in the courts. The general rule would
be that the unsuccessful party will be ordered to pay the cost to the successful party but for contrary decision,
reasons will have to be recorded in writing. Other circumstances i.e. frivolous claims/counter claims,
adjournments, dilatory tactics, effort to settle the case etc. shall be kept into consideration.
The above principle ensures that the “costs follow the event” regime governs all arbitrations/ arbitration related
court litigation. Such a regime would disincentivize frivolous proceedings and inequitable conduct. The basis of
the above provisions is Rule 44 of the Civil Procedure Rules of England.
3. Independence/Impartiality of arbitrators
The Law Commission Report has proposed amendments requiring mandatory written disclosures from the
prospective arbitrator(s) with regard to any circumstances which is likely to give rise to justifiable doubts as to
his independence or impartiality such as the existence either direct or indirect, of any past or present relationship
with or interest in any of the parties or in relation to the subject matter in dispute, whether financial, business,
professional or other kind. (Introduced Fourth, Fifth, Sixth and Seventh Schedule). There is an express bar of
certain persons though waivable but only subsequent to the dispute. i.e. even if the parties have mutually agreed
for appointment of such arbitrators, they shall not be eligible to be appointed as arbitrator provided that the
parties subsequent to the dispute waive the provision by an express agreement in writing.
So far the Courts have held the appointment of arbitrators by one of the parties who may be their employees,
Counsel etc. Originally this practice was followed by Govt. dept. But of late, the same practice has been followed
by Private Institutions and even Real Estate firms with the Buyers.
This is a welcome step in view of the Principle of Natural Justice. The list though very exhaustive, but still there
shall be disputes as regard to present/past relationship and interpretation for inclusion/exclusion of certain
impartiality. However, the time is not far off when the liberty to appoint the arbitrator by one party alone shall
also cease as there are still chances that the arbitrator appointed by one party alone shall have the soft corner
towards the party appointing him as an arbitrator.
4. Institutional arbitration
The Law Commission Report has laid stress on institutional arbitration since its structured procedure and
administrative support provides it the distinct advantages, which are unavailable to parties opting for ad hoc
arbitration. The spread of institutional arbitration however, is minimal in India and has unfortunately not really
kick-started. Presently, the Act is institutional arbitration agnostic – meaning thereby, it neither promotes nor
discourages parties to consider institutional arbitration. The changes suggested by the Commission attempts to
encourage the culture of institutional arbitration in India, which the Commission feels will go a long way to redress
the institutional and systemic malaise that has seriously affected the growth of arbitration.
The Commission has, therefore, recommended the addition of Explanation 3 to section 11(6A) of the Act with
the hope that High Courts and the Supreme Court, while acting in the exercise of their jurisdiction under section
11 of the Act will take steps to encourage the parties to refer their disputes to institutionalized arbitration.
Explanation 3: The High Court may take steps to encourage the parties to refer the disputes to institutionalized
arbitration by a professional Indian or International Arbitral Institute.
Similarly, the Commission seeks to accord legislative sanction to rules of institutional arbitration which recognize
the concept of an “emergency arbitrator” – and the same has been done by broadening the definition of an
“arbitral tribunal” under section 2(d).
The Government may also consider formation of a specialized body, like an Arbitral Commission of India, which
has representation from all the stakeholders of arbitration and which could be entrusted with the task of, inter
alia, encouraging the spread of institutional arbitration in the country.
To name the few, ICA (Indian Council of Arbitration) associated with FICCI, Indian Road Congress, Nani
Palkhivala Arbitration Centre are already working and many more may come in the near future depending upon
the location and the subject matter. The retired Govt. servants, Judges, Lawyers can contribute to the dispute
resolution in their fields by participating in such Institutions.
5. Setting aside of award
The challenge of awards and uncertainty in the courts had increased drastically after the decision of ONGC vs.
Saw Pipes Ltd. The Supreme Court held in Shri Lal Mahal case that the expansive construction accorded to the
term “public policy” cannot apply in foreign awards. However, the proposed amendment has further restricted
the scope of setting aside the award on the ground of conflict with public policy i.e.
(a) the making of the award was induced of affected by fraud or corruption or was in violation of section 75
or section 81; or
(b) it is in contravention with the fundamental policy of Indian law; or
(c) it is in conflict with the most basic notions of morality or justice.
The restricted provisions seeking to set aside or challenge the enforcement of arbitral awards will instill greater
confidence in arbitration as an effective and speedy dispute resolution mechanism for finality. As per the
proposed provisio, the award cannot be set aside merely on the ground of an erroneous application of the law
or by re-appreciating evidence. Hence, the arbitrators shall be required to take extreme judicial care preferably
having insight of Law aspects as such award may henceforth go unchecked.
Hitherto, as per the decision in ONGC vs. Saw Pipes the awards could be set aside if the same were not in
accordance with the terms of the Contract. This has been diluted and as per amendment, the tribunal shall
decide having regard to the terms of the contract indicating that term of contract are not mandatory . How the
Tribunals and Courts shall interpret, “regard to the terms of the contract” will get clear in the time to come.
6. Automatic stay of enforcement (likely to be amended)
The Supreme Court in National Aluminium observed, “However, we do notice that this automatic suspension of
the execution of the award, the moment an application challenging the said award is filed under section 34 of
the Act leaving no discretion in the court to put the parties on terms, in our opinion, defeats the very objective of
