SlideShare a Scribd company logo
1 of 51
Tran Trung Tuyen (Song Bung 4 HPMB)
Takafumi Kadono (ADB)
Song Bung 4 Hydropower Project Case Study
Presented at the
IHA 2013 World Congress
.
CASE STUDY FROM SONG BUNG 4
HYDROPOWER PROJECT – VIET NAM
Kuching 23rd May, 2013
Tran Trung Tuyen Takafumi Kadono
Song Bung 4 HPMB Energy Specialist-ADB
A. INTRODUCTION
Project site
Vu Gia-Thu
Bon Basin
Mapping of Project Location
Project General Layout
Overview Layout
RCC Dam 114mReservoir
Tunnel 3.2km
Power
house
Project Key Features and Time Schedule
 InstalledCapacity:156MW
with two Francis turbines
78MW each. Annual
Output: 586.25 GWH
 Reservoir: Surface Area
15.8 km2; FSL 222.5m.
Gross Vol:510,8 MCM
 Dam: RCC (about 800.000
m3), 114m high, crest
length 345m, CVC
Diversion Culvert 5mx9m.
 Headrace Tunnel: 3.2km,
inner diameter: 7.2m
Construction Progress
 Commencement: June 2010
 River Closure: Jan 2012
 Impoundment: Aug 2014
 Unit 1 Completion: 10/2014
 Unit 2 Completion:12/2014
Resettlement
 4 Villages, 253 Household
and 1041 People Relocated.
 First Relocation: Oct 2012
 Completion of all Relocated
Sites: Quarter III 2013.
B. WORKING WITH AFFECTED PEOPLE
MAPPING OF 4 RESETTLEMENT SITES
When we did: since 2006 following FS
approved by GoV, ADB provided TA and
fielded Consultant for PPTA.
 Where we did: Project affected land,
Reservoir, upstream and downstream.
 What we did: Conducting full survey
and consultation with AP to identify
best approach and to develop AP -
included program.
 How we did: by applying bottom up
method and by working together
towards the same objectives through
a transparent information and full
participatory by APs
Project Preparation
Survey Team
Old Thon 2
Pre-Project Situation
• Mainly dominance by
Co Tu Ethnic Minority.
• Limited Access and
livelihood activities
• Low level of literacy
and lack of health care
and public facilities.
• High incidence of
poverty. Self demand
and supply with limit
use of cash.
Traditional Guol House of CoTu Ethnic
Typical House made of Bamboo and Leaf
• Identify loss of land
and asset for support
and compensation
• Ensure AP rights on
land resources
allocation.
• Prepare Livelihood
Restoration for APs
• Provide trainings and
guidance for APs
recapturing normal
life and familiarizing
with change of life.
Components in Preparation
Slash&burn rotation
Old School
Hunting
PIB in Cotu
Institutional Arrangement
ADB , NGO, POE
and Province
Authority
PMB including
Contractor and
Consultant
RMIU at District
Level
VRDG at
Villages Level
APs ,
Community
mobilizer and
facilitator
AP supported by local Community
Mobilizer and local Facilitator takes
core position in all relocation related
activities
VDRG as a direct bridge with AP to
participate actively in all stage of
implementation.
RMIU to review compliance on
policy of compensation and support;
provide support on administration.
PMB from listening to and
understanding about AP, develop a
comprehensive and AP-based
resettlement plan.
ADB, POE, NGO, independent
Consultant... overseeing compliance
and application.
Criterion Decree 197/2003 & Land
Law
ADB Policy
Consultation Not specified. APs fully informed & consulted;
participatory; public disclosure.
Compensation for non-
titled land and assets
Not compensated. Compensated at market value.
Compensation for
economic displacement
Not compensated. Compensated for loss of
livelihood activities, access.
Compensation value Based on residual cost. Based on replacement cost w/o
deduction of salvaged materials;
incl. taxes & fees.
Support for significant
impact
AP losing >30% of
agricultural land entitled
to assistance for 3-6
months .
AP losing > 10% productive
land/asset entitled to
restoration of income and
livelihood.
Consideration for
women & vulnerable.
No specific provision but
poor APs are to be
supported by PPC.
Assistance for improvement;
gender-responsive
Major Policy Differences
Working with APs
• Public Regular meetings
and Consultation for
explanation of project and
AP entitlement
• Encouraged and empower
APs active participation.
• Listened to AP expectation
and put into design, plan
and implementation.
• Defined necessary support
and livelihood restoration
suited to AP wish. AP voiced up opinion
Meeting with
AP in progress
Meeting with APs and Local Community
With local officer
Joined Team at field
Addressing AP concern
Downstream Survey
APs Participation
• Get AP involved into all process
• Joint conduct of DMS, Selection of
Resettlement Site, Sample of Layout
