The N11 Gorey to Arklow Link road project in Ireland was completed two months ahead of schedule. The 22.9km dual carriageway project involved complex construction including two railway bridges, ten road bridges, environmental mitigation works, and addressing unstable soil conditions. Challenges during construction included planning works near rail lines and complying with strict environmental regulations. The new road is expected to reduce travel times, improve safety, and reduce traffic and pollution in the town of Gorey.
This document provides an overview of the Malampaya Deep Water Gas to Power Project in the Philippines. The key points are:
- The project developed an offshore natural gas field discovered in 1989 located 500 km from the nearest market.
- A subsea production system was developed with 5 wells tied back via flowlines to a shallow water platform for gas processing. The gas is then transported via a 504 km pipeline to an onshore gas plant.
- The project successfully delivered gas on schedule in October 2001 to fuel three new gas-fired power plants totaling 3,000 MW, providing much needed electricity to the Philippines.
- Developing this remote deepwater gas field and creating a new gas market required
This document provides information on Farrans, a UK-based building and civil engineering contractor. It summarizes some of Farrans' marine portfolio projects, including the construction of a new deep water berth and quay wall at Belfast Harbour, widening of the Seaforth Passage in Liverpool, repairs to a cooling water outfall structure in Heysham, construction of a new harbour wall in Granton, redevelopment of berthing areas and construction of a new quay wall at Montrose Deep Water Berth, construction of Pointhouse Quay in Glasgow, and renewal of Berth 6 in Montrose.
The document discusses the Sakhalin II Phase 2 Project, which involves further developing oil and gas resources on Sakhalin Island, Russia. Phase 2 will include building new offshore platforms at the Lunskoye and Piltun-Astokh fields, constructing a 1,870 km pipeline network, and building an LNG plant and oil export terminal. The project aims to produce up to 150,000 barrels of oil per day and 9.6 million tons per year of LNG for export to markets in Asia Pacific. Significant engineering challenges include the harsh environment of Sakhalin Island and coordination of partners from around the world.
The document summarizes the realignment of the N25 road from Rathsillagh to Harristown Little in County Wexford, Ireland. It took six years to design and complete the project, which involved examining alternative routes, acquiring land, archaeological testing, earthworks, drainage installation, and construction of structures like underbridges and cattle passes. The new road was funded with assistance from the National Roads Authority and European Union Cohesion Fund.
This document outlines two infrastructure projects in Qatar. Project 1 (PIC A-1094A) involves constructing roads, utilities, and 222, 215, and 211 villas in three residential areas. Project 2 (PIC A-1097) involves constructing and rehabilitating roads, installing storm drainage, water distribution, irrigation, and sewage systems in Haii Al-Mehan. The status of Project 1 design is 90% complete while Project 2 design is 100% complete.
Sublime Cascades: Water and Power in CoalbrookdalePaul Belford
Water power and the designed industrial landscape of the 17th, 18th and 19th centuries. Paper in the Industrial Archaeology Review (29.2, 2007) resulting from six years' research on the Coalbrookdale Watercourses system in the Ironbridge Gorge World Heritage site.
Transport Scotland requested that Scottish Water relocate their long sea outfall infrastructure to accommodate construction of a new pier for the Forth Replacement Crossing project. Grontmij was hired to design and oversee construction of a replacement outfall. They determined that using HDPE piping instead of the original expensive armored piping, along with changing from a twin pipe to single pipe design and simplifying the diffuser, would reduce costs and health and safety risks. The redesigned outfall was constructed on schedule by September 2010 through conventional barge techniques. The project demonstrated that thorough understanding of historical context and value engineering can produce substantial savings.
This document discusses the Chicago Tunnel and Reservoir Plan (TARP) which was developed to address drainage and pollution issues in the Chicago area. It provides an overview of TARP's history and phases. Phase I involved constructing 109 miles of tunnels to control pollution, which was completed in 2006. Phase II involves constructing 3 large reservoirs for flood control, including the McCook Reservoir currently under construction. The McCook Reservoir will provide 10.5 billion gallons of storage once completed and is one of the largest civil works projects of the US Army Corps of Engineers. The document outlines the status and costs of various TARP projects split between the responsibilities of the Corps and Metropolitan Water Reclamation District. It concludes with discussing next steps including connecting the McCook
This document provides an overview of the Malampaya Deep Water Gas to Power Project in the Philippines. The key points are:
- The project developed an offshore natural gas field discovered in 1989 located 500 km from the nearest market.
- A subsea production system was developed with 5 wells tied back via flowlines to a shallow water platform for gas processing. The gas is then transported via a 504 km pipeline to an onshore gas plant.
- The project successfully delivered gas on schedule in October 2001 to fuel three new gas-fired power plants totaling 3,000 MW, providing much needed electricity to the Philippines.
- Developing this remote deepwater gas field and creating a new gas market required
This document provides information on Farrans, a UK-based building and civil engineering contractor. It summarizes some of Farrans' marine portfolio projects, including the construction of a new deep water berth and quay wall at Belfast Harbour, widening of the Seaforth Passage in Liverpool, repairs to a cooling water outfall structure in Heysham, construction of a new harbour wall in Granton, redevelopment of berthing areas and construction of a new quay wall at Montrose Deep Water Berth, construction of Pointhouse Quay in Glasgow, and renewal of Berth 6 in Montrose.
The document discusses the Sakhalin II Phase 2 Project, which involves further developing oil and gas resources on Sakhalin Island, Russia. Phase 2 will include building new offshore platforms at the Lunskoye and Piltun-Astokh fields, constructing a 1,870 km pipeline network, and building an LNG plant and oil export terminal. The project aims to produce up to 150,000 barrels of oil per day and 9.6 million tons per year of LNG for export to markets in Asia Pacific. Significant engineering challenges include the harsh environment of Sakhalin Island and coordination of partners from around the world.