the alternate dispute resolution system to which arbitration belongs._ _ _ _” Accordingly sub-section 36(2) has
been added which states that the filing of such an application shall not by itself render the award unenforceable,
unless upon a separate application made for that purpose, the Court grants stay of the operation of the award
in accordance with the provisions of sub-section(3) hereof,”. The Courts may also direct the applicants to deposit
the award amount or portion thereof prior to any stay of the award being granted, thus reducing the incentive to
litigate.
7. Interim orders by the arbitral tribunal
Under section 17, the arbitral tribunal has the power to order interim measures of protection. However, the
efficacy of section 17 is seriously compromised given the lack of any suitable statutory mechanism for the
enforcement of such interim orders of the arbitral tribunal.
Hence, the Commission has, recommended amendments to section 17 of the Act which would give teeth to the
orders of the Arbitral Tribunal and the same would be statutorily enforceable in the same manner as the Orders
of a Court.
8. Interest on Sums Awarded
The issue of compound interest/ future interest remained controversial with divergent decisions i.e. whether the
sum on which post award interest is payable, included the interest accrued till the date of award. The controversy
has been set to rest after the 3 Judge Bench decision in Hyder Consulting vs. Governor of Orissa. in November,
2014 after the report of Law Commission.
So far, thought was that the arbitral tribunal was bound to pay post award statutory interest @ of 18% though it
was discretionary for the tribunal to fix the rate of interest. To keep the rate of interest as per market forces, the
Act is amended and, unless the award otherwise directs, carry interest at 2% per annum more than the current
rate of interest from the date of the award to the date of payment.
9. Arbitrability of fraud and complicated issues
Hitherto, there were divergent views of the Court whether issue of Fraud is arbitratble and hence the Law
Commission Report to bring the entire controversy to rest and make fraud expressly arbitrable and has proposed
insertion of section 16(7), ““(7) The arbitral tribunal shall have the power to make an award or give a ruling
notwithstanding that the dispute before it involves a serious question of law, complicated questions of fact or
allegations of fraud, corruption etc.” Now the fraud can be alleged without having to fear that the allegation would
be used to evade arbitration.
10. Parties to arbitration
The Law Commission in its report stated, “ a party does not necessarily mean only the “signatory” to the
arbitration agreement. In appropriate contexts, a “party” means not just a signatory, but also persons “claiming
through or under” such signatory – for instance, successors-of-interest of such parties, alter-ego’s of such parties
etc.”
Taking a clue from the judgment of the Supreme Court of India in Chloro Controls6, the definition of the word
'party' to an arbitration agreement has been expanded to also include persons claiming through or under such
party and modified section 2(h) as, “party" means a party to an arbitration agreement or any person claiming
through or under such party.
This would mean that going forward, arbitration may not be limited simply to signatories of the arbitration
agreement but even include sub-contractors, back to back contracts etc.
11. Statement of Defence/Counter Claims
The submission of Counter claims was opposed on the ground that they were not referred by the respondent
through the appointing authority. Hence, to save the time and it falls within the scope of arbitration agreement,
a new explanation to sec23 has been introduced, “
Explanation: In his defence the respondent may also submit a counter claim or plead a set off, which shall be
treated as being within the scope of reference and be adjudicated upon by the arbitral tribunal notwithstanding
that it may not fall within the scope of the initial reference to arbitration, but provided it falls within the scope of
the arbitration agreement.
12. Appointment of an arbitrator(Administrative/Judicial Powers)
The Law Commission Report proposes to make appointment of an arbitrator an administrative decision to be
carried out by the High Court or the Supreme Court, as the case may be. As per S.B.P. vs. Patel Engineering
decision, the decision of the Chief Justice was held to be a Judicial decision taking away the powers of the
tribunal to decide its own jurisdiction under Sec16 when the appointment of the Arbitrator was made by Courts
under sec 11. The decision of SBP case had also been differently interpreted in different ways i.e. very stale
and dead claims and controversial dead claims etc.
To set the controversy at rest and save the burden of the Courts in dealing with number of applications for the
appointment of arbitral tribunals, the Explanation has been added in Section 11 i.e.
Explanation 1: If the High Court is prima facie satisfied regarding the existence of an arbitration agreement, it
shall refer the parties to arbitration and leave the final determination of the existence of the arbitration
agreement to the arbitral tribunal in accordance with section 16, which shall decide the same as a preliminary
issue.
Explanation 2: For the removal of any doubt, it is clarified that reference by the High Court to any person or
institution designated by it shall not be regarded as a delegation of judicial power.
Explanation 3: The High Court may take steps to encourage the parties to refer the disputes to institutionalized
arbitration by a professional Indian or International Arbitral Institute.
Conclusion
The Law Commission Report attempts to streamline the alternative dispute resolution process to expedite the
settlement of disputes, rationalization of costs, impartiality/independence of arbitrators, time bound decisions by
Courts/Arbitral Tribunals, avoidance of unnecessary adjournment and dilatory tactics, the predictability of the
law etc. This is likely to arrest the flow of arbitration cases outside India to great extent due to the confidence
measures through the amendments.
However, to what extent the amendments will affect the outcome, shall depend how the Courts interpret the
Law after the amendments which the time to come shall only tell but it is definitely a positive step in the
direction of alternative dispute resolution in India.
It would be my pleasure to have an interaction to exchange the views if interested in the topic on
arbitration.
(M.K.Gupta)
Executive Director
Engineering Projects (India) Limited
9899300900 mkg_irse83@yahoo.co.in

