The document discusses the importance of keeping comprehensive contemporary site records to support claims related to delays, disruptions, and their effects. It provides guidance on how contractors can evidence exceptionality and the effects of adverse climatic conditions, specifically heavy rainfall. As an example, it shows how contractors can present rainfall records from both national weather data and site-specific weather stations to demonstrate that rainfall during a project was exceptional compared to historical data, and to evidence the impact of rainfall on work hours and productivity. Maintaining good records is crucial for contractors to prove entitlement to time extensions and associated costs for delays caused by weather or other external factors.
The Competition (Amendment ) Bill, 2012, Bill No. 136 of 2012 ( the Amendment
Bill 2012) lapsed before it could become a law because of the dissolution of the then
lower house of Parliament just before the general elections leading to the present
Government, at the centre, came to power. One of the amendments, proposed in
this Amendment Bill 2012, sought to make changes in Section 26 of the Act to
allow some clear lee way to the Competition Commission of India (Commission) to
differ from the report of the Director General(DG) and close the matter despite the
DG having come to the conclusion that there is a violation of competition law
after he has investigated into the allegations of violations of competition law. Such
clarity, sought to be introduced by the Amendment Bill, 2012, is missing in the
relevant provisions of the Act as they stand today. In the appropriate provisions, as
they exist today, there is enough room for inquiry by the Commission in addition
to the investigation by the Director General(DG) after investigation by DG is
done. The natural corrollary is that a poorly investigated report by DG can not be
either a basis or excuse for not upholding violations of competition law if found in
a prima facie opinion of the Commission. However, it is a moot point if this part of
the mandate is being fully exercised at present or not.
It is this part of inquiry by the Commission after the report has been submitted by
the DG which the author, who headed the Antitrust Division of CCI to actually
see the implementation of functional regulations in real practice and also assisted
the Commission in drafting these regulations, discusses in this article.
+ EU-Japan area of safe data flowing creation
+ An Overwork in contract for work
+ A debt relief
+ A fine for premature withdrawal from a contract is liable to VAT
+ A difference between value and purchase price of a debt can be liable to VAT
+ A set-off has to be executed in the currency in which the debt has to be performed
+ Requirements for a set-off of larger number of debts
Presentation of the SAI survey results carried out by SAIBiH, given at the Roundtable on Independence of Supreme Audit Institutions in Sarajevo on 8 September 2016.
The Competition (Amendment ) Bill, 2012, Bill No. 136 of 2012 ( the Amendment
Bill 2012) lapsed before it could become a law because of the dissolution of the then
lower house of Parliament just before the general elections leading to the present
Government, at the centre, came to power. One of the amendments, proposed in
this Amendment Bill 2012, sought to make changes in Section 26 of the Act to
allow some clear lee way to the Competition Commission of India (Commission) to
differ from the report of the Director General(DG) and close the matter despite the
DG having come to the conclusion that there is a violation of competition law
after he has investigated into the allegations of violations of competition law. Such
clarity, sought to be introduced by the Amendment Bill, 2012, is missing in the
relevant provisions of the Act as they stand today. In the appropriate provisions, as
they exist today, there is enough room for inquiry by the Commission in addition
to the investigation by the Director General(DG) after investigation by DG is
done. The natural corrollary is that a poorly investigated report by DG can not be
either a basis or excuse for not upholding violations of competition law if found in
a prima facie opinion of the Commission. However, it is a moot point if this part of
the mandate is being fully exercised at present or not.
It is this part of inquiry by the Commission after the report has been submitted by
the DG which the author, who headed the Antitrust Division of CCI to actually
see the implementation of functional regulations in real practice and also assisted
the Commission in drafting these regulations, discusses in this article.
+ EU-Japan area of safe data flowing creation
+ An Overwork in contract for work
+ A debt relief
+ A fine for premature withdrawal from a contract is liable to VAT
+ A difference between value and purchase price of a debt can be liable to VAT
+ A set-off has to be executed in the currency in which the debt has to be performed
+ Requirements for a set-off of larger number of debts
Presentation of the SAI survey results carried out by SAIBiH, given at the Roundtable on Independence of Supreme Audit Institutions in Sarajevo on 8 September 2016.
