“Advanced Session on Statutory procedure and
required documentations.”.
COMPILED AND PRESENTED BY KARTIKEY JOSHI
Preface:-A typical/normal building approval
process takes anything between 8 months to 12
months. It has been experienced that the DCR
has undergone changes during the approval
process, hence it is important to continuously
track the changes in DCR and check its impact
on ongoing & upcoming project.
GEOGRAPHY
Mumbai consists of two distinct regions:-
Mumbai City district & Mumbai Suburban district .
The total area of Mumbai is approx 600 km2. Of this,
island city spans 68 km2, while the suburban
district spans 370 km2, together accounting for 437
km2 under the administration of (BMC).The
remaining area belongs to Defense, BPT, Atomic
Energy Commission, MMRDA, MIDC and Borivali
National Park, which are out of the jurisdiction of
the BMC.
The Island City extends from Colaba in the south to
Mahim and Sion in the north (yellow color in map).
“A” Ward to “G” ward fall under Island City. Base
permissible FSI is 1.33. TDR cannot be loaded in
island city. The permissible FSI can however be
increased by coupling various provisions of DCR.
The Mumbai Suburban District is from Bandra to
Dahisar, from Kurla (Chunabhatti) to Mulund and
from Kurla up to Trombay creek (Green color in
map).“H”, “K”, “L”, “M”, “N”, “P”, “R”, “S” & “T”
wards fall under Mumbai Suburban District. Base
permissible FSI is 1. TDR of up to additional 1 FSI
can be loaded. Also, permissible FSI can be
increased by coupling various provisions of DCR
The original DCR 1991 underwent several modifications over the plan
period (as detailed in the next slide ) giving freedom to Builder Lobby
to exploit the end user (by charging for every inch of this external
space at the same rate as that of the flat) by flouting the rules
(Building 30% to 40% more as free of fsi space) codenamed as super
built up area or saleable area. This era was only benefitting the
Builder lobby & corrupt officials. Market intervention that impelled
all land owners to fully exploit permissible FSI and if possible breach
the prescribed FSI, wherever possible.
Under M.C. Subodh kumar ,with primary motive of bringing in
transparency & reducing arbitrary decision making at every level ,
Elements like Balcony , Elevation features , Niche , Flower beds were
to be counted in FSI. To compensate this loss in FSI , the concept of
Compensatory FSI up-to 35% in Residential & 20% in Commercial
development was introduced.The new rule meant pricing based on
max available FSI by bringing the concept of fungibility under the
pretext of compensatory F.S.I .Builder were to use this compensatory
FSI for building larger habitable areas or balconies/F.B/E.F. etc.
DCR after its introduction went for following major amendments:-
DCR 1991 CM Sharad Pawar (Congress) / Mayor Bhujbal (SS)
1997- SRA CM Manohar Joshi (SS) / Mayor Milind Vaidya (SS)
1999- Heritage/Cessed CM Narayan Rane (SS)/ Mayor Nandu Satam (SS)
2002 - Textile mills CM Vilasroa D (INC)/Mayor H Patil (SS)
2003 –Hospitals/Meds CM Sushil(INC)/Mayor Mahadeo (SS)
2008 - MHADA,IT / ITES, Multi storied/Parking lots
CM Vilasroa Desh (Shiv Sena) / Smt Raul (SS)
2009 -Cessed,5 Star hotels ,doubling the parking requirement
CM, Ashok C (INC)/ Shraddha (SS)
2010- IT/ITES , nalla and appurtenant service road .
2012 - Fungible FSI
CM Prithviraj Chavan (INC) / Mayor Sunil Prabhu (SS)
COMPENSATORY F.S.I.
The averages for various features proposed to be counted in F.S.I.
worked out for residential, commercial & industrial buildings are as
follows:
% of such compensatory F.S.I. given
by charging premium as thus:-
– Residential 35 %
– Industrial / Commercial 20%
Premium is to be charged
– For Residential buildings at 60%, of
the rate of dev. land
– For Industrial buildings at 80%, as
as per stamp duty.
– For Commercial buildings at 100%
Ready reckoner rate.
Compensatory F.S.I. proposed as fungible so as to give flexibility to
architect for designing the buildings, thereby achieving the dual
purpose of functionality coupled with architectural features and to
obviate need for policing by the M.C.G.M. staff for violation.
In some cases, deck parking alone is equivalent to flat area.300 – 400 Sq.ft. per flat sanctioned in the name
of Lily pond with deck area. Projections more than 1.2 MT are sought & sanctioned with creative
nomenclatures – eco-friendly deck , sit-out areas, cut-off passages, service passages & are enclosed after
O.C. Part/pocket terraces /Ducts / voids /RCC bands so proposed are later merged with room / habitable
areas. Free of FSI balconies & elevational features, flower beds sold to customers as habitable areas
Misuse of Terrace / Pocket Terrace – Example 1PASHMINA
PASHMINA Misuse of Terrace / Pocket Terrace – Example 2
MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 5PASHMINA
MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 9PASHMINA
MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 6PASHMINA
MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 7PASHMINA
MISUSE PROCESS – EXAMPLE 10PASHMINA
MISUSE – CAR DECK & CAR LIFT –EXAMPLE 8PASHMINA
MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 3PASHMINA
MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 4PASHMINA
Mumbai Approval Process
for Residential Development
(1)Submission of proposal to a)CFO b)Parking, c) Civil
Aviation Dept.
(2)Submission to MOEF if C.A. exceeds 2 LSFT
(3)Sending the file for concession for 2.00/2.7 FSI after
obtaining approvals after pt. 1 above . The concession
plan should consist of future TDR/0.33 FSI/Fungible FSI.
(4)To get IOD of 1.00 FSI after obtaining approval of
concession.
(5)Submission of plan / layout for approval of subdivision
to collector to get separate PRC for independent plots.
(6)Submission of plan / layout for approval of N/A order
from collector to change the it on PRC
(7)Compliance of IOD conditions such as SWD Remarks,
Road Remarks, HE NOC, Assessment NOC, Debris
NOC,RCC Plan, Janata Insurance Policy, etc.to get plinth
/ stilt C.C. (After obtaining MOEF).
(8) To hand over D.P. Reservations & to carry out
infrastructure work like SWD, Road, Sewer line etc.
(9) To complete the work at site up-to Plinth / Stilt level
as per approved drawings after obtaining plinth / stilt
C.C.
RESIDENTIAL DEVELOPMENT PROCESS <70M BUILDINGS
(10)To complete the work at site up-to Plinth / Stilt level as per
approved drawings after obtaining plinth / stilt C.C.
(11)To get the plinth/stilt and open space measurement checked from
respective municipal office in order to get C.C above plinth/stilt.
(12)Compliance of all the remarks obtained prior to plinth C.C i.e.
storm water drain, drainage, water, road, sewer, CFO, tree etc.
(13)After obtaining completion certificates for all the infrastructure
works, lift NOC, etc. and after completion of construction work of the
building at site ( as per the approved plans), we apply for Occupation
certificate (O.C)
(14)After application of O.C, BMC officer visits the site to
check/inspect if the work is completed as per approved plans. (Time
period to obtain OC is approx 1 months from the date of obtaining lift
certificate and final CFO NOC).
Documents required:- Ownership Document (PRC/Dev. Agreement /
POA),D.P. Remarks , Demarcation of D.P. Roads / Reservations (if
any),CTS Plan, Architectural Drawings & R.C.C. Drawings &
Calculation
1) Ownership document.
2) D.P. Remarks.
3) Labor NOC / No Dues pending Certificate.
4) Factory closure Certificate from Labor
Commissioner.
5) Surrender of license of water & Electricity.
6) CTS Plan
7) Block Plan /Location Plan showing exact
location of Amenity plot to be handed over to
MCGM.
Process :-
Submission of proposal to Chief Engineer (D.P.)
along with all required documents. After the
scrutiny the file goes to Municipal Commissioner
through S.E. / A.E. / E.E. / Dy. Ch.Eng./ E.E. (P)/
Ch.Eng. / P.A. to M.C. / M.C. Need to show the
location of amenity plot touching / close to
existing Municipal Road.
DOCUMENTS REQUIRED DOR I TO R CONVERSION & PROCESS.
Procedure:-
1) Proposal submission to Chief Engineer (D.P.) along with all document.
2) Site visit of S.E. & A.E. with all consultants will be done.
3) Presentation of proposal in the 1st meeting to be held in BMC office.
4) If Environmental Report , Structural & Architect drawings are OK, then
minutes of meeting are prepared by S.E., A.E. & Sent to approval of M.C
5)Simultaneously a letter to BP & CFO (If correction) for their remarks is
sent.
6)After pt.4 & 5 - a Report prepared by S.E. is sent to A.E.>
Dy.Che.Eng>E.E.(P)>Dy.Che.Eng D.P.>P.A. to M.C.>M.C. Issue of HR-Noc
Documents Required:-
1) D.P. Remark
2) Architect Drawing
3) EIA Report
4) Structural Report Hard & Soft Copy
5) DBR (Design Basic Report) & Structural Checklist
6) Soil Report - 3 sets
7) PPT Report (Powerpoint Presentation ) Soft copy & Hard copy
8) Google Image
9) Site summary
10) Building proposal scrutiny Report
PRCEDURE FOR HIGH RISE APPROVAL & DOCUMENTS.
1. Documents required - Ownership Document (PRC/Dev.
Agreement / POA),D.P. Remarks, CTS Plan , MHADA NOC ,
Environmental Parameter/ Rapid EIA , List of tenants certified
by MHADA , Soil Investigation Report , CFO NOC & Parking
NOC.
2. After receipt of both the reports MCZMA sends their report to
UDD & UDD after scrutiny sends back to MCZMA with their
remarks & further clarifications,
3. MCZMA forwards file back to BMC seeking clarification asked
by UDD.
4. BMC Reply to MCZMA.
5. Presentation by CRZ consultant in MCZMA meeting.
6. MCZMA issues letter for payment.
7. After payment, MCZMA issue final approval.
8. NOTE :- If Basement is proposed ,while granting final
approval MCZMA puts a condition to get NOC from Director of
Ground Water Dept. (whose office is at Vashi). It is required
for obtaining process of dewatering saline water in
basement.
DOCUMENTS REQUIRED FOR C.R.Z. APPROVAL & PROCESS
MCZMA REPORT - A MCZMA REPORT - B
1)CRZ Demarcation by National institute of Oceanography. 1)Submission of proposal to MPCB
2)Submission of proposal to EEBP (CITY) 2)MPCB issues notification to all tenants
3)Post concession ok by M.C.,Ch. Eng.(D.P.) they f/d the report to MCZMA 3) Public hearing with Hon. Collector followed by final report to MCZMA
“THANK YOU.”
COMPILED AND PRESENTED BY KARTIKEY JOSHI

