JedAir Hangar Development Project (HDP)
Guide
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
1 Submitted By: Amina Gidado
CONTENTS
INTRODUCTION 2 - 3
MILESTONE SCHEDULE 3 - 4
BUSINESS CASE 4- 7
Step One
PROJECT PLANNING 7
Step Two
Step Three
PROJECT EXCEUTION 7- 8
Step Four
PROJECT MONITORING 8 - 9
Step Five
PROJECT EVALUATION 9 - 10
Step Six
FINANCIAL SUMMARY 10 - 11
WORKING DOCUMENTS 11
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
2 Submitted By: Amina Gidado
INTRODUCTION (HIGH - LEVEL SUMMARY)
Approach: Hypbrid of Management and Sustainability methodologies – Project and
Program management
i) Project Management Cycle (PMC) / Phases / Steps / Stages: depicts strategy
implementation of Projects’ delivery with the following;
 Pre – Project commencement phase (Business Analysis)
 Project Cycle:- Project Initiation
 Project Design / Plan
 Project Set – up, Implementation / Execution
 and Monitoring & Evaluation
ii) Program Management Phases;
 Governance
 Relationship Management
 Benefit Management
 and Stakeholder Management
Theory of Change / Expected Returns:
 Profit made for the Organization
 Job Creation
 National Empowerment
 Contribution to policy Making
 and Fiscal Responsibility to the Federal Government of Nigeria (FGN)
Impact / Outcome: Private Hangar developed for Organizational and Tenants’ usage.
Outputs:
i) Sign - Off on Charter, Stakeholder Meeting Minutes & Stakeholder register,
Project Steering Committee, Project kick – Off Event / Meeting and Portfolio
Implementation Plan.
ii) Vendors Commence.
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
3 Submitted By: Amina Gidado
Figure 1
TYPICAL PROJECT MANAGEMENT CYCLE
The Hangar development project can typically be described in the schematic below;
Critical Success Factors
The first three steps of the PMC are the most critical in development of JedAir’s
Aircraft Hangar which will be managed by an Implementing Partner or Internal Staff
Member, the Project Execution step is also managed by the Implementing Partner or
Internal Team Member, the Monitoring step is managed by the Organization’s Project
Steering Committee whilst the Evaluation is managed by a Selected Third - Party
Vendor.
MILESTONE SCHEDULE
Duration:
Timeline: Start to End date
Phases Owner Description Deliverables Quality
Assurance
Initiation JedAir Milestone 1 Project Charter Signed - Off
Planning Project Team Milestone 2 Project Plan,
Monitoring and
Communication
Plan
Signed - Off
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
4 Submitted By: Amina Gidado
Execution TadBuilders Milestone 3 Project
Implementation
plan
Signed - Off
periodic
Communication
Reports (e.g.
Trend Reports)
Monitoring
& Control
Project Steering
Committee
Milestone 4 Issues & Risk
Management Plan,
Logs, Register and
Feedback Survey
plan
Inspection
Reports and
Quality Control
(Q. C) signified
by submitted
Certifications are
all signed - off
Evaluation Third Party
Vendor (External
Organization)
Milestone 5 Tenants feedback
report, Stakeholder
feedback report
Impact
Evaluation
Report, signed
off
Project
Close - Out
Milestone 6 Project Close – Out
report
Knowledge
Management &
Lessons Learnt
Report, signed -
off
Figure 2
Project Description
High Level Summary
STEP ONE: Where are we?
This the pre – commencement step generally referred to as the Business Case or the
Business Analysis step for the HDP. The following are the checklist for the successful
delivery of step 1;
i) Determine the need for the Hangar’s (type, size and number)
ii) Analyze the Airport environment
STEP TWO: Where do we want to be?
i) Explore alternate approaches
ii) Estimate financial impact
iii) Conduct Situational Analysis
iv) Analyze boundary Conditions
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
5 Submitted By: Amina Gidado
v) Conduct Stakeholder analysis
vi) Create a Business plan
STEP THREE: How Do We Get There?
i) Frame and Plan the project
ii) Build Stakeholder Support
iii) Prepare the Team
iv) Create the Preliminary Project Estimates
v) Identify the Funding sources
vi) Prepare the Financial Documentation
vii) Identify the Review and Approval steps
STEP FOUR: Project Execution
