IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
Â
Lessons from the Courts: How to Limit Your Professional Liability
1. Lessons from the Courts: How
to Limit Your Professional
Liability
by
Lawrence W. Falbe, J.D.
Partner, Quarles & Brady LLP
Former Adjunct Professor of Environmental Law,
Northwestern University
2. Overview
⢠Importance of Legal Principles in Limiting
Professional Liability
⢠Hypotheticals based on Reported
Decisions
⢠Final Thoughts
3. Key Legal Principles
⢠Economic Loss Rule (Moorman)
⢠Contractual Limitations on Liability
(monetary)
⢠Reliance / Privity
⢠Standard of Care
⢠Proving Damages
4. Hypothetical #1 â Economic Loss
Client wishes to investigate the possibility of contamination on a prospective
property purchase. Consultant proposes to Client to perform a Phase I at a
cost of $5000. Consultant performs the Phase I, which reveals no Recognized
Environmental Conditions (RECs). Client buys the property in reliance on the
Phase I, but during construction, several unknown leaking USTs are
discovered. Consultant is sued by Client claiming Consultant should have
identified the existence of the USTs before Client purchased the property.
Consultant denies its Phase I was faulty, but in any event claims that it is liable
for nothing more than the cost of the Phase I. Consultant argues that at worst,
it failed to provide what it promised the Client, a competent Phase I report.
Therefore Clientâs damages are limited to $5000.
Is Consultantâs defense successful?
5. Hypothetical #1 - Discussion
Is Consultantâs defense successful?
Answer: It depends on the type of legal claim⌠and on what jurisdiction you
are in.
6. Hypothetical #1 - Discussion
If Client sues simply for breach of contract, Client can recover for only the benefit of the
bargain, the value of which was $5000.
However, Client claims that it would not have purchased the property had it known of the
leaking USTs⌠or, at least investigated further to estimate the costs of clean-up and
subsequently tried to bargain down the price with the Seller. Clientâs damages are not
simply limited to the value of the contract with Consultant.
Solution: Client amends its Complaint to add a claim for Professional Negligence.
7. Hypothetical #1 - Discussion
Solution: Client amends its Complaint to add a claim for Professional Negligence.
Consultant Responds: Nope, nice try, but claims for professional negligence are
barred by the Economic Loss Rule- known in Illinois as the Moorman Doctrine:
âWhen the defect is of a qualitative nature and the harm relates to the consumerâs
expectation that a product is of a particular quality so that it is fit for ordinary use,
contract, rather than tort, law provides the appropriate set of rules for recovery.â
For example, an engineer who negligently builds a bridge (something tangible) cannot
be held liable for professional negligence; only for breach of contract â the damages
being the value of the bridge, not any consequential damages flowing from the negligent
design.
8. Hypothetical #1 - Discussion
However, Moorman is inappropriate where a professional relationship results in
something intangible. A great many businesses involve an exchange of information as
well as of tangible products.
In Tribune Company v. Geraghty & Miller, 1997 WL 438836 (N.D. Ill. July 25, 1997),
Tribune Company sued Geraghty & Miller for failure to identify asbestos-containing
materials after completing a Phase I ESA, which were identified in a later investigation
by a different consultant.
9. Hypothetical #1 - Discussion
The court held, âThe contract between the Tribune and G&M defined the scope of the
assessment to be performed and required G&M to produce a tangible report outlining
G&Mâs findings and conclusions. Nevertheless, the ultimate result of the relationship
between the Tribune and G&M was something intangible. Like a legal brief, financial
statement, or termite inspectorâs report, the value of G&Mâs services lies in the analytical
work summarized in the environmental assessment report, not in the report itself. Unlike
architectural or engineering plans, G&Mâs report was not meant to result in any tangible
structure, the characteristics of which could easily be embodied in contractual terms.â
10. Hypothetical #1 - Discussion
Similarly, in Neumann v. Carlson Environmental, 429 F. Supp. 946 (N.D. Ill. April 20,
2006), Carlson conducted a Phase I ESA and a subsequent subsurface soil
investigation to determine in USTs had impacted the property. Carlson determined that
the soil did not contain any VOCs in excess of Illinois TACO limits, but a subsequent
investigation by a different consultant identified several different VOCs in excess of
TACO limits on the property. The property owner had to agree to remove the USTs,
remediate the soil and deposit $300,000 into an escrow account to cover any further
needed remediation.
