SlideShare a Scribd company logo
1
SCHOOL OF ARCHITECTURE, BUILDING & DESIGN
Center for Architecture Studies in Southeast Asia (MASSA)
Bachelor of Science (Honours) in Architecture
BUILDING CONSTRUCTION 2 [ARC 2513]
Project 1 : Skeletal Construction “A Shelter For One”
Marks : 40% (30% groupwork & 10% individual)
Duration : 4 weeks
Submission date : 28 April 2015 - Week 6
(Presentation, Testing & Submission of Report)
Introduction
Experiencing and understanding skeletal construction is important as it is one of the most widely used structures
for building support. As a designer we should know how skeletal structure works.
Objectives of Assignment
The objectives of this project are as follows:
 To create an understanding of skeletal structure and its relevant structural components.
 To understand how a skeletal structure reacts under loading.
 To demonstrate a convincing understanding of how Skeletal Construction works.
 To be able to manipulate Skeletal Construction to solve an oblique Design problem.
2
Learning Outcomes
Learning outcomes assessed in this project include:
 Apply construction system in design.
 Recognize the implication of construction systems in design.
 Analyse the issues of strength, stiffness and stability of structures including modes of structural
systems, forces, stress and strain and laws of static.
Tasks - Methodology
Your task is to construct a shelter according to the following specifications.
 SCALE-Your shelter should be constructed to fit for one person in a sitting position (1:1 ). Max height is
1.5m. Max base size is 0.75 x 0.75 m
 CONSTRUCTION- It should demonstrate the knowledge of skeletal frames and its joints
o Should be elevated at least 5 inches from the ground
 JOINTS-The joints should be constructed to reflect actual joints. Eg, if a group chooses recycle steel
materials for the frame, the joints should be made to resemble bolts and nuts etc. You are not allowed
to use inappropriate materials for joints such as rope for steel.
 MATERIALS- You are only allowed to use recycle materials such as newspaper, pet bottles, cans, etc.
However, the chosen materials must relate to its function. Eg, roofing materials should not be made
from newspaper.
 OTHER DESIGN CONSIDERATIONS- This is just a minor component however; the shelter should be
light and portable.
o Resistant to outdoor weather.
o Allows easy access in and out from the shelter
o Shelter SHOULD NOT BE OVERLY DESIGN and must conform to the design criteria.
 TEST-The completed shelter will be tested to withstand the weight of average 60kg person up to 2
minutes.
 Analysis on the design, construction progress and test results are to be provided in the form of an
A3 bound report.
 Students are encouraged to use annotated sketches / diagrams to explain the construction, joints,
forces, structural movement experienced during the testing of the shelter.
 Photographs of the shelter should also be incorporated into the presentation report
Submission Requirement
 1:1 model of the shelter (students name and ID should be clearly included on the model)
 A3 bound report complete with visuals, sketches and inclusive of the detailing and progressive
documentation of your project.
 Visuals / Photos used in the submission must be clear and well communicated.
 Sketches are meant to provide visual documentation and communication. Therefore sketches are
required to be neat, clear and annotated.
 Assumptions can be made through reference from book/drawings. DO NOT PLAGIARISE.
 Softcopy is required to be attached with the hardcopy.
3
Assessment criteria
The assessment for the shelter construction will be based on your
 Ability to apply the knowledge of skeletal construction and its joints to actual construction and design
 Ability of the shelter to take the load applied in the specified duration.
 Creative design elements within the given requirements
 Understanding of appropriate materials to suit the functions of the shelter
The assessment for the report will be based on your
 Quality of the documentation of visuals sketches, drawings and load and forces detailing of the construction
elements.
 Clarity of the analysis on success / failure of the shelter.
Marking criteria
Marks shall be distributed as follows:
(1) Group Component ( will be calculated to 30%)
Marking
criteria
Marks%
Acquired
TGC
Fail
Poor
Satisfactory
Good
Excellent
UNDERSTANDING OF SKELETAL
CONSTRUCTION & ITS JOINTS
 The use of frame components-
interpretation of columns, beams,
roofing structure etc
 Joints
40
STRENGTH OF SHELTER
Ability of the model to take the total
load applied in the specified duration.
20
DESIGN
 Originality & practicality
 Weather resistant
 Easy access 10
MATERIALS
 Appropriate recycle materials are
used to suit the functions
10
ANALYSIS REPORT
 Quality of the documentation of
visuals sketches, drawings and
load and forces detailing of the
construction elements.
 Clarity of the analysis on success /
failure of the shelter.
20
4
(2) Individual Component (10%)
 10% based on peer evaluation and instructor’s evaluation on individual performance of a group
member in a group.
Assessment Criteria
Group(30%)
UNDERSTANDING OF SKELETAL
CONSTRUCTION & ITS JOINTS
 The use of frame components- interpretation of columns, beams, roofing structure etc. Joints
(40%)
STRENGTH OF SHELTER
Ability of the model to take the total load applied in the specified duration.
(20%)
DESIGN
 Originality & practicality
 Weather resistant
 Easy access
(10%)
MATERIALS
 Appropriate recycle materials are used to suit the functions
(10%)
ANALYSIS REPORT
 Quality of the documentation of visuals sketches, drawings and load and forces detailing of the
construction elements.
 Clarity of the analysis on success / failure of the shelter.
(20%)
(Total 100% will be converted to 30%)
Individual
(10%)
 peer evaluation and instructor’s evaluation on individual performance of a group member in a
group.
(10 %)
References
1. Chudley, R. 2006, Construction Technology. 4thedition. Pearson and Prentice Hall.
2. Lyons, Arthur, 2004. A. Materials for Architects and Builders. 2nd Edition. Oxford. Elsevier Butterwort-
Heinemann
3. Seeley, Ivor H.1995, Building Technology. 5th edition. Basingstoke, Hants: MacMillan
4. Ching, Francis D.K. 1991. Building Construction Illustrated. New York. Van Nostrand Reinhold.
5. Simmon, H. Leslie, 2001. Construction: Principles, Materials and Method. 7th Edition. New York. John
Wiley & Sons.
6. Zannos, Alexander. 1987, Form and Structure in Architecture: The Role of Statistical Function. Von
Nostrand Reinhold Company, New York

