SlideShare a Scribd company logo
1 of 16
Download to read offline
PART I
by Giovanni Di Folco and Mark Tiggeman
ENFORCEMENT OF DAB DECISIONS IN ARBITRATION
1. The authors wish to express their sincere thanks for the invaluable assistance provided by Ms Laura Teodorescu, Ms Maddison Barford, Ms Olena Gulyanytska and Mr Nicola
Melchiorre, all currently or lately working with Kennedys International Construction Team in London, during the preparation of this article.
2. The Dispute Board Federation, 14, rue du Rhone 1204 Geneva, Switzerland. www.dbfederation.org
1. The authors1
wrote an article for the DBF2
bulletin in September 2010 reporting on their success
in a then ongoing ICC arbitration concerning the early
enforcement of an interim-binding DAB Decision in their
client’s favour that had previously been given during the
course of a disputed project;
2. They argued that considerable legal support
for such interim enforcement among both arbitral
tribunals and some domestic courts alike was at that
time developing apace and, further, that a number of
clear rules or practice points had emerged from the
relevant decisions that could be used to increase the
chances of success when seeking interim enforcement
of DAB Decisions as early as possible in international
arbitration or court proceedings;
3. Since late 2010 the well known series of
Persero cases has progressed through the courts of
Singapore, culminating in the recent second Singapore
Court of Appeal judgment handed down on 27 May
2015. The authors acknowledge that, whilst often
complex, these cases are, overall, extremely helpful in
clarifying the law in this area. That is so not only from
the point of view of the domestic law of Singapore but
also by the significant focus of those judgments on the
true meaning of the terms of Clause 20 of the FIDIC
1999 Red Book thereby helping to clarify the proper
meaning of Clause 20 within an international
framework;
4. The authors’ own ongoing international
arbitration practices have given rise to numerous cases
on which they have worked since their last article which
have demonstrated the often varied procedure now
frequently being used by international arbitral tribunals,
in particular, when considering the best manner in
which to grant interim enforcement of DAB Decisions
on an early basis, namely subject to the ability to have
them altered, or even reversed, if necessary, upon a full
hearing later in the substantive proceedings;
5. Part I of this article will deal with some of the
more important issues on DAB Decision enforceability,
particularly emerging from the Persero cases. Also
included will be some warnings about potentially
important points of procedure when seeking to
maximise the chances of early DAB Decision
enforcement;
6. Part II, which will be published in next
month’s DBF Bulletin, will focus on the authors’
international arbitration experience applying for and
obtaining such enforcement over the last 5 years. It is
hoped that their experience, involving as it does a range
of interesting and sometimes surprising approaches
taken by international arbitral tribunals, will not only
show that this important area of the law is becoming
increasingly well-settled, but also that there are
arguably almost as many variations of approach as
there are applications to be made!
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 3 of 16
Giovanni Di Folco
Giovanni Di Folco is the Senior Partner of
the international consulting firm Techno
Engineering & Associates. Mr Di Folco
has over 25 years experience in civil
engineering, claims and dispute
resolution, 15 years of which specialising
in contentious construction projects
worldwide.
Mark Tiggeman
Mark Tiggeman is a partner of English
international law firm Kennedys. Mr
Tiggeman has over 27 years experience
in dispute resolution, 19 years of which
specialising in contentious construction
projects. Mr Tiggeman is based in
Kennedys’ London office and works
throughout the world.
Summary
INTRODUCTION
3
In most legal jurisdictions, DAB Decisions alone are not enforceable directly by Court proceedings as opposed to arbitral awards which are in many. That situation should, of course, be
contrasted with that which subsists in those legal jurisdictions which have some form of domestic adjudication process available where the adjudicator’s decision is able to be enforced
through their domestic courts via statutory or equivalent legal recognition. Vide the adjudication regime set out in the UK’s Housing Grants Construction and Regeneration Act 1996 (as
amended)
4
[2011] 4 SLR 305
5
Ibid., para.s 64-66.
6
[2010] 4 SLR 672
7
[2015] SGCA 30.
In September 2010, we published in this bulletin a
by now well known article entitled ‘Enforcement of
a DAB Decision through an ICC Final Partial Award.’
It discussed and analysed developments in the
enforcement of binding but not final Dispute
Adjudication Board (“DAB”) Decisions, particularly
by reference to an ICC arbitration in which they
had then recently been involved as co-counsel on
a construction project let on largely standard 1999
FIDIC Red Book conditions. It will be remembered
that in that case the arbitral tribunal found that
binding but not final DAB Decisions could be
enforced through a (Final Partial) Award. That
result was achieved via bifurcated (i.e. split)
proceedings which took place early in the
arbitration as a form of summary procedure. Given
that the premise of the enforcement of these DAB
Decisions in a summary way in arbitration by
partial, interim or even provisional awards is
essentially temporary until the underlying
dispute/s upon which the original DAB Decision
was based can be finally heard and determined in
arbitration, for the sake of simplicity we shall call
that process “Interim Enforcement”.
The Interim Enforcement approach has been
widely espoused by us (and indeed by many other
commentators) as a just and equitable solution to
the perennial problem of delayed payment;
particularly that suffered by parties in
international disputes who are successful before a
DAB but where there is no obvious legal structure
in place for the enforcement of that Decision.3
This approach subsequently received high level
judicial endorsement from the Singapore Court
of Appeal in the much discussed 2011 decision of
CRW Joint Operation v PT Perusahaan Gas Negara
(Persero) TBK4
("Persero CA [2011]") which also
suggested, albeit relatively fleetingly, an acceptance
of the principle of summary-type enforcement by
arbitration of binding but not final DAB Decisions5
.
That judgment followed the first instance decision
rendered in late 2010 by the Singapore High Court in
PT Perusahaan Gas Negara (Persero) TBK v CRW Joint
Operation6
("Persero HC (2010)”).
Particularly helpfully from the perspective of the
timing of this present article, the Singapore Court of
Appeal has very recently rendered yet another
judgment in the Persero saga, PT Perusahaan Gas
Negara (Persero) TBK v CRW Joint Operation7
("Persero
CA [2015]”). That judgment, by a strong majority
comprised of Chief Justice Sundaresh Menon and
Justice Quentin Loh (with Senior Judge Chan Sek
Keong dissenting), clearly endorses the principle
recognised in Persero CA [2011] - a binding but not
final DAB Decision is of itself capable of enforcement
through arbitration. Later in this article we shall return
to Persero CA [2015] to comment on it in some detail
and to see what it may actually mean in practice.
Since publishing our 2010 article, we have continued
to represent clients in further international
arbitrations involving Interim Enforcement
applications. In Part II of this article, to be published
next month in the DBF Bulletin, will also discuss some
key issues arising from those cases in order to
identify both pitfalls and advantages in this
developing jurisprudence for clients and lawyers
alike.
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 5 of 16
PROBLEMS ARISING FROM THE WORDING OF CLAUSE 20
IN THE 1999 FIDIC RED BOOK STANDARD FORM OF CONTRACT
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 7 of 16
8
Steve Mangan, ‘Notes from the FIDIC Users’ Conference, London, December 2011’, Construction Law International, vol. 7, No. 1, March 2012, p 34.
9
See for example: Taner Dedezade, ‘Mind the gap: analysis of cases and principles concerning the ability of ICC arbitral tribunals to enforce binding DAB Decisions under the 1999 FIDIC
conditions of contract’, (2012) IALR, Vol. 15.
10
Christopher Seppälä, ‘Sub-Clause 20.7 of the FIDIC Red Book does not justify denying enforcement of a ‘binding’ DAB Decision’, Construction Law International, Vol. 6, No. 3, October
2011, p 20.
11
Ibid.
As those familiar with the topic will by now know ad
nauseum, the enforceability of binding but not final
DAB Decisions has been the subject of very consider-
able international debate. A certain amount of the legal
uncertainty partially fuelling that debate originates
from a perceived ‘gap’ in the wording of Sub-Clause
20.7. In particular, a DAB Decision that has not been
disputed via either party filing a valid Notice of Dissat-
isfaction (“NoD”) within 28 days will become final and
binding on the parties in accordance with the terms of
Sub-Clause 20.4. A final and binding decision can then
be enforced under Sub-Clause 20.7, which allows the
aggrieved party to “…refer the failure [to comply with the
DAB Decision] itself to arbitration” pursuant to
Sub-Clause 20.6. So far, so clear.
The ‘binding but not final’ conundrum
However, upon the service of a NoD under Sub-Clause
20.4, a DAB Decision remains binding but becomes
non-final. The parties are provided with an express
entitlement then to proceed to arbitration to have any
underlying disputes resolved (but, interestingly, are not
forced to do so notwithstanding the existence of one
or more NoDs). The problem, therefore, is that nowhere
in Clause 20 is there an explicit mechanism for enforc-
ing binding but not yet final DAB Decisions, as
opposed to the underlying disputes contained within
them which are expressly dealt with under the terms of
Sub-Clause 20.6. As pointed out by Steve Mangan, if a
