SlideShare a Scribd company logo
PROJECT PORTFOLIO MANAGEMENT
PRESENTATION TO KENYA-PMP
By: Lawi Sultan Njeremani
CONTENT:
• Why PPM- What is PPM
• The PPM Pyramid
• Operating in the Value Zone
• Defining the Value Zone
• PPM & Resource Management
• 5-Steps to successful PPM
• Benefits & Challenges of PPM
• Why PPM
•Align resources with
business objectives
(Strategy)
•Build strong Governance
structure
•Ensure proper executive &
business support of projects
•Maximize investments
•Reduce No. of redundant
projects
•Make it easier to cancel
projects
•Set expectations
•Develop Plans and
Budgets
The PPM Pyramid
RulesPower
Culture
Goals
Operating in the Value Zone
The Zone
Portfolio
Management
Project
Management
Organizational
Infrastructure
& Culture
Defining the Value Zone
• Alignment – Do the projects
contribute to the strategic
goals of the company?
 Innovation – are we
receptive to and do we
invest in something New?
 Fit – is this project doable
with the resources we
have now?
Fit
 Value – is the value received
worth the effort?
Value
Zone
PPM Pyramid and the Language of
Resource Management
• The Role of Executive
Management is to Allocate
the money and the people
• The Role of Functional
Management is to Manage
the money and the people
• The Role of Project
Management is to spend
the money and support the
people
PMs and Project Teams
Functional
Management
Executive
Mgmt
5-Steps to Successful Project Portfolio
Management
1. Gather a detailed inventory of
all projects
Some companies using PPM, begin
with taking a complete inventory of
current requested projects.
Other companies benefit from
starting from scratch with the
process and require that all projects
be re-requested and re-assessed
through PPM.
5-Steps to Successful Project Portfolio
Management
2. Set strategic objectives for the company
+ One 3 hour meeting with all company HoDs & CEO
+ Operating Plan structure is set at 3 levels
Objectives (Why?)
Initiatives (What?)
Projects (How?)
+ Objectives are brainstormed and decided upon in this
meeting with all attendees prepared with 3-5
recommended objectives.
+ Discussion serves as kick-off to next year and a
chance to openly, informally discuss company strategies
and challenges.
5-Steps to Successful Project Portfolio
Management
2. Set strategic objectives for the company… Continued
+HoD’s brainstorm initiatives in support of the objectives with direct reports
(Supervisors and Team Leaders) within their department.
+Another 3 hour meeting is held with all HoD's and direct reports to review all
recommended initiatives by department. Initiatives are discussed and agreed
upon in this meeting.
+A good amount of cleanup is required on this list after the meeting (deleting
duplicates, merging similar initiatives, etc.
+Finalized list is distributed to all HoD's and direct reports.
+Involvement of direct reports at this level serves the purpose of generating
early buy-in to the Operating Plan process by senior management.
5-Steps to Successful Project Portfolio
Management
3. Align projects with objectives
1. HoD’s and their direct reports are responsible for recommending projects that will
support each initiative in alignment with the company objectives.
2. Only HoD approved projects are entered into the system, cutting down drastically
on frivolous project requests.
3. Each project entry requires a high level justification including project
description, business benefits, executive sponsor, business manager, estimated
quarter of completion, etc.
4. The projects are then assigned owners and estimate costs are established
5. All proposed projects are then reviewed in individual departmental meetings
chaired by the CEO together with Head of Finance with attendees being the
department VP and their direct reports.
6. Department VP’s and direct reports are given this opportunity to introduce the
project and “sell” it to the chairs for approval.
5- Steps to Successful Project Portfolio
Management
4. Score and categorize projects & Budget
During the project review meetings, each project is assessed based on
strength of support for initiative/objective, estimated business benefits, and
