PMP Refresher

Project Integration Management
     - Niraj Agarwal




                                 May 2011
                                   Slide 1
Project Integration Management
Definition

• It includes the processes and activities needed to identify, define,
combine, unify, and coordinate the various processes and project
management activities within the Project Management Process Groups.
• The bringing together of diverse organizations, groups or parts to
form a cohesive whole to successfully achieve PROJECT OBJECTIVES.
• Processes to bring different elements of project together so that they
are properly coordinated to meet or exceed stakeholders expectations.
• These processes may occur repeatedly over the project duration
• Historical Records are needed to perform project management well,
they are inputs to continuous improvement -> Files, Lessons Learned,
Actual Costs, Time Estimates, WBS, Benchmarks, Risks.


                                                                    May 2011
                                                                      Slide 2
Project Integration Management
Elements to Integrate

• Knowledge Areas—Scope, Time, Cost, Quality etc.
• Organizations
• Stakeholder Requirements
• Technical Elements
• People
• Communications
• Product Scope Components
• Phases
Integration requires that all these Elements are brought together
holistically and aligned in the direction of the project Goals!


                                                                    May 2011
                                                                      Slide 3
Project Integration Management
The Processes

Develop Project Charter – developing the project charter that formally
authorizes a project or a project phase.

Develop Project Management Plan – documenting the actions
necessary to define, prepare, integrate, and coordinate all subsidiary
plans into a project management plan.

Direct and Manage Project Execution – executing the work defined in
the project management plan to achieve the project’s requirements
defined in the project scope statement.




                                                                    May 2011
                                                                      Slide 4
Project Integration Management Processes


Monitor and Control Project Work – monitoring and controlling the
processes used to initiate, plan, execute, and close a project to meet the
performance objectives defined in the project management plan.

Integrated Change Control – reviewing all change requests, approving
changes, and controlling changes to the deliverables and organizational
process assets.

Close Project – finalizing all activities across all of the Project
Management Process Groups to formally close the project or a project
phase.



                                                                      May 2011
                                                                        Slide 5
Project Integration Management




                                 May 2011
                                   Slide 6
Develop Project Charter




                          May 2011
                            Slide 7
Develop Project Charter
What is Project Charter
• Formally recognizes project, created by senior manager, includes:
  - Business need/Business Case
  - Product description & title
  - Signed contract
  - Project Manager Identification & Authority level
  - Senior Management approval
  - Project’s Goals and Objectives
  - Constraints – factors that limit project management team’s
    options
  - Assumptions – factors that are considered true for planning
    purposes. Involve a degree of risk



                                                                  May 2011
                                                                    Slide 8
IceScream – Case Study
Background
You work for a midsize ice-cream company called IceScream in the
Kolkata. Business has been very, very good! Ice-cream is popular all over
the state. The owner, Anvita, has decided to set up shop in other cities:
Delhi, Mumbai, and Bangalore. She has established strong partnerships in
these areas and is now ready to connect the three sites together into one
network so that she can keep track of the daily activities of each location.
The prospective new locations are as follows:
Delhi - Anvita wants to set up a regional distributorship with Sonia
Gandhvi’s Delhi Kulfi (DK), utilizing DK’s special skills to improve the
quality of the ice-creams.
Mumbai – SRK has been making wonderful Barf ka Gola for several years
now. SRK is interested in branching out nationally and understands that a
partnership such as the one with Ice-Scream would be beneficial for both
companies.
Bangalore – Vijay Wallya has been dishing out ice-cream idly & dosas
which are a personal favourite of Anvita.

                                                                       May 2011
                                                                         Slide 9
IceScream – Case Study
The Work
• Anvita has entered into financial agreements and working partnerships
that give her a partial stake in the profits of each of the ice-cream
companies, while allowing them to retain their original look and feel and
maintain the management of their day-to-day operations.
• The people who work for each entity will ultimately report to Anvita, but
each Ice-cream company is free to continue doing what it does best. Anvita
has committed to not interfere.
• You have been with IceScream, serving as the head of IT, since the
installation of one small file server on which Anvita kept the spreadsheets
for the various accounts.
• Today Anvita told you that she wants you to install an email server in
each of the other three locations, connecting them so that everyone can
communicate with one another and all employees’ email addresses are in
the global address list. She also wants an intranet site set up so that the new
releases and other communications are available to everyone for comment
and approval.

