Lessons Learnt
Design & Engineering - Piping
MANIKANDAN BABU
Oct 22, 2022
2 Footer
Title: Systemized for Steam Tracing Field routed piping
Details : Steam tracing drawings not received from LE.
Causes/Reason : It was difficult to monitor work progress.
Solution: Drawing prepared by LTEH & systemized in Ealps system as
Field routed piping to ease of As built documentation, Material
reconciliation & Erection sequence.
Learning: To be systemized to ease Erection sequence , Material reconciliation & Invoice.
Impact: save in time & cost
Remarks:
Positive / Negative
3 Footer
Title: Victaulic coupling for Galvanized lines in Stick built piping
Details : Stick built drawings were issued as s spool with allowance.
Causes/Reason : Welding is not allowed on Galvanized lines as due to welding inner side of
pipe coating of galvanized removed due to temperature of welding
Solution: Proposed to use Victaulic coupling for Galvanized lines in Stick built piping
Learning: Where Green length has been specified on galvanized lines there Victaulic coupling shall be required at site as
field weld is forbidden in Pipe.
Impact: Victaulic pipe couplings can be installed faster than welding & flanging.
Remarks:
Positive / Negative
4 Footer
Title: Support drawing prepared from LE Standard
Details : Individual support drawing not received from LE, Complication in
understanding the pipe support fabrication & Erection.
Causes/Reason : LE support standard details includes a combination of 3 to 4
standards of Each support. This leads to tedious to fabricate pipe supports.
Solution: Ident wise drawing prepared to ease of fabrication & Erection.
Learning: Ident wise drawing to be received from client
Impact: save in time & cost
Remarks:
Positive / Negative
5 Footer
Title: Secondary support drawing Preparation
Details : Secondary support drawing not received from LE,
Causes/Reason : Complication in Fabrication & Installation of Sec.
support.
Solution: Snap was prepared from 3D model with combination of
Drg. no + Ident wise. Coordinates provided from near Colum
reference.
Learning: Secondary support drawing to be included in Structural
drawing.
Impact: save in time & cost
Remarks:
Positive / Negative
6 Footer
Title: Piping GA drawing Preparation
Details : : Piping GA drawing not received from LE,
Causes/Reason : Complication in Erection of Piping.
Solution: GA drawing were prepared pancake wise from 3D model
with adequate details.
Learning: Piping GA drawing to be received from client
Impact: save in time & cost
Remarks:
Positive / Negative
7 Footer
Title: Split of Piping Isometric Drawings
Details : Isometric drawings is being issued in smaller Length even for Straight line and Header line.
Causes/Reason : Isometric drawings received from client as splitted more drawings for Straight line / Header line.
Solution: Isometric drawings to be issued as single or minimum for Straight line / Header line
Learning: Drawings to be ensured before Issuing to minimize the field scope/ To be proposed to client to issue drawings as
single or min.
Impact: This leads to extra cost , Material & Delay in Schedule for Increasing field scope. Coordinates issue for branch
lines.
Remarks:
Positive / Negative
8 Footer
Title: Piping Drawing Preparation - size below 2” lines
Details : Piping Isometric drawing is being issued as Spool drawing for size below 2” lines
Causes/Reason : lot of modification at site, damages of spool & Misplacement of spool
Solution: No spooling required, to be issued as loose item.
Learning: This leads to lot of modification at site, damages of spool & Misplacement of spool.
Impact: Extra cost , Material & Delay in Schedule
Remarks:
Positive / Negative
9 Footer
Title: Piping Stick built – Welded valve scope
Details : Isometric drawing prepared, valve as erection item for Stick built drawings.
Causes/Reason : Communication mismatch with LE/LTEH
Solution: Scope to be freezed through proper communication from client.
Learning: Stick built welded scope to be finalized / Ensured before issuing drawing.
Impact: This leads lot of rework, extra cost & Delay in schedule.
Remarks:
Positive / Negative
10 Footer
Title: Painting system & NDT Detail change in CLL
Details : Change in Painting system & NDT details due to frequent revision of Construction Line list by Client
Causes/Reason : Cross checking latest construction line list with older revision for Painting system and NDT details and
incorporating the changes in Isometric drawing and Ealps.
Solution: To be avoided certain time of revision from client. Revision shall be minimum not bulk.
Learning: Construction line list to be finalized from client. To be avoided frequent revision.
Impact: Spool wrongly painted due to discrepancy.
Remarks:
Positive / Negative
11 Footer
Title: Valve handwheel orientation Missing
Details : Valve handwheel orientation detail missing in Piping Isometric drawing received from client
Causes/Reason : Misunderstanding in valve installation. valve handwheel not matching with Isometric orientation by
default received from vendor.
Solution: Proper valve handwheel orientation detail to be provided from client.
Learning: Valve handwheel orientation to be ensured before issuance of drawing.
Impact: This leads to lot of rework changing the valve handwheel orientation.