More Related Content

What's hot

Redevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)b
Redevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)bRedevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)b
Redevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)bOMKAR CHODANKAR
 
Exhibit a parking management plan
Exhibit a   parking management planExhibit a   parking management plan
Exhibit a parking management planE'ville Eye
 
Design approval procedure
Design approval procedureDesign approval procedure
Design approval procedureIqbál Ãzàm
 
Luis Munoz Marin redevelopment Plan 08.29.2012
Luis Munoz Marin redevelopment Plan 08.29.2012Luis Munoz Marin redevelopment Plan 08.29.2012
Luis Munoz Marin redevelopment Plan 08.29.2012Candice Osborne
 
City Council August 30, 2011 Planning Presentation
City Council August 30, 2011 Planning PresentationCity Council August 30, 2011 Planning Presentation
City Council August 30, 2011 Planning PresentationCity of San Angelo Texas
 
WORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen Ozukum
WORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen OzukumWORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen Ozukum
WORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen OzukumIPPAI
 
1 st 20 year road plan
1 st 20 year road plan1 st 20 year road plan
1 st 20 year road plan12cl0viren
 
Unit 3.building construction
Unit 3.building constructionUnit 3.building construction
Unit 3.building constructionChirag Bhanagale
 
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCEAPPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCEzubeditufail
 

What's hot (13)

MIA Central Terminal Redevelopment Program presentation, November 19, 2014
MIA Central Terminal Redevelopment Program presentation, November 19, 2014MIA Central Terminal Redevelopment Program presentation, November 19, 2014
MIA Central Terminal Redevelopment Program presentation, November 19, 2014
 
Said_Ghalayin_Sept 15
Said_Ghalayin_Sept 15Said_Ghalayin_Sept 15
Said_Ghalayin_Sept 15
 
Redevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)b
Redevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)bRedevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)b
Redevelopment under dcpr 2034 regulation section 33(7),33(7)a &amp; 33(7)b
 
Exhibit a parking management plan
Exhibit a   parking management planExhibit a   parking management plan
Exhibit a parking management plan
 
