PulseResident Newsletter | Winter 2015/2016
KEEPING YOU INFORMED.
In every quarterly issue of the Parkmerced Pulse, you’ll find important updates on the progress of implementing
the Parkmerced Vision. In early 2016 you will begin seeing the property being prepared for construction and
we’re committed to keeping you informed —and welcome your questions, comments, and concerns at any time.
WHAT IS THE PARKMERCED VISION?
The Parkmerced Vision is a long-term (approximately 20-30 years) project to
comprehensively replan and redesign Parkmerced. The Parkmerced Vision was
approved by the City of San Francisco in 2011. The project will be constructed
in phases, with construction of the Project’s Subphases 1A and 1B expected to
begin in Spring and Summer 2016, respetively. Additional information about the
Parkmerced Vision is available at parkmercedvision.com.
July 2011: Project Entitlement and Development Agreement Approved
May 2015: Development Phase 1 Application Approved
August 2015: Tentative Subdivision Maps for Subphases 1A and 1B Approved
October through December 2015: Design Review Applications Approved
August 2015
•	 On August 6 we provided the Planning Commission staff with an update on
Phase I of the project and held an informational Design Review hearing.
September 2015
•	 On September 9 we invited residents from the 56 to-be-replaced apartments
to join us to learn more about their anticipated move.
•	 On September 29 an appeal hearing for Teantative Subdivision Maps
pertaining to Subphases 1A and 1B was held by the San Francisco Board of
Supervisors (BOS). The BOS unanimously denied the appeal.
November 2015
•	 Revised Street Improvement Plans submitted to City Agencies for review.
December 2015
•	 On December 17, a tree removal hearing was held by the San Francisco
Department of Public Works following the submittal of a tree-removal
application. A decision on the application is pending. For more information on
tree removals as part of Subphase 1A and 1B, please see page 3.
RESIDENT AND COMMUNITY PARTICIPATION
Since late 2006, we’ve held well over 500 meetings with our residents, neighbors
and other stakeholders, ranging from small group briefings to large public
workshops. We look forward to continued discussions throughout the coming
months and beyond.
Parkmerced Resident Newsletter 1
RESIDENT PROTECTION
Parkmerced is committed to protecting residents’ rent-controlled apartments for
as long as they choose to live at Parkmerced.
The Parkmerced Vision involves removing and replacing all garden apartment
homes within Parkmerced in phases over the next 20-30 years. Subphase 1A
includes the construction of 56 replacement apartment homes for residents of to-
be-replaced apartments on existing blocks 37W, 34, and 19 (see map on page 5).
To protect our existing residents living at Parkmerced, prior to the replacement
of any existing rent-controlled apartment, Parkmerced will provide the resident
who lives in a to-be-replaced building with an apartment within one of the newly
constructed buildings in Parkmerced.
•	 New apartment homes will be rented at the same rent-controlled rate as the
existing apartments prior to demolition (and also subject to rent increase
limitations of the San Francisco Rent Control Ordinance).
•	 New apartments will be constructed prior to the replacement of existing
apartments. This ensures that affected residents only need to move once into
their new apartment and will not be displaced.
•	 Parkmerced will cover all moving expenses from residents’ existing units to
their brand new replacement unit. Additionally, moving services, including
packing and unpacking, will be paid for by Parkmerced.
Replacement apartments will:
•	 be comparable in size to existing units with the same number of bedrooms
and bathrooms, and in some cases more;
•	 be constructed with improved accessibility, making it more convenient for our
elderly and/or disabled residents;
•	 inlude brand new energy efficient appliances and new fixtures including
dishwashers and a washer/dryer; and
•	 be more comfortable due to better construction, including insulated walls and
efficient windows.
PARKMERCED AT FULL BUILD OUT
Parkmerced Resident Newsletter 3
PREPARING FOR CONSTRUCTION
The Parkmerced Vision will be constructed in discrete major phases, with
Subphases 1A and 1B expected to break ground in the Spring/Summer 2016.
Tree Removal: To prepare for street realignments, new buildings, and redesigned
open spaces, the tree removal process, which was anticipated in the Parkmerced
Project’s Environmental Impact Report (EIR), is scheduled to occur in early
2016. On December 17, 2015, a public hearing was held by the San Francisco
Department of Public Works to review Parkmerced’s tree removal permit
applications. The tree removal permits are anticipated to be approved by January
2016 with tree removals occurring shortly thereafter. For every tree that is
removed in Subphase 1A and 1B, approximately 3 new trees will be planted in
their place within Parkmerced.
Site Surveys: You may have noticed consultants collecting soil samples over the
past several months. This work is serving several purposes, such as understanding
soil suitability for new landscaping, assessing the soil’s ability to absorb or convey
water during storms or heavy rain, and determining its composition to ensure it
will provide a foundation for new planned buildings.
Cultural Resources: A Historic American Buildings Survey (HABS) and a Historic
American Landscapes Survey (HALS) are being completed to document
Parkmerced as a large-scale planned master residential development and
celebrate the work of master landscape architect Thomas Dolliver Church and
his colleague Robert Royston. Two interpretive displays will be installed in open
space around Parkmerced and a digital display will be installed in the leasing
office to demonstrate HABS/HALS findings. Further, the final report and plans
will be submitted to the History Room of the San Francisco Public Library and the
Northwest Information Center of the California Historical Information Research
System. Digital copies of the HALS/HABS reports will be made available online
at parkmercedvision.com and in Resident Services once the reports are finalized.
Original drawings will be donated to the University of California, Berkeley.
Wind Studies: To ensure wind conditions are consistent with those studied as part
of the Project’s Environmental Impact Report (EIR), wind tunnel tests have been
conducted for each new proposed building.
PARKING RELOCATION
Subphases 1A and 1B of the Parkmerced Vision include the replacement of
two existing parking garages (the Felix and Galindo garages) and two surface
parking lots (Arballo Circle and Chumasero surface lots). Prior to the removal of
the garages and surface lots, Parkmerced will work with affected residents who
currently have parking spaces at these locations to relocate their spaces. For
a majority of residents, parking spots will be relocated to the existing Higuera
Garage. The Higuera Garage may be accessed either from Higuera Avenue or
Garces Drive (see map on Page 5). Understanding that relocating parking spaces
to Higuera Garage may pose as a burden to those with special needs, Parkmerced
will work with these residents on a case-by-case basis to find a parking space
within a nearby existing carport as they are available.
At the time residents’ parking is relocated, Parkmerced will initiate a free resident
shuttle that will transport residents to locations within Parkmerced (including
Higuera Garage) as well as to Daly City BART Station. The shuttle will run on a
published schedule and stop locations will be placed conveniently throughout the
property and specifically around the eastern side of the property. Further details
regarding the shuttle will be in a future issue of the Parkmerced Pulse.
For residents that have parking spaces in Felix or Galindo garages or the Arballo
Circle or Chumasero surface lot, an informational meeting will be held in Spring
2016 prior to relocation. Invitations for this meeting and parking relocation
materials will be sent via certified mail in early 2016.
PARKING FOR NEW BUILDINGS
Higuera Garage will also be the closest available garage to the first buildings
constructed at 300 Arballo and 199 Vidal (see Subphase 1A and 1B map on Page
5). The overall parking plan includes new subterranean parking garages in the
majority of new buildings. Overall, Parkmerced will be able to construct up to one
(1) off-street parking space per apartment at Parkmerced. On-street parking will
also continue to be available around Parkmerced similar to as it is today.
The approved Parkmerced Vision also includes a detailed Transportation Plan
designed to improve all existing transportation modes and encourage residents
to take advantage of the convenient current and future transportation options.
We will be expanding our on-site carshare program as well as implementing a bike
share program with “bicycle libraries” located throughout the property. Of course,
a renewed emphasis will also be placed on walking, pedestrian safety, and transit.
A Look Back: Fall 2015
•	 Tenant Relocation Packets mailed to residents
in to-be-replaced apartments in existing blocks
37W, 34, and 19 (refer to map on Page 5)
•	 Invitation-only resident meeting for residents
in to-be-replaced apartments in existing blocks
37W, 34, and 19 (refer to map on Page 5)
Early 2016
•	 General residents meeting (January 19, 2016)
•	 Parking relocation meeting (Date TBD)
•	 Subphases 1A and 1B Development Site
Preparation: Phase 1 Subphases A and B tree
removal begins
Parkmerced Resident Newsletter 4
RESIDENT COMMUNICATION AND PRELIMINARY CONSTRUCTION SCHEDULE
RELOCATION PROCESS: EXISTING BLOCKS 37W, 34, and 19
SPRING/SUMMER
2015
FALL 2015 SPRING 2016 SPRING 2017
LATE
2017
Public
Meeting
Invitations
Existing
Tenant
Notice
Unit
Availability
Notice
Selection of
Replacement
Unit
Relocation
Notice
Moving
Services
Public Meetings
•	 Learn your tentative moving timeline
•	 Receive a copy of the Tenant Relocation
Plan
•	 Learn about the construction timeline
•	 View a project map
•	 VIew floor plans of the new units and
new buildings, if available
•	 An informational Tenant Relocation
Plan sent to the first to-be-replaced
apartments
Spring 2016: Initial Notice
•	 Confirm your seniority for the Unit Selection Process
•	 Receive Rent Board information on your rights as a tenant
Spring 2017: Unit Availability Notice
•	 Begin the Unit Selection Process
•	 Be invited to multiple Open Houses so that you can see a sample
unit and pick your preferred unit layout
•	 Rank your preferred replacement units for Unit Selection
Selection of Replacement Unit
•	 Receive results of Unit Selection Process
•	 Find out your future unit and address
•	 Confirm that you plan to move into the unit
Relocation Notice
•	 Receive notice that your unit is move-in
ready
•	 Work with Parkmerced to finalize a
Moving Day that works best for you
Moving Services
•	 Receive free moving services
•	 Settle into your new unit!
Informational
Tenant Relocation
Plan
WE ARE
HERE
WE ARE HERE
Mid 2016
•	 Break ground on Phase 1 Subphase A (~18-21
month construction)
•	 Break ground on Phase 1 Subphase B (~29-32
month construction)
•	 Submit Final Map for Phases 1A & 1B for approval
•	 Existing playground replacement/relocation
Parkmerced will provide multiple written notices to keep residents informed of the relocation timeline
Parkmerced Resident Newsletter 5
DEVELOPMENT SUBPHASES 1A AND 1B SITE MAP
Parkmerced Resident Newsletter 6
Where can I find up-to-date project information?
To stay informed with project progression and milestones, we welcome you to visit
parkmercedvision.com, email info@parkmercedvision.com, call 415.405.4666, and
look for our quarterly newsletter with updates.
If I have a question or concern about the noise levels on the property when
construction starts, who should I get in touch with?
Prior to the start of construction, Parkmerced will designate a Noise Disturbance
Coordinator that will be available to take calls and inquiries through the duration
of the construction process. The contact information of the coordinator will be
posted outside of each construction site, published in the next newsletter, and
available at parkmercedvision.com.
What will the construction hours be each day?
The San Francisco Police Code details specific hours during which construction
is allowed to take place. For projects under construction in San Francisco,
construction can occur between the hours of 7:00 AM and 8:00 PM, seven days
per week, including holidays. Any work done outside of these hours must not
exceed the noise level of five decibels at the nearest lot line. For the Parkmerced
project specifically, most work will take place between 7:00 AM and 4:30 PM daily
with no work currently planned for Sundays.
Having parking spaces in front of the existing towers is very important to
residents. During construction, will these spaces be eliminated?
The parking spaces next to and in front of the towers will continue to be available
to residents throughout the construction process with the exception of 310/350
Arballo Drive, 100/150 Font Boulevard, and 55 Chumasero Drive. The driveways
at 310/350 Arballo Drive, 100/150 Font Boulevard, and 55 Chumasero will be
reconfigured as part of the Subphase 1A and 1B development and unavailable
for extended periods during construction. We will work with our Contractors to
phase construction in such a way to provide temporary parking where possible.
Generally, the number of affected spaces at these locations will return at the end
of each subphase with similar parking restrictions with a new configuration. More
