1. Effective multi-party arbitration clauses in construction contracts require properly drafting the clause to encompass all potential disputes between related parties to the construction project under one proceeding.
2. Back-to-back agreements between contractors and subcontractors are important to ensure subcontractor obligations match those in the main contract. However, contractors sometimes fail to secure these agreements.
3. Independent dispute resolution clauses are needed in the main contract and any subcontracts. Awards from arbitrations between the client and contractor would not necessarily bind the subcontractor in separate arbitrations between the contractor and subcontractor.
This document discusses strategies a subcontractor can use to pursue payment from the main contractor when faced with a conditional payment clause. Conditional clauses like "pay when paid" aim to shift the risk of non-payment from the main contractor to the subcontractor. The document outlines two alternative bases for a subcontractor's claim: 1) negotiating a direct payment agreement with the employer; and 2) arguing the main contractor failed to fully pursue the subcontractor's claims against the employer as required by law. It also discusses the importance of timing, with the subcontractor systematically requesting evidence and pursuing legal action if needed. Overall, the document advises subcontractors to argue lack of pursuit by the main contractor rather than simply
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
A public lecture presentation on 8 July 2016 by Tom Joseph Mukasa, (sponsored by the Institution of Surveyors of Uganda) at Kyambogo University, Kampala - Uganda.
The document discusses construction disputes, their causes, and dispute resolution mechanisms. It provides details on:
1) Causes of construction disputes include late or non-payment, inaccurate cost valuations, delays in information, and ambiguities in contract requirements.
2) Dispute resolution clauses in contracts set out the mechanism for resolving disputes, often through arbitration.
3) For government construction contracts, disputes are typically resolved through a multi-level process involving engineers, committees, and potentially arbitration if issues remain unresolved.
The document discusses several questions related to construction contract delays. It defines concurrent delays as multiple delay events occurring simultaneously and impacting a project's completion date. It also explains that a contractor is typically entitled to an extension of time but not necessarily compensation for loss and expenses if delays are caused by both the employer and contractor, depending on the specific contract terms and whether employer delays were dominant.
This document discusses payment terms in the construction industry. It covers topics such as the importance of timely payments, payment procedures in standard contracts like FIDIC, remedies for payment default, statutory remedies under English law, self-help remedies, and conditional payment provisions. The document emphasizes that cash flow is critical in construction projects due to their long duration and capital-intensive nature. It provides an overview of payment mechanisms and remedies for delayed payment in construction contracts.
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSIAEME Publication
Contract forms, terms, specification, analysis of rate and conditions of contract
are being followed by various governments departments in the field of civil
construction are not uniform. Against the backdrop of India’s burgeoning macroeconomic prospects, the weaknesses of the construction industry create challenges,
particularly with respect to settlement of disputes between the owner and contractor
that it will have to overcome. Arbitration awards have been studied and based upon
their analyses a series of survey questionnaire have been developed. The responses to
the above along with the gist of focused discussions and interviews with domain
experts forms the basis for SWOT analyses of arbitration awards.
This document discusses penalty and liquidated damages clauses in contracts. It provides definitions and examples. Specifically:
1) Penalty refers to a sum named in a contract as payment for breach that is not a genuine pre-estimate of loss. Liquidated damages is a sum that is a genuine pre-estimate of the loss from breach.
2) Indian contract law allows for reasonable compensation for breach not exceeding any penalty or liquidated damages stipulated in the contract. Courts can reduce such sums if not a true estimate of damages.
3) Examples are provided of cases where courts reduced stipulated damages, including one where damages for delay in supplying pipes were reduced to reasonable compensation.
4) Stip
Liquidated Damages post Cavendish v MakdessiAdam Ramlugon
The document discusses a recent UK Supreme Court case that clarified the law around liquidated damages clauses and when they constitute unenforceable penalties. It provides an overview of key points for the superyacht industry based on the court's findings. Specifically, 1) the case did not reinvent prior tests but added other considerations, 2) the pre-estimate of loss test remains important but is part of a wider analysis, and 3) context and proportionality are crucial factors, especially for unique vessels like superyachts. However, large liquidated damages for charter cancellations may still be unenforceable penalties.
This document discusses strategies a subcontractor can use to pursue payment from the main contractor when faced with a conditional payment clause. Conditional clauses like "pay when paid" aim to shift the risk of non-payment from the main contractor to the subcontractor. The document outlines two alternative bases for a subcontractor's claim: 1) negotiating a direct payment agreement with the employer; and 2) arguing the main contractor failed to fully pursue the subcontractor's claims against the employer as required by law. It also discusses the importance of timing, with the subcontractor systematically requesting evidence and pursuing legal action if needed. Overall, the document advises subcontractors to argue lack of pursuit by the main contractor rather than simply
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
A public lecture presentation on 8 July 2016 by Tom Joseph Mukasa, (sponsored by the Institution of Surveyors of Uganda) at Kyambogo University, Kampala - Uganda.
The document discusses construction disputes, their causes, and dispute resolution mechanisms. It provides details on:
1) Causes of construction disputes include late or non-payment, inaccurate cost valuations, delays in information, and ambiguities in contract requirements.
2) Dispute resolution clauses in contracts set out the mechanism for resolving disputes, often through arbitration.
3) For government construction contracts, disputes are typically resolved through a multi-level process involving engineers, committees, and potentially arbitration if issues remain unresolved.
The document discusses several questions related to construction contract delays. It defines concurrent delays as multiple delay events occurring simultaneously and impacting a project's completion date. It also explains that a contractor is typically entitled to an extension of time but not necessarily compensation for loss and expenses if delays are caused by both the employer and contractor, depending on the specific contract terms and whether employer delays were dominant.
This document discusses payment terms in the construction industry. It covers topics such as the importance of timely payments, payment procedures in standard contracts like FIDIC, remedies for payment default, statutory remedies under English law, self-help remedies, and conditional payment provisions. The document emphasizes that cash flow is critical in construction projects due to their long duration and capital-intensive nature. It provides an overview of payment mechanisms and remedies for delayed payment in construction contracts.
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSIAEME Publication
Contract forms, terms, specification, analysis of rate and conditions of contract
are being followed by various governments departments in the field of civil
construction are not uniform. Against the backdrop of India’s burgeoning macroeconomic prospects, the weaknesses of the construction industry create challenges,
particularly with respect to settlement of disputes between the owner and contractor
that it will have to overcome. Arbitration awards have been studied and based upon
their analyses a series of survey questionnaire have been developed. The responses to
the above along with the gist of focused discussions and interviews with domain
experts forms the basis for SWOT analyses of arbitration awards.