Stirling Station Delegation
Stirling Station DelegationStirling Station Delegation
Stirling Station Delegation
 
Design approval procedure
Design approval procedureDesign approval procedure
Design approval procedure
 
Luis Munoz Marin redevelopment Plan 08.29.2012
Luis Munoz Marin redevelopment Plan 08.29.2012Luis Munoz Marin redevelopment Plan 08.29.2012
Luis Munoz Marin redevelopment Plan 08.29.2012
 
City Council August 30, 2011 Planning Presentation
City Council August 30, 2011 Planning PresentationCity Council August 30, 2011 Planning Presentation
City Council August 30, 2011 Planning Presentation
 
WORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen Ozukum
WORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen OzukumWORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen Ozukum
WORKSHOP CABLE CAR SHIMLA PRESENTATION FINAL 26 JUN 2014_Dr Toshimanen Ozukum
 
1 st 20 year road plan
1 st 20 year road plan1 st 20 year road plan
1 st 20 year road plan
 
Unit 3.building construction
Unit 3.building constructionUnit 3.building construction
Unit 3.building construction
 
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCEAPPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
 
Khaled fahmy cv
Khaled fahmy cvKhaled fahmy cv
Khaled fahmy cv
 

Viewers also liked

GIS mapping of electoral boundries with legends
GIS mapping of electoral boundries with legendsGIS mapping of electoral boundries with legends
GIS mapping of electoral boundries with legendsaditeevaidya
 
История создания войск Карабинеров Республики Молдова
История создания войск Карабинеров Республики МолдоваИстория создания войск Карабинеров Республики Молдова
История создания войск Карабинеров Республики Молдоваprivate
 
Человек спасший мир. The man who saved the world
Человек спасший мир.  The man who saved the worldЧеловек спасший мир.  The man who saved the world
Человек спасший мир. The man who saved the worldprivate
 
TalentRecruitCorp_Key Features_April2015
TalentRecruitCorp_Key Features_April2015TalentRecruitCorp_Key Features_April2015
TalentRecruitCorp_Key Features_April2015Zakir Hussain
 
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issuedbansi default
 
Haroon Usman's DFM Professional Report
Haroon Usman's DFM Professional ReportHaroon Usman's DFM Professional Report
Haroon Usman's DFM Professional ReportHaroon Usman
 
Real Estate Regulation and Development Act (RERA)
Real Estate Regulation and Development Act (RERA)Real Estate Regulation and Development Act (RERA)
Real Estate Regulation and Development Act (RERA)Kartikey Joshi
 
Praja Foundation's - Ward committee White Paper 2011
Praja Foundation's - Ward committee White Paper 2011Praja Foundation's - Ward committee White Paper 2011
Praja Foundation's - Ward committee White Paper 2011Milind Mhaske
 
8466_Syn_AnalyticsToolkit_11 155
8466_Syn_AnalyticsToolkit_11 1558466_Syn_AnalyticsToolkit_11 155
8466_Syn_AnalyticsToolkit_11 155David Liebskind
 
Presentation to MCGM regarding Mumbai Development Plan 2014-34 - SWM
Presentation to MCGM regarding Mumbai Development Plan 2014-34 - SWMPresentation to MCGM regarding Mumbai Development Plan 2014-34 - SWM
Presentation to MCGM regarding Mumbai Development Plan 2014-34 - SWMRishi Aggarwal
 
Animais e ecosistemas_t5_natu_5_b
Animais e ecosistemas_t5_natu_5_bAnimais e ecosistemas_t5_natu_5_b
Animais e ecosistemas_t5_natu_5_bSonia Vidal Puga
 

Viewers also liked (16)

Bmc final map
Bmc  final mapBmc  final map
Bmc final map
 
GIS mapping of electoral boundries with legends
GIS mapping of electoral boundries with legendsGIS mapping of electoral boundries with legends
GIS mapping of electoral boundries with legends
 
Carey Danis & Lowe
Carey Danis & LoweCarey Danis & Lowe
Carey Danis & Lowe
 
История создания войск Карабинеров Республики Молдова
История создания войск Карабинеров Республики МолдоваИстория создания войск Карабинеров Республики Молдова
История создания войск Карабинеров Республики Молдова
 
Человек спасший мир. The man who saved the world
Человек спасший мир.  The man who saved the worldЧеловек спасший мир.  The man who saved the world
Человек спасший мир. The man who saved the world
 
