Jeddah Public Transportation Program (JPTP)
From Vision to Operations
Metro Lines Project
Slide 2 of25
Agenda
1. JPTP Strategic Alignment with V2030
2. City of Jeddah
3. Company Profile
4. MJC Vision, Mission and Goals
5. MJC Strategic Objectives
6. MJC Governance Framework
7. Jeddah Today
8. Context Program Scope- Ministerial Decision 131
9. JPTP Master Plan 2015
10. Transportation Modes and Characteristic – 2015
11. Metro Lines Project
12. Metro Lines Project – Phase 1
13. Discussions and Q & A
Slide 3 of25
1253
‫سكان‬ ‫وعدد‬ ‫مربع‬‫كيلىمتر‬
4
‫وسمة‬ ‫ن‬‫مليى‬
1253SquareKm Population:4 Million
2018
‫م‬
1947
‫م‬
1
‫سكان‬ ‫وعدد‬ ‫مربع‬‫كيلىمتر‬
60
‫وسمة‬ ‫ألف‬
1 SquareKmPopulation:60Thousand
‫ل‬‫التحى‬
‫خالل‬
70
‫عام‬
‫مراحل‬
‫همى‬
‫جدة‬ ‫مديىة‬
Historical Development of JeddahCity
Slide 4 of25
58
‫كيلىمتر‬
18
‫كيلىمتر‬
Jeddah in 2018
Slide 5 of25
• LargestCountryinArabianPeninsulawith
populationof33.4millionin2018and
• Jeddahis2nd largestcityafter Riyadhwitha
populationof4.3million
• Jeddahisalsoknownas Gateway toHolyCities
MeccaandMedinaand
• BrideofRedSea,
• EconomicalHub
Jeddah Saudi Arabia
Slide 6 of25
Vital
Community
Prosperous
Economy
Increase thecapacity toreceivepilgrimsfrom 8 to30million pilgrims
3 citiesrankedamongthetop100 citiesin theworld
Increase theaveragelife expectancy from 74 to80years
Reducing unemployment ratefrom11.6%to7%
Raisetheproportionof women's participationin thelabor marketfrom 22%to30%
Raisethesizeof oureconomy from 19thto15thin theworld
Increase thepercentageof foreign directinvestmentfrom totaldomestic production from 3.8%to5.7%
Access toprivatesectorcontributiontototaldomestic production from 40%to65%
Increase non-oilgovernmentrevenuesfrom 163billion to1 trillionriyals annually
An ambitious
nation
JPTP Strategic Alignmentwith Vision 2030
Slide 7 of25
 Statistical studies indicate that the number of vehicles in Saudi Arabia exceeds 20 million vehicles and the number is
increasing bymore than (7%)per year
 The number of vehicles licensed in the Makkah region is 32%, more than (6 million) vehicles, including more than 50%
(3 million)vehicles within the cityof Jeddah
 The annual increaseof vehicles within the city of Jeddah more than 105 thousand vehicles *
Source: General Directorate of Traffic
Increased trafficcongestion problemin thecityof Jeddahon a daily basis
Jeddah Today
Slide 8 of25
• Rail Network
This will consist of the Metro Network and Light Rail Transit system
• Bus Network
This will consist of a Bus Rapid Transit as feeder system for the Metro
• Marine transportation line
This will consist of Marine ferry Services and water taxis
• Corniche Tram
This will consist of a tram system covering the full length of the Corniche.
• Obhur Suspension Bridge
This will be an iconic structure facilitating both roads transport and Metro
• Public transportation station Al Muntalaq.
This will form an integral part of the Al-Muntalaq development offering intermodal change facility
• Program Completion Date: 2020
Context: Program Scope –MinisterialDecision 131
Slide 9 of25
Metro Jeddah Company (MJC) was set up as developer and asset owner of the Jeddah
PublicTransportation Program (JPTP).
MJC was established in March 2013 pursuant to Counsel of Ministers Decree No. 131. MJC
is registered (CR No. 4030247766) in Saudi Arabia and is a Government Linked Company
(GLC), a subsidiary of Jeddah Municipality (JM).
Company Profile
Slide 10 of25
OurVision: A SustainablePublicTransportation System for Jeddah
Our Goal: Integrate SustainabilityAcross MJC tolever operational excellence
Our Mission: Access tothe Public Transport System willbe sympathetic to"access
for all"principles and shallcomply with applicablelaws, regulations, standards and
codes.
MJC’s Vision,Mission & Goals
Slide 11 of25
 Provide Public Transport for resident in Jeddah as 2nd Largest City in the Country
 Provide additional Transport capacity to allow economic growth
 To improve quality of life and the environment (reduce in congestion, accidents & delays)
 Provide Mass Transit for annual events (Hajj & Umrah; Sports; Tourism; Entertainment)
 To scope, design and operate a transport network that will:
 Optimise the overall economic impact of the network
 Integrate with all modes of transport
 Minimise whole life cycle costs of all JPTP Projects
 Create business opportunities and employment for Saudi Nationals by establishing key
commercial operations as part of the local rail industry
MJC’s StrategicObjectives
Slide 12 of25
MJC’s Governance Frameworkfor JPTP
Metro Jeddah Company