party with an interim binding DAB Decision “…fails to
comply with [it]..., the [Red Book] … do[es] not expressly
permit an aggrieved party to enforce the decision by
referring the failure to arbitration, as it may do under
Sub-Clause 20.7 of the Red Book in the case of a final
and binding decision” (emphasis added). 8
It is the failure of the FIDIC Red Book standard form
wording to provide an explicit means to refer a binding
but not final decision, as opposed to its underlying
disputes, to arbitration that has been interpreted by
commentators, tribunals and courts alike as impliedly
limiting the parties’ ability to enforce such decisions.9
The supposed legal “gap”
However, there has also been strong criticism of what
many see as an unduly restrictive interpretation of
these important sub-clauses. Influential commenta-
tors, such as Christopher Seppälä, have argued that
“courts and tribunals are … going too far to suggest that,
because Sub-Clause 20.7 does not refer to binding
decisions of a DAB, a failure to comply with a binding
decision may not be referred to arbitration.” 10
Seppälä
further clarifies that “Sub-Clause 20.7 should not be
interpreted as implying that a failure to comply with a
binding decision cannot be referred to arbitration.” 11
Whilst these comments are certainly helpful, particu-
larly coming from one who has actually been involved
in drafting the FIDIC standard form wording, they have
not quelled the widespread speculation about the
existence of a so-called legal “gap”.
This “gap” is generally conceived as a lacuna in the
operation of Sub-Clause 20.7. However, rather than a
true “gap” it may be more accurate to ascribe the
confusion surrounding the enforceability of binding
but not final DAB Decisions to a problem of interopera-
bility between the respective Sub-Clauses comprising
Clause 20. Indeed, as seen above, Sub-Clause 20.7 is
reserved for decisions that have already become bind-
ing and final; it would therefore perhaps seem more
accurate to focus on Sub-Clause 20.6 as the correct
provision to apply when dealing with decisions that are
binding but not yet final. Sub-Clause 20.6 provides:
Unless settled amicably, any dispute in
respect of which the DAB’ Decision (if any)
has not become final and binding shall be
finally settled by international arbitra-
tion…The arbitrator(s) shall have the full
power to open up, review and revise any
certificate, determination, instruction, opin-
ion or valuation of the Engineer, and any
decision of the DAB relevant to the dispute.
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 8 of 16
It must be remembered that, according to the
standard wording of Sub-Clause 20.4 in the 1999
FIDIC Red Book, a DAB Decision given thereunder
“…shall be binding on both Parties, who shall give
effect to it unless and until it shall be revised in
an amicable settlement or an arbitration award ...”
(emphasis added). Accordingly, this gives rise to
the oft-referred to concept of an “interim binding”
DAB Decision - being legally binding in the sense
of being required to be complied with by the
parties whilst they await the final determination
of their respective legal rights and obligations
through arbitration.
Sub-Clause 20.4 imposes two key obligations
upon parties to any DAB process. First, that any
resultant decisions shall be binding upon them.
Second, that they shall give prompt effect to DAB
Decisions. The use of the term “binding” for all
DAB Decisions regardless of whether a NoD has
been served must, if there is any real meaning in
that term at all, denote the parties’ express
agreement to comply with any DAB Decision
regardless of whether a NoD has been served by
either of them or both.
This has been expressed in other words thus:
Other commentators take a similar view; in
circumstances where a party fails to give effect
to a DAB Decision it will be in breach of contract
irrespective of the existence of any NoDs. That
is simply because a NoD is a precondition for a
party seeking to have a DAB Decision reviewed
in arbitration but does not have any bearing on
the binding nature of that DAB Decision in the
meantime. This view is supported by others
involved in the drafting of the 1999 FIDIC Red
Book such a Mangan, who states:
“Disputes” vs “decisions” (sub-clauses 20.6
and 20.7 of the 1999 FIDIC Red Book)
We would argue that the legal debate is now
largely settled on this point (i.e. the enforceabil-
ity per se of an interim-binding DAB Decision),
obviously generally in favour of Interim Enforce-
ment. However, a point of ongoing contention is
the legal consequence of the distinction made
between binding but not final DAB Decisions
referred to in Sub-Clause 20.6 and the final and
binding DAB Decisions referred to in
Sub-Clause 20.7. In short, Sub-Clause 20.6
seems to require any disputes (i.e. as opposed
to decisions) that have not been settled amica-
bly and have not become final and binding to be
referred to arbitration for final resolution. How-
ever, Sub-Clause 20.7 by contrast provides that
where a party has failed to comply with a final
and binding DAB Decision, the “failure itself” can
be referred to arbitration.
‘…a temporarily or finally binding DAB Decision
must be dealt with as a matter of legal fact,
being binding on the parties according to
Sub-Clause 20.4. In other words, according to
Sub-Clause 20.4, the parties to the contract
have promised each other to give effect to the
DAB Decision, which is a contractual obliga-
tion governed by the proper law of the contract
whether the DAB Decision is based on the
proper law of the contract or on tort law.’ 12
It had never been FIDIC’s intention to
create a situation where the decision of a
DAB could simply be ignored. Compliance
was assumed and expected of the parties,
failing which, enforcement should be
available in the form of an arbitral award.13
12
FIDIC – A guide for Practitioners [2010] by Axel-Volmar Jaeger and Gotz-Sebastian Hok in 2010 at p 406.
13
Steve Mangan, ‘Notes from the FIDIC Users’ Conference, London, December 2011’, p 34.
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 9 of 16
Hence, in a sense, the scope of the resulting arbitra-
tions is pre-defined by the express terms of these two
significantly different sub-clauses in the 1999 FIDIC
Red Book. To us, the key distinction is the use of the
word “disputes” in Sub-Clause 20.6 as opposed to
“decisions” in Sub-Clause 20.7. This implies that the
merits of the former are required to be re-opened in
order to be heard and determined but that only the
formalities of the latter need be considered in any refer-
ence to arbitration. How else are disputes capable of
being resolved finally? Conversely, DAB Decisions are
exactly that – the consequence of a (final and binding,
by the time Sub-Clause 20.7 applies) determination
that has already taken place which a fortiori do not
need to be re-opened. Accordingly, thereafter the only
issue is whether those DAB Decisions are technically
enforceable (e.g. in the sense of not suffering from any
serious irregularity, etc).
To us, a natural legal result of this way of looking at the
distinction is that an interim-binding DAB Decision can
and ought to be enforced by an arbitral tribunal in the
same manner as a final and binding decision, albeit as
a preliminary-type issue in a bifurcated process in the
case of the former. However, we also feel that the
enforcement of an interim-binding DAB Decision
through, inter alia, the Sub-Clause 20.6 process, is only
capable of being done, in accordance with the terms of
the 1999 FIDIC Red Book in any event, on a temporary
or interim basis with the merits of the decision’s under-
lying dispute/s at the same time being referred to the
(we believe) same arbitral tribunal to be heard and
determined later in the arbitration process (i.e. at the
main hearing dealing with substantive matters). As
discussed below in connection with the Persero cases,
aspects of this proposition may now be under some
doubt. However, with respect, we still feel that it is likely
to be the preferable position internationally when
dealing with Interim Enforcement.
What is also important to remember is that any arbitral
award granting interim enforcement of a final but not
binding DAB Decision (i.e. whether it be partial, interim
or provisional in nature) should, in our view, be able to
be adjusted for in the Final Award later in that same
arbitration should that become necessary.
This simply acknowledges the reality of any Inter-
im Enforcement procedure; its results may poten-
tially need to be modified, or even entirely
reversed, in the event that the arbitral tribunal
ultimately does not agree with the DAB after it has
heard and determined all the merits of the under-
lying dispute/s in the full arbitration. Whilst an
entire reversal of the DAB’s original decision is,
fortunately, far from the norm on construction
projects, our experience is that it is common for
there to be derogations between DAB Decisions
and Final Awards which can sometimes be signifi-
cant. Indeed, that is to be expected given the usual
summary nature of the DAB procedure which,
philosophically at least, is intended to keep cash-
flow moving on construction projects in exchange
for an amount of legal flexibility. Justice is essen-
tially served by greater scrutiny being achievable
in arbitration which will, of course, usually involve
a far more detailed examination of all the facts
and the parties’ respective legal rights and obliga-
tions.
A return to the DAB?
It had for a long time been argued by those of the
more pedantic persuasion that only after returning
to the DAB itself for another decision concerning
the fact of non compliance with one of its own
earlier decisions under Sub-Clause 20.4 could the
disappointed party be entitled to take the issue of
that non compliance to arbitration - but not, in turn,
before supposedly also having to pass (again)
through the requirements of Sub-Clauses 20.4
[Obtaining Dispute Adjudication Board’s Decision],
20.5 [Amicable Settlement] and 20.6 [Referral of
Disputes to Arbitration]! As ridiculous as this may