More Related Content

What's hot

What are the key elements of the companies (amendment) bill, 2020
What are the key elements of the companies (amendment) bill, 2020What are the key elements of the companies (amendment) bill, 2020
What are the key elements of the companies (amendment) bill, 2020DVSResearchFoundatio
 
Union Budget 2021: Clause by Clause Analysis of Direct Tax Provisions
Union Budget 2021: Clause by Clause Analysis of Direct Tax ProvisionsUnion Budget 2021: Clause by Clause Analysis of Direct Tax Provisions
Union Budget 2021: Clause by Clause Analysis of Direct Tax ProvisionsDVSResearchFoundatio
 
Section - 8 of the Arbitration and Conciliation Act, 1996, A Saving Beacon
Section - 8 of the Arbitration and Conciliation Act, 1996, A Saving BeaconSection - 8 of the Arbitration and Conciliation Act, 1996, A Saving Beacon
Section - 8 of the Arbitration and Conciliation Act, 1996, A Saving BeaconSinghania2015
 
Recovering costs in legal proceedings: a victory for in-house counsel
Recovering costs in legal proceedings: a victory for in-house counselRecovering costs in legal proceedings: a victory for in-house counsel
Recovering costs in legal proceedings: a victory for in-house counselShoosmiths LLP
 
Law-Exchange.co.uk Shared Resource
Law-Exchange.co.uk Shared ResourceLaw-Exchange.co.uk Shared Resource
Law-Exchange.co.uk Shared Resourcelawexchange.co.uk
 
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...DVSResearchFoundatio
 
ITT for 2013 face-to-face Legal Aid Contracts
ITT for 2013 face-to-face Legal Aid ContractsITT for 2013 face-to-face Legal Aid Contracts
ITT for 2013 face-to-face Legal Aid ContractsPatrick Torsney
 
What falls within the ambit of Royalty?
What falls within the ambit of Royalty?What falls within the ambit of Royalty?
What falls within the ambit of Royalty?DVSResearchFoundatio
 
Aw burlington pres_icm_workingwithhceos
Aw burlington pres_icm_workingwithhceosAw burlington pres_icm_workingwithhceos
Aw burlington pres_icm_workingwithhceosBurlington Group
 
Multilateral instrument (MLI) Final provisions [Articles 27-39]
Multilateral instrument (MLI) Final provisions [Articles 27-39]Multilateral instrument (MLI) Final provisions [Articles 27-39]
Multilateral instrument (MLI) Final provisions [Articles 27-39]DVSResearchFoundatio
 
Godfrey Morgan v Cobalt
Godfrey Morgan v CobaltGodfrey Morgan v Cobalt
Godfrey Morgan v CobaltMurray Grant
 
WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA
WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA
WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA DVSResearchFoundatio
 
Service tax - employer vs employee
Service tax  - employer vs employeeService tax  - employer vs employee
Service tax - employer vs employeeSoumyaranjan Biswal
 
Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...
Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...
Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...DVSResearchFoundatio
 
Eo1008 creating arbitration machinery for phil cons.industry
Eo1008 creating arbitration machinery for phil cons.industryEo1008 creating arbitration machinery for phil cons.industry
Eo1008 creating arbitration machinery for phil cons.industryjbonvier
 
Analysis of "Fees for Technical Services" and its Taxability
Analysis of "Fees for Technical Services" and its TaxabilityAnalysis of "Fees for Technical Services" and its Taxability
Analysis of "Fees for Technical Services" and its TaxabilityDVSResearchFoundatio
 
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...DVSResearchFoundatio
 
Arbitration in India- an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India-  an outlook by Rupendra Porwal, RallyMark LegalArbitration in India-  an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India- an outlook by Rupendra Porwal, RallyMark LegalRupendra Porwal
 

What's hot (20)

Vanhi
VanhiVanhi
Vanhi
 
What are the key elements of the companies (amendment) bill, 2020
What are the key elements of the companies (amendment) bill, 2020What are the key elements of the companies (amendment) bill, 2020
What are the key elements of the companies (amendment) bill, 2020
 