11. Hypothetical #1 - Discussion
Carlson was sued and argued that the claim for professional negligence was barred by
the Moorman doctrine. Following the Tribune case, the court held that Carlsonâs
particularized knowledge and expertise gave rise to a duty independent of contract with
plaintiffs (its professional duty to provide an accurate environmental assessment) and
because the primary service provided to plaintiffs was intangible, the Moorman doctrine
does not bar a claim for professional negligence based on professional malpractice by
an environmental consultant.
12. Hypothetical #1 - Discussion
Does Moorman apply in other states? Yes, but they donât call it Moorman, which was
a specific Illinois case, so it is referred to generically as the âeconomic loss doctrine.â
A majority of jurisdictions follow the reasoning of the Tribune and Neumann courts.
See, e.g., Brandsmart USA of West Palm Beach, Inc. v. Della Ratta, Inc., 2003 WL
23926113 (S.D. Fla. December 3, 2003), where BrandSmart sued consultant Qore for
allegedly defective Phase I, court held that âthe economic loss rule does not bar a cause
of action against a professional for his or her negligence even though damages are
purely economic in nature and the aggrieved party has entered into a contract with the
professionalâs employer.â
But see Iron Partners, LLC v. Dames & Moore, 2009 WL 1587898 (W.D. Wash. June 8,
2009), holding that economic loss doctrine would apply to professional negligence
claims based on allegedly defective Phase I report.
13. Hypothetical #2 â Monetary Limitations
Consultant, knowing now that it can be sued for professional negligence and that the
economic loss doctrine exposes it to liability for negligence potentially far beyond the
value of the contract, wants to figure out another way to limit its liability to a client if it
messes up.
Solution: Consultant inserts a contractual limitation of liability into its standard Terms &
Conditions in its contract with prospective clients that states that Consultant disclaims
any and all warranties and is not responsible for any damages to client resulting from
any errors or omissions in the report.
Consultant is then sued and raises the contractual limitation of liability as a defense.
Is Consultantâs attempt to disclaim all liability successful?
14. Hypothetical #2 - Discussion
Is Consultantâs attempt to disclaim all liability successful?
Answer: Probably not.
Reasoning: Most courts will hold that a limitation of liability is unenforceable if it
violates public policy. Exculpatory provisions in professional service contracts are
contrary to public policy because such clauses âare antithetical to a professional service
relationship.â An exculpation clause is a contractual provision relieving a party from any
liability resulting from a negligent or wrongful act. 66 WMD Associates, LLC v. Melick-
Tully & Associates PC, 2011 WL 3503160 (N.J. Super. A.D. August 11, 2011).
15. Hypothetical #2 - Discussion
Okay â what about a limitation of liability that does not completely exclude
damages for liability, but limits the monetary amount?
Answer: It depends. Courts first will look at the limitation of liability in terms of dollar
amount in relation to the contract price to see if there is still an incentive to properly
perform the contract. They will also look at the relative sophistication and bargaining
position of the parties.
16. Hypothetical #2 - Discussion
In 66 VMD Associates, VMD contracted with Melick-Tully & Associates (MTA), to
perform several investigations and remediation costs estimates. MTAâs standard Terms
& Conditions included the following paragraph:
14.1 Many risks potentially affect MTA by virtue of entering into this Agreement
for Consulting Services on behalf of the Client. The principal risk is the potential
for human error by MTA. For Client to obtain the benefit of a fee which includes a
nominal allowance for dealing with MTAâs liability, Client agrees to limit MTAâs
liability to Client and to all other parties for claims arising out of MTAâs
performance of the services described in this Agreement. The aggregate liability
of MTA will not exceed $25,000 for negligent professional acts, errors or
omissionsâŚ
17. Hypothetical #2 - Discussion
For the particular contract at issue in 66 VMD Associates, the client VMD had paid
$19,826.35 to MTA. VMD sued MTA, claiming professional negligence. MTA raised the
liability limitation provision as a defense and claimed that VMDâs damages were capped
at $25,000. VMD countered that the limitation on liability clause was unenforceable as
against public policy, and was impermissible in professional services contracts.
18. Hypothetical #2 - Discussion
Held: Public policy does not disfavor limitations of liability in professional services
contracts, at least where there is no significant disparity in bargaining position between
the two parties. The court stated that the contracts were ânegotiated and executed
between two experienced and knowledgeable parties.â Moreover, the $25,000 limitation
of liability âprovided ample motivation for MTA to perform diligent work because it
exposed MTA to damagesâŚ. $5,000 in excess of its entire fee.â
19. Hypothetical #2 - Discussion
Discussion Points: What would have happened if the client had not been a
sophisticated real estate developer, experienced with hiring consultants and negotiating
professional services contracts?