and House….
• Public Consultation with AP’s
participation.
• Making own house and community
facilities. Monitoring entire program.
• APs shaped their expected
perspectives in a new life.
Entitlement Matrix
Items at New RS For Areas
Housing Plot and
adjacent Garden
Household 400-600m2
Production Land HH 1.5 ha
Public Wet Rice Field Relocated
Sites
11 ha
Community Agro -
Forest Land for NTP
HH 8 - 10 ha
Construction of
housing size
HH 40 – 65 m2
Kitchen, bath room,
toilet…facilities
HH 22 m2
Public Facilities including access road, domestic
water & power supply, school, medial station,
cultural house, wet rice irrigation, administrative
zone as appropriate to all relocated sites.
Compensated and Support made at
replacement cost by cash on the basis of
Support Provided Training Provided
Create Job & change of
Career, Poverty Reduce
Agricultural
Development
Stabilizations of Live:
food, protein, health
care, fuel…
Develop Rearing:
domestic cattle&
poultry, fisheries
Agriculture Production:
Seedlings, fertilizer,
pesticide, caring..
Non-Farming
Activities: hair cut,
carpenter, knitting
Stock Rearing: Pig, cow,
chicken..
Health Care, HIV,
human trafficking,
Reforestation for
production and NTPs
Nutrient for
Children & Woman
Technical assistance,
method of production,
trading and commercial
Capacity building,
Literacy demolition,
Monitoring works
Others: Moving, grave,
worshiping, visiting
Driving, repairing
motorbike…
Finalization of REMDP
• Comprehensive document
covering various issues and
aspects with incorporation of
APs desires and concerns.
• Supported by Gender Action
Plan; Social Management Plan
• Updated and developed
regularly along the time
• JFPR as a plus focusing on
vocational training, providing
seedlings & livestock, capacity
building, health care , enhance
awareness to APs for new life
REMDP
Implementation in progress
• Conducting DMS and
Selection of Resettlement
Site with participation of
local APs especially women.
• Public Disclosure of Matrix
Design and Planning .
• Gathering feedback and
comment for revision. Woman participates in DMS at field
Inventory Asset on Land
Public Disclosure at Village
• Selection of resettlement
Site and Production land
• Site clearance and
Monitoring from APs
• Access to forest for hunting,
foods and NTP collection.
Implementation in progress
Woman participates
construction monitoring
Combined Team in the forest
New RS under
Clearance
Implementation in progress
Disclosure on compensation in
participation of men and women
AP gathers up for consultation
Seeking for Expected Resettled Sites
Reaching final agreement
• Compensation and
Support Payment.
• Advising APs to put
monies at Bank for saving.
• Both wife and husband’s
name appears in all papers
Implementation in progress
Woman opens
separate bank
account
Get compensated in spouses
Papers in the name of husband and wife
• Construction of Public
Facilities including
health care station,
school, power supply,
access road, domestic
water system…
Implementation in progress
School at new RS
School under construction
Health Center at new RS
Weekly meeting in RS including VRDG,
SB4, Contractor, ADB consultant
After Relocation
Individual house at new
RS
Community Hall for Public Activities
Overview to a village. • APs build their own
house and Guol house
under their choice &
traditional style.
• Land Use Certificate
under name of spouse.
A new life begins
A view at New Resettlement Site
Traditional Guol and Community Court
Typical
new
house
built by
AP
Collection of rattanVehicle accessible
Restoration After Relocation
Wet rice development Traditional
Knitting at
home
Fish Pond
House Gardening
Emerging of Challenges
• Conflict of interest within family.
• Abuse of Alcohol; Driving
motorbike; Using modern home
appliances and facilities.
• More vulnerable by social
impacts from contacting with
outer world.
• Long term financial management
• Maintaining traditional culture.
• Stable restoration of livelihood
activities.
PMB is continuing
with APs for
sustainable
development by
extending more
efforts on:
 Training AP towards
new life and career.
 Providing further
supports.
 Improving APs
awareness and
capacity.
 Sharing knowledge
and benefit…
Respecting and maintaining locally social and
cultural characteristic.
Well preparation with design factoring much
traditionally cultural settings and tailoring to
AP’s expectation.
Encouraging and Empowering APs to actively
participating throughout all stages.