Remarks:
Positive / Negative
12 Footer
Title: Steam tracing scope finalization
Details : Stick built coordination & Routing guidance not provided properly for Lead & tail of steam tracing.
Causes/Reason : Information are not clear from Steam tracing and jacketing schedule document and Specification
Solution: Proper details to be provided from client.
Learning: Lot of rework, Fouling with cable tray and other instrument connection.
Impact: Delay in schedule & cost.
Remarks:
Positive / Negative
13 Footer
Title: Steam Jacketing Inlet/outlet connection
Details : Steam Jacketing Inlet/outlet connection small bore pipe drawing issued as spool.
Causes/Reason : small bore coordinates & Orientation mismatch with connecting line
Solution: small bore pipe to be issued as loose item/ allowances shall be given in x, y and z directions
Learning: lot of CRW, material waste
Impact: delay in Schedule & cost
Remarks:
Positive / Negative
14 Footer
Title: Valve orientation VOR & HOR
Details : Some of the welded valve, valve orientation has been mentioned as HOR and
VOR reference like STEM HOR -125 DEG VOR -45DEG
Causes/Reason : It is extremely difficult to understand from drawings
Solution: Orientation to be provided as easy of method for better understanding.
Learning: Wrongly welded valve based on wrong interpretation.
Impact: . Delay in schedule & cost.
Remarks:
Positive / Negative
15 Footer
Title: Cavity relief Gate Valve Flow direction missing
Details : Cavity relief Gate Valve Flow direction missing in Isometrics.
Causes/Reason : It was missed in LTHE spool isometrics and valves were wrongly welded.
Solution: Valve flow direction to be ensured before issuance of drawing
Learning: Special valve flow direction to be taken care in Isometrics.
Impact: delay in Schedule & cost.
Remarks:
Positive / Negative
16 Footer
Title: Galvanized line support/ Shear plate welding
Details : Shear plate welding provided in Isometrics as Erection scope for GI pipe & Identified the issue & instructed to
weld shop itself.
Causes/Reason : Shear plate not welded on GI pipe in some of lines
Solution: All welding to be ensured before Galvanizing Drawing to be prepared properly.
Learning: Welding is not allowed on Galvanized lines. All welding to be ensured before Galvanizing
Impact: delay in schedule & cost.
Remarks:
Positive / Negative
17 Footer
Title: Cut length short in Modified flange connection – Jacketed piping
Details : Cut length short in Modified slip on flange connection - Jacketed piping, welding not met as per code
requirement.
Causes/Reason : Special part shall not be properly customized as per drawing.
Solution: It was identified during early stage of fabrication and resolved.
Learning: Drawing to be checked as per special item dimensional standard.
Impact: This leads to rework of spool & cost
Remarks:
Positive / Negative
18 Footer
Title: Moment free anchor support at Elbow
Details : Moment free anchor support at elbow - LS 544-01
Causes/Reason : Insertion of pipe to pipe & weld as trunnion, 30deg tap in second
trunnion is too tedious task to complete welding of support
Solution: Result to avoid 2nd trunnion pipe, Extra sch pipe can be added in main pipe of trunnion support.
Learning: Type of support to be changed/ Proposed at Initial stage
Impact: Cost & Time
Remarks:
Positive / Negative
19 Footer
Title: Piping secondary support drawing
Details : Piping secondary support drawing issued as snapshot for not received from client.
Causes/Reason : Separate secondary support drawing leads to separate erection
sequences.
Solution: secondary support details to be provided in structural drawing.
Learning: Lot of cut & weld activities at work at height lead to more scaffolding access, Erected in pancake itself same can
be completed.
Impact: Extra manhours to Install
Remarks:
Positive / Negative
20 Footer
Title: Shear plate weld
Details : Shear plate to be welded as Equivalent parent material
Causes/Reason : usage of shear plate discrepancy w.r.t. support specification & Purchase specification. Support spec.
Material – A36/304, as per purchase spec. Equivalent parent material.
Solution: Shear plate to be welded as Parent material
Learning: scope & Procurement material qty to be listed & prior approval will save cost & time.
Impact: wrong welding w.r.t. shear plate & Parent pipe lead to delay in MC and get it approval.
Remarks:
Positive / Negative
21 Footer
Title: Support shipping attachment
Details : Shipping attachment bolting connection to be done. LS 545-91
Causes/Reason : Drilling hinderance on beam.
Solution: Shipping attachment stich weld to be done with column & beam.
Learning: Drilling hole during erection found hard.
Impact: This leads to extra stich weld, cost & time.
Remarks:
Positive / Negative
22 Footer
Title: Special item procurement - Support
Details : Delay in Procurement Special item scope confirmation - support
Causes/Reason : usage of special item in piping support consolidated procurement are needs to be done in prior. like SS
plate / PTFE, Puf & Graphite plate etc.
Solution: Pipe support special item MTO to be received from client
Learning: based on client support special item procurement to be finalized earlier.
Impact: delay in schedule
Remarks:
Positive / Negative
23 Footer
Thank You