This document discusses penalty and liquidated damages clauses in contracts. It provides definitions and examples. Specifically:
1) Penalty refers to a sum named in a contract as payment for breach that is not a genuine pre-estimate of loss. Liquidated damages is a sum that is a genuine pre-estimate of the loss from breach.
2) Indian contract law allows for reasonable compensation for breach not exceeding any penalty or liquidated damages stipulated in the contract. Courts can reduce such sums if not a true estimate of damages.
3) Examples are provided of cases where courts reduced stipulated damages, including one where damages for delay in supplying pipes were reduced to reasonable compensation.
4) Stip
Liquidated Damages post Cavendish v MakdessiAdam Ramlugon
The document discusses a recent UK Supreme Court case that clarified the law around liquidated damages clauses and when they constitute unenforceable penalties. It provides an overview of key points for the superyacht industry based on the court's findings. Specifically, 1) the case did not reinvent prior tests but added other considerations, 2) the pre-estimate of loss test remains important but is part of a wider analysis, and 3) context and proportionality are crucial factors, especially for unique vessels like superyachts. However, large liquidated damages for charter cancellations may still be unenforceable penalties.
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
The document discusses two issues regarding a construction contract:
1) Whether a contractor is entitled to an extension of time if a project is suspended by a stop work order from local authorities. The answer depends on whether the stop work was due to the contractor's fault.
2) Whether an employer can take over a project from the contractor and appoint a third party to finish without terminating the original contract. Generally no, unless the contract allows termination for convenience or there is a breach by the contractor. Simply facing delays does not allow the employer to replace the contractor.
The document discusses various types of delays that can occur in construction projects and their classifications. It provides examples of:
1) Excusable delays such as labor disputes, fires, and unavoidable delays that are beyond the contractor's control.
2) Non-excusable delays like ordinary weather, subcontractor delays, and failures by the contractor to properly manage the site.
3) Compensable delays caused by unforeseen issues like transportation delays beyond the contractor's control.
It also discusses the differences between critical and non-critical delays as well as concurrent delays caused by multiple parties. The key takeaway is that excusable, non-critical, and concurrent delays may provide grounds for claims for
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...Werksmans Attorneys
This document summarizes two recent court cases, Coface South Africa Insurance Co v East London Own Haven and Guardrisk Insurance Company Ltd v Kentz, regarding the interpretation and application of demand guarantees. Both cases establish that demand guarantees are enforceable based on their terms alone, without consideration of any issues between the holder and other party to the underlying contract. The document also discusses standard contract conditions regarding insolvency, business rescue, and the rights of parties. Key considerations discussed include the wording of securities and underlying contracts with regards to business rescue versus winding up.
This document discusses extension of time (EoT) clauses in construction contracts. It provides definitions and examples of force majeure events that can provide grounds for an EoT, such as acts of God, vis major events, and exceptionally inclement weather. It also discusses civil commotion, strikes, and lockouts as events in clause 23.8(d) that can result in an EoT. The document reviews case law that interprets these clauses and whether certain events qualify for an EoT or not. It also notes new provisions in clause 23.8 and discusses the process for reviewing and granting an EoT after default or practical completion.
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Francis Ho
This document discusses liquidated damages clauses in construction contracts. It defines liquidated damages as a pre-determined sum payable in the event of a specified breach of contract, and explains that they aim to provide a genuine pre-estimate of loss to avoid disputes over damages calculations. The document outlines reasons for using liquidated damages clauses and defenses against them, and analyzes how courts determine whether a clause imposes a penalty rather than reasonable damages. It also discusses implications if a challenge to liquidated damages succeeds.
When Do Liquidated Damages Become an Irrecoverable Penalty?Sarah Fox
The document summarizes guidelines from the case Makdessi v Cavendish for determining whether a contractual sum is an unenforceable penalty or a valid liquidated damages clause. It outlines seven guidelines from the case, including that a sum is more likely to be considered a penalty if it is extravagant compared to possible losses or applies to breaches of different types. It also notes that the guidelines have limitations and contracting parties have freedom to agree terms, making penalties difficult for courts to invalidate.
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
This document discusses liquidated damages and penalties in commercial contracts. It begins with an introduction explaining damages for breach of contract and how liquidated damages provisions aim to provide certainty. It then covers the differences between general damages and liquidated damages, and how liquidated damages differ from penalties. The document discusses best practices for calculating liquidated damages and their advantages. It also examines liquidated damages in standard forms of contract and case law from various jurisdictions. An example case study is also provided to illustrate liquidated damages in practice.
This document discusses negotiations in the context of commercial disputes, complex deals, and entrepreneurship. It provides an overview of negotiations, including definitions and examples. It outlines key approaches to negotiations, such as principled negotiation. It also discusses specific negotiation contexts like investor negotiations, co-founder negotiations, and technology deals. Challenges in different types of negotiations are highlighted, like controlling technology after licensing it.
1. The document discusses the relevance and applicability of force majeure clauses in contracts in light of the COVID-19 pandemic and resulting nationwide shutdown in India.
2. It examines whether COVID-19 qualifies as a force majeure event and what parties must consider before invoking a force majeure clause, such as determining relevant contract provisions and governing laws.
3. In the absence of a force majeure clause, parties may rely on the common law doctrine of frustration. The real estate sector will likely be significantly impacted due to project delays, and developers may seek one-year extensions from regulatory authorities by arguing force majeure.
CIPAA Update June 2019 - a case of creeping complexities?Kheng Hoe Advocates
This document summarizes the evolution of case law surrounding Malaysia's Construction Industry Payment and Adjudication Act (CIPAA) from 2015 to 2018. Initially, courts overwhelmingly supported CIPAA and claimants. However, challenges became more complex over time regarding jurisdiction, contract legality, and whether claims were contractual or quantum meruit. A pivotal 2018 Federal Court decision found adjudicators must consider all defenses, opening the door for merits review of decisions. Another 2018 appellate ruling questioned if CIPAA applies retrospectively. Overall, the document traces how CIPAA jurisprudence and respondent strategies shifted as courts clarified the legislation.
The case of Hancock v Brazier (Annerly) Ltd dealt with the issue of implied term in building contracts. In this case, the Court of Appeal held that in a contract for building a house, in the absence of express agreement, three terms should be implied: 1) the builder would do his work in a good and workmanlike manner 2) he would supply good and proper materials and 3) the house would be reasonably fit for human habitation.