Applying bottom up approach and making APs
core part of Project in a long run.
High consensus from AP towards project
objectives by Working with Affected People.
C. LESSON LEARNED
THANK YOU FOR ATTENTION
.
.
.
,
.
Song Bung 4 Hydropower Project
Takafumi Kadono, ADB
Tran Trung Tuyen, SB4HPMB
23 May 2013
Resettlement
Livelihood Improvement (JFPR)
Civil Society Organization Collaboration
Basin Sustainability
ADB’s Hydropower Engagement
28
Song Bung 4 HPP Land Acquisition and
Resettlement Process
• Mobilizing and empowering APs from early stages;
continuous involvement.
• Meaningful consultation – not just ticking the box.
– Selection of resettlement site
– Design of resettlement site and own houses
– Discussion on livelihood restoration activities
– Bottom-up approach
• Community mobilization & additional livelihood
restoration support funded by Japan Fund for
Poverty Reduction (JFPR)
29
Song Bung 4 HPP Land Acquisition and
Resettlement Process
30
Old House Old House New House New Concrete House in
A Vuong HPP
Old Classroom New Classroom
Song Bung 4 HPP Land Acquisition and
Resettlement Process
• Gender-responsive.
– Women have been empowered to participate in consultation,
resettlement site selection and planning, DMS, compensation payment
– Half of VRDG members and extension workers are women
– Female village extension workers
– Livelihood restoration programs for women
– Farm and non-farm skills training for women (para-vet, plumbing, etc.)
– Improved maternal health care
– Separate bank accounts for men and women
• Application of ADB policies.
• ADB staff dedicated to LAR.
• Capacity building of PMB and local authorities.
31
JFPR 9120-VIE:Livelihood Improvement
of Vulnerable Ethnic
Minority Communities Affected by the
Song Bung 4
Hydropower Project in Quang Nam
Province
Japan Fund for Poverty Reduction
Objective and Activities
• Japan Fund for Poverty Reduction grant ($2 million) to
complement income restoration and for social preparation.
• Village Resettlement Development Group (2009)
– Consisting of representatives of affected persons (44% women).
– To develop awareness about entitlement, resettlement activities,
grievance redress mechanism, plan & implement resettlement,
design and implement livelihood programs.
– Meet every 2 weeks and monthly.
– Supported by JFPR Community Mobilizer.
• Village Extension Worker
– Community facilitator, village para-vet, agriculture, fishery, health.
– All both man and woman.
33
Objective and Activities
• Training and awareness program
– Health awareness, immunization, treatment of mosquito net, etc.
– Traffic safety
– HIV/AIDS and human trafficking
– Water management, irrigation, plumbing, forest protection
– Build awareness on use and maintenance of village infrastructure
• Livelihood Activities - Diversification
– Livestock (pig, chicken, duck, buffalo…)
– Agriculture (home garden, wet rice, improve traditional upland
farming…)
– Fishery, agro-forestry, industrial trees
– Non-farm income generating activities
34
Safeguard Policy Statement
(2009)
Safeguard Policy Statement (2009)
• Effective on 20 Jan 2010
• Consolidation of Previous Policies:
– Environment Policy (2002)
– Indigenous Peoples Policy (1998)
– Involuntary Resettlement Policy (1995)
• Ambiguities clarified
• Consistent with WB and IFC’s approaches
• Requirements tailored appropriately to different financing
modalities
• Strengthened monitoring and supervision
• Country Safeguard Systems (CSS)
• Emphasis on capacity development in DMCs
36
Safeguard Policy Statement (2009)
• Overarching Objectives:
– Avoid adverse impacts of projects on the
environment and affected people, where possible;
– Minimize, mitigate, and/or compensate for adverse
project impacts on the environment and affected
people when avoidance is not possible; and
– Help borrowers/clients to strengthen their safeguard
systems and develop the capacity to manage
environmental and social risks.
37
Major Difference: Environmental Safeguards
Previous SPS
o Includes explicit
requirements on (i)
environmental
assessment process
o No equivalent
requirements on (ii)-
(v), while
environmental
assessment reports
examine these issues
in practice but often in
an ad hoc manner
Includes explicit policy principles and
requirements on:
i. environmental assessment process
ii. biodiversity protection and natural
resources management
iii. pollution prevention and abatement
iv. occupational and community health
and safety