estimated costs.
As a closing to the discussion on each project, the project is assigned a status
and an action level.
The action level is assigned first and drives the status and next steps, as
outlined below:
Action Level: Status: Next Steps:
1. Start Project Accepted Begin projects in order of priority
2. Start after validation* Proposed Begin validation process
3. More research needed Proposed Continue research and propose again
4. Unlikely to start this year Proposed Hold (candidate for Q4 if resources allow)
5. Do not start this year Deferred Hold for next year and propose again
5- Steps to Successful Project Portfolio
Management
4. Score and categorize projects & Budget……continued
+After all projects are reviewed and scored, the HoD’s are tasked with
prioritizing all action level 1 and 2 projects for their department. The priorities
are simply high, medium and low.
+The Operating Plan is then handed over to the respective Head of Portfolio
to schedule all action level 1 and 2 projects that require Portfolio support into
the four quarters of the year with estimated start and complete quarters. This
scheduling is based on priority and action level with the high priority, action
level 1 projects at the top. Resource leveling is done at this time.
+This schedule is the first draft of the respective plan for the coming year. It is
then tweaked as needed when looked at on paper for anomalies, special
considerations, etc. This schedule will also become the basis for the
respective Portoflio budget.
5- Steps to Successful Project Portfolio
Management
5. Actively manage portfolio
Monthly Steering Committee (Executive Committee) chaired by CEO.
Members of committee include CEO, CFO and Head of Investment. All other
HoD’s attend as needed based on agenda of items to be discussed.
Purpose of committee:
Business owners and HoD’s present projects requiring validation before approval.
Steering Committee approves or denies these projects.
Monthly status given on large-scale, strategic projects from the Operating Plan.
Provides forum for strategic spending decisions and updates on critical system
issues/concerns.
Provides forum for reprioritizing projects based on mid-year changes in company
priorities/strategies.
5- Steps to Successful Project Portfolio
Management
5. Actively manage portfolio… continued
Quarterly review of entire Operating Plan at standing Executive Committee
meetings. All HoD’s are required to give status of initiatives and projects
quarterly.
Quarterly review by CEO of high-level Operating Plan at Board of Directors
Meetings.
“Portfolio Management without governance is an empty concept”
PPM PROCESS SUMMARY
BENEFITS OF PPM
1. Justifies “Killing” projects that don’t support Company strategy
2. Balances Risk across projects
3. Prioritizes project proposals across a common criteria rather than emotions
or politics
4. Allocates resources to projects that align with strategic direction
5. Improves Communication and supports agreement on project goals
6. Builds discipline into project selection process
7. Provides Executive oversight of Company
8. Provides the structure/process for project portfolio Governance and avoids
waste/duplication
CHALLENGES OF PPM
Team: Many executives are initially uncomfortable having their decisions
scrutinized. It requires real teamwork at the executive level to support portfolio
management and governance. Executive buy-in is absolutely required up front.
Complexity: The desire to overcomplicate this process with complex scoring
and red tape is overwhelming. Keep it simple at first then improve upon the
process as participants become familiar with the steps.
Software: Do not rely on project portfolio management tools to manage this
process for you. No one tool does everything and many tools complicate the
process. Sage wrote their own tool in an attempt to keep it simple.
Time: This requires an additional time commitment from Executives above and
beyond their usual constraints. Coming to meetings prepared is the key to
keeping this process time sensitive.
THANK YOU FOR YOUR PATIENCE
VELOCITY
Project Management
http://www.velocityprojectmanagement.com/