The document discusses exclusion clauses in standard form contracts, how courts interpret them strictly, and seek to protect consumers from harsh effects by requiring clauses to be incorporated and reasonable. It also outlines statutes that void clauses restricting liability for negligence, death, or injury, and defines unfair terms that cause imbalance to the consumer's detriment.
This document discusses direct payments from employers to subcontractors in construction contracts. It begins by defining contractual and non-contractual direct payments. It then examines several court cases that have addressed the issue:
1) The courts will strictly observe privity of contracts and will not find a direct contractual relationship between employers and subcontractors based on direct payments alone, unless there is a tripartite agreement.
2) However, the courts have allowed subcontractors to sue employers directly for payment in some cases where there is evidence of an oral or implied agreement for direct payment, such as past direct payments, representations made, or contemporaneous documents.
3) The legal issues around direct obligations of subcontractors
This seminar was part of the Bar Council practical construction law series presented by the Construction Law Committee to practitioners. It covers the topic of payments and common issues arising in the construction industry.
This document discusses the "fit for purpose" obligation in international arbitrations. It defines "fit for purpose" as an implied obligation for goods to be suitable for the intended purpose. The obligation is addressed in sale of goods acts and the CISG. For services, providers must exercise reasonable skill and care. In design-build contracts, the contractor assumes responsibility for both design and construction being fit for purpose. Arbitrators must consider how the purpose is defined in the contract and look to case law and standard contracts for guidance when determining issues related to fit for purpose obligations.
Most construction contracts do not give employers much control over contractors' work progress schedules. However, contracts commonly require contractors to submit work programs. These programs are not legally binding like the project specifications. They simply indicate how the contractor intends to schedule the work.
If a contract does not include provisions for extending the completion deadline, employers can claim liquidated damages for delays. In one case, a contractor failed to complete work by the original deadline or an extended one, so the owner validly terminated the contract.
Contracts also typically include clauses governing extensions of time for contractors. These clauses outline the process for requesting extensions and the events that would warrant granting more time, such as delays beyond a contractor's control.
This document summarizes changes between the 2000 and 2014 editions of the Joint Building Contracts Committee (JBCC) standard form construction contracts used in South Africa. Some key changes include streamlining and restructuring the contract from 40 to 30 clauses, expanding and clarifying contractor and employer duties, consolidating insurance provisions, reformulating security provisions, and increasing contractor liability for works risk while defining force majeure events. Specific changes are outlined for indemnities, setting out, subcontractors, and completion phases. The document provides an overview of the evolution of the JBCC standard forms and significant differences between editions.
My presentation at Indian Institution of Technical Arbitrators on October 26,2012. Topic: Dispute resolution in UAE; An overview on the recent developments.
PRC Contract Law Principles and Risk Management in Contract DraftingRHKLegal
An overview of contract drafting techniques with regard to the PRC Contract Law principles and recent Supreme Court Directions. An analysis of limitation of liability and liquidated damages clauses in the China market context.
This newsletter discusses statutory adjudication and how it can benefit the construction industry in Hong Kong. It provides an overview of current alternative dispute resolution methods like mediation and arbitration and their limitations in resolving payment disputes quickly. Statutory adjudication addresses this gap by providing a fast-track dispute process that delivers a temporary binding decision within a strict timetable of around 4 months. It also gives the unpaid party the right to suspend work if the adjudicated payment is not made, as well as prohibiting "pay-when-paid" clauses that can delay payments down the supply chain. While some question how just the short adjudication timetable is, overall it aims to ease cash flow problems in the industry through prompt resolution of payment disputes.
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
The document discusses two issues regarding a construction contract:
1) Whether a contractor is entitled to an extension of time if a project is suspended by a stop work order from local authorities. The answer depends on whether the stop work was due to the contractor's fault.
2) Whether an employer can take over a project from the contractor and appoint a third party to finish without terminating the original contract. Generally no, unless the contract allows termination for convenience or there is a breach by the contractor. Simply facing delays does not allow the employer to replace the contractor.
The document discusses various types of delays that can occur in construction projects and their classifications. It provides examples of:
1) Excusable delays such as labor disputes, fires, and unavoidable delays that are beyond the contractor's control.
2) Non-excusable delays like ordinary weather, subcontractor delays, and failures by the contractor to properly manage the site.
3) Compensable delays caused by unforeseen issues like transportation delays beyond the contractor's control.
It also discusses the differences between critical and non-critical delays as well as concurrent delays caused by multiple parties. The key takeaway is that excusable, non-critical, and concurrent delays may provide grounds for claims for
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...Werksmans Attorneys
This document summarizes two recent court cases, Coface South Africa Insurance Co v East London Own Haven and Guardrisk Insurance Company Ltd v Kentz, regarding the interpretation and application of demand guarantees. Both cases establish that demand guarantees are enforceable based on their terms alone, without consideration of any issues between the holder and other party to the underlying contract. The document also discusses standard contract conditions regarding insolvency, business rescue, and the rights of parties. Key considerations discussed include the wording of securities and underlying contracts with regards to business rescue versus winding up.
This document discusses extension of time (EoT) clauses in construction contracts. It provides definitions and examples of force majeure events that can provide grounds for an EoT, such as acts of God, vis major events, and exceptionally inclement weather. It also discusses civil commotion, strikes, and lockouts as events in clause 23.8(d) that can result in an EoT. The document reviews case law that interprets these clauses and whether certain events qualify for an EoT or not. It also notes new provisions in clause 23.8 and discusses the process for reviewing and granting an EoT after default or practical completion.
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Francis Ho
This document discusses liquidated damages clauses in construction contracts. It defines liquidated damages as a pre-determined sum payable in the event of a specified breach of contract, and explains that they aim to provide a genuine pre-estimate of loss to avoid disputes over damages calculations. The document outlines reasons for using liquidated damages clauses and defenses against them, and analyzes how courts determine whether a clause imposes a penalty rather than reasonable damages. It also discusses implications if a challenge to liquidated damages succeeds.
When Do Liquidated Damages Become an Irrecoverable Penalty?Sarah Fox
The document summarizes guidelines from the case Makdessi v Cavendish for determining whether a contractual sum is an unenforceable penalty or a valid liquidated damages clause. It outlines seven guidelines from the case, including that a sum is more likely to be considered a penalty if it is extravagant compared to possible losses or applies to breaches of different types. It also notes that the guidelines have limitations and contracting parties have freedom to agree terms, making penalties difficult for courts to invalidate.