Union Budget 2021: Clause by Clause Analysis of Direct Tax Provisions
Union Budget 2021: Clause by Clause Analysis of Direct Tax ProvisionsUnion Budget 2021: Clause by Clause Analysis of Direct Tax Provisions
Union Budget 2021: Clause by Clause Analysis of Direct Tax Provisions
 
Section - 8 of the Arbitration and Conciliation Act, 1996, A Saving Beacon
Section - 8 of the Arbitration and Conciliation Act, 1996, A Saving BeaconSection - 8 of the Arbitration and Conciliation Act, 1996, A Saving Beacon
Section - 8 of the Arbitration and Conciliation Act, 1996, A Saving Beacon
 
Recovering costs in legal proceedings: a victory for in-house counsel
Recovering costs in legal proceedings: a victory for in-house counselRecovering costs in legal proceedings: a victory for in-house counsel
Recovering costs in legal proceedings: a victory for in-house counsel
 
Law-Exchange.co.uk Shared Resource
Law-Exchange.co.uk Shared ResourceLaw-Exchange.co.uk Shared Resource
Law-Exchange.co.uk Shared Resource
 
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
 
ITT for 2013 face-to-face Legal Aid Contracts
ITT for 2013 face-to-face Legal Aid ContractsITT for 2013 face-to-face Legal Aid Contracts
ITT for 2013 face-to-face Legal Aid Contracts
 
Public issue of debentures
Public issue of debenturesPublic issue of debentures
Public issue of debentures
 
What falls within the ambit of Royalty?
What falls within the ambit of Royalty?What falls within the ambit of Royalty?
What falls within the ambit of Royalty?
 
Aw burlington pres_icm_workingwithhceos
Aw burlington pres_icm_workingwithhceosAw burlington pres_icm_workingwithhceos
Aw burlington pres_icm_workingwithhceos
 
Multilateral instrument (MLI) Final provisions [Articles 27-39]
Multilateral instrument (MLI) Final provisions [Articles 27-39]Multilateral instrument (MLI) Final provisions [Articles 27-39]
Multilateral instrument (MLI) Final provisions [Articles 27-39]
 
Godfrey Morgan v Cobalt
Godfrey Morgan v CobaltGodfrey Morgan v Cobalt
Godfrey Morgan v Cobalt
 
WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA
WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA
WITHHOLDING ON GRATUITY PAYMENT SUPREME COURT OF INDIA
 
Service tax - employer vs employee
Service tax  - employer vs employeeService tax  - employer vs employee
Service tax - employer vs employee
 
Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...
Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...
Deduction of Leave Encashment on Payment Basis: Analysis of SC Ruling Union o...
 
Eo1008 creating arbitration machinery for phil cons.industry
Eo1008 creating arbitration machinery for phil cons.industryEo1008 creating arbitration machinery for phil cons.industry
Eo1008 creating arbitration machinery for phil cons.industry
 
Analysis of "Fees for Technical Services" and its Taxability
Analysis of "Fees for Technical Services" and its TaxabilityAnalysis of "Fees for Technical Services" and its Taxability
Analysis of "Fees for Technical Services" and its Taxability
 
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
Arrangements, Reconstructions and Amalgamations under Singapore Companies Act...
 
Arbitration in India- an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India-  an outlook by Rupendra Porwal, RallyMark LegalArbitration in India-  an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India- an outlook by Rupendra Porwal, RallyMark Legal
 

Similar to Proposed radical changes a & c 1996

Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...
Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...
Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...Allen Matkins
 
Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)SME Technologist
 
Regulatory Update - 10 December 2015.PDF
Regulatory Update - 10 December 2015.PDFRegulatory Update - 10 December 2015.PDF
Regulatory Update - 10 December 2015.PDFBen Wong
 
Recovery_from_insurers_under_the_s601AG_of
Recovery_from_insurers_under_the_s601AG_ofRecovery_from_insurers_under_the_s601AG_of
Recovery_from_insurers_under_the_s601AG_ofRyan Tozer
 
15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.Andrew Downie
 
NCLT- Will it live up to its promise
NCLT- Will it live up to its promiseNCLT- Will it live up to its promise
NCLT- Will it live up to its promisePrachi Narang
 
Bar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptxBar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptxphilipjamero
 
Corporate Restructuring Benefits of the Companies Act 2014
Corporate Restructuring Benefits of the Companies Act 2014 Corporate Restructuring Benefits of the Companies Act 2014
Corporate Restructuring Benefits of the Companies Act 2014 Jim Stafford
 
Can ATE be available for an arbitration claim? MLM 27
Can ATE be available for an arbitration claim? MLM 27Can ATE be available for an arbitration claim? MLM 27
Can ATE be available for an arbitration claim? MLM 27Demi Edmunds
 
A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016Mahesh Gupta
 
Public matters newsletter, June 2014
Public matters newsletter, June 2014Public matters newsletter, June 2014
Public matters newsletter, June 2014Browne Jacobson LLP
 
Recent Amendments to the Commercial Division Rules_MFD_GCW
Recent Amendments to the Commercial Division Rules_MFD_GCWRecent Amendments to the Commercial Division Rules_MFD_GCW
Recent Amendments to the Commercial Division Rules_MFD_GCWGracie C. Wright
 
Arbitration In India
Arbitration In IndiaArbitration In India
Arbitration In IndiaMANSI DHINGRA
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Pierrette Khoury BComm/B Laws, GDLP
 
role of judiciary in promoting ADR
role of judiciary in promoting ADRrole of judiciary in promoting ADR
role of judiciary in promoting ADRsteffz
 

Similar to Proposed radical changes a & c 1996 (20)

Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...
Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...
Recon 2011: Recapping New Laws from 2010 and The Who When and What to Expect...
 
Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)
 
ORDINANCE 2015
ORDINANCE 2015ORDINANCE 2015
ORDINANCE 2015
 
Regulatory Update - 10 December 2015.PDF
Regulatory Update - 10 December 2015.PDFRegulatory Update - 10 December 2015.PDF
Regulatory Update - 10 December 2015.PDF
 
Recovery_from_insurers_under_the_s601AG_of
Recovery_from_insurers_under_the_s601AG_ofRecovery_from_insurers_under_the_s601AG_of
Recovery_from_insurers_under_the_s601AG_of
 
15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.
 
GLCMANTHAN
GLCMANTHANGLCMANTHAN
GLCMANTHAN
 
NCLT- Will it live up to its promise
NCLT- Will it live up to its promiseNCLT- Will it live up to its promise
NCLT- Will it live up to its promise
 
Bar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptxBar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptx
 
Corporate Restructuring Benefits of the Companies Act 2014
Corporate Restructuring Benefits of the Companies Act 2014 Corporate Restructuring Benefits of the Companies Act 2014
Corporate Restructuring Benefits of the Companies Act 2014
 
Can ATE be available for an arbitration claim? MLM 27
Can ATE be available for an arbitration claim? MLM 27Can ATE be available for an arbitration claim? MLM 27
Can ATE be available for an arbitration claim? MLM 27
 
A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016
 
ICLR_2016_Part_3_Skaik_FINAL
ICLR_2016_Part_3_Skaik_FINALICLR_2016_Part_3_Skaik_FINAL
ICLR_2016_Part_3_Skaik_FINAL
 
Fast track procedure
Fast track procedureFast track procedure
Fast track procedure
 
Public matters newsletter, June 2014
Public matters newsletter, June 2014Public matters newsletter, June 2014
Public matters newsletter, June 2014
 
Recent Amendments to the Commercial Division Rules_MFD_GCW
Recent Amendments to the Commercial Division Rules_MFD_GCWRecent Amendments to the Commercial Division Rules_MFD_GCW
Recent Amendments to the Commercial Division Rules_MFD_GCW
 
Technical claims brief march 2010
Technical claims brief   march 2010Technical claims brief   march 2010
Technical claims brief march 2010
 
Arbitration In India
Arbitration In IndiaArbitration In India
Arbitration In India
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
role of judiciary in promoting ADR
role of judiciary in promoting ADRrole of judiciary in promoting ADR
role of judiciary in promoting ADR
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerapareshmondalnita
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Electivekarthi keyan
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxCenterEnamel
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 