More Related Content

What's hot

Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3
Rajiv Kumar
 
what is process piping
what is process pipingwhat is process piping
what is process piping
Varun Patel
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
raghunathan janarthanan
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
MobinVarghese8
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
Velmurugan Sivaraman
 
Fundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerFundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas Engineer
Varun Patel
 
Introduction To Piping Engineering | Gaurav Singh Rajput
Introduction To Piping Engineering | Gaurav Singh RajputIntroduction To Piping Engineering | Gaurav Singh Rajput
Introduction To Piping Engineering | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Introduction to piping department
Introduction to piping departmentIntroduction to piping department
Introduction to piping department
Amir Razmi
 
178680732 pipe-hanger-design
178680732 pipe-hanger-design178680732 pipe-hanger-design
178680732 pipe-hanger-design
Tiago Farinhas
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02Mario Fonseca
 
Piping Fundamentals .pdf
Piping Fundamentals .pdfPiping Fundamentals .pdf
Piping Fundamentals .pdf
VenkataSivaNagaSai
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
IEI GSC
 
Codes and standards by madhur mahajan
Codes and standards by madhur mahajanCodes and standards by madhur mahajan
Codes and standards by madhur mahajan
Madhur Mahajan
 
Piping interview
Piping interviewPiping interview
Piping interview
Akhilesh Kumar
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
Sharad Naik
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
Greg Pajak - P. Tech (Eng.), ISA84 SIS Expert
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
Md Gaffar Beag
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
Sarath Krishnakumar
 

What's hot (20)

Basic piping
Basic pipingBasic piping
Basic piping
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
Fundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerFundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas Engineer
 
Introduction To Piping Engineering | Gaurav Singh Rajput
Introduction To Piping Engineering | Gaurav Singh RajputIntroduction To Piping Engineering | Gaurav Singh Rajput
Introduction To Piping Engineering | Gaurav Singh Rajput
 