                                                                         May 2011
                                                                          Slide 10
IceScream – Case Study
Needs & Stakeholders

Basic requirements - You have two requirements that you must
fulfil:
• Set up an email system for all four sites.
• Set up an intranet.
Stakeholders - Anvita is the project sponsor. In addition to her, there
are three primary stakeholders: Sonia Gandhvi , SRK, Vijay Wallya
Other key staff members within each of the ice-cream companies are
stakeholders on the project as well. They most likely include the general
manager, director of sales, accounting director, and human resources
director.
Now that you have identified the stakeholders and understand the
requirements for the project, you set about gathering the goals for the
project, including the due date, high-level milestones, key deliverables,
estimated costs, assumptions, constraints, and high-level risks.
                                                                     May 2011
                                                                      Slide 11
Icescream – Case Study
Assumptions, Constraints & Risks

Assumptions - IT personnel are available at each Ice-cream company
(or you are able to hire consultants) to assist with all the technical
aspects of implementing this project. English will be the primary
language for all communications.
Constraints - This project has a budget of INR 1,000,000. Each site
requires new hardware, a backup solution, ISP, licensing fees, contract
help, and so on.
High-level risks - Downtime at one or more of the sites. Security
intrusions. Improper training of users on the use of the intranet site.


You document the project charter, and Anvita signs it, authorizing the
project to begin.

                                                                     May 2011
                                                                      Slide 12
Develop Project Management Plan
Definition

• This process includes the actions necessary to define, integrate, and
coordinate all subsidiary plans into a project management plan.
• It uses the outputs of the other planning processes to create a
consistent, coherent document that can be used to guide both project
execution and project control.
• Document project planning assumptions
• Provide a baseline for progress measurement and project control




                                                                    May 2011
                                                                     Slide 13
Develop Project Management Plan
Project Plan

• A comprehensive set of documents used to guide
  execution of Project work to monitor project status,
  collect and disseminate performance information,
  progress measurement, manage changes and control the
  project work.
• It is a dynamic document in the sense that, it is updated
  and changes with progressive elaboration of project.
• It includes all performance baselines which changes only
  intermittently.
• It consists of Subsidiary Management Plans.

                                                         May 2011
                                                          Slide 14
Develop Project Management Plan




                                  May 2011
                                   Slide 15
Direct and Manage Project Execution
Definition

• Is the actual performance of all project activities to create the project
product .
• Requires the project manager and the project team to perform
multiple actions to execute the project management plan
• The vast majority of the project efforts and cost will be expended in
performing the execution process
• Staff, train, and manage the project team members assigned to the
project
• Managing the technical and organizational project interfaces
• Performance monitoring & Periodic forecasts of final cost and
schedule results to support the analysis
• Collect and document lessons learned, and implement approved
process improvement activities.                                May 2011
                                                                       Slide 16
Direct and Manage Project Execution
ITTO




                                      May 2011
                                       Slide 17
Direct and Manage Project Execution




                                      May 2011
                                       Slide 18
Monitor and Control Project Work
Definition

This process is performed to monitor project processes associated with
initiating, planning, executing, and closing.
Corrective or preventive actions are taken to control the project
performance.
Monitoring is an aspect of project management performed throughout
the project. It includes collecting, measuring, and disseminating
performance information, and assessing measurements and trends to
effect process improvements.




                                                                    May 2011
                                                                     Slide 19
Monitor and Control Project Work
ITTO




                                   May 2011
                                    Slide 20
Perform Integrated Change Control
Definition

• Determine that a change has occurred
• Coordinates Changes across all knowledge areas—entire project
• Ensures that the changes are beneficial
• Reviewing and approving all recommended corrective and preventive
actions.
• Managing the actual changes when and as they occur
• Maintain integrity of any performance measurement baseline.
• Ensures that changes are reflected in the scope definition and
product specifications
• Documenting the complete impact of requested changes.