The document summarizes the realignment of the N25 road from Rathsillagh to Harristown Little in County Wexford, Ireland. It took six years to design and complete the project, which involved examining alternative routes, acquiring land, archaeological testing, earthworks, drainage installation, and construction of structures like underbridges and cattle passes. The new road was funded with assistance from the National Roads Authority and European Union Cohesion Fund.
This document outlines two infrastructure projects in Qatar. Project 1 (PIC A-1094A) involves constructing roads, utilities, and 222, 215, and 211 villas in three residential areas. Project 2 (PIC A-1097) involves constructing and rehabilitating roads, installing storm drainage, water distribution, irrigation, and sewage systems in Haii Al-Mehan. The status of Project 1 design is 90% complete while Project 2 design is 100% complete.
Sublime Cascades: Water and Power in CoalbrookdalePaul Belford
Water power and the designed industrial landscape of the 17th, 18th and 19th centuries. Paper in the Industrial Archaeology Review (29.2, 2007) resulting from six years' research on the Coalbrookdale Watercourses system in the Ironbridge Gorge World Heritage site.
Transport Scotland requested that Scottish Water relocate their long sea outfall infrastructure to accommodate construction of a new pier for the Forth Replacement Crossing project. Grontmij was hired to design and oversee construction of a replacement outfall. They determined that using HDPE piping instead of the original expensive armored piping, along with changing from a twin pipe to single pipe design and simplifying the diffuser, would reduce costs and health and safety risks. The redesigned outfall was constructed on schedule by September 2010 through conventional barge techniques. The project demonstrated that thorough understanding of historical context and value engineering can produce substantial savings.
This document discusses the Chicago Tunnel and Reservoir Plan (TARP) which was developed to address drainage and pollution issues in the Chicago area. It provides an overview of TARP's history and phases. Phase I involved constructing 109 miles of tunnels to control pollution, which was completed in 2006. Phase II involves constructing 3 large reservoirs for flood control, including the McCook Reservoir currently under construction. The McCook Reservoir will provide 10.5 billion gallons of storage once completed and is one of the largest civil works projects of the US Army Corps of Engineers. The document outlines the status and costs of various TARP projects split between the responsibilities of the Corps and Metropolitan Water Reclamation District. It concludes with discussing next steps including connecting the McCook
This document summarizes a residential project on Vasilievsky Island in St. Petersburg, Russia. The project involves reclaiming 4 plots of land totaling 87 hectares from the Gulf of Finland and constructing new residential communities. It will include over 800,000 square meters of residential space across 48 buildings, as well as commercial and community spaces. The development aims to provide residents with a unique waterfront lifestyle and easy access to the city center via planned transportation improvements.
New Pacific Metals Corporate Presentationnewpacific
The document summarizes New Pacific Metals Corp's 2011 exploration program at its Skukum Creek project in Yukon, Canada. Key points include: 1) Expansion of the camp facility was completed. 2) Refurbishment of the geological office was finished. 3) Access roads to exploration targets including Raca, Chieftain Hill, and Goddell were built. 4) Surface and underground drilling was underway or planned at Raca, Chieftain Hill, Skukum Creek, and Goddell to test targets defined by geological mapping and geophysical surveys.
The document summarizes New Pacific Metals' 2011 exploration plans and activities at its Skukum Creek gold-silver project in Yukon, Canada. Key points include: expanding their camp facilities, refurbishing offices, completing road building, conducting surface mapping and sampling, re-interpreting geology, beginning surface drilling at Raca and Chieftain Hill targets, preparing an underground drill rig at Skukum Creek, planning surface and underground drilling there and at Goddell, and experiencing delays in dewatering the Goddell decline requiring alternative drilling from the surface.
The Onshore Processing Facility (OPF) in Nogliki district, Sakhalin Island is the key component of the Sakhalin II oil and gas development project. It processes oil and gas from two offshore platforms and pipelines it to an LNG plant and oil export terminal. The OPF was challenging to build due to its remote location, harsh weather, lack of infrastructure and skilled labor. ENKA overcame these challenges by mobilizing a large camp, sourcing labor from across Russia, and developing logistics plans to transport all personnel and materials to site. The completed OPF is the largest combined oil and gas processing facility in the world and has achieved excellent safety records during construction and operation.
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
Dr Ian Campbell - Background and Environmental ImpactsPAS_Team
The document discusses unconventional hydrocarbons exploration and development in the UK and related environmental impacts. It provides background on unconventional resources like shale gas and coal bed methane. It outlines the significant increase in US shale gas production in recent decades. The UK government supports unconventional development subject to controls. Public concerns include climate change, water contamination, earthquakes and health impacts. Exploration and development operations are described along with waste management, water use, emissions and other environmental considerations. The regulatory system in the UK is explained along with industry best practices and guidelines.
Open-hole sand-control completions using expandable sand screens (ESS) offer advantages over traditional cased-hole completions including improved production rates and lower installation costs. The documents discusses several case studies where formate brines and ESS were used together, setting world records for longest, hottest, and deepest ESS installations. This included projects by Shell in the Brigantine field in the UK North Sea and by Saudi Aramco in the K-field in Saudi Arabia, improving well economics in both cases.
Pohick Stream Stabilization Phase II - Areas 2 and 3Fairfax County
The Pohick Stream Stabilization Phase II project restored approximately 1,000 feet of Pohick Creek along the southern and western perimeters of the Noman M. Cole Jr., Pollution Control Plant. The restored stream reduces the energy of flowing water and keeps the creek from eroding into the plant’s property line.
The document provides information on Richmond, Virginia's flood protection system, including details on the floodwall, pump stations, and ponding areas. It discusses the materials used in the floodwall's construction, the staffing levels for maintenance, inspection schedules, and the last major flood event. FAQs are answered on topics like the floodwall's length, height variations, typical inspection ratings, and certifying organizations. Relevant city code sections are also excerpted regarding construction standards and prohibitions in special flood hazard areas.
