Project-Fit Blueprint
Client: <Insert client name>
Project: <Insert project name>
2
TABLE OF CONTENTS
1. INTRODUCTION 3
1.1. Document Purpose 3
1.2. Complimentary Documents 3
2. PROJECT OVERVIEW 4
2.1. Background 4
2.2. Current Situation 4
2.3. Business Justification 4
2.4. Project Objectives 4
2.5. Project Approach 4
2.6. Task Management Tool 4
3. ASSIGNED RESOURCES 5
4. PROGRAM GOVERNANCE 6
5. ROADMAP & PRODUCTS 7
5.1. Roadmap 7
5.2. Products 7
5.3. Transactional Relationship 9
5.4. Data Center(s) 9
6. PHASE OVERVIEW 10
6.1. Phase 1 10
7. USE CASES 10
8. FUNCTIONAL REQUIREMENTS 12
9. APPLICATION OF CONSENT RECOMMENDED PRACTICES 13
8. KEY MILESTONES 13
9. SAP CUSTOMER DATA CLOUD WORK PACKAGES 14
9.1. Project Exclusions 14
9.2. Risks 15
9.3. Project Controls 15
9.4. Scope Change and Project Tolerance 15
10. CLIENT SIGN OFF 15
3
1. INTRODUCTION
1.1. Document Purpose
This Project-fit Blueprint is created specifically for <Client Name> (hereinafter referred to as “Client”) and intends
to align all resources on high-level information for <Project Name>. Information in this document includes but is
not limited to project scope, resources and schedules.
1.2. Complimentary Documents
To complement this Project-fit Blueprint, the below Client-specific documents are also available:
The Technical Design Document provides details on the recommended architecture, configuration and
development design strategy. It is intended for technical resources.
The Config & Data Mapping Tracker includes recommended configurations, implementation policies and data field
mapping for the migration exercise.
The Project-fit Blueprint is intended to be a static document. As such, amendments to the scope and plan which
did not impact the scheduled hours will be recorded in the Change Control Document.
Amendments which alter the allocated hours requires a Change Order. Contact your Implementation Consult for
Change Orders.
Technical Design Document <hyperlink>
Config & Data MappingSheet <hyperlink>
Change Control Document <hyperlink>
4
2. PROJECT OVERVIEW
2.1. Background
Give context on the client and why this project is happening.
2.2. Current Situation
Describe what functionality their site currently has.
2.3. Business Justification
Provide a clear concise description of the issue(s) that need(s) to be addressed by SAP Customer Data Cloud
2.4. Project Objectives
What is this project looking to accomplish? What defines the project as successful?
2.5. Project Approach
Waterfall, Iterative, etc?
2.6. Task Management Tool
What task management tool will Client and SAP Customer Data Cloud use (i.e. TeamWork)
5
3. ASSIGNED RESOURCES
The following are resources which are directly assigned to plan, consult or build on the project.
Organization Name Role Responsibilities
SAP Customer
Data Cloud
EX: John Doe Implementation Consultant Primary contact, managing
resources, project plans, strategy
and the over all implementation
SAP Customer
Data Cloud
Technical Consultant Dedicated technical resource,
consulting on technical strategy and
implementation
EX: Client Org
EX: Client Org
6
4. PROGRAM GOVERNANCE
In the event of an escalation, contact the following individuals
Organization Name Role Responsibilities
SAP Customer
Data Cloud
EX: John Doe Account Manager All escalated issues
EX: Client Org Deviation from scope
EX: Client Org Approvals
EX: Client Org Scheduling changes
7
5. ROADMAP & PRODUCTS
5.1. Roadmap
Features will be implemented in a phased approach as outlined below.
Example:
5.2. Products
The following highlights the standard product capabilities, by phase. Click the product name for a full description
of the standard product. Specific implementation decisions and guidance are recorded in the Technical Design
Document.