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
This document discusses liquidated damages and penalties in commercial contracts. It begins with an introduction explaining damages for breach of contract and how liquidated damages provisions aim to provide certainty. It then covers the differences between general damages and liquidated damages, and how liquidated damages differ from penalties. The document discusses best practices for calculating liquidated damages and their advantages. It also examines liquidated damages in standard forms of contract and case law from various jurisdictions. An example case study is also provided to illustrate liquidated damages in practice.
This document discusses negotiations in the context of commercial disputes, complex deals, and entrepreneurship. It provides an overview of negotiations, including definitions and examples. It outlines key approaches to negotiations, such as principled negotiation. It also discusses specific negotiation contexts like investor negotiations, co-founder negotiations, and technology deals. Challenges in different types of negotiations are highlighted, like controlling technology after licensing it.
1. The document discusses the relevance and applicability of force majeure clauses in contracts in light of the COVID-19 pandemic and resulting nationwide shutdown in India.
2. It examines whether COVID-19 qualifies as a force majeure event and what parties must consider before invoking a force majeure clause, such as determining relevant contract provisions and governing laws.
3. In the absence of a force majeure clause, parties may rely on the common law doctrine of frustration. The real estate sector will likely be significantly impacted due to project delays, and developers may seek one-year extensions from regulatory authorities by arguing force majeure.
CIPAA Update June 2019 - a case of creeping complexities?Kheng Hoe Advocates
This document summarizes the evolution of case law surrounding Malaysia's Construction Industry Payment and Adjudication Act (CIPAA) from 2015 to 2018. Initially, courts overwhelmingly supported CIPAA and claimants. However, challenges became more complex over time regarding jurisdiction, contract legality, and whether claims were contractual or quantum meruit. A pivotal 2018 Federal Court decision found adjudicators must consider all defenses, opening the door for merits review of decisions. Another 2018 appellate ruling questioned if CIPAA applies retrospectively. Overall, the document traces how CIPAA jurisprudence and respondent strategies shifted as courts clarified the legislation.
The case of Hancock v Brazier (Annerly) Ltd dealt with the issue of implied term in building contracts. In this case, the Court of Appeal held that in a contract for building a house, in the absence of express agreement, three terms should be implied: 1) the builder would do his work in a good and workmanlike manner 2) he would supply good and proper materials and 3) the house would be reasonably fit for human habitation.
The document discusses exclusion clauses in standard form contracts, how courts interpret them strictly, and seek to protect consumers from harsh effects by requiring clauses to be incorporated and reasonable. It also outlines statutes that void clauses restricting liability for negligence, death, or injury, and defines unfair terms that cause imbalance to the consumer's detriment.
This document discusses direct payments from employers to subcontractors in construction contracts. It begins by defining contractual and non-contractual direct payments. It then examines several court cases that have addressed the issue:
1) The courts will strictly observe privity of contracts and will not find a direct contractual relationship between employers and subcontractors based on direct payments alone, unless there is a tripartite agreement.
2) However, the courts have allowed subcontractors to sue employers directly for payment in some cases where there is evidence of an oral or implied agreement for direct payment, such as past direct payments, representations made, or contemporaneous documents.
3) The legal issues around direct obligations of subcontractors
This seminar was part of the Bar Council practical construction law series presented by the Construction Law Committee to practitioners. It covers the topic of payments and common issues arising in the construction industry.
This document discusses the "fit for purpose" obligation in international arbitrations. It defines "fit for purpose" as an implied obligation for goods to be suitable for the intended purpose. The obligation is addressed in sale of goods acts and the CISG. For services, providers must exercise reasonable skill and care. In design-build contracts, the contractor assumes responsibility for both design and construction being fit for purpose. Arbitrators must consider how the purpose is defined in the contract and look to case law and standard contracts for guidance when determining issues related to fit for purpose obligations.
Most construction contracts do not give employers much control over contractors' work progress schedules. However, contracts commonly require contractors to submit work programs. These programs are not legally binding like the project specifications. They simply indicate how the contractor intends to schedule the work.
If a contract does not include provisions for extending the completion deadline, employers can claim liquidated damages for delays. In one case, a contractor failed to complete work by the original deadline or an extended one, so the owner validly terminated the contract.
Contracts also typically include clauses governing extensions of time for contractors. These clauses outline the process for requesting extensions and the events that would warrant granting more time, such as delays beyond a contractor's control.
This document summarizes changes between the 2000 and 2014 editions of the Joint Building Contracts Committee (JBCC) standard form construction contracts used in South Africa. Some key changes include streamlining and restructuring the contract from 40 to 30 clauses, expanding and clarifying contractor and employer duties, consolidating insurance provisions, reformulating security provisions, and increasing contractor liability for works risk while defining force majeure events. Specific changes are outlined for indemnities, setting out, subcontractors, and completion phases. The document provides an overview of the evolution of the JBCC standard forms and significant differences between editions.
My presentation at Indian Institution of Technical Arbitrators on October 26,2012. Topic: Dispute resolution in UAE; An overview on the recent developments.
PRC Contract Law Principles and Risk Management in Contract DraftingRHKLegal
An overview of contract drafting techniques with regard to the PRC Contract Law principles and recent Supreme Court Directions. An analysis of limitation of liability and liquidated damages clauses in the China market context.
This newsletter discusses statutory adjudication and how it can benefit the construction industry in Hong Kong. It provides an overview of current alternative dispute resolution methods like mediation and arbitration and their limitations in resolving payment disputes quickly. Statutory adjudication addresses this gap by providing a fast-track dispute process that delivers a temporary binding decision within a strict timetable of around 4 months. It also gives the unpaid party the right to suspend work if the adjudicated payment is not made, as well as prohibiting "pay-when-paid" clauses that can delay payments down the supply chain. While some question how just the short adjudication timetable is, overall it aims to ease cash flow problems in the industry through prompt resolution of payment disputes.
CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'BrienJohn FFF O'Brien
The document discusses alternative dispute resolution (ADR) for commercial construction contract disputes in Ireland. It makes three key points:
1) ADR processes like arbitration, mediation, and conciliation all occur behind closed doors, maintaining confidentiality of proceedings and outcomes. This has both benefits and drawbacks for resolving disputes and industry learning.
2) The new adjudication process established in 2013 provides another option for resolving payment disputes, but it remains untested in Ireland and may face legal challenges regarding fairness.
3) Mediation and conciliation remain the best forums for construction dispute resolution if parties engage in good faith, but dispute prevention through robust project management is most important.