The meeting summarized proposed amendments to development plans for an area of Albuquerque bounded by Petroglyph National Monument, Unser Boulevard, Interstate 40, and the western edge of the city. Recent developments by Albuquerque Public Schools and the city necessitated changes to the original plans. Neighborhood representatives expressed general satisfaction with the proposed amendments, which included adjustments to zoning, land use designations, and road networks. The only concern was about insufficient notification of the meeting to all interested parties.
The document summarizes a feasibility study for the proposed Eagle Downs Coal Project in Queensland, Australia. Key points include:
- The project involves developing an underground longwall hard coking coal mine with a planned production of over 5 million tonnes per year.
- A definitive feasibility study estimated the total capital cost at $1.25-1.26 billion and found the project would have an internal rate of return of 15.16-15.22% and payback period of 2022-2025, indicating it is economically viable.
- The target coal seams are the Harrow Creek Upper, Harrow Creek Lower and Dysart seams, which are estimated to contain a JOR
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
Post Harvey Flood Data and the Future of Resilient Infrastructurejuliekannai
John Blount, Harris County Engineer
In late August, a downgraded tropical storm Harvey, which made landfall as a category 4 hurricane just days before, stalled over southwest Texas causing torrential flooding throughout the region. Unincorporated Harris County alone was inundated with in excess of a trillions gallons of storm water over 4 days, enough to fill the Astrodome 3200 times. In the aftermath of the unprecedented event, local officials were left to shepherd constituents through recovery and back to a sense of normalcy.
In this presentation, the county engineer, John Blount, gives a detailed account of the after events of Hurricane Harvey and its effects on the environment, infrastructure and community. Mr. Blount will analyze flood data yet to be released to the public, in order give the audience a perspective of just how devastating Harvey’s flood waters were. This session will breaks down the county facilities destroyed by Hurricane Harvey and John’s vision to respond with resilient solutions instead of temporary fixes because with the frequency and severity of recent storms, this could be the new normal.
The document discusses the process of generating electricity from coal at a coal-based power plant. Coal is mined and brought to the plant, where it is burned in a boiler to produce high-pressure steam. The steam spins turbines connected to generators, which produce electricity. The electricity is then distributed through power lines to homes and businesses. Key components of the plant discussed include the coal handling, boiler, turbine, generator and ash handling systems.
The document provides an overview of Honeywell's Hopewell, Virginia plant and its environmental performance. It describes the plant's history and products, including its position as the world's largest producer of caprolactam and ammonium sulfate. The plant ships over 900,000 tons of ammonium sulfate annually via its pier on the James River. It also discusses projects undertaken to reduce nutrient pollution to the river by over 85% while increasing production. The document highlights the plant's certified wildlife habitat and efforts to prevent water pollution and eliminate hydraulic oil from its loading equipment.
“The History of WEHLU from Conventional to Unconventional”Gib Knight
For a snapshot of the history of the West Edmond Hunton Lime Unit take a look at the “The History of WEHLU from Conventional to Unconventional” by Galen Miller, Sr. Geologist with Gastar Exploration.
This document provides information from a meeting of the James River Partnership regarding vessel traffic on the James River. It shows statistics on the number of ship and barge roundtrips on the river from 2008 to the projected numbers for 2013. Ship traffic has declined from 133 roundtrips in 2008 to a projected 61 in 2013. Barge traffic has fluctuated but remains significant, with over 2,000 roundtrips projected for 2013. Key cargos transported include petroleum products, aggregates, chemicals and containers.
The document summarizes the construction of a new cement import terminal in Charleston, South Carolina built by Blue Circle Cement, Kinder Morgan Bulk Terminals, and River Consulting. A project execution committee was formed to oversee the project. The terminal included a new ship unloader, conveyor systems, two 40,000 metric ton concrete storage domes built by DOMTEC, and a mechanical reclaiming system. The project was completed on schedule and established a new global standard for cement import terminals.
2008 annual report for Phoenix Coal (TSX: PHC), a company engaged in the exploration, production, acquisition and sale of coal from the Illinois Basin. The current mining operations and near-term development projects of the Company are located
in Western Kentucky, an area that comprises a part of the Illinois Basin.
The document discusses several ongoing and planned infrastructure upgrade projects at the Port of Durban in South Africa. It provides details about:
1) A R1.5 billion project to reconstruct quay walls and deepen berths at Maydon Wharf using 409 inclined anchor piles installed at angles up to 45 degrees.
2) Upgrades to the Prince Edward Graving dry dock to support larger ship repairs and increase capacity to 100%, including repairing a 900-ton caisson.
3) Clean-up efforts nearing completion following a 2015 vegetable oil spill in the port area, with over 663,000 liters of oil recovered.
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
The document provides updates on construction activities for different sections of the Eglinton Crosstown LRT project from September 2022. Vehicle testing is ongoing from Brentcliffe to Kennedy. Road and sidewalk restoration is ongoing from Brentcliffe to Don Mills through summer 2022. Landscaping along Eglinton is also ongoing through summer 2022. Finishing work at various stations including Science Centre station is ongoing through summer 2022 with periodic lane closures on Eglinton and Don Mills for inspections.
The Hallandsås Tunnel project in Sweden took over 20 years to complete due to major geological and groundwater challenges. Initial attempts to bore the tunnel failed and contaminated local water supplies with toxic grout. The project was halted for 7 years while a new shielded tunnel boring machine and concrete lining method were developed. This successful approach allowed the 8.7 km twin tunnels to be completed in 2013, improving rail capacity and travel times along the west coast of Sweden.
This document summarizes a residential project on Vasilievsky Island in St. Petersburg, Russia. The project involves reclaiming 4 plots of land totaling 87 hectares from the Gulf of Finland and constructing new residential communities. It will include over 800,000 square meters of residential space across 48 buildings, as well as commercial and community spaces. The development aims to provide residents with a unique waterfront lifestyle and easy access to the city center via planned transportation improvements.