i) Design and Secure Funding for Hangars
ii) Solicit Bids and Award Construction Contracts
iii) Build Hangars
iv) Complete the Project and move in Tenants
STEP FIVE: Monitoring
i) Service Delivery and Operations
STEP FIVE:
i) Evaluate the Project Financial Performance
ii) Prepare a Project Summary for Hangar Owner (JedAir)
iii) Conduct User(s) Survey
WHERE ARE WE NOW? (BUSINESS CASE / ANALYSIS) - STEP ONE
i) Stakeholder Mapping
a) Identifying all key players who can assist with the Project
b) Create the Project Steering Committee
 Airport Representatives
 Hanger Owner Representatives
 Engineering Consultants
 Airport / Hangers’ representatives
ii) Current state of Airport
a) Quantifying Demand
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
6 Submitted By: Amina Gidado
b) Need for Hangars
c) Assessing Environment
d) Obtaining support for Key Decision Makers
iii) Identify Prospective Tenants of Hangar
iv) Determine Type of Hangar
Critical Success Factors
i) What is the Demand for Hangar?
ii) Sensitivity Analysis; Will Tenant pay for Higher Rent?
Airport Environment Analysis Guide
i) Where is the Funding coming from?
ii) Do we have Airport owner support?
iii) Do we have community support?
iv) Do we have approved FAAN Airport Master Plan?
v) Do we have Zoning and Land use?
vi) Do we have Environmental Issues?
vii) Do we have Airport Community Design Standards?
viii) Do we have existing Tenants support?
ix) Do we have availability of Project Funding?
x) Do we have current Hangar owner Financial situation?
Critical Success Factors
i) Airport Support Owner: The buy in of the Airport Owner is required,when it
comes to situations like Permits, Contractor Bid & Award, Airport Manager, Airport
Commission, Planning Department and Local Government Council and Management
Staff.
ii) Community Support: Good neighbours, Local Community Heads and Business
Groups.
iii) Land Use: Requirements on the Development of Hangars.
iv) Airport Community Design Standards: there may be restrictions on Building Size,
Infrastructure (Parking and Handicap access).
v) Airport Tenant Support: Database for Tenants’ waiting list; Check for competition,
potential conflicts or lease documents.
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
7 Submitted By: Amina Gidado
vi) Environmental issues: Will Hangar require an Environmental Impact Report (EIR)?
For mitigation of issues which could include, Noise, Traffic, Water Run – Off, Water
use, Soil degradation, Visual Impact and Vegetation or Animal Reports. 1
WHERE DO WE WANT TO BE? PROJECT PLANNING STEP TWO
Scope
i) What approach are we using? Do we have a situational analysis (SWOT)?
ii) Do we have Boundary Conditions Analysis?
iii) Have we identified key decision makers?
iv) Do we have a compelling Business Case for our Approach?
Expected Outputs:
i) Estimate the Financial Impact?
ii) Conduct a Situational Analysis
iii) Boundary Conditions Analysis
iv) Create a Business Plan for Official and Management purposes
v) Select Decision Makers
vi) Confirm Project Team Members
HOW DO WE GET THERE – PROJECT PLANNING STEP THREE
i) Complete project Framing
ii) Build Stakeholder Support
iii) Prepare Project Team
iv) Create Preliminary Project Estimates
v) Identify Funding Sources
vi) Prepare Final Documentation
vii) Identify Review and Approval steps
viii) Proceed
PROJECT EXECUTION - STEP FOUR
 Design Elements
 Underground Drainage and Storm, Water Run - Off control
1
Help can be sought from Airports Management Office Authority on EIRs.
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
8 Submitted By: Amina Gidado
 Underground Utility layouts, Fire Protection,Sprinkler Systems, Electricals,
Telephone, Cable, Sewer and tie – ins to existing Systems.
 Site Grading, Contour, Excavation and Sub – Base Material Plans.
 Concrete Hangar foundations
 Ramp, Taxiway and Apron paving.
 Architectural Treatments and Material Specifications for Hangars.
 Structural Design of Hangars (may be done by Builder Supplier).
 Ramp and Hangar lighting
 Landscaping
 Security Fencing, Gates and Personnel walk through gates.
 Parking Space required and Pedestrian Walkways.
Critical Success Factor
