Kirsty Gowans from the Australian Renewable Energy Agency discussed ARENA's Regional Australia's Renewables initiative and lessons learned from projects. The RAR program from 2013-2015 provided grant funding for off-grid and remote renewable energy projects aimed at displacing diesel. However, most projects experienced delays of 10-12 months on average. Lessons included underestimating costs for remote projects and difficulties with stakeholder engagement. Data monitoring was also undervalued but important for evaluating performance and costs. ARENA resources are available to share knowledge from the portfolio of off-grid renewable projects.