New Pacific Metals Corporate Presentationnewpacific
The document summarizes New Pacific Metals Corp's 2011 exploration program at its Skukum Creek project in Yukon, Canada. Key points include: 1) Expansion of the camp facility was completed. 2) Refurbishment of the geological office was finished. 3) Access roads to exploration targets including Raca, Chieftain Hill, and Goddell were built. 4) Surface and underground drilling was underway or planned at Raca, Chieftain Hill, Skukum Creek, and Goddell to test targets defined by geological mapping and geophysical surveys.
The document summarizes New Pacific Metals' 2011 exploration plans and activities at its Skukum Creek gold-silver project in Yukon, Canada. Key points include: expanding their camp facilities, refurbishing offices, completing road building, conducting surface mapping and sampling, re-interpreting geology, beginning surface drilling at Raca and Chieftain Hill targets, preparing an underground drill rig at Skukum Creek, planning surface and underground drilling there and at Goddell, and experiencing delays in dewatering the Goddell decline requiring alternative drilling from the surface.
The Onshore Processing Facility (OPF) in Nogliki district, Sakhalin Island is the key component of the Sakhalin II oil and gas development project. It processes oil and gas from two offshore platforms and pipelines it to an LNG plant and oil export terminal. The OPF was challenging to build due to its remote location, harsh weather, lack of infrastructure and skilled labor. ENKA overcame these challenges by mobilizing a large camp, sourcing labor from across Russia, and developing logistics plans to transport all personnel and materials to site. The completed OPF is the largest combined oil and gas processing facility in the world and has achieved excellent safety records during construction and operation.
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
Dr Ian Campbell - Background and Environmental ImpactsPAS_Team
The document discusses unconventional hydrocarbons exploration and development in the UK and related environmental impacts. It provides background on unconventional resources like shale gas and coal bed methane. It outlines the significant increase in US shale gas production in recent decades. The UK government supports unconventional development subject to controls. Public concerns include climate change, water contamination, earthquakes and health impacts. Exploration and development operations are described along with waste management, water use, emissions and other environmental considerations. The regulatory system in the UK is explained along with industry best practices and guidelines.
Open-hole sand-control completions using expandable sand screens (ESS) offer advantages over traditional cased-hole completions including improved production rates and lower installation costs. The documents discusses several case studies where formate brines and ESS were used together, setting world records for longest, hottest, and deepest ESS installations. This included projects by Shell in the Brigantine field in the UK North Sea and by Saudi Aramco in the K-field in Saudi Arabia, improving well economics in both cases.
Pohick Stream Stabilization Phase II - Areas 2 and 3Fairfax County
The Pohick Stream Stabilization Phase II project restored approximately 1,000 feet of Pohick Creek along the southern and western perimeters of the Noman M. Cole Jr., Pollution Control Plant. The restored stream reduces the energy of flowing water and keeps the creek from eroding into the plant’s property line.
The document provides information on Richmond, Virginia's flood protection system, including details on the floodwall, pump stations, and ponding areas. It discusses the materials used in the floodwall's construction, the staffing levels for maintenance, inspection schedules, and the last major flood event. FAQs are answered on topics like the floodwall's length, height variations, typical inspection ratings, and certifying organizations. Relevant city code sections are also excerpted regarding construction standards and prohibitions in special flood hazard areas.
The meeting summarized proposed amendments to development plans for an area of Albuquerque bounded by Petroglyph National Monument, Unser Boulevard, Interstate 40, and the western edge of the city. Recent developments by Albuquerque Public Schools and the city necessitated changes to the original plans. Neighborhood representatives expressed general satisfaction with the proposed amendments, which included adjustments to zoning, land use designations, and road networks. The only concern was about insufficient notification of the meeting to all interested parties.
The document summarizes a feasibility study for the proposed Eagle Downs Coal Project in Queensland, Australia. Key points include:
- The project involves developing an underground longwall hard coking coal mine with a planned production of over 5 million tonnes per year.
- A definitive feasibility study estimated the total capital cost at $1.25-1.26 billion and found the project would have an internal rate of return of 15.16-15.22% and payback period of 2022-2025, indicating it is economically viable.
- The target coal seams are the Harrow Creek Upper, Harrow Creek Lower and Dysart seams, which are estimated to contain a JOR
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
Post Harvey Flood Data and the Future of Resilient Infrastructurejuliekannai
John Blount, Harris County Engineer
In late August, a downgraded tropical storm Harvey, which made landfall as a category 4 hurricane just days before, stalled over southwest Texas causing torrential flooding throughout the region. Unincorporated Harris County alone was inundated with in excess of a trillions gallons of storm water over 4 days, enough to fill the Astrodome 3200 times. In the aftermath of the unprecedented event, local officials were left to shepherd constituents through recovery and back to a sense of normalcy.
In this presentation, the county engineer, John Blount, gives a detailed account of the after events of Hurricane Harvey and its effects on the environment, infrastructure and community. Mr. Blount will analyze flood data yet to be released to the public, in order give the audience a perspective of just how devastating Harvey’s flood waters were. This session will breaks down the county facilities destroyed by Hurricane Harvey and John’s vision to respond with resilient solutions instead of temporary fixes because with the frequency and severity of recent storms, this could be the new normal.
The document discusses the process of generating electricity from coal at a coal-based power plant. Coal is mined and brought to the plant, where it is burned in a boiler to produce high-pressure steam. The steam spins turbines connected to generators, which produce electricity. The electricity is then distributed through power lines to homes and businesses. Key components of the plant discussed include the coal handling, boiler, turbine, generator and ash handling systems.
The document provides an overview of Honeywell's Hopewell, Virginia plant and its environmental performance. It describes the plant's history and products, including its position as the world's largest producer of caprolactam and ammonium sulfate. The plant ships over 900,000 tons of ammonium sulfate annually via its pier on the James River. It also discusses projects undertaken to reduce nutrient pollution to the river by over 85% while increasing production. The document highlights the plant's certified wildlife habitat and efforts to prevent water pollution and eliminate hydraulic oil from its loading equipment.