Phase/s Identity Products and Services
1,3
User Migration
SAP Customer Data Cloud performs an import of Client’s existing database and will consult on
the schema design. To achieve this import, Client must export data from the current database,
and provide SAP Customer Data Cloud with necessary information such as password hashing,
test users, etc.
1,2,3
Consent Management
Manage user consent for ToS, PP, and other custom consent. Allow for initial consent, re-
consent, version management, user transparency and control.
1,2,3
Lite Registration
Store user emails without passwords for use-cases like newsletter subscriptions and
sweepstakes.
8
1,2,3
Registration-as-a-Service (RaaS)
RaaS is a complete set of tools for integrating end-to-end registration.
Core workflows that are available as standard within the UI Builder are:
● Registration: new users can register on to the Website or Mobile Apps
● Login: existing users can login to their account using known credentials
● Link Accounts: users can link accounts between a social and email profile, if the user
tries to register with one, and SAP Customer Data Cloud identifies that the email
already exists in the other.
● Reset Password: when forgotten, users can create a new password
1,2,3
Site Grouping or Single Sign-on
Allows for multiple sites to have shared configurations or user sessions.
1,2,3
Federation
Federation uses the SAML protocol to allow users seamless access across your business’
touch-points without having to re-enter or create new usernames and passwords, regardless of
whether these touch-points are managed by third parties or do not share a database.
1,2,3
IdentitySync
As a one-time or recurring job, IdentitySync allows data to transfer between two platforms in
bulk
1
Profile Management
Collects and manages your entire customer base in a secure, cloud-hosted repository.
1
Identity Access
Easily manage high volumes of user records and get a complete view of any customer within
your database from a user-friendly dashboard.
1
Identity Compliance
Eliminate the complexities of managing various data laws and social network policies through
features such as automatic account deletion and user data controls.
1
Analytics
Access more than 20 key reports, including new users, demographics and referred traffic, to
better understand your audience and measure on-site behaviors.
1
Customer Insights
Visualize the first-party demographic data of any user who connects with your brand, including
his or her age, gender, relationship status, location and more.
1
Customer Insights Plus
Gain a deeper understanding of your customers with the ability to view their Facebook Likes,
favorite brands, media preferences and more.
1,3
User Migration
SAP Customer Data Cloud performs an import of Client’s existing database and will consult on
the schema design. To achieve this import, Client must export data from the current database,
and provide SAP Customer Data Cloud with necessary information such as password hashing,
test users, etc.
9
Phase/s Identity Products and Services
1,2,3
Social Share Bar
Allow users to share content from your site and into their social stream.
1,2,3
Comments or Ratings & Review Import
SAP Customer Data Cloud performs an import of Client’s existing comments/reviews and will
consult on the schema design. To achieve this import, Client must export data from the current
database, and provide SAP Customer Data Cloud with any necessary information.
1,2,3
Comments
RaaS is a complete set of tools for integrating end-to-end registration.
Core workflows that are available as standard within the UI Builder are:
● Registration - a new user can register on to the Website or Mobile Apps
● Login - existing users can login to their account using known credentials
● Link Accounts - users can link accounts between a social and email profile, if the user
tries to register with one, and SAP Customer Data Cloud identifies that the email
already exists in the other.
● Reset Password - when forgotten, users can create a new password
1,2,3
Ratings & Review
Allow users to rate and comment on products within your site, with an option to share to their
social stream.
5.3. Transactional Relationship
☐ B2C
☐ B2B
☐ B2B2C
☐ B2B2 employee
5.4. Data Center(s)
☐ North America
☐ EU
☐ AU
☐ Russia
☐ China
10
6. PHASE OVERVIEW
6.1. Phase 1
The remainder of this document focuses on <Phase 1,2,3,>
While all technical details are documented in the Technical Design Document<hyperlink> the following is an overview for this
phase.
Option: replace this section by adding content to the Config and Data Mapping Sheet.
