SlideShare a Scribd company logo
1 of 21
PRE-CONSTRUCTION ACTIVITY IN EPC WORKS
SEQUENCE OF PRESENTATION
 DPR Preparation.
 Land Acquisition.
 Forest Clearance.
 Shifting of utility.
PRE-CONSTRUCTION ACTIVITY IN EPC WORKS
DPR PREPARATION
DPR PREPARATION
.Finalization of alignment and approval of DPR is the first step in pre-construction activity of
EPC work.
 DPR preparation in EPC works is outsourced through DPR consultant who is responsible for
carrying out feasibility study, preparation of DPR and providing all the pre-construction services
required for road construction works.
 Project preparation activities are split into three stages as under with preliminary design work
to be commenced without waiting for feasibility study to be completed :-
(a) Stage 1 : Inception report
(b) Stage 2 : Feasibility report
(c) Stage 3 : Detailed project report
 The details of document to be submitted by Consultant in the three stages is as under :-
Stage 1 : Inception report
Srl Name of document Brief description
(a) Quality Assurance Plan
(QAP)
Immediately upon the award of Contract, the
consultants shall submit four copies of QAP
covering all aspects of field studies, investigations
design and economic financial analysis. The field
and design activities shall start after QAP is
approved by Department.
DPR PREPARATION
Srl Name of document Brief description
(b) Inception report (IR) The inception report shall cover all the major
aspects of project such as project appreciation, task
assignment and manning schedule, work
programme, design standards, key plan, linear plan
etc. and same is to be approved by Department.
Stage 2 : Feasibility report
(a) Feasibility report The consultant should commence feasibility study
after approval of IR. The feasibility study should
cover executive summary, project description
including alignment details, socio-economic
profiles, indicative design standards, traffic survey
and analysis, environmental and social assessment
report alongwith cost estimate, economic and
financial analysis and recommendation/ conclusion.
(b) Strip plan and
clearances
Consultant shall submit details of centre line of
proposed road, information concerning the area for
land acquisition, position of existing utilities and
services with relocation points in consultation with
local authorities, details of environmental and forest
clearances required, utility shifting plan, land
acquisition plan etc.
DPR PREPARATION
Srl Name of document Brief description
(c) Land Acquisition report The land acquisition report for the entire stretch
shall include detailed schedule about acquisition of
land holdings as per revenue records and their
locations on a strip plan and also the cost as per
district authorities alongwith resettlement plans and
plans for compensatory afforestation.
Stage 3 : Detailed project report
(a) Draft Detailed Project
report
The draft DPR submission shall consist of package
wise main report, design report, materials report,
drainage design report, economic and financial
analysis report, environmental assessment report
including resettlement action plan (RAP), package-
wise bid documents and drawings.
(b) Final Detailed Project
report
The final package wise DPR consisting of main
report, design report, drainage design report and
material report incorporating all revisions deemed
relevant following receipt of comments from the
Department on the draft DPR.
PRE-CONSTRUCTION ACTIVITY IN EPC WORKS
LAND ACQUISITION
 All activity related to EPC before award of contract
 Land Acquisition which includes gazette publication of 3a, 3A and 3D and its
timely publication in two local news papers at least one in vernacular language.
 Completion of 3C within stipulated time.
 3G Award for compensation and its timely disbursement to affected pers.
 Forest, Environmental and wild life clearance
 Estimate for shifting of utilities and its sanction by CFA
LAND ACQUISITION
Its essential so that 90 % RoW can be handed over to contractor on appointed
date. It is a time consuming activity which involves many State Govt agencies
like Revenue, PWD, horticulture, electricity department, Jal Sansadhan
Department etc.
It is a time consuming activity which involves many State Govt agencies like
Revenue, PWD, horticulture, electricity department, Jal Sansadhan Department
etc.
 Its essential so that 90 % RoW can be handed over to contractor on
appointed date.
 Shall be started immediately after approval of alignment.
LAND ACQUISITION
EPC Contract Provisions
 RFP Clauses
 Performance Security : Contractor has to submit performance security
within 30 days of receipt of LoA.
 EPC Contract Provisions