TalentRecruitCorp_Key Features_April2015
TalentRecruitCorp_Key Features_April2015TalentRecruitCorp_Key Features_April2015
TalentRecruitCorp_Key Features_April2015
 
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
 
Haroon Usman's DFM Professional Report
Haroon Usman's DFM Professional ReportHaroon Usman's DFM Professional Report
Haroon Usman's DFM Professional Report
 
Real Estate Regulation and Development Act (RERA)
Real Estate Regulation and Development Act (RERA)Real Estate Regulation and Development Act (RERA)
Real Estate Regulation and Development Act (RERA)
 
Safety Shoes
Safety ShoesSafety Shoes
Safety Shoes
 
Praja Foundation's - Ward committee White Paper 2011
Praja Foundation's - Ward committee White Paper 2011Praja Foundation's - Ward committee White Paper 2011
Praja Foundation's - Ward committee White Paper 2011
 
Fault lines
Fault linesFault lines
Fault lines
 
8466_Syn_AnalyticsToolkit_11 155
8466_Syn_AnalyticsToolkit_11 1558466_Syn_AnalyticsToolkit_11 155
8466_Syn_AnalyticsToolkit_11 155
 
Presentation to MCGM regarding Mumbai Development Plan 2014-34 - SWM
Presentation to MCGM regarding Mumbai Development Plan 2014-34 - SWMPresentation to MCGM regarding Mumbai Development Plan 2014-34 - SWM
Presentation to MCGM regarding Mumbai Development Plan 2014-34 - SWM
 
Tema 4 natu. as plantas
Tema 4 natu. as plantasTema 4 natu. as plantas
Tema 4 natu. as plantas
 
Animais e ecosistemas_t5_natu_5_b
Animais e ecosistemas_t5_natu_5_bAnimais e ecosistemas_t5_natu_5_b
Animais e ecosistemas_t5_natu_5_b
 

Similar to Advanced Session on Statutory Procedure and Required Documentation

Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Jogani Reinforcement
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxsyedaliabl2023
 
Preconstruction Activity in EPC Contract
Preconstruction Activity in EPC ContractPreconstruction Activity in EPC Contract
Preconstruction Activity in EPC ContractROHIT4772
 
Highway projects
Highway projects Highway projects
Highway projects Ajith Kumar
 
CV Muhammad Kashif Khan
CV Muhammad Kashif KhanCV Muhammad Kashif Khan
CV Muhammad Kashif KhanMUHAMMAD KHAN
 
Emerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersEmerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersAnil Kumar Gupta
 
Shen_Presentation_CBTC_Conf_2011
Shen_Presentation_CBTC_Conf_2011Shen_Presentation_CBTC_Conf_2011
Shen_Presentation_CBTC_Conf_2011Jian Shen
 
Site analysis and documentation
Site analysis and documentation Site analysis and documentation
Site analysis and documentation Lawin Langat
 
110005 Simap2 Mouchtie 2009 047261 F05 En
110005 Simap2 Mouchtie 2009 047261 F05 En110005 Simap2 Mouchtie 2009 047261 F05 En
110005 Simap2 Mouchtie 2009 047261 F05 Ensuror
 
TRUSTONE ADVANCITY, DETAILS @ 9654953105
TRUSTONE ADVANCITY, DETAILS @ 9654953105TRUSTONE ADVANCITY, DETAILS @ 9654953105
TRUSTONE ADVANCITY, DETAILS @ 9654953105ashokjai
 
TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105
TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105
TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105ashokjai
 
ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...
ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...
ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...ashokjai
 
07 how to select pmc
07   how to select pmc07   how to select pmc
07 how to select pmcspandane
 
IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...
IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...
IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...IRJET Journal
 
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)Seann Smith, AICP
 
Environmental clearance for construction projects optima
Environmental clearance for construction projects optimaEnvironmental clearance for construction projects optima
Environmental clearance for construction projects optimaSiddharth Choksi
 

Similar to Advanced Session on Statutory Procedure and Required Documentation (20)

CV Amr Zaki - PMP®
CV Amr Zaki - PMP®CV Amr Zaki - PMP®
CV Amr Zaki - PMP®
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...
 