Work Description
Data Imports Include # of records and sources
IdentitySync Listthe names and descriptions ofeach integration
Consulton Schema Design Ex: Design consulting for Profile,Preferences and Subscription schemas
Consulton BestPractices Consulton bestdesigns for
7. USE CASES
The Use Case should define whatneeds to happen upon a particular action in order for that action to be completed
successfully.The use case should outline all thatis needed for a particular process to succeed and also outlines all the
participants involved in it.
Use Case Name Provide name for Use Case
Summary Provide a general overview/summary of the Use Case along with the goal to be achieved
Assumptions Any assumptions that are implicit in the definition of the Use Case
Participants The person(s) who will perform each of the steps described in this use case
Preconditions These are the conditions that need to be met to ensure that the use case can be fulfilled.
If these conditions are not met then the case cannot run its course. For example:
● The website needs to be accessible by the customer
● Age requirement-verification of 18+
Description/
Steps
Steps and interactions between participants and system that are necessary to achieve
goal
1.
2.
3.
4.
Exceptions Provide description of what happens when a failure occurs in the flow.
11
Recommended
Flows
Provide diagram that defines everything involved in the Use Case.
Note: The below recommended flow examples may not be final
Example #1: Full Registration Flow
Gray: Client-hosted content
Blue: SAP Customer Data Cloud-hosted screens
Example #2: Lite Registration
Green: Social provider-hosted screen
Blue: SAP Customer Data Cloud-hosted screens
12
8. FUNCTIONAL REQUIREMENTS
13
The following sections include a setof tables summarizing the requirements thatapplyfor each use case.All the tables
include the following information for each requirement:
● RequirementID: Unique identifier for the requirement
● Requirement:Description ofthe requirement.
● Type: Indicates whether the requirementis a reference to a standard (Std) or a new requirement(New).
● Feature: Identifies the functional category which the requirementis linked to.
Requirement
ID
Requirement Type Feature Phase Notes
ID001 Ensure data accuracy,
security and privacy with
email and CAPTCHA
verification
Std Registration-as-a-Service 1
ID002 The system shall identify
the
user based on their email
address
Std Lite Registration 1
ID003 Ability to log consent in the
SAP Customer Data Cloud
Consent Vault
Std Consent 1
9. APPLICATION OF CONSENT RECOMMENDED PRACTICES
The below are recommended practices to help safe-guard Client from consent compliance issus. Check off each
item to indicate that the development plan supports these recommendations. Not checking off a practice may
require written acknowledgement of the below decisions.
Planned Recommended Practice Notes
Ensure data accuracy, security and privacy with email and
CAPTCHA verification
Indicate reasons why it may not be
planned
X SAP Customer Data Cloud serves as the source of truth
Require re-consent for imported users
Only push consented users to marketing applications
Make consent & withdrawal easy for the user
Require re-consent for new PP & ToS
Always authenticate the user
Use real-time imports & ID tracking for proxy consent
Provide lifetime accessibility to legal documents
10. KEY MILESTONES
The following are key milestones which are critical to the project’s success.
Key Milestones Owner Date
14
Ex: Technical Kick-off EX: SAP Customer Data Cloud
EX: Blueprint Workshop EX: SAP Customer Data Cloud
EX: Identity Strategy Workshop EX: SAP Customer Data Cloud
EX: Project-fit Blueprint and Technical Design
Document Delivered
EX: SAP Customer Data Cloud
EX: Start User Migration EX: SAP Customer Data Cloud
11. SAP CUSTOMER DATA CLOUD WORK PACKAGES
Work Packages and Deliverables
Work Package Ex: Project-fit Blueprint and Technical Design Document
Ex: Consult on RaaS, IdentitySync, Consent Management
Ex: Import of users
Description Ex: Creation of integration documents
Ex: Consultation of Client’s UX and technical designs
Ex: Migration of user profile data
Ex: Best practices review
Project hours Ex: Phase 1 is scheduled to utilize 200 of the 750 contracted hours
End deliverable(s) Ex: Project-fit Blueprint and Technical Design Document
11.1. Project Exclusions
● Work not included in the above scope will be considered out of scope of this project.