seem, particularly given the terms of Sub-Clause
20.6 and how relatively fast international jurispru-
dence around Interim Enforcement has developed,
this argument has in the authors’ own combined
experience been used many times by recalcitrant
parties on the losing end of DAB Decisions seeking
simply to delay enforcement for as long as possible.
As we shall see in a moment, this position now
seems finally to be dead.
THE PERSERO CASES
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 11 of 16
This important series of Singaporean cases has
unfolded since 2009 as sort of legal soap opera
– lengthy, with something for everyone including
some nuggets of brilliance. A useful summary of
the procedural background to each of the cases
can be found on the Kluwer Arbitration Blog.14
Finally, the issue of the supposed need to return
to the DAB (under Sub-Clause 20.4), effectively
as a pre-condition to proceed to arbitration for
any non compliance with an existing DAB Deci-
sion, has been squarely addressed and disposed
of by the Court of Appeal in its latest judg-
ment.15
In particular, the court cited with
approval Christopher Seppälä’s well known
views that it was not necessary to re-invent the
wheel in that respect16
and also endorsed
FIDIC’s own guidance on the matter, issued in
April 2013, which states:
The Court of Appeal put it thus:
However, rather intriguingly, it is the procedure
by which binding but not final DAB Decisions are
actually dealt with by way of Interim Enforce-
ment (albeit driven by the Court of Appeal’s view
that two separate legal rights arise from the
issuance of a NoD19
) that appears to have preoc-
cupied the Singapore courts and caused the
greatest degree of variation in the judgments in
Persero. To the extent that the point has square-
ly been addressed, whilst the previous deci-
sions, particularly the decision in Persero CA
[2011], acknowledged the ability of the dissatis-
fied party to bring a claim for Interim Enforce-
ment, they did so emphasising the need also to
refer to the same arbitration the underlying
dispute upon which the DAB Decision was based
(albeit with the latter being likely to be heard and
determined later in those proceedings).20
This Guidance Memorandum is designed
to make explicit the intentions of FIDIC in
relation to the enforcement of the DAB
Decisions that are binding and not yet
final, which is that in the case of failure to
comply with these decisions, the failure
itself should be capable of being referred
to arbitration under Sub-Clause 20.6 [Arbi-
tration], without Sub-Clause 20.4 [Obtain-
ing Dispute Adjudication Board’s Decision]
and Sub-Clause 20.5 [Amicable Settle-
ment] being applicable to the reference.17
To sum up our analysis at [83-[87]
above, cl. 20.4 imposes a distinct
contractual obligation on a paying party
to comply promptly with a DAB Decision
regardless of whether the decision is
final and binding or merely binding but
non-final, and this obligation is capable
of being directly enforced by arbitration
without the parties having to first go
through the preliminary steps set out in
cll 20.4 and 20.5...18
14
S “Another (Unsuccessful) Challenge to the Finality of Interim Arbitral Awards in Singapore and Enforcing DAB Decisions on International Projects Under FIDIC”, posted 14 June 2015
10:07PM PDT by Eugene Tan and Rupert Coldwell.
15
[2015] SGCA 30, para.s 64 – 69.
16
Ibid, para. 65 in turn approving of the article by Seppälä, op. Cit., note 9.
17
Guidance Memorandum for Users of the 1999 Red Book, issued 1 April 2013.
18
[2015] SGCA 30, para. 88.
19
Ibid., p. 47, para. 83.
20
[2011] 4 SLR 305, para.s 67-68.
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 12 of 16
The key development arising out of the latest
Persero instalment, Persero CA [2015], is that now
the “underlying dispute” - also usefully categorised
by the Court of Appeal as the “Primary Dispute”
concerning the merits underlying the DAB Deci-
sion, as opposed to the “Secondary Dispute”
concerning the non-complied with DAB Decision
sought to be enforced - does not now have to be
referred to arbitration at the same time or, it would
seem, at all! The Court of Appeal puts it this way:
...Further, we consider that a tribunal
would be entitled to make a final deter-
mination on the issue of prompt compli-
ance alone if that is all it has been
asked to rule on, as was the case in the
2009 Arbitration...21
...On the other hand, where both the dispute
over the paying party’s non-compliance with
a binding but not final DAB Decision as well
as the dispute over the merits of that DAB
Decision are put before the same tribunal,
as was done in the 2011 Arbitration and,
hence, in the case before us now, the tribu-
nal can: (a) make an interim or partial award
which finally disposes of the first issue (i.e.
whether the paying party has to promptly
comply with the DAB Decision); (b) then
proceed to consider the second issue (i.e.
the merits of the DAB Decision), which is a
separate and conceptually distinct matter
as we have already noted; and (c) subse-
quently, make a final determination of the
underlying dispute between the parties...22
21
Op cit., note 17.
22
Ibid.
What we appear to have now is a very liberal approach having been taken, in
clear terms, by a strong majority judgment in Singapore’s Court of Appeal.
This is essentially to the effect that a party can seek interim enforcement of
a DAB Decision [made under the 1999 FIDIC Red Book] via arbitration
without the need also to refer the underlying dispute to be heard and
determined in the same arbitration or, as we read it, at all. One can imagine
the joy experienced by the contractor in Persero, CRW, which has essentially
been toiling in the legal system for 6 years to achieve just that result!
What now?
It is true, however, that the Court of Appeal goes on
immediately to deal with what we hitherto had
thought was the correct position, namely:
SOME THOUGHTS
Enforcement of a DAB Decision in Arbitration, Part I
by Giovanni Di Folco and Mark Tiggeman
Page 14 of 16
Whilst judicial support for Interim Enforcement is
obviously greatly appreciated by users and supporters
of the dispute board procedure on projects across the
world, with the greatest of respect to the Court of
Appeal it remains to be seen if its rather avant-garde
approach on this potentially important point will prove
popular elsewhere. Obviously, as it stands it is good
law in Singapore and is likely to remain so for a long
time given its very senior origin (and notwithstanding
its lack of unanimity). No doubt that will be seen by
many in the context of Singapore’s continuing, and
largely successful, development of its legal services
sector involving international arbitration and its desire
to be seen at the forefront of developments in this area.
In any event, it must also immediately be acknowl-
edged that the Court of Appeal simultaneously
endorsed the somewhat more traditional position of
the putative claimant referring all of its disputes (i.e.
both “Primary” and “Secondary”, as described in Perse-
ro CA [2015]) to the same arbitration to be determined
in the appropriate order.
However, we have to ask ourselves the question: why
would anyone beyond the jurisdiction of Singapore
want to take the risk of referring only the Secondary
Dispute, namely the dispute about payment per se, to
arbitration when there is a strong chance that many
other legal systems will not interpret Clause 20 in the
same manner and that Interim Enforcement will even-
tually be refused in the absence of the underlying
dispute (the Primary Dispute) being referred to arbitra-
tion at the same time (as, we must remember, was the
case for a long time in Persero, i.e. until the latest
Persero CA [2015] decision was delivered in May
2015)?
At least until this potentially crucial point is clarified
further, we strongly recommend that parties refer all of
their disputes relating to , i.e. Primary and Secondary,
when seeking Interim Enforcement from arbitral
tribunals.
A short note about awards
The key thing to ensure is that a sufficient amount of
finality is achieved with any arbitral award that is
obtained at any stage of arbitral proceedings if, as is
likely to be the case with Interim Enforcement, you
are likely to find it necessary to seek to convert that
into something enforceable by the Courts (i.e. a judg-
ment). We see no reason why Interim Enforcement
should not be achievable through either a “Partial” or
“Interim” Award (as opposed to a provisional award
which is generally seen as a more protecting or
preserving instrument). It is important, however, to
check the law of your anticipated place of enforce-
ment to ensure a thorough understanding as to the
vagaries of any preferences that the domestic courts
of that jurisdiction might have when it comes to
enforcing anything other than “Final” Awards.23
Obviously, the arbitral tribunal can and should make
a Final Award at the main hearing which proceeds to
deal with the legal effect of the underlying dispute/s.
That may involve effectively undoing some or all of
the legal effect of an earlier award in the same
arbitration giving interim effect to a binding but not
final DAB Decision. “Oh, but res judicata” we hear
some readers cry! Not at all. Why? Because any such
award made earlier would solely be concerned with
recognising the legal (i.e. essentially contractual)
enforceability of the DAB Decision (described in
Persero CA [2015] as the “Secondary Dispute”) and
not with the parties’ respective entitlements flowing
from the dispute/s underlying that decision
(described in Persero CA [2015] as the “Primary
Dispute”).24
Accordingly, there is nothing whatever
preventing the arbitral tribunal from dealing with
those entitlements later in the arbitration by way of a
Final Award as that would be the first time, as a
matter of law, that the arbitral tribunal had done so.
23
This has been suggested to the authors to have been the case in Romania, at least prior to that country’s adoption of the New Civil Code in 2011.
24
[2015] SGCA 30, para.s 83–88.
Bucharest/London
26 June 2015