More Related Content

What's hot

Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
SM Parvej Islam
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmo
Erin Jones
 
ePMO & Enterprise Implementations
ePMO & Enterprise ImplementationsePMO & Enterprise Implementations
ePMO & Enterprise Implementations
Plexlane+
 
Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2
Becky Flint
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
Think For A Change
 
APM Body of Knowledge Refresh Guide
APM Body of Knowledge Refresh GuideAPM Body of Knowledge Refresh Guide
APM Body of Knowledge Refresh Guide
APMProjectManagement
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
Anand Subramaniam
 
Project initiation topic 2.5_project organization structure
Project initiation topic 2.5_project organization structureProject initiation topic 2.5_project organization structure
Project initiation topic 2.5_project organization structure
RudreshSamant
 
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
Dcolearning
 
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre..."Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
SN Panigrahi, PMP
 
Project Management: Importance in Detail
Project Management: Importance in DetailProject Management: Importance in Detail
Project Management: Importance in Detail
NIILM University Online
 
Creating a colaborative program governance
Creating a colaborative program governanceCreating a colaborative program governance
Creating a colaborative program governance
Alan Bueno, PMP, Prince2, ITIL
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Fida Karim 🇵🇰
 
4 Phases of Project Management Cycle
4 Phases of Project Management Cycle4 Phases of Project Management Cycle
4 Phases of Project Management Cycle
Multisoft Virtual Academy
 
PMO - Delivering Business Results
PMO - Delivering Business ResultsPMO - Delivering Business Results
PMO - Delivering Business Results
Daniels College of Business
 
Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508
Maria Cristina Co, MBA
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
ejlp12
 
Portfolios, Programs, Projects and the Enterprise PMO
Portfolios, Programs, Projects and the Enterprise PMOPortfolios, Programs, Projects and the Enterprise PMO
Portfolios, Programs, Projects and the Enterprise PMO
Shea Heaver
 
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENTPROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 

What's hot (20)

Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmo
 
ePMO & Enterprise Implementations
ePMO & Enterprise ImplementationsePMO & Enterprise Implementations
ePMO & Enterprise Implementations
 
Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
APM Body of Knowledge Refresh Guide
APM Body of Knowledge Refresh GuideAPM Body of Knowledge Refresh Guide
APM Body of Knowledge Refresh Guide
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Project initiation topic 2.5_project organization structure
Project initiation topic 2.5_project organization structureProject initiation topic 2.5_project organization structure
Project initiation topic 2.5_project organization structure
 
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
 
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre..."Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
 
Project Management: Importance in Detail
Project Management: Importance in DetailProject Management: Importance in Detail
Project Management: Importance in Detail
 
Creating a colaborative program governance
Creating a colaborative program governanceCreating a colaborative program governance
Creating a colaborative program governance
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 
4 Phases of Project Management Cycle
4 Phases of Project Management Cycle4 Phases of Project Management Cycle
4 Phases of Project Management Cycle
 
PMO - Delivering Business Results
PMO - Delivering Business ResultsPMO - Delivering Business Results
PMO - Delivering Business Results
 
Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Portfolios, Programs, Projects and the Enterprise PMO
Portfolios, Programs, Projects and the Enterprise PMOPortfolios, Programs, Projects and the Enterprise PMO
Portfolios, Programs, Projects and the Enterprise PMO
 
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENTPROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 

Viewers also liked

@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
Daniel Brody
 
Kanban for Portfolio Management
Kanban for Portfolio ManagementKanban for Portfolio Management
Kanban for Portfolio Management
Gaetano Mazzanti
 
90 Day Action Plan for Property Management
90 Day Action Plan for Property Management 90 Day Action Plan for Property Management
90 Day Action Plan for Property Management
RPJ Housing
 
The Agile Stakeholder Management Framework for Teams, Programs, and Portfolios
The Agile Stakeholder Management Framework for Teams, Programs, and PortfoliosThe Agile Stakeholder Management Framework for Teams, Programs, and Portfolios
The Agile Stakeholder Management Framework for Teams, Programs, and Portfolios
Drew Jemilo
 
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service StrategyIT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
NUS-ISS
 
The Project Management Process - Week 2
The Project Management Process - Week 2The Project Management Process - Week 2
The Project Management Process - Week 2
Craig Brown
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio Management
Anand Subramaniam
 

Viewers also liked (7)

@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Kanban for Portfolio Management
Kanban for Portfolio ManagementKanban for Portfolio Management
Kanban for Portfolio Management
 
90 Day Action Plan for Property Management
90 Day Action Plan for Property Management 90 Day Action Plan for Property Management
90 Day Action Plan for Property Management
 
The Agile Stakeholder Management Framework for Teams, Programs, and Portfolios
The Agile Stakeholder Management Framework for Teams, Programs, and PortfoliosThe Agile Stakeholder Management Framework for Teams, Programs, and Portfolios
The Agile Stakeholder Management Framework for Teams, Programs, and Portfolios
 
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service StrategyIT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
 