information will be distributed to our residents on a building-by-building basis as
we learn more about expected construction impacts and space needs.
FREQUENTLY ASKED QUESTIONS
Which building(s) will be constructed first?
In Subphase 1A, Block 1 buildings (199 Vidal Drive and 300 Arballo Drive) will
be constructed first. These buildings will include the first 56 replacement units.
Additionally, Subphase 1A includes the construction of 455 Serrano and 850
Gonzalez on Block 6. In Subphase 1B, construction includes Block 20 (1208 -
1218 Junipero Serra Boulevard) and Block 22 (95-99 Chumasero Drive). See map
included on Page 5.
How long will construction last for Subphases 1A & 1B?
Construction lengths will vary depending on building size and complexity.
Buildings and street improvements in Subphase 1A are expected to take 18-21
months to complete; buildings and street improvements in Subphase 1B are
expected to take 29-32 months to complete.
I currently have a parking space in a Galindo/Felix/Arballo Circle parking area.
When will I get more info about parking relocation?
Affected residents will be notified in early 2016 with details. Garage preparation
and deconstruction will begin as early as June 2016, so we anticipate residents’
parking relocation to take place in late Spring 2016. This timeline is subject to
change based on the project’s overall construction schedule.
Architect: Fougeron Architecture
Units: 64 homes (40 replacement)
Bike Parking: 64 spaces
Architect: Leddy Maytum Stacy
Units: 89 homes (16 replacement)
Bike Parking: 89 spaces
Parkmerced Resident Newsletter 7
CONSTRUCTION IN 2016: WHAT TO EXPECT
Construction of Subphases 1A and 1B are expected to begin in Spring and
Summer 2016, respectively. Parkmerced understands that the residents have
concerns about the effect of construction on their quality of life. Residents can
rest assured that Parkmerced is committed to making diligent efforts to maintain
a comfortable living environment during construction of all phases of the
Parkmerced Vision through continual communication and transparency.
Construction contractors on site will adhere to all applicable laws and regulations
during the construction process, as well as obligations and mitigations identified
in the Project’s Environmental Impact Report (EIR). These regulations will ensure
that residents experience as little disruption as possible from construction noise
and vibration, road closures, construction dust, etc. A summary of several of
the construction-related mitigation measures that the project will adhere to are
described below.
Transportation, Circulation, and Parking
Parkmerced is developing a Construction Traffic and Parking Management
Plan to ensure that traffic and parking management best practices are used
during construction. The Plan will be reviewed and approved by the City prior
to the commencement of construction. A cohesive plan for maintaining traffic
operations during all times of day and periods of construction will be included in
the Traffic and Parking Management Plan. Where possible, Parkmerced will work
to ameliorate added traffic and parking impacts from nearby construction projects
(e.g. San Francisco State University) and coordinate.
Noise
The San Francisco Police Code sets noise restrictions and guidelines that all
construction projects in San Francisco must follow. Consistent with these
requirements, our construction hours will be restricted to 7:00 AM to 8:00 PM.
However, it is anticipated that our construction hours will be 7:00 AM to 4:30 PM
on typical days. Specific measures for reducing noise levels during construction
will include practices such as:
•	 requiring that stationary equipment, such as generators and augers, to be
modified to reduce noise;
•	 installing barriers around particularly noisy activities that are designed to
minimize noise;
•	 using equipment with lower noise emission ratings whenever possible;
•	 locating stationary equipment, material stockpiles, and vehicle staging areas as
far from existing residents’ homes where feasible; and/or
•	 requiring construction-related vehicles and equipment to use designated truck
routes to access project sites. This includes minimizing construction-related
traffic between Subphases 1A and 1B sites.
In addition to meeting these noise requirements, Parkmerced will also have a
Noise Disturbance Coordinator that residents will be able to contact throughout
the duration of construction. The contact information of this coordinator will be
included in a future newsletter and will be posted at or near the entrances of each
construction site. Additionally, you can always contact a project representative on
the Vision Information line at 415.405.4666.
199 VIDAL 300 ARBALLOPLANNED NEW CONSTRUCTION:
SUBPHASE 1A AND 1B
Development Subphases 1A and 1B will include the
construction of 7 new residential buildings by 5 different
architects. The basis of the architectural design is being
driven by the adopted Design Standards & Guidelines,
but each design is unique. Similar to how growth occurs
throughout San Francisco, over time Parkmerced will look,
feel, and grow more organically.
Biological Resources
Great care will be taken around certain plant and animal species in Parkmerced
property during all phases of construction. During construction of Subphases 1A
and 1B, efforts will be focused on protecting the breeding bird population and
completing required tree removal, detailed below.
Birds: A bird survey will be conducted prior to any construction activities,
especially tree removals. If active nests are found in the work area, a buffer will be
established and no construction will be allowed within a defined distance of the
nest until the young have successfully fledged.
Tree Removal: Certain trees must be removed to prepare for property
improvements such as sidewalks, bike lanes, stormwater systems, roadways,
utilities, and new landscaping. In Subphases 1A and 1B, 120 trees have been
posted for removal. The overall site strategy involves an expanded planting of new
trees of various sizes for each one removed at an approximate ratio of 3 to 1.
Subsequent Phases: Other plant and animal species that may be affected by
construction have been identified and studied in the Project EIR. Many plant and
animal species are unique to specific georgraphic locations within Parkmerced and
appropriate mitigations have been tailored to respond to potential impacts on a
location-by-location basis.
--
The next issue of the Parkmerced Pulse will take an in-depth look at all
construction related activities and the effect of these activities to residents and
neighbors. Full text for the Mitigation Monitoring and Reporting Program (MMRP)
approved as part of the Project’s Environmental Impact Report (EIR) can be found
on SF Planning’s Parkmerced Project page at http://www.sf-planning.org/index.
aspx?page=2529.
Parkmerced Resident Newsletter 8
Air Quality
The San Francisco Planning Department, the Department of Building Inspections
and the Bay Area Air Quality Management District have established guidelines
to maintain proper air quality at and near construction project sites. Measures in
place to reduce construction related emissions include:
•	 making sure that equipment and trucks are regularly serviced to minimize
exhaust emissions;
•	 requiring construction contractors to shut down engines when they are not in
use;
•	 strategic placement of signage for construction workers at all access points for
efficient travel into and around Parkmerced;
•	 use of equipment with engines that meet emission reduction standards set
forth by the US Environmental Protection Agency (EPA); and
•	 requiring that construction contractors operate haul trucks which are 2007 or
newer models.
Also, because certain phases of the construction process generates dust,
measures to minimize dust, both during and after work hours, will be in place.
Dust control measures may involve watering or covering exposed soils and
installing sediment traps throughout the construction sites. Beyond current
requirements, Parkmerced is also looking into including wash down stations for
construction trucks, vehicles, and equipment entering and exiting the site as
appropriate and able. As required per the Project’s Environmental Impact Report
(EIR), Parkmerced will have the air quality in and around construction sites
monitored regularly.
455 SERRANO / 850 GONZALEZ 95-99 CHUMASERO1208-1218 JUNIPERO SERRA
Architect: Woods Bagot
Units: 248 homes
Unbundled Parking: 429 spaces
Bike Parking: 250 spaces
Architect: Kwan Henmi
Units: 299 homes
Unbundled Parking: 343 spaces
Bike Parking: 332 spaces
Architect: Skidmore, Owings and Merrill
Units: 313 homes
Unbundled Parking: 266 spaces
Bike Parking: 160 spaces
Parkmerced Resident Newsletter
9
AREAS IMPACTED BY CONSTRUCTION IN SUBPHASES 1A & 1B
•	 Subphases 1A and 1B construction will impact the areas shaded in orange
below.
•	 All existing towers will remain intact during all phases of construction of the
Parkmerced Vision.
•	 In addition to new buildings being constructed, a street improvements plan
(SIP) and corresponding permit is also being implemented. The SIP will include
road resurfacing, new sidewalks, improved landscaping, bike lanes, additional
street lighting, and new utility lines. The following streets will be included in
the SIP: Vidal Drive, Acevedo Avenue, Arballo Drive, Higuera Avenue, Serrano
Avenue, Gonzalez Drive, Lake Merced Boulevard in Subphase 1A; Font
SUBPHASE 1A SUBPHASE 1B
100 Font Blvd
150 Font Blvd
125 Cambon Dr
55 Chumasero Dr
50 Chumasero Dr
310 Arballo Dr
350 Arballo Dr
405 Serrano Dr
810 Gonzalez Dr
IMAGE SOURCE: GOOGLE EARTH
800 Brotherhood Way
Boulevard, Chumasero Drive, Brotherhood Way, and Junipero Serra Boulevard
in Subphase 1B.
•	 In the next issue of the Parkmerced Pulse, we will provide further details on
efforts to prepare residents for what to expect during construction. It is a
top priority to keep residents informed as we develop details around how
construction might impact the broader Parkmerced community.
ANNOUNCEMENTS
Scholarship & Internship Program
To view the full application form and requirements, visit parkmercedvision.com,
email opportunities@parkmercedvision.com, or call 415.405.4666.
2016 Parkmerced Robert L. Pender Memorial Scholarship
Applications Available early 2016, due May 2016
The Parkmerced Robert L. Pender Memorial Scholarship was established to
encourage the pursuit of career paths in engineering, architecture, urban planning,
and related fields. The $1,000 scholarship will be awarded to any full-time student
pursuing undergraduate or graduate studies in engineering, architecture, urban
planning, or a related field. Priority will be given to students enrolled at San
Francisco State University or City College of San Francisco.
2016 Parkmerced Vision Intern Program
Applications Available Spring 2016, due June 2016
Parkmerced is currently accepting applications for our 2016 Parkmerced Vision
Intern Program based in San Francisco, California. Up to two (2) applicants may be
selected to participate. The position is paid and will occur over a 6-month period.
Parkmerced will give priority to students currently enrolled at San Francisco State
University or City College of San Francisco in urban design, planning, architecture,
engineering, or related programs.
Save the Date: Resident Meeting
When: 	 Tuesday, January 19, 2016, 6pm - 8pm
Where: 	St. Thomas More, Carroll Hall
	 1300 Junipero Serra Boulevard at Brotherhood Way
Please join us at our next meeting open to all existing Parkmerced residents
where we will be providing an update on the Parkmerced Vision Plan. A shuttle
will be provided with pick-up locations at the Parkmerced Leasing Office and
810 Gonzalez Drive; the shuttle will operate on a loop beginning at 5:30PM until
8:30PM. Refreshments will be served. We look forward to seeing you there!
To stay up-to-date with the latest information at Parkmerced, look for the
next issue of Parkmerced Pulse, visit parkmercedvision.com, email info@
parkmercedvision.com, or call 415.405.4666.
Parkmerced Resident Newsletter 10
CONTACT INFORMATION
Parkmerced Vision
Attn: Development Manager
3711 Nineteenth Avenue
San Francisco, CA 94132
info@parkmercedvision.com
415.405.4666
parkmercedvision.com
Parkmerced Resident Services
1 Varela Avenue
San Francisco, CA 94132
services@parkmerced.com
415.405.4600
parkmerced.com
San Francisco Planning Department
Joshua Switzky
1650 Mission Street, Suite 400
San Francisco, CA 94103
joshua.switzky@sfgov.org
415.558.6378
You can also view all public documents on the Planning Department Parkmerced
Project Page: http://www.sf-planning.org/index.aspx?page=2529.
San Francisco Rent Board
25 Van Ness Avenue, Suite 320
San Francisco, CA 94102
415.252.4602
Provides counseling information on subjects covered by the Rent Ordinance. You can
speak with a counselor during weekday counseling hours (9am - Noon and 1 - 4pm).
Counselors are also available at the Rent Board office 8am - 5pm, Monday through
Friday, excluding holidays.
Residents’ Organization
Parkmerced Residents Organization
Any group of tenants interested in becoming a recognized residents’ organization can do
so by notifying Parkmerced and the San Francisco Planning Department of
its formation in writing. To formally be recognized, the group must show proof that
they have more than 10 members (defined as tenants of Parkmerced, each occupying
a separate unit) and have been in existence for at least 24 months. Please contact Bert
Polacci at 415.405.4666 for more information or email info@parkmercedvision.com.
415.405.4666
parkmerced.com
info@parkmercedvision.com