v. physical cultural resources
Major Difference: Involuntary Resettlement Safeguards
Previous SPS
o The 1995 Policy does
not clearly define
policy scope and
triggers
The IR safeguards cover physical
displacements (relocation, loss of residential
land, or loss of shelter) and economic
displacements (loss of land, assets, access
to assets, income sources and means of
livelihoods) as a result of (i) involuntary
acquisition of land, or (ii) involuntary
restrictions on land use or on access to legally
designated parks and protected areas.
Major Difference: Involuntary Resettlement Safeguards
Previous SPS
o No equivalent
provision
If potential adverse economic, social, or
environmental impacts from project
activities other than land acquisition are
identified, they will be avoided, or at least
minimized, mitigated, or compensated for,
through the environmental assessment
process.
If these impacts are found to be significantly
adverse at any stage of the project, the
borrower/client will be required to develop and
implement a management plan to restore the
livelihood of affected persons to at least pre-
project levels or better.
Major Difference: Indigenous Peoples Safeguards
Previous SPS
o For projects involving
Indigenous Peoples,
initiatives should be
conceived, planned,
and implemented, to
the maximum extent
possible, with the
informed consent of
affected communities.
However, no specific
provisions on how to
operationalize this
concept.
The borrower and ADB will ascertain the
consent of affected IP communities to the
following three types of project activities:
o commercial development of the cultural
resources and knowledge of IP;
o physical displacement from traditional or
customary lands; and
o commercial development of natural
resources within customary lands under
use that would impact the livelihoods or
the cultural, ceremonial, or spiritual uses
that define the identity and community of
IP.
Major Difference: Indigenous Peoples Safeguards
Previous SPS
o No equivalent
provision
o The consent of affected Indigenous
Peoples communities refers to a collective
expression by the affected Indigenous
Peoples communities, through individuals
and/or their recognized representatives, of
broad community support for such project
activities. Broad community support
may exist even if some individuals or
groups object to the project activities.
o ADB will assure that broad community
support is demonstrated. ADB will not
finance the project if such broad support
does not exist.
Collaboration with CSO
Collaboration with CSO
Collaboration between ADB and CSO
• Policy level
• Country Partnership Strategy level
• Project level
Collaboration indicated in:
• Strategy 2020
• Public Communications Policy
• Accountability Mechanism
• Safeguard Policy Statement, etc.
44
Collaboration with CSO
Roles Performed by CSO
• Policy design and review
• Advocacy across a range of issues
• Information provider
• Consultation during project design
• Beneficiaries and stakeholders
• Co-financer
• Technical expert and trainers
• Implementing agency
• Monitoring and evaluation
45
CSO in Song Bung 4 HPP
• Service provider for livelihood development
under JFPR 9120-VIE.
• Independent monitoring.
46
Workshop organized by Vietnam Rivers Network
Basin Sustainability
Vu Gia – Thu Bon River Basin
Payment for Ecosystem Services (PfES)
• Benefit Sharing Mechanism supported through ADB TA
4689-VIE; piloted in A Vuong HPP – same Vu Gia - Thu
Bon basin as Song Bung 4 HPP.
• Suggested 2% of gross generation to finance Benefit
Sharing Fund for livelihood development.
• Decree 99 on PFES approved 2010.
• Hydropower plants pay VND20/kWh (¢0.1/kWh)
• $26 million collected in 2012, but disbursement to
households and monitoring challenging.
• ADB TA 6422-REG promotes (i) “household groups” and
(ii) GIS & remote sensing.
48
Rapid Basin-wide Hydropower Sustainability Assessment Tool (RSAT)
• Developed by ADB, MRC, WWF.
• Assess hydropower sustainability issues in a
basin wide, multiple project context.
• Assessment by stakeholders.
• Action orientated.
• Multi-criteria gap analysis.
• Scheduled for piloting in Vu Gia
- Thu Bon river basin (July).
(To be financed by Water Financing Partnership
Facility: WFPF)
49
Hydropower Operation Rules
• MoNRE tasked to prepare dry season operating
rules for hydropower reservoirs in the Vu Gia -
Thu Bon river basin.
• ADB providing support (financed by WFPF)
• ADB also supporting study on minimum flow
requirements.
50