The Engineering contractor will be able to provide approvable guidance.
Expected Outputs:
i) FAAN Design Criteria
ii) Obtain Project Design and Funding
iii) Bid & Award Construction Contruct
iv) Construct Hangars
v) Complete Hangar Project and move in Tenants
Critical Success Factor
It is important that both the construction and the Design Engineers have prior
experience working on Airport Projects.
MONITORING - STEP FIVE
Using a sample of a Hangar that has been successfully developed with optimal profit
and services delivery, the below pre – construction agenda forms the input on
Monitoring of JedAir’s Hangar development.
Agenda Sample Pre- Construction
1) Labour, Provisions, Prevailing wages etc
2) Project Scope reviews
3) Construction objectives and Quality Assurance
i) Project Management
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
9 Submitted By: Amina Gidado
a. Sponsor / Owner Engineer
b. FAAN / JedAir’s Project Engineer
c. Engineering Consultant representatives
d. Airport Manager
ii) Construction objectives / material testing
a. Project Administration
b. Materials testing/ Quality assurance testing
c. Resident Job Site Engineer
iii) Coordination with Airport / City Staff FAAN, Airport Users
a. Construction acting coordination
b. Weekly progress meeting
c. NOTAMs issued by Airport Manager
iv) Construction contractor key Personnel identified
4) Administration
i) Contract award signatures completed
ii) Notice to proceed, first day of work, materials etc
iii) Project schedule and time limitations reviewed
iv) Charge orders, review, approval
v) Progress payments
a. Request and documentation
b. Schedule of values ( unit price)
c. Documentation of progress
d. Retention of escrow account
5) Construction Operations
i) Airport access, security during construction, Operations.
ii) Limitations on Contractor operations during Construction
iii) Public safety, Barricades, Warning signs, Night lighting
iv) Protection and restriction of Property
6) Conclusion of Construction
i) General limitations
ii) Specific Project Limitations (Access to certain areas)
iii) Pavement closures and Notifications to Airport Managers
PROJECT EVALUATION - STEP SIX
Expected Output (s):
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
10 Submitted By: Amina Gidado
i) Track Financial Performance of New Hangar Operations
ii) Adjust Rental rates as appropriate
iii) Debrief Project team
iv) Feedback Survey of Airport Tenants
v) Project Close out report to and Decision makers
FINANCIAL SUMMARY
Airport Operations and Expense Summary
REVENUE PLANNED ACTUAL 1Q 2Q 3Q 4Q
Fuel Sales Xxx xxx xxx xxx xxx xxx
Hangar Rent Xxx xxx xxx xxx xxx xxx
Tie down Rent Xxx xxx xxx xxx xxx xxx
Ground Rent Xxx xxx xxx xxx xxx xxx
Interest Earnings Xxx xxx xxx xxx xxx xxx
Property Tax
Returns
Xxx xxx xxx xxx xxx xxx
Miscellanous Xxx xxx xxx xxx xxx xxx
TOTAL xxx xxx xxx xxx xxx xxx
EXPENSES PLANNED ACTUAL 1Q 2Q 3Q 4Q
Over Heads xxx xxx xxx xxx xxx xxx
Fuel purchases xxx xxx xxx xxx xxx xxx
Contract Services xxx xxx xxx xxx xxx xxx
Utilities xxx xxx xxx xxx xxx xxx
Bank Fees xxx xxx xxx xxx xxx xxx
Telecommunications xxx xxx xxx xxx xxx xxx
Office Supplies xxx xxx xxx xxx xxx xxx
Repairs: Parts xxx xxx xxx xxx xxx xxx
Repairs:Maintenance xxx xxx xxx xxx xxx xxx
Insurance xxx xxx xxx xxx xxx xxx
Miscellaenous xxx xxx xxx xxx xxx xxx
Provision for Bad
Debt
xxx xxx xxx xxx xxx xxx
Taxes xxx xxx xxx xxx xxx xxx
TOTAL xxx xxx xxx xxx xxx xxx
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
11 Submitted By: Amina Gidado
OTHER PLANNED ACTUAL 1Q 2Q 3Q 4Q
Loan: Principal xxx xxx xxx xxx xxx xxx
Loan: Interest xxx xxx xxx xxx xxx xxx
Grants (if any) xxx xxx xxx xxx xxx xxx
Capital Project
Expenses
xxx xxx xxx xxx xxx xxx
Depreciation xxx xxx xxx xxx xxx xxx
TOTAL xxx xxx xxx xxx xxx xxx
WORKING DOCUMENTS
1) Meeting Brief on Sunday, 30th
July 2017 from meeting held with C. E. O JedAir
and Miss Amina Gidado.
2) Meeting Brief from meeting held between JedAir Team and TadBuilders Team.
3) Proposal Submitted by TadBuilders.
4) AirCraft Hangar Development Guide:A Valuable Airport Resource.
HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability
12 Submitted By: Amina Gidado