Hver væg er forskellig, og du behøver de rette workflow-værktøjer for at sikre, at dit design – hvad enten det er et stort vægmaleri eller gentagne mønstre – printes ordentligt og nøjagtigt. Nøjagtigheden af print og beskæring er altafgørende for at garantere, at hver bane tapet passer perfekt sammen, når det sættes op på væggen. Tapet bruges i mange rum, så vaskbarhed, giftighedsgrad og svag lugt er vigtige faktorer, man skal tage højde for, inden produktionen går i gang.
Innovation indenfor variabel data og personalisering transformerer forretningskommunikation. I dag arbejder printudbydere hurtigere end nogensinde: flere short-runs, strammere deadlines og øget personalisering.
Personalisering og variabel dataprint transformerer forretningskommunikation og gør det nemmere for brands at have en reel, effektfuld og værdifuld dialog med deres kunder via print.
Besøg canon.dk/unleashprint
Libro Informe Nacional de Capital Humano Municipal 2016Nelson Leiva®
Este texto contiene un profundo análisis sobre esta situación, de Capital Humano Municipal, en especial por la promulgación de la ley Nº 20.922 sobre el Fortalecimiento de la Gestión y Profesionalización del personal municipal, sin duda, significa el inicio de una nueva era en la gestión municipal, en cuanto a la labor que desarrollan en los municipios de Chile, para cada uno de los 345 municipios del país, estableciendo incluso comparaciones tanto a nivel regional como nacional.
Asia Counsel Insights gives readers a concise insight into legal and business developments in Vietnam. This edition has news on proposed changes to investment and business laws; changes to minimum wage; and anti-dumping duties imposed on galvanised steel from China and Korea.
Hver væg er forskellig, og du behøver de rette workflow-værktøjer for at sikre, at dit design – hvad enten det er et stort vægmaleri eller gentagne mønstre – printes ordentligt og nøjagtigt. Nøjagtigheden af print og beskæring er altafgørende for at garantere, at hver bane tapet passer perfekt sammen, når det sættes op på væggen. Tapet bruges i mange rum, så vaskbarhed, giftighedsgrad og svag lugt er vigtige faktorer, man skal tage højde for, inden produktionen går i gang.
Innovation indenfor variabel data og personalisering transformerer forretningskommunikation. I dag arbejder printudbydere hurtigere end nogensinde: flere short-runs, strammere deadlines og øget personalisering.
Personalisering og variabel dataprint transformerer forretningskommunikation og gør det nemmere for brands at have en reel, effektfuld og værdifuld dialog med deres kunder via print.
Besøg canon.dk/unleashprint
Libro Informe Nacional de Capital Humano Municipal 2016Nelson Leiva®
Este texto contiene un profundo análisis sobre esta situación, de Capital Humano Municipal, en especial por la promulgación de la ley Nº 20.922 sobre el Fortalecimiento de la Gestión y Profesionalización del personal municipal, sin duda, significa el inicio de una nueva era en la gestión municipal, en cuanto a la labor que desarrollan en los municipios de Chile, para cada uno de los 345 municipios del país, estableciendo incluso comparaciones tanto a nivel regional como nacional.
Asia Counsel Insights gives readers a concise insight into legal and business developments in Vietnam. This edition has news on proposed changes to investment and business laws; changes to minimum wage; and anti-dumping duties imposed on galvanised steel from China and Korea.
2019 Transfer Pricing Overview for the Czech RepublicAccace
Transfer pricing regulations deal with the determination of prices in transactions (e.g. sale of goods, provision of services or provision of loans) realized between economically or personally related companies. The aim is to ascertain that the arm’s length principle is met.
The annual market and competition law is set forth in Law 23 July 2009, no. 99. Although the Competition Bill is supposed to be tabled annually, only one Competition Law has been passed to date. Why is this? The reasons are many; however, the first is the challenge of agreeing politically on where and how to intervene.
A look at intra-group loans and safe harbour rules in CyprusChristos Theophilou
Christos Theophilou and Demis Ioannou of Taxatelier present a case study of how the Cypriot tax authorities use safe harbour rules in determining arm’s-length interest rates. The article appears in International Tax Review, published by Euromoney PLC.
