SlideShare a Scribd company logo
PRODUCTION FLOW IN THE CONSTRUCTION
OF TALL BUILDINGS
Rafael Sacks1, Rebecca Partouche2
Associate Professor, Faculty of Civil and Env. Engineering, Technion – Israel Institute of Technology
Graduate Student, Faculty of Civil and Env. Engineering, Technion – Israel Institute of Technology
2/1/2018 1
Present: Trần Nguyễn Nhật Nam 1770716
Phạm Hoàng Nam 1770415
1. MOTIVATION
The time required for construction of tall buildings, whether measured
per floor or per unit area built, increased consistently through most of
the 20th century despite the introduction of improved construction
technologies
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
2
- More technologically complex ?
- Networks of subcontracting ?
Construction management has become focused on contract
management and the allocation of risk and less on explicit
management of the production system
 Buffers of time, work in process and materials to accumulate
2. BACKGROUND INFORMATION
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
3
From 1929 to 2008 , the Empire State Building represents an international
record in terms of the pace of construction
Possible reasons for this seeming contradiction.
1. The increasing number of building systems and their complexity
2. The prevailing economic conditions.
3. The variation and reliability of the design information.
The production system itself, particularly in the ways in which labor
resources are applied.
2. BACKGROUND INFORMATION
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
4
The model's primary purpose was to enable experimentation with different
management strategies, such as the 'WIP accumulation’ and 'WIP
minimization' strategy, the impact of design and other errors, and resource
constraints
2. BACKGROUND INFORMATION
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
5
IMPROVE
CONSTRUCTION FLOW
1 - Minimizing WIP
2 - Improving design
information quality
Difficult because their design and
production detailing is carried out
by numerous different people
Need intensive use of building
information modeling and
integration tools
focus on 1st strategy:
reduced WIP
3. NEW METHODS
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
6
The research method was to compare different strategies using a Discrete
Event Simulation Model. This tool is common in construction research
(Martinez and Ioannou 1999; Sacks et al. 2007; Tommelein 1998)
The measures for comparison are cycle times, overall crew productivity and
construction duration. Focus on Simulating WIP Accumulation vs. WIP
Reduction
3. NEW METHODS
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
7
Using ProModel
simulation software
(ProModel 2007)
Simulate
construction
of buildings
Five horizontal
space types
Three vertical
space types
Parking floors
Entrance floors
Typical office floors
Lobby elevatorspaces
on each floor
Roof space
Elevator
Technical shafts
in the core
Facades
3. NEW METHODS
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
8
All in all 116 distinct types of activities are modeled
The durations for the activities are stochastic, varying according to triangular
distributions defined by minimum, most common and maximum duration.
The durations are also corrected to account for the learning curve as each
team learns the best ways to perform each floor:
Corrected duration = Base duration ×
Maximum crew size
# workers available
× 1 +
Learning curve factor
# repetition s
3. NEW METHODS
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF TALL
BUILDINGS
9
Wip definition
4. RESULTS
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF
TALL BUILDINGS
10
Strategy
Average
Project
Duration
(months),
Resources Work flow
Maximum
number of
workers
needed
Labor
Capacity
Utilization
(%)
Floor Cycle Time for the finishes
(days)
Minimum Average Maximum Std. Dev.
WIP accumulation 29.9 101 90.6% 53 92 181 37%
No explicit strategy 28.7 98 89.9% 40 53 74 18%
WIP reduction 29.8 95 90.0% 37 50 76 17%
Table 1. Selected results for each of the strategies A to C (the number of workers made
available for each trade was the same for all.)
4. SUMMARY
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF
TALL BUILDINGS
11
The significant differences in the project outcomes resulting from
WIP accumulation vs. WIP reduction strategies.
In buildings that are highly uniform, as the Empire State Building
was, mass construction, with predetermined progress of trades from
floor to floor using fairly uniform production rates and carefully set
buffers can work well.
Their construction could be improved if managers were better versed
in the ‘physics’ of construction production systems
4. SUMMARY
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF
TALL BUILDINGS
12
But where buildings are more complex and variation in design and
production rates cannot be removed, as in the case of modern
buildings, project schedules that pre-determine the sequence of
progression of trades from space to space result in long cycle times
and long project durations.
This is exacerbated where trade subcontractors are allowed to
determine their own progression through a building and accumulate
buffers of WIP
4. REFERENCES
2/1/2018
PRODUCTION FLOW IN THE CONSTRUCTION OF
TALL BUILDINGS
13
1. CTBUH. (2008). "Tall Building Database." Council for Tall Buildings and Urban Habitat, Chicago, IL.
2. Eastman, C. M., Teicholz, P., Sacks, R., and Liston, K. (2008). BIM Handbook: A Guide to Building Information Modeling for Owners, Managers,
Architects, Engineers, Contractors, and Fabricators, John Wiley and Sons, Hoboken, NJ.
3. Hopp, W. J., and Spearman, M. L. (1996). Factory Physics, IRWIN, Chicago.
4. Khanzode, A., Fischer, M., and Reed, D. (2005). "Case Study of the Implementation of the Lean Project Delivery System (LPDS) using Virtual
Building Technologies on a Large Healthcare Project." 13th Conference of the International Group for Lean Construction, Sydney, Australia, 153-160.
ASCE Construction Research Congress 2009.
5. Koskela, L., and Howell, G. (2002). "The underlying theory of project management is obsolete." PMI Research Conference, 293-302.
6. Martinez, J. C., and Ioannou, P. G. (1999). "General Purpose Systems for Effective Construction Simulation." Journal of Construction Engineering
and Management, ASCE, 125(4), 265-276.
7. Partouche, R., Sacks, R., and Bertelsen, S. (2008). "Craft construction, mass construction, lean construction: lessons from the empire state building."
Proceedings of the 16th Annual Conference of the International Group for Lean Construction IGLC16, Manchester, UK.
8. ProModel. (2007). "ProModel." ProModel Corporation, Orem UT.
9. Sacks, R., Esquenazi, A., and Goldin, M. (2007). "LEAPCON: Simulation of Lean Construction of High-Rise Apartment Buildings." Journal of
Construction Engineering and Management, 133(7), 529-539.
10. Sacks, R., and Harel, M. (2006). "An economic game theory model of subcontractor resource allocation behavior." Construction Management &
Economics, 24(8), 869-881.
11. Skyscraper. (2008). "SkyscraperPage.com." Skyscraper Source Media, Victoria BC, Canada.
12. Tauranac, J. (1995). The Empire State Building: The Making of a Landmark, Scribner, New-York.
13. Tommelein, I. D. (1998). "Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction Technique." ASCE Journal of
Construction Engineering and Management, 124(4), 279-288.
14. Willis, C., and Friedman, D. (1998). Building the Empire State Building, W. W. Norton & Company, Inc., New York, London.