More Related Content

What's hot

Psm cv presentation jan15, 2013
Psm cv presentation jan15, 2013Psm cv presentation jan15, 2013
Psm cv presentation jan15, 2013psmuga9
 
Vimal, Civil Engr CV
Vimal, Civil Engr CVVimal, Civil Engr CV
Vimal, Civil Engr CVvimal nc
 
Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012REDceo.net
 
Mills Robert CV 2015-2
Mills Robert CV 2015-2Mills Robert CV 2015-2
Mills Robert CV 2015-2Robert Mills
 
Updated CV (LEONARDO M VILLAMIL JR) 19-1-16
Updated CV  (LEONARDO M  VILLAMIL JR) 19-1-16Updated CV  (LEONARDO M  VILLAMIL JR) 19-1-16
Updated CV (LEONARDO M VILLAMIL JR) 19-1-16Leonardo Villamil
 
Igbc green new buildings nbt precertification preliminary review infin...
Igbc green new buildings nbt precertification preliminary review   infin...Igbc green new buildings nbt precertification preliminary review   infin...
Igbc green new buildings nbt precertification preliminary review infin...sheelam khare
 
An Introduction to Dione Oil Ltd.
An Introduction to Dione Oil Ltd.An Introduction to Dione Oil Ltd.
An Introduction to Dione Oil Ltd.Sadegh Yazdani
 
my CV Hashim project/Site engineer
my CV   Hashim project/Site engineermy CV   Hashim project/Site engineer
my CV Hashim project/Site engineerHashim Vayalilakath
 
Mohamed sanoussi cv
Mohamed sanoussi cvMohamed sanoussi cv
Mohamed sanoussi cvBladina.com
 
Estimation & Technical Engr CV
Estimation & Technical Engr CVEstimation & Technical Engr CV
Estimation & Technical Engr CVmuhammad abdullah
 

What's hot (18)

Psm cv presentation jan15, 2013
Psm cv presentation jan15, 2013Psm cv presentation jan15, 2013
Psm cv presentation jan15, 2013
 
Vimal, Civil Engr CV
Vimal, Civil Engr CVVimal, Civil Engr CV
Vimal, Civil Engr CV
 
Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012
 
Jawad Ali Khan ARE-2
Jawad Ali Khan  ARE-2 Jawad Ali Khan  ARE-2
Jawad Ali Khan ARE-2
 
zk resume
zk resumezk resume
zk resume
 
Narciso cv
Narciso cvNarciso cv
Narciso cv
 
Structural Engineer
Structural EngineerStructural Engineer
Structural Engineer
 
Psm Cv Presentation 3 2012
Psm Cv Presentation 3  2012Psm Cv Presentation 3  2012
Psm Cv Presentation 3 2012
 
CV 2016.doc
CV 2016.docCV 2016.doc
CV 2016.doc
 
Mills Robert CV 2015-2
Mills Robert CV 2015-2Mills Robert CV 2015-2
Mills Robert CV 2015-2
 
Zain Ul Abideen_281116
Zain Ul Abideen_281116Zain Ul Abideen_281116
Zain Ul Abideen_281116
 
Updated CV (LEONARDO M VILLAMIL JR) 19-1-16
Updated CV  (LEONARDO M  VILLAMIL JR) 19-1-16Updated CV  (LEONARDO M  VILLAMIL JR) 19-1-16
Updated CV (LEONARDO M VILLAMIL JR) 19-1-16
 
Igbc green new buildings nbt precertification preliminary review infin...
Igbc green new buildings nbt precertification preliminary review   infin...Igbc green new buildings nbt precertification preliminary review   infin...
Igbc green new buildings nbt precertification preliminary review infin...
 
An Introduction to Dione Oil Ltd.
An Introduction to Dione Oil Ltd.An Introduction to Dione Oil Ltd.
An Introduction to Dione Oil Ltd.
 