More Related Content

What's hot

Tantallon tweaks slideshow2 a
Tantallon tweaks slideshow2 aTantallon tweaks slideshow2 a
Tantallon tweaks slideshow2 a
Marcus Garnet
 
Tantallon crossroads briefing
Tantallon crossroads briefingTantallon crossroads briefing
Tantallon crossroads briefingMarcus Garnet
 
Building plans
Building plansBuilding plans
Building plans
Mariette Van Zyl
 
Group housing case study
Group housing case studyGroup housing case study
Group housing case study
Vishwas Sahni
 
Affordable Housing Design at Hathazari
Affordable Housing Design at HathazariAffordable Housing Design at Hathazari
Affordable Housing Design at Hathazari
Anik Gouala
 
Riverhaven design guidelines
Riverhaven design guidelinesRiverhaven design guidelines
Riverhaven design guidelinesRiverhaven
 
A_Oeth_Portfolio_LinkedIn
A_Oeth_Portfolio_LinkedInA_Oeth_Portfolio_LinkedIn
A_Oeth_Portfolio_LinkedInAmy Oeth
 
Conscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochure
Conscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochureConscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochure
Conscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochure
Ashwani Kumar
 
20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final
Jeremy Chin
 
A&M Super Storage Rezoning
A&M Super Storage RezoningA&M Super Storage Rezoning
A&M Super Storage Rezoning
City of College Station
 
January 19, 2016 Parkmerced Vision Update
January 19, 2016 Parkmerced Vision UpdateJanuary 19, 2016 Parkmerced Vision Update
January 19, 2016 Parkmerced Vision Update
parkmercedvision
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Fairfax County
 
Suburban Commercial Zoning Changes
Suburban Commercial Zoning ChangesSuburban Commercial Zoning Changes
Suburban Commercial Zoning Changes
City of College Station
 