More Related Content

Viewers also liked

Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015Anthony Chew
 
Project brief buidling science 1 032015
Project  brief buidling science 1 032015Project  brief buidling science 1 032015
Project brief buidling science 1 032015Anthony Chew
 
Project 2 integration (1)
Project 2  integration (1)Project 2  integration (1)
Project 2 integration (1)
Anthony Chew
 
M outline (general)
M outline (general)M outline (general)
M outline (general)Anthony Chew
 
Arc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief finalArc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief finalAnthony Chew
 
Module outline building science1 aug 2014
Module outline building science1 aug 2014Module outline building science1 aug 2014
Module outline building science1 aug 2014Anthony Chew
 
Arc60103 (arc1313) march 2014 module outline
Arc60103 (arc1313) march 2014 module outlineArc60103 (arc1313) march 2014 module outline
Arc60103 (arc1313) march 2014 module outlineAnthony Chew
 
Project 3 report jan2015
Project 3 report jan2015Project 3 report jan2015
Project 3 report jan2015Anthony Chew
 
Tau march 2016
Tau march 2016Tau march 2016
Tau march 2016
Anthony Chew
 
Project 2 measured drawing jan2015 rev
Project 2 measured drawing jan2015 revProject 2 measured drawing jan2015 rev
Project 2 measured drawing jan2015 revAnthony Chew
 
Project brief 3 architecture studio 3 s1 2015 (4)
Project brief 3 architecture studio 3 s1 2015 (4)Project brief 3 architecture studio 3 s1 2015 (4)
Project brief 3 architecture studio 3 s1 2015 (4)Anthony Chew
 
Studio 3 module outline (s1 2015)
Studio 3 module outline (s1 2015)Studio 3 module outline (s1 2015)
Studio 3 module outline (s1 2015)Anthony Chew
 
Theories report
Theories reportTheories report
Theories report
Anthony Chew
 
Enbe.project one 04.13
Enbe.project one 04.13Enbe.project one 04.13
Enbe.project one 04.13Anthony Chew
 
Project2 brief web book
Project2 brief web bookProject2 brief web book
Project2 brief web bookAnthony Chew
 
Asian architecture
Asian architectureAsian architecture
Asian architecture
Anthony Chew
 

Viewers also liked (20)

Synopsis 2
Synopsis 2Synopsis 2
Synopsis 2
 
Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015
 
Project brief buidling science 1 032015
Project  brief buidling science 1 032015Project  brief buidling science 1 032015
Project brief buidling science 1 032015
 
Project 2 integration (1)
Project 2  integration (1)Project 2  integration (1)
Project 2 integration (1)
 
M outline (general)
M outline (general)M outline (general)
M outline (general)
 