The Steering Committee of the project under the chairmanship of His Excellency
the Mayor of Jeddah
Representativeofthe
Ministryof Finance
DirectorofJeddah
TrafficDepartment
DeputyMinisterof
Transport
HEAdvisortotheGovernor
ofMakkahRegion
HEPresidentof thePublic
TransportAuthority
Higher Committee to oversee the project under the chairmanship of His Royal
Highness the Prince of Makkah Region
HE the Minister of Finance
HE Minister of Municipaland
RuralAffairs
HE the Minister of Transport Members
Members
Slide 13 of25
‫جدة‬ ‫بمحافظة‬ ‫العام‬ ‫الىقل‬ ‫ع‬‫و‬‫ملشر‬ ‫العام‬ ‫املخطط‬‫ثطىير‬ ‫مراحل‬
2033
‫م‬
JeddahCityStructurePlan2014 JeddahPublicTransportation
MasterPlan2015
2008 2013
2013
‫خلفيات‬
‫العام‬ ‫املخطط‬
‫ع‬‫و‬‫للمشر‬
Slide 14 of25
‫الىقل‬ ‫مخطط‬
‫جدة‬ ‫بمحافظة‬ ‫العام‬
JPTP Master Plan-2015
Slide 15 of25
‫الرئيسية‬ ‫البيعة‬‫دوار‬ ‫محطة‬
‫الرئيسية‬ ‫الىعيم‬ ‫محطة‬
‫الرئيسية‬ ‫القديم‬ ‫مكة‬ ‫طريق‬ ‫محطة‬
‫الرئيسية‬ ‫صاري‬ ‫شرق‬ ‫محطة‬
‫الاستخدامات‬ ‫متعددة‬ ‫املىطلق‬ ‫محطة‬
‫أبحر‬ ‫شرم‬‫جسر‬
(
‫جدة‬ ‫مديىة‬ ‫شمال‬ ‫السكاوي‬‫الىمى‬ ‫ويخدم‬ ‫البرثقالي‬ ‫املترو‬ ‫خط‬ ‫خالله‬‫يمر‬
)
‫العائدات‬ ‫لتقىية‬ ‫فرص‬
TOD
‫العائدات‬ ‫لتقىية‬ ‫فرص‬
TOD
‫الحافالت‬ ‫شبكة‬ ‫محطات‬ ‫أحد‬
Architecture Design of JPTP Components
Slide 16 of25
Mode Length (Km) Stations (Nr)
4 Metro Lines T:161.1; EL: 71.5; UG: 76.9; G: 12.7 T: 70; EL: 36; UG: 28; G: 1
Orange Line T: 44.8 ; EL: 33.9; UG: 10.9 T:29; EL: 20; UG: 9
Blue Line T: 39.6; EL: 18.3; UG: 21.3 T: 16; EL: 9; UG: 7
Green Line T: 17; UG: 17 T: 6; UG: 6
Red Line
T: 59.7; EL: 19.3;
UG: 27.7; G: 12.7
T: 19; EL: 7; UG: 6; G: 6
3 Light Rail Transit (LRT) T: 39.3; Sari: 18.3; Tahlia: 10.7; Falestine: 10.3
T: 45; Sari: 21; Tahlia: 12;
Falastine: 12
Corniche Tram G: 15.6 G: 15
Commuter Rail T: 196; EL: 15; UG: 6; G: 175 T: 20; EL: 3; UG: 5; G: 12
2 Bus Rapid Transit ((BRT-1A & 3A)
T: 26.4; Heraa-1A: 15.6;
King Fahad Street-3A: 10.8
T: 60; Heraa: 32;
King Fahad Street: 28
4 Major Bus Corridors (MBC-2A,2B,2C & 3B) T: 92 T: 150 (Bus Stops)
Local Feeder Buses T: 180.4 T: 494 (Bus Stops)
Transportation Modes and Characteristics-2015
Slide 17 of25
Boarding and AlightingFigures for JPTP
2033 Line PPHPD (PM Peak) Total Boardings (PM Peak)
Daily Ridership Modal Daily Boarding Annual Ridership Modal Annual Boarding
Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound
Metro
Red 9211 60002 600 020 1 068 036
1 784 420 3 176 268
180 006 000 320 410 680
535 326 000 952 880 280
Orange 8528 62478 624 780 1 112 108 187 434 000 333 632 520
Blue 7881 37690 376 900 670 882 113 070 000 201 264 600
Green 4583 18272 182 720 325 242 54 816 000 97 572 480
Rail Commuter Rail 8929 44479 444 790 791 726 444 790 791 726 133 437 000 237 517 860 133 437 000 237 517 860
LRT
Corniche Tram 1083 6139 61 390 109 274
649 680 1 156 430
18 417 000 32 782 260
194 904 000 346 929 120
LRT1B Sari 5955 27633 276 330 491 867 82 899 000 147 560 220
LRT 1C Tahlia 3173 13462 134 620 239 624 40 386 000 71 887 080
LRT1D Falastine 4211 17734 177 340 315 665 53 202 000 94 699 560
BRT
BRT1A 4677 16833 168 330 299 627
403 880 718 906
50 499 000 89 888 220
121 164 000 215 671 920
BRT3A 4927 23555 235 550 419 279 70 665 000 125 783 700
MBC
MBC 2A 3152 16263 162 630 289 481
616 110 1 096 676
48 789 000 86 844 420
184 833 000 329 002 740
MBC2B 4873 21780 217 800 387 684 65 340 000 116 305 200
MBC2C 1645 9841 98 410 175 170 29 523 000 52 550 940
MBC3B 3445 13727 137 270 244 341 41 181 000 73 302 180
Marine Services
Beach - Obhur Marina 687 6 870 12 229
58 110 103 436
2 061 000 3 668 580
17 433 000 31 030 740
Floating Mosque to Waterfront South 952 9 520 16 946 2 856 000 5 083 680
Hassan Enany Mosque - Jeddah Central 694 6 940 12 353 2 082 000 3 705 960
Coastal Tour 1658 16 580 29 512 4 974 000 8 853 720
Commute 1820 18 200 32 396 5 460 000 9 718 800
Slide 18 of25
Riderships Estimates for Metro Lines
• Ridership of Metro lines for Jeddah is estimated to be 535 Millionsannualboardings in 2033
(lower bound estimate) – equivalent to 1.78 Millionboardings per day.
2033 Line PPHPD (PM Peak)
Total
Boardings
(PM Peak)
Daily Ridership Modal Daily Boarding Annual Ridership Modal Annual Boarding
Lower
Bound
Upper
Bound
Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound
Metro
Red 9211 60002 600 020 1 068 036
1 784 420 3 176 268
180 006 000 320 410 680
535 326 000 952 880 280
Orange 8528 62478 624 780 1 112 108 187 434 000 333 632 520
Blue 7881 37690 376 900 670 882 113 070 000 201 264 600
Green 4583 18272 182 720 325 242 54 816 000 97 572 480
Slide 19 of25
 Corniche Tram.
 Marine Buses.
 Obhur Creek Bridge.