“The History of WEHLU from Conventional to Unconventional”Gib Knight
For a snapshot of the history of the West Edmond Hunton Lime Unit take a look at the “The History of WEHLU from Conventional to Unconventional” by Galen Miller, Sr. Geologist with Gastar Exploration.
This document provides information from a meeting of the James River Partnership regarding vessel traffic on the James River. It shows statistics on the number of ship and barge roundtrips on the river from 2008 to the projected numbers for 2013. Ship traffic has declined from 133 roundtrips in 2008 to a projected 61 in 2013. Barge traffic has fluctuated but remains significant, with over 2,000 roundtrips projected for 2013. Key cargos transported include petroleum products, aggregates, chemicals and containers.
The document summarizes the construction of a new cement import terminal in Charleston, South Carolina built by Blue Circle Cement, Kinder Morgan Bulk Terminals, and River Consulting. A project execution committee was formed to oversee the project. The terminal included a new ship unloader, conveyor systems, two 40,000 metric ton concrete storage domes built by DOMTEC, and a mechanical reclaiming system. The project was completed on schedule and established a new global standard for cement import terminals.
2008 annual report for Phoenix Coal (TSX: PHC), a company engaged in the exploration, production, acquisition and sale of coal from the Illinois Basin. The current mining operations and near-term development projects of the Company are located
in Western Kentucky, an area that comprises a part of the Illinois Basin.
The document discusses several ongoing and planned infrastructure upgrade projects at the Port of Durban in South Africa. It provides details about:
1) A R1.5 billion project to reconstruct quay walls and deepen berths at Maydon Wharf using 409 inclined anchor piles installed at angles up to 45 degrees.
2) Upgrades to the Prince Edward Graving dry dock to support larger ship repairs and increase capacity to 100%, including repairing a 900-ton caisson.
3) Clean-up efforts nearing completion following a 2015 vegetable oil spill in the port area, with over 663,000 liters of oil recovered.
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
The document provides updates on construction activities for different sections of the Eglinton Crosstown LRT project from September 2022. Vehicle testing is ongoing from Brentcliffe to Kennedy. Road and sidewalk restoration is ongoing from Brentcliffe to Don Mills through summer 2022. Landscaping along Eglinton is also ongoing through summer 2022. Finishing work at various stations including Science Centre station is ongoing through summer 2022 with periodic lane closures on Eglinton and Don Mills for inspections.
The Hallandsås Tunnel project in Sweden took over 20 years to complete due to major geological and groundwater challenges. Initial attempts to bore the tunnel failed and contaminated local water supplies with toxic grout. The project was halted for 7 years while a new shielded tunnel boring machine and concrete lining method were developed. This successful approach allowed the 8.7 km twin tunnels to be completed in 2013, improving rail capacity and travel times along the west coast of Sweden.
Blase Townsing has over 12 years experience in civil construction and has held roles as a site supervisor, leading hand, plant operator and labourer. He has extensive experience supervising road construction, airport upgrades, detention basin construction, pipeline projects and flood restoration works. He has qualifications in construction supervision, safety leadership, road construction and plant operation. Blase is skilled in planning works, monitoring safety and productivity, and meeting client requirements for on-time and high quality delivery. He has a strong track record of successfully delivering civil projects for government and private clients.
This document provides a method statement for repair works to existing river walls and installation of a new secant pile wall to support the widening of an access road for the North Blyth Renewable Energy Project. The existing river walls are in poor condition with sections that have collapsed or are subsiding. The selected design option is to install an interlocking bored secant pile wall approximately 4-4.5m landward of the existing walls. This will provide support for the widened road without requiring excavation of contaminated fill materials or causing loss of intertidal mudflat habitat, while reducing noise and vibration impacts compared to other options.
The document summarizes a site visit to a construction project upgrading an existing bridge and building a new bridge under the N1 freeway near Tygervalley Shopping Mall in Cape Town. The R9.3 million contract was awarded to Murray & Roberts Cape Limited to upgrade the existing 1947 and 1974 bridge substructures to support a new bridge deck without the existing middle pier. The contract involved three phases of temporary diversions on the N1 freeway while demolishing the old decks and constructing new concrete decks on the old substructures and a new bridge concurrently. The project was completed with no fatalities or lost time due to accidents while minimizing traffic disruptions on the busy N1 freeway.
The document provides a preliminary brief for a flood alleviation project along the Clontarf Promenade between Alfie Byrne Road and the Wooden Bridge in Dublin. It summarizes discussions from a Joint Working Group regarding flood protection options and outlines a proposed dual defence system using the existing seawall and a new secondary wall near the road. The consultant is asked to review flood risk levels, calculate required defence heights, produce preliminary designs and cost estimates, and advise on planning and development of the Promenade going forward while minimizing visual impacts. The goal is to finalize a preliminary plan for the flood protection scheme and Promenade redevelopment.
Elgin Country Estate Project Summary as on 20160606 John M Riggs
The document provides details of the Elgin Country Estate residential development project in Grabouw, Western Cape. Key points include:
- The 16.65 hectare site will include 115 residential stands, with 53 lots of 1500sqm and 62 lots of 400sqm.
- The development has received all required planning approvals and bulk services are available.
- An investment of R5 million is sought, which will provide a 20% return on investment in cash or through a house.
- So far R19 million has been invested with 49 stands presold, leaving 13 larger and 53 smaller lots remaining.
The document summarizes the final consultation phase for Forewind's Dogger Bank Teesside A & B offshore wind farm project. It will include the publication of documents and plans, and three public events from November 4th to December 20th. This consultation is the result of four years of environmental and engineering surveys. Project Manager Chris Nunn said it is the main opportunity for public comment before the consent application is submitted. The consultation documents will be available to view online and at local libraries and public events.
Raymond Wesley Acheson has over 30 years of experience in construction management, including roles as Managing Director and Senior Contracts Manager. He has extensive experience managing multi-million pound projects involving reinforced concrete structures, marine works, utilities work and dispute resolution. His background includes education in civil engineering and qualifications in areas such as health and safety, quality auditing and business administration.