Hrc nmmc guidelines
Hrc nmmc guidelinesHrc nmmc guidelines
Hrc nmmc guidelines
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
 
Preconstruction Activity in EPC Contract
Preconstruction Activity in EPC ContractPreconstruction Activity in EPC Contract
Preconstruction Activity in EPC Contract
 
13
1313
13
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
Highway projects
Highway projects Highway projects
Highway projects
 
CV Muhammad Kashif Khan
CV Muhammad Kashif KhanCV Muhammad Kashif Khan
CV Muhammad Kashif Khan
 
Emerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersEmerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway Engineers
 
Shen_Presentation_CBTC_Conf_2011
Shen_Presentation_CBTC_Conf_2011Shen_Presentation_CBTC_Conf_2011
Shen_Presentation_CBTC_Conf_2011
 
Site analysis and documentation
Site analysis and documentation Site analysis and documentation
Site analysis and documentation
 
110005 Simap2 Mouchtie 2009 047261 F05 En
110005 Simap2 Mouchtie 2009 047261 F05 En110005 Simap2 Mouchtie 2009 047261 F05 En
110005 Simap2 Mouchtie 2009 047261 F05 En
 
TRUSTONE ADVANCITY, DETAILS @ 9654953105
TRUSTONE ADVANCITY, DETAILS @ 9654953105TRUSTONE ADVANCITY, DETAILS @ 9654953105
TRUSTONE ADVANCITY, DETAILS @ 9654953105
 
TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105
TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105
TRUSTONE ADVANCITY NOIDA SEZ, CALL 9654953105
 
ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...
ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...
ASSURED RETURN PROJECTS IN NOIDA&lt; CALL 9654953105, WEGMANS SEZ NOIDA EXTEN...
 
07 how to select pmc
07   how to select pmc07   how to select pmc
07 how to select pmc
 
IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...
IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...
IRJET- Best Feasible Transportation Route Analysis for Delivering Ready Mixed...
 
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
 
Environmental clearance for construction projects optima
Environmental clearance for construction projects optimaEnvironmental clearance for construction projects optima
Environmental clearance for construction projects optima
 