Overcoming cultural barriers to Second ChanceOECDglobal
Session 4: Georgios Karrotsakis
Head of the Insolvency Service Cyprus and
Bankruptcies and Liquidations Section
Department of Registrar of Companies and Official Receiver
Ministry of Energy, Commerce, Industry and Tourism
Thursday, 14 September 2017
OECD Conference Centre, Paris
Mihaela Vulpescu, Manager of Contracts Department - "Early warnings";
Cristina Pirjan, Senior QS Advisor - "Claims at termination under FIDIC 1999 Sub-Clauses 16.4 and 19.6 of the Contract"
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...Cerasela Angelescu
All the parties involved in a contract will wish for the respective project to be successful. Therefore, understanding that it takes not only a fair and balanced contract which sets out the roles of the parties, but also mechanisms which will ensure that the issues which may arise will be dealt with promptly and fairly, proactively identifying options and solutions to challenges, the International Federation of Consulting Engineers (FIDIC) and the Georgian Association of Consulting Engineers (ACEG) have organized the FIDIC-ACEG European Regional Infrastructure Conference in Tbilisi, Georgia, 6/7 March 2018.
In this issue:
Planning for Adverse Weather – p.1
Sorin Ghiuta, Senior Planning Engineer
Termination of the Contract: A means to an end or an end to the means? – p.3
Radu Giumanca, Senior Contracts Manager
Changes in legislation and claims pursuant to FIDIC Sub-Clause 13.7 – p.5
Flaviu Rusu, Quantity Surveyor
Our employees are our most valuable asset! – p.8
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
6th International Conference on Machine Learning & Applications (CMLA 2024)ClaraZara1
6th International Conference on Machine Learning & Applications (CMLA 2024) will provide an excellent international forum for sharing knowledge and results in theory, methodology and applications of on Machine Learning & Applications.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
1. Payment mechanism of amounts awarded
through DAB decisions, introduced by
Emergency Government Ordinance
no. 7 on 18 March 2016
Payment mechanism of amounts awarded
through DAB decisions, introduced by
Emergency Government Ordinance no. 7
on 18 March 2016
Valentin Serban
Lawyer
Site Records
How Contractors should evidence
exceptionality and the effects of
Adverse Climatic Conditions
Mircea Triculescu
Claims Manager and Head of
Forensic International & QA
Techno Engineering & Associates is
pleased to announce its involvement
with the DRBF Regional Conference &
Workshop Livingstone, Zambia
6
1. Introduction
Emergency Government Ordinance no.
7/2016 introduced various measures in
order to accelerate the implementation of
t h e t r a n s - E u r o p e a n t r a n s p o r t
infrastructure projects and also to amend
other legal provisions (“EGO 7/2016”), was
published in the Official Gazette no. 204 on
18 March 2016, and entered into force on
same day, and is applicable inclusively to
Contractsconcludedbeforethatdate.
EGO 7/2016 is applicable exclusively to
projects related to the trans-European
transport infrastructure, consisting of
road, public railway, air and waterway
transport infrastructure located on the
Core and Comprehensive trans-European
transport network (TEN-T), as it is defined
byRegulation(EU)no.1315/2013of11
December2013onUnionguidelinesforthe
development of the trans-European
transportnetwork.
2. Conditions for applying the payment
mechanismprovidedbyEGO7/2016
EGO 7/2016 provides, amongst others, the
ability for the Employers under the
authority/coordination of the Ministry of
Transportation (such as CNADNR, CFR and
the like) to ensure, only by way of an
Addendum to the Contract concluded in
accordance with the Emergency
Government Ordinance no. 34/2006, the
enforcement of decisions issued by a
Dispute Adjudication Board (DAB), under
thefollowingcumulativeconditions:
(I) TheContractwaslegallyconcluded;
(ii) The mechanism of adjudication by a
DABisexpresslyprovidedbytheContract;
(iii) The Contractor agrees by an
Addendum to the Contract to waive the
potentialinterestsrelatedtothedisputes;
(iv) The Contractor provides the
Employer with a Bank Guarantee in
accordancewiththeEGO7/2016.