Item # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool RenovationsItem # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool Renovations
ahcitycouncil
 
VBHC Palmhaven - Upcoming Project Kengeri Bangalore
VBHC Palmhaven - Upcoming Project Kengeri Bangalore VBHC Palmhaven - Upcoming Project Kengeri Bangalore
VBHC Palmhaven - Upcoming Project Kengeri Bangalore
hquaiser
 
Blurring the Llines - Dibakar Chintala
Blurring the Llines - Dibakar ChintalaBlurring the Llines - Dibakar Chintala
Blurring the Llines - Dibakar Chintala
WRI Ross Center for Sustainable Cities
 
Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017
Brian Hong
 
Equis Lake Design Guidelines Brochure
Equis Lake Design Guidelines BrochureEquis Lake Design Guidelines Brochure
Equis Lake Design Guidelines Brochure
EquisLake the Vine
 
HOUSING CASE STUDY
HOUSING CASE STUDYHOUSING CASE STUDY
HOUSING CASE STUDY
Integral University
 

What's hot (19)

Tantallon tweaks slideshow2 a
Tantallon tweaks slideshow2 aTantallon tweaks slideshow2 a
Tantallon tweaks slideshow2 a
 
Tantallon crossroads briefing
Tantallon crossroads briefingTantallon crossroads briefing
Tantallon crossroads briefing
 
Building plans
Building plansBuilding plans
Building plans
 
Group housing case study
Group housing case studyGroup housing case study
Group housing case study
 
Affordable Housing Design at Hathazari
Affordable Housing Design at HathazariAffordable Housing Design at Hathazari
Affordable Housing Design at Hathazari
 
Riverhaven design guidelines
Riverhaven design guidelinesRiverhaven design guidelines
Riverhaven design guidelines
 
A_Oeth_Portfolio_LinkedIn
A_Oeth_Portfolio_LinkedInA_Oeth_Portfolio_LinkedIn
A_Oeth_Portfolio_LinkedIn
 
Conscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochure
Conscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochureConscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochure
Conscient habitat residences sector 78 Daridabad | 9911 81-6000 | brochure
 
20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final
 
A&M Super Storage Rezoning
A&M Super Storage RezoningA&M Super Storage Rezoning
A&M Super Storage Rezoning
 
January 19, 2016 Parkmerced Vision Update
January 19, 2016 Parkmerced Vision UpdateJanuary 19, 2016 Parkmerced Vision Update
January 19, 2016 Parkmerced Vision Update
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
 
Suburban Commercial Zoning Changes
Suburban Commercial Zoning ChangesSuburban Commercial Zoning Changes
Suburban Commercial Zoning Changes
 
Item # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool RenovationsItem # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool Renovations
 
VBHC Palmhaven - Upcoming Project Kengeri Bangalore
VBHC Palmhaven - Upcoming Project Kengeri Bangalore VBHC Palmhaven - Upcoming Project Kengeri Bangalore
VBHC Palmhaven - Upcoming Project Kengeri Bangalore
 
Blurring the Llines - Dibakar Chintala
Blurring the Llines - Dibakar ChintalaBlurring the Llines - Dibakar Chintala
Blurring the Llines - Dibakar Chintala
 
Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017
 
Equis Lake Design Guidelines Brochure
Equis Lake Design Guidelines BrochureEquis Lake Design Guidelines Brochure
Equis Lake Design Guidelines Brochure
 
HOUSING CASE STUDY
HOUSING CASE STUDYHOUSING CASE STUDY
HOUSING CASE STUDY
 

Similar to Parkmerced Pulse (Issue 3, January 2016)

Summary - Wilmot Creek Phase 8
Summary - Wilmot Creek Phase 8Summary - Wilmot Creek Phase 8
Summary - Wilmot Creek Phase 8
Greg Bolger
 
Terms of agreement sw final 9 02 16
Terms of agreement   sw final 9 02 16Terms of agreement   sw final 9 02 16
Terms of agreement sw final 9 02 16
E'ville Eye
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
Crosstown TO
 
Milpitas redevelopment case study,
Milpitas redevelopment case study, Milpitas redevelopment case study,
Milpitas redevelopment case study,
Ar Pankaj Kumar
 
Max Environmental Bulger Landfill Expansion Fact Sheet
Max Environmental Bulger Landfill Expansion Fact SheetMax Environmental Bulger Landfill Expansion Fact Sheet
Max Environmental Bulger Landfill Expansion Fact Sheet
Marcellus Drilling News
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
Capital Campaign Analysis Sample
Capital Campaign Analysis SampleCapital Campaign Analysis Sample
Capital Campaign Analysis SampleGeorge Dusenbury
 
Planjprox summary proposed changes 12.8.16
Planjprox   summary proposed changes 12.8.16Planjprox   summary proposed changes 12.8.16
Planjprox summary proposed changes 12.8.16
timothygreardon
 
South Park Development Presentation
South Park Development PresentationSouth Park Development Presentation
South Park Development PresentationJordan Dias
 
Toufic jreije portfolio
Toufic jreije portfolioToufic jreije portfolio
Toufic jreije portfolio
tkjreije
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
Crosstown TO
 
Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020
RamaChilamkurthy
 
PDR Housing estate renewal capability.FINAL[1]
PDR Housing estate renewal capability.FINAL[1]PDR Housing estate renewal capability.FINAL[1]
PDR Housing estate renewal capability.FINAL[1]Michael Walton
 
BUS 101 Final Report Project 2016
BUS 101 Final Report Project 2016BUS 101 Final Report Project 2016
BUS 101 Final Report Project 2016Allen Green
 
Pcw community report_2016-web
Pcw community report_2016-webPcw community report_2016-web
Pcw community report_2016-web
Mary Murphy
 
PCW_Community_Report_2016-web
PCW_Community_Report_2016-webPCW_Community_Report_2016-web
PCW_Community_Report_2016-webMary Murphy
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Crosstown TO
 
2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy Statement2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy StatementBen Johnson
 

Similar to Parkmerced Pulse (Issue 3, January 2016) (20)

Summary - Wilmot Creek Phase 8
Summary - Wilmot Creek Phase 8Summary - Wilmot Creek Phase 8
Summary - Wilmot Creek Phase 8
 
Terms of agreement sw final 9 02 16
Terms of agreement   sw final 9 02 16Terms of agreement   sw final 9 02 16
Terms of agreement sw final 9 02 16
 
draftstadiumeir
draftstadiumeirdraftstadiumeir
draftstadiumeir
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Milpitas redevelopment case study,
Milpitas redevelopment case study, Milpitas redevelopment case study,
Milpitas redevelopment case study,
 
Max Environmental Bulger Landfill Expansion Fact Sheet
Max Environmental Bulger Landfill Expansion Fact SheetMax Environmental Bulger Landfill Expansion Fact Sheet
Max Environmental Bulger Landfill Expansion Fact Sheet
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Capital Campaign Analysis Sample
Capital Campaign Analysis SampleCapital Campaign Analysis Sample
Capital Campaign Analysis Sample
 
Planjprox summary proposed changes 12.8.16
Planjprox   summary proposed changes 12.8.16Planjprox   summary proposed changes 12.8.16
Planjprox summary proposed changes 12.8.16
 
South Park Development Presentation
South Park Development PresentationSouth Park Development Presentation
South Park Development Presentation
 
Toufic jreije portfolio
Toufic jreije portfolioToufic jreije portfolio
Toufic jreije portfolio
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
 
Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020
 
PDR Housing estate renewal capability.FINAL[1]
PDR Housing estate renewal capability.FINAL[1]PDR Housing estate renewal capability.FINAL[1]
PDR Housing estate renewal capability.FINAL[1]
 
BUS 101 Final Report Project 2016
BUS 101 Final Report Project 2016BUS 101 Final Report Project 2016
BUS 101 Final Report Project 2016
 
Pcw community report_2016-web
Pcw community report_2016-webPcw community report_2016-web
Pcw community report_2016-web
 
PCW_Community_Report_2016-web
PCW_Community_Report_2016-webPCW_Community_Report_2016-web
PCW_Community_Report_2016-web
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
 
2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy Statement2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy Statement
 

More from parkmercedvision

September 14, 2022 Parkmerced Vision Update
September 14, 2022 Parkmerced Vision UpdateSeptember 14, 2022 Parkmerced Vision Update
September 14, 2022 Parkmerced Vision Update
parkmercedvision
 
February 20, 2019 Parkmerced Vision Update
February 20, 2019 Parkmerced Vision UpdateFebruary 20, 2019 Parkmerced Vision Update
February 20, 2019 Parkmerced Vision Update
parkmercedvision
 
September 24, 2018 Parkmerced Vision Update
September 24, 2018 Parkmerced Vision UpdateSeptember 24, 2018 Parkmerced Vision Update
September 24, 2018 Parkmerced Vision Update
parkmercedvision
 
