SlideShare a Scribd company logo
1 of 2
Download to read offline
Improving Uniformity:
Increasing First Pass Yield Through the Tire Building Machine
By Morgan Allis
Uniformity kick outs in department 614 has been an ongoing issue. The percentage of tires that passed uniformity
testing the first time, also known as first pass yield, was an area the business center wanted to improve upon. Reprocessing
tires, while hard on our employees, also costs the plant money; sometimes ticket is missed due to low first pass yield. .
Before our team began investigating this area of opportunity we verified that the machines that test uniformity,
Kokusai #1 and #2, were taking precise and accurate measurements. Through the implementation of new procedures, including
daily repeatability tests and shiftly rim cleanings, the two Kokusais were verified to be both accurate and precise.
As seen in figure 1, out of all the MTR build machines, TBM #14 has the highest number of kickouts (for a sample size
of approximately 1 week). A significant number of kickouts failed for the test metric most commonly associated with vibration
(radial runout and first harmonic). TBM #14’s low performance was the perfect opportunity to strategically design an
experiment to study the varying factors that affect tire uniformity; this was done through isolation of variables. In order to
achieve accurate results, variables such as builder and green tire #, were controlled for. A multifunctional team was organized
which included engineers, PQAMS, BCMs, TTLs, tire builders, FARO mechanics, and PM mechanics.
Figure 1. Pre-Alignment Kickout Results [10/28-11-04]
0
200
400
600
800
1000
TBM Kickouts Before
Improvements
The first variable to be studied was machine alignment. With invaluable data from the FARO alignment team it was
obvious that there was room for improvement. In conjunction with each other, the PM mechanics and FARO mechanics
efficiently aligned the build machine. The alignment included shaft-to-transfer-ring alignment, transfer ring to belt drum
alignment, and transfer ring to former alignment.
As seen in figures 2 and 3, the impact on uniformity from the TBM alignment was significant. First pass yield increased
from 72% to 98% (figure 2) and the overall number of kickouts significantly decreased from a weekly average of approximately
550 to 23 (figure 3). That is, our employees went from needing to handle tires 28% of the time to 2% of the time. This equated
to a significant amount of time where operators and PQAMs could work on other tasks.
Figure 2. Post-Alignment First Pass Yield Uniformity Results for TBM 14
Figure 3. TBM 14 kickouts [10/11-11/15]
Moving forward, while closely working with the FARO team, we plan to apply our findings to more build machines,
while at the same time also isolating and studying other variables such as centering capability, splice capability, green tire #,
and any other relevant variables. The study has demonstrated that build machine alignment is a critical component of tire
uniformity. Furthermore, the alignment results demonstrate the value that the FARO alignment team brings to the quality of
our product. Eventually we will use our findings to drive the quality of our product throughout all three business centers.
72%
98.43%
0%
20%
40%
60%
80%
100%
Uniformity First Pass Yield
Week Before
Alignment
Week After
Alignment
0
100
200
300
400
500
600
700
#ofKickouts
TBM 14 Kickouts
Alignment
Completed

More Related Content

What's hot

mixing report final
mixing report finalmixing report final
mixing report finalHassan Bilal
 
Extruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery WorldExtruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery WorldRubber & Tyre Machinery World
 
Rubber Injection Molding.pptx
Rubber Injection Molding.pptxRubber Injection Molding.pptx
Rubber Injection Molding.pptxLuis Tormento
 
Design of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy AttenuationDesign of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy AttenuationIRJET Journal
 
Wheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & OverhaulWheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & OverhaulYash Lad
 
Design & Fabrication of Film Frame by Geneva Mechanism
Design & Fabrication of Film Frame by Geneva MechanismDesign & Fabrication of Film Frame by Geneva Mechanism
Design & Fabrication of Film Frame by Geneva MechanismSuchit Moon
 
Cam and follower theory prof. sagar a dhotare
Cam and follower theory   prof. sagar a dhotareCam and follower theory   prof. sagar a dhotare
Cam and follower theory prof. sagar a dhotareSagar Dhotare
 
Ideal process parameters in injection moulding
Ideal process parameters in injection  mouldingIdeal process parameters in injection  moulding
Ideal process parameters in injection mouldingNaik Devang
 
National Rubber Conference (NRC) Mumbai 2015 E-Souvenir
National Rubber Conference (NRC) Mumbai 2015 E-SouvenirNational Rubber Conference (NRC) Mumbai 2015 E-Souvenir
National Rubber Conference (NRC) Mumbai 2015 E-SouvenirRubber & Tyre Machinery World
 
Wheels and tyres for automobile
Wheels and tyres for automobileWheels and tyres for automobile
Wheels and tyres for automobilesgrsoni45
 

What's hot (20)

mixing report final
mixing report finalmixing report final
mixing report final
 
Extruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery WorldExtruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery World
 
Rubber Injection Molding.pptx
Rubber Injection Molding.pptxRubber Injection Molding.pptx
Rubber Injection Molding.pptx
 
Design of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy AttenuationDesign of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy Attenuation
 
Wheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & OverhaulWheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & Overhaul
 
V-Belt Introduction
V-Belt IntroductionV-Belt Introduction
V-Belt Introduction
 
Rubber calenders at a glance
Rubber calenders at a glanceRubber calenders at a glance
Rubber calenders at a glance
 
Design & Fabrication of Film Frame by Geneva Mechanism
Design & Fabrication of Film Frame by Geneva MechanismDesign & Fabrication of Film Frame by Geneva Mechanism
Design & Fabrication of Film Frame by Geneva Mechanism
 
1.2 bearing life
1.2 bearing life1.2 bearing life
1.2 bearing life
 
Screw and Barrel Inspection
Screw and Barrel InspectionScrew and Barrel Inspection
Screw and Barrel Inspection
 
Tyres
TyresTyres
Tyres
 
Cam and follower theory prof. sagar a dhotare
Cam and follower theory   prof. sagar a dhotareCam and follower theory   prof. sagar a dhotare
Cam and follower theory prof. sagar a dhotare
 
Blow molding Process
Blow molding ProcessBlow molding Process
Blow molding Process
 
Ideal process parameters in injection moulding
Ideal process parameters in injection  mouldingIdeal process parameters in injection  moulding
Ideal process parameters in injection moulding
 
Tyres
TyresTyres
Tyres
 
National Rubber Conference (NRC) Mumbai 2015 E-Souvenir
National Rubber Conference (NRC) Mumbai 2015 E-SouvenirNational Rubber Conference (NRC) Mumbai 2015 E-Souvenir
National Rubber Conference (NRC) Mumbai 2015 E-Souvenir
 
Production Packer
Production PackerProduction Packer
Production Packer
 
The Art of Owning & Operating Rubber Calenders
The Art of Owning & Operating Rubber CalendersThe Art of Owning & Operating Rubber Calenders
The Art of Owning & Operating Rubber Calenders
 
1. clutch
1. clutch1. clutch
1. clutch
 
Wheels and tyres for automobile
Wheels and tyres for automobileWheels and tyres for automobile
Wheels and tyres for automobile
 

Viewers also liked

Goodyear aquatred launch
Goodyear   aquatred launchGoodyear   aquatred launch
Goodyear aquatred launchSameer Mathur
 
Apollo Tyres case study analysis - HR perspective
Apollo Tyres case study analysis - HR perspectiveApollo Tyres case study analysis - HR perspective
Apollo Tyres case study analysis - HR perspectiveShubham Singhal
 
APOLLO TYRE CASE STUDY
APOLLO TYRE CASE STUDYAPOLLO TYRE CASE STUDY
APOLLO TYRE CASE STUDYAnkur Patel
 
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...Unmetric
 
Marketing Strategy of Apollo Tyres
Marketing Strategy of Apollo TyresMarketing Strategy of Apollo Tyres
Marketing Strategy of Apollo TyresPrakhar Jain
 
Steering system forces and moments
Steering system forces and momentsSteering system forces and moments
Steering system forces and momentssaffrony09
 

Viewers also liked (8)

Michelin - Mairuk Al-Huq
Michelin - Mairuk Al-HuqMichelin - Mairuk Al-Huq
Michelin - Mairuk Al-Huq
 
Goodyear aquatred launch
Goodyear   aquatred launchGoodyear   aquatred launch
Goodyear aquatred launch
 
Apollo Tyres case study analysis - HR perspective
Apollo Tyres case study analysis - HR perspectiveApollo Tyres case study analysis - HR perspective
Apollo Tyres case study analysis - HR perspective
 
APOLLO TYRE CASE STUDY
APOLLO TYRE CASE STUDYAPOLLO TYRE CASE STUDY
APOLLO TYRE CASE STUDY
 
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
 
Marketing Strategy of Apollo Tyres
Marketing Strategy of Apollo TyresMarketing Strategy of Apollo Tyres
Marketing Strategy of Apollo Tyres
 
Tyre Industry Analysis
Tyre Industry AnalysisTyre Industry Analysis
Tyre Industry Analysis
 
Steering system forces and moments
Steering system forces and momentsSteering system forces and moments
Steering system forces and moments
 

Similar to Improving Uniformity at the Tire Building Machine

aakash101.pptx
aakash101.pptxaakash101.pptx
aakash101.pptxakash99112
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingAlwin Thomas
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET Journal
 
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...IAEME Publication
 
Success Story - GKN-Aero-Success Story-2016-force
Success Story - GKN-Aero-Success Story-2016-forceSuccess Story - GKN-Aero-Success Story-2016-force
Success Story - GKN-Aero-Success Story-2016-forceMohamed Abuali
 
Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet ManagementIJMER
 
A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...
A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...
A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...IOSR Journals
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET Journal
 
Representative Testing of Emissions and Fuel Consumption of Working Machines ...
Representative Testing of Emissions and Fuel Consumption of Working Machines ...Representative Testing of Emissions and Fuel Consumption of Working Machines ...
Representative Testing of Emissions and Fuel Consumption of Working Machines ...Reno Filla
 