‫الكورنٌش‬ ‫ترام‬ ‫مشروع‬
.

‫البحري‬ ً‫التاكس‬ ‫مشروع‬
.

‫أبحر‬ ‫شرم‬ ‫جسر‬ ‫مشروع‬
.
‫الخاص‬ ‫القطاع‬ ‫لمشاركة‬ ‫المستهدفة‬ ‫المشارٌع‬
JPTP Components

‫المترو‬ ‫شبكة‬ ‫مشروع‬
(
‫للتشغٌل‬ ‫األدنى‬ ‫الحد‬ ‫ضمن‬
)

‫الحافالت‬ ‫شبكة‬ ‫مشروع‬
(
‫للتشغٌل‬ ‫األدنى‬ ‫الحد‬ ‫ضمن‬
)
 Metro Package (MOS)
 Bus Package (MOS)

‫مطار‬ ‫مترو‬ ‫لمحطة‬ ‫المدنٌة‬ ‫األعمال‬ ‫إنشاء‬ ‫مشروع‬
ً‫الول‬ ‫عبدالعزٌز‬ ‫الملك‬
.

‫اإلستخدامات‬ ‫المتعددة‬ ‫المنطلق‬ ‫محطة‬ ‫مشروع‬
.

‫اإلستخدامات‬ ‫متعددة‬ ‫العرب‬ ‫مول‬ ‫محطة‬ ‫تطوٌر‬ ‫مشروع‬
.

‫للمترو‬ ‫السٌارات‬ ‫مواقف‬ ‫مرافق‬
.
 Civil Works Construction for Metro Station
in KAIA.
 Mall of Arabia Triangle.
 Al-Montalaq Mixed-use Station.
 Park & Ride.
‫عناصر‬
‫أساسية‬
‫عناصر‬
‫مرتبطة‬
‫بالمشروع‬
‫عناصر‬
‫مرشحة‬
‫لمشاركة‬
‫القطاع‬
‫الخاص‬
Main
Components
Supporting
Components
PPPP
Components
Slide 20 of25
Metro Lines Project
Slide 21 of25
Line gauge
1435mm
Power-750 V DC
Train Control
(SIL) 4 -CBTC
Line length
(km)
Average
Interstation (mtrs)
Max Ops
Speed
Commercial
speed (km/h)
Operational
Headway (sec)
Red Line 59.7 2515 100 57.2 155
Orange Line 44.8 1447 100 46,3 160
Blue Line 39.6 1848 100 50,8 210
Green Line 17.0 1449 100 45,0 290
Metro fleet requirements 6 car x 3 Class VIP, Family & Standard
Unattended Train Operations (UTO), GoA4 Technology
T: 591 cars; OL- 162 cars (27 trains); BL – 156 cars (26 trains)
GL – 45 cars (3 cars/train, 15 trains) and RL – 228 cars (38 trains)
4 Depots (OL-1; RL- 2 & 1 Heavy maintenance) and 9 Parks & Rides
System Characteristics (Metro)
Slide 22 of25
Metro Lines Alignment
# Description KM Construction Cost (SAR)
1 Metro Orange Line 44.8 17,910,223,499
2 Metro Blue Line 39.6 12,923,003,609
3 Metro Green Line 17.0 7,546,758,228
4 Metro Red Line 59.7 20,306,782,870
Total 161.1 58,686,768,206
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are not
Included
Slide 23 of25
 Completed Program Masterplan (JPTMP) including Ridership Estimates
 Completed Pre-Program Management Activities by Aecom-USA which incudes Procurement Strategy, Industry Brief
Day, Program Schedule, EDMS, ProgramManual, Design Engineering Review, Contracts & Tendering Procedures
 Completed Preliminary (30%)Engineering Design and Relevant Studies by Systra-France
 Completed Architectural Design including Branding &Way Finding, and preliminary TOD by Foster &Partners UK
Metro Lines Schemes Updated Status
Slide 24 of25
• Tender Dossiers
• Orange Metro Line Civil Works
• Red Metro Line Civil Works
• Green & Blue Metro Lines and Almuntalaq Station Civil Works
• Rolling Stock, Depots Equipment, Track Works, Systems, MEP, for Metro Lines
• Automated Fare Collection System
• Each Tender Dossier Comprise of 10 Volume
Volume 1 – Instructions to Tenderers
Volume 2 – Form of Proposal
Volume 3 – Contract Agreement and Particular Conditions
Volume 4 – Employer’s Requirements – Particular
Volume 5 – Employer’s Requirements – Technical
Volume 6 – Employer’s Requirements – Design Specifications
Volume 7 – Employer’s Requirements – Materials and Workmanship Specifications
Volume 8 – Employer’s Tender Drawings
Volume 9 – Employer’s Investigations
Volume 10 – Employer’s Program Plans and Processes
Tender Dossiers for MetroLines
Slide 25 of25
Metro Lines Project– Phase 1
Slide 26 of25
Phase 1 Metro Line NetworkDiagram (Option 1)
# Description KM Construction Cost Estimates
(SAR)
1 Metro Orange Line 27.1 12.0 Bln
2 Metro Blue Line 9.4 2.7 Bln
3 Metro Green Line 9.5 5.0 Bln
Total 46.0 19.7 Bln
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation
and Contingencies are not Included
Boarding PM peak input data
Year 2020 2033
Peak Hour AM PM
Network Min Op Sys Min Op Sys
Orange Line 16,820 41,926
Blue Line 498 1,916
Green Green 3,154 12,774
TOTAL 20,472 56,616
Slide 27 of25
MOS MetroPhaseI
Phase 1 Metro Line NetworkDiagram (Option 2)
# Description KM Construction Cost Estimates
(SAR)
1 Metro Orange Line 27.1 12.0 Bln
2 Metro Blue Line 39.6 13.0 Bln
Total 66.7 25.0 Bln
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are
not Included
Slide 28 of25
MOS MetroPhaseI
Phase 1 Metro Line NetworkDiagram (Option 3)
# Description KM Construction Cost Estimates
(SAR)
1 Metro Orange Line 27.1 12.0 Bln
2 Metro Blue Line 39.6 13.0 Bln
3 Metro Green Line 9.5 5.0 Bln
Total 76.2 30.0 Bln
Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are
not Included
Slide 29 of25
Discussions and Q & A
Thank you