September 25, 2017 Parkmerced Vision Update
September 25, 2017 Parkmerced Vision UpdateSeptember 25, 2017 Parkmerced Vision Update
September 25, 2017 Parkmerced Vision Update
parkmercedvision
 
20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final 20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final
parkmercedvision
 
20170131 pm bhw update final
20170131 pm bhw update final20170131 pm bhw update final
20170131 pm bhw update final
parkmercedvision
 
January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update
parkmercedvision
 
September 26, 2016 Parkmerced Vision Update
September 26, 2016 Parkmerced Vision UpdateSeptember 26, 2016 Parkmerced Vision Update
September 26, 2016 Parkmerced Vision Update
parkmercedvision
 
May 9, 2016 Parkmerced Vision Update
May 9, 2016 Parkmerced Vision Update May 9, 2016 Parkmerced Vision Update
May 9, 2016 Parkmerced Vision Update
parkmercedvision
 

More from parkmercedvision (9)

September 14, 2022 Parkmerced Vision Update
September 14, 2022 Parkmerced Vision UpdateSeptember 14, 2022 Parkmerced Vision Update
September 14, 2022 Parkmerced Vision Update
 
February 20, 2019 Parkmerced Vision Update
February 20, 2019 Parkmerced Vision UpdateFebruary 20, 2019 Parkmerced Vision Update
February 20, 2019 Parkmerced Vision Update
 
September 24, 2018 Parkmerced Vision Update
September 24, 2018 Parkmerced Vision UpdateSeptember 24, 2018 Parkmerced Vision Update
September 24, 2018 Parkmerced Vision Update
 
September 25, 2017 Parkmerced Vision Update
September 25, 2017 Parkmerced Vision UpdateSeptember 25, 2017 Parkmerced Vision Update
September 25, 2017 Parkmerced Vision Update
 
20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final 20170515 Parkmerced Resident Update Final
20170515 Parkmerced Resident Update Final
 
20170131 pm bhw update final
20170131 pm bhw update final20170131 pm bhw update final
20170131 pm bhw update final
 
January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update
 
September 26, 2016 Parkmerced Vision Update
September 26, 2016 Parkmerced Vision UpdateSeptember 26, 2016 Parkmerced Vision Update
September 26, 2016 Parkmerced Vision Update
 
May 9, 2016 Parkmerced Vision Update
May 9, 2016 Parkmerced Vision Update May 9, 2016 Parkmerced Vision Update
May 9, 2016 Parkmerced Vision Update
 

Recently uploaded

Rixos Tersane Istanbul Residences Brochure_May2024_ENG.pdf
Rixos Tersane Istanbul Residences Brochure_May2024_ENG.pdfRixos Tersane Istanbul Residences Brochure_May2024_ENG.pdf
Rixos Tersane Istanbul Residences Brochure_May2024_ENG.pdf
Listing Turkey
 
GT234 CADASTRAL SURVEYING gggggggggg.ppt
GT234 CADASTRAL SURVEYING gggggggggg.pptGT234 CADASTRAL SURVEYING gggggggggg.ppt
GT234 CADASTRAL SURVEYING gggggggggg.ppt
leonardmichael1
 
Brigade Insignia at Yelahanka Brochure.pdf
Brigade Insignia at Yelahanka Brochure.pdfBrigade Insignia at Yelahanka Brochure.pdf
Brigade Insignia at Yelahanka Brochure.pdf
SachinChauhan191
 
Torun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing TurkeyTorun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing Turkey
Listing Turkey
 
Total Environment Tangled Up In The Green - Residential Plots Where Nature an...
Total Environment Tangled Up In The Green - Residential Plots Where Nature an...Total Environment Tangled Up In The Green - Residential Plots Where Nature an...
Total Environment Tangled Up In The Green - Residential Plots Where Nature an...
JagadishKR1
 
Riverview City Loni Kalbhor Pune Brochure
Riverview City Loni Kalbhor Pune BrochureRiverview City Loni Kalbhor Pune Brochure
Riverview City Loni Kalbhor Pune Brochure
kishor21012022
 
Optimizing Your MCA Lead Capture Process for Better Results
Optimizing Your MCA Lead Capture Process for Better ResultsOptimizing Your MCA Lead Capture Process for Better Results
Optimizing Your MCA Lead Capture Process for Better Results
Lead Generation Media
 
Dynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction ProjectsDynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction Projects
Dynamic Netsoft
 
Deutsche EuroShop | Company Presentation | 06/24
Deutsche EuroShop | Company Presentation | 06/24Deutsche EuroShop | Company Presentation | 06/24
Deutsche EuroShop | Company Presentation | 06/24
Deutsche EuroShop AG
 
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Volition Properties
 
Victory by Maskeen Group Surrey Floor plans June 2024 PDF
Victory by Maskeen Group Surrey Floor plans June 2024 PDFVictory by Maskeen Group Surrey Floor plans June 2024 PDF
Victory by Maskeen Group Surrey Floor plans June 2024 PDF
VickyAulakh1
 
Presentation to Windust Meadows HOA Board of Directors June 4, 2024: Focus o...
Presentation to Windust Meadows HOA Board of Directors June 4, 2024:  Focus o...Presentation to Windust Meadows HOA Board of Directors June 4, 2024:  Focus o...
Presentation to Windust Meadows HOA Board of Directors June 4, 2024: Focus o...
Joseph Lewis Aguirre
 
Sense Levent Kagithane Catalog - Listing Turkey
Sense Levent Kagithane Catalog - Listing TurkeySense Levent Kagithane Catalog - Listing Turkey
Sense Levent Kagithane Catalog - Listing Turkey
Listing Turkey
 
Omaxe Sports City Dwarka A Comprehensive Guide
Omaxe Sports City Dwarka A Comprehensive GuideOmaxe Sports City Dwarka A Comprehensive Guide
Omaxe Sports City Dwarka A Comprehensive Guide
omaxesportscitydwark
 
SVN Live 6.3.24 Weekly Property Broadcast
SVN Live 6.3.24 Weekly Property BroadcastSVN Live 6.3.24 Weekly Property Broadcast
SVN Live 6.3.24 Weekly Property Broadcast
SVN International Corp.
 
Digital marketing strategy for Real Estate
Digital marketing strategy for Real EstateDigital marketing strategy for Real Estate
Digital marketing strategy for Real Estate
dheerajkumar8179
 
Biography and career about Lixin Azarmehr
Biography and career about Lixin AzarmehrBiography and career about Lixin Azarmehr
Biography and career about Lixin Azarmehr
Lixin Azarmehr
 
Hawthorn Module 1 Coverted to Slide Show - 04.06.2024.docx
Hawthorn Module 1 Coverted to Slide Show - 04.06.2024.docxHawthorn Module 1 Coverted to Slide Show - 04.06.2024.docx
Hawthorn Module 1 Coverted to Slide Show - 04.06.2024.docx
anothershaneroberts
 
Architectural & Interior design portfolio.pdf
Architectural & Interior design portfolio.pdfArchitectural & Interior design portfolio.pdf
Architectural & Interior design portfolio.pdf
susantebinum
 
How to keep your Home naturally Cool and Warm
How to keep your Home naturally Cool and WarmHow to keep your Home naturally Cool and Warm
How to keep your Home naturally Cool and Warm
Vinra Construction
 

Recently uploaded (20)

Rixos Tersane Istanbul Residences Brochure_May2024_ENG.pdf
Rixos Tersane Istanbul Residences Brochure_May2024_ENG.pdfRixos Tersane Istanbul Residences Brochure_May2024_ENG.pdf
Rixos Tersane Istanbul Residences Brochure_May2024_ENG.pdf
 
GT234 CADASTRAL SURVEYING gggggggggg.ppt
GT234 CADASTRAL SURVEYING gggggggggg.pptGT234 CADASTRAL SURVEYING gggggggggg.ppt
GT234 CADASTRAL SURVEYING gggggggggg.ppt
 
Brigade Insignia at Yelahanka Brochure.pdf
Brigade Insignia at Yelahanka Brochure.pdfBrigade Insignia at Yelahanka Brochure.pdf
Brigade Insignia at Yelahanka Brochure.pdf
 
Torun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing TurkeyTorun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing Turkey
 
Total Environment Tangled Up In The Green - Residential Plots Where Nature an...
Total Environment Tangled Up In The Green - Residential Plots Where Nature an...Total Environment Tangled Up In The Green - Residential Plots Where Nature an...
Total Environment Tangled Up In The Green - Residential Plots Where Nature an...
 