More Related Content

What's hot

Enforcement of DAB decisions under FIDIC conditions of contract
Enforcement of DAB decisions under FIDIC conditions of contractEnforcement of DAB decisions under FIDIC conditions of contract
Enforcement of DAB decisions under FIDIC conditions of contractDaan Goedkoop
 
media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)John McMahon
 
Supreme Court of Texas Marries Contractual Limitations to Insurance Policies
Supreme Court of Texas Marries Contractual Limitations to Insurance PoliciesSupreme Court of Texas Marries Contractual Limitations to Insurance Policies
Supreme Court of Texas Marries Contractual Limitations to Insurance PoliciesNationalUnderwriter
 
Bogdan fidic trainings
Bogdan  fidic trainingsBogdan  fidic trainings
Bogdan fidic trainingsbogdan66
 
Dispute Resolution And DAAB FIDIC Contracts.docx
Dispute Resolution  And DAAB FIDIC Contracts.docxDispute Resolution  And DAAB FIDIC Contracts.docx
Dispute Resolution And DAAB FIDIC Contracts.docxKinzaIrfan2
 
Writing Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu NwaigboWriting Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu NwaigboOnyeka Nwaigbo
 
Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...
Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...
Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...Allen Matkins
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...Werksmans Attorneys
 
Presentation Commitment Letters
Presentation   Commitment LettersPresentation   Commitment Letters
Presentation Commitment Lettersefstra
 
Guarantees in Lending Transactions
Guarantees in Lending TransactionsGuarantees in Lending Transactions
Guarantees in Lending TransactionsJoanneMarsh
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 

What's hot (20)

Enforcement of DAB decisions under FIDIC conditions of contract
Enforcement of DAB decisions under FIDIC conditions of contractEnforcement of DAB decisions under FIDIC conditions of contract
Enforcement of DAB decisions under FIDIC conditions of contract
 
media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)
 
10000001244
1000000124410000001244
10000001244
 
10000001241
1000000124110000001241
10000001241
 
Supreme Court of Texas Marries Contractual Limitations to Insurance Policies
Supreme Court of Texas Marries Contractual Limitations to Insurance PoliciesSupreme Court of Texas Marries Contractual Limitations to Insurance Policies
Supreme Court of Texas Marries Contractual Limitations to Insurance Policies
 
Bogdan fidic trainings
Bogdan  fidic trainingsBogdan  fidic trainings
Bogdan fidic trainings
 
Dispute Resolution And DAAB FIDIC Contracts.docx
Dispute Resolution  And DAAB FIDIC Contracts.docxDispute Resolution  And DAAB FIDIC Contracts.docx
Dispute Resolution And DAAB FIDIC Contracts.docx
 
Jbcc - out with the old
Jbcc - out with the oldJbcc - out with the old
Jbcc - out with the old
 
Against all odds
Against all odds Against all odds
Against all odds
 
Writing Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu NwaigboWriting Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu Nwaigbo
 
Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...
Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...
Commitment Letters in Commercial Loans Borrower and Lender Strategies to Nego...
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
 
Presentation Commitment Letters
Presentation   Commitment LettersPresentation   Commitment Letters
Presentation Commitment Letters
 
10000001240
1000000124010000001240
10000001240
 
10000001237
1000000123710000001237
10000001237
 
Guarantees in Lending Transactions
Guarantees in Lending TransactionsGuarantees in Lending Transactions
Guarantees in Lending Transactions
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
UK Adjudicators September 2021 Newsletter
UK Adjudicators  September 2021 Newsletter UK Adjudicators  September 2021 Newsletter
UK Adjudicators September 2021 Newsletter
 
Reicon14 session 3 final ppt
Reicon14 session 3 final pptReicon14 session 3 final ppt
Reicon14 session 3 final ppt
 
UK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletterUK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletter
 

Similar to Enforcement of a DAB decision in Arbitration. Part I

Looking forward in international arbitration
Looking forward in international arbitration Looking forward in international arbitration
Looking forward in international arbitration Rebecca Davis
 
The interphase between the english national arbitation laws
The interphase between the english national arbitation lawsThe interphase between the english national arbitation laws
The interphase between the english national arbitation lawsValentine Ataka
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONOluwaseyi Bamigboye
 
Saving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationSaving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationOluwaseyi Bamigboye
 
ADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxzulkiflimohdzain1
 
2015 09 10 Peter Boase LLM Dissertation.Pdf
2015 09 10 Peter Boase LLM Dissertation.Pdf2015 09 10 Peter Boase LLM Dissertation.Pdf
2015 09 10 Peter Boase LLM Dissertation.PdfLeonard Goudy
 
The singapore mediation convention
The singapore mediation conventionThe singapore mediation convention
The singapore mediation conventionZafar Kalanauri
 
Brighton joint ngo input to ongoing negotiations 20 march
Brighton joint ngo input to ongoing negotiations 20 marchBrighton joint ngo input to ongoing negotiations 20 march
Brighton joint ngo input to ongoing negotiations 20 marchXatuna Gvelesiani
 
Verträge China in Chinesisch 中国合同
Verträge China in Chinesisch 中国合同Verträge China in Chinesisch 中国合同
Verträge China in Chinesisch 中国合同Global Negotiator
 
China Contracts in English-Chinese 中国合同
China Contracts in English-Chinese 中国合同China Contracts in English-Chinese 中国合同
China Contracts in English-Chinese 中国合同Global Negotiator
 
Contrats pour la Chine en Chinois 中国合同
Contrats pour la Chine en Chinois 中国合同Contrats pour la Chine en Chinois 中国合同
Contrats pour la Chine en Chinois 中国合同Global Negotiator
 
International commercial arbitration
International commercial arbitrationInternational commercial arbitration
International commercial arbitrationMainan Ray
 
In Dire Need of Resolution
In Dire Need of ResolutionIn Dire Need of Resolution
In Dire Need of ResolutionRoland Schroeder
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterSeanGibbs12
 
International Arbitration Quarterly Bulletin, February 2016
International Arbitration Quarterly Bulletin, February 2016International Arbitration Quarterly Bulletin, February 2016
International Arbitration Quarterly Bulletin, February 2016Resolution Institute
 

Similar to Enforcement of a DAB decision in Arbitration. Part I (20)

Looking forward in international arbitration
Looking forward in international arbitration Looking forward in international arbitration
Looking forward in international arbitration
 
Dissertation
DissertationDissertation
Dissertation
 
The interphase between the english national arbitation laws
The interphase between the english national arbitation lawsThe interphase between the english national arbitation laws
The interphase between the english national arbitation laws
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
 
Saving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationSaving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial Arbitration
 
ADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptx
 
2015 09 10 Peter Boase LLM Dissertation.Pdf
2015 09 10 Peter Boase LLM Dissertation.Pdf2015 09 10 Peter Boase LLM Dissertation.Pdf
2015 09 10 Peter Boase LLM Dissertation.Pdf
 
The singapore mediation convention
The singapore mediation conventionThe singapore mediation convention
The singapore mediation convention
 
Brighton joint ngo input to ongoing negotiations 20 march
Brighton joint ngo input to ongoing negotiations 20 marchBrighton joint ngo input to ongoing negotiations 20 march
Brighton joint ngo input to ongoing negotiations 20 march
 
Verträge China in Chinesisch 中国合同
Verträge China in Chinesisch 中国合同Verträge China in Chinesisch 中国合同
Verträge China in Chinesisch 中国合同
 
China Contracts in English-Chinese 中国合同
China Contracts in English-Chinese 中国合同China Contracts in English-Chinese 中国合同
China Contracts in English-Chinese 中国合同
 
Contrats pour la Chine en Chinois 中国合同
Contrats pour la Chine en Chinois 中国合同Contrats pour la Chine en Chinois 中国合同
Contrats pour la Chine en Chinois 中国合同
 
Jacobs University Bremen International Trade Law - Lecture 2: WTO and DSU
Jacobs University Bremen International Trade Law - Lecture 2: WTO and DSUJacobs University Bremen International Trade Law - Lecture 2: WTO and DSU
Jacobs University Bremen International Trade Law - Lecture 2: WTO and DSU
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 
International commercial arbitration
International commercial arbitrationInternational commercial arbitration
International commercial arbitration
 
In Dire Need of Resolution
In Dire Need of ResolutionIn Dire Need of Resolution
In Dire Need of Resolution
 
Treading the Thin Wedge between "Unfair trade Practices" and "Abuse of Domina...
Treading the Thin Wedge between "Unfair trade Practices" and "Abuse of Domina...Treading the Thin Wedge between "Unfair trade Practices" and "Abuse of Domina...
Treading the Thin Wedge between "Unfair trade Practices" and "Abuse of Domina...
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
H0331044050
H0331044050H0331044050
H0331044050
 
International Arbitration Quarterly Bulletin, February 2016
International Arbitration Quarterly Bulletin, February 2016International Arbitration Quarterly Bulletin, February 2016
International Arbitration Quarterly Bulletin, February 2016
 

More from Cerasela Angelescu

TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019Cerasela Angelescu
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...Cerasela Angelescu
 
Understanding the Importance of Risk
Understanding the Importance of RiskUnderstanding the Importance of Risk
Understanding the Importance of RiskCerasela Angelescu
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsCerasela Angelescu
 

More from Cerasela Angelescu (11)

TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
 
TE&A news
TE&A newsTE&A news
TE&A news
 
Newsletter august
Newsletter augustNewsletter august
Newsletter august
 
December Newsletter
December NewsletterDecember Newsletter
December Newsletter
 
Understanding the Importance of Risk
Understanding the Importance of RiskUnderstanding the Importance of Risk
Understanding the Importance of Risk
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
 
Let's pick a TE&A news!
Let's pick a TE&A news! Let's pick a TE&A news!
Let's pick a TE&A news!
 
Let's pick a TE&A news
Let's pick a TE&A newsLet's pick a TE&A news
Let's pick a TE&A news
 

Recently uploaded

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Enforcement of a DAB decision in Arbitration. Part I