Muhammad Tariq MGI
Muhammad Tariq MGIMuhammad Tariq MGI
Muhammad Tariq MGI
 
my CV Hashim project/Site engineer
my CV   Hashim project/Site engineermy CV   Hashim project/Site engineer
my CV Hashim project/Site engineer
 
Mohamed sanoussi cv
Mohamed sanoussi cvMohamed sanoussi cv
Mohamed sanoussi cv
 
Estimation & Technical Engr CV
Estimation & Technical Engr CVEstimation & Technical Engr CV
Estimation & Technical Engr CV
 

Similar to Jed air hangar development project final draft vrs 3

Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability EngineerAngela Lopez
 
Creek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxCreek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxZiyad Zaidi
 
Sustainable Architecture: Design Green with the Client in Mind.pdf
Sustainable Architecture: Design Green with the Client in Mind.pdfSustainable Architecture: Design Green with the Client in Mind.pdf
Sustainable Architecture: Design Green with the Client in Mind.pdfAggregage
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectIOSR Journals
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviromentjuwes
 
Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Pang Khai Shuen
 
EPC_Business_model
EPC_Business_modelEPC_Business_model
EPC_Business_modelavnish
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
 
Project Delivery Lifecycle
Project Delivery LifecycleProject Delivery Lifecycle
Project Delivery LifecycleMousumi Borah
 
Service Execution Process.pptx
Service Execution Process.pptxService Execution Process.pptx
Service Execution Process.pptxssuserfb3b311
 
projectappraisal-161115132308 (1).pdf
projectappraisal-161115132308 (1).pdfprojectappraisal-161115132308 (1).pdf
projectappraisal-161115132308 (1).pdfSwapanRoy16
 

Similar to Jed air hangar development project final draft vrs 3 (20)

Construction process
Construction processConstruction process
Construction process
 
RIBA Revit.pdf
RIBA Revit.pdfRIBA Revit.pdf
RIBA Revit.pdf
 
Rafeek's CV
Rafeek's CV Rafeek's CV
Rafeek's CV
 
Work Background and Activities
Work Background and ActivitiesWork Background and Activities
Work Background and Activities
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
 
Creek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxCreek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docx
 
Sustainable Architecture: Design Green with the Client in Mind.pdf
Sustainable Architecture: Design Green with the Client in Mind.pdfSustainable Architecture: Design Green with the Client in Mind.pdf
Sustainable Architecture: Design Green with the Client in Mind.pdf
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
Apprisal of loan proposal .
Apprisal of loan proposal . Apprisal of loan proposal .
Apprisal of loan proposal .
 
Apprisal of Loan proposal
Apprisal of Loan proposal Apprisal of Loan proposal
Apprisal of Loan proposal
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviroment
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
EPC_Business_model
EPC_Business_modelEPC_Business_model
EPC_Business_model
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Project Delivery Lifecycle
Project Delivery LifecycleProject Delivery Lifecycle
Project Delivery Lifecycle
 
Service Execution Process.pptx
Service Execution Process.pptxService Execution Process.pptx
Service Execution Process.pptx
 
projectappraisal-161115132308 (1).pdf
projectappraisal-161115132308 (1).pdfprojectappraisal-161115132308 (1).pdf
projectappraisal-161115132308 (1).pdf
 

Recently uploaded

BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfHenry Tapper
 
Financial institutions facilitate financing, economic transactions, issue fun...
Financial institutions facilitate financing, economic transactions, issue fun...Financial institutions facilitate financing, economic transactions, issue fun...
Financial institutions facilitate financing, economic transactions, issue fun...Avanish Goel
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Modelshematsharma006
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdfHenry Tapper
 
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办fqiuho152
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designsegoetzinger
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...Suhani Kapoor
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
Quantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector CompaniesQuantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector Companiesprashantbhati354
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Roomdivyansh0kumar0
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithAdamYassin2
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdfAdnet Communications
 
SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managmentfactical
 

Recently uploaded (20)

Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
 
Financial institutions facilitate financing, economic transactions, issue fun...
Financial institutions facilitate financing, economic transactions, issue fun...Financial institutions facilitate financing, economic transactions, issue fun...
Financial institutions facilitate financing, economic transactions, issue fun...
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Models
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdf
 
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
 
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road
 
Quantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector CompaniesQuantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector Companies
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam Smith
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf
 
SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managment
 

Jed air hangar development project final draft vrs 3

  • 1. 2017 AMINA GIDADO Submitted by: Portfolio Management Advisor & Quality Assurance Director 8/1/2017 JedAir Hangar Development Project (HDP) Guide
  • 2. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 1 Submitted By: Amina Gidado CONTENTS INTRODUCTION 2 - 3 MILESTONE SCHEDULE 3 - 4 BUSINESS CASE 4- 7 Step One PROJECT PLANNING 7 Step Two Step Three PROJECT EXCEUTION 7- 8 Step Four PROJECT MONITORING 8 - 9 Step Five PROJECT EVALUATION 9 - 10 Step Six FINANCIAL SUMMARY 10 - 11 WORKING DOCUMENTS 11
  • 3. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 2 Submitted By: Amina Gidado INTRODUCTION (HIGH - LEVEL SUMMARY) Approach: Hypbrid of Management and Sustainability methodologies – Project and Program management i) Project Management Cycle (PMC) / Phases / Steps / Stages: depicts strategy implementation of Projects’ delivery with the following;  Pre – Project commencement phase (Business Analysis)  Project Cycle:- Project Initiation  Project Design / Plan  Project Set – up, Implementation / Execution  and Monitoring & Evaluation ii) Program Management Phases;  Governance  Relationship Management  Benefit Management  and Stakeholder Management Theory of Change / Expected Returns:  Profit made for the Organization  Job Creation  National Empowerment  Contribution to policy Making  and Fiscal Responsibility to the Federal Government of Nigeria (FGN) Impact / Outcome: Private Hangar developed for Organizational and Tenants’ usage. Outputs: i) Sign - Off on Charter, Stakeholder Meeting Minutes & Stakeholder register, Project Steering Committee, Project kick – Off Event / Meeting and Portfolio Implementation Plan. ii) Vendors Commence.
  • 4. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 3 Submitted By: Amina Gidado Figure 1 TYPICAL PROJECT MANAGEMENT CYCLE The Hangar development project can typically be described in the schematic below; Critical Success Factors The first three steps of the PMC are the most critical in development of JedAir’s Aircraft Hangar which will be managed by an Implementing Partner or Internal Staff Member, the Project Execution step is also managed by the Implementing Partner or Internal Team Member, the Monitoring step is managed by the Organization’s Project Steering Committee whilst the Evaluation is managed by a Selected Third - Party Vendor. MILESTONE SCHEDULE Duration: Timeline: Start to End date Phases Owner Description Deliverables Quality Assurance Initiation JedAir Milestone 1 Project Charter Signed - Off Planning Project Team Milestone 2 Project Plan, Monitoring and Communication Plan Signed - Off
  • 5. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 4 Submitted By: Amina Gidado Execution TadBuilders Milestone 3 Project Implementation plan Signed - Off periodic Communication Reports (e.g. Trend Reports) Monitoring & Control Project Steering Committee Milestone 4 Issues & Risk Management Plan, Logs, Register and Feedback Survey plan Inspection Reports and Quality Control (Q. C) signified by submitted Certifications are all signed - off Evaluation Third Party Vendor (External Organization) Milestone 5 Tenants feedback report, Stakeholder feedback report Impact Evaluation Report, signed off Project Close - Out Milestone 6 Project Close – Out report Knowledge Management & Lessons Learnt Report, signed - off Figure 2 Project Description High Level Summary STEP ONE: Where are we? This the pre – commencement step generally referred to as the Business Case or the Business Analysis step for the HDP. The following are the checklist for the successful delivery of step 1; i) Determine the need for the Hangar’s (type, size and number) ii) Analyze the Airport environment STEP TWO: Where do we want to be? i) Explore alternate approaches ii) Estimate financial impact iii) Conduct Situational Analysis iv) Analyze boundary Conditions