For the purpose of this analysis, conditions
(i) and (ii) above will be presumed to have
beenmet.
Issue 7, May 2016
Valentin Serban
Lawyer
6
Techno Engineering & Associates further
consolidates its prominent position with
the appointment of Mr. Valentin Stoica in
the position of Business Development
Manager 7
2. In relation with condition (iii) above, the
interests related to the disputes are
defined by EGO 7/2016 as “the additional
amounts consisting in delay increases, delay
penalties,interestsandanyothersprovided
by the execution/services contracts, in
accordance with the law, for the failure to
complywiththecontractualterms”.
The above definition is very general and
ambiguous. Therefore, it shall be assessed
whether the interests refer only to such
amounts that have been awarded by the
DAB or to the full amount of interests to
which the Contractor is entitled, including
the penalties which had been subject of
the disputes settled by the DAB and the
penalties which remain to be referred to
furtherarbitralproceedings.
T h e l o g i c a l a n d c o m m o n - s e n s e
interpretation shall be that the interests
thattheContractorshallwaiveareonlythe
interests calculated in respect of the
Employer's delay in making payment of
the amounts awarded by the DAB and not
the amount of interests already included
within a DAB award in its decision or the
potential amounts to be awarded by an
arbitraltribunal/courtoflaw.
However, other interpretation cannot be
ignored (most likely that which would be
embraced by the Employer) that the
Contractor shall waive all interests related
to the dispute, calculated from the start of
the event or from the issuance of the DAB
decision,untilthedateofthefinalaward.
In respect of condition (iv), EGO 7/2016
provides that the voluntary payment of the
amounts awarded by the DAB is subject to
the issuance of a bank guarantee by the
Contractor, amounting the sums to be paid
bytheEmployerandtheinterestscalculated
based on the BNR official rate plus three (3)
percentage points, for a period of three (3)
years from the issuance of the bank
guarantee.
The bank guarantee shall be maintained by
the Contractor until the issuance of the final
award (in Romanian “titlu executoriu”) of
the dispute thereof. Regarding the situation
of final payments, there are three (3)
scenarios, asfollows:
(a) in the case where the final award is
fully in the Contractor's favour, the
guarantee shall be returned by the
Employer;
(b) in the case where the final award is
fully in the Employer's favour, then the
Contractor shall return the amounts paid by
the Employer based upon the DAB decision.
In the case where the Contractor would fail
to return the amounts paid, the bank
guarantee shall be enforced by the
Employer;
(c) in the case where the final award
grantspartialamounts,theContractorshall
return the difference between the sums
which where paid by the Employer and the
amount awarded. In the case of a failure by
the Contractor to repay, the bank guarantee
shall be proportionally enforced by the
Employer.
3. Necessaryfunds
It is worthy of note that Employers who
choose to apply for the voluntary payment
procedure provided by EGO 7/2016, will have
to ensure the availability of funds from the
budgetapprovedforthe respectiveprojects,
upon the prior approval issued by the main
budget administrator (in Romanian
“ordonatorprincipaldecredite”).
In the case where the amounts to be paid by
the Employers exceed the available funds
from the national budget approved for the
transport infrastructure of national interest,
the Ministry of Transport shall establish,
within the limits of the approved budget, the
priority criteria for payment of amounts
arisingfromDABdecisions.
Moreover, the Employers under the
authority/coordination of the Ministry of
Transportation may apply for the payment
mechanism provided by EGO 7/2016, within
the maximum limit of 35% of the amounts of
the budgetary loans (in Romanian “credite
bugetare”) annually approved by the state
budget for projects related to the trans-
Europeantransportinfrastructure.
4. Conclusions
The payment mechanism introduced by
EGO 7/2016 is optional for the Employer, not
anobligation;
If invoked, the payment mechanism
shall be applied by the Parties only based on
an Addendum to the Contract. The
Addendum shall be concluded in accordance
withthepublicprocurementlegislation,with
allthelegalimplicationsarisingtherefrom.
The Contractor has no control on the
budgetallocationorontheprioritycriteriato
be established by the Employer and / or the
MinistryofTransportation.