Arc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief finalArc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief final
 
Module outline building science1 aug 2014
Module outline building science1 aug 2014Module outline building science1 aug 2014
Module outline building science1 aug 2014
 
Arc60103 (arc1313) march 2014 module outline
Arc60103 (arc1313) march 2014 module outlineArc60103 (arc1313) march 2014 module outline
Arc60103 (arc1313) march 2014 module outline
 
Project 3 report jan2015
Project 3 report jan2015Project 3 report jan2015
Project 3 report jan2015
 
Synopsis 1
Synopsis 1Synopsis 1
Synopsis 1
 
Tau march 2016
Tau march 2016Tau march 2016
Tau march 2016
 
Project 2 measured drawing jan2015 rev
Project 2 measured drawing jan2015 revProject 2 measured drawing jan2015 rev
Project 2 measured drawing jan2015 rev
 
Sypnosis 3
Sypnosis 3Sypnosis 3
Sypnosis 3
 
Project brief 3 architecture studio 3 s1 2015 (4)
Project brief 3 architecture studio 3 s1 2015 (4)Project brief 3 architecture studio 3 s1 2015 (4)
Project brief 3 architecture studio 3 s1 2015 (4)
 
Studio 3 module outline (s1 2015)
Studio 3 module outline (s1 2015)Studio 3 module outline (s1 2015)
Studio 3 module outline (s1 2015)
 
Theories report
Theories reportTheories report
Theories report
 
Enbe.project one 04.13
Enbe.project one 04.13Enbe.project one 04.13
Enbe.project one 04.13
 
Project2 brief web book
Project2 brief web bookProject2 brief web book
Project2 brief web book
 
Asian architecture
Asian architectureAsian architecture
Asian architecture
 
Project 1b layout
Project 1b layoutProject 1b layout
Project 1b layout
 

Similar to Project 1 brief

SEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTION
SEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTIONSEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTION
SEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTION
Darshiini Vig
 
Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016
Arvindhan Balasingam
 
Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016
Chow Hong Da
 
Project brief 2 b construction 2 march 2016 (new)
Project brief 2 b construction 2 march 2016 (new)Project brief 2 b construction 2 march 2016 (new)
Project brief 2 b construction 2 march 2016 (new)
Arvindhan Balasingam
 
SEMESTER 3 : PROJECT 2 BRIEF BCON 2
SEMESTER 3 : PROJECT 2 BRIEF BCON 2SEMESTER 3 : PROJECT 2 BRIEF BCON 2
SEMESTER 3 : PROJECT 2 BRIEF BCON 2
Darshiini Vig
 
Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1
Chow Hong Da
 
B. structure project 1 brief august 2015
B. structure project 1 brief august 2015B. structure project 1 brief august 2015
B. structure project 1 brief august 2015
Preston Liew
 
B. structure project 1 brief august 2015
B. structure project 1 brief august 2015B. structure project 1 brief august 2015
B. structure project 1 brief august 2015
Anthony Chew
 
B. structure project 1 brief august 2015
B. structure project 1 brief august 2015B. structure project 1 brief august 2015
B. structure project 1 brief august 2015
JoyeeLee0131
 
SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE
SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE
SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE
Darshiini Vig
 
Chapter 1_JWAn_ECE 340.pptx
Chapter 1_JWAn_ECE 340.pptxChapter 1_JWAn_ECE 340.pptx
Chapter 1_JWAn_ECE 340.pptx
jinwooan4
 
SEM 4 : PROJECT 1 BRIEF BUILDING SERVICES
SEM 4 : PROJECT 1 BRIEF BUILDING SERVICESSEM 4 : PROJECT 1 BRIEF BUILDING SERVICES
SEM 4 : PROJECT 1 BRIEF BUILDING SERVICES
Darshiini Vig
 
B. structure project 2 brief august 2015 (1)
B. structure project 2 brief august 2015 (1)B. structure project 2 brief august 2015 (1)
B. structure project 2 brief august 2015 (1)
Anthony Chew
 
B. structure project 2 brief august 2015
B. structure project 2 brief august 2015B. structure project 2 brief august 2015
B. structure project 2 brief august 2015
JoyeeLee0131
 
B. structure project 2 brief august 2015
B. structure project 2 brief august 2015B. structure project 2 brief august 2015
B. structure project 2 brief august 2015
Preston Liew
 