Advanced Session on Statutory Procedure and Required Documentation

  • 1. “Advanced Session on Statutory procedure and required documentations.”. COMPILED AND PRESENTED BY KARTIKEY JOSHI
  • 2. Preface:-A typical/normal building approval process takes anything between 8 months to 12 months. It has been experienced that the DCR has undergone changes during the approval process, hence it is important to continuously track the changes in DCR and check its impact on ongoing & upcoming project.
  • 3. GEOGRAPHY Mumbai consists of two distinct regions:- Mumbai City district & Mumbai Suburban district . The total area of Mumbai is approx 600 km2. Of this, island city spans 68 km2, while the suburban district spans 370 km2, together accounting for 437 km2 under the administration of (BMC).The remaining area belongs to Defense, BPT, Atomic Energy Commission, MMRDA, MIDC and Borivali National Park, which are out of the jurisdiction of the BMC. The Island City extends from Colaba in the south to Mahim and Sion in the north (yellow color in map). “A” Ward to “G” ward fall under Island City. Base permissible FSI is 1.33. TDR cannot be loaded in island city. The permissible FSI can however be increased by coupling various provisions of DCR. The Mumbai Suburban District is from Bandra to Dahisar, from Kurla (Chunabhatti) to Mulund and from Kurla up to Trombay creek (Green color in map).“H”, “K”, “L”, “M”, “N”, “P”, “R”, “S” & “T” wards fall under Mumbai Suburban District. Base permissible FSI is 1. TDR of up to additional 1 FSI can be loaded. Also, permissible FSI can be increased by coupling various provisions of DCR
  • 4. The original DCR 1991 underwent several modifications over the plan period (as detailed in the next slide ) giving freedom to Builder Lobby to exploit the end user (by charging for every inch of this external space at the same rate as that of the flat) by flouting the rules (Building 30% to 40% more as free of fsi space) codenamed as super built up area or saleable area. This era was only benefitting the Builder lobby & corrupt officials. Market intervention that impelled all land owners to fully exploit permissible FSI and if possible breach the prescribed FSI, wherever possible. Under M.C. Subodh kumar ,with primary motive of bringing in transparency & reducing arbitrary decision making at every level , Elements like Balcony , Elevation features , Niche , Flower beds were to be counted in FSI. To compensate this loss in FSI , the concept of Compensatory FSI up-to 35% in Residential & 20% in Commercial development was introduced.The new rule meant pricing based on max available FSI by bringing the concept of fungibility under the pretext of compensatory F.S.I .Builder were to use this compensatory FSI for building larger habitable areas or balconies/F.B/E.F. etc.
  • 5. DCR after its introduction went for following major amendments:- DCR 1991 CM Sharad Pawar (Congress) / Mayor Bhujbal (SS) 1997- SRA CM Manohar Joshi (SS) / Mayor Milind Vaidya (SS) 1999- Heritage/Cessed CM Narayan Rane (SS)/ Mayor Nandu Satam (SS) 2002 - Textile mills CM Vilasroa D (INC)/Mayor H Patil (SS) 2003 –Hospitals/Meds CM Sushil(INC)/Mayor Mahadeo (SS) 2008 - MHADA,IT / ITES, Multi storied/Parking lots CM Vilasroa Desh (Shiv Sena) / Smt Raul (SS) 2009 -Cessed,5 Star hotels ,doubling the parking requirement CM, Ashok C (INC)/ Shraddha (SS) 2010- IT/ITES , nalla and appurtenant service road . 2012 - Fungible FSI CM Prithviraj Chavan (INC) / Mayor Sunil Prabhu (SS)
  • 6. COMPENSATORY F.S.I. The averages for various features proposed to be counted in F.S.I. worked out for residential, commercial & industrial buildings are as follows: % of such compensatory F.S.I. given by charging premium as thus:- – Residential 35 % – Industrial / Commercial 20% Premium is to be charged – For Residential buildings at 60%, of the rate of dev. land – For Industrial buildings at 80%, as as per stamp duty. – For Commercial buildings at 100% Ready reckoner rate. Compensatory F.S.I. proposed as fungible so as to give flexibility to architect for designing the buildings, thereby achieving the dual purpose of functionality coupled with architectural features and to obviate need for policing by the M.C.G.M. staff for violation.
  • 7. In some cases, deck parking alone is equivalent to flat area.300 – 400 Sq.ft. per flat sanctioned in the name of Lily pond with deck area. Projections more than 1.2 MT are sought & sanctioned with creative nomenclatures – eco-friendly deck , sit-out areas, cut-off passages, service passages & are enclosed after O.C. Part/pocket terraces /Ducts / voids /RCC bands so proposed are later merged with room / habitable areas. Free of FSI balconies & elevational features, flower beds sold to customers as habitable areas
  • 8. Misuse of Terrace / Pocket Terrace – Example 1PASHMINA
  • 9. PASHMINA Misuse of Terrace / Pocket Terrace – Example 2
  • 10. MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 5PASHMINA
  • 11. MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 9PASHMINA
  • 12. MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 6PASHMINA
  • 13. MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 7PASHMINA
  • 14. MISUSE PROCESS – EXAMPLE 10PASHMINA