Wardell Armstrong was commissioned by National Grid Gas Transmission to provide environmental and engineering consultancy support for the design and early construction of the 65 km Asselby to Pannal gas pipeline from June 2006 to January 2008. This included reviewing documentation to ensure compliance, undertaking surveys to inform routing, advising on environmental impacts and mitigation, and providing an on-site environmental adviser. The scope of work involved ecological and archaeological surveys, private water supply assessment, and ensuring activities followed legislation and best practices.
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfCrosstown TO
Metrolinx acknowledges that the Crosstown LRT operates on Indigenous land and is committed to meaningful reconciliation. Construction updates were provided for the Chaplin and Avenue stations, including ongoing work on station entrances, boxes and infrastructure through summer 2022. Traffic configurations in the areas will be changing as work progresses.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
Waterman is a UK-based multi-disciplinary engineering and environmental consultancy. It employs over 1,300 staff across 20 offices in the UK and internationally. Waterman's specialist secondment service seconds staff into both short and long-term roles in areas such as bridges, highways, transportation infrastructure, and more. Majority of seconded staff are permanently employed by Waterman and receive training and performance reviews. Waterman has extensive experience providing seconded staff and services to clients such as local authorities, transport agencies, and private consultants.
Waterman is a UK-based multi-disciplinary engineering and environmental consultancy. It employs over 1,300 staff across 20 offices in the UK and internationally. Waterman's specialist secondment service seconds staff into both short and long-term roles in areas such as bridges, highways, transportation infrastructure, and more. Majority of seconded staff are permanently employed by Waterman and receive training and performance reviews. Waterman has extensive experience providing seconded staff and services to clients such as local authorities, transport agencies, and private consultants.
Waterman is a large multi-disciplinary engineering and environmental consultancy firm in the UK. It employs over 1,300 staff across 20 offices and had a turnover of £68.8 million in 2013. Waterman provides specialist secondment services, placing staff into short or long-term roles in civil engineering, transportation, infrastructure, and other areas. Majority of staff are permanently employed by Waterman and then outsourced to clients, which include local authorities and private consultants. Waterman's secondment services offer flexibility and opportunities for career progression.
The document summarizes a training visit to the Visakhapatnam port trust in India. It describes the port's infrastructure including three harbors and berths capable of accommodating large vessels. It also discusses capital dredging projects to deepen harbors and channels to accommodate larger ships. Specific projects mentioned include deepening the inner harbor channel and turning circle to allow 14 meter draft vessels, and relocating tug jetties along the north and south sides of a canal to develop a new berth. The port plays an important role in India's economy by facilitating trade, exports, and industrial development.
We've been working on tunnelling projects since 1961. In total, we’ve been involved in over 780km of tunnelling projects worldwide.
This slideshow provides just a small selection of our tunnelling projects from around the world.
To find out more about how we create our compelling portfolio of tunnelling projects, go to http://www.atkinsglobal.com/en-GB/group/sectors-and-services/services/tunnelling-and-underground-space
This local impact report summarizes a proposal by Network Rail to construct a 3km railway chord linking the Askern and Skellow lines over the East Coast Main Line in Doncaster, as well as replacing an existing level crossing with a road bridge. The report provides details on the site and surroundings, proposal details, the need for the proposal, relevant planning history, site constraints, and relevant development plan policies. It also identifies issues and considerations related to landscape, ecology, noise, flooding, transport, and the economy. The report concludes with an assessment of the potential impacts of the proposed development.
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
The document provides updates on construction progress at the Chaplin Station and Avenue Station sites of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the main, secondary, and tertiary entrances through December 2022, along with station box construction and road closures. At Avenue Station, station box construction and work on the main and secondary entrances is progressing through December 2022, along with Eglinton Avenue streetscape and cycle track construction between Eastbourne and Duplex Avenues. Construction photos depict ongoing work.
The document summarizes the winners of the Engineers Ireland Excellence Awards 2016. The top award, Engineering Project of the Year, went to the €3.5 billion Corrib onshore gas pipeline project. Other winners included William Egenton for President's Award, the Irish Rail Cutting and Embankment Decision Support Tool for Geoscience Ireland Award, and Network Innovation Competition Robotics Project for Technical Innovation of the Year. The awards ceremony recognized innovative engineering projects and individuals that have made significant contributions to industry and society.
Mr. Tony O'Neill served as the National Road Authority's Site Representative for the 41 km M7/M8 motorway project from 2007 to 2011. He led a team of up to twelve people and displayed excellent management and liaison skills that were vital to the project's success in opening four months ahead of schedule. Mr. O'Neill also helped negotiate financial issues relating to the 27-year operations and maintenance phase and wrote a comprehensive handover report. The author has no hesitation in recommending Mr. O'Neill to any employer.
1. I~ ;:e.~ l5rue6 L_.,_:> .:._g.s. 2001
INTERCHA~NG!E F:Q:RESIHADOWS
COMPL'ET1IOIN O'F N11 GOREY/ARKLOW
A 15 <.<r sec: o~ c= :re ' r 1 Gorey to Arklow Link- from Clogh to the Tinnock
lmercna-ge - ooened on July 4th. The contractor, Roadbridge Ltd., will deliver the
ema'noer of the € 179 million Design & Build project on September 5th, two months
aheao of schedule. Tony O'Neill, Project Resident Engineer for the N11 Gorey to
Arklow Link describes the distinctive aspects of the project, the challenges faced in
delivering it and the benefits that will result.
T
he N 11 Gorey to Arklow Link comprises the
construction of approximately 22.9km of dual
carriageway and includes a by-pass of Gorey Town.
It commences on the existing N1 1 approximately three km
south of the village of Clogh and progresses northwards
deviating from the existing N11 at Ballinclare where it takes
an easterly route around Gorey town. Between Gorey and
Arklow, it bypasses the village of Inch and runs roughly
parallel to the existing N1 1 ultimately connecting to the
existing southern junction of the Arklow By-Pass. It crosses
the county boundary from iVexford to iVicklow County at the
tributary of the Avoca River.