 Agreement to be signed within 10 days of receipt of performance
security.
 Appointed date to be given within 90 days of signing of contract
agrrement.
 On appointed date at least 90% of RoW to be handed over to contractor
which shall be in contiguous stretches of not less than 5 Km.
LAND ACQUISITION
EPC Contract Provisions
 Appointed Date does not occur, for any reason whatsoever, within 90
days of signing of the Agreement and submission of the full Performance
Security by the Contractor, the Agreement shall be deemed to have been
terminated. The Authority shall pay damages to the Contractor equivalent
to 1% of the Contract Price (3% in case of standalone bridge projects).
 There are penalty and reward provisions for contractor for completion of
work within contract period.
 Therefore to avoid penalty on Authority, it is essential to complete
preconstruction activities in a time bound manner before award of LoA.
 Once LoA issued the time line are fixed and Authority has to handover 90 %
RoW on appointed date.
LAND ACQUISITION
The details of land acquisition proceedings is as under :-
LAND ACQUISITION
Srl Activity Scope of work Agency bearing/ sharing the cost
(a) Section 3(a)
of the NH
Act, 1956
Notification of Competent Authority for
LA (CALA) by the Ministry on the
recommendations of State concerned
Involves no administrative cost. Invariably, CALA
are full-time serving officers who look after this
work in addition to their own office work.
(b) Section 3-A
of the NH
Act, 1956
Preparation of the notification and
issue of initial notification containing
brief description of land
Basic ground work done by the LA Supporting
Unit (comprising a team of contract/ retired
revenue officials) engaged by NHAI/ NHIDCL
and cost met by the acquiring agency.
Vetting and issue of Notification by
CALA
The time and effort put in by CALA and his
supporting staff of one or two employees is very
limited.
Publication in the newspapers Cost of publication in the newspapers is borne
by MoRTH or its agency e.g. NHAI, NHIDCL etc.
(c) Action under
Section 3-B
of the NH
Act, 1956
Survey and investigation of the land Action by CALA duly supported by the DPR
consultant and the Land Acquisition Supporting
unit of NHAI/NHIDCL
(d) Section 3-C
of the NH
Act, 1956
Invitation, examination and settlement
of Objections received/ filed by the
landowners/ interested persons
This is a substantive work but the inputs are
provided by the DPR consultants/ Land
Acquisition supporting unit
LAND ACQUISITION
Srl Activity Scope of work Agency bearing/ sharing the cost
(e) Section 3-D
of the NH
Act, 1956
Declaration of acquisition The basic ground work and details under this
sub-section are prepared by the DPR
consultants and the Land Acquisition Supporting
units, of course with due involvement/
association of the revenue officials of the
jurisdiction. The actual expenditure on issue/
publication of Notices in the local newspaper is
in any case borne by the land acquiring agency.
(f) Section 3-E
of the NH
Act, 1956
Power to take possession
(g) Section 3-F
of the NH
Act, 1956
Entering upon the land vesting in the
Central Government
(h) Section 3-G
of the NH
Act, 1956
Determination of amount payable as
compensation
The details under this sub-section are prepared
by the DPR Consultants and the Land
Acquisition Supporting units, of course with
association of the revenue officials of the
jurisdiction. The actual expenditure on issue/
publication of Notices in the local newspapers is
borne by the land acquiring agency.
(i) Section 3-H
of the NH
Act, 1956
Deposit and payment of amount
PRE-CONSTRUCTION ACTIVITY IN EPC WORKS
FOREST CLEARANCE
 Forest clearance is a very crucial process and it takes time because every aspect of the
project is carefully studied and after scrutinizing all the documents the MoEF grants
permission or reject the proposal.
Project proposals are classified based on the area of forest land required for diversion
for non-forest purposes as under :-
(a) Upto 05 hectares : Clearance granted by Regional Chief Conservator of
Forest (RCCF)
(b) 5 to 40 hectares : Clearance granted by RCCF in consultation with
State Advisory Group formed by RO of MoEF.
(c) Above 40 hectares : Forest Advisory Committee formed by MoEF.
 Project details are submitted to Nodal Officer online in form of Form A (grant of fresh
forest land), Form B (for extension of lease) or Form C (require approval of inspection of
minerals.
 Nodal officer scrutinizes the user agency proposal and sends acceptance letter to user
agency if all relevant documents are uploaded properly by user agency or may ask for
uploading of missing information. After forwarding acceptance letter to project proponent,