15
11.2. Risks
● Client is held responsible for development, as recommended by SAP Customer Data Cloud.
● Delay by Client team will result in the project delivery being delayed.
● SAP Customer Data Cloud recommends limiting the number of users that can access the RaaS
screensets (in the Development environment) to control deployments and updates to screensets
and policies.
● SAP Customer Data Cloud will be in code freeze state from November - January. No amendments
(i.e. product features) will be deployed to SAP Customer Data Cloud’s production environment
within this period.
11.3. Project Controls
● Any changes to the scope or plan will result in resource adjustment and possible project delay.
● Any changes to the project that affect scope and/or fees must be documented and agreed to in
writing by both Client and SAP Customer Data Cloud before commencing work; if additional hours
are needed beyond the total authorized in this Blueprint, another Work Order or Change Order
will be required.
● Client and SAP Customer Data Cloud must agree to the project schedules (i.e. sprints) and
systems used to track the project. Access to agreed upon platforms must be provided before
development begins.
11.4. Scope Change and Project Tolerance
● Deviation from the agreed scope, may result in the project being put on hold until a change
assessment has been completed. Scope change will be managed through a change request
process whereby the Implementation Consultant will assess the impact of the change, estimate
the cost and timescales required to implement the change and request sign off from the client.
● Agreed timelines and scope rely on the following:
a. Timely supply of any documentation and assets from client or third
parties as agreed in the above document.
b. Timely written feedback and approval of work in progress and final
deliverables according to the agreed project plan.
c. No change to the project scope and deliverables once agreed
d. No change in direction once project deliverables are approved
12. CLIENT SIGN OFF
16
The undersigned acknowledge they have reviewed the <Project Name> plan and agree with the approach it
presents. Changes to this Project-fit Blueprint will be coordinated with and approved by the undersigned or their
designated representatives.
Client
Signature
Full Name
Title
Date

Project-fit Blueprint.docx

  • 1.
    Project-Fit Blueprint Client: <Insertclient name> Project: <Insert project name>
  • 2.
    2 TABLE OF CONTENTS 1.INTRODUCTION 3 1.1. Document Purpose 3 1.2. Complimentary Documents 3 2. PROJECT OVERVIEW 4 2.1. Background 4 2.2. Current Situation 4 2.3. Business Justification 4 2.4. Project Objectives 4 2.5. Project Approach 4 2.6. Task Management Tool 4 3. ASSIGNED RESOURCES 5 4. PROGRAM GOVERNANCE 6 5. ROADMAP & PRODUCTS 7 5.1. Roadmap 7 5.2. Products 7 5.3. Transactional Relationship 9 5.4. Data Center(s) 9 6. PHASE OVERVIEW 10 6.1. Phase 1 10 7. USE CASES 10 8. FUNCTIONAL REQUIREMENTS 12 9. APPLICATION OF CONSENT RECOMMENDED PRACTICES 13 8. KEY MILESTONES 13 9. SAP CUSTOMER DATA CLOUD WORK PACKAGES 14 9.1. Project Exclusions 14 9.2. Risks 15 9.3. Project Controls 15 9.4. Scope Change and Project Tolerance 15 10. CLIENT SIGN OFF 15
  • 3.
    3 1. INTRODUCTION 1.1. DocumentPurpose This Project-fit Blueprint is created specifically for <Client Name> (hereinafter referred to as “Client”) and intends to align all resources on high-level information for <Project Name>. Information in this document includes but is not limited to project scope, resources and schedules. 1.2. Complimentary Documents To complement this Project-fit Blueprint, the below Client-specific documents are also available: The Technical Design Document provides details on the recommended architecture, configuration and development design strategy. It is intended for technical resources. The Config & Data Mapping Tracker includes recommended configurations, implementation policies and data field mapping for the migration exercise. The Project-fit Blueprint is intended to be a static document. As such, amendments to the scope and plan which did not impact the scheduled hours will be recorded in the Change Control Document. Amendments which alter the allocated hours requires a Change Order. Contact your Implementation Consult for Change Orders. Technical Design Document <hyperlink> Config & Data MappingSheet <hyperlink> Change Control Document <hyperlink>
  • 4.