The document discusses contracts management and the Indian Contract Act of 1872. It provides definitions of key terms related to contracts such as offer, acceptance, consideration, void agreements, remedies for breach of contract, and classifications of contracts. It also summarizes general conditions of contracts including scope, time for completion, guarantees and liabilities, and procedures for contract execution and changes.
INTERNATIONAL JOINT VENTURE CONTRACT - Contract Template and SampleGlobal Negotiator
The International Joint Venture (www.globalnegotiator.com) governs the relationship between two companies based in different countries, and which set up a third company (the Joint Venture).
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART IIcmmindia2017
This document discusses the enforcement of foreign arbitration awards under the Arbitration and Conciliation Act of India. It covers key parts of the Act related to New York Convention awards and Geneva Convention awards. For NY Convention awards, it outlines the conditions for an award to be considered foreign and enforceable in India, including the evidence required and grounds for refusing enforcement. It also discusses the conciliation process in India, including commencement of proceedings, appointment of conciliators, their role and flexibility in procedures.
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docxedmondpburgess27164
Show Me My Money (Reisenfeld & Company v. The Network Group Inc., p. 313)
Why does the court see this case as involving a quasi-contract as opposed to an actual contract? What other case law does the court rely on in finding precedent/support for compensating Reisenfeld? Does this decision appear to follow the golden rule guideline set forth in Chapter 2 (pp. 27 and 28)? Describe another example of an implied-in-fact or quasi-contract that you have experienced or is mentioned in the text.
Note: please read all the information correctly before you begin the assignment I have also copy and paste pages 27 and 28 that you would need to complete the assignment.
CASE
13-3
REISENFELD & CO. v. THE NETWORK GROUP, INC.;
BUILDERS SQUARE, INC.; KMART CORP. U.S. COURT OF APPEALS FOR THE SIXTH CIRCUIT 277 F.3d 856 U.S. App. (2002)
Network Group (“Network”) was contracted by BSI to assist in selling or subleasing closed Kmart stores in Ohio. A few years later, Network entered into a commission agreement with Reisenfeld, a real estate broker for Dick's Clothing and Sporting Goods (“Dicks”). Dicks then subleased two stores from BSI. According to executed assignment and assumption agreements signed in November of 1994, BSI was to pay a commission to Network. Network was then responsible, pursuant to the commission agreement with Reisenfeld, to pay a commission of $1 per square foot to Reisenfeld. There was no direct agreement made between BSI and Reisenfeld.
During this time, Network's sole shareholder was defrauding BSI. This shareholder was convicted of several criminal charges stemming from his fraudulent acts. Network was ordered by the district court to disgorge any commissions received from BSI, and BSI was relieved of any duty to pay additional commissions to Network. As such, Reisenfeld never received his commission related to the Dicks sublease.
Reisenfeld sued in state court for the $160,320 in commissions he had not been paid. In addition to suing Network, Reisenfeld also named BSI as a defendant. The suit alleged, among other things, that based on a theory of quasi-contracts, BSI was jointly and severally liable for the commission.
JUDGE BOOGS: . . .
A contract implied-in-law, or “quasi-contract,” is not a true contract, but instead a liability imposed by courts in order to prevent unjust enrichment. … Under Ohio law, there are three elements for a quasi-contract claim. There must be: (1) a benefit conferred by the plaintiff upon the defendant; (2) knowledge by the defendant of the benefit; and (3) retention of the benefit by the defendant under circumstances where it would be unjust to do so without payment. …
There is no disagreement as to the first two requirements. It is clear that Reisenfeld's work as broker benefited BSI and that BSI was aware of the work Reisenfeld was doing. The disagreement rests on the third requirement—whether it would be unjust for BSI to retain the benefit it received without paying Reisenfeld for it. … U.
The interphase between the english national arbitation lawsValentine Ataka
This document discusses procedural issues relating to arbitration under the English National Arbitration Laws, the New York Convention, and the Rules of the London Court of International Arbitration.
It addresses pre-arbitration, during arbitration, and post-arbitration procedures. Pre-arbitration issues include establishing a dispute under the contract, identifying the dispute resolution forum, required negotiations, and initiating arbitration. During arbitration, key procedural matters are appointing arbitrators, conducting hearings, maintaining confidentiality, and applying for interim orders. Post-arbitration, the document discusses challenging awards and enforcement.
This document summarizes a legal paper about implied terms in building contracts. It discusses the following key points:
1) Historically, courts were reluctant to modify commercial contracts but would imply terms through legal fiction to address unfair bargains in building contracts.
2) The landmark case The Moorcock established that implied terms are based on the presumed intentions of parties to give business efficacy and prevent failure of consideration.
3) The paper examines how courts distinguish between terms implied by fact and those implied by law, with a focus on construction contracts. It traces the development of this area of law over time.
Aspects of contract and negligence for businessNovoraj Roy
Law identified with business can be finished up as all the law which applies to the rights,
relations and behavior of people and organizations occupied with trade, marketing, exchange,
and deals. This report calls attention to the Essential Elements required for the Formation of a
contract, the distinctive sorts of agreements and their effects.
The Hon'ble Supreme Court in the case of Afcons Judgment has interpreted Section 89 of CPC. In the said judgment Hon'ble Supreme Court has laid down what the referral judge is supposed to do while referring the case for any Alternative Dispute Resolution (ADR). New Mediation Rules come into existance in the year 2015. Wherein also provisions for referral judges are made. This ppt will help Hon'ble Judges to refer cases for Mediation. This document also speaks about Lok Adalat, Conciliation, Arbitration and Judicial Settlement and intricacies involved therein.
Assignment #12 -hajer al rubaiai ( business) (1)projectname
This document provides an overview of business contracts and torts under Omani law. It analyzes two legal cases. The first case involves a singer, Mr. Badar, who failed to attend required rehearsals for a musical performance due to illness. The event organizer, Mr. Yosuf, terminated their contract. Analyzing Omani contract law, the termination was likely valid as Mr. Badar broke a key term of the agreement. The second case involves a construction dispute that raises issues of negligence and liability. The document provides advice to each party based on the relevant Omani laws.
