6. Slide 6 of25
Vital
Community
Prosperous
Economy
Increase thecapacity toreceivepilgrimsfrom 8 to30million pilgrims
3 citiesrankedamongthetop100 citiesin theworld
Increase theaveragelife expectancy from 74 to80years
Reducing unemployment ratefrom11.6%to7%
Raisetheproportionof women's participationin thelabor marketfrom 22%to30%
Raisethesizeof oureconomy from 19thto15thin theworld
Increase thepercentageof foreign directinvestmentfrom totaldomestic production from 3.8%to5.7%
Access toprivatesectorcontributiontototaldomestic production from 40%to65%
Increase non-oilgovernmentrevenuesfrom 163billion to1 trillionriyals annually
An ambitious
nation
JPTP Strategic Alignmentwith Vision 2030
7. Slide 7 of25
Statistical studies indicate that the number of vehicles in Saudi Arabia exceeds 20 million vehicles and the number is
increasing bymore than (7%)per year
The number of vehicles licensed in the Makkah region is 32%, more than (6 million) vehicles, including more than 50%
(3 million)vehicles within the cityof Jeddah
The annual increaseof vehicles within the city of Jeddah more than 105 thousand vehicles *
Source: General Directorate of Traffic
Increased trafficcongestion problemin thecityof Jeddahon a daily basis
Jeddah Today
8. Slide 8 of25
• Rail Network
This will consist of the Metro Network and Light Rail Transit system
• Bus Network
This will consist of a Bus Rapid Transit as feeder system for the Metro
• Marine transportation line
This will consist of Marine ferry Services and water taxis
• Corniche Tram
This will consist of a tram system covering the full length of the Corniche.
• Obhur Suspension Bridge
This will be an iconic structure facilitating both roads transport and Metro
• Public transportation station Al Muntalaq.
This will form an integral part of the Al-Muntalaq development offering intermodal change facility
• Program Completion Date: 2020
Context: Program Scope –MinisterialDecision 131
9. Slide 9 of25
Metro Jeddah Company (MJC) was set up as developer and asset owner of the Jeddah
PublicTransportation Program (JPTP).
MJC was established in March 2013 pursuant to Counsel of Ministers Decree No. 131. MJC
is registered (CR No. 4030247766) in Saudi Arabia and is a Government Linked Company
(GLC), a subsidiary of Jeddah Municipality (JM).
Company Profile
10. Slide 10 of25
OurVision: A SustainablePublicTransportation System for Jeddah
Our Goal: Integrate SustainabilityAcross MJC tolever operational excellence
Our Mission: Access tothe Public Transport System willbe sympathetic to"access
for all"principles and shallcomply with applicablelaws, regulations, standards and
codes.
MJC’s Vision,Mission & Goals
11. Slide 11 of25
Provide Public Transport for resident in Jeddah as 2nd Largest City in the Country
Provide additional Transport capacity to allow economic growth
To improve quality of life and the environment (reduce in congestion, accidents & delays)
Provide Mass Transit for annual events (Hajj & Umrah; Sports; Tourism; Entertainment)
To scope, design and operate a transport network that will:
Optimise the overall economic impact of the network
Integrate with all modes of transport
Minimise whole life cycle costs of all JPTP Projects
Create business opportunities and employment for Saudi Nationals by establishing key
commercial operations as part of the local rail industry
MJC’s StrategicObjectives
12. Slide 12 of25
MJC’s Governance Frameworkfor JPTP
Metro Jeddah Company
The Steering Committee of the project under the chairmanship of His Excellency
the Mayor of Jeddah
Representativeofthe
Ministryof Finance
DirectorofJeddah
TrafficDepartment
DeputyMinisterof
Transport
HEAdvisortotheGovernor
ofMakkahRegion
HEPresidentof thePublic