    4 2. PROJECT OVERVIEW 2.1.Background Give context on the client and why this project is happening. 2.2. Current Situation Describe what functionality their site currently has. 2.3. Business Justification Provide a clear concise description of the issue(s) that need(s) to be addressed by SAP Customer Data Cloud 2.4. Project Objectives What is this project looking to accomplish? What defines the project as successful? 2.5. Project Approach Waterfall, Iterative, etc? 2.6. Task Management Tool What task management tool will Client and SAP Customer Data Cloud use (i.e. TeamWork)
  • 5.
    5 3. ASSIGNED RESOURCES Thefollowing are resources which are directly assigned to plan, consult or build on the project. Organization Name Role Responsibilities SAP Customer Data Cloud EX: John Doe Implementation Consultant Primary contact, managing resources, project plans, strategy and the over all implementation SAP Customer Data Cloud Technical Consultant Dedicated technical resource, consulting on technical strategy and implementation EX: Client Org EX: Client Org
  • 6.
    6 4. PROGRAM GOVERNANCE Inthe event of an escalation, contact the following individuals Organization Name Role Responsibilities SAP Customer Data Cloud EX: John Doe Account Manager All escalated issues EX: Client Org Deviation from scope EX: Client Org Approvals EX: Client Org Scheduling changes
  • 7.
    7 5. ROADMAP &PRODUCTS 5.1. Roadmap Features will be implemented in a phased approach as outlined below. Example: 5.2. Products The following highlights the standard product capabilities, by phase. Click the product name for a full description of the standard product. Specific implementation decisions and guidance are recorded in the Technical Design Document. Phase/s Identity Products and Services 1,3 User Migration SAP Customer Data Cloud performs an import of Client’s existing database and will consult on the schema design. To achieve this import, Client must export data from the current database, and provide SAP Customer Data Cloud with necessary information such as password hashing, test users, etc. 1,2,3 Consent Management Manage user consent for ToS, PP, and other custom consent. Allow for initial consent, re- consent, version management, user transparency and control. 1,2,3 Lite Registration Store user emails without passwords for use-cases like newsletter subscriptions and sweepstakes.
  • 8.
    8 1,2,3 Registration-as-a-Service (RaaS) RaaS isa complete set of tools for integrating end-to-end registration. Core workflows that are available as standard within the UI Builder are: ● Registration: new users can register on to the Website or Mobile Apps ● Login: existing users can login to their account using known credentials ● Link Accounts: users can link accounts between a social and email profile, if the user tries to register with one, and SAP Customer Data Cloud identifies that the email already exists in the other. ● Reset Password: when forgotten, users can create a new password 1,2,3 Site Grouping or Single Sign-on Allows for multiple sites to have shared configurations or user sessions. 1,2,3 Federation Federation uses the SAML protocol to allow users seamless access across your business’ touch-points without having to re-enter or create new usernames and passwords, regardless of whether these touch-points are managed by third parties or do not share a database. 1,2,3 IdentitySync As a one-time or recurring job, IdentitySync allows data to transfer between two platforms in bulk 1 Profile Management Collects and manages your entire customer base in a secure, cloud-hosted repository. 1 Identity Access Easily manage high volumes of user records and get a complete view of any customer within your database from a user-friendly dashboard. 1 Identity Compliance Eliminate the complexities of managing various data laws and social network policies through features such as automatic account deletion and user data controls. 1 Analytics Access more than 20 key reports, including new users, demographics and referred traffic, to better understand your audience and measure on-site behaviors. 1 Customer Insights Visualize the first-party demographic data of any user who connects with your brand, including his or her age, gender, relationship status, location and more. 1 Customer Insights Plus Gain a deeper understanding of your customers with the ability to view their Facebook Likes, favorite brands, media preferences and more. 1,3 User Migration SAP Customer Data Cloud performs an import of Client’s existing database and will consult on the schema design. To achieve this import, Client must export data from the current database, and provide SAP Customer Data Cloud with necessary information such as password hashing, test users, etc.