  • 1. PART I by Giovanni Di Folco and Mark Tiggeman ENFORCEMENT OF DAB DECISIONS IN ARBITRATION
  • 2.
  • 3. 1. The authors wish to express their sincere thanks for the invaluable assistance provided by Ms Laura Teodorescu, Ms Maddison Barford, Ms Olena Gulyanytska and Mr Nicola Melchiorre, all currently or lately working with Kennedys International Construction Team in London, during the preparation of this article. 2. The Dispute Board Federation, 14, rue du Rhone 1204 Geneva, Switzerland. www.dbfederation.org 1. The authors1 wrote an article for the DBF2 bulletin in September 2010 reporting on their success in a then ongoing ICC arbitration concerning the early enforcement of an interim-binding DAB Decision in their client’s favour that had previously been given during the course of a disputed project; 2. They argued that considerable legal support for such interim enforcement among both arbitral tribunals and some domestic courts alike was at that time developing apace and, further, that a number of clear rules or practice points had emerged from the relevant decisions that could be used to increase the chances of success when seeking interim enforcement of DAB Decisions as early as possible in international arbitration or court proceedings; 3. Since late 2010 the well known series of Persero cases has progressed through the courts of Singapore, culminating in the recent second Singapore Court of Appeal judgment handed down on 27 May 2015. The authors acknowledge that, whilst often complex, these cases are, overall, extremely helpful in clarifying the law in this area. That is so not only from the point of view of the domestic law of Singapore but also by the significant focus of those judgments on the true meaning of the terms of Clause 20 of the FIDIC 1999 Red Book thereby helping to clarify the proper meaning of Clause 20 within an international framework; 4. The authors’ own ongoing international arbitration practices have given rise to numerous cases on which they have worked since their last article which have demonstrated the often varied procedure now frequently being used by international arbitral tribunals, in particular, when considering the best manner in which to grant interim enforcement of DAB Decisions on an early basis, namely subject to the ability to have them altered, or even reversed, if necessary, upon a full hearing later in the substantive proceedings; 5. Part I of this article will deal with some of the more important issues on DAB Decision enforceability, particularly emerging from the Persero cases. Also included will be some warnings about potentially important points of procedure when seeking to maximise the chances of early DAB Decision enforcement; 6. Part II, which will be published in next month’s DBF Bulletin, will focus on the authors’ international arbitration experience applying for and obtaining such enforcement over the last 5 years. It is hoped that their experience, involving as it does a range of interesting and sometimes surprising approaches taken by international arbitral tribunals, will not only show that this important area of the law is becoming increasingly well-settled, but also that there are arguably almost as many variations of approach as there are applications to be made! Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 3 of 16 Giovanni Di Folco Giovanni Di Folco is the Senior Partner of the international consulting firm Techno Engineering & Associates. Mr Di Folco has over 25 years experience in civil engineering, claims and dispute resolution, 15 years of which specialising in contentious construction projects worldwide. Mark Tiggeman Mark Tiggeman is a partner of English international law firm Kennedys. Mr Tiggeman has over 27 years experience in dispute resolution, 19 years of which specialising in contentious construction projects. Mr Tiggeman is based in Kennedys’ London office and works throughout the world. Summary
  • 5. 3 In most legal jurisdictions, DAB Decisions alone are not enforceable directly by Court proceedings as opposed to arbitral awards which are in many. That situation should, of course, be contrasted with that which subsists in those legal jurisdictions which have some form of domestic adjudication process available where the adjudicator’s decision is able to be enforced through their domestic courts via statutory or equivalent legal recognition. Vide the adjudication regime set out in the UK’s Housing Grants Construction and Regeneration Act 1996 (as amended) 4 [2011] 4 SLR 305 5 Ibid., para.s 64-66. 6 [2010] 4 SLR 672 7 [2015] SGCA 30. In September 2010, we published in this bulletin a by now well known article entitled ‘Enforcement of a DAB Decision through an ICC Final Partial Award.’ It discussed and analysed developments in the enforcement of binding but not final Dispute Adjudication Board (“DAB”) Decisions, particularly by reference to an ICC arbitration in which they had then recently been involved as co-counsel on a construction project let on largely standard 1999 FIDIC Red Book conditions. It will be remembered that in that case the arbitral tribunal found that binding but not final DAB Decisions could be enforced through a (Final Partial) Award. That result was achieved via bifurcated (i.e. split) proceedings which took place early in the arbitration as a form of summary procedure. Given that the premise of the enforcement of these DAB Decisions in a summary way in arbitration by partial, interim or even provisional awards is essentially temporary until the underlying dispute/s upon which the original DAB Decision was based can be finally heard and determined in arbitration, for the sake of simplicity we shall call that process “Interim Enforcement”. The Interim Enforcement approach has been widely espoused by us (and indeed by many other commentators) as a just and equitable solution to the perennial problem of delayed payment; particularly that suffered by parties in international disputes who are successful before a DAB but where there is no obvious legal structure in place for the enforcement of that Decision.3 This approach subsequently received high level judicial endorsement from the Singapore Court of Appeal in the much discussed 2011 decision of CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK4 ("Persero CA [2011]") which also suggested, albeit relatively fleetingly, an acceptance of the principle of summary-type enforcement by arbitration of binding but not final DAB Decisions5 . That judgment followed the first instance decision rendered in late 2010 by the Singapore High Court in PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation6 ("Persero HC (2010)”). Particularly helpfully from the perspective of the timing of this present article, the Singapore Court of Appeal has very recently rendered yet another judgment in the Persero saga, PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation7 ("Persero CA [2015]”). That judgment, by a strong majority comprised of Chief Justice Sundaresh Menon and Justice Quentin Loh (with Senior Judge Chan Sek Keong dissenting), clearly endorses the principle recognised in Persero CA [2011] - a binding but not final DAB Decision is of itself capable of enforcement through arbitration. Later in this article we shall return to Persero CA [2015] to comment on it in some detail and to see what it may actually mean in practice. Since publishing our 2010 article, we have continued to represent clients in further international arbitrations involving Interim Enforcement applications. In Part II of this article, to be published next month in the DBF Bulletin, will also discuss some key issues arising from those cases in order to identify both pitfalls and advantages in this developing jurisprudence for clients and lawyers alike. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 5 of 16
  • 6. PROBLEMS ARISING FROM THE WORDING OF CLAUSE 20 IN THE 1999 FIDIC RED BOOK STANDARD FORM OF CONTRACT
  • 7. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 7 of 16 8 Steve Mangan, ‘Notes from the FIDIC Users’ Conference, London, December 2011’, Construction Law International, vol. 7, No. 1, March 2012, p 34. 9 See for example: Taner Dedezade, ‘Mind the gap: analysis of cases and principles concerning the ability of ICC arbitral tribunals to enforce binding DAB Decisions under the 1999 FIDIC conditions of contract’, (2012) IALR, Vol. 15. 10 Christopher Seppälä, ‘Sub-Clause 20.7 of the FIDIC Red Book does not justify denying enforcement of a ‘binding’ DAB Decision’, Construction Law International, Vol. 6, No. 3, October 2011, p 20. 11 Ibid. As those familiar with the topic will by now know ad nauseum, the enforceability of binding but not final DAB Decisions has been the subject of very consider- able international debate. A certain amount of the legal uncertainty partially fuelling that debate originates from a perceived ‘gap’ in the wording of Sub-Clause 20.7. In particular, a DAB Decision that has not been disputed via either party filing a valid Notice of Dissat- isfaction (“NoD”) within 28 days will become final and binding on the parties in accordance with the terms of Sub-Clause 20.4. A final and binding decision can then be enforced under Sub-Clause 20.7, which allows the aggrieved party to “…refer the failure [to comply with the DAB Decision] itself to arbitration” pursuant to Sub-Clause 20.6. So far, so clear. The ‘binding but not final’ conundrum However, upon the service of a NoD under Sub-Clause 20.4, a DAB Decision remains binding but becomes non-final. The parties are provided with an express entitlement then to proceed to arbitration to have any underlying disputes resolved (but, interestingly, are not forced to do so notwithstanding the existence of one or more NoDs). The problem, therefore, is that nowhere in Clause 20 is there an explicit mechanism for enforc- ing binding but not yet final DAB Decisions, as opposed to the underlying disputes contained within them which are expressly dealt with under the terms of Sub-Clause 20.6. As pointed out by Steve Mangan, if a party with an interim binding DAB Decision “…fails to comply with [it]..., the [Red Book] … do[es] not expressly permit an aggrieved party to enforce the decision by referring the failure to arbitration, as it may do under Sub-Clause 20.7 of the Red Book in the case of a final and binding decision” (emphasis added). 