More Related Content

Similar to PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS

IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET Journal
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
Dimitrios Kordas
 
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using EtabsIRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET Journal
 
Modular buildings in_modern_construction
Modular buildings in_modern_constructionModular buildings in_modern_construction
Modular buildings in_modern_construction
ANTONYYONIANCCOHUACC
 
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
Marco Lisi
 
Coordination of Building Services: A Review
Coordination of Building Services: A ReviewCoordination of Building Services: A Review
Coordination of Building Services: A Review
IRJET Journal
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
IRJET Journal
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
IRJET Journal
 
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
IRJET Journal
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
VEMANA INSTITUTE OF TECHNOLOGY, VTU
 
Structural Building and Cost Optimization with Different Floor System
Structural Building and Cost Optimization with Different Floor SystemStructural Building and Cost Optimization with Different Floor System
Structural Building and Cost Optimization with Different Floor System
ijtsrd
 
Project management chapter 4
Project management chapter 4Project management chapter 4
Project management chapter 4
VancityInstitute
 
Could Modular Construction Influence Housing Affordability?
Could Modular Construction Influence Housing Affordability?Could Modular Construction Influence Housing Affordability?
Could Modular Construction Influence Housing Affordability?
Scott Robinson
 
Could modular construction influence housing affordability 7.27.16
Could modular construction influence housing affordability 7.27.16Could modular construction influence housing affordability 7.27.16
Could modular construction influence housing affordability 7.27.16
Denham Apperley
 
Ijciet 10 01_029
Ijciet 10 01_029Ijciet 10 01_029
Ijciet 10 01_029
IAEME Publication
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.kiebut
 
A Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkA Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical Framework
Ricardo Magno Antunes
 
IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot Technology
IRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Mary Montoya
 
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERACOMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
IRJET Journal
 

Similar to PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS (20)

IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
 
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using EtabsIRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
 
Modular buildings in_modern_construction
Modular buildings in_modern_constructionModular buildings in_modern_construction
Modular buildings in_modern_construction
 
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
 
Coordination of Building Services: A Review
Coordination of Building Services: A ReviewCoordination of Building Services: A Review
Coordination of Building Services: A Review
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
 
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
 
Structural Building and Cost Optimization with Different Floor System
Structural Building and Cost Optimization with Different Floor SystemStructural Building and Cost Optimization with Different Floor System
Structural Building and Cost Optimization with Different Floor System
 
Project management chapter 4
Project management chapter 4Project management chapter 4
Project management chapter 4
 
Could Modular Construction Influence Housing Affordability?
Could Modular Construction Influence Housing Affordability?Could Modular Construction Influence Housing Affordability?
Could Modular Construction Influence Housing Affordability?
 