What if the fee paid had ended up being in excess of the limitation ($25,000) â what if, in
fact, the fee paid was $50,000. Might the judge have ruled that it was the practical
equivalent of an exculpation clause? (Consider - Was that limitation specifically
negotiated or was that a âboilerplateâ limit that just happened to work out in this case?)
Practice Tip: Ensure that any specific liability limitations are comfortably in excess of
the value of the contract, to provide the âsufficient economic compulsionâ to complete
the work diligently. Often, limiting liability to the value of the contractorâs professional
liability insurance is acceptable by clients.
20. Hypothetical #3 â Reliance/Privity
Consultant knows that environmental reports such as Phase Is often fall into the hands
of persons other than the client who contracted for and paid for the report. Consultant
therefore next tries to limit its liability (at least to third parties) by making sure that the
contract for its Phase I services states very clearly that the report is for the exclusive use
of the party who hired it (the âClientâ). Consultant expressly states that only the Client
may rely on the Phase I that will be produced, and that express written authorization by
Consultant is required before any other party can rely on the Phase I (and theoretically
sue Consultant for professional negligence). Consultant states this in the contract
Terms & Conditions but also inserts it into the text of each environmental report it
produces.
Is Consultantâs scheme to limit liability only to the Client legally effective?
21. Hypothetical #3 â Discussion
Is Consultantâs scheme to limit liability only to the Client legally effective?
Answer: Generally yes. Most courts will uphold a contractual limitation on who is
entitled to rely on a professional report.
âAbsent privity of contract, or the functional equivalent of privity of contract⌠entities
have no right to recover from Impact [the consultant] either for breach of contract or
professional negligence.â Southern Wine & Spirits of America v. Impact Environmental
Engineering, 104 A.D.3d. 613 (N.Y. Sup. Ct. 2013). âFurther, the partiesâ agreements
contained a clause in which Impact disclaimed any intention to benefit third parties, and
there is no evidence of any provisions in the partiesâ agreements granting enforceable
rights to any entity other than Impact.â
22. Hypothetical #3 â Discussion
In Grand Pier Center LLC v. ATC Group Services, 2008 WL 4933971 (N.D. Ill. Nov. 14,
2008), Raymond Chin, a principal of RM Chin and Associates (RMC) was the managing
member of Grand Pier LLC, an entity formed to purchase property in the Streeterville
area of Chicago. RMC (not Grand Pier) contracted for a Phase I ESA from ATC.
ATCâs Phase I allegedly did not identify a former gaslight mantle manufacturer that used
radioactive thorium on the subject property and over 10,000 tons of radioactive
contaminated soil had to be removed from the Grand Pier site. Grand Pier LLC sued
ATC for professional negligence. ATC argued that its contract was with RMC, not
Grand Pier (even though they were related parties) and that ATC owed no duty to Grand
Pier given that a reliance limitation was included in the RMC contract.
Held: Grand Pier was not a foreseeable user of the Phase I report and had no right to
rely on the report.
23. Hypothetical #3 â Discussion
Interestingly in the Grand Pier case, ATC had granted Grand Pier permission to rely on
a Phase II report it had prepared (but not the Phase I). Grand Pier tried to argue that
permission to rely on one report constituted permission to rely on all of the reports
involved in the case. The Court found no evidence in the language of the reports to
support this argument and rejected it.
24. Hypothetical #3 â Discussion
Food for Thought: In Mercy Center, Inc. v. JLC Environmental Consultants, Inc., 2005
WL 4441855 (N.Y. Sup. Ct. Dec. 12, 2005), the court deemed a sub consultant
(Advanced Cleanup Technologies) who performed ground-penetrating radar services for
consultant JLC, to have potential liability to plaintiff Mercy Center, who hired JLC, even
though there was no contract between Mercy and Advanced.