Introduction to piping department
Introduction to piping departmentIntroduction to piping department
Introduction to piping department
 
178680732 pipe-hanger-design
178680732 pipe-hanger-design178680732 pipe-hanger-design
178680732 pipe-hanger-design
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
Piping Fundamentals .pdf
Piping Fundamentals .pdfPiping Fundamentals .pdf
Piping Fundamentals .pdf
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
Codes and standards by madhur mahajan
Codes and standards by madhur mahajanCodes and standards by madhur mahajan
Codes and standards by madhur mahajan
 
Piping interview
Piping interviewPiping interview
Piping interview
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
 

Similar to Lessons Learnt - Linde Engg-Piping Final.ppt

Engineering and Design Webinar - September
Engineering and Design Webinar - SeptemberEngineering and Design Webinar - September
Engineering and Design Webinar - September
Piping Technology & Products, Inc.
 
Pipe Support Engineering & Design - June
Pipe Support Engineering & Design - JunePipe Support Engineering & Design - June
Pipe Support Engineering & Design - June
Piping Technology & Products, Inc.
 
Engineering & Design - April
Engineering & Design - April Engineering & Design - April
Engineering & Design - April
Piping Technology & Products, Inc.
 
Engineering & Design - January
Engineering & Design - JanuaryEngineering & Design - January
Engineering & Design - January
Piping Technology & Products, Inc.
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
Piping Technology & Products, Inc.
 
What Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobWhat Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning job
joseph william
 
Pipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case StudiesPipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case Studies
Piping Technology & Products, Inc.
 
Pipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case StudiesPipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case Studies
Piping Technology & Products, Inc.
 
Field Services: Problem Resolution
Field Services: Problem ResolutionField Services: Problem Resolution
Field Services: Problem Resolution
Piping Technology & Products, Inc.
 
Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010
Piping Technology & Products, Inc.
 
Hot runner nozzle cooling method and its influence
Hot runner nozzle cooling method and its influenceHot runner nozzle cooling method and its influence
Hot runner nozzle cooling method and its influence
Gud Mould Industry Limited
 
Case studies in cfd analysis by kk parthiban
Case studies in cfd analysis by kk parthibanCase studies in cfd analysis by kk parthiban
Case studies in cfd analysis by kk parthiban
parthi2006
 
Case Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent AnalysisCase Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent Analysis
Flex Process
 
Presentasi Indra Gunawan_R.2.pdf
Presentasi Indra Gunawan_R.2.pdfPresentasi Indra Gunawan_R.2.pdf
Presentasi Indra Gunawan_R.2.pdf
indra497818
 
Case Study On Metal To Plastic Substitution Opm
Case Study On Metal To Plastic Substitution OpmCase Study On Metal To Plastic Substitution Opm
Case Study On Metal To Plastic Substitution Opm
Nilesh Nevrekar
 
In Rural Trenchless Apps
In Rural Trenchless AppsIn Rural Trenchless Apps
In Rural Trenchless Appsebiskis
 
OEM FinalPresentation 2015
OEM FinalPresentation 2015OEM FinalPresentation 2015
OEM FinalPresentation 2015Nathan Eastburn
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
Case Study of Solar Flat Plat Collector
Case Study of Solar Flat Plat CollectorCase Study of Solar Flat Plat Collector
Case Study of Solar Flat Plat Collector
IRJET Journal
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
Amer Abdul Aziz
 

Similar to Lessons Learnt - Linde Engg-Piping Final.ppt (20)

Engineering and Design Webinar - September
Engineering and Design Webinar - SeptemberEngineering and Design Webinar - September
Engineering and Design Webinar - September
 
Pipe Support Engineering & Design - June
Pipe Support Engineering & Design - JunePipe Support Engineering & Design - June
Pipe Support Engineering & Design - June
 