Could modular construction influence housing affordability 7.27.16
Could modular construction influence housing affordability 7.27.16Could modular construction influence housing affordability 7.27.16
Could modular construction influence housing affordability 7.27.16
 
Ijciet 10 01_029
Ijciet 10 01_029Ijciet 10 01_029
Ijciet 10 01_029
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
A Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkA Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical Framework
 
IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot Technology
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERACOMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
 

More from Nam N.N Tran M.Eng, PMP

Structural Equation Modeling (SEM) with AMOS
Structural Equation Modeling (SEM) with AMOSStructural Equation Modeling (SEM) with AMOS
Structural Equation Modeling (SEM) with AMOS
Nam N.N Tran M.Eng, PMP
 
Factor analysis (FA)
Factor analysis (FA)Factor analysis (FA)
Factor analysis (FA)
Nam N.N Tran M.Eng, PMP
 
Assessment the relationship of variation orders on dispute avoidance for cons...
Assessment the relationship of variation orders on dispute avoidance for cons...Assessment the relationship of variation orders on dispute avoidance for cons...
Assessment the relationship of variation orders on dispute avoidance for cons...
Nam N.N Tran M.Eng, PMP
 
Shaft Grouting - Improving the capacity of bored piles by shaft grouting
Shaft Grouting - Improving the capacity of bored piles by shaft grouting Shaft Grouting - Improving the capacity of bored piles by shaft grouting
Shaft Grouting - Improving the capacity of bored piles by shaft grouting
Nam N.N Tran M.Eng, PMP
 
ANALYTIC HIERARCHY PROCESS (AHP)
ANALYTIC HIERARCHY PROCESS (AHP)ANALYTIC HIERARCHY PROCESS (AHP)
ANALYTIC HIERARCHY PROCESS (AHP)
Nam N.N Tran M.Eng, PMP
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
Nam N.N Tran M.Eng, PMP
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
Nam N.N Tran M.Eng, PMP
 

More from Nam N.N Tran M.Eng, PMP (7)

Structural Equation Modeling (SEM) with AMOS
Structural Equation Modeling (SEM) with AMOSStructural Equation Modeling (SEM) with AMOS
Structural Equation Modeling (SEM) with AMOS
 
Factor analysis (FA)
Factor analysis (FA)Factor analysis (FA)
Factor analysis (FA)
 
Assessment the relationship of variation orders on dispute avoidance for cons...
Assessment the relationship of variation orders on dispute avoidance for cons...Assessment the relationship of variation orders on dispute avoidance for cons...
Assessment the relationship of variation orders on dispute avoidance for cons...
 
Shaft Grouting - Improving the capacity of bored piles by shaft grouting
Shaft Grouting - Improving the capacity of bored piles by shaft grouting Shaft Grouting - Improving the capacity of bored piles by shaft grouting
Shaft Grouting - Improving the capacity of bored piles by shaft grouting
 
ANALYTIC HIERARCHY PROCESS (AHP)
ANALYTIC HIERARCHY PROCESS (AHP)ANALYTIC HIERARCHY PROCESS (AHP)
ANALYTIC HIERARCHY PROCESS (AHP)
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 

Recently uploaded

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
azkamurat
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 

Recently uploaded (20)