Issue 7, May 2016
3. inactions, or those of his subcontractor or
other suppliers under his responsibility.
However, such delay and disruption is also
commonly attributable to employers or other
extraneouscauses.
All claims must be proven, where the burden
of proof is with the claimant. Therefore, all
Contractor claims must include the following
minimumcomponents:
Definition of relevant events forming
the facts of the case, which must be
evidenced;
Identificationanddemonstrationofthe
effect of the events, showing how those
effectshavebeencausedbytheevents,being
theproofofcauseandeffect.
Difficulties often arise in linking cause with
effect, exacerbated when little or no precise
recordsareavailable.
3. Specific example: the effects of
exceptionaladverseclimaticconditions.
As we will be aware, the weather plays a
major role when progressing a construction
contract. Weather is always present and
contractors are familiar with its effects, when
hot and sunny, concreting activities will
require more specialist curing techniques,
hessian wrapping, continuous wetting and
the like. When faced with periods of
prolonged rainfall, obligations to maintain
earthworks free of water become far more
onerous. Yet the weather is a matter at the
risk of the contractor under most contracts,
yet often there is an opportunity to claim in
the event that the weather experienced over
aspecificperiodmaybeexceptional.
The key word here is exceptional, whereby
the need to prove exceptionality will be
fundamental to the merits of such a claim. In
the following paragraphs, we show a specific
example of how the contemporary weather
records kept on the site could be used to
graphically present the effect of rainfall on
thenumberofworkeddays.
Mircea Triculescu
Claims Manager and Head of
Forensic International & QA
Site Records
How Contractors should evidence exceptionality and
the effects of Adverse Climatic Conditions
1. Rationale
Whenever one researches publications from
practitioners, the common view regarding
theevidencingofclaimsisthepremiseof “the
continuous keeping of comprehensive site
contemporary records is a legal and
contractual obligation. It provides an effective
means of controlling and monitoring all
activities on the site. The contemporary
records have a vital role to play in the
assessmentandsettlementofdisputes”.
In reality, it can never be stressed enough
what the real meaning of keeping
contemporary records is and the extent and
nature of the records which should be. For
many professionals in the industry, this may
becommonsense,butexperienceshowsthat
for the majority, record keeping is often
considered to be a waste of time, where
records of a minimum nature are kept solely
to satisfy the legal or contractual obligation,
until such time as those records are required
tobereliedupon.
This is the moment when Contractors will
realise the importance of records, that maybe
they are not a waste of time and money and
without them their entitlement to an
extension of the time for completion (or
other substantial opportunities to claim) and
the additional payments thereof will fail,
exposing them to the loss of those claims and
little defence against Employer's claims
againstthemfordelaydamages.
This is the moment when contractors
opinions on the importance of keeping
records change, yet in most instances that
realisation will be too late for the purposes of
their claims and defences to Employer's
claimsagainstthem.
2. The Need for Records: Proving
causation for delay claims and the effects
thereof.
In practice, any record is of value. Primarily,
records would serve to compile data bases
which should prove useful when organising
and planning similar projects. Secondly, and
arguably more importantly, they will be the
basis upon which contractor's claims for time
andcostwillultimatelyrely.
Contemporaneous documentation should be
maintained and ideally agreed with the
relevant parties at the time they are kept,
whenever possible, yet even if such records
cannot be agreed, they will serve as the
contractor's own evidence for use later, as
maybeappropriate.
Contractors should maintain and request
agreement to as many types of records as
possible, in order to broaden future access to
fully comprehensive contemporaneous
records.
Construction contracts are all too often not
completed on schedule for a multitude of
reasons. A contractor may experience delay
or disruption due to his own actions or
Issue 7, May 2016
4. Thisisnotsodifficult.Dailyrecordskeptbythelocalmeteorologicalofficeshouldbeobtained,relevanttoaperiodof10yearsprecedingtheperiod
of the time for completion. Then, upon the order to commence, daily records from the same source should be obtained and maintained for the
durationoftheWorksuptotheactualcompletiondateasrecordedintheTaking-Overcertificate.