Engineering & Design - April
Engineering & Design - April Engineering & Design - April
Engineering & Design - April
 
Engineering & Design - January
Engineering & Design - JanuaryEngineering & Design - January
Engineering & Design - January
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
What Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobWhat Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning job
 
Pipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case StudiesPipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case Studies
 
Pipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case StudiesPipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case Studies
 
Field Services: Problem Resolution
Field Services: Problem ResolutionField Services: Problem Resolution
Field Services: Problem Resolution
 
Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010
 
Hot runner nozzle cooling method and its influence
Hot runner nozzle cooling method and its influenceHot runner nozzle cooling method and its influence
Hot runner nozzle cooling method and its influence
 
Case studies in cfd analysis by kk parthiban
Case studies in cfd analysis by kk parthibanCase studies in cfd analysis by kk parthiban
Case studies in cfd analysis by kk parthiban
 
Case Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent AnalysisCase Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent Analysis
 
Presentasi Indra Gunawan_R.2.pdf
Presentasi Indra Gunawan_R.2.pdfPresentasi Indra Gunawan_R.2.pdf
Presentasi Indra Gunawan_R.2.pdf
 
Case Study On Metal To Plastic Substitution Opm
Case Study On Metal To Plastic Substitution OpmCase Study On Metal To Plastic Substitution Opm
Case Study On Metal To Plastic Substitution Opm
 
In Rural Trenchless Apps
In Rural Trenchless AppsIn Rural Trenchless Apps
In Rural Trenchless Apps
 
OEM FinalPresentation 2015
OEM FinalPresentation 2015OEM FinalPresentation 2015
OEM FinalPresentation 2015
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Case Study of Solar Flat Plat Collector
Case Study of Solar Flat Plat CollectorCase Study of Solar Flat Plat Collector
Case Study of Solar Flat Plat Collector
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
 

Recently uploaded

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 

Recently uploaded (20)