Proposed radical changes a & c 1996

  • 1. Proposed radical changes in,“The Arbitration & Conciliation Act, 1996” Preface The Law Commission vide its Report No. 246 has proposed various amendments to the Arbitration and Conciliation Act 1996. The Hon’ble President of India promulgated THE ARBITRATION AND CONCILIATION (AMENDMENT) ORDINANCE, 2015 on 23rd October, 2015. Considering the eagerness of the Govt. to reduce fruitless litigation, instill confidence in foreign investors, the proposed amendment to the Arbitration and Conciliation Act promulgated as an ordinance as the parliament was not in session. The proposed amendments to the said Act will bring major revolution to the Arbitration process (procedural as well as statutory) deviating from the existing act in many aspects. There is bound to be frequent discussions at various forums i.e. by Legal experts and Institutions through seminars, papers and Lectures etc. for reaching the consensus. However, the Law shall take a clear shape only after the various judgments in the litigation consequent to the introduction of the amendments to the Act while the Institutions/Legal Society etc. have to be in readiness to cope up with the changing environment. The main objective of the amendment to the Act are namely, expediting of the arbitration cases delayed inordinately, limiting the cost of arbitration (although debatable), discouragement to frivolous claims, independent/impartial arbitrators, encouragement to Institutional Arbitration, making India friendly arbitration seat to stop flying of cases to Singapore and other countries, diluting the stringent Conditions of Contract , jurisdiction of arbitrator, challenge of award and various other aspects. The salient amendments with their objective and consequences, the deviation from the existing Act and its effect on the existing Arbitration process and the various concerns are as follows: 1. Time bound Arbitration (avoidance of delays) Hitherto, there was no time limit for the Arbitrators to expedite the arbitration process. Now it will be mandatory for the arbitrator to make a disclosure of their ability to devote sufficient time to complete the arbitration proceedings and publish the award expeditiously. (24 months for arbitration proceedings and 3 months for publication of award). The arbitral tribunal has also been empowered to impose costs for frequent and unnecessary adjournments in the light of Salem Advocate Bar Association case. Moreover, the fee being fixed on the basis of amount of claim, the arbitrators shall not unnecessarily prolong the arbitration to continue their meter inordinately. The arbitrators can now decide when the fee is chargeable to them. The fixed fee implies that the arbitrators shall be paid on contract basis instead of daily basis and hence an incentive for them to expedite the case. The Law Commission Report provides that an application challenging the award, be endeavored to be disposed of expeditiously and in any event within a period of 1 year from the date of service of notice. The Law Commission Report also seeks to deal with each issue in a systematic and analytical manner. Separately, the Law Commission Report also recommends that specialized and dedicated arbitration benches be constituted (as done in the Delhi High Court). It is also provided that such an application (appointment of arbitrator u/s 11) be endeavored to be disposed of expeditiously, and requires the Court to make an endeavor to dispose of the matter within 60 days from the service of notice on the opposite party. The above changes shall discipline the arbitrators and the parties to expedite the whole process and to take the arbitration sincerely. The amendment doesn’t specify the action/remedy if the process is not completed within 24 months i.e. the mandate of the tribunal shall be terminated or the parties can agree to extend the time period. 2. Fees & Costs Supreme Court in one of its judgment observed that the cost of arbitration can be high if the arbitral tribunal consists of retired Judges and many a times exceeding the amount of dispute. Hence, the amendment specifies the model fee schedule for guidance. The prescribed fees are not mandatory and applicable only in the case of, fee not fixed by the parties. It is apprehended that the arbitral tribunal shall henceforth fix the fee as per the model fee taking it as a moral support and it would be quite embarrassing for either of the parties to contest the fee fixed by the arbitral tribunal. This introduction will not in any way lead to the reduction of fees by retired
  • 2. judges but instead cause the fee of the Non retired Judges arbitrators increase abnormally e.g. if the total claim of Claims and Counter claims is Rs.40.0 crore (say), the cost of arbitration as per model fee structure shall be approx. Rs.30.0 lakhs. In some cases, the arbitrator may simply decide in 2 to 3 hearings that the tribunal has no jurisdiction due to limitation or accord and satisfaction. Sometimes, the cost of claims may be quite high but the issue may not be so complex to require many hearings for adjudication but the fee has been kept uniform. There has to be some connection of fee with the number of hearings and the amount of claim. The model fee prescribed by the Law commission is as follows: Sum in Dispute (Rs.) Model Fees (Indicative) Upto Rs. 5,00,000/- Rs. 45,000/- Above Rs. 5,00,000/- and upto Rs. 20,00,000/- Rs. 45,000/- + 3.5% of the claim amount over and above Rs. 5,00,000/- Above Rs. 20,00,000/- and upto Rs. 1,00,00,000/- Rs. 97,500/- + 3% of the claim amount over and above Rs. 20,00,000/- Above Rs. 1,00,00,000/- and upto Rs. 10,00,00,000/- Rs. 3,37,500/- + 1% of the claim amount over and above Rs. 1,00,00,000/- Above Rs. 10,00,00,000/- and upto Rs. 20,00,00,000/- Rs. 12,37,500/- + 0.75% of the claim amount over and above Rs. 1,00,00,000/- Above Rs. 20,00,00,000/- Rs. 19,87,500/- + 0. 5% of the claim amount over and above Rs. 20,00,00,000/- with a ceiling of Rs. 30,00,000/- * In the event, the arbitrator to be appointed is a Sole Arbitrator, he shall be entitled to an additional amount of 25% on the fee payable as per the table set out above. It would be advisable to fix the fee of the arbitrators while drafting the arbitration agreement so that there is check on unusual high fee in view of the subject to clause still existing in the proposed amended Act. Even if one of the parties has the right to appoint the arbitrator, the fees must be fixed in the arbitration agreement so that in the eventuality of appointment of arbitrators by the High Court, the fees remain unchanged. A new sub-section, ”Regime for costs” has been introduced for cost payable by one party to another, though not mandatory, but recommendatory since it is the liberal attitude of the tribunals of not awarding costs. This leads to frivolous points being raised in appeals or frivolous appeals being filed in the courts. The general rule would be that the unsuccessful party will be ordered to pay the cost to the successful party but for contrary decision, reasons will have to be recorded in writing. Other circumstances i.e. frivolous claims/counter claims, adjournments, dilatory tactics, effort to settle the case etc. shall be kept into consideration. The above principle ensures that the “costs follow the event” regime governs all arbitrations/ arbitration related court litigation. Such a regime would disincentivize frivolous proceedings and inequitable conduct. The basis of the above provisions is Rule 44 of the Civil Procedure Rules of England. 