the proposal details are automatically forwarded to concerned DFOs and DCs.
FOREST CLEARANCE
 When DFO uploads his/ her comment and site inspection reports, the proposal details
are automatically forwarded to concerned CF/ CCF.
 Then CF/ CCF uploads his/ her comment and site inspection report on the portal, the
proposal details are automatically forwarded to concerned Nodal Officer who can view the
proposal and comments of DFO and CF/CCF.
 Nodal officer conveys his/ her comment and site inspection reports, proposal details are
automatically forwarded to concerned State Secretary.
 State Secretary views the whole proposal and comments of Nodal Officer, DFO and
CF/CCF and then processes the proposal alongwith his comments to Regional Officer or
Head Office.
 The permission is then granted by Regional Office/ Head Office.
 According to FC rules, prior approval of Central Government is given in two stages. In
1st stage, the proposal is agreed to in-principle. Conditions relating to transfer, mutation
and declaration of a Reserved Forest/ Protected Forest under the Indian Forest Act, 1927
of equivalent non-forest land for compensatory afforestation (CA) and funds for raising CA
are stipulated after 1st stage approval. After receipt of report from State Government
regarding compliance with stipulated conditions, formal approval (2nd stage approval or
final clearance) under the Act is issued.
FOREST CLEARANCE
 DFO/ Nodal Officer will coordinate and raise the demand note on portal after 1st stage of
clearance. The Nodal Officer will check/ approve the demand note and submit it to user
agency to proceed for payment. Nodal Officer can also send the demand note back to
DFO for correction before submitting it to user agency for payment.
 The user agency will perform the payment (out of the portal) and once completed will fill
the payment details on portal and submit.
 The CAMPA will then login into portal and confirm the payment details. The payment
details are also verified by Bank users.
 Once verification is done by CAMPA and Bank user, the proposal is processed for 2nd
stage of clearance.
FOREST CLEARANCE
PRE-CONSTRUCTION ACTIVITY IN EPC WORKS
SHIFTING OF UTILITY
 Delays in utility shifting is one of the major reasons affecting timely completion of the
project.
 Utilities (both under-ground and over-ground) that are required to be shifted for a
Project should be clearly assessed by DPR consultant during Project Preparation stage.
The scope of work and estimated cost of shifting of utilities (excluding the supervision
charges and without credit of dismantled scrape material) should be included in bids under
civil construction cost as per detailed estimates duly reviewed/ verified by the DPR
consultant and sanctioned by utility agencies at the appropriate level.
 Utility shifting plan should show existing utilities to be shifted and proposed utilities with
offset, development plan of project highway duly dimensioned and proposed right of way.
 There should be no variation in quantum of existing utilities to be shifted and new
facilities to be provided except where the variation is technically explained and justified
and acceptable to executing agencies. A comparative statement of existing utilities and
proposed provision should be prepared and included in the estimate.
 There should not be any up-gradation/ augmentation of facilities except where the
corresponding technologies/ codal provisions are obsolete. In case, up-gradation/
augmentation insisted upon by utility owning agencies, then the difference in the cost of
such up-gradation/ augmentation shall be borne by the utility owning agencies.
SHIFTING OF UTILITY
 Reference/code No. of SOR items shall invariably be given in the estimates and no
centages/ contingency shall be allowed on percentage basis unless the same are
provisioned in the applicable SORhaving reference/code no.
 Market rate of non-scheduled items shall be supported with variable documentary
evidence verified by concerned Executing Agency.
 Credit of dismantled material shall be given on realistic basis with detailed
calculation/quantities and rates instead of lump-sum/percentage basis.
 As the credit of dismantled material is already accounted for in the cost estimates, the
dismantled material/scrap of existing utility to be shifted/dismantled shall belong to the
contractor/concessionaire who would be free to dispose of the dismantled material as
deemed fit.
 The details of utility shifting should be a part of EPC agreement and be included in
Schedules of Agreement.
SHIFTING OF UTILITY
Preconstruction Activity in EPC Contract