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 

Lessons Learnt - Linde Engg-Piping Final.ppt

  • 1. 1 Footer Lessons Learnt Design & Engineering - Piping MANIKANDAN BABU Oct 22, 2022
  • 2. 2 Footer Title: Systemized for Steam Tracing Field routed piping Details : Steam tracing drawings not received from LE. Causes/Reason : It was difficult to monitor work progress. Solution: Drawing prepared by LTEH & systemized in Ealps system as Field routed piping to ease of As built documentation, Material reconciliation & Erection sequence. Learning: To be systemized to ease Erection sequence , Material reconciliation & Invoice. Impact: save in time & cost Remarks: Positive / Negative
  • 3. 3 Footer Title: Victaulic coupling for Galvanized lines in Stick built piping Details : Stick built drawings were issued as s spool with allowance. Causes/Reason : Welding is not allowed on Galvanized lines as due to welding inner side of pipe coating of galvanized removed due to temperature of welding Solution: Proposed to use Victaulic coupling for Galvanized lines in Stick built piping Learning: Where Green length has been specified on galvanized lines there Victaulic coupling shall be required at site as field weld is forbidden in Pipe. Impact: Victaulic pipe couplings can be installed faster than welding & flanging. Remarks: Positive / Negative
  • 4. 4 Footer Title: Support drawing prepared from LE Standard Details : Individual support drawing not received from LE, Complication in understanding the pipe support fabrication & Erection. Causes/Reason : LE support standard details includes a combination of 3 to 4 standards of Each support. This leads to tedious to fabricate pipe supports. Solution: Ident wise drawing prepared to ease of fabrication & Erection. Learning: Ident wise drawing to be received from client Impact: save in time & cost Remarks: Positive / Negative
  • 5. 5 Footer Title: Secondary support drawing Preparation Details : Secondary support drawing not received from LE, Causes/Reason : Complication in Fabrication & Installation of Sec. support. Solution: Snap was prepared from 3D model with combination of Drg. no + Ident wise. Coordinates provided from near Colum reference. Learning: Secondary support drawing to be included in Structural drawing. Impact: save in time & cost Remarks: Positive / Negative
  • 6. 6 Footer Title: Piping GA drawing Preparation Details : : Piping GA drawing not received from LE, Causes/Reason : Complication in Erection of Piping. Solution: GA drawing were prepared pancake wise from 3D model with adequate details. Learning: Piping GA drawing to be received from client Impact: save in time & cost Remarks: Positive / Negative
  • 7. 7 Footer Title: Split of Piping Isometric Drawings Details : Isometric drawings is being issued in smaller Length even for Straight line and Header line. Causes/Reason : Isometric drawings received from client as splitted more drawings for Straight line / Header line. Solution: Isometric drawings to be issued as single or minimum for Straight line / Header line Learning: Drawings to be ensured before Issuing to minimize the field scope/ To be proposed to client to issue drawings as single or min. Impact: This leads to extra cost , Material & Delay in Schedule for Increasing field scope. Coordinates issue for branch lines. Remarks: Positive / Negative
  • 8. 8 Footer Title: Piping Drawing Preparation - size below 2” lines Details : Piping Isometric drawing is being issued as Spool drawing for size below 2” lines Causes/Reason : lot of modification at site, damages of spool & Misplacement of spool Solution: No spooling required, to be issued as loose item. Learning: This leads to lot of modification at site, damages of spool & Misplacement of spool. Impact: Extra cost , Material & Delay in Schedule Remarks: Positive / Negative
  • 9. 9 Footer Title: Piping Stick built – Welded valve scope Details : Isometric drawing prepared, valve as erection item for Stick built drawings. Causes/Reason : Communication mismatch with LE/LTEH Solution: Scope to be freezed through proper communication from client. Learning: Stick built welded scope to be finalized / Ensured before issuing drawing. Impact: This leads lot of rework, extra cost & Delay in schedule. Remarks: Positive / Negative
  • 10. 10 Footer Title: Painting system & NDT Detail change in CLL Details : Change in Painting system & NDT details due to frequent revision of Construction Line list by Client Causes/Reason : Cross checking latest construction line list with older revision for Painting system and NDT details and incorporating the changes in Isometric drawing and Ealps. Solution: To be avoided certain time of revision from client. Revision shall be minimum not bulk. Learning: Construction line list to be finalized from client. To be avoided frequent revision. Impact: Spool wrongly painted due to discrepancy. Remarks: Positive / Negative
  • 11. 11 Footer Title: Valve handwheel orientation Missing Details : Valve handwheel orientation detail missing in Piping Isometric drawing received from client Causes/Reason : Misunderstanding in valve installation. valve handwheel not matching with Isometric orientation by default received from vendor. Solution: Proper valve handwheel orientation detail to be provided from client. Learning: Valve handwheel orientation to be ensured before issuance of drawing. Impact: This leads to lot of rework changing the valve handwheel orientation. Remarks: Positive / Negative