25. Hypothetical #3 â Discussion
Held: The Mercy Center court stated, in finding potential liability against Advanced
under the theory of negligent misrepresentation:
âThis is not a case where the defendant is being sued by a member of the public at
large, who happened to rely on figures, statistics, or facts which the defendant prepared
while oblivious to the existence of the relying party. Advanced was retained by JLC to
conduct a radar survey of a particular parcel of real property. It cannot be denied as a
matter of law that Advanced possessed a clear understanding that such a survey was
being performed preparatory to reliance by some party having an ownership interest, or
responsibility, vis-a-vis the surveyed propertyâŚ. The law does not require that
Advanced knows the precise name of the individual, just that it knows there exists such
an individual, whose use of the report is⌠the end and aim of the transaction.â
26. Hypothetical #3 â Discussion
Caution: Some courts have found that liability can be imposed on a consultant even in
the absence of contractual privity (typically the tort of negligent misrepresentation)
where there is:
1) an awareness by the maker of the statement that it is to be used for a particular
purpose;
2) reliance by a known party on the statement in furtherance of that purpose; and
3) some conduct from the maker of the statement linking it to the relying party and
evincing its understanding of that reliance.
Ridge Seneca Plaza v. BP Products North America, 2008 WL 5244014 (W.D.N.Y. Dec.
16th 2008).
27. Hypothetical #3 â Discussion
Caution: Be aware of actions that can cause the appearance of a âspecial relationshipâ
that could lead a party (and a court) to believe that it could reasonably rely on the
consultantâs advice, even in the absence of a contractual relationship (and typical
disclaimers).
Consider: What might a court rule if Consultant was hired to do a Phase I by the owner
of a property, and then was asked to discuss the results with a prospective buyer â even
if the buyer does not pay for a reliance letter, or potentially ever receive a copy of the
Phase I? Could the prospective buyer bring a claim against Consultant even if no privity
of contract existed?
Practice Tip: Resist the temptation to âbe a good consultantâ and â even if requested
by your Client -- discuss the results of a Phase I with anyone else who might be able to
make a claim that they relied to their detriment on your work.
28. Hypothetical #3a â Reliance Letters
Consultantâs policy is that if a third party wants to rely on its work, it will issue a
âReliance Letterâ for $500 that will entitle the recipient to fully rely on the Phase I just as
if the third party had originally commissioned it (as provided under ASTM 1527-13,
section 4.6).
Consultant provides such a letter to a third-party for a previously issued Phase I that is
still viable under E1527-13. However, the third-party then claims it relied on the report
to its detriment and sues Consultant for malpractice, claiming $2,000,000 in damages.
Consultant defends on the basis that the original Terms & Conditions in the
contract for the Phase I limits its liability to $50,000. Is Consultantâs defense
legally valid?
29. Hypothetical #3a â Reliance Letters
Consultant defends on the basis that the original Terms & Conditions in the
contract for the Phase I limits its liability to $50,000. Is Consultantâs defense
legally valid?
Answer: Maybe (probably) not. Anecdotally, a Texas trial court ruled that where a
consulting firm agreed to sell a copy of its Phase I report (identifying no RECs) to a
prospective developer for a property for $180, and buried drums and battery cases were
discovered, the court held that the developer was not bound by the contractual
limitations in the original contract with the original client. Moreover, since the consultant
charged the developer a fee (albeit a nominal fee), the court held that the consultant
owed the developer the benefit of their professional expertise. Settlement costs were
reportedly close to $1,800,000. Legally, this result should probably be expected where
the developer paid value to the consultant and had no way to be apprised of the original
terms of the contract.
30. Hypothetical #4 â Standard of Care
Consultant was retained to perform a Phase I ESA on a property located next to a public
park. Consultant, under cost pressures to perform competitive Phase Is, begins using
an intern to help with Phase I investigations. Consultant sends Intern out alone to do
the site visit. Intern sees nothing constituting a REC and the Phase I otherwise
identifies no RECs. It turns out later that a municipal landfill was present under the
public park, and some of the waste had been disposed of over the lot line onto the
subject property. There was no visible evidence of the former landfill. Consultant is
sued for professional negligence for failure to identify the former landfill and recommend
Phase II testing.
Consultant defends by stating that the ASTM E1527-13 practice does not require that
the environmental professional to conduct the site visit himself or herself.
Is conformance to the ASTM Phase I standard an absolute defense against
professional negligence?
31. Hypothetical #4 â Standard of Care
Is conformance to the ASTM Phase I standard an absolute defense against
professional negligence?
Answer: Itâs something of a trick question. In this scenario, we canât say the Intern
was unqualified as a rule, since the Phase I standard states that âthe interviews and site
reconnaissance shall be performed by a person possessing sufficient training and
experience necessary to conduct the site reconnaissance and interviews in accordance
with this practice, and having the ability to identify issues relevant to recognized
environmental conditions in connection with the property.â E1527-13 sec. 7.5.1
It really depends on the personâs training and capabilities, intern or not.