More Related Content

Similar to JPTP-Metro Lines Project_Korean Embassy WS_Sun Dec 2 2018 (1).pdf

Solving KL Traffic Woes Myth or Reality
Solving KL Traffic Woes Myth or RealitySolving KL Traffic Woes Myth or Reality
Solving KL Traffic Woes Myth or RealitySoo Kok Chua
 
Defining public transport routes for tod 8 october 2013 daisy dwango
Defining public transport routes for tod 8 october 2013 daisy dwangoDefining public transport routes for tod 8 october 2013 daisy dwango
Defining public transport routes for tod 8 october 2013 daisy dwangoReaVaya_KM
 
Transport Infrastructure Planning development and Non Motorised Transport
Transport Infrastructure Planning development and Non Motorised TransportTransport Infrastructure Planning development and Non Motorised Transport
Transport Infrastructure Planning development and Non Motorised TransportTristan Wiggill
 
Readying our ports for an onslaught of trade
Readying our ports for an onslaught of tradeReadying our ports for an onslaught of trade
Readying our ports for an onslaught of tradeTransnet Port Terminals
 
South East Europe Rail conference - Predrag Janković
South East Europe Rail conference - Predrag JankovićSouth East Europe Rail conference - Predrag Janković
South East Europe Rail conference - Predrag JankovićRussell Publishing
 
Transforming Urban Mobility in Africa: A Strong Institution, a Prerequisite
Transforming Urban Mobility in Africa: A Strong Institution, a PrerequisiteTransforming Urban Mobility in Africa: A Strong Institution, a Prerequisite
Transforming Urban Mobility in Africa: A Strong Institution, a PrerequisiteWRI Ross Center for Sustainable Cities
 
BRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdf
BRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdfBRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdf
BRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdfranvirsahi1
 
Djibouti ports: infrastructure & investments
Djibouti ports: infrastructure & investmentsDjibouti ports: infrastructure & investments
Djibouti ports: infrastructure & investmentsTristan Wiggill
 
Financial analysis of sahara darwaja case study
Financial analysis of sahara darwaja case studyFinancial analysis of sahara darwaja case study
Financial analysis of sahara darwaja case studyshubham sharma
 
Towards an effective transitioning of public transport system in Ghana
Towards an effective transitioning of public transport system in GhanaTowards an effective transitioning of public transport system in Ghana
Towards an effective transitioning of public transport system in GhanaInstitute for Transport Studies (ITS)
 
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...Sok-Tharath CHREUNG
 
[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)
[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)
[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)shrdcinfo
 
Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)Ibrahim Al-Hudhaif
 
28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...
28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...
28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...The Business Council of Mongolia
 
Sri Lanka - The hub of South Asia
Sri Lanka - The hub of South AsiaSri Lanka - The hub of South Asia
Sri Lanka - The hub of South AsiaenergiewaechterGmbH
 

Similar to JPTP-Metro Lines Project_Korean Embassy WS_Sun Dec 2 2018 (1).pdf (20)

Solving KL Traffic Woes Myth or Reality
Solving KL Traffic Woes Myth or RealitySolving KL Traffic Woes Myth or Reality
Solving KL Traffic Woes Myth or Reality
 