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 

PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS

  • 1. PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS Rafael Sacks1, Rebecca Partouche2 Associate Professor, Faculty of Civil and Env. Engineering, Technion – Israel Institute of Technology Graduate Student, Faculty of Civil and Env. Engineering, Technion – Israel Institute of Technology 2/1/2018 1 Present: Trần Nguyễn Nhật Nam 1770716 Phạm Hoàng Nam 1770415
  • 2. 1. MOTIVATION The time required for construction of tall buildings, whether measured per floor or per unit area built, increased consistently through most of the 20th century despite the introduction of improved construction technologies 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 2 - More technologically complex ? - Networks of subcontracting ? Construction management has become focused on contract management and the allocation of risk and less on explicit management of the production system  Buffers of time, work in process and materials to accumulate
  • 3. 2. BACKGROUND INFORMATION 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 3 From 1929 to 2008 , the Empire State Building represents an international record in terms of the pace of construction Possible reasons for this seeming contradiction. 1. The increasing number of building systems and their complexity 2. The prevailing economic conditions. 3. The variation and reliability of the design information. The production system itself, particularly in the ways in which labor resources are applied.
  • 4. 2. BACKGROUND INFORMATION 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 4 The model's primary purpose was to enable experimentation with different management strategies, such as the 'WIP accumulation’ and 'WIP minimization' strategy, the impact of design and other errors, and resource constraints
  • 5. 2. BACKGROUND INFORMATION 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 5 IMPROVE CONSTRUCTION FLOW 1 - Minimizing WIP 2 - Improving design information quality Difficult because their design and production detailing is carried out by numerous different people Need intensive use of building information modeling and integration tools focus on 1st strategy: reduced WIP
  • 6. 3. NEW METHODS 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 6 The research method was to compare different strategies using a Discrete Event Simulation Model. This tool is common in construction research (Martinez and Ioannou 1999; Sacks et al. 2007; Tommelein 1998) The measures for comparison are cycle times, overall crew productivity and construction duration. Focus on Simulating WIP Accumulation vs. WIP Reduction
  • 7. 3. NEW METHODS 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 7 Using ProModel simulation software (ProModel 2007) Simulate construction of buildings Five horizontal space types Three vertical space types Parking floors Entrance floors Typical office floors Lobby elevatorspaces on each floor Roof space Elevator Technical shafts in the core Facades
  • 8. 3. NEW METHODS 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 8 All in all 116 distinct types of activities are modeled The durations for the activities are stochastic, varying according to triangular distributions defined by minimum, most common and maximum duration. The durations are also corrected to account for the learning curve as each team learns the best ways to perform each floor: Corrected duration = Base duration × Maximum crew size # workers available × 1 + Learning curve factor # repetition s
  • 9. 3. NEW METHODS 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 9 Wip definition
  • 10. 4. RESULTS 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 10 Strategy Average Project Duration (months), Resources Work flow Maximum number of workers needed Labor Capacity Utilization (%) Floor Cycle Time for the finishes (days) Minimum Average Maximum Std. Dev. WIP accumulation 29.9 101 90.6% 53 92 181 37% No explicit strategy 28.7 98 89.9% 40 53 74 18% WIP reduction 29.8 95 90.0% 37 50 76 17% Table 1. Selected results for each of the strategies A to C (the number of workers made available for each trade was the same for all.)
  • 11. 4. SUMMARY 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 11 The significant differences in the project outcomes resulting from WIP accumulation vs. WIP reduction strategies. In buildings that are highly uniform, as the Empire State Building was, mass construction, with predetermined progress of trades from floor to floor using fairly uniform production rates and carefully set buffers can work well. Their construction could be improved if managers were better versed in the ‘physics’ of construction production systems
  • 12. 4. SUMMARY 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 12 But where buildings are more complex and variation in design and production rates cannot be removed, as in the case of modern buildings, project schedules that pre-determine the sequence of progression of trades from space to space result in long cycle times and long project durations. This is exacerbated where trade subcontractors are allowed to determine their own progression through a building and accumulate buffers of WIP
  • 13. 4. REFERENCES 2/1/2018 PRODUCTION FLOW IN THE CONSTRUCTION OF TALL BUILDINGS 13 1. CTBUH. (2008). "Tall Building Database." Council for Tall Buildings and Urban Habitat, Chicago, IL. 2. Eastman, C. M., Teicholz, P., Sacks, R., and Liston, K. (2008). BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Architects, Engineers, Contractors, and Fabricators, John Wiley and Sons, Hoboken, NJ. 3. Hopp, W. J., and Spearman, M. L. (1996). Factory Physics, IRWIN, Chicago. 4. Khanzode, A., Fischer, M., and Reed, D. (2005). "Case Study of the Implementation of the Lean Project Delivery System (LPDS) using Virtual Building Technologies on a Large Healthcare Project." 13th Conference of the International Group for Lean Construction, Sydney, Australia, 153-160. ASCE Construction Research Congress 2009. 5. Koskela, L., and Howell, G. (2002). "The underlying theory of project management is obsolete." PMI Research Conference, 293-302. 6. Martinez, J. C., and Ioannou, P. G. (1999). "General Purpose Systems for Effective Construction Simulation." Journal of Construction Engineering and Management, ASCE, 125(4), 265-276. 7. Partouche, R., Sacks, R., and Bertelsen, S. (2008). "Craft construction, mass construction, lean construction: lessons from the empire state building." Proceedings of the 16th Annual Conference of the International Group for Lean Construction IGLC16, Manchester, UK. 8. ProModel. (2007). "ProModel." ProModel Corporation, Orem UT. 9. Sacks, R., Esquenazi, A., and Goldin, M. (2007). "LEAPCON: Simulation of Lean Construction of High-Rise Apartment Buildings." Journal of Construction Engineering and Management, 133(7), 529-539. 10. Sacks, R., and Harel, M. (2006). "An economic game theory model of subcontractor resource allocation behavior." Construction Management & Economics, 24(8), 869-881. 11. Skyscraper. (2008). "SkyscraperPage.com." Skyscraper Source Media, Victoria BC, Canada. 12. Tauranac, J. (1995). The Empire State Building: The Making of a Landmark, Scribner, New-York. 13. Tommelein, I. D. (1998). "Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction Technique." ASCE Journal of Construction Engineering and Management, 124(4), 279-288. 14. Willis, C., and Friedman, D. (1998). Building the Empire State Building, W. W. Norton & Company, Inc., New York, London.