  • 15. MISUSE – CAR DECK & CAR LIFT –EXAMPLE 8PASHMINA
  • 16. MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 3PASHMINA
  • 17. MISUSE - ARCHITECTURAL FEATURES – EXAMPLE 4PASHMINA
  • 18. Mumbai Approval Process for Residential Development
  • 19. (1)Submission of proposal to a)CFO b)Parking, c) Civil Aviation Dept. (2)Submission to MOEF if C.A. exceeds 2 LSFT (3)Sending the file for concession for 2.00/2.7 FSI after obtaining approvals after pt. 1 above . The concession plan should consist of future TDR/0.33 FSI/Fungible FSI. (4)To get IOD of 1.00 FSI after obtaining approval of concession. (5)Submission of plan / layout for approval of subdivision to collector to get separate PRC for independent plots. (6)Submission of plan / layout for approval of N/A order from collector to change the it on PRC (7)Compliance of IOD conditions such as SWD Remarks, Road Remarks, HE NOC, Assessment NOC, Debris NOC,RCC Plan, Janata Insurance Policy, etc.to get plinth / stilt C.C. (After obtaining MOEF). (8) To hand over D.P. Reservations & to carry out infrastructure work like SWD, Road, Sewer line etc. (9) To complete the work at site up-to Plinth / Stilt level as per approved drawings after obtaining plinth / stilt C.C. RESIDENTIAL DEVELOPMENT PROCESS <70M BUILDINGS
  • 20. (10)To complete the work at site up-to Plinth / Stilt level as per approved drawings after obtaining plinth / stilt C.C. (11)To get the plinth/stilt and open space measurement checked from respective municipal office in order to get C.C above plinth/stilt. (12)Compliance of all the remarks obtained prior to plinth C.C i.e. storm water drain, drainage, water, road, sewer, CFO, tree etc. (13)After obtaining completion certificates for all the infrastructure works, lift NOC, etc. and after completion of construction work of the building at site ( as per the approved plans), we apply for Occupation certificate (O.C) (14)After application of O.C, BMC officer visits the site to check/inspect if the work is completed as per approved plans. (Time period to obtain OC is approx 1 months from the date of obtaining lift certificate and final CFO NOC). Documents required:- Ownership Document (PRC/Dev. Agreement / POA),D.P. Remarks , Demarcation of D.P. Roads / Reservations (if any),CTS Plan, Architectural Drawings & R.C.C. Drawings & Calculation
  • 21. 1) Ownership document. 2) D.P. Remarks. 3) Labor NOC / No Dues pending Certificate. 4) Factory closure Certificate from Labor Commissioner. 5) Surrender of license of water & Electricity. 6) CTS Plan 7) Block Plan /Location Plan showing exact location of Amenity plot to be handed over to MCGM. Process :- Submission of proposal to Chief Engineer (D.P.) along with all required documents. After the scrutiny the file goes to Municipal Commissioner through S.E. / A.E. / E.E. / Dy. Ch.Eng./ E.E. (P)/ Ch.Eng. / P.A. to M.C. / M.C. Need to show the location of amenity plot touching / close to existing Municipal Road. DOCUMENTS REQUIRED DOR I TO R CONVERSION & PROCESS.
  • 22. Procedure:- 1) Proposal submission to Chief Engineer (D.P.) along with all document. 2) Site visit of S.E. & A.E. with all consultants will be done. 3) Presentation of proposal in the 1st meeting to be held in BMC office. 4) If Environmental Report , Structural & Architect drawings are OK, then minutes of meeting are prepared by S.E., A.E. & Sent to approval of M.C 5)Simultaneously a letter to BP & CFO (If correction) for their remarks is sent. 6)After pt.4 & 5 - a Report prepared by S.E. is sent to A.E.> Dy.Che.Eng>E.E.(P)>Dy.Che.Eng D.P.>P.A. to M.C.>M.C. Issue of HR-Noc Documents Required:- 1) D.P. Remark 2) Architect Drawing 3) EIA Report 4) Structural Report Hard & Soft Copy 5) DBR (Design Basic Report) & Structural Checklist 6) Soil Report - 3 sets 7) PPT Report (Powerpoint Presentation ) Soft copy & Hard copy 8) Google Image 9) Site summary 10) Building proposal scrutiny Report PRCEDURE FOR HIGH RISE APPROVAL & DOCUMENTS.
  • 23. 1. Documents required - Ownership Document (PRC/Dev. Agreement / POA),D.P. Remarks, CTS Plan , MHADA NOC , Environmental Parameter/ Rapid EIA , List of tenants certified by MHADA , Soil Investigation Report , CFO NOC & Parking NOC. 2. After receipt of both the reports MCZMA sends their report to UDD & UDD after scrutiny sends back to MCZMA with their remarks & further clarifications, 3. MCZMA forwards file back to BMC seeking clarification asked by UDD. 4. BMC Reply to MCZMA. 5. Presentation by CRZ consultant in MCZMA meeting. 6. MCZMA issues letter for payment. 7. After payment, MCZMA issue final approval. 8. NOTE :- If Basement is proposed ,while granting final approval MCZMA puts a condition to get NOC from Director of Ground Water Dept. (whose office is at Vashi). It is required for obtaining process of dewatering saline water in basement. DOCUMENTS REQUIRED FOR C.R.Z. APPROVAL & PROCESS MCZMA REPORT - A MCZMA REPORT - B 1)CRZ Demarcation by National institute of Oceanography. 1)Submission of proposal to MPCB 2)Submission of proposal to EEBP (CITY) 2)MPCB issues notification to all tenants 3)Post concession ok by M.C.,Ch. Eng.(D.P.) they f/d the report to MCZMA 3) Public hearing with Hon. Collector followed by final report to MCZMA
  • 24. “THANK YOU.” COMPILED AND PRESENTED BY KARTIKEY JOSHI