Defining public transport routes for tod 8 october 2013 daisy dwango
Defining public transport routes for tod 8 october 2013 daisy dwangoDefining public transport routes for tod 8 october 2013 daisy dwango
Defining public transport routes for tod 8 october 2013 daisy dwango
 
Transport Infrastructure Planning development and Non Motorised Transport
Transport Infrastructure Planning development and Non Motorised TransportTransport Infrastructure Planning development and Non Motorised Transport
Transport Infrastructure Planning development and Non Motorised Transport
 
Readying our ports for an onslaught of trade
Readying our ports for an onslaught of tradeReadying our ports for an onslaught of trade
Readying our ports for an onslaught of trade
 
South East Europe Rail conference - Predrag Janković
South East Europe Rail conference - Predrag JankovićSouth East Europe Rail conference - Predrag Janković
South East Europe Rail conference - Predrag Janković
 
Bangalore Metro Project
Bangalore Metro ProjectBangalore Metro Project
Bangalore Metro Project
 
Transforming Urban Mobility in Africa: A Strong Institution, a Prerequisite
Transforming Urban Mobility in Africa: A Strong Institution, a PrerequisiteTransforming Urban Mobility in Africa: A Strong Institution, a Prerequisite
Transforming Urban Mobility in Africa: A Strong Institution, a Prerequisite
 
BRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdf
BRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdfBRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdf
BRT-System-in-Delhi-Presen-and-Future-Scenario_2010.pdf
 
Djibouti ports: infrastructure & investments
Djibouti ports: infrastructure & investmentsDjibouti ports: infrastructure & investments
Djibouti ports: infrastructure & investments
 
Financial analysis of sahara darwaja case study
Financial analysis of sahara darwaja case studyFinancial analysis of sahara darwaja case study
Financial analysis of sahara darwaja case study
 
Towards an effective transitioning of public transport system in Ghana
Towards an effective transitioning of public transport system in GhanaTowards an effective transitioning of public transport system in Ghana
Towards an effective transitioning of public transport system in Ghana
 
Dhaka metro rail
Dhaka metro railDhaka metro rail
Dhaka metro rail
 
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
 
RDP Chapter 19
RDP Chapter 19RDP Chapter 19
RDP Chapter 19
 
Makkah Metro Presentation
Makkah Metro Presentation Makkah Metro Presentation
Makkah Metro Presentation
 
Improvement of urban transport system
Improvement of urban transport systemImprovement of urban transport system
Improvement of urban transport system
 
[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)
[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)
[Sustainable Mobility Workshop with UCLG-ASPAC] City Paper : Batam(Indonesia)
 
Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)
 
28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...
28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...
28.01.2013, The UB-Metro toward a world competitive city - Ulaanbaatar, Dr. K...
 
Sri Lanka - The hub of South Asia
Sri Lanka - The hub of South AsiaSri Lanka - The hub of South Asia
Sri Lanka - The hub of South Asia
 

Recently uploaded

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Recently uploaded (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