More Related Content

What's hot

Idea of mainstreaming DRR plan within the Gram Panchayat development plan
Idea of mainstreaming DRR plan within the Gram Panchayat development plan    Idea of mainstreaming DRR plan within the Gram Panchayat development plan
Idea of mainstreaming DRR plan within the Gram Panchayat development plan MINTU DEBNATH
 
Comments on the Draft Plan and Sewers
Comments on the Draft Plan and SewersComments on the Draft Plan and Sewers
Comments on the Draft Plan and SewersGabrielleDondero
 
POST PROJECT EVALUATION REPORT
POST PROJECT EVALUATION REPORTPOST PROJECT EVALUATION REPORT
POST PROJECT EVALUATION REPORT03363635718
 
Introduction to cGanga - Namami Gange
Introduction to cGanga - Namami GangeIntroduction to cGanga - Namami Gange
Introduction to cGanga - Namami Gangecmmindia2017
 
Global Strategies For Water Sustainability in Baguio City
Global Strategies For Water Sustainability in Baguio CityGlobal Strategies For Water Sustainability in Baguio City
Global Strategies For Water Sustainability in Baguio CityMita Angela M. Dimalanta
 

What's hot (6)

Idea of mainstreaming DRR plan within the Gram Panchayat development plan
Idea of mainstreaming DRR plan within the Gram Panchayat development plan    Idea of mainstreaming DRR plan within the Gram Panchayat development plan
Idea of mainstreaming DRR plan within the Gram Panchayat development plan
 
Rebecca Williams, National Trust for Historic Preservation
Rebecca Williams, National Trust for Historic PreservationRebecca Williams, National Trust for Historic Preservation
Rebecca Williams, National Trust for Historic Preservation
 
Comments on the Draft Plan and Sewers
Comments on the Draft Plan and SewersComments on the Draft Plan and Sewers
Comments on the Draft Plan and Sewers
 
POST PROJECT EVALUATION REPORT
POST PROJECT EVALUATION REPORTPOST PROJECT EVALUATION REPORT
POST PROJECT EVALUATION REPORT
 
Introduction to cGanga - Namami Gange
Introduction to cGanga - Namami GangeIntroduction to cGanga - Namami Gange
Introduction to cGanga - Namami Gange
 
Global Strategies For Water Sustainability in Baguio City
Global Strategies For Water Sustainability in Baguio CityGlobal Strategies For Water Sustainability in Baguio City
Global Strategies For Water Sustainability in Baguio City
 

Similar to Case Study on Song Bung 4 Hydropower Project Resettlement Process in Vietnam

Community Based Adaptation as a Pillar of National Adaptation Efforts
Community Based Adaptation as a Pillar of National Adaptation EffortsCommunity Based Adaptation as a Pillar of National Adaptation Efforts
Community Based Adaptation as a Pillar of National Adaptation EffortsNAP Events
 
Brief document for CSA project team meeting 13 October 2013
Brief document for CSA project team meeting 13 October 2013 Brief document for CSA project team meeting 13 October 2013
Brief document for CSA project team meeting 13 October 2013 Soksophors yim
 
Theun-Hinboun Power Company Social and Environment Division
Theun-Hinboun Power Company Social and Environment DivisionTheun-Hinboun Power Company Social and Environment Division
Theun-Hinboun Power Company Social and Environment DivisionCPWF Mekong
 
Jharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.Sharma
Jharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.SharmaJharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.Sharma
Jharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.SharmaDr.Vijay Prakash Sharma
 
Community Event Slideshow
Community Event SlideshowCommunity Event Slideshow
Community Event Slideshowpnpgroup
 
NRM Innovations for Risk Management and Agricultural Transformation in Semiar...
NRM Innovations for Risk Management and Agricultural Transformation in Semiar...NRM Innovations for Risk Management and Agricultural Transformation in Semiar...
NRM Innovations for Risk Management and Agricultural Transformation in Semiar...World Agroforestry (ICRAF)
 
JHARKHAND-A village development model for rural India- DR. V.P.SHARMA
JHARKHAND-A village development model for rural India- DR. V.P.SHARMAJHARKHAND-A village development model for rural India- DR. V.P.SHARMA
JHARKHAND-A village development model for rural India- DR. V.P.SHARMADr.Vijay Prakash Sharma
 
Busiki Project.
Busiki Project.Busiki Project.
Busiki Project.beroya
 
Amy Hanna Downey Resume 4.5.2020
Amy Hanna Downey Resume 4.5.2020Amy Hanna Downey Resume 4.5.2020
Amy Hanna Downey Resume 4.5.2020Amy Hanna Downey
 
GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...
GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...
GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...UNDP Climate
 
Sustainable communities 2013
Sustainable communities 2013Sustainable communities 2013
Sustainable communities 2013Mike Allen
 
Role of NGO's in Sustainable Development (Sustainability in 21st Century)
Role of NGO's in Sustainable Development (Sustainability in 21st Century)Role of NGO's in Sustainable Development (Sustainability in 21st Century)
Role of NGO's in Sustainable Development (Sustainability in 21st Century)Gaurav Wadhwa
 
12. Working with local communities to protect the Maigue - Tom Harrington, Ma...
12. Working with local communities to protect the Maigue - Tom Harrington, Ma...12. Working with local communities to protect the Maigue - Tom Harrington, Ma...
12. Working with local communities to protect the Maigue - Tom Harrington, Ma...Environmental Protection Agency, Ireland
 
Can Household-Scale Biogas Support Rural Development? Insight from the Study ...
Can Household-Scale Biogas Support Rural Development? Insight from the Study ...Can Household-Scale Biogas Support Rural Development? Insight from the Study ...
Can Household-Scale Biogas Support Rural Development? Insight from the Study ...Purnama Alamsyah
 