The document discusses different approaches to claims management in construction contracts. It describes observing two schools of thought within contractor organizations: a production side focused on execution and viewing contractual rules as hindrances, and a contracts department seeking opportunities to claim in order to recoup losses. The author reflects on behaving similarly as a young site manager and later as a claims manager focused on claiming. Through experience, the author's views have changed and the document shares lessons learned, advocating that contractors should always submit timely notices of claim when issues arise to protect their rights, rather than hesitating, as delayed notices can increase losses or result in lost entitlements. Effective claims specialists are important to properly support claims submissions and discussions should focus on notice timing rather than questioning
Eo1008 creating arbitration machinery for phil cons.industryjbonvier
The document establishes an arbitration commission for the Philippine construction industry. It creates the Construction Industry Arbitration Commission (CIAC) to settle disputes arising from construction contracts. The CIAC will have jurisdiction over voluntary arbitrations and will be composed of a chairman and two members appointed by the Construction Industry Authority of the Philippines. It will formulate arbitration rules and procedures and appoint arbitrators to settle disputes in the construction sector.
This document summarizes a seminar on construction adjudication. It discusses the differences between contractual and statutory adjudication, features of statutory adjudication like being fast, temporary binding decisions, and recent cases interpreting security of payment legislation. A recent Malaysian case found that pay-when-paid clauses are void and security of payment laws can apply retrospectively to existing contracts unless the legislation clearly states otherwise. The seminar provides tips for contractors in adjudication.
This document discusses hardship clauses in contracts and whether they can effectively address unforeseen difficulties that arise during contract performance. It provides three key points:
1) Hardship clauses currently only require parties to meet and negotiate if difficulties arise, but do not obligate reaching an agreement. They provide no alternative like termination if negotiations fail.
2) Past arbitration cases have rejected hardship claims as an attempt to avoid onerous performance, as all contracts assume future risk.
3) Hardship clauses may work if they confer revision powers on arbitrators and clearly define hardship events, or allow termination if no alternative terms are agreed. Their effectiveness depends on being well-drafted.
This executive order creates an arbitration commission for the Philippine construction industry. The order establishes the Construction Industry Arbitration Commission (CIAC) to settle disputes arising from construction contracts. The CIAC will have original and exclusive jurisdiction over disputes involving both government and private construction contracts. The order outlines the composition, functions, and authority of the CIAC to appoint arbitrators, collect fees, and make final and binding rulings on contract disputes in the Philippine construction sector.
Alternative dispute resolution: Interim MeasuresRittika Dattana
This document provides an overview of interim measures in arbitration proceedings under the Indian Arbitration and Conciliation Act of 1996. It defines interim measures as temporary relief granted pending the final resolution of a dispute. Section 9 of the Act allows parties to approach courts to seek interim measures to preserve assets or evidence. The document discusses the types of interim measures available, including injunctive relief, attachment orders, and appointing receivers. It analyzes the scope of interim measures under Section 9 and their purpose of safeguarding parties from harm due to delays in the arbitration process.
Similar to IJAA Vol 7 No. 2 - Hazem Hussein - (20)
1. TABLE OF CONTENTS
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
1
International Journal of Arab Arbitration
< <
Volume 7 - No. (2) 2015
Table of Contents
Page
#46+%.'5
- Arbitration in the Dubai International Financial Center – By Natasha Bakirci,
Mahika Hart, Reza Mohtashami and Shamlan Al Sawalehi ................................................... 5
- The Requirements for an Effective Multi–Party Arbitration Clause in Construction
Contracts–By Hazem Hussein.......................................................................................................... 15
#4$+64#6+10Ō4'.#6'& &'%+5+105 +557'& $; 56#6' %17465 +0
#4#$ ,74+5&+%6+105
'I[RVKCP %CUG .CY
- Cairo Court of Appeals – 62 Commercial Area –Appeal No. 14 of the year 130 –
Session of 10 September 2014 Arbitral Award – Dissenting Opinion –
Challenge Against the Award – Alleged Non-Application of the Law Agreed Upon
by the Parties by Disregarding Egyptian Law No.112/1985 – Dissenting Opinion
not Included in the Award – Egyptian Law as Applicable Law – Arbitral Tribunal
Applied Egyptian Law No.43/1979 – Egyptian Law Duly Applied – No Power for the
Court to Rule on the Correct Application of the Egyptian Law – Signature of the
Majority of the Arbitrators Sufficient for the Validity of the Award – Inclusion of the
Dissenting Opinion not Required – Challenge Dismissed....................................................... 21
+TCSK %CUG .CY
- Federal Court of Cassation, Decision No. 112/B/2013 – 18 November 2013
Arbitral Award – Request for Confirmation Before the Commercial Court of First
Instance – Request Dismissed – Court’s Decision to Set Aside the Award Instead
Based on Article 272 of the Iraqi Arbitration Law – Award Rendered Without
Supporting Evidence – Material Procedural Default – Award Exceeding the Scope
of the Arbitration Agreement – Appeal Before the Federal Court of Appeals in
2. TABLE OF CONTENTS
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
2
Bagdad – Alleged Misapplication of the Law by the Court of Appeals – Court of
Appeals Having Duly Applied the Law – Appeal Dismissed – Challenge of the
Appeal Decision Before the Court of Cassation – Challenge Dismissed........................... 27
-5# %CUG .CY
- Board of Grievances – Commercial Court of Appeals (undated) Consultancy and
Design Agreement – Arbitration Clause – Rules of Arbitration of the Saudi Council of
Engineers – Cancellation of the Agreement – Refusal by One of the Parties to
Appear Before the Saudi Council of Engineers – Recourse to the Commercial Court
of Appeals – Request to Refer the Parties to Arbitration – Relationship Between the
Parties not Commercial – Lack of Jurisdiction – Request Dismissed.................................... 29
.GDCPGUG %CUG .CY
- President of the Court of First Instance in Beirut – Decision 13/46 – 30 March 2015
Arbitration Agreement – Ex Aequo Et Bono Arbitration – Sole Arbitrator – No
Agreement Between the Parties on the Sole Arbitrator – Obstacles as to the
Appointment of the Sole Arbitrator – Jurisdiction of the President of the First
Instance Court in Beirut Under Article 764 of the Lebanese Code of Civil
Procedure – Encountered Obstacles Not Affecting the Validity of the Arbitration
Agreement – Obstacles not Due to the Ambiguity of the Arbitration Agreement –
Appointment of the Arbitrator by the President of the First Instance Court....................... 31
6WPKUKCP %CUG .CY
- Tunis Court of Appeals – Case No.1003053 – Session of 7 November 2013
Distribution Agreement Relating to a Tunisian Trademark – Arbitration Clause –
Request for the Extension of the Arbitration Clause to Include Several Companies
Before the Tunis Court of Appeals – The Companies’ Alleged Participation in the