Riverview City Loni Kalbhor Pune Brochure
Riverview City Loni Kalbhor Pune BrochureRiverview City Loni Kalbhor Pune Brochure
Riverview City Loni Kalbhor Pune Brochure
 
Optimizing Your MCA Lead Capture Process for Better Results
Optimizing Your MCA Lead Capture Process for Better ResultsOptimizing Your MCA Lead Capture Process for Better Results
Optimizing Your MCA Lead Capture Process for Better Results
 
Dynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction ProjectsDynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction Projects
 
Deutsche EuroShop | Company Presentation | 06/24
Deutsche EuroShop | Company Presentation | 06/24Deutsche EuroShop | Company Presentation | 06/24
Deutsche EuroShop | Company Presentation | 06/24
 
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
 
Victory by Maskeen Group Surrey Floor plans June 2024 PDF
Victory by Maskeen Group Surrey Floor plans June 2024 PDFVictory by Maskeen Group Surrey Floor plans June 2024 PDF
Victory by Maskeen Group Surrey Floor plans June 2024 PDF
 
Presentation to Windust Meadows HOA Board of Directors June 4, 2024: Focus o...
Presentation to Windust Meadows HOA Board of Directors June 4, 2024:  Focus o...Presentation to Windust Meadows HOA Board of Directors June 4, 2024:  Focus o...
Presentation to Windust Meadows HOA Board of Directors June 4, 2024: Focus o...
 
Sense Levent Kagithane Catalog - Listing Turkey
Sense Levent Kagithane Catalog - Listing TurkeySense Levent Kagithane Catalog - Listing Turkey
Sense Levent Kagithane Catalog - Listing Turkey
 
Omaxe Sports City Dwarka A Comprehensive Guide
Omaxe Sports City Dwarka A Comprehensive GuideOmaxe Sports City Dwarka A Comprehensive Guide
Omaxe Sports City Dwarka A Comprehensive Guide
 
SVN Live 6.3.24 Weekly Property Broadcast
SVN Live 6.3.24 Weekly Property BroadcastSVN Live 6.3.24 Weekly Property Broadcast
SVN Live 6.3.24 Weekly Property Broadcast
 
Digital marketing strategy for Real Estate
Digital marketing strategy for Real EstateDigital marketing strategy for Real Estate
Digital marketing strategy for Real Estate
 
Biography and career about Lixin Azarmehr
Biography and career about Lixin AzarmehrBiography and career about Lixin Azarmehr
Biography and career about Lixin Azarmehr
 
Hawthorn Module 1 Coverted to Slide Show - 04.06.2024.docx
Hawthorn Module 1 Coverted to Slide Show - 04.06.2024.docxHawthorn Module 1 Coverted to Slide Show - 04.06.2024.docx
Hawthorn Module 1 Coverted to Slide Show - 04.06.2024.docx
 
Architectural & Interior design portfolio.pdf
Architectural & Interior design portfolio.pdfArchitectural & Interior design portfolio.pdf
Architectural & Interior design portfolio.pdf
 
How to keep your Home naturally Cool and Warm
How to keep your Home naturally Cool and WarmHow to keep your Home naturally Cool and Warm
How to keep your Home naturally Cool and Warm
 

Parkmerced Pulse (Issue 3, January 2016)