JPTP-Metro Lines Project_Korean Embassy WS_Sun Dec 2 2018 (1).pdf

  • 1. Slide 1 of25 Jeddah Public Transportation Program (JPTP) From Vision to Operations Metro Lines Project
  • 2. Slide 2 of25 Agenda 1. JPTP Strategic Alignment with V2030 2. City of Jeddah 3. Company Profile 4. MJC Vision, Mission and Goals 5. MJC Strategic Objectives 6. MJC Governance Framework 7. Jeddah Today 8. Context Program Scope- Ministerial Decision 131 9. JPTP Master Plan 2015 10. Transportation Modes and Characteristic – 2015 11. Metro Lines Project 12. Metro Lines Project – Phase 1 13. Discussions and Q & A
  • 3. Slide 3 of25 1253 ‫سكان‬ ‫وعدد‬ ‫مربع‬‫كيلىمتر‬ 4 ‫وسمة‬ ‫ن‬‫مليى‬ 1253SquareKm Population:4 Million 2018 ‫م‬ 1947 ‫م‬ 1 ‫سكان‬ ‫وعدد‬ ‫مربع‬‫كيلىمتر‬ 60 ‫وسمة‬ ‫ألف‬ 1 SquareKmPopulation:60Thousand ‫ل‬‫التحى‬ ‫خالل‬ 70 ‫عام‬ ‫مراحل‬ ‫همى‬ ‫جدة‬ ‫مديىة‬ Historical Development of JeddahCity
  • 5. Slide 5 of25 • LargestCountryinArabianPeninsulawith populationof33.4millionin2018and • Jeddahis2nd largestcityafter Riyadhwitha populationof4.3million • Jeddahisalsoknownas Gateway toHolyCities MeccaandMedinaand • BrideofRedSea, • EconomicalHub Jeddah Saudi Arabia
  • 6. Slide 6 of25 Vital Community Prosperous Economy Increase thecapacity toreceivepilgrimsfrom 8 to30million pilgrims 3 citiesrankedamongthetop100 citiesin theworld Increase theaveragelife expectancy from 74 to80years Reducing unemployment ratefrom11.6%to7% Raisetheproportionof women's participationin thelabor marketfrom 22%to30% Raisethesizeof oureconomy from 19thto15thin theworld Increase thepercentageof foreign directinvestmentfrom totaldomestic production from 3.8%to5.7% Access toprivatesectorcontributiontototaldomestic production from 40%to65% Increase non-oilgovernmentrevenuesfrom 163billion to1 trillionriyals annually An ambitious nation JPTP Strategic Alignmentwith Vision 2030
  • 7. Slide 7 of25  Statistical studies indicate that the number of vehicles in Saudi Arabia exceeds 20 million vehicles and the number is increasing bymore than (7%)per year  The number of vehicles licensed in the Makkah region is 32%, more than (6 million) vehicles, including more than 50% (3 million)vehicles within the cityof Jeddah  The annual increaseof vehicles within the city of Jeddah more than 105 thousand vehicles * Source: General Directorate of Traffic Increased trafficcongestion problemin thecityof Jeddahon a daily basis Jeddah Today
  • 8. Slide 8 of25 • Rail Network This will consist of the Metro Network and Light Rail Transit system • Bus Network This will consist of a Bus Rapid Transit as feeder system for the Metro • Marine transportation line This will consist of Marine ferry Services and water taxis • Corniche Tram This will consist of a tram system covering the full length of the Corniche. • Obhur Suspension Bridge This will be an iconic structure facilitating both roads transport and Metro • Public transportation station Al Muntalaq. This will form an integral part of the Al-Muntalaq development offering intermodal change facility • Program Completion Date: 2020 Context: Program Scope –MinisterialDecision 131
  • 9. Slide 9 of25 Metro Jeddah Company (MJC) was set up as developer and asset owner of the Jeddah PublicTransportation Program (JPTP). MJC was established in March 2013 pursuant to Counsel of Ministers Decree No. 131. MJC is registered (CR No. 4030247766) in Saudi Arabia and is a Government Linked Company (GLC), a subsidiary of Jeddah Municipality (JM). Company Profile
  • 10. Slide 10 of25 OurVision: A SustainablePublicTransportation System for Jeddah Our Goal: Integrate SustainabilityAcross MJC tolever operational excellence Our Mission: Access tothe Public Transport System willbe sympathetic to"access for all"principles and shallcomply with applicablelaws, regulations, standards and codes. MJC’s Vision,Mission & Goals
  • 11. Slide 11 of25  Provide Public Transport for resident in Jeddah as 2nd Largest City in the Country  Provide additional Transport capacity to allow economic growth  To improve quality of life and the environment (reduce in congestion, accidents & delays)  Provide Mass Transit for annual events (Hajj & Umrah; Sports; Tourism; Entertainment)  To scope, design and operate a transport network that will:  Optimise the overall economic impact of the network  Integrate with all modes of transport  Minimise whole life cycle costs of all JPTP Projects  Create business opportunities and employment for Saudi Nationals by establishing key commercial operations as part of the local rail industry MJC’s StrategicObjectives