The development also includes the construction of
approximately 1.5km of single carriageway road, the new
Arklow Link Road, which will join the existing N11 to
LJ.--..ll 6 the western roundabout of the southern junction of the
Infrastructure
Arklow by-pass. Further realignments are being carried
out on a number of local and regional roads where they are
intersected by the N 11 Gorey to Arklow Link. A number
of new junctions are being constructed as part of the road
de'elopment:
An at-grade roundabout is located at the southern rie-in ro
the existing N ll , south of Clogh. This will pro,·ide access
to Clogh village, Gorey town, the N ll Gorey to .-rklow
Link and existing N 'll ;
The Raheenagurren grade-separated juncu• n will provide
access to the R741 Ballycanew Road, the R/.J.2 Courtown
Road, Gorey town and the L-5082-02 Kn. ockduff Road;
The T innock grade-separated junction" •II provide access
to the the existing N11 and Nl l Gore~ to Arklow Link,
Gorey town and the North Vexford hm1erland including
Inch.
2. T he scheme also includes:
Two railway underbridges;
ten overbridges;
seven underbri dges;
twelve farm underpasses, and;
The scheme includes
railway underbridges.
three major culverts across the Banoge, the Inch and the
Clonough Rivers.
Making a start
The official stan date of ::o,•ember 5th 2005 was nor an
ideal time to begin work. ~lany com~ct• .r,._ 1:mn all. prefe·
to make a stan ar..und April. H ·• e- c~: Roadbrid::e L;d.
(contractor) and Fehily, Timo~e:r & Giii'o:d (ckoi;nc).~: up
temporary site offic.,-, i:1 o:re of 5~~ hou..~· uq~ed a• pa:-:
of this scheme and tht>n mobtli•ed m Oc;,obc; - embracin~
favou rable weather C1 ·ndi:ion-. ~ilicb. excep:in::; the month
of April, would last tnrou::h :he ~ummer of ::: o6 - to begin
construction of a haul r03d a:td construction of structures tO
carry this haul road o,·er :hecounty roads.
Environmental co nsiderations
There were numerous en"Jr< ·nmemal constraints imposed
oy the Environmental lmp-.cr Statement and conditions
set by An Borel Pleanala. subsequently reflected in the
contract documents, which had to be addressed in detail by
the contractor in order tO delh·er the project on time. These
conditions included:
No removal of mature trees between ::ovember and
August inclusive;
No removal of hedgerows berween :larch and August
inclusive;
No in-stream works in watercourses between October and
Engineers Journal IVolume 61: Issue 61 July/August 2007
April inclusive;
Noise and vibration limitation;
Dust nuisance;
Avoiding siltation of watercourses due to run-off
from the site;
Prevention of groundwater contamination -the
carriageway drainage for approximately 6km is lined with a
reinforced birumin•>U"' membrane to prevent the possibility
of zroundw:ner comammauon, and;
:: -e mi1igation - almost three km of timber noise barrier,
t:--. udin~ p;.rapt:: intill across structures- ISEN 1794
& 1- j.;. compliant- was installed over the extent of the
s.:heme to comply with the noise mitigation requi rements
set out in the Environmental Impact Statement and
conditions set by An Bord Pleanala.
In addition, this mitigation was supplemented by low
noise thin layer asphalt wearing course used throughout
the scheme.
Stability concerns
JVIacamore soils occupy 9.01 per cent of County Wexford.
The parent material consists of dense, calcareous, marine
muds and oozes. It is natu rall y poorly drained, has a weak
structllre and is 'heavy' in textu re. Reflecting concerns
about the medium-to-long term stability of this material,
the specimen design called for side slopes of one vertical
to three horizontal where this material- over a distance of
approximately 1Okm - impacted on the new N11.
The contractOr addressed this at detailed design stage by
revising the vertical al ignmen t, and at construction stage by
'working' the material with appropriate plant in appropriate
weather conditions.
Infrastructure
3Tl
3. j 378
~· Iss:.'!! 6 1.L.!'J ..:U.-g.&. 2fYJ1
The contractor is confident that the project will be delivered two months ahead of schedule.
Serious challenges
T u
B~ -P..,.::-.
The planning and design process for both structures involved
significant project time by all parties as all communications,
submissions etc. to be provided by the contractor to Iarnrod
Eireann had to be submitted via the engineer. Nowhere
during the project was the commitment given by all
signatories to the project charter- to work together with
openness and integrity and to commit to effective teamwork
and co-operation to make this a successful project- more
in evidence than during this process. Approval to begin
construction of the Coolnastud structu re was finally given
in mid-September 2006 and the finished product now ranks
as the longest- approximately 150 metres- reinforced earth
larnrod Eireann underbridge in the country.
Earthworks
The contractor adjusted the specimen design vertical
alignment to minimise cut/fill operations and, fu rthermore,
assigned a huge volume of earthmoving plant - which peaked
at over 30 excavators, 40 dumptrucks, 12 dozers and 12
rollers- to the site enabling substantial completion of this
element during the season of 2006.
Infrastructure
Safety management
...~fe: !' ,..ue :~pPcd ·he a:::enda at all progre;;, meetings.
- ;be;-e M~ been rwo reportable incidents - both
~"nl ii:-.-; :aid Ttquin:mem, ::.mce the
.e ;ht bzckd:op i~ !hat
•.i = ho;;;.;--' ~ bten uur:.ed to date
·h m re :h..n ~ :'C="- ·:-.-..:~ ;.,du<:ed 0.'1 .-i:e. G~: credit
i::. due to lorgan Sheehy BE C En~ :II EI Eudn; I IHT
-Project :Ianager for Roadbridge Ltd on the ,;cheme - and
his staff fo r delivering this project ahead of programme, but
above all, for delivering it with a safety record on site that is,
arguably, second to none.
