$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
July 29-1130-Kris Reynolds
1. Right Practice, Right Place
Increasing the Nutrient Reduction Potential of
Conservation Activities in the Upper Macoupin Creek
Watershed
Emily Bruner1
Kris Reynolds1
Jeff Boeckler2
1 American Farmland Trust
2 Northwater Consulting
3. SWAMM
Custom and spatially explicit GIS based nonpoint
source model (surface runoff)
Shares characteristics with other models such as
SWAT and pLoad except:
• Can evaluate loading at the field level
• Can evaluate the exact placement of treatment practices
• Can be visualized in map format
It is relatively simple, relying on good input data for
accurate outputs rather than complicated equations
Easy to perform needed analysis
• Load allocation and load reductions
4.
5. All fields are not created equal
Model Characteristics
• Soils
• Climate
• Landuse
• Tillage etc
• Delivery
• Management
Practices
10. Current Management (Structural)
Terraces (42)
25 to 60% P reduction (SWAMM)
30 to 65% Sediment reduction (SWAMM)
WASCOBs (1,138)
10 to 60% P reduction (SWAMM)
15 to 65% Sediment reduction (SWAMM)
11. Individual fields ranked
according to annual
P load (lb/acre):
• 1) Not a priority: < 1
• 2) Low: 1 – 2
• 3) Medium 2 -5
• 4) High >5
Defining Critical Areas
12. Critical Areas by Practice
Priority Areas for Reduced Tillage
Upper Macoupin Creek
µ
0 2 4 6 81
Miles
Priority Level
Medium
High
Practice
P Load
Reduction
in lbs (%)
Total
Available
Acres (Fields)
Switch from
Conventional to
Conservation
Tillage 5,756 (5) 3,462 (173)
Lower P
Application
Rate 3,487 (3) 11,272 (746)
13. Critical Areas by Practice
Practice
P Load
Reduction
in lbs (%)
Total
Available
Acres (Fields)
Cover Crops on
Current Mulch,
No, Reduced
and Strip Till
Acres 4,462 (4) 5,180 (361)
Priority Areas for Cover Crops
Upper Macoupin Creek
µ
0 2 4 6 81
Miles
Priority Level
Medium
High
15. Model based outreach
• NFWF grant received in 2019
• Provide Technical Assistance to farmers
and landowners
• Another set of boots on the ground
16. Outreach project goals
• More conservation adoption on critical
areas
• FA dollars from MRBI and RCPP programs
being spent in critical areas
• Right Practice, Right Place, Right
Investment
• Make local ranking questions work
17. Outreach plan
• Identify Farmers in critical areas
• Work with Ag retailers in the watershed
• Identify farmers with NRCS and SWCD
• Letters, direct calls, farm visits
• Provide farmers with info and resources
they need
18. Saving the Land that Sustains Us
www.farmland.org
Questions?
19. Coop Branch Load Reductions
Practice
P Load
Reduction
(lbs)
P Load
Reduction
(%)
Total
Available
Acres
Switch from
Conventional to
Conservation Tillage 1,796 5 979
Cover Crops on Current
Conventional, Mulch,
No, Reduced and Strip
Till Acres 1,302 4 1,582
Lower P Application
Rate 1,312 4 4,216
20. Spanish Needle Load Reductions
Practice
P Load
Reduction
(lbs)
P Load
Reduction
(%)
Total
Available
Acres
Switch from
Conventional to
Conservation Tillage 867 3 593
Cover Crops on Current
Conventional, Mulch,
No, Reduced and Strip
Till Acres 1,055 4 1,101
Lower P Application
Rate 701 2 2,208
21. Load Contribution by Source
Source P Load
(%)
N Load
(%)
Sediment
Load
(%)
Runoff 82 97 70
Streambank 9 2 15
Gully 9 1 15
Total (lbs) 143,242 1,471,866 144,544
25. Current Management
1
8
16
75
2
8
18
72
15 14
23
48
14 16
21
49
0
10
20
30
40
50
60
70
80
90
100
No till (%) Mulch Till (%) Reduced Till
(%)
Conventional
Till (%)
Percent of Corn Acres by Tillage Method for
UMC and Statewide
UMC 2017 UMC 2018 State 2017 State 2018
26. Load Reductions
Practice
P Load
Reduction
(lbs)
P Load
Reduction
(%)
Total
Available
Acres
Switch from
Conventional to
Conservation Tillage 14,430 12 18,141
Cover Crops on Current
Conventional, Mulch,
No, Reduced and Strip
Till Acres 29,372 25 75,750
Lower P Application
Rate 6,854 6 75,750
27. Coop Branch Load by Land Use
Landuse P
(lbs)
P
(lbs/ac)
N
(lbs)
N
(lbs/ac)
Sediment
(tons)
Sediment
(tons/ac)
Forest 761 0.11 6,812 1.02 128 0.02
Pasture 1,962 1.46 14,624 10.91 147 0.11
Rowcrops 31,841 1.44 381,751 17.27 34,849 1.58
Watershed 36,570 1.04 420,437 12.01 35,343 1.01
Rowcrops contribute 91% of P and N and 99% of Sediment Loads
Gully P (highest contribution of all sub-watersheds) = 4,098 lbs
Streambank P = 2,741 lbs
28. Coop Branch Load Reductions
Practice
P Load
Reduction
(lbs)
P Load
Reduction
(%)
Total
Available
Acres
Switch from
Conventional to
Conservation Tillage 4,987 14 6,041
Cover Crops on Current
Conventional, Mulch,
No, Reduced and Strip
Till Acres 9,389 27 21,132
Lower P Application
Rate 2,191 6 21,132
29. Spanish Needle Load by Land Use
Landuse P
(lbs)
P
(lbs/ac)