The Project Management Process - Week 2
The Project Management Process - Week 2The Project Management Process - Week 2
The Project Management Process - Week 2
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio Management
 

Similar to Kenya PMP presentation on Project Portfolio Management

PMI Global Congress 2005: Portfolio and Program Management implementation in ...
PMI Global Congress 2005: Portfolio and Program Management implementation in ...PMI Global Congress 2005: Portfolio and Program Management implementation in ...
PMI Global Congress 2005: Portfolio and Program Management implementation in ...
Thomas Walenta, PMI Fellow
 
PMO's and the CxO webinar, 6 June 2023
PMO's and the CxO webinar, 6 June 2023PMO's and the CxO webinar, 6 June 2023
PMO's and the CxO webinar, 6 June 2023
Association for Project Management
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMO
Anthony Natoli
 
Archibald Slides Interfaces Keynote Dynamics2010
Archibald Slides Interfaces Keynote Dynamics2010Archibald Slides Interfaces Keynote Dynamics2010
Archibald Slides Interfaces Keynote Dynamics2010
Russell Archibald
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
Chetan Khanzode
 
Table of ContentsEXECUTIVE SUMMARY3The mission of.docx
Table of ContentsEXECUTIVE SUMMARY3The mission of.docxTable of ContentsEXECUTIVE SUMMARY3The mission of.docx
Table of ContentsEXECUTIVE SUMMARY3The mission of.docx
deanmtaylor1545
 
ASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptxASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptx
Ashraf206702
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO Capabilities
Erin Jones
 
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
irrosennen
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
Knowledge Train
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
PM Majik
 
Planning And Project Management
Planning And Project ManagementPlanning And Project Management
Planning And Project Management
ST. JAMES COLLEGE
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
Ahmed Rami Elsherif, PMP, ITBMC
 
Week 5 foundation of planning - 05 02 2012
Week 5   foundation of planning - 05 02 2012Week 5   foundation of planning - 05 02 2012
Week 5 foundation of planning - 05 02 2012
Ezzy Izzuddin
 
Matinée PMI - Why so many technology projects failing
Matinée PMI - Why so many technology projects failingMatinée PMI - Why so many technology projects failing
Matinée PMI - Why so many technology projects failing
PMI-Montréal
 
PMO for Supply Chain - Setting Up a Project Mangement Office for Non-IT
PMO for Supply Chain - Setting Up a Project Mangement Office for Non-ITPMO for Supply Chain - Setting Up a Project Mangement Office for Non-IT
PMO for Supply Chain - Setting Up a Project Mangement Office for Non-IT
Chief Innovation
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio management
Juha-Matti Saario
 
PMO OBjectives - a quick guide
PMO OBjectives - a quick guidePMO OBjectives - a quick guide
PMO OBjectives - a quick guide
PM Majik
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposal
Hugh Shults
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
HamzaMessaoudi10
 

Similar to Kenya PMP presentation on Project Portfolio Management (20)

PMI Global Congress 2005: Portfolio and Program Management implementation in ...
PMI Global Congress 2005: Portfolio and Program Management implementation in ...PMI Global Congress 2005: Portfolio and Program Management implementation in ...
PMI Global Congress 2005: Portfolio and Program Management implementation in ...
 
PMO's and the CxO webinar, 6 June 2023
PMO's and the CxO webinar, 6 June 2023PMO's and the CxO webinar, 6 June 2023
PMO's and the CxO webinar, 6 June 2023
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMO
 
Archibald Slides Interfaces Keynote Dynamics2010
Archibald Slides Interfaces Keynote Dynamics2010Archibald Slides Interfaces Keynote Dynamics2010
Archibald Slides Interfaces Keynote Dynamics2010
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Table of ContentsEXECUTIVE SUMMARY3The mission of.docx
Table of ContentsEXECUTIVE SUMMARY3The mission of.docxTable of ContentsEXECUTIVE SUMMARY3The mission of.docx
Table of ContentsEXECUTIVE SUMMARY3The mission of.docx
 
ASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptxASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptx
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO Capabilities
 