More Related Content

Similar to Preconstruction Activity in EPC Contract

170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptxAnandkumarJoshi2
 
Guidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontarioGuidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontariojameschisholm
 
Economic and Socialized Housing BP 220 (04)
Economic and Socialized Housing BP 220 (04)Economic and Socialized Housing BP 220 (04)
Economic and Socialized Housing BP 220 (04)SQSY
 
Advanced Session on Statutory procedure and required documentations.
Advanced Session on Statutory procedure and required documentations.Advanced Session on Statutory procedure and required documentations.
Advanced Session on Statutory procedure and required documentations.Kartikey Joshi
 
Highway projects
Highway projects Highway projects
Highway projects Ajith Kumar
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxhurain5
 
GSP TDOT Utility Presentation
GSP TDOT Utility PresentationGSP TDOT Utility Presentation
GSP TDOT Utility PresentationRichard Yeager
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectVR M
 
Planning Process. Nairobi City County
Planning Process. Nairobi City CountyPlanning Process. Nairobi City County
Planning Process. Nairobi City CountyMido Collins
 
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade ProjectMillennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade ProjectMarcellus Drilling News
 
Navi mumbai metro new
Navi mumbai metro newNavi mumbai metro new
Navi mumbai metro newRashid Kaskar
 
GOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERA
GOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERAGOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERA
GOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERACA. (Dr.) Rajkumar Adukia
 
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...Bhalindra Bath - projects & M&A law
 
Plan preparation techniques
Plan preparation techniquesPlan preparation techniques
Plan preparation techniquesCoEP
 
Cellular Communications Tower Regulations
Cellular Communications Tower RegulationsCellular Communications Tower Regulations
Cellular Communications Tower Regulationsgscplanning
 
PPT HIWAY Junin Peru English.pptx
PPT HIWAY Junin Peru English.pptxPPT HIWAY Junin Peru English.pptx
PPT HIWAY Junin Peru English.pptxCESARREQUEJOTORRES1
 
Condominium property law part 4 - Revisions and Cessation of a condominium ...
Condominium property law   part 4 - Revisions and Cessation of a condominium ...Condominium property law   part 4 - Revisions and Cessation of a condominium ...
Condominium property law part 4 - Revisions and Cessation of a condominium ...Ajithaa Edirimane
 

Similar to Preconstruction Activity in EPC Contract (20)

170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx
 
Guidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontarioGuidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontario
 
Economic and Socialized Housing BP 220 (04)
Economic and Socialized Housing BP 220 (04)Economic and Socialized Housing BP 220 (04)
Economic and Socialized Housing BP 220 (04)
 
Railway Siding
Railway SidingRailway Siding
Railway Siding
 
Advanced Session on Statutory procedure and required documentations.
Advanced Session on Statutory procedure and required documentations.Advanced Session on Statutory procedure and required documentations.
Advanced Session on Statutory procedure and required documentations.
 
Highway projects
Highway projects Highway projects
Highway projects
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
 
GSP TDOT Utility Presentation
GSP TDOT Utility PresentationGSP TDOT Utility Presentation
GSP TDOT Utility Presentation
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
 
Planning Process. Nairobi City County
Planning Process. Nairobi City CountyPlanning Process. Nairobi City County
Planning Process. Nairobi City County
 
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade ProjectMillennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
 
Navi mumbai metro new
Navi mumbai metro newNavi mumbai metro new
Navi mumbai metro new
 
Emp
EmpEmp
Emp
 
GOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERA
GOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERAGOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERA
GOLDMINE OF PROFESSIONAL OPPORTUNITIES UNDER RERA
 
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
 
Plan preparation techniques
Plan preparation techniquesPlan preparation techniques
Plan preparation techniques
 
Cellular Communications Tower Regulations
Cellular Communications Tower RegulationsCellular Communications Tower Regulations
Cellular Communications Tower Regulations
 
Hrc nmmc guidelines
Hrc nmmc guidelinesHrc nmmc guidelines
Hrc nmmc guidelines
 
PPT HIWAY Junin Peru English.pptx
PPT HIWAY Junin Peru English.pptxPPT HIWAY Junin Peru English.pptx
PPT HIWAY Junin Peru English.pptx
 
Condominium property law part 4 - Revisions and Cessation of a condominium ...
Condominium property law   part 4 - Revisions and Cessation of a condominium ...Condominium property law   part 4 - Revisions and Cessation of a condominium ...
Condominium property law part 4 - Revisions and Cessation of a condominium ...
 