N
(lbs)
N
(lbs/ac)
Sediment
(tons)
Sediment
(tons/ac)
Forest 885 0.11 7,951 1.02 147 0.02
Pasture 1,180 1.39 8,636 10.18 84 0.10
Rowcrops 23,619 1.33 303,942 17.17 23,081 1.30
Watershed 28,425 0.87 342,330 10.46 23,642 0.72
Rowcrops contribute 72% of P, 89% of N and 98% of Sediment Loads
Gully P = 2,387 lbs
Streambank P (highest contribution of all sub-watersheds) 4,656 lbs
30. Spanish Needle Load Reductions
Practice
P Load
Reduction
(lbs)
P Load
Reduction
(%)
Total
Available
Acres
Switch from
Conventional to
Conservation Tillage 2,886 9 3,606
Cover Crops on Current
Conventional, Mulch,
No, Reduced and Strip
Till Acres 6,891 21 16,491
Lower P Application
Rate 1,608 5 16,491
KRIS—Introduce Emily and Jeff and their roles in the project
As I was putting this together, I attempted to generate slides that could be recycled for our SWCS presentation.
So think of this as our first draft of that presentation as well. We can use this slide deck as a template and begin to add/delete content as appropriate. Text in italics are notes pertaining to revisions for SWCS. Please keep notes for SWCS in italics for consistency and ease of revisions in the future.
For SWCS slides will need to enter 2 or 3 project background and location slides (some potential ones are at the end of this slide deck)
The UMC watershed has been identified as one of the top three non-point source P loading watersheds in Illinois. AFT is the lead partner in RCPP and MRBI for parts of the watershed. 2nd year of RCPP 4th year of MRBI.
Watershed Model will allow us to prioritize applications based on critical area. Outreach will also be based off of results from watershed model beginning with critical sub-watersheds and then field area prioritization.
Items in bold represent factors we can manipulate to generate different loading outcomes
Organisms would be influenced via management (crop rotation, tillage, chemical and fertilizer use, etc.)
Artificial drainage primarily being tile, but drainage water management and other structural manipulations (terraces, WASCOBs, wetlands, etc.) would apply here as well.
Watershed Area = (total acres in each landuse / total acres in watershed) * 100
P, N, and Sed Load (%) = (total load (lbs) from each landuse / total load (lbs) from entire watershed) * 100
***Remember this is just surface loading estimated via SWAMM, gully and streambank loading not included. ***
Watershed Area = (total acres in each landuse / total acres in watershed) * 100
P, N, and Sed Load (%) = (total load (lbs) from each landuse / total load (lbs) from entire watershed) * 100
***Remember this is just surface loading estimated via SWAMM, gully and streambank loading not included. ***
These numbers are from SWAMM and were generated via the windshield survey (conventional acreage is combined total of conventional and conventional high (17,255 + 886), wheat (organic)=38, reduced-till (organic)=51, cover crop strip (24) and mulch till (103) comprise less than 1% of cropped area acreage and are not included in any chart categories, but were included in total cropped acreage (80,675) estimates for calculating percentages
Wheat crop rotations (1446) are 2% of cropped acreage and hay (482) in the crop rotation is 1% of cropped acres.
What criteria did Jeff use to define terrace vs WASCOB? Are the N_eff, P_eff and Sed_effs just a straight percentage reduction (i.e. what is in the slide now)
Numbers in parentheses represent the current georeferenced point total for the entire watershed based off the windshield survey, (Existing_BMP.shp file)
Want to add numbers from lit review? Other definitions?
These classifications were chosen strictly via eyeballing the maps, i.e. no specific criteria was used.
May want to revisit classification scheme after we decide how we are defining critical areas.
From Jeff
Table represents TOTAL LOAD Estimates from Run2
Steering committee identified the need for more technical assistance. Farmers that weren’t in programs or interested in programs didn’t receive the same attention that farmers in the programs did.
The model is great, but we knew from the beginning that if we wanted to get anything out of it, we needed someone to use it on a consistent basis.
The NFWF grant allowed us to hire a Conservation Technician (Introduce Sarah) that could use the model to reach farmers that were farming cropland in the critical areas of the watershed.
Model tells us where cropland is but we needed to know who is farming.
2 Ag retail coops are part of the watershed project with customers in the watershed. We are working with them and their customers to provide program information and advice on conservation practices.