  • 12. 12 Footer Title: Steam tracing scope finalization Details : Stick built coordination & Routing guidance not provided properly for Lead & tail of steam tracing. Causes/Reason : Information are not clear from Steam tracing and jacketing schedule document and Specification Solution: Proper details to be provided from client. Learning: Lot of rework, Fouling with cable tray and other instrument connection. Impact: Delay in schedule & cost. Remarks: Positive / Negative
  • 13. 13 Footer Title: Steam Jacketing Inlet/outlet connection Details : Steam Jacketing Inlet/outlet connection small bore pipe drawing issued as spool. Causes/Reason : small bore coordinates & Orientation mismatch with connecting line Solution: small bore pipe to be issued as loose item/ allowances shall be given in x, y and z directions Learning: lot of CRW, material waste Impact: delay in Schedule & cost Remarks: Positive / Negative
  • 14. 14 Footer Title: Valve orientation VOR & HOR Details : Some of the welded valve, valve orientation has been mentioned as HOR and VOR reference like STEM HOR -125 DEG VOR -45DEG Causes/Reason : It is extremely difficult to understand from drawings Solution: Orientation to be provided as easy of method for better understanding. Learning: Wrongly welded valve based on wrong interpretation. Impact: . Delay in schedule & cost. Remarks: Positive / Negative
  • 15. 15 Footer Title: Cavity relief Gate Valve Flow direction missing Details : Cavity relief Gate Valve Flow direction missing in Isometrics. Causes/Reason : It was missed in LTHE spool isometrics and valves were wrongly welded. Solution: Valve flow direction to be ensured before issuance of drawing Learning: Special valve flow direction to be taken care in Isometrics. Impact: delay in Schedule & cost. Remarks: Positive / Negative
  • 16. 16 Footer Title: Galvanized line support/ Shear plate welding Details : Shear plate welding provided in Isometrics as Erection scope for GI pipe & Identified the issue & instructed to weld shop itself. Causes/Reason : Shear plate not welded on GI pipe in some of lines Solution: All welding to be ensured before Galvanizing Drawing to be prepared properly. Learning: Welding is not allowed on Galvanized lines. All welding to be ensured before Galvanizing Impact: delay in schedule & cost. Remarks: Positive / Negative
  • 17. 17 Footer Title: Cut length short in Modified flange connection – Jacketed piping Details : Cut length short in Modified slip on flange connection - Jacketed piping, welding not met as per code requirement. Causes/Reason : Special part shall not be properly customized as per drawing. Solution: It was identified during early stage of fabrication and resolved. Learning: Drawing to be checked as per special item dimensional standard. Impact: This leads to rework of spool & cost Remarks: Positive / Negative
  • 18. 18 Footer Title: Moment free anchor support at Elbow Details : Moment free anchor support at elbow - LS 544-01 Causes/Reason : Insertion of pipe to pipe & weld as trunnion, 30deg tap in second trunnion is too tedious task to complete welding of support Solution: Result to avoid 2nd trunnion pipe, Extra sch pipe can be added in main pipe of trunnion support. Learning: Type of support to be changed/ Proposed at Initial stage Impact: Cost & Time Remarks: Positive / Negative
  • 19. 19 Footer Title: Piping secondary support drawing Details : Piping secondary support drawing issued as snapshot for not received from client. Causes/Reason : Separate secondary support drawing leads to separate erection sequences. Solution: secondary support details to be provided in structural drawing. Learning: Lot of cut & weld activities at work at height lead to more scaffolding access, Erected in pancake itself same can be completed. Impact: Extra manhours to Install Remarks: Positive / Negative
  • 20. 20 Footer Title: Shear plate weld Details : Shear plate to be welded as Equivalent parent material Causes/Reason : usage of shear plate discrepancy w.r.t. support specification & Purchase specification. Support spec. Material – A36/304, as per purchase spec. Equivalent parent material. Solution: Shear plate to be welded as Parent material Learning: scope & Procurement material qty to be listed & prior approval will save cost & time. Impact: wrong welding w.r.t. shear plate & Parent pipe lead to delay in MC and get it approval. Remarks: Positive / Negative
  • 21. 21 Footer Title: Support shipping attachment Details : Shipping attachment bolting connection to be done. LS 545-91 Causes/Reason : Drilling hinderance on beam. Solution: Shipping attachment stich weld to be done with column & beam. Learning: Drilling hole during erection found hard. Impact: This leads to extra stich weld, cost & time. Remarks: Positive / Negative
  • 22. 22 Footer Title: Special item procurement - Support Details : Delay in Procurement Special item scope confirmation - support Causes/Reason : usage of special item in piping support consolidated procurement are needs to be done in prior. like SS plate / PTFE, Puf & Graphite plate etc. Solution: Pipe support special item MTO to be received from client Learning: based on client support special item procurement to be finalized earlier. Impact: delay in schedule Remarks: Positive / Negative