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWSTUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWIAEME Publication
 
IRJET- The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...
IRJET-  	  The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...IRJET-  	  The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...
IRJET- The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...IRJET Journal
 
IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...
IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...
IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...IRJET Journal
 
Effect of equipment utilisation on economics of mining project a case study
Effect of equipment utilisation on economics of mining project a case studyEffect of equipment utilisation on economics of mining project a case study
Effect of equipment utilisation on economics of mining project a case studyIAEME Publication
 

Similar to Improving Uniformity at the Tire Building Machine (20)

EGR 590 Final GM
EGR 590 Final GM EGR 590 Final GM
EGR 590 Final GM
 
aakash101.pptx
aakash101.pptxaakash101.pptx
aakash101.pptx
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream Mapping
 
Sip
SipSip
Sip
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
 
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
 
Success Story - GKN-Aero-Success Story-2016-force
Success Story - GKN-Aero-Success Story-2016-forceSuccess Story - GKN-Aero-Success Story-2016-force
Success Story - GKN-Aero-Success Story-2016-force
 
Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet Management
 
A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...
A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...
A Comparative Reliability Analysis of Bulldozers arriving at workshop in East...
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
 
Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...
Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...
Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...
 
Representative Testing of Emissions and Fuel Consumption of Working Machines ...
Representative Testing of Emissions and Fuel Consumption of Working Machines ...Representative Testing of Emissions and Fuel Consumption of Working Machines ...
Representative Testing of Emissions and Fuel Consumption of Working Machines ...
 
Steve Mutch
Steve MutchSteve Mutch
Steve Mutch
 
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWSTUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
 
IRJET- The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...
IRJET-  	  The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...IRJET-  	  The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...
IRJET- The Effectvof Tyreover Load and Inflation Pressure on the Rolling ...
 
IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...
IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...
IRJET- Analysis of Constructions Productivity based on Progress Payment Certi...
 
Effect of equipment utilisation on economics of mining project a case study
Effect of equipment utilisation on economics of mining project a case studyEffect of equipment utilisation on economics of mining project a case study
Effect of equipment utilisation on economics of mining project a case study
 

Improving Uniformity at the Tire Building Machine

  • 1. Improving Uniformity: Increasing First Pass Yield Through the Tire Building Machine By Morgan Allis Uniformity kick outs in department 614 has been an ongoing issue. The percentage of tires that passed uniformity testing the first time, also known as first pass yield, was an area the business center wanted to improve upon. Reprocessing tires, while hard on our employees, also costs the plant money; sometimes ticket is missed due to low first pass yield. . Before our team began investigating this area of opportunity we verified that the machines that test uniformity, Kokusai #1 and #2, were taking precise and accurate measurements. Through the implementation of new procedures, including daily repeatability tests and shiftly rim cleanings, the two Kokusais were verified to be both accurate and precise. As seen in figure 1, out of all the MTR build machines, TBM #14 has the highest number of kickouts (for a sample size of approximately 1 week). A significant number of kickouts failed for the test metric most commonly associated with vibration (radial runout and first harmonic). TBM #14’s low performance was the perfect opportunity to strategically design an experiment to study the varying factors that affect tire uniformity; this was done through isolation of variables. In order to achieve accurate results, variables such as builder and green tire #, were controlled for. A multifunctional team was organized which included engineers, PQAMS, BCMs, TTLs, tire builders, FARO mechanics, and PM mechanics. Figure 1. Pre-Alignment Kickout Results [10/28-11-04] 0 200 400 600 800 1000 TBM Kickouts Before Improvements
  • 2. The first variable to be studied was machine alignment. With invaluable data from the FARO alignment team it was obvious that there was room for improvement. In conjunction with each other, the PM mechanics and FARO mechanics efficiently aligned the build machine. The alignment included shaft-to-transfer-ring alignment, transfer ring to belt drum alignment, and transfer ring to former alignment. As seen in figures 2 and 3, the impact on uniformity from the TBM alignment was significant. First pass yield increased from 72% to 98% (figure 2) and the overall number of kickouts significantly decreased from a weekly average of approximately 550 to 23 (figure 3). That is, our employees went from needing to handle tires 28% of the time to 2% of the time. This equated to a significant amount of time where operators and PQAMs could work on other tasks. Figure 2. Post-Alignment First Pass Yield Uniformity Results for TBM 14 Figure 3. TBM 14 kickouts [10/11-11/15] Moving forward, while closely working with the FARO team, we plan to apply our findings to more build machines, while at the same time also isolating and studying other variables such as centering capability, splice capability, green tire #, and any other relevant variables. The study has demonstrated that build machine alignment is a critical component of tire uniformity. Furthermore, the alignment results demonstrate the value that the FARO alignment team brings to the quality of our product. Eventually we will use our findings to drive the quality of our product throughout all three business centers. 72% 98.43% 0% 20% 40% 60% 80% 100% Uniformity First Pass Yield Week Before Alignment Week After Alignment 0 100 200 300 400 500 600 700 #ofKickouts TBM 14 Kickouts Alignment Completed