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Planning And Project Management
Planning And Project ManagementPlanning And Project Management
Planning And Project Management
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 
Week 5 foundation of planning - 05 02 2012
Week 5   foundation of planning - 05 02 2012Week 5   foundation of planning - 05 02 2012
Week 5 foundation of planning - 05 02 2012
 
Matinée PMI - Why so many technology projects failing
Matinée PMI - Why so many technology projects failingMatinée PMI - Why so many technology projects failing
Matinée PMI - Why so many technology projects failing
 
PMO for Supply Chain - Setting Up a Project Mangement Office for Non-IT
PMO for Supply Chain - Setting Up a Project Mangement Office for Non-ITPMO for Supply Chain - Setting Up a Project Mangement Office for Non-IT
PMO for Supply Chain - Setting Up a Project Mangement Office for Non-IT
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio management
 
PMO OBjectives - a quick guide
PMO OBjectives - a quick guidePMO OBjectives - a quick guide
PMO OBjectives - a quick guide
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposal
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
 

More from Lawi Njeremani

SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...
SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...
SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...
Lawi Njeremani
 
Dca souvenir magazine
Dca souvenir magazineDca souvenir magazine
Dca souvenir magazine
Lawi Njeremani
 
9 10drr bulletin march april 08
9 10drr bulletin march april 089 10drr bulletin march april 08
9 10drr bulletin march april 08
Lawi Njeremani
 
8drr bulletin feb 08
8drr bulletin feb 088drr bulletin feb 08
8drr bulletin feb 08
Lawi Njeremani
 
7drr january 08
7drr january 087drr january 08
7drr january 08
Lawi Njeremani
 
6december 07 bulletin
6december 07 bulletin6december 07 bulletin
6december 07 bulletin
Lawi Njeremani
 
5district bulletin november
5district bulletin november5district bulletin november
5district bulletin november
Lawi Njeremani
 
4drr bulletin oct 07
4drr bulletin oct 074drr bulletin oct 07
4drr bulletin oct 07
Lawi Njeremani
 
3drr sept 07 bulletin
3drr sept 07 bulletin3drr sept 07 bulletin
3drr sept 07 bulletin
Lawi Njeremani
 
2drr august 07 bulletin
2drr august 07 bulletin2drr august 07 bulletin
2drr august 07 bulletin
Lawi Njeremani
 
1 drr july_07_bulletin
1 drr july_07_bulletin1 drr july_07_bulletin
1 drr july_07_bulletin
Lawi Njeremani
 
How many trees do i need to plant annually
How many trees do i need to plant annuallyHow many trees do i need to plant annually
How many trees do i need to plant annually
Lawi Njeremani
 

More from Lawi Njeremani (12)

SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...
SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...
SURVEY REPORT ON FACTORS AFFECTING THE EFFECTIVENESS OF YOUTH AND YOUNG PROFE...
 
Dca souvenir magazine
Dca souvenir magazineDca souvenir magazine
Dca souvenir magazine
 
9 10drr bulletin march april 08
9 10drr bulletin march april 089 10drr bulletin march april 08
9 10drr bulletin march april 08
 
8drr bulletin feb 08
8drr bulletin feb 088drr bulletin feb 08
8drr bulletin feb 08
 
7drr january 08
7drr january 087drr january 08
7drr january 08
 
6december 07 bulletin
6december 07 bulletin6december 07 bulletin
6december 07 bulletin
 
5district bulletin november
5district bulletin november5district bulletin november
5district bulletin november
 
4drr bulletin oct 07
4drr bulletin oct 074drr bulletin oct 07
4drr bulletin oct 07
 
3drr sept 07 bulletin
3drr sept 07 bulletin3drr sept 07 bulletin
3drr sept 07 bulletin
 
2drr august 07 bulletin
2drr august 07 bulletin2drr august 07 bulletin
2drr august 07 bulletin
 
1 drr july_07_bulletin
1 drr july_07_bulletin1 drr july_07_bulletin
1 drr july_07_bulletin
 
How many trees do i need to plant annually
How many trees do i need to plant annuallyHow many trees do i need to plant annually
How many trees do i need to plant annually
 

