1. Technical Note
Job No: 102144-06 Job Name: JSW Detailed Design
By: Alan Sayler Subject:
Ausenco Review – Mainline Laying Spec-Part II
Specification
Date: 14 July 2022 Doc. No.: 102144-06-G-TN-020 Rev.: A
As per JSW’s request Ausenco has reviewed all the provided Specifications for the Palashpanga to
Jajpur Slurry Transportation Pipeline Project. This technical note provides our feedback regarding the
Mainline Laying Spec-Part II (Doc# MEC/Q7R5/05/28/PL/SPEC/002_rev-00):
In general, the specification Doc# MEC/Q7R5/05/28/PL/SPEC/002_rev-00, incorporates typical
drawings for construction, in general covers what is required, JSW should work with Ausenco
to improve on field site conditions with investigation for crossings and typical installations to
improve on the required drawings and utilize the revised documents for the construction
contractors use and management..
This document has a process that can be followed, and it should be reviewed with the JSW Client
Construction Management Team together to determine what is appropriate for the project and what
should be added for the project acceptance and monitoring, as well as final documentation and as-
built data requirements.
102144-06-G-TN-020