Archaeological impact
T he 23km long scheme revealed an exciting archaeological
landscape. An intensive investigation strategy consisting of
desk-based archaeological assessment and a walkover study
was undertaken to assess the impact of the scheme on the
archaeological heritage. The development was designed to
avoid all the known archaeological monuments identified
within the scheme's proximity.
This archaeological assessment was further informed by both
a geophysical and underwater survey. In January 2005, Irish
Archaeological Consultancy Ltd undertook test excavations
to ensu re the investigation and preservation of sites along the
route. As a result, a total of 53 previously unknown sites were
identified.
That summer, on behalf of the National Roads Authority and
vVexford County Council, archaeological excavations were
carried out by Valerie]. Keely Ltd to ensure the investigation
4. and preservation of sites in advance of road construction.
Analysis of the results is ongoing but it is clear that the work
yielded a diversity of archaeological evidence dating from the
'nineteenth century AD to the fifth millennium BC.
Evidence of later Mesolithic acth·ity (Mesolithic refers to
the middle stone age, 7000-·J.OOO BC) was encountered in the
townland of Coolnaveagh where a collection of Aint tools was
uncovered close to a hearth.
The site was on a plateau o,·erlooking the River Banoge to the
south-west of Gorey. The tools probably indicate a temporary
camp for fishing or hunting-related activities. Their discovery
shows that people had penetrated the dense canopy of
woodland that would ha'e existed in North Wexford during
the era of Ireland's earliest inhabitants.
Current characte ristics
The existing N ll from Dublin to Wexford is characterised
by a range of road types and qualities, reflecting the staged
improvement of the road. In the vicinity of the proposed Nll
Gorey to Arklow Link, the road varies from dual carriageway
on the Arldow by-pass to single carriageway sections with
limited hard shoulder and overtaking opportunities.
This section of the.:-11 has a large number of direct accesses
onto and off the road.
In 2003, four years ago, the average speed on the existing
N11 between Clogh and the Arklow by-pass was 40.9mph
(65.5kmph)
The existing.:- 11 goes through Gorey town and the
villages of Inch and Clogh. It passes through Gorey town
centre (McCurtain Street and Main Street) for a stretch of
ABdesign &burld
On lm•
INCH
Co,.,;cac.c·
Engineers Journal IVolume 61 : Issue 61July/August 2007
m
Des•g";;;;.e.;.... __
www.abmdesignandbuild.ie • Umt 28 FeiiNn Business Park, Drynam Road , Swords, Co. Dublin • T: +353 (0)1 890 0919 F: +353 (0)1 890 0932
Infrastructure
.312
5. l8.Q
-.::n.."n3~ely one km.
CO.""lrlic<oi local traffic including pedestrians/cyclists
~c n;.~tional primary route traffic causes severe delays,
,e-:ton and safety issues within the town.
he -.urrent 'Oiume of traffic in the town is such that
iCC ..re significant difficulties experienced by pedestrians
~cmpting ro cross the road, which creates a safety hazard as
lumes increase over the yea rs.
Au•·erse environmental effects are experienced in the town
nduding increased levels of noise, vibration and atmospheric
emissions.
In 2003, fou r years ago, the average speed through Gorey
rown was 14.8mph (23.8kmph).
Le'el of Service (LOS) is a term used to represent an
objective average journey speed, under ideal conditions,
combined with satisfactory conditions for overtaking and
driver operation (as identified by the USA Highway Capacity
:.'vlanual). The National Roads Needs Study 1998 identified
that the LOS on the N11 between Gorey and Arldow was
"D" in 1995 except for the section immediately South of
Arklow which was deemed to have a LOS of "E". The study
predicted that conditions were projected to deteriorate even
further as traffic volumes continued to grow.
Generally, LOS "D", equivalent to an nverage inter-urban
journey speed of 80kph, is regarded as a minimu m acceptable
NSAI Certified Sign Manufacturer
Traffic & Road Works Signs
Health & Safety Signage
Large Format Digital Printing
Traffic Control Equipment
Road Cones, Safety Barrier
Varioguard & Lane Dividers
Cone Trailers
Site Safety EquJp.ment. _.
.,~ t. _ I fl__.,~
Infrastructure
standard. The N l1 Gorey to Arklow Link has been designed
to provide sufficient capacity to ensu re a mini mum le,·el of
service "D " and is in accordance with the National Roads
Needs Study and the strategy for National Primary Roads
outlined in the National Development Plan 2000-2006.
Future benefits
The scheme will provide several important benefits including
the following:
A significant reduction in accident figures on this section
of carriageway;
Grearly reduced travel times on the N 'l1 national primary
route between Dublin and the south-east including the
ferry connections with France and Wales;
lmpro,·ed access between Dublin and the south east;
An alumment wh ich is commensurate with current
st..nd;~rds:
Recl..:..::i,.,n in the amount of through traffic entering the
town - up to 12,000 vehicles per day according to a recent
;oa.ffic 'lln·cy:
Pr.n"i,ion of easy access to Gorey town and tou rist areas
:! ;he CO:.'t :
~,·eb of noise, vib ration in Gorey town, and;
~-d• of atmospheric emissions giving rise to
<=:o:s=•nl L:npr•)·ement of ai r qual ity in the town. <!>
Tony 0':'eiJJ graduated in 1984 from University
CoU~e, Galway with a Bachelor of Engineering D egree
and completed a n M.Eng.Sc. Degree in Offshore &
Coastal Engineering at University College, Cork in 1986.
Tony spent six years working with Mott MacDonald
Ltd Consulting Engineers in the U.K., two of which
were with the Special Projects Design Group working
on the Channel Tunnel Project and the remaining four
yea rs as Assistant Resident Engineer on the Lower Lea
Crossing Project in London.
On his return from the UK in 1993 he has worked as
Project Resident Engineer on numerous sche m es
including the d emolition and reconstruc tion of
Wexford Bridge and the N8 Cashel by-pass & N74 Link
Road sch em e.