3. Independence/Impartiality of arbitrators The Law Commission Report has proposed amendments requiring mandatory written disclosures from the prospective arbitrator(s) with regard to any circumstances which is likely to give rise to justifiable doubts as to his independence or impartiality such as the existence either direct or indirect, of any past or present relationship with or interest in any of the parties or in relation to the subject matter in dispute, whether financial, business, professional or other kind. (Introduced Fourth, Fifth, Sixth and Seventh Schedule). There is an express bar of certain persons though waivable but only subsequent to the dispute. i.e. even if the parties have mutually agreed for appointment of such arbitrators, they shall not be eligible to be appointed as arbitrator provided that the parties subsequent to the dispute waive the provision by an express agreement in writing. So far the Courts have held the appointment of arbitrators by one of the parties who may be their employees, Counsel etc. Originally this practice was followed by Govt. dept. But of late, the same practice has been followed by Private Institutions and even Real Estate firms with the Buyers.
  • 3. This is a welcome step in view of the Principle of Natural Justice. The list though very exhaustive, but still there shall be disputes as regard to present/past relationship and interpretation for inclusion/exclusion of certain impartiality. However, the time is not far off when the liberty to appoint the arbitrator by one party alone shall also cease as there are still chances that the arbitrator appointed by one party alone shall have the soft corner towards the party appointing him as an arbitrator. 4. Institutional arbitration The Law Commission Report has laid stress on institutional arbitration since its structured procedure and administrative support provides it the distinct advantages, which are unavailable to parties opting for ad hoc arbitration. The spread of institutional arbitration however, is minimal in India and has unfortunately not really kick-started. Presently, the Act is institutional arbitration agnostic – meaning thereby, it neither promotes nor discourages parties to consider institutional arbitration. The changes suggested by the Commission attempts to encourage the culture of institutional arbitration in India, which the Commission feels will go a long way to redress the institutional and systemic malaise that has seriously affected the growth of arbitration. The Commission has, therefore, recommended the addition of Explanation 3 to section 11(6A) of the Act with the hope that High Courts and the Supreme Court, while acting in the exercise of their jurisdiction under section 11 of the Act will take steps to encourage the parties to refer their disputes to institutionalized arbitration. Explanation 3: The High Court may take steps to encourage the parties to refer the disputes to institutionalized arbitration by a professional Indian or International Arbitral Institute. Similarly, the Commission seeks to accord legislative sanction to rules of institutional arbitration which recognize the concept of an “emergency arbitrator” – and the same has been done by broadening the definition of an “arbitral tribunal” under section 2(d). The Government may also consider formation of a specialized body, like an Arbitral Commission of India, which has representation from all the stakeholders of arbitration and which could be entrusted with the task of, inter alia, encouraging the spread of institutional arbitration in the country. To name the few, ICA (Indian Council of Arbitration) associated with FICCI, Indian Road Congress, Nani Palkhivala Arbitration Centre are already working and many more may come in the near future depending upon the location and the subject matter. The retired Govt. servants, Judges, Lawyers can contribute to the dispute resolution in their fields by participating in such Institutions. 5. Setting aside of award The challenge of awards and uncertainty in the courts had increased drastically after the decision of ONGC vs. Saw Pipes Ltd. The Supreme Court held in Shri Lal Mahal case that the expansive construction accorded to the term “public policy” cannot apply in foreign awards. However, the proposed amendment has further restricted the scope of setting aside the award on the ground of conflict with public policy i.e. (a) the making of the award was induced of affected by fraud or corruption or was in violation of section 75 or section 81; or (b) it is in contravention with the fundamental policy of Indian law; or (c) it is in conflict with the most basic notions of morality or justice. The restricted provisions seeking to set aside or challenge the enforcement of arbitral awards will instill greater confidence in arbitration as an effective and speedy dispute resolution mechanism for finality. As per the proposed provisio, the award cannot be set aside merely on the ground of an erroneous application of the law or by re-appreciating evidence. Hence, the arbitrators shall be required to take extreme judicial care preferably having insight of Law aspects as such award may henceforth go unchecked. Hitherto, as per the decision in ONGC vs. Saw Pipes the awards could be set aside if the same were not in accordance with the terms of the Contract. This has been diluted and as per amendment, the tribunal shall decide having regard to the terms of the contract indicating that term of contract are not mandatory . How the Tribunals and Courts shall interpret, “regard to the terms of the contract” will get clear in the time to come.