  • 12. Slide 12 of25 MJC’s Governance Frameworkfor JPTP Metro Jeddah Company The Steering Committee of the project under the chairmanship of His Excellency the Mayor of Jeddah Representativeofthe Ministryof Finance DirectorofJeddah TrafficDepartment DeputyMinisterof Transport HEAdvisortotheGovernor ofMakkahRegion HEPresidentof thePublic TransportAuthority Higher Committee to oversee the project under the chairmanship of His Royal Highness the Prince of Makkah Region HE the Minister of Finance HE Minister of Municipaland RuralAffairs HE the Minister of Transport Members Members
  • 13. Slide 13 of25 ‫جدة‬ ‫بمحافظة‬ ‫العام‬ ‫الىقل‬ ‫ع‬‫و‬‫ملشر‬ ‫العام‬ ‫املخطط‬‫ثطىير‬ ‫مراحل‬ 2033 ‫م‬ JeddahCityStructurePlan2014 JeddahPublicTransportation MasterPlan2015 2008 2013 2013 ‫خلفيات‬ ‫العام‬ ‫املخطط‬ ‫ع‬‫و‬‫للمشر‬
  • 14. Slide 14 of25 ‫الىقل‬ ‫مخطط‬ ‫جدة‬ ‫بمحافظة‬ ‫العام‬ JPTP Master Plan-2015
  • 15. Slide 15 of25 ‫الرئيسية‬ ‫البيعة‬‫دوار‬ ‫محطة‬ ‫الرئيسية‬ ‫الىعيم‬ ‫محطة‬ ‫الرئيسية‬ ‫القديم‬ ‫مكة‬ ‫طريق‬ ‫محطة‬ ‫الرئيسية‬ ‫صاري‬ ‫شرق‬ ‫محطة‬ ‫الاستخدامات‬ ‫متعددة‬ ‫املىطلق‬ ‫محطة‬ ‫أبحر‬ ‫شرم‬‫جسر‬ ( ‫جدة‬ ‫مديىة‬ ‫شمال‬ ‫السكاوي‬‫الىمى‬ ‫ويخدم‬ ‫البرثقالي‬ ‫املترو‬ ‫خط‬ ‫خالله‬‫يمر‬ ) ‫العائدات‬ ‫لتقىية‬ ‫فرص‬ TOD ‫العائدات‬ ‫لتقىية‬ ‫فرص‬ TOD ‫الحافالت‬ ‫شبكة‬ ‫محطات‬ ‫أحد‬ Architecture Design of JPTP Components
  • 16. Slide 16 of25 Mode Length (Km) Stations (Nr) 4 Metro Lines T:161.1; EL: 71.5; UG: 76.9; G: 12.7 T: 70; EL: 36; UG: 28; G: 1 Orange Line T: 44.8 ; EL: 33.9; UG: 10.9 T:29; EL: 20; UG: 9 Blue Line T: 39.6; EL: 18.3; UG: 21.3 T: 16; EL: 9; UG: 7 Green Line T: 17; UG: 17 T: 6; UG: 6 Red Line T: 59.7; EL: 19.3; UG: 27.7; G: 12.7 T: 19; EL: 7; UG: 6; G: 6 3 Light Rail Transit (LRT) T: 39.3; Sari: 18.3; Tahlia: 10.7; Falestine: 10.3 T: 45; Sari: 21; Tahlia: 12; Falastine: 12 Corniche Tram G: 15.6 G: 15 Commuter Rail T: 196; EL: 15; UG: 6; G: 175 T: 20; EL: 3; UG: 5; G: 12 2 Bus Rapid Transit ((BRT-1A & 3A) T: 26.4; Heraa-1A: 15.6; King Fahad Street-3A: 10.8 T: 60; Heraa: 32; King Fahad Street: 28 4 Major Bus Corridors (MBC-2A,2B,2C & 3B) T: 92 T: 150 (Bus Stops) Local Feeder Buses T: 180.4 T: 494 (Bus Stops) Transportation Modes and Characteristics-2015
  • 17. Slide 17 of25 Boarding and AlightingFigures for JPTP 2033 Line PPHPD (PM Peak) Total Boardings (PM Peak) Daily Ridership Modal Daily Boarding Annual Ridership Modal Annual Boarding Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound Metro Red 9211 60002 600 020 1 068 036 1 784 420 3 176 268 180 006 000 320 410 680 535 326 000 952 880 280 Orange 8528 62478 624 780 1 112 108 187 434 000 333 632 520 Blue 7881 37690 376 900 670 882 113 070 000 201 264 600 Green 4583 18272 182 720 325 242 54 816 000 97 572 480 Rail Commuter Rail 8929 44479 444 790 791 726 444 790 791 726 133 437 000 237 517 860 133 437 000 237 517 860 LRT Corniche Tram 1083 6139 61 390 109 274 649 680 1 156 430 18 417 000 32 782 260 194 904 000 346 929 120 LRT1B Sari 5955 27633 276 330 491 867 82 899 000 147 560 220 LRT 1C Tahlia 3173 13462 134 620 239 624 40 386 000 71 887 080 LRT1D Falastine 4211 17734 177 340 315 665 53 202 000 94 699 560 BRT BRT1A 4677 16833 168 330 299 627 403 880 718 906 50 499 000 89 888 220 121 164 000 215 671 920 BRT3A 4927 23555 235 550 419 279 70 665 000 125 783 700 MBC MBC 2A 3152 16263 162 630 289 481 616 110 1 096 676 48 789 000 86 844 420 184 833 000 329 002 740 MBC2B 4873 21780 217 800 387 684 65 340 000 116 305 200 MBC2C 1645 9841 98 410 175 170 29 523 000 52 550 940 MBC3B 3445 13727 137 270 244 341 41 181 000 73 302 180 Marine Services Beach - Obhur Marina 687 6 870 12 229 58 110 103 436 2 061 000 3 668 580 17 433 000 31 030 740 Floating Mosque to Waterfront South 952 9 520 16 946 2 856 000 5 083 680 Hassan Enany Mosque - Jeddah Central 694 6 940 12 353 2 082 000 3 705 960 Coastal Tour 1658 16 580 29 512 4 974 000 8 853 720 Commute 1820 18 200 32 396 5 460 000 9 718 800
  • 18. Slide 18 of25 Riderships Estimates for Metro Lines • Ridership of Metro lines for Jeddah is estimated to be 535 Millionsannualboardings in 2033 (lower bound estimate) – equivalent to 1.78 Millionboardings per day. 2033 Line PPHPD (PM Peak) Total Boardings (PM Peak) Daily Ridership Modal Daily Boarding Annual Ridership Modal Annual Boarding Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound Lower Bound Upper Bound Metro Red 9211 60002 600 020 1 068 036 1 784 420 3 176 268 180 006 000 320 410 680 535 326 000 952 880 280 Orange 8528 62478 624 780 1 112 108 187 434 000 333 632 520 Blue 7881 37690 376 900 670 882 113 070 000 201 264 600 Green 4583 18272 182 720 325 242 54 816 000 97 572 480