                                                                   May 2011
                                                                    Slide 21
Perform Integrated Change Control
ITTO




                                    May 2011
                                     Slide 22
Perform Integrated
Change Control




                     May 2011
                      Slide 23
Close Project
Definition

• It involves performing the project closure portion of the project
management plan.
• In multi-phase projects, the Close Project process closes out the
portion of the project scope and associated activities applicable to a
given phase.
• This process includes finalizing all activities completed across all
Project Management Process Groups to formally close the project or a
project phase, and transfer the completed or cancelled project as
appropriate.
• The Close Project process also establishes the procedures to
coordinate activities needed to verify and document the project
deliverables, to coordinate and interact to formalize acceptance of those
deliverables by the customer or sponsor, and to investigate and
document the reasons for actions taken if a project is terminated before
                                                                     May 2011
completion.                                                           Slide 24
Close Project
ITTO




                May 2011
                 Slide 25
Pop Quiz
Question 1

Randy is a key technical resource for your project. You have
worked with Randy on past projects and have identified him
in the project charter as one of the team members who will
work on the project. The charter has been published, and
there is great excitement about this project. You have
scheduled a meeting to talk to Randy ’ s functional manager
next week. Which of the following conditions does this
describe?
A. Risk
B. Assumption
C. Deliverable
D. Constraint

                                                         May 2011
                                                          Slide 26
Pop Quiz
Question 2

From the following options, select those that best describe the
definition of a deliverable. (Choose three.)
A. Marks the completion of a project phase
B. Has measurable outcomes or results
C. Is a specific item that must be produced to consider the project
complete
D. Describes the characteristics of the product of the project
E. Is documented in the project charter
F. Is tangible and easily verified




                                                                      May 2011
                                                                       Slide 27
Pop Quiz
Question 3

From the following options, select the one that does not
describe a constraint.
A. Project team actions are dictated.
B. It may regard budget, resources, or schedule.
C. Project team actions are restricted
D. Project situations are believed to be true.




                                                           May 2011
                                                            Slide 28
Pop Quiz
Question 4

Your project is to be performed outdoors. You are only four
days from the big event, and there is a hurricane headed for
shore. This is an example of which of the following?
A. Risk
B. Assumption
C. Deliverable
D. Constraint




                                                         May 2011
                                                          Slide 29
Thank You!

More Related Content

What's hot

Social Media Project Charter Template
Social Media Project Charter TemplateSocial Media Project Charter Template
Social Media Project Charter TemplateDemand Metric
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera CloudPRMYAZILIM
 
PM Training Slides
PM Training SlidesPM Training Slides
PM Training SlidesAhmed303
 
Avenew Project Management Fundamental
Avenew Project Management FundamentalAvenew Project Management Fundamental
Avenew Project Management FundamentalAVENEW INDONESIA
 
Project Management Foundations Series Course 102 - Project Management Processes
Project Management Foundations Series Course 102 - Project Management ProcessesProject Management Foundations Series Course 102 - Project Management Processes
Project Management Foundations Series Course 102 - Project Management ProcessesThink For A Change
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project ManagementKamuran Koçak
 
The Powerof One+Pmo Overview
The Powerof One+Pmo OverviewThe Powerof One+Pmo Overview
The Powerof One+Pmo OverviewDJ EVERETTE
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
Project charterexample (1) (1)
Project charterexample (1) (1)Project charterexample (1) (1)
Project charterexample (1) (1)owaishazara
 
Introduction of software project management
Introduction of software project managementIntroduction of software project management
Introduction of software project managementREHMAT ULLAH
 
Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Treehouse Agency
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAssociation for Project Management
 
Pmi presentation structuring project v2
Pmi presentation   structuring project v2Pmi presentation   structuring project v2
Pmi presentation structuring project v2Deepak Mehtani
 
Using agile for business process design and development oct 19, 2010 ottawa
Using agile for business process design and development oct 19, 2010 ottawaUsing agile for business process design and development oct 19, 2010 ottawa
Using agile for business process design and development oct 19, 2010 ottawaAdaptiveOrg Inc.
 