  • 9.
    9 Phase/s Identity Productsand Services 1,2,3 Social Share Bar Allow users to share content from your site and into their social stream. 1,2,3 Comments or Ratings & Review Import SAP Customer Data Cloud performs an import of Client’s existing comments/reviews and will consult on the schema design. To achieve this import, Client must export data from the current database, and provide SAP Customer Data Cloud with any necessary information. 1,2,3 Comments RaaS is a complete set of tools for integrating end-to-end registration. Core workflows that are available as standard within the UI Builder are: ● Registration - a new user can register on to the Website or Mobile Apps ● Login - existing users can login to their account using known credentials ● Link Accounts - users can link accounts between a social and email profile, if the user tries to register with one, and SAP Customer Data Cloud identifies that the email already exists in the other. ● Reset Password - when forgotten, users can create a new password 1,2,3 Ratings & Review Allow users to rate and comment on products within your site, with an option to share to their social stream. 5.3. Transactional Relationship ☐ B2C ☐ B2B ☐ B2B2C ☐ B2B2 employee 5.4. Data Center(s) ☐ North America ☐ EU ☐ AU ☐ Russia ☐ China
  • 10.
    10 6. PHASE OVERVIEW 6.1.Phase 1 The remainder of this document focuses on <Phase 1,2,3,> While all technical details are documented in the Technical Design Document<hyperlink> the following is an overview for this phase. Option: replace this section by adding content to the Config and Data Mapping Sheet. Work Description Data Imports Include # of records and sources IdentitySync Listthe names and descriptions ofeach integration Consulton Schema Design Ex: Design consulting for Profile,Preferences and Subscription schemas Consulton BestPractices Consulton bestdesigns for 7. USE CASES The Use Case should define whatneeds to happen upon a particular action in order for that action to be completed successfully.The use case should outline all thatis needed for a particular process to succeed and also outlines all the participants involved in it. Use Case Name Provide name for Use Case Summary Provide a general overview/summary of the Use Case along with the goal to be achieved Assumptions Any assumptions that are implicit in the definition of the Use Case Participants The person(s) who will perform each of the steps described in this use case Preconditions These are the conditions that need to be met to ensure that the use case can be fulfilled. If these conditions are not met then the case cannot run its course. For example: ● The website needs to be accessible by the customer ● Age requirement-verification of 18+ Description/ Steps Steps and interactions between participants and system that are necessary to achieve goal 1. 2. 3. 4. Exceptions Provide description of what happens when a failure occurs in the flow.
  • 11.
    11 Recommended Flows Provide diagram thatdefines everything involved in the Use Case. Note: The below recommended flow examples may not be final Example #1: Full Registration Flow Gray: Client-hosted content Blue: SAP Customer Data Cloud-hosted screens Example #2: Lite Registration Green: Social provider-hosted screen Blue: SAP Customer Data Cloud-hosted screens
  • 12.
  • 13.