Recently uploaded

Easy Earnings Through Refer and Earn Apps Without KYC.pptx
Easy Earnings Through Refer and Earn Apps Without KYC.pptxEasy Earnings Through Refer and Earn Apps Without KYC.pptx
Easy Earnings Through Refer and Earn Apps Without KYC.pptx
Fx Lotus
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
pavelborek
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Stainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers ChennaiStainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers Chennai
ConveyorSystem
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
dpbossdpboss69
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
Helen Meek
 
TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024
Adnet Communications
 
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) PrincipleMECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
Operational Excellence Consulting
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
eaqmokn
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
PennapaKeavsiri
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani case
 
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian MatkaDpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
Eternity Paralegal Services
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
advik4387
 

Recently uploaded (20)

Easy Earnings Through Refer and Earn Apps Without KYC.pptx
Easy Earnings Through Refer and Earn Apps Without KYC.pptxEasy Earnings Through Refer and Earn Apps Without KYC.pptx
Easy Earnings Through Refer and Earn Apps Without KYC.pptx
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Stainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers ChennaiStainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers Chennai
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
 
TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024
 
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) PrincipleMECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
IMG_20240615_091110.pdf dpboss guessing
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
 
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian MatkaDpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
 

Kenya PMP presentation on Project Portfolio Management

  • 1. PROJECT PORTFOLIO MANAGEMENT PRESENTATION TO KENYA-PMP By: Lawi Sultan Njeremani
  • 2. CONTENT: • Why PPM- What is PPM • The PPM Pyramid • Operating in the Value Zone • Defining the Value Zone • PPM & Resource Management • 5-Steps to successful PPM • Benefits & Challenges of PPM
  • 3. • Why PPM •Align resources with business objectives (Strategy) •Build strong Governance structure •Ensure proper executive & business support of projects •Maximize investments •Reduce No. of redundant projects •Make it easier to cancel projects •Set expectations •Develop Plans and Budgets
  • 5. Operating in the Value Zone The Zone Portfolio Management Project Management Organizational Infrastructure & Culture
  • 6. Defining the Value Zone • Alignment – Do the projects contribute to the strategic goals of the company?  Innovation – are we receptive to and do we invest in something New?  Fit – is this project doable with the resources we have now? Fit  Value – is the value received worth the effort? Value Zone
  • 7. PPM Pyramid and the Language of Resource Management • The Role of Executive Management is to Allocate the money and the people • The Role of Functional Management is to Manage the money and the people • The Role of Project Management is to spend the money and support the people PMs and Project Teams Functional Management Executive Mgmt
  • 8. 5-Steps to Successful Project Portfolio Management 1. Gather a detailed inventory of all projects Some companies using PPM, begin with taking a complete inventory of current requested projects. Other companies benefit from starting from scratch with the process and require that all projects be re-requested and re-assessed through PPM.
  • 9. 5-Steps to Successful Project Portfolio Management 2. Set strategic objectives for the company + One 3 hour meeting with all company HoDs & CEO + Operating Plan structure is set at 3 levels Objectives (Why?) Initiatives (What?) Projects (How?) + Objectives are brainstormed and decided upon in this meeting with all attendees prepared with 3-5 recommended objectives. + Discussion serves as kick-off to next year and a chance to openly, informally discuss company strategies and challenges.
  • 10. 5-Steps to Successful Project Portfolio Management 2. Set strategic objectives for the company… Continued +HoD’s brainstorm initiatives in support of the objectives with direct reports (Supervisors and Team Leaders) within their department. +Another 3 hour meeting is held with all HoD's and direct reports to review all recommended initiatives by department. Initiatives are discussed and agreed upon in this meeting. +A good amount of cleanup is required on this list after the meeting (deleting duplicates, merging similar initiatives, etc. +Finalized list is distributed to all HoD's and direct reports. +Involvement of direct reports at this level serves the purpose of generating early buy-in to the Operating Plan process by senior management.