  • 19. Slide 19 of25  Corniche Tram.  Marine Buses.  Obhur Creek Bridge.  ‫الكورنٌش‬ ‫ترام‬ ‫مشروع‬ .  ‫البحري‬ ً‫التاكس‬ ‫مشروع‬ .  ‫أبحر‬ ‫شرم‬ ‫جسر‬ ‫مشروع‬ . ‫الخاص‬ ‫القطاع‬ ‫لمشاركة‬ ‫المستهدفة‬ ‫المشارٌع‬ JPTP Components  ‫المترو‬ ‫شبكة‬ ‫مشروع‬ ( ‫للتشغٌل‬ ‫األدنى‬ ‫الحد‬ ‫ضمن‬ )  ‫الحافالت‬ ‫شبكة‬ ‫مشروع‬ ( ‫للتشغٌل‬ ‫األدنى‬ ‫الحد‬ ‫ضمن‬ )  Metro Package (MOS)  Bus Package (MOS)  ‫مطار‬ ‫مترو‬ ‫لمحطة‬ ‫المدنٌة‬ ‫األعمال‬ ‫إنشاء‬ ‫مشروع‬ ً‫الول‬ ‫عبدالعزٌز‬ ‫الملك‬ .  ‫اإلستخدامات‬ ‫المتعددة‬ ‫المنطلق‬ ‫محطة‬ ‫مشروع‬ .  ‫اإلستخدامات‬ ‫متعددة‬ ‫العرب‬ ‫مول‬ ‫محطة‬ ‫تطوٌر‬ ‫مشروع‬ .  ‫للمترو‬ ‫السٌارات‬ ‫مواقف‬ ‫مرافق‬ .  Civil Works Construction for Metro Station in KAIA.  Mall of Arabia Triangle.  Al-Montalaq Mixed-use Station.  Park & Ride. ‫عناصر‬ ‫أساسية‬ ‫عناصر‬ ‫مرتبطة‬ ‫بالمشروع‬ ‫عناصر‬ ‫مرشحة‬ ‫لمشاركة‬ ‫القطاع‬ ‫الخاص‬ Main Components Supporting Components PPPP Components
  • 20. Slide 20 of25 Metro Lines Project
  • 21. Slide 21 of25 Line gauge 1435mm Power-750 V DC Train Control (SIL) 4 -CBTC Line length (km) Average Interstation (mtrs) Max Ops Speed Commercial speed (km/h) Operational Headway (sec) Red Line 59.7 2515 100 57.2 155 Orange Line 44.8 1447 100 46,3 160 Blue Line 39.6 1848 100 50,8 210 Green Line 17.0 1449 100 45,0 290 Metro fleet requirements 6 car x 3 Class VIP, Family & Standard Unattended Train Operations (UTO), GoA4 Technology T: 591 cars; OL- 162 cars (27 trains); BL – 156 cars (26 trains) GL – 45 cars (3 cars/train, 15 trains) and RL – 228 cars (38 trains) 4 Depots (OL-1; RL- 2 & 1 Heavy maintenance) and 9 Parks & Rides System Characteristics (Metro)
  • 22. Slide 22 of25 Metro Lines Alignment # Description KM Construction Cost (SAR) 1 Metro Orange Line 44.8 17,910,223,499 2 Metro Blue Line 39.6 12,923,003,609 3 Metro Green Line 17.0 7,546,758,228 4 Metro Red Line 59.7 20,306,782,870 Total 161.1 58,686,768,206 Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are not Included
  • 23. Slide 23 of25  Completed Program Masterplan (JPTMP) including Ridership Estimates  Completed Pre-Program Management Activities by Aecom-USA which incudes Procurement Strategy, Industry Brief Day, Program Schedule, EDMS, ProgramManual, Design Engineering Review, Contracts & Tendering Procedures  Completed Preliminary (30%)Engineering Design and Relevant Studies by Systra-France  Completed Architectural Design including Branding &Way Finding, and preliminary TOD by Foster &Partners UK Metro Lines Schemes Updated Status
  • 24. Slide 24 of25 • Tender Dossiers • Orange Metro Line Civil Works • Red Metro Line Civil Works • Green & Blue Metro Lines and Almuntalaq Station Civil Works • Rolling Stock, Depots Equipment, Track Works, Systems, MEP, for Metro Lines • Automated Fare Collection System • Each Tender Dossier Comprise of 10 Volume Volume 1 – Instructions to Tenderers Volume 2 – Form of Proposal Volume 3 – Contract Agreement and Particular Conditions Volume 4 – Employer’s Requirements – Particular Volume 5 – Employer’s Requirements – Technical Volume 6 – Employer’s Requirements – Design Specifications Volume 7 – Employer’s Requirements – Materials and Workmanship Specifications Volume 8 – Employer’s Tender Drawings Volume 9 – Employer’s Investigations Volume 10 – Employer’s Program Plans and Processes Tender Dossiers for MetroLines
  • 25. Slide 25 of25 Metro Lines Project– Phase 1
  • 26. Slide 26 of25 Phase 1 Metro Line NetworkDiagram (Option 1) # Description KM Construction Cost Estimates (SAR) 1 Metro Orange Line 27.1 12.0 Bln 2 Metro Blue Line 9.4 2.7 Bln 3 Metro Green Line 9.5 5.0 Bln Total 46.0 19.7 Bln Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are not Included Boarding PM peak input data Year 2020 2033 Peak Hour AM PM Network Min Op Sys Min Op Sys Orange Line 16,820 41,926 Blue Line 498 1,916 Green Green 3,154 12,774 TOTAL 20,472 56,616
  • 27. Slide 27 of25 MOS MetroPhaseI Phase 1 Metro Line NetworkDiagram (Option 2) # Description KM Construction Cost Estimates (SAR) 1 Metro Orange Line 27.1 12.0 Bln 2 Metro Blue Line 39.6 13.0 Bln Total 66.7 25.0 Bln Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are not Included
  • 28. Slide 28 of25 MOS MetroPhaseI Phase 1 Metro Line NetworkDiagram (Option 3) # Description KM Construction Cost Estimates (SAR) 1 Metro Orange Line 27.1 12.0 Bln 2 Metro Blue Line 39.6 13.0 Bln 3 Metro Green Line 9.5 5.0 Bln Total 76.2 30.0 Bln Land Acquisition Cost, Operations and Maintenance (OPEX), Escalation and Contingencies are not Included
  • 29. Slide 29 of25 Discussions and Q & A Thank you