    13 The following sectionsinclude a setof tables summarizing the requirements thatapplyfor each use case.All the tables include the following information for each requirement: ● RequirementID: Unique identifier for the requirement ● Requirement:Description ofthe requirement. ● Type: Indicates whether the requirementis a reference to a standard (Std) or a new requirement(New). ● Feature: Identifies the functional category which the requirementis linked to. Requirement ID Requirement Type Feature Phase Notes ID001 Ensure data accuracy, security and privacy with email and CAPTCHA verification Std Registration-as-a-Service 1 ID002 The system shall identify the user based on their email address Std Lite Registration 1 ID003 Ability to log consent in the SAP Customer Data Cloud Consent Vault Std Consent 1 9. APPLICATION OF CONSENT RECOMMENDED PRACTICES The below are recommended practices to help safe-guard Client from consent compliance issus. Check off each item to indicate that the development plan supports these recommendations. Not checking off a practice may require written acknowledgement of the below decisions. Planned Recommended Practice Notes Ensure data accuracy, security and privacy with email and CAPTCHA verification Indicate reasons why it may not be planned X SAP Customer Data Cloud serves as the source of truth Require re-consent for imported users Only push consented users to marketing applications Make consent & withdrawal easy for the user Require re-consent for new PP & ToS Always authenticate the user Use real-time imports & ID tracking for proxy consent Provide lifetime accessibility to legal documents 10. KEY MILESTONES The following are key milestones which are critical to the project’s success. Key Milestones Owner Date
  • 14.
    14 Ex: Technical Kick-offEX: SAP Customer Data Cloud EX: Blueprint Workshop EX: SAP Customer Data Cloud EX: Identity Strategy Workshop EX: SAP Customer Data Cloud EX: Project-fit Blueprint and Technical Design Document Delivered EX: SAP Customer Data Cloud EX: Start User Migration EX: SAP Customer Data Cloud 11. SAP CUSTOMER DATA CLOUD WORK PACKAGES Work Packages and Deliverables Work Package Ex: Project-fit Blueprint and Technical Design Document Ex: Consult on RaaS, IdentitySync, Consent Management Ex: Import of users Description Ex: Creation of integration documents Ex: Consultation of Client’s UX and technical designs Ex: Migration of user profile data Ex: Best practices review Project hours Ex: Phase 1 is scheduled to utilize 200 of the 750 contracted hours End deliverable(s) Ex: Project-fit Blueprint and Technical Design Document 11.1. Project Exclusions ● Work not included in the above scope will be considered out of scope of this project.
  • 15.
    15 11.2. Risks ● Clientis held responsible for development, as recommended by SAP Customer Data Cloud. ● Delay by Client team will result in the project delivery being delayed. ● SAP Customer Data Cloud recommends limiting the number of users that can access the RaaS screensets (in the Development environment) to control deployments and updates to screensets and policies. ● SAP Customer Data Cloud will be in code freeze state from November - January. No amendments (i.e. product features) will be deployed to SAP Customer Data Cloud’s production environment within this period. 11.3. Project Controls ● Any changes to the scope or plan will result in resource adjustment and possible project delay. ● Any changes to the project that affect scope and/or fees must be documented and agreed to in writing by both Client and SAP Customer Data Cloud before commencing work; if additional hours are needed beyond the total authorized in this Blueprint, another Work Order or Change Order will be required. ● Client and SAP Customer Data Cloud must agree to the project schedules (i.e. sprints) and systems used to track the project. Access to agreed upon platforms must be provided before development begins. 11.4. Scope Change and Project Tolerance ● Deviation from the agreed scope, may result in the project being put on hold until a change assessment has been completed. Scope change will be managed through a change request process whereby the Implementation Consultant will assess the impact of the change, estimate the cost and timescales required to implement the change and request sign off from the client. ● Agreed timelines and scope rely on the following: a. Timely supply of any documentation and assets from client or third parties as agreed in the above document. b. Timely written feedback and approval of work in progress and final deliverables according to the agreed project plan. c. No change to the project scope and deliverables once agreed d. No change in direction once project deliverables are approved 12. CLIENT SIGN OFF
  • 16.
    16 The undersigned acknowledgethey have reviewed the <Project Name> plan and agree with the approach it presents. Changes to this Project-fit Blueprint will be coordinated with and approved by the undersigned or their designated representatives. Client Signature Full Name Title Date