32. Hypothetical #4 â Standard of Care
It really depends on the personâs training and capabilities, intern or not â but also
what actions the person took or did not take, irrespective of their
training/experience.
So, how do we evaluate that? In the context of a lawsuit for professional negligence, it
will probably turn on expert testimony concerning the industry standard, as applied to
the specific facts of the case.
See, e.g., Watco v. Pickering Environmental Consultants, Inc., 2007 WL 1610093 (Tenn.
Ct. App. June 5, 2007). In Watco, the âinternâ was a college graduate who had just
received a bachelor of science degree in physics, and performed the site visit after two
weeks of training by the environmental professional, Mr. Pickering.
33. Hypothetical #4 â Standard of Care
Mr. Williams, an expert for the plaintiff testified regarding the standard of care that
should apply in the case, and focused on several aspects of the Pickering Phase I,
including whether conducting interviews of nearby property owners would have revealed
anecdotes of the former landfill, and whether the search of county record had been
sufficiently thorough.
However, Mr. Williams admitted on cross examination that there was nothing observable
on the site visit in terms of the existence of the former landfill (it was, after all, three feet
below the surface) that would have indicated to anyone, regardless of experience, that a
recognized environmental condition existed on the subject property as a result of the
former landfill.
34. Hypothetical #5 â Proving Damages
Despite Consultantâs best efforts and diligence, Consultant is sued by Client, who
alleges that failure to identify contamination on a piece of property has resulted in
significant monetary damage to the Client. Client claims that had it known of
contamination that Consultantâs investigation should have identified, it could have
avoided buying the property, negotiated a lower purchase price, asked the seller to
conduct remediation, or various other actions that it could not take.
Consultant, backed into a corner, says âprove it.â
Is Consultant successful?
35. Hypothetical #5 â Discussion
Is Consultant successful?
Answer: Maybe â it depends entirely on the facts. But hereâs what to look for:
In Chartis v. Aqua Services Engineers, Inc., 2014 WL 2730442 (N.D. Cal. June 16,
2014), Loweâs Companies hired consultant Aqua Sciences Engineers (ASE) to perform
Phase I services, and subsequent Phase II testing, for a prospective store site. After the
purchase closed (for $26 million), Loweâs discovered significant contamination on the
property, resulting in cleanup costs of $1,050,103. Chartis, Loweâs insurer, paid the
cleanup costs and then sued ASE as Loweâs subrogee.
AES argued to the jury that Chartis had no evidence that Loweâs would not have
consummated the transaction even if it had known about the contamination and no
evidence that Loweâs would have paid any less for the property had it known. In short,
there was no evidence that Loweâs would have done anything differently.
36. Hypothetical #5 â Discussion
Held: Loweâs failed to prove it suffered any damages as a result of ârelyingâ on the ASE
report.
While witnesses for Loweâs testified that they âreliedâ on the ASE report, none of them
were able to explain what the course of that reliance was. While Loweâs testified that it
waited for the Phase I report to close on the property, there was no testimony that about
what Loweâs would have done if it had known the report was inaccurate. Loweâs
representatives admitted they were not necessarily surprised to find out the property
was contaminated. Loweâs also admitted that in the overall scope of the project ($26
million), $1 million for remediation costs was not something Loweâs considered
significant. There was no testimony that Loweâs would not have purchased the property,
tried to negotiate a lower purchase price (and that such an agreement would have been
possible), or even that Loweâs would have extended its due diligence period to conduct
further investigation.
37. Final Thoughts
1. Under ASTM, there are only two possible conclusions to a
Phase I: Either there are no Recognized Environmental
Conditions, OR, there are no Recognized Environmental
Conditions except for ___________.
2. Stick to rendering an opinion on whether there are RECs,
HRECs, CRECs or de minimis conditions. Do not use non-
ASTM-language such as âenvironmental concernsâ or
âenvironmental issues.â
3. Do not caveat or modify statements regarding RECs such
as âthere are no Recognized Environmental Conditions that
would have a negative impact on the property.â
38. Final Thoughts
4. Do not use âweaselâ language such as âthere does not appear
to be any clear evidence of recognized environmental
conditions.â
5. Where possible, avoid giving non-ASTM opinions such as âwe
believe the property is suitable for commercial development.â
6. Donât assume T&C for a Phase I carries over to the Phase II.
7. Think twice before issuing a reliance letter to pick up a few
extra bucks, and if you do, include the original terms and
conditions (or include new ones) to limit your liability in the
same way as the original contract.