Recently uploaded

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Preconstruction Activity in EPC Contract

  • 2. SEQUENCE OF PRESENTATION  DPR Preparation.  Land Acquisition.  Forest Clearance.  Shifting of utility.
  • 3. PRE-CONSTRUCTION ACTIVITY IN EPC WORKS DPR PREPARATION
  • 4. DPR PREPARATION .Finalization of alignment and approval of DPR is the first step in pre-construction activity of EPC work.  DPR preparation in EPC works is outsourced through DPR consultant who is responsible for carrying out feasibility study, preparation of DPR and providing all the pre-construction services required for road construction works.  Project preparation activities are split into three stages as under with preliminary design work to be commenced without waiting for feasibility study to be completed :- (a) Stage 1 : Inception report (b) Stage 2 : Feasibility report (c) Stage 3 : Detailed project report  The details of document to be submitted by Consultant in the three stages is as under :- Stage 1 : Inception report Srl Name of document Brief description (a) Quality Assurance Plan (QAP) Immediately upon the award of Contract, the consultants shall submit four copies of QAP covering all aspects of field studies, investigations design and economic financial analysis. The field and design activities shall start after QAP is approved by Department.
  • 5. DPR PREPARATION Srl Name of document Brief description (b) Inception report (IR) The inception report shall cover all the major aspects of project such as project appreciation, task assignment and manning schedule, work programme, design standards, key plan, linear plan etc. and same is to be approved by Department. Stage 2 : Feasibility report (a) Feasibility report The consultant should commence feasibility study after approval of IR. The feasibility study should cover executive summary, project description including alignment details, socio-economic profiles, indicative design standards, traffic survey and analysis, environmental and social assessment report alongwith cost estimate, economic and financial analysis and recommendation/ conclusion. (b) Strip plan and clearances Consultant shall submit details of centre line of proposed road, information concerning the area for land acquisition, position of existing utilities and services with relocation points in consultation with local authorities, details of environmental and forest clearances required, utility shifting plan, land acquisition plan etc.
  • 6. DPR PREPARATION Srl Name of document Brief description (c) Land Acquisition report The land acquisition report for the entire stretch shall include detailed schedule about acquisition of land holdings as per revenue records and their locations on a strip plan and also the cost as per district authorities alongwith resettlement plans and plans for compensatory afforestation. Stage 3 : Detailed project report (a) Draft Detailed Project report The draft DPR submission shall consist of package wise main report, design report, materials report, drainage design report, economic and financial analysis report, environmental assessment report including resettlement action plan (RAP), package- wise bid documents and drawings. (b) Final Detailed Project report The final package wise DPR consisting of main report, design report, drainage design report and material report incorporating all revisions deemed relevant following receipt of comments from the Department on the draft DPR.
  • 7. PRE-CONSTRUCTION ACTIVITY IN EPC WORKS LAND ACQUISITION
  • 8.  All activity related to EPC before award of contract  Land Acquisition which includes gazette publication of 3a, 3A and 3D and its timely publication in two local news papers at least one in vernacular language.  Completion of 3C within stipulated time.  3G Award for compensation and its timely disbursement to affected pers.  Forest, Environmental and wild life clearance  Estimate for shifting of utilities and its sanction by CFA LAND ACQUISITION
  • 9. Its essential so that 90 % RoW can be handed over to contractor on appointed date. It is a time consuming activity which involves many State Govt agencies like Revenue, PWD, horticulture, electricity department, Jal Sansadhan Department etc. It is a time consuming activity which involves many State Govt agencies like Revenue, PWD, horticulture, electricity department, Jal Sansadhan Department etc.  Its essential so that 90 % RoW can be handed over to contractor on appointed date.  Shall be started immediately after approval of alignment. LAND ACQUISITION