What's hot (19)

Organizational Project Management; short workshop
Organizational Project Management; short workshopOrganizational Project Management; short workshop
Organizational Project Management; short workshop
 
Social Media Project Charter Template
Social Media Project Charter TemplateSocial Media Project Charter Template
Social Media Project Charter Template
 
Project Management 02
Project Management 02Project Management 02
Project Management 02
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera Cloud
 
Pe ch 1
Pe ch   1Pe ch   1
Pe ch 1
 
PM Training Slides
PM Training SlidesPM Training Slides
PM Training Slides
 
Avenew Project Management Fundamental
Avenew Project Management FundamentalAvenew Project Management Fundamental
Avenew Project Management Fundamental
 
Project Management Foundations Series Course 102 - Project Management Processes
Project Management Foundations Series Course 102 - Project Management ProcessesProject Management Foundations Series Course 102 - Project Management Processes
Project Management Foundations Series Course 102 - Project Management Processes
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 
Module - PM in Arts, Media, Entertainment
Module - PM in Arts, Media, EntertainmentModule - PM in Arts, Media, Entertainment
Module - PM in Arts, Media, Entertainment
 
The Powerof One+Pmo Overview
The Powerof One+Pmo OverviewThe Powerof One+Pmo Overview
The Powerof One+Pmo Overview
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
Project charterexample (1) (1)
Project charterexample (1) (1)Project charterexample (1) (1)
Project charterexample (1) (1)
 
Emerging Trends in PMO Governance
Emerging Trends in PMO Governance Emerging Trends in PMO Governance
Emerging Trends in PMO Governance
 
Introduction of software project management
Introduction of software project managementIntroduction of software project management
Introduction of software project management
 
Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challenges
 
Pmi presentation structuring project v2
Pmi presentation   structuring project v2Pmi presentation   structuring project v2
Pmi presentation structuring project v2
 
Using agile for business process design and development oct 19, 2010 ottawa
Using agile for business process design and development oct 19, 2010 ottawaUsing agile for business process design and development oct 19, 2010 ottawa
Using agile for business process design and development oct 19, 2010 ottawa
 

Similar to Pm deep dive integration management

PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 
STEVE VEATCH - Resume Feb 2015
STEVE VEATCH - Resume Feb 2015STEVE VEATCH - Resume Feb 2015
STEVE VEATCH - Resume Feb 2015Steve Veatch
 
Applying both of waterfall and iterative development
Applying both of waterfall and iterative developmentApplying both of waterfall and iterative development
Applying both of waterfall and iterative developmentDeny Prasetia
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resumeRajib Paul
 
Rajib paul Resume
Rajib paul   ResumeRajib paul   Resume
Rajib paul ResumeRajib Paul
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resumeRajib Paul
 
James dimas it infrastructure approach
James dimas it infrastructure approachJames dimas it infrastructure approach
James dimas it infrastructure approachJames (JD) Dimas
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmuhammadyasirsaeedqa
 
PMP Training - Project Integration Management - Part 1
PMP Training - Project Integration Management - Part 1PMP Training - Project Integration Management - Part 1
PMP Training - Project Integration Management - Part 1Skillogic Solutions
 
Project integration management ch 4
Project integration management ch 4Project integration management ch 4
Project integration management ch 4Sammer Qader
 
Drs 255 project management skills
Drs 255 project management skillsDrs 255 project management skills
Drs 255 project management skillspaulyeboah
 
Project Management Policy
Project Management PolicyProject Management Policy
Project Management PolicyDemand Metric
 
4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf
4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf
4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdfmovocode
 

Similar to Pm deep dive integration management (20)

PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
STEVE VEATCH - Resume Feb 2015
STEVE VEATCH - Resume Feb 2015STEVE VEATCH - Resume Feb 2015
STEVE VEATCH - Resume Feb 2015
 
ICT 4109.pdf
ICT 4109.pdfICT 4109.pdf
ICT 4109.pdf
 
Applying both of waterfall and iterative development
Applying both of waterfall and iterative developmentApplying both of waterfall and iterative development
Applying both of waterfall and iterative development
 
Resume - Anil Kumar Krishna
Resume - Anil Kumar KrishnaResume - Anil Kumar Krishna
Resume - Anil Kumar Krishna
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resume
 
Rajib paul Resume
Rajib paul   ResumeRajib paul   Resume
Rajib paul Resume
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resume
 
James dimas it infrastructure approach
James dimas it infrastructure approachJames dimas it infrastructure approach
James dimas it infrastructure approach
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
1. introduction
1. introduction1. introduction
1. introduction
 