  • 4. 6. Automatic stay of enforcement (likely to be amended) The Supreme Court in National Aluminium observed, “However, we do notice that this automatic suspension of the execution of the award, the moment an application challenging the said award is filed under section 34 of the Act leaving no discretion in the court to put the parties on terms, in our opinion, defeats the very objective of the alternate dispute resolution system to which arbitration belongs._ _ _ _” Accordingly sub-section 36(2) has been added which states that the filing of such an application shall not by itself render the award unenforceable, unless upon a separate application made for that purpose, the Court grants stay of the operation of the award in accordance with the provisions of sub-section(3) hereof,”. The Courts may also direct the applicants to deposit the award amount or portion thereof prior to any stay of the award being granted, thus reducing the incentive to litigate. 7. Interim orders by the arbitral tribunal Under section 17, the arbitral tribunal has the power to order interim measures of protection. However, the efficacy of section 17 is seriously compromised given the lack of any suitable statutory mechanism for the enforcement of such interim orders of the arbitral tribunal. Hence, the Commission has, recommended amendments to section 17 of the Act which would give teeth to the orders of the Arbitral Tribunal and the same would be statutorily enforceable in the same manner as the Orders of a Court. 8. Interest on Sums Awarded The issue of compound interest/ future interest remained controversial with divergent decisions i.e. whether the sum on which post award interest is payable, included the interest accrued till the date of award. The controversy has been set to rest after the 3 Judge Bench decision in Hyder Consulting vs. Governor of Orissa. in November, 2014 after the report of Law Commission. So far, thought was that the arbitral tribunal was bound to pay post award statutory interest @ of 18% though it was discretionary for the tribunal to fix the rate of interest. To keep the rate of interest as per market forces, the Act is amended and, unless the award otherwise directs, carry interest at 2% per annum more than the current rate of interest from the date of the award to the date of payment. 9. Arbitrability of fraud and complicated issues Hitherto, there were divergent views of the Court whether issue of Fraud is arbitratble and hence the Law Commission Report to bring the entire controversy to rest and make fraud expressly arbitrable and has proposed insertion of section 16(7), ““(7) The arbitral tribunal shall have the power to make an award or give a ruling notwithstanding that the dispute before it involves a serious question of law, complicated questions of fact or allegations of fraud, corruption etc.” Now the fraud can be alleged without having to fear that the allegation would be used to evade arbitration. 10. Parties to arbitration The Law Commission in its report stated, “ a party does not necessarily mean only the “signatory” to the arbitration agreement. In appropriate contexts, a “party” means not just a signatory, but also persons “claiming through or under” such signatory – for instance, successors-of-interest of such parties, alter-ego’s of such parties etc.” Taking a clue from the judgment of the Supreme Court of India in Chloro Controls6, the definition of the word 'party' to an arbitration agreement has been expanded to also include persons claiming through or under such party and modified section 2(h) as, “party" means a party to an arbitration agreement or any person claiming through or under such party. This would mean that going forward, arbitration may not be limited simply to signatories of the arbitration agreement but even include sub-contractors, back to back contracts etc.
  • 5. 11. Statement of Defence/Counter Claims The submission of Counter claims was opposed on the ground that they were not referred by the respondent through the appointing authority. Hence, to save the time and it falls within the scope of arbitration agreement, a new explanation to sec23 has been introduced, “ Explanation: In his defence the respondent may also submit a counter claim or plead a set off, which shall be treated as being within the scope of reference and be adjudicated upon by the arbitral tribunal notwithstanding that it may not fall within the scope of the initial reference to arbitration, but provided it falls within the scope of the arbitration agreement. 12. Appointment of an arbitrator(Administrative/Judicial Powers) The Law Commission Report proposes to make appointment of an arbitrator an administrative decision to be carried out by the High Court or the Supreme Court, as the case may be. As per S.B.P. vs. Patel Engineering decision, the decision of the Chief Justice was held to be a Judicial decision taking away the powers of the tribunal to decide its own jurisdiction under Sec16 when the appointment of the Arbitrator was made by Courts under sec 11. The decision of SBP case had also been differently interpreted in different ways i.e. very stale and dead claims and controversial dead claims etc. To set the controversy at rest and save the burden of the Courts in dealing with number of applications for the appointment of arbitral tribunals, the Explanation has been added in Section 11 i.e. Explanation 1: If the High Court is prima facie satisfied regarding the existence of an arbitration agreement, it shall refer the parties to arbitration and leave the final determination of the existence of the arbitration agreement to the arbitral tribunal in accordance with section 16, which shall decide the same as a preliminary issue. Explanation 2: For the removal of any doubt, it is clarified that reference by the High Court to any person or institution designated by it shall not be regarded as a delegation of judicial power. Explanation 3: The High Court may take steps to encourage the parties to refer the disputes to institutionalized arbitration by a professional Indian or International Arbitral Institute. Conclusion The Law Commission Report attempts to streamline the alternative dispute resolution process to expedite the settlement of disputes, rationalization of costs, impartiality/independence of arbitrators, time bound decisions by Courts/Arbitral Tribunals, avoidance of unnecessary adjournment and dilatory tactics, the predictability of the law etc. This is likely to arrest the flow of arbitration cases outside India to great extent due to the confidence measures through the amendments. However, to what extent the amendments will affect the outcome, shall depend how the Courts interpret the Law after the amendments which the time to come shall only tell but it is definitely a positive step in the direction of alternative dispute resolution in India. It would be my pleasure to have an interaction to exchange the views if interested in the topic on arbitration. (M.K.Gupta) Executive Director Engineering Projects (India) Limited 9899300900 mkg_irse83@yahoo.co.in