  • 10. EPC Contract Provisions  RFP Clauses  Performance Security : Contractor has to submit performance security within 30 days of receipt of LoA.  EPC Contract Provisions  Agreement to be signed within 10 days of receipt of performance security.  Appointed date to be given within 90 days of signing of contract agrrement.  On appointed date at least 90% of RoW to be handed over to contractor which shall be in contiguous stretches of not less than 5 Km. LAND ACQUISITION
  • 11. EPC Contract Provisions  Appointed Date does not occur, for any reason whatsoever, within 90 days of signing of the Agreement and submission of the full Performance Security by the Contractor, the Agreement shall be deemed to have been terminated. The Authority shall pay damages to the Contractor equivalent to 1% of the Contract Price (3% in case of standalone bridge projects).  There are penalty and reward provisions for contractor for completion of work within contract period.  Therefore to avoid penalty on Authority, it is essential to complete preconstruction activities in a time bound manner before award of LoA.  Once LoA issued the time line are fixed and Authority has to handover 90 % RoW on appointed date. LAND ACQUISITION
  • 12. The details of land acquisition proceedings is as under :- LAND ACQUISITION Srl Activity Scope of work Agency bearing/ sharing the cost (a) Section 3(a) of the NH Act, 1956 Notification of Competent Authority for LA (CALA) by the Ministry on the recommendations of State concerned Involves no administrative cost. Invariably, CALA are full-time serving officers who look after this work in addition to their own office work. (b) Section 3-A of the NH Act, 1956 Preparation of the notification and issue of initial notification containing brief description of land Basic ground work done by the LA Supporting Unit (comprising a team of contract/ retired revenue officials) engaged by NHAI/ NHIDCL and cost met by the acquiring agency. Vetting and issue of Notification by CALA The time and effort put in by CALA and his supporting staff of one or two employees is very limited. Publication in the newspapers Cost of publication in the newspapers is borne by MoRTH or its agency e.g. NHAI, NHIDCL etc. (c) Action under Section 3-B of the NH Act, 1956 Survey and investigation of the land Action by CALA duly supported by the DPR consultant and the Land Acquisition Supporting unit of NHAI/NHIDCL (d) Section 3-C of the NH Act, 1956 Invitation, examination and settlement of Objections received/ filed by the landowners/ interested persons This is a substantive work but the inputs are provided by the DPR consultants/ Land Acquisition supporting unit
  • 13. LAND ACQUISITION Srl Activity Scope of work Agency bearing/ sharing the cost (e) Section 3-D of the NH Act, 1956 Declaration of acquisition The basic ground work and details under this sub-section are prepared by the DPR consultants and the Land Acquisition Supporting units, of course with due involvement/ association of the revenue officials of the jurisdiction. The actual expenditure on issue/ publication of Notices in the local newspaper is in any case borne by the land acquiring agency. (f) Section 3-E of the NH Act, 1956 Power to take possession (g) Section 3-F of the NH Act, 1956 Entering upon the land vesting in the Central Government (h) Section 3-G of the NH Act, 1956 Determination of amount payable as compensation The details under this sub-section are prepared by the DPR Consultants and the Land Acquisition Supporting units, of course with association of the revenue officials of the jurisdiction. The actual expenditure on issue/ publication of Notices in the local newspapers is borne by the land acquiring agency. (i) Section 3-H of the NH Act, 1956 Deposit and payment of amount
  • 14. PRE-CONSTRUCTION ACTIVITY IN EPC WORKS FOREST CLEARANCE
  • 15.  Forest clearance is a very crucial process and it takes time because every aspect of the project is carefully studied and after scrutinizing all the documents the MoEF grants permission or reject the proposal. Project proposals are classified based on the area of forest land required for diversion for non-forest purposes as under :- (a) Upto 05 hectares : Clearance granted by Regional Chief Conservator of Forest (RCCF) (b) 5 to 40 hectares : Clearance granted by RCCF in consultation with State Advisory Group formed by RO of MoEF. (c) Above 40 hectares : Forest Advisory Committee formed by MoEF.  Project details are submitted to Nodal Officer online in form of Form A (grant of fresh forest land), Form B (for extension of lease) or Form C (require approval of inspection of minerals.  Nodal officer scrutinizes the user agency proposal and sends acceptance letter to user agency if all relevant documents are uploaded properly by user agency or may ask for uploading of missing information. After forwarding acceptance letter to project proponent, the proposal details are automatically forwarded to concerned DFOs and DCs. FOREST CLEARANCE