Spring 2018
Total available acres for scenario 1 (tillage conversion) = sum of conventional tillage and conventional tillage high acres
P Load reduction (lbs) = sum of total load for conventional and conventional high acres * .50
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Total available acres for scenario 2 (cover crop adoption) = sum of conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres
P Load reduction (lbs) = sum of total load for conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres * .30
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Watershed total = Coop Branch – 433,395 lbs (N), 43,491 lbs (P), 46,241 tons (sediment)
Add if reduce P Application levels from above maintenance levels (how many of rowcrop acreage to include in 7% reduction)? Use same number as Cover crops?
Total available acres for scenario 1 (tillage conversion) = sum of conventional tillage and conventional tillage high acres
P Load reduction (lbs) = sum of total load for conventional and conventional high acres * .50
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Total available acres for scenario 2 (cover crop adoption) = sum of conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres
P Load reduction (lbs) = sum of total load for conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres * .30
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Watershed total = Spanish Needle –355,536 lbs (N), 35,467 lbs (P), 36,140 tons (sediment)
Total loads from .shp files in Dropbox.
There is a discrepancy between runoff and gully load estimates provided by Jeff via Run2 Spreadsheet and estimates calculated from running statistics on various columns of attribute tables, specifically P, N and Sediment runoff values are higher (Run2) and gully P, N and sediment loads are lower (.shps). Streambank values are the same for Run2 spreadsheet and .shp calculations.
Image courtesy of Left: https://www.monotec.co.za/products/strip-till/
Right: https://www.striptillfarmer.com/articles/66-michigan-study-confirms-benefits-of-strip-till
Table modified from http://draindrop.cropsci.illinois.edu/wp-content/uploads/2016/10/IL-NLRS-Practice-Factsheet_2016.pdf
From : https://agbmps.osu.edu/bmp/saturated-buffer-nrcs-604
Data collected via SWCD during tillage transect survey. UMC results are watershed specific (a subset of individual county survey results).
Data collected via SWCD during tillage transect survey. UMC results are watershed specific (a subset of individual county survey results).
Total available acres for scenario 1 (tillage conversion) = sum of conventional tillage and conventional tillage high acres
P Load reduction (lbs) = sum of total load for conventional and conventional high acres * .50
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Total available acres for scenario 2 (cover crop adoption) = sum of conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres
P Load reduction (lbs) = sum of total load for conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres * .30
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Total available acres , switch tillage = 22% of cropped watershed acres
Total available acres, cover crops = 94% of cropped watershed acres
Numbers in table are from .shp calculations
Percent of watershed total (runoff contribution)
P = forest – 2 , pasture – 6 , rowcrop – 91
Sediment = forest – less than 1 , pasture – less than 1 , rowcrop – 99
N = forest – 2, pasture – 3, rowcrop – 91
Additional contribution from Gully and Streambank (these numbers from Jeff Run2)
Gully P (highest contribution of all subwatersheds) (4,098 lbs)
Streambank P ( 2,741 lbs)
Total available acres for scenario 1 (tillage conversion) = sum of conventional tillage and conventional tillage high acres
P Load reduction (lbs) = sum of total load for conventional and conventional high acres * .50
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Total available acres for scenario 2 (cover crop adoption) = sum of conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres
P Load reduction (lbs) = sum of total load for conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres * .30
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Watershed total = Coop Branch – 433,395 lbs (N), 43,491 lbs (P), 46,241 tons (sediment)
Add if reduce P Application levels from above maintenance levels (how many of rowcrop acreage to include in 7% reduction)? Use same number as Cover crops?
Percent of watershed total (runoff contribution)
P = forest – 3, pasture – 4, rowcrop – 72
Sediment = forest – 1, pasture – less than 1, rowcrop – 98
N = forest – 2, pasture – 3, rowcrop – 89
Additional contribution from Gully and Streambank (Run2 estimates)
Gully P = 2,387 lbs
Streambank P (highest contribution of all sub-watersheds) 4,656 lbs
Total available acres for scenario 1 (tillage conversion) = sum of conventional tillage and conventional tillage high acres
P Load reduction (lbs) = sum of total load for conventional and conventional high acres * .50
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Total available acres for scenario 2 (cover crop adoption) = sum of conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres
P Load reduction (lbs) = sum of total load for conventional till, conventional till high, mulch till, mulch till, reduced till, reduced till (organic), no till, and strip till acres * .30
Watershed total P load reduction (%) = P Load reduction (lbs) / total watershed P load (lbs) * 100
Watershed total = Spanish Needle –355,536 lbs (N), 35,467 lbs (P), 36,140 tons (sediment)
Example from Winter meeting
Will need to refine after we set critical area criteria. Will need to run specific load reduction scenarios from in field and edge of field practices once agree on how want to calculate stacked practices.
Example from Winter meeting
List of potential questions for critical area definition –
Area limit? Minimum of 5, 10, or 15 acres to set initial screen/filter in SWAMM?
lots of teeny polygons, how to define “fields”?
P load criteria?
Sediment load criteria?
Need to be HEL?
Distance to stream? Use this to weight candidate fields? Already taken into consideration by the model?