Formation and Execution of the Contract – Arbitral Tribunal’s Exclusive
Jurisdiction Regarding the Extension of the Arbitration Clause to Third Parties –
Request Dismissed............................................................................................................................... 35
7#' %CUG .CY
- Dubai Court of Cassation – Challenge No. 212 in 2014 – Civil Session of 8
January 2015 Institutional Arbitration – Dubai International Arbitration Center
(DIAC) – Arbitrator’s Immunity – Arbitrator’s Issuance of the Award Outside the
Arbitration Time-Limit – Action for Liability Against the Arbitrator Before the Dubai
Merits Courts – Action Dismissed by the First Degree Courts – Recourse to the
Dubai Court of Cassation – Principle of the Immunity of the Arbitrator Under Article
24 of the DIAC Statutes – Exception in Case of Gross Professional Fault or
Excessive Negligence – Estimation of the Gross Professional Fault within the
Discretionary Powers of the Merits Courts – None Established – Action Dismissed..... 41
3. TABLE OF CONTENTS
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
3
#4$+64#. #9#4&5 4'0&'4'& 70&'4 6*' #752+%'5 1(
#4$+64#. +056+676+105
- ICSID Award – Case No ARB/11/33 – 3 November 2015 – Adel Hamdi El Tamimi
against Sultanate of Oman Investment Agreement Between Two Companies
Owned by Adel El Tamimi (An American Citizen) and an Omani State Entity for
Extraction of Stone Materials – Lease Agreement Between One of the Two
Companies and the State Entity – Works Completed – Termination by the State
Entity of both Agreements – Recourse to ICSID Arbitration Against the State of
Oman on the Basis of a Convention Between Oman and the USA – Convention’s
Effective date Being 1 January 2009 – Convention Applicable the Termination of
the Investment Agreement – Requirements for the State to Be Liable for the Acts
of One of its Entities – Effective Supervisory or Administrative Powers – Not
Satisfied – State of Oman not Liable for the State Entity’s Acts. Commentary by
Hady Slim................................................................................................................................................. 45
#4$+64#6+10 0'95
I. Updates on New and Recent Laws, Cases and State Activities........................................... 243
II. Conferences, Trainings and Seminars.......................................................................................... 246
III. Miscellaneous News about Lawyers, Law Firms and Other Institutions......................... 247
IV. Books, Articles and Other Publications....................................................................................... 248
4. ARTICLES
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
15
6JG 4GSWKTGOGPVU HQT CP 'HHGEVKXG /WNVK2CTV[
#TDKVTCVKQP %NCWUG KP %QPUVTWEVKQP %QPVTCEVU
$[ *CGO *WUUGKP∗
Disputes arising from construction agreements usually encounter multiple
contentions, claims, and parties, which are very apt to avail from the well organized nature
of the arbitration proceedings. In order to accomplish the advantages sought in the view of
the disputing parties, an arbitration agreement has to be properly drafted. This is in order to
encompass all the potential disputes between all the related parties to the construction
project under the ambit of one proceeding.
The contractor may find himself in an odd position if the obligations owed by him
according to the main contract are different from the obligations of the subcontractor
according to the corresponding subcontract. In order for the contractor to mitigate the risks
arising from this situation, he may enter into a 'back-to-back agreement' with the
subcontractor. This is where the subcontractor will be obliged to observe all the
obligations of the contractor in his relation with the client with regards to the parts of the
project which have been entrusted by the contractor to the subcontractor.
The contractor may fail, in some instances, to enter into a ‘back to back agreement'
with the subcontractor. This may occur in situations where the subcontracted party is
required for a very technical obligations which other subcontractors are incapable of
delivering. In this case, the subcontractor may be in a strong negotiating position which
will enable him to negotiate and deny the ‘back-to-back agreement'. Additionally, the
contractor may fail to impose the ‘back-to-back agreement’ on the subcontractor if he is
nominated or designated by the client. In such a case, the Contractor may be rendered
liable before the Employer if there are differences between the provisions governing the
obligations of the subcontractor under the main contract and the same provisions under
the corresponding subcontract.
∗ PhD in Law – Senior Associate, Al Tamimi Co, Qatar.
5. ARTICLES
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
16
Each contract, either the main contract and/or the subcontract, should contain an
independent dispute resolution clause. If a dispute arises from the subcontract, then a
dispute may arise between the client and the contractor and another dispute may arise
between the contractor and the subcontractor. With regard to the first potential
proceedings, any award resulting from such proceedings shall not be binding on the
subcontractor.
For instance, if the arbitral award rules that the subcontracted part of the works has
been inappropriately executed by the subcontractor, then the tribunal may order the
contractor to provide the client with an adequate remedy or compensation pursuant to the
provisions of the main contract. If the subcontractor refuses to comply voluntarily with the
award, then the contractor will have no choice but to file an arbitration case against the
subcontractor under the dispute resolution clause mentioned in the subcontract. However,
the arbitral tribunal, constituted under the subcontract, is free to adopt a new factual and
legal position regarding the case before it. This is only if the findings reached by the
arbitral tribunal are different to those that have been constituted under the main contract.
Therefore the tribunal constituted under the subcontract may decide that the subcontractor
has satisfactorily fulfilled its contractual obligations under the subcontract. This decision
will be in contrary to the previous decision rendered by the tribunal, constituted under the
main contract, which considered that the subcontracted part was improperly executed. In
this scenario, the contractor shall be compelled to indemnify the client and remain without
any relief or remedy from the subcontractor. Even the ‘back-to-back agreement’ in this
assumption will not avail the contractor.
From the other side of the spectrum, the subcontractor may be in a similar position to
the contractor. For example, the subcontractor may file an arbitration case against the
contractor to request for financial claims resulting from prolongation costs or any other
reason. If the tribunal upheld the subcontractor’s claims, then the contractor will be
obligated to indemnify the subcontractor even if the default of the contractor was
attributable to the client. At this time, the contractor will require to be reimbursed by filing a
case against the client. The arbitral tribunal composed under the main contract may adopt
a totally different approach other than the award rendered by the tribunal constituted under
the subcontract.
In order to dispel all problems that may arise from the above situations, the best
solution would be to have a sole arbitration proceeding where all the disputants are
gathered under the ambit of one arbitral tribunal. This optimal solution will secure the
consistency of all the relevant awards and will resolve all the disputes among all the
contentious parties in one case. This will also have the benefit of saving time and money.