  • 6. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 5 Submitted By: Amina Gidado v) Conduct Stakeholder analysis vi) Create a Business plan STEP THREE: How Do We Get There? i) Frame and Plan the project ii) Build Stakeholder Support iii) Prepare the Team iv) Create the Preliminary Project Estimates v) Identify the Funding sources vi) Prepare the Financial Documentation vii) Identify the Review and Approval steps STEP FOUR: Project Execution i) Design and Secure Funding for Hangars ii) Solicit Bids and Award Construction Contracts iii) Build Hangars iv) Complete the Project and move in Tenants STEP FIVE: Monitoring i) Service Delivery and Operations STEP FIVE: i) Evaluate the Project Financial Performance ii) Prepare a Project Summary for Hangar Owner (JedAir) iii) Conduct User(s) Survey WHERE ARE WE NOW? (BUSINESS CASE / ANALYSIS) - STEP ONE i) Stakeholder Mapping a) Identifying all key players who can assist with the Project b) Create the Project Steering Committee  Airport Representatives  Hanger Owner Representatives  Engineering Consultants  Airport / Hangers’ representatives ii) Current state of Airport a) Quantifying Demand
  • 7. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 6 Submitted By: Amina Gidado b) Need for Hangars c) Assessing Environment d) Obtaining support for Key Decision Makers iii) Identify Prospective Tenants of Hangar iv) Determine Type of Hangar Critical Success Factors i) What is the Demand for Hangar? ii) Sensitivity Analysis; Will Tenant pay for Higher Rent? Airport Environment Analysis Guide i) Where is the Funding coming from? ii) Do we have Airport owner support? iii) Do we have community support? iv) Do we have approved FAAN Airport Master Plan? v) Do we have Zoning and Land use? vi) Do we have Environmental Issues? vii) Do we have Airport Community Design Standards? viii) Do we have existing Tenants support? ix) Do we have availability of Project Funding? x) Do we have current Hangar owner Financial situation? Critical Success Factors i) Airport Support Owner: The buy in of the Airport Owner is required,when it comes to situations like Permits, Contractor Bid & Award, Airport Manager, Airport Commission, Planning Department and Local Government Council and Management Staff. ii) Community Support: Good neighbours, Local Community Heads and Business Groups. iii) Land Use: Requirements on the Development of Hangars. iv) Airport Community Design Standards: there may be restrictions on Building Size, Infrastructure (Parking and Handicap access). v) Airport Tenant Support: Database for Tenants’ waiting list; Check for competition, potential conflicts or lease documents.
  • 8. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 7 Submitted By: Amina Gidado vi) Environmental issues: Will Hangar require an Environmental Impact Report (EIR)? For mitigation of issues which could include, Noise, Traffic, Water Run – Off, Water use, Soil degradation, Visual Impact and Vegetation or Animal Reports. 1 WHERE DO WE WANT TO BE? PROJECT PLANNING STEP TWO Scope i) What approach are we using? Do we have a situational analysis (SWOT)? ii) Do we have Boundary Conditions Analysis? iii) Have we identified key decision makers? iv) Do we have a compelling Business Case for our Approach? Expected Outputs: i) Estimate the Financial Impact? ii) Conduct a Situational Analysis iii) Boundary Conditions Analysis iv) Create a Business Plan for Official and Management purposes v) Select Decision Makers vi) Confirm Project Team Members HOW DO WE GET THERE – PROJECT PLANNING STEP THREE i) Complete project Framing ii) Build Stakeholder Support iii) Prepare Project Team iv) Create Preliminary Project Estimates v) Identify Funding Sources vi) Prepare Final Documentation vii) Identify Review and Approval steps viii) Proceed PROJECT EXECUTION - STEP FOUR  Design Elements  Underground Drainage and Storm, Water Run - Off control 1 Help can be sought from Airports Management Office Authority on EIRs.
