cKenney’s replaced the cooling
system in the data hub of a
state-of-the-art fully operational
football stadium in Atlanta, Georgia.
THE CHALLENGE
McKenney’s was commissioned to add a
­cooling system with redundancy in the data
hub of the massive, technology-advanced sta-
dium. The hub features most of the controls
for thousands of video boards, digital signs,
wireless access points and other connected
options, and is considered the “brains” for
the entire complex. The work in the data hub
had to be completed quickly, efficiently and
without interrupting service or events.
THE SOLUTION
With limited time available at the stadium,
the McKenney’s team mapped out a coordi­
nation schedule—including pre-planning,
walk-downs of cooling options, backups
and trial runs—to ensure seamless execution
during installation and new equipment testing.
THE RESULTS
The McKenney’s team completed the work
on time, under budget and with no disruption
to stadium operations. Now, the stadium has
redundant cooling capabilities in its main data
hub−contributing to the high guest satisfac-
tion rating at the stadium.
Keeping the Fans Waving
PROJECT NAME
žž State-0f-the-Art Stadium
Data Hub
PROJECT LOCATION
žž Atlanta, Georgia
PROJECT TEAM
žž General Contractor:
HHRM Joint Venture
žž Subcontractor:
McKenney’s, Inc.
SPECIALIZATIONS
	 Sheet Metal Shop Prefab
MARKETS
žž Mission Critical
žž Entertainment & Media
žž Public Assembly &
Places of Worship
The content of this document is not intended as an endorsement.
www.mckenneys.com
© 2018 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.
McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.
404-622-5000
info@mckenneys.com
1056 Moreland Industrial Boulevard
Atlanta, Georgia 30316
704-357-1200
info@mckenneys.com
3601 Performance Road
Charlotte, North Carolina 28214

Keeping the Fans Waving - Cooling Systems Replacement

  • 1.
    M cKenney’s replaced thecooling system in the data hub of a state-of-the-art fully operational football stadium in Atlanta, Georgia. THE CHALLENGE McKenney’s was commissioned to add a ­cooling system with redundancy in the data hub of the massive, technology-advanced sta- dium. The hub features most of the controls for thousands of video boards, digital signs, wireless access points and other connected options, and is considered the “brains” for the entire complex. The work in the data hub had to be completed quickly, efficiently and without interrupting service or events. THE SOLUTION With limited time available at the stadium, the McKenney’s team mapped out a coordi­ nation schedule—including pre-planning, walk-downs of cooling options, backups and trial runs—to ensure seamless execution during installation and new equipment testing. THE RESULTS The McKenney’s team completed the work on time, under budget and with no disruption to stadium operations. Now, the stadium has redundant cooling capabilities in its main data hub−contributing to the high guest satisfac- tion rating at the stadium. Keeping the Fans Waving PROJECT NAME žž State-0f-the-Art Stadium Data Hub PROJECT LOCATION žž Atlanta, Georgia PROJECT TEAM žž General Contractor: HHRM Joint Venture žž Subcontractor: McKenney’s, Inc. SPECIALIZATIONS Sheet Metal Shop Prefab MARKETS žž Mission Critical žž Entertainment & Media žž Public Assembly & Places of Worship The content of this document is not intended as an endorsement. www.mckenneys.com © 2018 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A. McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners. 404-622-5000 info@mckenneys.com 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316 704-357-1200 info@mckenneys.com 3601 Performance Road Charlotte, North Carolina 28214