  • 1. PulseResident Newsletter | Winter 2015/2016
  • 2. KEEPING YOU INFORMED. In every quarterly issue of the Parkmerced Pulse, you’ll find important updates on the progress of implementing the Parkmerced Vision. In early 2016 you will begin seeing the property being prepared for construction and we’re committed to keeping you informed —and welcome your questions, comments, and concerns at any time. WHAT IS THE PARKMERCED VISION? The Parkmerced Vision is a long-term (approximately 20-30 years) project to comprehensively replan and redesign Parkmerced. The Parkmerced Vision was approved by the City of San Francisco in 2011. The project will be constructed in phases, with construction of the Project’s Subphases 1A and 1B expected to begin in Spring and Summer 2016, respetively. Additional information about the Parkmerced Vision is available at parkmercedvision.com. July 2011: Project Entitlement and Development Agreement Approved May 2015: Development Phase 1 Application Approved August 2015: Tentative Subdivision Maps for Subphases 1A and 1B Approved October through December 2015: Design Review Applications Approved August 2015 • On August 6 we provided the Planning Commission staff with an update on Phase I of the project and held an informational Design Review hearing. September 2015 • On September 9 we invited residents from the 56 to-be-replaced apartments to join us to learn more about their anticipated move. • On September 29 an appeal hearing for Teantative Subdivision Maps pertaining to Subphases 1A and 1B was held by the San Francisco Board of Supervisors (BOS). The BOS unanimously denied the appeal. November 2015 • Revised Street Improvement Plans submitted to City Agencies for review. December 2015 • On December 17, a tree removal hearing was held by the San Francisco Department of Public Works following the submittal of a tree-removal application. A decision on the application is pending. For more information on tree removals as part of Subphase 1A and 1B, please see page 3. RESIDENT AND COMMUNITY PARTICIPATION Since late 2006, we’ve held well over 500 meetings with our residents, neighbors and other stakeholders, ranging from small group briefings to large public workshops. We look forward to continued discussions throughout the coming months and beyond. Parkmerced Resident Newsletter 1 RESIDENT PROTECTION Parkmerced is committed to protecting residents’ rent-controlled apartments for as long as they choose to live at Parkmerced. The Parkmerced Vision involves removing and replacing all garden apartment homes within Parkmerced in phases over the next 20-30 years. Subphase 1A includes the construction of 56 replacement apartment homes for residents of to- be-replaced apartments on existing blocks 37W, 34, and 19 (see map on page 5). To protect our existing residents living at Parkmerced, prior to the replacement of any existing rent-controlled apartment, Parkmerced will provide the resident who lives in a to-be-replaced building with an apartment within one of the newly constructed buildings in Parkmerced. • New apartment homes will be rented at the same rent-controlled rate as the existing apartments prior to demolition (and also subject to rent increase limitations of the San Francisco Rent Control Ordinance). • New apartments will be constructed prior to the replacement of existing apartments. This ensures that affected residents only need to move once into their new apartment and will not be displaced. • Parkmerced will cover all moving expenses from residents’ existing units to their brand new replacement unit. Additionally, moving services, including packing and unpacking, will be paid for by Parkmerced. Replacement apartments will: • be comparable in size to existing units with the same number of bedrooms and bathrooms, and in some cases more; • be constructed with improved accessibility, making it more convenient for our elderly and/or disabled residents; • inlude brand new energy efficient appliances and new fixtures including dishwashers and a washer/dryer; and • be more comfortable due to better construction, including insulated walls and efficient windows.
  • 3. PARKMERCED AT FULL BUILD OUT
  • 4. Parkmerced Resident Newsletter 3 PREPARING FOR CONSTRUCTION The Parkmerced Vision will be constructed in discrete major phases, with Subphases 1A and 1B expected to break ground in the Spring/Summer 2016. Tree Removal: To prepare for street realignments, new buildings, and redesigned open spaces, the tree removal process, which was anticipated in the Parkmerced Project’s Environmental Impact Report (EIR), is scheduled to occur in early 2016. On December 17, 2015, a public hearing was held by the San Francisco Department of Public Works to review Parkmerced’s tree removal permit applications. The tree removal permits are anticipated to be approved by January 2016 with tree removals occurring shortly thereafter. For every tree that is removed in Subphase 1A and 1B, approximately 3 new trees will be planted in their place within Parkmerced. Site Surveys: You may have noticed consultants collecting soil samples over the past several months. This work is serving several purposes, such as understanding soil suitability for new landscaping, assessing the soil’s ability to absorb or convey water during storms or heavy rain, and determining its composition to ensure it will provide a foundation for new planned buildings. Cultural Resources: A Historic American Buildings Survey (HABS) and a Historic American Landscapes Survey (HALS) are being completed to document Parkmerced as a large-scale planned master residential development and celebrate the work of master landscape architect Thomas Dolliver Church and his colleague Robert Royston. Two interpretive displays will be installed in open space around Parkmerced and a digital display will be installed in the leasing office to demonstrate HABS/HALS findings. Further, the final report and plans will be submitted to the History Room of the San Francisco Public Library and the Northwest Information Center of the California Historical Information Research System. Digital copies of the HALS/HABS reports will be made available online at parkmercedvision.com and in Resident Services once the reports are finalized. Original drawings will be donated to the University of California, Berkeley. Wind Studies: To ensure wind conditions are consistent with those studied as part of the Project’s Environmental Impact Report (EIR), wind tunnel tests have been conducted for each new proposed building. PARKING RELOCATION Subphases 1A and 1B of the Parkmerced Vision include the replacement of two existing parking garages (the Felix and Galindo garages) and two surface parking lots (Arballo Circle and Chumasero surface lots). Prior to the removal of the garages and surface lots, Parkmerced will work with affected residents who currently have parking spaces at these locations to relocate their spaces. For a majority of residents, parking spots will be relocated to the existing Higuera Garage. The Higuera Garage may be accessed either from Higuera Avenue or Garces Drive (see map on Page 5). Understanding that relocating parking spaces to Higuera Garage may pose as a burden to those with special needs, Parkmerced will work with these residents on a case-by-case basis to find a parking space within a nearby existing carport as they are available. At the time residents’ parking is relocated, Parkmerced will initiate a free resident shuttle that will transport residents to locations within Parkmerced (including Higuera Garage) as well as to Daly City BART Station. The shuttle will run on a published schedule and stop locations will be placed conveniently throughout the property and specifically around the eastern side of the property. Further details regarding the shuttle will be in a future issue of the Parkmerced Pulse. For residents that have parking spaces in Felix or Galindo garages or the Arballo Circle or Chumasero surface lot, an informational meeting will be held in Spring 2016 prior to relocation. Invitations for this meeting and parking relocation materials will be sent via certified mail in early 2016. PARKING FOR NEW BUILDINGS Higuera Garage will also be the closest available garage to the first buildings constructed at 300 Arballo and 199 Vidal (see Subphase 1A and 1B map on Page 5). The overall parking plan includes new subterranean parking garages in the majority of new buildings. Overall, Parkmerced will be able to construct up to one (1) off-street parking space per apartment at Parkmerced. On-street parking will also continue to be available around Parkmerced similar to as it is today. The approved Parkmerced Vision also includes a detailed Transportation Plan designed to improve all existing transportation modes and encourage residents to take advantage of the convenient current and future transportation options. We will be expanding our on-site carshare program as well as implementing a bike share program with “bicycle libraries” located throughout the property. Of course, a renewed emphasis will also be placed on walking, pedestrian safety, and transit.
  • 5. A Look Back: Fall 2015 • Tenant Relocation Packets mailed to residents in to-be-replaced apartments in existing blocks 37W, 34, and 19 (refer to map on Page 5) • Invitation-only resident meeting for residents in to-be-replaced apartments in existing blocks 37W, 34, and 19 (refer to map on Page 5) Early 2016 • General residents meeting (January 19, 2016) • Parking relocation meeting (Date TBD) • Subphases 1A and 1B Development Site Preparation: Phase 1 Subphases A and B tree removal begins Parkmerced Resident Newsletter 4 RESIDENT COMMUNICATION AND PRELIMINARY CONSTRUCTION SCHEDULE RELOCATION PROCESS: EXISTING BLOCKS 37W, 34, and 19 SPRING/SUMMER 2015 FALL 2015 SPRING 2016 SPRING 2017 LATE 2017 Public Meeting Invitations Existing Tenant Notice Unit Availability Notice Selection of Replacement Unit Relocation Notice Moving Services Public Meetings • Learn your tentative moving timeline • Receive a copy of the Tenant Relocation Plan • Learn about the construction timeline • View a project map • VIew floor plans of the new units and new buildings, if available • An informational Tenant Relocation Plan sent to the first to-be-replaced apartments Spring 2016: Initial Notice • Confirm your seniority for the Unit Selection Process • Receive Rent Board information on your rights as a tenant Spring 2017: Unit Availability Notice • Begin the Unit Selection Process • Be invited to multiple Open Houses so that you can see a sample unit and pick your preferred unit layout • Rank your preferred replacement units for Unit Selection Selection of Replacement Unit • Receive results of Unit Selection Process • Find out your future unit and address • Confirm that you plan to move into the unit Relocation Notice • Receive notice that your unit is move-in ready • Work with Parkmerced to finalize a Moving Day that works best for you Moving Services • Receive free moving services • Settle into your new unit! Informational Tenant Relocation Plan WE ARE HERE WE ARE HERE Mid 2016 • Break ground on Phase 1 Subphase A (~18-21 month construction) • Break ground on Phase 1 Subphase B (~29-32 month construction) • Submit Final Map for Phases 1A & 1B for approval • Existing playground replacement/relocation Parkmerced will provide multiple written notices to keep residents informed of the relocation timeline
  • 6. Parkmerced Resident Newsletter 5 DEVELOPMENT SUBPHASES 1A AND 1B SITE MAP
  • 7. Parkmerced Resident Newsletter 6 Where can I find up-to-date project information? To stay informed with project progression and milestones, we welcome you to visit parkmercedvision.com, email info@parkmercedvision.com, call 415.405.4666, and look for our quarterly newsletter with updates. If I have a question or concern about the noise levels on the property when construction starts, who should I get in touch with? Prior to the start of construction, Parkmerced will designate a Noise Disturbance Coordinator that will be available to take calls and inquiries through the duration of the construction process. The contact information of the coordinator will be posted outside of each construction site, published in the next newsletter, and available at parkmercedvision.com. What will the construction hours be each day? The San Francisco Police Code details specific hours during which construction is allowed to take place. For projects under construction in San Francisco, construction can occur between the hours of 7:00 AM and 8:00 PM, seven days per week, including holidays. Any work done outside of these hours must not exceed the noise level of five decibels at the nearest lot line. For the Parkmerced project specifically, most work will take place between 7:00 AM and 4:30 PM daily with no work currently planned for Sundays. Having parking spaces in front of the existing towers is very important to residents. During construction, will these spaces be eliminated? The parking spaces next to and in front of the towers will continue to be available to residents throughout the construction process with the exception of 310/350 Arballo Drive, 100/150 Font Boulevard, and 55 Chumasero Drive. The driveways at 310/350 Arballo Drive, 100/150 Font Boulevard, and 55 Chumasero will be reconfigured as part of the Subphase 1A and 1B development and unavailable for extended periods during construction. We will work with our Contractors to phase construction in such a way to provide temporary parking where possible. Generally, the number of affected spaces at these locations will return at the end of each subphase with similar parking restrictions with a new configuration. More information will be distributed to our residents on a building-by-building basis as we learn more about expected construction impacts and space needs. FREQUENTLY ASKED QUESTIONS Which building(s) will be constructed first? In Subphase 1A, Block 1 buildings (199 Vidal Drive and 300 Arballo Drive) will be constructed first. These buildings will include the first 56 replacement units. Additionally, Subphase 1A includes the construction of 455 Serrano and 850 Gonzalez on Block 6. In Subphase 1B, construction includes Block 20 (1208 - 1218 Junipero Serra Boulevard) and Block 22 (95-99 Chumasero Drive). See map included on Page 5. How long will construction last for Subphases 1A & 1B? Construction lengths will vary depending on building size and complexity. Buildings and street improvements in Subphase 1A are expected to take 18-21 months to complete; buildings and street improvements in Subphase 1B are expected to take 29-32 months to complete. I currently have a parking space in a Galindo/Felix/Arballo Circle parking area. When will I get more info about parking relocation? Affected residents will be notified in early 2016 with details. Garage preparation and deconstruction will begin as early as June 2016, so we anticipate residents’ parking relocation to take place in late Spring 2016. This timeline is subject to change based on the project’s overall construction schedule.