B sc (hons)(arch) asian architecture arc60403 project aug 2015
B sc (hons)(arch)  asian architecture arc60403 project aug 2015B sc (hons)(arch)  asian architecture arc60403 project aug 2015
B sc (hons)(arch) asian architecture arc60403 project aug 2015
Preston Liew
 
B sc (hons)(arch) asian architecture arc60403 project aug 2015 (4)
B sc (hons)(arch)  asian architecture arc60403 project aug 2015 (4)B sc (hons)(arch)  asian architecture arc60403 project aug 2015 (4)
B sc (hons)(arch) asian architecture arc60403 project aug 2015 (4)
Anthony Chew
 
SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1
SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1
SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1
Darshiini Vig
 
Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014Preston Liew
 

Similar to Project 1 brief (20)

SEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTION
SEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTIONSEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTION
SEMESTER 3 : PROJECT 1 BRIEF BUILDING CONSTRUCTION
 
Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016
 
Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016Project brief 1 b construction 2 march 2016
Project brief 1 b construction 2 march 2016
 
Bcon 2 proj 2
Bcon 2 proj 2Bcon 2 proj 2
Bcon 2 proj 2
 
Project brief 2 b construction 2 march 2016 (new)
Project brief 2 b construction 2 march 2016 (new)Project brief 2 b construction 2 march 2016 (new)
Project brief 2 b construction 2 march 2016 (new)
 
SEMESTER 3 : PROJECT 2 BRIEF BCON 2
SEMESTER 3 : PROJECT 2 BRIEF BCON 2SEMESTER 3 : PROJECT 2 BRIEF BCON 2
SEMESTER 3 : PROJECT 2 BRIEF BCON 2
 
Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1
 
B. structure project 1 brief august 2015
B. structure project 1 brief august 2015B. structure project 1 brief august 2015
B. structure project 1 brief august 2015
 
B. structure project 1 brief august 2015
B. structure project 1 brief august 2015B. structure project 1 brief august 2015
B. structure project 1 brief august 2015
 
B. structure project 1 brief august 2015
B. structure project 1 brief august 2015B. structure project 1 brief august 2015
B. structure project 1 brief august 2015
 
SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE
SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE
SEM 4 : PROJECT 1 BRIEF BUILDING STRUCTURE
 
Chapter 1_JWAn_ECE 340.pptx
Chapter 1_JWAn_ECE 340.pptxChapter 1_JWAn_ECE 340.pptx
Chapter 1_JWAn_ECE 340.pptx
 
SEM 4 : PROJECT 1 BRIEF BUILDING SERVICES
SEM 4 : PROJECT 1 BRIEF BUILDING SERVICESSEM 4 : PROJECT 1 BRIEF BUILDING SERVICES
SEM 4 : PROJECT 1 BRIEF BUILDING SERVICES
 
B. structure project 2 brief august 2015 (1)
B. structure project 2 brief august 2015 (1)B. structure project 2 brief august 2015 (1)
B. structure project 2 brief august 2015 (1)
 
B. structure project 2 brief august 2015
B. structure project 2 brief august 2015B. structure project 2 brief august 2015
B. structure project 2 brief august 2015
 
B. structure project 2 brief august 2015
B. structure project 2 brief august 2015B. structure project 2 brief august 2015
B. structure project 2 brief august 2015
 
B sc (hons)(arch) asian architecture arc60403 project aug 2015
B sc (hons)(arch)  asian architecture arc60403 project aug 2015B sc (hons)(arch)  asian architecture arc60403 project aug 2015
B sc (hons)(arch) asian architecture arc60403 project aug 2015
 
B sc (hons)(arch) asian architecture arc60403 project aug 2015 (4)
B sc (hons)(arch)  asian architecture arc60403 project aug 2015 (4)B sc (hons)(arch)  asian architecture arc60403 project aug 2015 (4)
B sc (hons)(arch) asian architecture arc60403 project aug 2015 (4)
 
SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1
SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1
SEMESTER 3 : PROJECT 1 BRIEF BUILDING SCIENCE 1
 
Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014
 

More from Anthony Chew

Project 1-performance-evaluation-2
Project 1-performance-evaluation-2Project 1-performance-evaluation-2
Project 1-performance-evaluation-2
Anthony Chew
 
Bscience report ff
Bscience report ffBscience report ff
Bscience report ff
Anthony Chew
 
Sunshading device studies 1 05-02-16
Sunshading device studies 1   05-02-16Sunshading device studies 1   05-02-16
Sunshading device studies 1 05-02-16
Anthony Chew
 