  • 16.  When DFO uploads his/ her comment and site inspection reports, the proposal details are automatically forwarded to concerned CF/ CCF.  Then CF/ CCF uploads his/ her comment and site inspection report on the portal, the proposal details are automatically forwarded to concerned Nodal Officer who can view the proposal and comments of DFO and CF/CCF.  Nodal officer conveys his/ her comment and site inspection reports, proposal details are automatically forwarded to concerned State Secretary.  State Secretary views the whole proposal and comments of Nodal Officer, DFO and CF/CCF and then processes the proposal alongwith his comments to Regional Officer or Head Office.  The permission is then granted by Regional Office/ Head Office.  According to FC rules, prior approval of Central Government is given in two stages. In 1st stage, the proposal is agreed to in-principle. Conditions relating to transfer, mutation and declaration of a Reserved Forest/ Protected Forest under the Indian Forest Act, 1927 of equivalent non-forest land for compensatory afforestation (CA) and funds for raising CA are stipulated after 1st stage approval. After receipt of report from State Government regarding compliance with stipulated conditions, formal approval (2nd stage approval or final clearance) under the Act is issued. FOREST CLEARANCE
  • 17.  DFO/ Nodal Officer will coordinate and raise the demand note on portal after 1st stage of clearance. The Nodal Officer will check/ approve the demand note and submit it to user agency to proceed for payment. Nodal Officer can also send the demand note back to DFO for correction before submitting it to user agency for payment.  The user agency will perform the payment (out of the portal) and once completed will fill the payment details on portal and submit.  The CAMPA will then login into portal and confirm the payment details. The payment details are also verified by Bank users.  Once verification is done by CAMPA and Bank user, the proposal is processed for 2nd stage of clearance. FOREST CLEARANCE
  • 18. PRE-CONSTRUCTION ACTIVITY IN EPC WORKS SHIFTING OF UTILITY
  • 19.  Delays in utility shifting is one of the major reasons affecting timely completion of the project.  Utilities (both under-ground and over-ground) that are required to be shifted for a Project should be clearly assessed by DPR consultant during Project Preparation stage. The scope of work and estimated cost of shifting of utilities (excluding the supervision charges and without credit of dismantled scrape material) should be included in bids under civil construction cost as per detailed estimates duly reviewed/ verified by the DPR consultant and sanctioned by utility agencies at the appropriate level.  Utility shifting plan should show existing utilities to be shifted and proposed utilities with offset, development plan of project highway duly dimensioned and proposed right of way.  There should be no variation in quantum of existing utilities to be shifted and new facilities to be provided except where the variation is technically explained and justified and acceptable to executing agencies. A comparative statement of existing utilities and proposed provision should be prepared and included in the estimate.  There should not be any up-gradation/ augmentation of facilities except where the corresponding technologies/ codal provisions are obsolete. In case, up-gradation/ augmentation insisted upon by utility owning agencies, then the difference in the cost of such up-gradation/ augmentation shall be borne by the utility owning agencies. SHIFTING OF UTILITY
  • 20.  Reference/code No. of SOR items shall invariably be given in the estimates and no centages/ contingency shall be allowed on percentage basis unless the same are provisioned in the applicable SORhaving reference/code no.  Market rate of non-scheduled items shall be supported with variable documentary evidence verified by concerned Executing Agency.  Credit of dismantled material shall be given on realistic basis with detailed calculation/quantities and rates instead of lump-sum/percentage basis.  As the credit of dismantled material is already accounted for in the cost estimates, the dismantled material/scrap of existing utility to be shifted/dismantled shall belong to the contractor/concessionaire who would be free to dispose of the dismantled material as deemed fit.  The details of utility shifting should be a part of EPC agreement and be included in Schedules of Agreement. SHIFTING OF UTILITY