8 It is the failure of the FIDIC Red Book standard form wording to provide an explicit means to refer a binding but not final decision, as opposed to its underlying disputes, to arbitration that has been interpreted by commentators, tribunals and courts alike as impliedly limiting the parties’ ability to enforce such decisions.9 The supposed legal “gap” However, there has also been strong criticism of what many see as an unduly restrictive interpretation of these important sub-clauses. Influential commenta- tors, such as Christopher Seppälä, have argued that “courts and tribunals are … going too far to suggest that, because Sub-Clause 20.7 does not refer to binding decisions of a DAB, a failure to comply with a binding decision may not be referred to arbitration.” 10 Seppälä further clarifies that “Sub-Clause 20.7 should not be interpreted as implying that a failure to comply with a binding decision cannot be referred to arbitration.” 11 Whilst these comments are certainly helpful, particu- larly coming from one who has actually been involved in drafting the FIDIC standard form wording, they have not quelled the widespread speculation about the existence of a so-called legal “gap”. This “gap” is generally conceived as a lacuna in the operation of Sub-Clause 20.7. However, rather than a true “gap” it may be more accurate to ascribe the confusion surrounding the enforceability of binding but not final DAB Decisions to a problem of interopera- bility between the respective Sub-Clauses comprising Clause 20. Indeed, as seen above, Sub-Clause 20.7 is reserved for decisions that have already become bind- ing and final; it would therefore perhaps seem more accurate to focus on Sub-Clause 20.6 as the correct provision to apply when dealing with decisions that are binding but not yet final. Sub-Clause 20.6 provides: Unless settled amicably, any dispute in respect of which the DAB’ Decision (if any) has not become final and binding shall be finally settled by international arbitra- tion…The arbitrator(s) shall have the full power to open up, review and revise any certificate, determination, instruction, opin- ion or valuation of the Engineer, and any decision of the DAB relevant to the dispute.
  • 8. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 8 of 16 It must be remembered that, according to the standard wording of Sub-Clause 20.4 in the 1999 FIDIC Red Book, a DAB Decision given thereunder “…shall be binding on both Parties, who shall give effect to it unless and until it shall be revised in an amicable settlement or an arbitration award ...” (emphasis added). Accordingly, this gives rise to the oft-referred to concept of an “interim binding” DAB Decision - being legally binding in the sense of being required to be complied with by the parties whilst they await the final determination of their respective legal rights and obligations through arbitration. Sub-Clause 20.4 imposes two key obligations upon parties to any DAB process. First, that any resultant decisions shall be binding upon them. Second, that they shall give prompt effect to DAB Decisions. The use of the term “binding” for all DAB Decisions regardless of whether a NoD has been served must, if there is any real meaning in that term at all, denote the parties’ express agreement to comply with any DAB Decision regardless of whether a NoD has been served by either of them or both. This has been expressed in other words thus: Other commentators take a similar view; in circumstances where a party fails to give effect to a DAB Decision it will be in breach of contract irrespective of the existence of any NoDs. That is simply because a NoD is a precondition for a party seeking to have a DAB Decision reviewed in arbitration but does not have any bearing on the binding nature of that DAB Decision in the meantime. This view is supported by others involved in the drafting of the 1999 FIDIC Red Book such a Mangan, who states: “Disputes” vs “decisions” (sub-clauses 20.6 and 20.7 of the 1999 FIDIC Red Book) We would argue that the legal debate is now largely settled on this point (i.e. the enforceabil- ity per se of an interim-binding DAB Decision), obviously generally in favour of Interim Enforce- ment. However, a point of ongoing contention is the legal consequence of the distinction made between binding but not final DAB Decisions referred to in Sub-Clause 20.6 and the final and binding DAB Decisions referred to in Sub-Clause 20.7. In short, Sub-Clause 20.6 seems to require any disputes (i.e. as opposed to decisions) that have not been settled amica- bly and have not become final and binding to be referred to arbitration for final resolution. How- ever, Sub-Clause 20.7 by contrast provides that where a party has failed to comply with a final and binding DAB Decision, the “failure itself” can be referred to arbitration. ‘…a temporarily or finally binding DAB Decision must be dealt with as a matter of legal fact, being binding on the parties according to Sub-Clause 20.4. In other words, according to Sub-Clause 20.4, the parties to the contract have promised each other to give effect to the DAB Decision, which is a contractual obliga- tion governed by the proper law of the contract whether the DAB Decision is based on the proper law of the contract or on tort law.’ 12 It had never been FIDIC’s intention to create a situation where the decision of a DAB could simply be ignored. Compliance was assumed and expected of the parties, failing which, enforcement should be available in the form of an arbitral award.13 12 FIDIC – A guide for Practitioners [2010] by Axel-Volmar Jaeger and Gotz-Sebastian Hok in 2010 at p 406. 13 Steve Mangan, ‘Notes from the FIDIC Users’ Conference, London, December 2011’, p 34.
  • 9. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 9 of 16 Hence, in a sense, the scope of the resulting arbitra- tions is pre-defined by the express terms of these two significantly different sub-clauses in the 1999 FIDIC Red Book. To us, the key distinction is the use of the word “disputes” in Sub-Clause 20.6 as opposed to “decisions” in Sub-Clause 20.7. This implies that the merits of the former are required to be re-opened in order to be heard and determined but that only the formalities of the latter need be considered in any refer- ence to arbitration. How else are disputes capable of being resolved finally? Conversely, DAB Decisions are exactly that – the consequence of a (final and binding, by the time Sub-Clause 20.7 applies) determination that has already taken place which a fortiori do not need to be re-opened. Accordingly, thereafter the only issue is whether those DAB Decisions are technically enforceable (e.g. in the sense of not suffering from any serious irregularity, etc). To us, a natural legal result of this way of looking at the distinction is that an interim-binding DAB Decision can and ought to be enforced by an arbitral tribunal in the same manner as a final and binding decision, albeit as a preliminary-type issue in a bifurcated process in the case of the former. However, we also feel that the enforcement of an interim-binding DAB Decision through, inter alia, the Sub-Clause 20.6 process, is only capable of being done, in accordance with the terms of the 1999 FIDIC Red Book in any event, on a temporary or interim basis with the merits of the decision’s under- lying dispute/s at the same time being referred to the (we believe) same arbitral tribunal to be heard and determined later in the arbitration process (i.e. at the main hearing dealing with substantive matters). As discussed below in connection with the Persero cases, aspects of this proposition may now be under some doubt. However, with respect, we still feel that it is likely to be the preferable position internationally when dealing with Interim Enforcement. What is also important to remember is that any arbitral award granting interim enforcement of a final but not binding DAB Decision (i.e. whether it be partial, interim or provisional in nature) should, in our view, be able to be adjusted for in the Final Award later in that same arbitration should that become necessary. This simply acknowledges the reality of any Inter- im Enforcement procedure; its results may poten- tially need to be modified, or even entirely reversed, in the event that the arbitral tribunal ultimately does not agree with the DAB after it has heard and determined all the merits of the under- lying dispute/s in the full arbitration. Whilst an entire reversal of the DAB’s original decision is, fortunately, far from the norm on construction projects, our experience is that it is common for there to be derogations between DAB Decisions and Final Awards which can sometimes be signifi- cant. Indeed, that is to be expected given the usual summary nature of the DAB procedure which, philosophically at least, is intended to keep cash- flow moving on construction projects in exchange for an amount of legal flexibility. Justice is essen- tially served by greater scrutiny being achievable in arbitration which will, of course, usually involve a far more detailed examination of all the facts and the parties’ respective legal rights and obliga- tions. A return to the DAB? It had for a long time been argued by those of the more pedantic persuasion that only after returning to the DAB itself for another decision concerning the fact of non compliance with one of its own earlier decisions under Sub-Clause 20.4 could the disappointed party be entitled to take the issue of that non compliance to arbitration - but not, in turn, before supposedly also having to pass (again) through the requirements of Sub-Clauses 20.4 [Obtaining Dispute Adjudication Board’s Decision], 20.5 [Amicable Settlement] and 20.6 [Referral of Disputes to Arbitration]! As ridiculous as this may seem, particularly given the terms of Sub-Clause 20.6 and how relatively fast international jurispru- dence around Interim Enforcement has developed, this argument has in the authors’ own combined experience been used many times by recalcitrant parties on the losing end of DAB Decisions seeking simply to delay enforcement for as long as possible. As we shall see in a moment, this position now seems finally to be dead.