Ethiopian Experience in Irrigatiion Development by Mr. Zena Habtewold Biru
Ethiopian Experience in Irrigatiion Development by Mr. Zena Habtewold BiruEthiopian Experience in Irrigatiion Development by Mr. Zena Habtewold Biru
Ethiopian Experience in Irrigatiion Development by Mr. Zena Habtewold BiruMalabo-Montpellier-Panel
 

Similar to Case Study on Song Bung 4 Hydropower Project Resettlement Process in Vietnam (20)

Community Based Adaptation as a Pillar of National Adaptation Efforts
Community Based Adaptation as a Pillar of National Adaptation EffortsCommunity Based Adaptation as a Pillar of National Adaptation Efforts
Community Based Adaptation as a Pillar of National Adaptation Efforts
 
Brief document for CSA project team meeting 13 October 2013
Brief document for CSA project team meeting 13 October 2013 Brief document for CSA project team meeting 13 October 2013
Brief document for CSA project team meeting 13 October 2013
 
Worldvision Ethiopia, Humbo Assisted natural regeneration project
Worldvision Ethiopia, Humbo Assisted natural regeneration projectWorldvision Ethiopia, Humbo Assisted natural regeneration project
Worldvision Ethiopia, Humbo Assisted natural regeneration project
 
Rcdc balangir
Rcdc balangirRcdc balangir
Rcdc balangir
 
Theun-Hinboun Power Company Social and Environment Division
Theun-Hinboun Power Company Social and Environment DivisionTheun-Hinboun Power Company Social and Environment Division
Theun-Hinboun Power Company Social and Environment Division
 
Jharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.Sharma
Jharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.SharmaJharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.Sharma
Jharkhand:A proposal for Village development( kanchiVillage). Dr. V.P.Sharma
 
Community Event Slideshow
Community Event SlideshowCommunity Event Slideshow
Community Event Slideshow
 
2012 team 8
2012 team 82012 team 8
2012 team 8
 
NRM Innovations for Risk Management and Agricultural Transformation in Semiar...
NRM Innovations for Risk Management and Agricultural Transformation in Semiar...NRM Innovations for Risk Management and Agricultural Transformation in Semiar...
NRM Innovations for Risk Management and Agricultural Transformation in Semiar...
 
JHARKHAND-A village development model for rural India- DR. V.P.SHARMA
JHARKHAND-A village development model for rural India- DR. V.P.SHARMAJHARKHAND-A village development model for rural India- DR. V.P.SHARMA
JHARKHAND-A village development model for rural India- DR. V.P.SHARMA
 
Busiki Project.
Busiki Project.Busiki Project.
Busiki Project.
 
Amy Hanna Downey Resume 4.5.2020
Amy Hanna Downey Resume 4.5.2020Amy Hanna Downey Resume 4.5.2020
Amy Hanna Downey Resume 4.5.2020
 
GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...
GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...
GCF Concept Note - Training-Workshop to Develop Concept Notes of Indigenous P...
 
Sustainable communities 2013
Sustainable communities 2013Sustainable communities 2013
Sustainable communities 2013
 
Role of NGO's in Sustainable Development (Sustainability in 21st Century)
Role of NGO's in Sustainable Development (Sustainability in 21st Century)Role of NGO's in Sustainable Development (Sustainability in 21st Century)
Role of NGO's in Sustainable Development (Sustainability in 21st Century)
 
Updated CV_Munge 2(1)
Updated CV_Munge 2(1)Updated CV_Munge 2(1)
Updated CV_Munge 2(1)
 
12. Working with local communities to protect the Maigue - Tom Harrington, Ma...
12. Working with local communities to protect the Maigue - Tom Harrington, Ma...12. Working with local communities to protect the Maigue - Tom Harrington, Ma...
12. Working with local communities to protect the Maigue - Tom Harrington, Ma...
 
Can Household-Scale Biogas Support Rural Development? Insight from the Study ...
Can Household-Scale Biogas Support Rural Development? Insight from the Study ...Can Household-Scale Biogas Support Rural Development? Insight from the Study ...
Can Household-Scale Biogas Support Rural Development? Insight from the Study ...
 