  • 8. Architect: Fougeron Architecture Units: 64 homes (40 replacement) Bike Parking: 64 spaces Architect: Leddy Maytum Stacy Units: 89 homes (16 replacement) Bike Parking: 89 spaces Parkmerced Resident Newsletter 7 CONSTRUCTION IN 2016: WHAT TO EXPECT Construction of Subphases 1A and 1B are expected to begin in Spring and Summer 2016, respectively. Parkmerced understands that the residents have concerns about the effect of construction on their quality of life. Residents can rest assured that Parkmerced is committed to making diligent efforts to maintain a comfortable living environment during construction of all phases of the Parkmerced Vision through continual communication and transparency. Construction contractors on site will adhere to all applicable laws and regulations during the construction process, as well as obligations and mitigations identified in the Project’s Environmental Impact Report (EIR). These regulations will ensure that residents experience as little disruption as possible from construction noise and vibration, road closures, construction dust, etc. A summary of several of the construction-related mitigation measures that the project will adhere to are described below. Transportation, Circulation, and Parking Parkmerced is developing a Construction Traffic and Parking Management Plan to ensure that traffic and parking management best practices are used during construction. The Plan will be reviewed and approved by the City prior to the commencement of construction. A cohesive plan for maintaining traffic operations during all times of day and periods of construction will be included in the Traffic and Parking Management Plan. Where possible, Parkmerced will work to ameliorate added traffic and parking impacts from nearby construction projects (e.g. San Francisco State University) and coordinate. Noise The San Francisco Police Code sets noise restrictions and guidelines that all construction projects in San Francisco must follow. Consistent with these requirements, our construction hours will be restricted to 7:00 AM to 8:00 PM. However, it is anticipated that our construction hours will be 7:00 AM to 4:30 PM on typical days. Specific measures for reducing noise levels during construction will include practices such as: • requiring that stationary equipment, such as generators and augers, to be modified to reduce noise; • installing barriers around particularly noisy activities that are designed to minimize noise; • using equipment with lower noise emission ratings whenever possible; • locating stationary equipment, material stockpiles, and vehicle staging areas as far from existing residents’ homes where feasible; and/or • requiring construction-related vehicles and equipment to use designated truck routes to access project sites. This includes minimizing construction-related traffic between Subphases 1A and 1B sites. In addition to meeting these noise requirements, Parkmerced will also have a Noise Disturbance Coordinator that residents will be able to contact throughout the duration of construction. The contact information of this coordinator will be included in a future newsletter and will be posted at or near the entrances of each construction site. Additionally, you can always contact a project representative on the Vision Information line at 415.405.4666. 199 VIDAL 300 ARBALLOPLANNED NEW CONSTRUCTION: SUBPHASE 1A AND 1B Development Subphases 1A and 1B will include the construction of 7 new residential buildings by 5 different architects. The basis of the architectural design is being driven by the adopted Design Standards & Guidelines, but each design is unique. Similar to how growth occurs throughout San Francisco, over time Parkmerced will look, feel, and grow more organically.
  • 9. Biological Resources Great care will be taken around certain plant and animal species in Parkmerced property during all phases of construction. During construction of Subphases 1A and 1B, efforts will be focused on protecting the breeding bird population and completing required tree removal, detailed below. Birds: A bird survey will be conducted prior to any construction activities, especially tree removals. If active nests are found in the work area, a buffer will be established and no construction will be allowed within a defined distance of the nest until the young have successfully fledged. Tree Removal: Certain trees must be removed to prepare for property improvements such as sidewalks, bike lanes, stormwater systems, roadways, utilities, and new landscaping. In Subphases 1A and 1B, 120 trees have been posted for removal. The overall site strategy involves an expanded planting of new trees of various sizes for each one removed at an approximate ratio of 3 to 1. Subsequent Phases: Other plant and animal species that may be affected by construction have been identified and studied in the Project EIR. Many plant and animal species are unique to specific georgraphic locations within Parkmerced and appropriate mitigations have been tailored to respond to potential impacts on a location-by-location basis. -- The next issue of the Parkmerced Pulse will take an in-depth look at all construction related activities and the effect of these activities to residents and neighbors. Full text for the Mitigation Monitoring and Reporting Program (MMRP) approved as part of the Project’s Environmental Impact Report (EIR) can be found on SF Planning’s Parkmerced Project page at http://www.sf-planning.org/index. aspx?page=2529. Parkmerced Resident Newsletter 8 Air Quality The San Francisco Planning Department, the Department of Building Inspections and the Bay Area Air Quality Management District have established guidelines to maintain proper air quality at and near construction project sites. Measures in place to reduce construction related emissions include: • making sure that equipment and trucks are regularly serviced to minimize exhaust emissions; • requiring construction contractors to shut down engines when they are not in use; • strategic placement of signage for construction workers at all access points for efficient travel into and around Parkmerced; • use of equipment with engines that meet emission reduction standards set forth by the US Environmental Protection Agency (EPA); and • requiring that construction contractors operate haul trucks which are 2007 or newer models. Also, because certain phases of the construction process generates dust, measures to minimize dust, both during and after work hours, will be in place. Dust control measures may involve watering or covering exposed soils and installing sediment traps throughout the construction sites. Beyond current requirements, Parkmerced is also looking into including wash down stations for construction trucks, vehicles, and equipment entering and exiting the site as appropriate and able. As required per the Project’s Environmental Impact Report (EIR), Parkmerced will have the air quality in and around construction sites monitored regularly. 455 SERRANO / 850 GONZALEZ 95-99 CHUMASERO1208-1218 JUNIPERO SERRA Architect: Woods Bagot Units: 248 homes Unbundled Parking: 429 spaces Bike Parking: 250 spaces Architect: Kwan Henmi Units: 299 homes Unbundled Parking: 343 spaces Bike Parking: 332 spaces Architect: Skidmore, Owings and Merrill Units: 313 homes Unbundled Parking: 266 spaces Bike Parking: 160 spaces
  • 10. Parkmerced Resident Newsletter 9 AREAS IMPACTED BY CONSTRUCTION IN SUBPHASES 1A & 1B • Subphases 1A and 1B construction will impact the areas shaded in orange below. • All existing towers will remain intact during all phases of construction of the Parkmerced Vision. • In addition to new buildings being constructed, a street improvements plan (SIP) and corresponding permit is also being implemented. The SIP will include road resurfacing, new sidewalks, improved landscaping, bike lanes, additional street lighting, and new utility lines. The following streets will be included in the SIP: Vidal Drive, Acevedo Avenue, Arballo Drive, Higuera Avenue, Serrano Avenue, Gonzalez Drive, Lake Merced Boulevard in Subphase 1A; Font SUBPHASE 1A SUBPHASE 1B 100 Font Blvd 150 Font Blvd 125 Cambon Dr 55 Chumasero Dr 50 Chumasero Dr 310 Arballo Dr 350 Arballo Dr 405 Serrano Dr 810 Gonzalez Dr IMAGE SOURCE: GOOGLE EARTH 800 Brotherhood Way Boulevard, Chumasero Drive, Brotherhood Way, and Junipero Serra Boulevard in Subphase 1B. • In the next issue of the Parkmerced Pulse, we will provide further details on efforts to prepare residents for what to expect during construction. It is a top priority to keep residents informed as we develop details around how construction might impact the broader Parkmerced community.
  • 11. ANNOUNCEMENTS Scholarship & Internship Program To view the full application form and requirements, visit parkmercedvision.com, email opportunities@parkmercedvision.com, or call 415.405.4666. 2016 Parkmerced Robert L. Pender Memorial Scholarship Applications Available early 2016, due May 2016 The Parkmerced Robert L. Pender Memorial Scholarship was established to encourage the pursuit of career paths in engineering, architecture, urban planning, and related fields. The $1,000 scholarship will be awarded to any full-time student pursuing undergraduate or graduate studies in engineering, architecture, urban planning, or a related field. Priority will be given to students enrolled at San Francisco State University or City College of San Francisco. 2016 Parkmerced Vision Intern Program Applications Available Spring 2016, due June 2016 Parkmerced is currently accepting applications for our 2016 Parkmerced Vision Intern Program based in San Francisco, California. Up to two (2) applicants may be selected to participate. The position is paid and will occur over a 6-month period. Parkmerced will give priority to students currently enrolled at San Francisco State University or City College of San Francisco in urban design, planning, architecture, engineering, or related programs. Save the Date: Resident Meeting When: Tuesday, January 19, 2016, 6pm - 8pm Where: St. Thomas More, Carroll Hall 1300 Junipero Serra Boulevard at Brotherhood Way Please join us at our next meeting open to all existing Parkmerced residents where we will be providing an update on the Parkmerced Vision Plan. A shuttle will be provided with pick-up locations at the Parkmerced Leasing Office and 810 Gonzalez Drive; the shuttle will operate on a loop beginning at 5:30PM until 8:30PM. Refreshments will be served. We look forward to seeing you there! To stay up-to-date with the latest information at Parkmerced, look for the next issue of Parkmerced Pulse, visit parkmercedvision.com, email info@ parkmercedvision.com, or call 415.405.4666. Parkmerced Resident Newsletter 10 CONTACT INFORMATION Parkmerced Vision Attn: Development Manager 3711 Nineteenth Avenue San Francisco, CA 94132 info@parkmercedvision.com 415.405.4666 parkmercedvision.com Parkmerced Resident Services 1 Varela Avenue San Francisco, CA 94132 services@parkmerced.com 415.405.4600 parkmerced.com San Francisco Planning Department Joshua Switzky 1650 Mission Street, Suite 400 San Francisco, CA 94103 joshua.switzky@sfgov.org 415.558.6378 You can also view all public documents on the Planning Department Parkmerced Project Page: http://www.sf-planning.org/index.aspx?page=2529. San Francisco Rent Board 25 Van Ness Avenue, Suite 320 San Francisco, CA 94102 415.252.4602 Provides counseling information on subjects covered by the Rent Ordinance. You can speak with a counselor during weekday counseling hours (9am - Noon and 1 - 4pm). Counselors are also available at the Rent Board office 8am - 5pm, Monday through Friday, excluding holidays. Residents’ Organization Parkmerced Residents Organization Any group of tenants interested in becoming a recognized residents’ organization can do so by notifying Parkmerced and the San Francisco Planning Department of its formation in writing. To formally be recognized, the group must show proof that they have more than 10 members (defined as tenants of Parkmerced, each occupying a separate unit) and have been in existence for at least 24 months. Please contact Bert Polacci at 415.405.4666 for more information or email info@parkmercedvision.com.