These nationally published records will serve to evidence the periods during construction when exceptionality occurred. This is simplistic yet
effective, where graphically and numerically, one can demonstrate the extent that a contractor could have defined its risk of rainfall at tender
(based on the preceding 10 years of daily records) in order to compare with the rainfall actually experienced during the Works, as depicted for a
limitedperiodintabularformbelow:
From the above (theoretical table of national records) it can be demonstrated that on the dates of 1, 2, 3, 4, 10, 11 & 12 March 2015 (Works) rainfall
exceeded the average rainfall during the preceding 10 years. Further, it demonstrates that on 1 and 2 March 2015, rainfall had exceeded the
maximumrainfallrecordedoverthelast10years.AlloftheabovewouldevidenceinfavouroftheContractor'scase.
However, other than proving exceptionality, nationally published records would not necessarily be sufficient to prove what actually occurred on
the site. For this reason, the contractor should set up an adequate number of weather recording stations, comprising quite basic but effective
monitoringequipment,inorderforadedicatedrecordkeepertorecordthemeasurementssoascertained.
Thesitediaryweatherrecordswillbeusedtoshowhowthecauseofthedelaysduetoinclementweathercanbedemonstratedandhowtheeffect
ontheWorkscouldbeproven.
For instance, activities performed in the open will undoubtedly be affected by uncontrolled factors such as heavy rainfall, exceptional heat,
extremecold,andmaybeevenstorms,highwindsandthelike.
Methodofpresentingrainfallrecords(examples)
(I) Actual daily hours of rainfall, for a sample period from 1 January to 30 April 2015, have been plotted as negative figures (in blue) on the
chartbelow:
4
National Rainfall Data measured in mm (lt/m2)
HistoricalNationalDatarelatingtothe
preceding10yearsPeriod
Month: March
Year/date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
2005 12 10 - - - 2 5 7 6 - - - 10 11 4 8 - 5
2006 8 7 8 - - - 4 9 8 7 8 - - - 11 10 6 -
2007 7 - 2 4 8 9 11 10 - - - - - - 4 3 8 10
2008 2 3 5 8 - - - 9 - - 11 12 15 - - - - -
2009 10 1 7 9 6 7 - - - - - 14 11 12 10 9 - 2
2010 - - 3 5 7 10 3 4 - - - - - 6 7 8 6 6
2011 5 4 6 8 2 - - - - 7 8 7 9 10 4 - - -
2012 9 6 2 3 5 7 - - - - - 3 4 3 12 15 17 2
2013 7 6 - - 2 4 3 4 3 5 - - - - - - - -
2014 4 2 - - - - - - 4 5 4 5 6 - - - - -
Average 6.4 3.9 3.3 3.7 3 3.9 2.6 4.3 2.1 2.4 3.1 4.1 5.5 4.2 5.2 5.3 3.7 2.5
Works
Period
2015 18 12 14 6 2 3 - - - 5 6 9 5 4 2 - - -
Issue 7, May 2016
5. (ii) Actual daily hours recorded as lost or standing time following the effects of heavy rain (clean-up time, pumping time or temporary ditch
work)areaddedtothehoursofrainfalltoshownon-productivehours(inorange)onthechartbelow:
(iii) Actual daily productive hours (in this case three shifts of 8 hrs. each) are added as positive values (in grey) to the chart below:
Within the above, the sum of the above three sets of data (the sum of the grey, blue and orange areas) will always equate to each 24 hours period,
proving by graphical means and supported by the contemporary Site-based weather records, demonstrating that the Contractor was only able to
performworkactivitiesintheopenduringtheperiodswhentheworkareawasnotadverselyaffectedbythedelayingeventofheavyrainfall.
From the above, one can see the importance of the Data Recording and Reporting system recommended, which support the contractor's actions
andhowtheywouldsupportstatementsmadewithinrelevantclaims.Ifaccuraterecordsoftheperiodswhenrainfalloccurredarenotkept,claim
statementswouldnotbesupportedordemonstrable,andsuchaclaimwouldfail.
5
Issue 7, May 2016
6. Techno Engineering & Associates is proud to
announce that we have joined the Annual
meeting and Conference organized by the
Dispute Resolution Board Foundation (DRBF),
a non-profit organization dedicated to
promoting avoidance and the resolution of
disputes worldwide using the unique and
provenDisputeResolutionBoardmethod.