  • 11. 5-Steps to Successful Project Portfolio Management 3. Align projects with objectives 1. HoD’s and their direct reports are responsible for recommending projects that will support each initiative in alignment with the company objectives. 2. Only HoD approved projects are entered into the system, cutting down drastically on frivolous project requests. 3. Each project entry requires a high level justification including project description, business benefits, executive sponsor, business manager, estimated quarter of completion, etc. 4. The projects are then assigned owners and estimate costs are established 5. All proposed projects are then reviewed in individual departmental meetings chaired by the CEO together with Head of Finance with attendees being the department VP and their direct reports. 6. Department VP’s and direct reports are given this opportunity to introduce the project and “sell” it to the chairs for approval.
  • 12. 5- Steps to Successful Project Portfolio Management 4. Score and categorize projects & Budget During the project review meetings, each project is assessed based on strength of support for initiative/objective, estimated business benefits, and estimated costs. As a closing to the discussion on each project, the project is assigned a status and an action level. The action level is assigned first and drives the status and next steps, as outlined below: Action Level: Status: Next Steps: 1. Start Project Accepted Begin projects in order of priority 2. Start after validation* Proposed Begin validation process 3. More research needed Proposed Continue research and propose again 4. Unlikely to start this year Proposed Hold (candidate for Q4 if resources allow) 5. Do not start this year Deferred Hold for next year and propose again
  • 13. 5- Steps to Successful Project Portfolio Management 4. Score and categorize projects & Budget……continued +After all projects are reviewed and scored, the HoD’s are tasked with prioritizing all action level 1 and 2 projects for their department. The priorities are simply high, medium and low. +The Operating Plan is then handed over to the respective Head of Portfolio to schedule all action level 1 and 2 projects that require Portfolio support into the four quarters of the year with estimated start and complete quarters. This scheduling is based on priority and action level with the high priority, action level 1 projects at the top. Resource leveling is done at this time. +This schedule is the first draft of the respective plan for the coming year. It is then tweaked as needed when looked at on paper for anomalies, special considerations, etc. This schedule will also become the basis for the respective Portoflio budget.
  • 14. 5- Steps to Successful Project Portfolio Management 5. Actively manage portfolio Monthly Steering Committee (Executive Committee) chaired by CEO. Members of committee include CEO, CFO and Head of Investment. All other HoD’s attend as needed based on agenda of items to be discussed. Purpose of committee: Business owners and HoD’s present projects requiring validation before approval. Steering Committee approves or denies these projects. Monthly status given on large-scale, strategic projects from the Operating Plan. Provides forum for strategic spending decisions and updates on critical system issues/concerns. Provides forum for reprioritizing projects based on mid-year changes in company priorities/strategies.
  • 15. 5- Steps to Successful Project Portfolio Management 5. Actively manage portfolio… continued Quarterly review of entire Operating Plan at standing Executive Committee meetings. All HoD’s are required to give status of initiatives and projects quarterly. Quarterly review by CEO of high-level Operating Plan at Board of Directors Meetings. “Portfolio Management without governance is an empty concept”
  • 17. BENEFITS OF PPM 1. Justifies “Killing” projects that don’t support Company strategy 2. Balances Risk across projects 3. Prioritizes project proposals across a common criteria rather than emotions or politics 4. Allocates resources to projects that align with strategic direction 5. Improves Communication and supports agreement on project goals 6. Builds discipline into project selection process 7. Provides Executive oversight of Company 8. Provides the structure/process for project portfolio Governance and avoids waste/duplication
  • 18. CHALLENGES OF PPM Team: Many executives are initially uncomfortable having their decisions scrutinized. It requires real teamwork at the executive level to support portfolio management and governance. Executive buy-in is absolutely required up front. Complexity: The desire to overcomplicate this process with complex scoring and red tape is overwhelming. Keep it simple at first then improve upon the process as participants become familiar with the steps. Software: Do not rely on project portfolio management tools to manage this process for you. No one tool does everything and many tools complicate the process. Sage wrote their own tool in an attempt to keep it simple. Time: This requires an additional time commitment from Executives above and beyond their usual constraints. Coming to meetings prepared is the key to keeping this process time sensitive.
  • 19. THANK YOU FOR YOUR PATIENCE VELOCITY Project Management http://www.velocityprojectmanagement.com/