  • 11. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 11 of 16 This important series of Singaporean cases has unfolded since 2009 as sort of legal soap opera – lengthy, with something for everyone including some nuggets of brilliance. A useful summary of the procedural background to each of the cases can be found on the Kluwer Arbitration Blog.14 Finally, the issue of the supposed need to return to the DAB (under Sub-Clause 20.4), effectively as a pre-condition to proceed to arbitration for any non compliance with an existing DAB Deci- sion, has been squarely addressed and disposed of by the Court of Appeal in its latest judg- ment.15 In particular, the court cited with approval Christopher Seppälä’s well known views that it was not necessary to re-invent the wheel in that respect16 and also endorsed FIDIC’s own guidance on the matter, issued in April 2013, which states: The Court of Appeal put it thus: However, rather intriguingly, it is the procedure by which binding but not final DAB Decisions are actually dealt with by way of Interim Enforce- ment (albeit driven by the Court of Appeal’s view that two separate legal rights arise from the issuance of a NoD19 ) that appears to have preoc- cupied the Singapore courts and caused the greatest degree of variation in the judgments in Persero. To the extent that the point has square- ly been addressed, whilst the previous deci- sions, particularly the decision in Persero CA [2011], acknowledged the ability of the dissatis- fied party to bring a claim for Interim Enforce- ment, they did so emphasising the need also to refer to the same arbitration the underlying dispute upon which the DAB Decision was based (albeit with the latter being likely to be heard and determined later in those proceedings).20 This Guidance Memorandum is designed to make explicit the intentions of FIDIC in relation to the enforcement of the DAB Decisions that are binding and not yet final, which is that in the case of failure to comply with these decisions, the failure itself should be capable of being referred to arbitration under Sub-Clause 20.6 [Arbi- tration], without Sub-Clause 20.4 [Obtain- ing Dispute Adjudication Board’s Decision] and Sub-Clause 20.5 [Amicable Settle- ment] being applicable to the reference.17 To sum up our analysis at [83-[87] above, cl. 20.4 imposes a distinct contractual obligation on a paying party to comply promptly with a DAB Decision regardless of whether the decision is final and binding or merely binding but non-final, and this obligation is capable of being directly enforced by arbitration without the parties having to first go through the preliminary steps set out in cll 20.4 and 20.5...18 14 S “Another (Unsuccessful) Challenge to the Finality of Interim Arbitral Awards in Singapore and Enforcing DAB Decisions on International Projects Under FIDIC”, posted 14 June 2015 10:07PM PDT by Eugene Tan and Rupert Coldwell. 15 [2015] SGCA 30, para.s 64 – 69. 16 Ibid, para. 65 in turn approving of the article by Seppälä, op. Cit., note 9. 17 Guidance Memorandum for Users of the 1999 Red Book, issued 1 April 2013. 18 [2015] SGCA 30, para. 88. 19 Ibid., p. 47, para. 83. 20 [2011] 4 SLR 305, para.s 67-68.
  • 12. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 12 of 16 The key development arising out of the latest Persero instalment, Persero CA [2015], is that now the “underlying dispute” - also usefully categorised by the Court of Appeal as the “Primary Dispute” concerning the merits underlying the DAB Deci- sion, as opposed to the “Secondary Dispute” concerning the non-complied with DAB Decision sought to be enforced - does not now have to be referred to arbitration at the same time or, it would seem, at all! The Court of Appeal puts it this way: ...Further, we consider that a tribunal would be entitled to make a final deter- mination on the issue of prompt compli- ance alone if that is all it has been asked to rule on, as was the case in the 2009 Arbitration...21 ...On the other hand, where both the dispute over the paying party’s non-compliance with a binding but not final DAB Decision as well as the dispute over the merits of that DAB Decision are put before the same tribunal, as was done in the 2011 Arbitration and, hence, in the case before us now, the tribu- nal can: (a) make an interim or partial award which finally disposes of the first issue (i.e. whether the paying party has to promptly comply with the DAB Decision); (b) then proceed to consider the second issue (i.e. the merits of the DAB Decision), which is a separate and conceptually distinct matter as we have already noted; and (c) subse- quently, make a final determination of the underlying dispute between the parties...22 21 Op cit., note 17. 22 Ibid. What we appear to have now is a very liberal approach having been taken, in clear terms, by a strong majority judgment in Singapore’s Court of Appeal. This is essentially to the effect that a party can seek interim enforcement of a DAB Decision [made under the 1999 FIDIC Red Book] via arbitration without the need also to refer the underlying dispute to be heard and determined in the same arbitration or, as we read it, at all. One can imagine the joy experienced by the contractor in Persero, CRW, which has essentially been toiling in the legal system for 6 years to achieve just that result! What now? It is true, however, that the Court of Appeal goes on immediately to deal with what we hitherto had thought was the correct position, namely:
  • 14. Enforcement of a DAB Decision in Arbitration, Part I by Giovanni Di Folco and Mark Tiggeman Page 14 of 16 Whilst judicial support for Interim Enforcement is obviously greatly appreciated by users and supporters of the dispute board procedure on projects across the world, with the greatest of respect to the Court of Appeal it remains to be seen if its rather avant-garde approach on this potentially important point will prove popular elsewhere. Obviously, as it stands it is good law in Singapore and is likely to remain so for a long time given its very senior origin (and notwithstanding its lack of unanimity). No doubt that will be seen by many in the context of Singapore’s continuing, and largely successful, development of its legal services sector involving international arbitration and its desire to be seen at the forefront of developments in this area. In any event, it must also immediately be acknowl- edged that the Court of Appeal simultaneously endorsed the somewhat more traditional position of the putative claimant referring all of its disputes (i.e. both “Primary” and “Secondary”, as described in Perse- ro CA [2015]) to the same arbitration to be determined in the appropriate order. However, we have to ask ourselves the question: why would anyone beyond the jurisdiction of Singapore want to take the risk of referring only the Secondary Dispute, namely the dispute about payment per se, to arbitration when there is a strong chance that many other legal systems will not interpret Clause 20 in the same manner and that Interim Enforcement will even- tually be refused in the absence of the underlying dispute (the Primary Dispute) being referred to arbitra- tion at the same time (as, we must remember, was the case for a long time in Persero, i.e. until the latest Persero CA [2015] decision was delivered in May 2015)? At least until this potentially crucial point is clarified further, we strongly recommend that parties refer all of their disputes relating to , i.e. Primary and Secondary, when seeking Interim Enforcement from arbitral tribunals. A short note about awards The key thing to ensure is that a sufficient amount of finality is achieved with any arbitral award that is obtained at any stage of arbitral proceedings if, as is likely to be the case with Interim Enforcement, you are likely to find it necessary to seek to convert that into something enforceable by the Courts (i.e. a judg- ment). We see no reason why Interim Enforcement should not be achievable through either a “Partial” or “Interim” Award (as opposed to a provisional award which is generally seen as a more protecting or preserving instrument). It is important, however, to check the law of your anticipated place of enforce- ment to ensure a thorough understanding as to the vagaries of any preferences that the domestic courts of that jurisdiction might have when it comes to enforcing anything other than “Final” Awards.23 Obviously, the arbitral tribunal can and should make a Final Award at the main hearing which proceeds to deal with the legal effect of the underlying dispute/s. That may involve effectively undoing some or all of the legal effect of an earlier award in the same arbitration giving interim effect to a binding but not final DAB Decision. “Oh, but res judicata” we hear some readers cry! Not at all. Why? Because any such award made earlier would solely be concerned with recognising the legal (i.e. essentially contractual) enforceability of the DAB Decision (described in Persero CA [2015] as the “Secondary Dispute”) and not with the parties’ respective entitlements flowing from the dispute/s underlying that decision (described in Persero CA [2015] as the “Primary Dispute”).24 Accordingly, there is nothing whatever preventing the arbitral tribunal from dealing with those entitlements later in the arbitration by way of a Final Award as that would be the first time, as a matter of law, that the arbitral tribunal had done so. 23 This has been suggested to the authors to have been the case in Romania, at least prior to that country’s adoption of the New Civil Code in 2011. 24 [2015] SGCA 30, para.s 83–88.
  • 15.