The DRBF Regional Conference & Workshop
th th
was held between 25 and 26 of February
2016, in Livingstone, Zambia. The main
objective of the conference was to share
“BestPracticeintheUseofDisputeBoardsfor
Dispute Avoidance and Resolution” in the
region. Dispute Boards (DB) are recognized
worldwide for their effectiveness in real-time
avoidanceandresolutionofdisputesonmajor
infrastructure projects. This Regional
Conference is the largest and most prominent
professional group of Dispute Board (DB)
users and practitioners in the world.
Experienced project owners, contractors,
consultantsandDBmembershavejoinedwith
representatives from financing institutions to
present “best practices” and “lessons
learned” drawing from a wide spectrum of
existing projects in the region and the global
arena.
Some of the topics discussed during the
conferenceincluded:
DisputeBoardsUnderFIDICContracts;
The financing Institutions' View and DBs
PracticalConsiderations;
DBasaProjectManagementResource.
Several key DRBF members contributed at the
conference, including our President & Senior
Partner, Mr. Giovanni Di Folco on the topic
“Dispute Boards as a Project management
Resource: The Parties' View”. Techno
Engineering & Associates was delighted to
have the opportunity to support and to be
involved in this event which covered the
essentials for a better understanding of
effectiveimplementationofaDisputeBoard.
6
Techno Engineering & Associates is pleased to announce its involvement
with the DRBF Regional Conference & Workshop Livingstone, Zambia
Issue 7, May 2016
7. Techno Engineering & Associates further consolidates its
prominent position with the appointment of Mr. Valentin Stoica
in the position of Business Development Manager
7
We are delighted to publicize the
appointment of Mr. Valentin Stoica as
Business Development Manager for TE&A,
one of the most prominent figures in the civil
engineering domain. Mr. Stoica graduated in
2001 from the University of Oklahoma, USA -
Michael F. Price College of Business - Business
Administration, with a double major in
International Business and Management. In
2004 he obtained his Master's Degree in
International Business from the Academy of
Economic Studies in Bucharest, Romania.
Additionally, in 2005, he completed the post-
graduate course of Design, Construction and
Maintenance of Roads (EUROHOT) from the
BucharestTechnicalUniversity(CFDP).
During his career extending over 15 years, he
has gathered unmatched expertise. In 2001,
he started working at Search Corporation, the
leading engineering company in Romania,
providing services of planning, design,
the present trends and approaches of the
present government, Mr. Stoica also presented
the risks of re-centralizing design and works
supervision activities under the state authority,
and the considerable negative impact that
would have, an approach where all disputes
would be referred strictly to the Romanian
Chamber of Commerce and Romanian Courts.
AlsopresentatthiseventwereMr.VasileDancu
(Vice Prime Minister of Romania, Minister of
R e g i o n a l D e v e l o p m e n t a n d P u b l i c
Administration), Mr. Marcel Bolos (State
Secretary, Ministry of Transportation), Mr.
Emanoil Dascalu (State Secretary, Ministry of
European Funds), Mr. Catalin Homor (General
Manager of the Romanian National Company
forMotorwaysandNationalRoads),Mr.Marius
Chiper (General Manager, Romanian Railway
Company) and many other prestigious leaders
inprivateindustry.
supervision, consulting and management of
road, environment and air transport
infrastructure. He occupied several senior
positions within Search Corporation, which
included Marketing Manager, Marketing and
Development Vice-President, and for the last
eightyears,GeneralManager.
Mr. Stoica is very familiar with the design and
works supervision activities and challenges
within large infrastructure projects. Moreover,
he has also been elected for a second term as
Vice-president of the Romanian Contractors'
Association(ARIC)andheisarticulateinspoken
English,aswellasinSpanish.
From this perspective and as Vice-President of
ARACO, on 15 March 2016 Mr. Stoica delivered a
presentation at the conference organized by
the Capital Magazine, stressing the importance
of the application of the FIDIC Contract
framework at a national level in Romania. Given
Issue 7, May 2016