Ethiopian Experience in Irrigatiion Development by Mr. Zena Habtewold Biru
Ethiopian Experience in Irrigatiion Development by Mr. Zena Habtewold BiruEthiopian Experience in Irrigatiion Development by Mr. Zena Habtewold Biru
Ethiopian Experience in Irrigatiion Development by Mr. Zena Habtewold Biru
 
IAR&T Success Story
IAR&T Success StoryIAR&T Success Story
IAR&T Success Story
 

More from International Hydropower Association

IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...International Hydropower Association
 
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...International Hydropower Association
 
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...International Hydropower Association
 
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...International Hydropower Association
 
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...International Hydropower Association
 
IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...
IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...
IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...International Hydropower Association
 
IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
 IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ... IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...International Hydropower Association
 
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropowerIHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropowerInternational Hydropower Association
 
IHA 2013 World Congress: IGA: Renewable systems: sharing experience
IHA 2013 World Congress: IGA: Renewable systems: sharing experienceIHA 2013 World Congress: IGA: Renewable systems: sharing experience
IHA 2013 World Congress: IGA: Renewable systems: sharing experienceInternational Hydropower Association
 
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?International Hydropower Association
 
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...International Hydropower Association
 
IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...
IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...
IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...International Hydropower Association
 
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...International Hydropower Association
 

More from International Hydropower Association (20)

IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
 
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
 
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
 
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
 
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
 
IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...
IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...
IHA 2013 World Congress: GDF Suez: Climate change: Four dimensions for hydrop...
 
IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
 IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ... IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
 
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropowerIHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
 
IHA 2013 World Congress: IGA: Renewable systems: sharing experience
IHA 2013 World Congress: IGA: Renewable systems: sharing experienceIHA 2013 World Congress: IGA: Renewable systems: sharing experience
IHA 2013 World Congress: IGA: Renewable systems: sharing experience
 
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
 
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
 
IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...
IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...
IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of De...
 
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
 
Gil Maranhão Neto, GDF SUEZ
Gil Maranhão Neto, GDF SUEZGil Maranhão Neto, GDF SUEZ
Gil Maranhão Neto, GDF SUEZ
 
Rikard Liden, World Bank
Rikard Liden, World BankRikard Liden, World Bank
Rikard Liden, World Bank
 
Ricardo Krauskopf Neto, Itaipu
Ricardo Krauskopf Neto, ItaipuRicardo Krauskopf Neto, Itaipu
Ricardo Krauskopf Neto, Itaipu
 
Cameron Ironside, IHA
Cameron Ironside, IHACameron Ironside, IHA
Cameron Ironside, IHA
 
Valdineuza do Nascimento Borges, CPPT Cuniã
Valdineuza do Nascimento Borges, CPPT CuniãValdineuza do Nascimento Borges, CPPT Cuniã
Valdineuza do Nascimento Borges, CPPT Cuniã
 
Sergio Leao, Acreditar
Sergio Leao, Acreditar Sergio Leao, Acreditar
Sergio Leao, Acreditar
 
Hon. Omar Tejada
Hon. Omar TejadaHon. Omar Tejada
Hon. Omar Tejada
 

Recently uploaded

Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationReyMonsales
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Axel Bruns
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...Ismail Fahmi
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerOmarCabrera39
 
Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfauroraaudrey4826
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaignanjanibaddipudi1
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfauroraaudrey4826
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 

Recently uploaded (15)

Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and information
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert Oppenheimer
 
Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdf
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdf
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 