  • 9. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 8 Submitted By: Amina Gidado  Underground Utility layouts, Fire Protection,Sprinkler Systems, Electricals, Telephone, Cable, Sewer and tie – ins to existing Systems.  Site Grading, Contour, Excavation and Sub – Base Material Plans.  Concrete Hangar foundations  Ramp, Taxiway and Apron paving.  Architectural Treatments and Material Specifications for Hangars.  Structural Design of Hangars (may be done by Builder Supplier).  Ramp and Hangar lighting  Landscaping  Security Fencing, Gates and Personnel walk through gates.  Parking Space required and Pedestrian Walkways. Critical Success Factor The Engineering contractor will be able to provide approvable guidance. Expected Outputs: i) FAAN Design Criteria ii) Obtain Project Design and Funding iii) Bid & Award Construction Contruct iv) Construct Hangars v) Complete Hangar Project and move in Tenants Critical Success Factor It is important that both the construction and the Design Engineers have prior experience working on Airport Projects. MONITORING - STEP FIVE Using a sample of a Hangar that has been successfully developed with optimal profit and services delivery, the below pre – construction agenda forms the input on Monitoring of JedAir’s Hangar development. Agenda Sample Pre- Construction 1) Labour, Provisions, Prevailing wages etc 2) Project Scope reviews 3) Construction objectives and Quality Assurance i) Project Management
  • 10. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 9 Submitted By: Amina Gidado a. Sponsor / Owner Engineer b. FAAN / JedAir’s Project Engineer c. Engineering Consultant representatives d. Airport Manager ii) Construction objectives / material testing a. Project Administration b. Materials testing/ Quality assurance testing c. Resident Job Site Engineer iii) Coordination with Airport / City Staff FAAN, Airport Users a. Construction acting coordination b. Weekly progress meeting c. NOTAMs issued by Airport Manager iv) Construction contractor key Personnel identified 4) Administration i) Contract award signatures completed ii) Notice to proceed, first day of work, materials etc iii) Project schedule and time limitations reviewed iv) Charge orders, review, approval v) Progress payments a. Request and documentation b. Schedule of values ( unit price) c. Documentation of progress d. Retention of escrow account 5) Construction Operations i) Airport access, security during construction, Operations. ii) Limitations on Contractor operations during Construction iii) Public safety, Barricades, Warning signs, Night lighting iv) Protection and restriction of Property 6) Conclusion of Construction i) General limitations ii) Specific Project Limitations (Access to certain areas) iii) Pavement closures and Notifications to Airport Managers PROJECT EVALUATION - STEP SIX Expected Output (s):
  • 11. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 10 Submitted By: Amina Gidado i) Track Financial Performance of New Hangar Operations ii) Adjust Rental rates as appropriate iii) Debrief Project team iv) Feedback Survey of Airport Tenants v) Project Close out report to and Decision makers FINANCIAL SUMMARY Airport Operations and Expense Summary REVENUE PLANNED ACTUAL 1Q 2Q 3Q 4Q Fuel Sales Xxx xxx xxx xxx xxx xxx Hangar Rent Xxx xxx xxx xxx xxx xxx Tie down Rent Xxx xxx xxx xxx xxx xxx Ground Rent Xxx xxx xxx xxx xxx xxx Interest Earnings Xxx xxx xxx xxx xxx xxx Property Tax Returns Xxx xxx xxx xxx xxx xxx Miscellanous Xxx xxx xxx xxx xxx xxx TOTAL xxx xxx xxx xxx xxx xxx EXPENSES PLANNED ACTUAL 1Q 2Q 3Q 4Q Over Heads xxx xxx xxx xxx xxx xxx Fuel purchases xxx xxx xxx xxx xxx xxx Contract Services xxx xxx xxx xxx xxx xxx Utilities xxx xxx xxx xxx xxx xxx Bank Fees xxx xxx xxx xxx xxx xxx Telecommunications xxx xxx xxx xxx xxx xxx Office Supplies xxx xxx xxx xxx xxx xxx Repairs: Parts xxx xxx xxx xxx xxx xxx Repairs:Maintenance xxx xxx xxx xxx xxx xxx Insurance xxx xxx xxx xxx xxx xxx Miscellaenous xxx xxx xxx xxx xxx xxx Provision for Bad Debt xxx xxx xxx xxx xxx xxx Taxes xxx xxx xxx xxx xxx xxx TOTAL xxx xxx xxx xxx xxx xxx
  • 12. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 11 Submitted By: Amina Gidado OTHER PLANNED ACTUAL 1Q 2Q 3Q 4Q Loan: Principal xxx xxx xxx xxx xxx xxx Loan: Interest xxx xxx xxx xxx xxx xxx Grants (if any) xxx xxx xxx xxx xxx xxx Capital Project Expenses xxx xxx xxx xxx xxx xxx Depreciation xxx xxx xxx xxx xxx xxx TOTAL xxx xxx xxx xxx xxx xxx WORKING DOCUMENTS 1) Meeting Brief on Sunday, 30th July 2017 from meeting held with C. E. O JedAir and Miss Amina Gidado. 2) Meeting Brief from meeting held between JedAir Team and TadBuilders Team. 3) Proposal Submitted by TadBuilders. 4) AirCraft Hangar Development Guide:A Valuable Airport Resource.
  • 13. HANGAR DEVELOPMENT PROJECT GUIDE JedAir – Efficiency and Reliability 12 Submitted By: Amina Gidado