Building structure (1) (1)
Building structure (1) (1)Building structure (1) (1)
Building structure (1) (1)
Anthony Chew
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
Anthony Chew
 
Abstract ( asian architecture )
Abstract ( asian architecture )Abstract ( asian architecture )
Abstract ( asian architecture )
Anthony Chew
 
Topic issue proposal 2014
Topic  issue proposal 2014Topic  issue proposal 2014
Topic issue proposal 2014
Anthony Chew
 
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
Anthony Chew
 
Module intro aug 2015
Module intro aug 2015Module intro aug 2015
Module intro aug 2015
Anthony Chew
 
Service ready to print (1)
Service ready to print  (1)Service ready to print  (1)
Service ready to print (1)
Anthony Chew
 
Project 2 brief b services aug 2015
Project 2 brief b services aug 2015Project 2 brief b services aug 2015
Project 2 brief b services aug 2015
Anthony Chew
 
Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015
Anthony Chew
 
Module outline building services august 2015(lecturer)
Module outline building services august 2015(lecturer)Module outline building services august 2015(lecturer)
Module outline building services august 2015(lecturer)
Anthony Chew
 
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
Project 2 brief  architecture studio 4 arc60206 august 2015 (1)Project 2 brief  architecture studio 4 arc60206 august 2015 (1)
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
Anthony Chew
 
Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015
Anthony Chew
 
Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)
Anthony Chew
 

More from Anthony Chew (17)

Project 1-performance-evaluation-2
Project 1-performance-evaluation-2Project 1-performance-evaluation-2
Project 1-performance-evaluation-2
 
Bscience report ff
Bscience report ffBscience report ff
Bscience report ff
 
Sunshading device studies 1 05-02-16
Sunshading device studies 1   05-02-16Sunshading device studies 1   05-02-16
Sunshading device studies 1 05-02-16
 
Building structure (1) (1)
Building structure (1) (1)Building structure (1) (1)
Building structure (1) (1)
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
 
Aa presentatin
Aa presentatinAa presentatin
Aa presentatin
 
Abstract ( asian architecture )
Abstract ( asian architecture )Abstract ( asian architecture )
Abstract ( asian architecture )
 
Topic issue proposal 2014
Topic  issue proposal 2014Topic  issue proposal 2014
Topic issue proposal 2014
 
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
 
Module intro aug 2015
Module intro aug 2015Module intro aug 2015
Module intro aug 2015
 
Service ready to print (1)
Service ready to print  (1)Service ready to print  (1)
Service ready to print (1)
 
Project 2 brief b services aug 2015
Project 2 brief b services aug 2015Project 2 brief b services aug 2015
Project 2 brief b services aug 2015
 
Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015
 
Module outline building services august 2015(lecturer)
Module outline building services august 2015(lecturer)Module outline building services august 2015(lecturer)
Module outline building services august 2015(lecturer)
 
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
Project 2 brief  architecture studio 4 arc60206 august 2015 (1)Project 2 brief  architecture studio 4 arc60206 august 2015 (1)
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
 
Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015
 
Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)
 