TransportAuthority
Higher Committee to oversee the project under the chairmanship of His Royal
Highness the Prince of Makkah Region
HE the Minister of Finance
HE Minister of Municipaland
RuralAffairs
HE the Minister of Transport Members
Members
21. Slide 21 of25
Line gauge
1435mm
Power-750 V DC
Train Control
(SIL) 4 -CBTC
Line length
(km)
Average
Interstation (mtrs)
Max Ops
Speed
Commercial
speed (km/h)
Operational
Headway (sec)
Red Line 59.7 2515 100 57.2 155
Orange Line 44.8 1447 100 46,3 160
Blue Line 39.6 1848 100 50,8 210
Green Line 17.0 1449 100 45,0 290
Metro fleet requirements 6 car x 3 Class VIP, Family & Standard
Unattended Train Operations (UTO), GoA4 Technology
T: 591 cars; OL- 162 cars (27 trains); BL – 156 cars (26 trains)
GL – 45 cars (3 cars/train, 15 trains) and RL – 228 cars (38 trains)
4 Depots (OL-1; RL- 2 & 1 Heavy maintenance) and 9 Parks & Rides
System Characteristics (Metro)
22. Slide 22 of25
Metro Lines Alignment
# Description KM Construction Cost (SAR)
1 Metro Orange Line 44.8 17,910,223,499
2 Metro Blue Line 39.6 12,923,003,609
3 Metro Green Line 17.0 7,546,758,228
4 Metro Red Line 59.7 20,306,782,870
Total 161.1 58,686,768,206
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are not
Included
23. Slide 23 of25
Completed Program Masterplan (JPTMP) including Ridership Estimates
Completed Pre-Program Management Activities by Aecom-USA which incudes Procurement Strategy, Industry Brief
Day, Program Schedule, EDMS, ProgramManual, Design Engineering Review, Contracts & Tendering Procedures
Completed Preliminary (30%)Engineering Design and Relevant Studies by Systra-France
Completed Architectural Design including Branding &Way Finding, and preliminary TOD by Foster &Partners UK
Metro Lines Schemes Updated Status
24. Slide 24 of25
• Tender Dossiers
• Orange Metro Line Civil Works
• Red Metro Line Civil Works
• Green & Blue Metro Lines and Almuntalaq Station Civil Works
• Rolling Stock, Depots Equipment, Track Works, Systems, MEP, for Metro Lines
• Automated Fare Collection System
• Each Tender Dossier Comprise of 10 Volume
Volume 1 – Instructions to Tenderers
Volume 2 – Form of Proposal
Volume 3 – Contract Agreement and Particular Conditions
Volume 4 – Employer’s Requirements – Particular
Volume 5 – Employer’s Requirements – Technical
Volume 6 – Employer’s Requirements – Design Specifications
Volume 7 – Employer’s Requirements – Materials and Workmanship Specifications
Volume 8 – Employer’s Tender Drawings
Volume 9 – Employer’s Investigations
Volume 10 – Employer’s Program Plans and Processes
Tender Dossiers for MetroLines
26. Slide 26 of25
Phase 1 Metro Line NetworkDiagram (Option 1)
# Description KM Construction Cost Estimates
(SAR)
1 Metro Orange Line 27.1 12.0 Bln
2 Metro Blue Line 9.4 2.7 Bln
3 Metro Green Line 9.5 5.0 Bln
Total 46.0 19.7 Bln
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation
and Contingencies are not Included
Boarding PM peak input data
Year 2020 2033
Peak Hour AM PM
Network Min Op Sys Min Op Sys
Orange Line 16,820 41,926
Blue Line 498 1,916
Green Green 3,154 12,774
TOTAL 20,472 56,616
27. Slide 27 of25
MOS MetroPhaseI
Phase 1 Metro Line NetworkDiagram (Option 2)
# Description KM Construction Cost Estimates
(SAR)
1 Metro Orange Line 27.1 12.0 Bln
2 Metro Blue Line 39.6 13.0 Bln
Total 66.7 25.0 Bln
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are
not Included
28. Slide 28 of25
MOS MetroPhaseI
Phase 1 Metro Line NetworkDiagram (Option 3)
# Description KM Construction Cost Estimates
(SAR)
1 Metro Orange Line 27.1 12.0 Bln
2 Metro Blue Line 39.6 13.0 Bln
3 Metro Green Line 9.5 5.0 Bln
Total 76.2 30.0 Bln
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are
not Included