Ch01
Ch01Ch01
Ch01
 
PMP Training - Project Integration Management - Part 1
PMP Training - Project Integration Management - Part 1PMP Training - Project Integration Management - Part 1
PMP Training - Project Integration Management - Part 1
 
Project integration management ch 4
Project integration management ch 4Project integration management ch 4
Project integration management ch 4
 
Mc PM Resume
Mc PM ResumeMc PM Resume
Mc PM Resume
 
Drs 255 project management skills
Drs 255 project management skillsDrs 255 project management skills
Drs 255 project management skills
 
Project Management Policy
Project Management PolicyProject Management Policy
Project Management Policy
 
4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf
4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf
4-Agility & Agile process, 12 Agile Principles-10-01-2024.pdf
 

More from Niraj Agarwal

Pmp refresher know the exam
Pmp refresher   know the examPmp refresher   know the exam
Pmp refresher know the examNiraj Agarwal
 
Pm deep dive time management
Pm deep dive   time managementPm deep dive   time management
Pm deep dive time managementNiraj Agarwal
 
Pm deep dive the processes
Pm deep dive   the processesPm deep dive   the processes
Pm deep dive the processesNiraj Agarwal
 
Pm deep dive risk management
Pm deep dive   risk managementPm deep dive   risk management
Pm deep dive risk managementNiraj Agarwal
 
Pm deep dive quality management
Pm deep dive   quality managementPm deep dive   quality management
Pm deep dive quality managementNiraj Agarwal
 
Pm deep dive hr - comm - procurement - pr
Pm deep dive   hr - comm - procurement - prPm deep dive   hr - comm - procurement - pr
Pm deep dive hr - comm - procurement - prNiraj Agarwal
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost managementNiraj Agarwal
 
Pm deep dive scope management
Pm deep dive   scope managementPm deep dive   scope management
Pm deep dive scope managementNiraj Agarwal
 
Fundamentals of data structures
Fundamentals of data structuresFundamentals of data structures
Fundamentals of data structuresNiraj Agarwal
 

More from Niraj Agarwal (10)

Pmp refresher know the exam
Pmp refresher   know the examPmp refresher   know the exam
Pmp refresher know the exam
 
Pm deep dive time management
Pm deep dive   time managementPm deep dive   time management
Pm deep dive time management
 
Pm deep dive the processes
Pm deep dive   the processesPm deep dive   the processes
Pm deep dive the processes
 
Pm deep dive risk management
Pm deep dive   risk managementPm deep dive   risk management
Pm deep dive risk management
 
Pm deep dive quality management
Pm deep dive   quality managementPm deep dive   quality management
Pm deep dive quality management
 
Pm deep dive hr - comm - procurement - pr
Pm deep dive   hr - comm - procurement - prPm deep dive   hr - comm - procurement - pr
Pm deep dive hr - comm - procurement - pr
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost management
 
Pm deep dive scope management
Pm deep dive   scope managementPm deep dive   scope management
Pm deep dive scope management
 
Fundamentals of data structures
Fundamentals of data structuresFundamentals of data structures
Fundamentals of data structures
 
Corporate Etiquette
Corporate EtiquetteCorporate Etiquette
Corporate Etiquette
 

Recently uploaded

Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 

Recently uploaded (20)

Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 

Pm deep dive integration management

  • 1. PMP Refresher Project Integration Management - Niraj Agarwal May 2011 Slide 1
  • 2. Project Integration Management Definition • It includes the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. • The bringing together of diverse organizations, groups or parts to form a cohesive whole to successfully achieve PROJECT OBJECTIVES. • Processes to bring different elements of project together so that they are properly coordinated to meet or exceed stakeholders expectations. • These processes may occur repeatedly over the project duration • Historical Records are needed to perform project management well, they are inputs to continuous improvement -> Files, Lessons Learned, Actual Costs, Time Estimates, WBS, Benchmarks, Risks. May 2011 Slide 2
  • 3. Project Integration Management Elements to Integrate • Knowledge Areas—Scope, Time, Cost, Quality etc. • Organizations • Stakeholder Requirements • Technical Elements • People • Communications • Product Scope Components • Phases Integration requires that all these Elements are brought together holistically and aligned in the direction of the project Goals! May 2011 Slide 3
  • 4. Project Integration Management The Processes Develop Project Charter – developing the project charter that formally authorizes a project or a project phase. Develop Project Management Plan – documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan. Direct and Manage Project Execution – executing the work defined in the project management plan to achieve the project’s requirements defined in the project scope statement. May 2011 Slide 4
  • 5. Project Integration Management Processes Monitor and Control Project Work – monitoring and controlling the processes used to initiate, plan, execute, and close a project to meet the performance objectives defined in the project management plan. Integrated Change Control – reviewing all change requests, approving changes, and controlling changes to the deliverables and organizational process assets. Close Project – finalizing all activities across all of the Project Management Process Groups to formally close the project or a project phase. May 2011 Slide 5
  • 7. Develop Project Charter May 2011 Slide 7
  • 8. Develop Project Charter What is Project Charter • Formally recognizes project, created by senior manager, includes: - Business need/Business Case - Product description & title - Signed contract - Project Manager Identification & Authority level - Senior Management approval - Project’s Goals and Objectives - Constraints – factors that limit project management team’s options - Assumptions – factors that are considered true for planning purposes. Involve a degree of risk May 2011 Slide 8
  • 9. IceScream – Case Study Background You work for a midsize ice-cream company called IceScream in the Kolkata. Business has been very, very good! Ice-cream is popular all over the state. The owner, Anvita, has decided to set up shop in other cities: Delhi, Mumbai, and Bangalore. She has established strong partnerships in these areas and is now ready to connect the three sites together into one network so that she can keep track of the daily activities of each location. The prospective new locations are as follows: Delhi - Anvita wants to set up a regional distributorship with Sonia Gandhvi’s Delhi Kulfi (DK), utilizing DK’s special skills to improve the quality of the ice-creams. Mumbai – SRK has been making wonderful Barf ka Gola for several years now. SRK is interested in branching out nationally and understands that a partnership such as the one with Ice-Scream would be beneficial for both companies. Bangalore – Vijay Wallya has been dishing out ice-cream idly & dosas which are a personal favourite of Anvita. May 2011 Slide 9
  • 10. IceScream – Case Study The Work • Anvita has entered into financial agreements and working partnerships that give her a partial stake in the profits of each of the ice-cream companies, while allowing them to retain their original look and feel and maintain the management of their day-to-day operations. • The people who work for each entity will ultimately report to Anvita, but each Ice-cream company is free to continue doing what it does best. Anvita has committed to not interfere. • You have been with IceScream, serving as the head of IT, since the installation of one small file server on which Anvita kept the spreadsheets for the various accounts. • Today Anvita told you that she wants you to install an email server in each of the other three locations, connecting them so that everyone can communicate with one another and all employees’ email addresses are in the global address list. She also wants an intranet site set up so that the new releases and other communications are available to everyone for comment and approval. May 2011 Slide 10
  • 11. IceScream – Case Study Needs & Stakeholders Basic requirements - You have two requirements that you must fulfil: • Set up an email system for all four sites. • Set up an intranet. Stakeholders - Anvita is the project sponsor. In addition to her, there are three primary stakeholders: Sonia Gandhvi , SRK, Vijay Wallya Other key staff members within each of the ice-cream companies are stakeholders on the project as well. They most likely include the general manager, director of sales, accounting director, and human resources director. Now that you have identified the stakeholders and understand the requirements for the project, you set about gathering the goals for the project, including the due date, high-level milestones, key deliverables, estimated costs, assumptions, constraints, and high-level risks. May 2011 Slide 11