However, in order to do so, all three parties (client, contractor and subcontractor) agree to
submit to such arbitration proceedings. Essentially, third parties cannot be compelled to an
6. ARTICLES
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
17
arbitration to which they did not agree pursuant to the underlying arbitration clause in
accordance with the principle of the privity of contracts. Therefore, it is ultimately difficult
for the contractor to obtain the consent of both the client and the subcontractor to submit to
a sole arbitration procedure.
The client will also be reluctant to give his consent to the same arbitration procedure
with the contractor and the subcontractor. The client may justify his refusal by his
reluctancy to enter into any direct and legal relationship with the subcontractor.
Additionally, the client may not wish to enter into such proceedings in order not to consider
this as a limitation for the contractor’s liability under the main contract.
For the subcontractor, the acceptance for the multi-party arbitration is heavily
dependent on the leverage the contractor may have on the subcontractor. In fact, the
subcontractor is generally only concerned with the scope of the subcontract alone and
therefore may not wish to involve himself with further complexities arising from the entire
project which might result from the main contract.
In light of the above, should the contractor wish to include an arbitration clause
that would alleviate the risks the latter may encounter from the dual relationship
between the client and the subcontractor, such clause should take into consideration
the following:
1) It is recommended that the arbitration be conducted under the auspices of an
internationally recognized arbitration Center. As this type of arbitration is
complicated enough to the extent that necessitates the management of the
arbitration case by an independent and well-established independent body.
2) The subcontractor shall undertake to help the contractor in providing any
substantial documents or relevant information to the contractor to assist the latter
in substantiating his arguments against the client.
3) If there is an arbitration dispute between the contractor and the client, and the
contractor believes that such dispute is pertaining to the subcontract, then the
contractor may be eligible to request from the subcontractor –in writing – to
participate in the appointment of an arbitrator. This arbitrator will sit on the tribunal
constituted under the arbitration clause of the main contract.
It would be advantageous for the subcontractor to agree to the contractor's
proposal. Should the subcontractor refuse to cooperate with the contractor in
this scope, then the factual and legal findings of the tribunal constituted under
the main contract relating to the subcontract relationships would bind the
7. ARTICLES
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
18
contractor, the subcontractor and the tribunal which may be constituted under
the provisions of the subcontract.
Accordingly the subcontractor may be ordered by the tribunal, constituted under
the subcontract, to render the contractor not responsible for any compensation that
was paid by the latter to the client in execution of the award, which had been
rendered by the tribunal constituted under the main contract. This occurs if such
tribunal realized that the subcontractor has defaulted in the execution of the
subcontract. Conversely, the contractor shall be obligated to compensate the
subcontractor with any payments which he would have received from the client
regarding the part of the project entrusted to the subcontractor in the application of
the arbitral award rendered under the main contract.
The fourth point deals with the situation where the arbitration proceedings have
commenced between the contractor and the subcontractor and where, on any
party's request, the tribunal would find that the dispute relates to the rights and
obligations in the main contract. In this situation, if the tribunal agrees to this
request, it shall be authorized to stay the procedure for the related part of the
proceedings. They will be stayed until such time as it takes for the arbitral tribunal
to be composed under the main contract and has rendered a final award on this
question. The contractor shall then be given a short period to begin the arbitration
proceedings against the client. If no proceedings are initiated by the contractor
before the end of such period, the arbitral tribunal constituted under the
subcontract would resume the proceedings and render its award.
4) The last point of this arbitration agreement relates to the case where the
subcontractor, who did not initiate arbitration proceedings under the subcontract,
requests the contractor to make a claim against the client. In this case, the
contractor may choose between two alternatives. The first alternative is that the
contractor may honor the subcontractor's request. In this case, the arbitrator who is
supposed to be appointed by the contractor, shall be actually selected by the
subcontractor or at least by a joint decision from the contractor and the
subcontractor. The second alternative is that the contractor may refuse the
subcontractor's request and accordingly the contractor would have to pay a
suitable remedy for the subcontractor regarding his thwarted claim. In order for the
contractor to avoid that, he will need to justify that his refusal to initiate any
arbitration proceedings against the client is reasoned by the fact that the
subcontractor's claim is not sufficiently substantiated.
Although an arbitration clause between the client and the main contractor is not
binding upon the subcontractor for being a third party thereto, an arbitral award, rendered
8. ARTICLES
International Journal of Arab Arbitration, Volume 7, N°2 - 2015
19
based on an arbitration clause that has been agreed between the client, main contractor
and the subcontractor is valid by virtue of the principle of party autonomy.
Therefore, nothing would preclude the contractor and the subcontractor from agreeing
mutually in the subcontract that the arbitral award, which may be rendered under the
provisions of the main contract, should be binding to their relationship. Therefore, all the
factual and legal findings that have been reached by the tribunal appointed to decide the
dispute between the client and the contractor shall be binding to the tribunal appointed to
decide the dispute between the contractor and the subcontractor.
Consequently, if the tribunal under the main contract decided that the contractor is
responsible to compensate the client for the contractor’s default of his execution, then the
contractor may agree with the subcontractor that the latter shall indemnify the contractor
for any compensations he has paid to the client for his default in executing his obligations.
This will be the case if such default is attributable to the subcontractor in executing his
obligations under the subcontract.
On the other hand, although the subcontractor has no legal or contractual ties with the
client he may, contractually, be entitled to request from the contractor that he will be
reimbursed with any indemnities that have been received by the contractor from the client.
This will be in the execution of the subcontract pursuant to the award rendered by the
tribunal constituted under the main contract.
In order to put such consequences in the appropriate legal framework, the contractor
has to, legally, enable the subcontractor to defend his claims against the client in the same
capacity as if he is a party to the dispute against the client. Accordingly, the subcontractor
has to contribute in the appointment of the arbitrator selected by the contractor under the
main contract. He must be authorized to address all the factual and legal points which are
necessary to substantiate his claims. If all the pre-mentioned conditions are met, then the
contractor will avoid any potential blame from the subcontractor if the contractor has been
ordered to compensate the client regarding the part of the project which has been
entrusted to the subcontractor. Conversely, the contractor shall be blameless if the
subcontractor’s claims have been denied by the tribunal appointed under the main
contract.
Taking into consideration the contractor’s relationship with both the client and the
subcontractor, the proposed terms of a standard arbitration clause for such a relationship
will ensure a fair and equitable settlement procedure to both the contractor and the
subcontractor. Therefore, this clause may aid a smoother implementation of the project in
the interest of the involved parties.