Project 1 brief

  • 1. 1 SCHOOL OF ARCHITECTURE, BUILDING & DESIGN Center for Architecture Studies in Southeast Asia (MASSA) Bachelor of Science (Honours) in Architecture BUILDING CONSTRUCTION 2 [ARC 2513] Project 1 : Skeletal Construction “A Shelter For One” Marks : 40% (30% groupwork & 10% individual) Duration : 4 weeks Submission date : 28 April 2015 - Week 6 (Presentation, Testing & Submission of Report) Introduction Experiencing and understanding skeletal construction is important as it is one of the most widely used structures for building support. As a designer we should know how skeletal structure works. Objectives of Assignment The objectives of this project are as follows:  To create an understanding of skeletal structure and its relevant structural components.  To understand how a skeletal structure reacts under loading.  To demonstrate a convincing understanding of how Skeletal Construction works.  To be able to manipulate Skeletal Construction to solve an oblique Design problem.
  • 2. 2 Learning Outcomes Learning outcomes assessed in this project include:  Apply construction system in design.  Recognize the implication of construction systems in design.  Analyse the issues of strength, stiffness and stability of structures including modes of structural systems, forces, stress and strain and laws of static. Tasks - Methodology Your task is to construct a shelter according to the following specifications.  SCALE-Your shelter should be constructed to fit for one person in a sitting position (1:1 ). Max height is 1.5m. Max base size is 0.75 x 0.75 m  CONSTRUCTION- It should demonstrate the knowledge of skeletal frames and its joints o Should be elevated at least 5 inches from the ground  JOINTS-The joints should be constructed to reflect actual joints. Eg, if a group chooses recycle steel materials for the frame, the joints should be made to resemble bolts and nuts etc. You are not allowed to use inappropriate materials for joints such as rope for steel.  MATERIALS- You are only allowed to use recycle materials such as newspaper, pet bottles, cans, etc. However, the chosen materials must relate to its function. Eg, roofing materials should not be made from newspaper.  OTHER DESIGN CONSIDERATIONS- This is just a minor component however; the shelter should be light and portable. o Resistant to outdoor weather. o Allows easy access in and out from the shelter o Shelter SHOULD NOT BE OVERLY DESIGN and must conform to the design criteria.  TEST-The completed shelter will be tested to withstand the weight of average 60kg person up to 2 minutes.  Analysis on the design, construction progress and test results are to be provided in the form of an A3 bound report.  Students are encouraged to use annotated sketches / diagrams to explain the construction, joints, forces, structural movement experienced during the testing of the shelter.  Photographs of the shelter should also be incorporated into the presentation report Submission Requirement  1:1 model of the shelter (students name and ID should be clearly included on the model)  A3 bound report complete with visuals, sketches and inclusive of the detailing and progressive documentation of your project.  Visuals / Photos used in the submission must be clear and well communicated.  Sketches are meant to provide visual documentation and communication. Therefore sketches are required to be neat, clear and annotated.  Assumptions can be made through reference from book/drawings. DO NOT PLAGIARISE.  Softcopy is required to be attached with the hardcopy.
  • 3. 3 Assessment criteria The assessment for the shelter construction will be based on your  Ability to apply the knowledge of skeletal construction and its joints to actual construction and design  Ability of the shelter to take the load applied in the specified duration.  Creative design elements within the given requirements  Understanding of appropriate materials to suit the functions of the shelter The assessment for the report will be based on your  Quality of the documentation of visuals sketches, drawings and load and forces detailing of the construction elements.  Clarity of the analysis on success / failure of the shelter. Marking criteria Marks shall be distributed as follows: (1) Group Component ( will be calculated to 30%) Marking criteria Marks% Acquired TGC Fail Poor Satisfactory Good Excellent UNDERSTANDING OF SKELETAL CONSTRUCTION & ITS JOINTS  The use of frame components- interpretation of columns, beams, roofing structure etc  Joints 40 STRENGTH OF SHELTER Ability of the model to take the total load applied in the specified duration. 20 DESIGN  Originality & practicality  Weather resistant  Easy access 10 MATERIALS  Appropriate recycle materials are used to suit the functions 10 ANALYSIS REPORT  Quality of the documentation of visuals sketches, drawings and load and forces detailing of the construction elements.  Clarity of the analysis on success / failure of the shelter. 20
  • 4. 4 (2) Individual Component (10%)  10% based on peer evaluation and instructor’s evaluation on individual performance of a group member in a group. Assessment Criteria Group(30%) UNDERSTANDING OF SKELETAL CONSTRUCTION & ITS JOINTS  The use of frame components- interpretation of columns, beams, roofing structure etc. Joints (40%) STRENGTH OF SHELTER Ability of the model to take the total load applied in the specified duration. (20%) DESIGN  Originality & practicality  Weather resistant  Easy access (10%) MATERIALS  Appropriate recycle materials are used to suit the functions (10%) ANALYSIS REPORT  Quality of the documentation of visuals sketches, drawings and load and forces detailing of the construction elements.  Clarity of the analysis on success / failure of the shelter. (20%) (Total 100% will be converted to 30%) Individual (10%)  peer evaluation and instructor’s evaluation on individual performance of a group member in a group. (10 %) References 1. Chudley, R. 2006, Construction Technology. 4thedition. Pearson and Prentice Hall. 2. Lyons, Arthur, 2004. A. Materials for Architects and Builders. 2nd Edition. Oxford. Elsevier Butterwort- Heinemann 3. Seeley, Ivor H.1995, Building Technology. 5th edition. Basingstoke, Hants: MacMillan 4. Ching, Francis D.K. 1991. Building Construction Illustrated. New York. Van Nostrand Reinhold. 5. Simmon, H. Leslie, 2001. Construction: Principles, Materials and Method. 7th Edition. New York. John Wiley & Sons. 6. Zannos, Alexander. 1987, Form and Structure in Architecture: The Role of Statistical Function. Von Nostrand Reinhold Company, New York