  • 12. Icescream – Case Study Assumptions, Constraints & Risks Assumptions - IT personnel are available at each Ice-cream company (or you are able to hire consultants) to assist with all the technical aspects of implementing this project. English will be the primary language for all communications. Constraints - This project has a budget of INR 1,000,000. Each site requires new hardware, a backup solution, ISP, licensing fees, contract help, and so on. High-level risks - Downtime at one or more of the sites. Security intrusions. Improper training of users on the use of the intranet site. You document the project charter, and Anvita signs it, authorizing the project to begin. May 2011 Slide 12
  • 13. Develop Project Management Plan Definition • This process includes the actions necessary to define, integrate, and coordinate all subsidiary plans into a project management plan. • It uses the outputs of the other planning processes to create a consistent, coherent document that can be used to guide both project execution and project control. • Document project planning assumptions • Provide a baseline for progress measurement and project control May 2011 Slide 13
  • 14. Develop Project Management Plan Project Plan • A comprehensive set of documents used to guide execution of Project work to monitor project status, collect and disseminate performance information, progress measurement, manage changes and control the project work. • It is a dynamic document in the sense that, it is updated and changes with progressive elaboration of project. • It includes all performance baselines which changes only intermittently. • It consists of Subsidiary Management Plans. May 2011 Slide 14
  • 15. Develop Project Management Plan May 2011 Slide 15
  • 16. Direct and Manage Project Execution Definition • Is the actual performance of all project activities to create the project product . • Requires the project manager and the project team to perform multiple actions to execute the project management plan • The vast majority of the project efforts and cost will be expended in performing the execution process • Staff, train, and manage the project team members assigned to the project • Managing the technical and organizational project interfaces • Performance monitoring & Periodic forecasts of final cost and schedule results to support the analysis • Collect and document lessons learned, and implement approved process improvement activities. May 2011 Slide 16
  • 17. Direct and Manage Project Execution ITTO May 2011 Slide 17
  • 18. Direct and Manage Project Execution May 2011 Slide 18
  • 19. Monitor and Control Project Work Definition This process is performed to monitor project processes associated with initiating, planning, executing, and closing. Corrective or preventive actions are taken to control the project performance. Monitoring is an aspect of project management performed throughout the project. It includes collecting, measuring, and disseminating performance information, and assessing measurements and trends to effect process improvements. May 2011 Slide 19
  • 20. Monitor and Control Project Work ITTO May 2011 Slide 20
  • 21. Perform Integrated Change Control Definition • Determine that a change has occurred • Coordinates Changes across all knowledge areas—entire project • Ensures that the changes are beneficial • Reviewing and approving all recommended corrective and preventive actions. • Managing the actual changes when and as they occur • Maintain integrity of any performance measurement baseline. • Ensures that changes are reflected in the scope definition and product specifications • Documenting the complete impact of requested changes. May 2011 Slide 21
  • 22. Perform Integrated Change Control ITTO May 2011 Slide 22
  • 24. Close Project Definition • It involves performing the project closure portion of the project management plan. • In multi-phase projects, the Close Project process closes out the portion of the project scope and associated activities applicable to a given phase. • This process includes finalizing all activities completed across all Project Management Process Groups to formally close the project or a project phase, and transfer the completed or cancelled project as appropriate. • The Close Project process also establishes the procedures to coordinate activities needed to verify and document the project deliverables, to coordinate and interact to formalize acceptance of those deliverables by the customer or sponsor, and to investigate and document the reasons for actions taken if a project is terminated before May 2011 completion. Slide 24
  • 25. Close Project ITTO May 2011 Slide 25
  • 26. Pop Quiz Question 1 Randy is a key technical resource for your project. You have worked with Randy on past projects and have identified him in the project charter as one of the team members who will work on the project. The charter has been published, and there is great excitement about this project. You have scheduled a meeting to talk to Randy ’ s functional manager next week. Which of the following conditions does this describe? A. Risk B. Assumption C. Deliverable D. Constraint May 2011 Slide 26
  • 27. Pop Quiz Question 2 From the following options, select those that best describe the definition of a deliverable. (Choose three.) A. Marks the completion of a project phase B. Has measurable outcomes or results C. Is a specific item that must be produced to consider the project complete D. Describes the characteristics of the product of the project E. Is documented in the project charter F. Is tangible and easily verified May 2011 Slide 27
  • 28. Pop Quiz Question 3 From the following options, select the one that does not describe a constraint. A. Project team actions are dictated. B. It may regard budget, resources, or schedule. C. Project team actions are restricted D. Project situations are believed to be true. May 2011 Slide 28
  • 29. Pop Quiz Question 4 Your project is to be performed outdoors. You are only four days from the big event, and there is a hurricane headed for shore. This is an example of which of the following? A. Risk B. Assumption C. Deliverable D. Constraint May 2011 Slide 29