Case Study on Song Bung 4 Hydropower Project Resettlement Process in Vietnam

  • 1. Tran Trung Tuyen (Song Bung 4 HPMB) Takafumi Kadono (ADB) Song Bung 4 Hydropower Project Case Study Presented at the IHA 2013 World Congress
  • 2. . CASE STUDY FROM SONG BUNG 4 HYDROPOWER PROJECT – VIET NAM Kuching 23rd May, 2013 Tran Trung Tuyen Takafumi Kadono Song Bung 4 HPMB Energy Specialist-ADB
  • 3. A. INTRODUCTION Project site Vu Gia-Thu Bon Basin Mapping of Project Location
  • 4. Project General Layout Overview Layout RCC Dam 114mReservoir Tunnel 3.2km Power house
  • 5. Project Key Features and Time Schedule  InstalledCapacity:156MW with two Francis turbines 78MW each. Annual Output: 586.25 GWH  Reservoir: Surface Area 15.8 km2; FSL 222.5m. Gross Vol:510,8 MCM  Dam: RCC (about 800.000 m3), 114m high, crest length 345m, CVC Diversion Culvert 5mx9m.  Headrace Tunnel: 3.2km, inner diameter: 7.2m Construction Progress  Commencement: June 2010  River Closure: Jan 2012  Impoundment: Aug 2014  Unit 1 Completion: 10/2014  Unit 2 Completion:12/2014 Resettlement  4 Villages, 253 Household and 1041 People Relocated.  First Relocation: Oct 2012  Completion of all Relocated Sites: Quarter III 2013.
  • 6. B. WORKING WITH AFFECTED PEOPLE MAPPING OF 4 RESETTLEMENT SITES
  • 7. When we did: since 2006 following FS approved by GoV, ADB provided TA and fielded Consultant for PPTA.  Where we did: Project affected land, Reservoir, upstream and downstream.  What we did: Conducting full survey and consultation with AP to identify best approach and to develop AP - included program.  How we did: by applying bottom up method and by working together towards the same objectives through a transparent information and full participatory by APs Project Preparation Survey Team Old Thon 2
  • 8. Pre-Project Situation • Mainly dominance by Co Tu Ethnic Minority. • Limited Access and livelihood activities • Low level of literacy and lack of health care and public facilities. • High incidence of poverty. Self demand and supply with limit use of cash. Traditional Guol House of CoTu Ethnic Typical House made of Bamboo and Leaf
  • 9. • Identify loss of land and asset for support and compensation • Ensure AP rights on land resources allocation. • Prepare Livelihood Restoration for APs • Provide trainings and guidance for APs recapturing normal life and familiarizing with change of life. Components in Preparation Slash&burn rotation Old School Hunting PIB in Cotu
  • 10. Institutional Arrangement ADB , NGO, POE and Province Authority PMB including Contractor and Consultant RMIU at District Level VRDG at Villages Level APs , Community mobilizer and facilitator AP supported by local Community Mobilizer and local Facilitator takes core position in all relocation related activities VDRG as a direct bridge with AP to participate actively in all stage of implementation. RMIU to review compliance on policy of compensation and support; provide support on administration. PMB from listening to and understanding about AP, develop a comprehensive and AP-based resettlement plan. ADB, POE, NGO, independent Consultant... overseeing compliance and application.
  • 11. Criterion Decree 197/2003 & Land Law ADB Policy Consultation Not specified. APs fully informed & consulted; participatory; public disclosure. Compensation for non- titled land and assets Not compensated. Compensated at market value. Compensation for economic displacement Not compensated. Compensated for loss of livelihood activities, access. Compensation value Based on residual cost. Based on replacement cost w/o deduction of salvaged materials; incl. taxes & fees. Support for significant impact AP losing >30% of agricultural land entitled to assistance for 3-6 months . AP losing > 10% productive land/asset entitled to restoration of income and livelihood. Consideration for women & vulnerable. No specific provision but poor APs are to be supported by PPC. Assistance for improvement; gender-responsive Major Policy Differences
  • 12. Working with APs • Public Regular meetings and Consultation for explanation of project and AP entitlement • Encouraged and empower APs active participation. • Listened to AP expectation and put into design, plan and implementation. • Defined necessary support and livelihood restoration suited to AP wish. AP voiced up opinion Meeting with AP in progress
  • 13. Meeting with APs and Local Community With local officer Joined Team at field Addressing AP concern Downstream Survey
  • 14. APs Participation • Get AP involved into all process • Joint conduct of DMS, Selection of Resettlement Site, Sample of Layout and House…. • Public Consultation with AP’s participation. • Making own house and community facilities. Monitoring entire program. • APs shaped their expected perspectives in a new life.
  • 15. Entitlement Matrix Items at New RS For Areas Housing Plot and adjacent Garden Household 400-600m2 Production Land HH 1.5 ha Public Wet Rice Field Relocated Sites 11 ha Community Agro - Forest Land for NTP HH 8 - 10 ha Construction of housing size HH 40 – 65 m2 Kitchen, bath room, toilet…facilities HH 22 m2 Public Facilities including access road, domestic water & power supply, school, medial station, cultural house, wet rice irrigation, administrative zone as appropriate to all relocated sites. Compensated and Support made at replacement cost by cash on the basis of Support Provided Training Provided Create Job & change of Career, Poverty Reduce Agricultural Development Stabilizations of Live: food, protein, health care, fuel… Develop Rearing: domestic cattle& poultry, fisheries Agriculture Production: Seedlings, fertilizer, pesticide, caring.. Non-Farming Activities: hair cut, carpenter, knitting Stock Rearing: Pig, cow, chicken.. Health Care, HIV, human trafficking, Reforestation for production and NTPs Nutrient for Children & Woman Technical assistance, method of production, trading and commercial Capacity building, Literacy demolition, Monitoring works Others: Moving, grave, worshiping, visiting Driving, repairing motorbike…
  • 16. Finalization of REMDP • Comprehensive document covering various issues and aspects with incorporation of APs desires and concerns. • Supported by Gender Action Plan; Social Management Plan • Updated and developed regularly along the time • JFPR as a plus focusing on vocational training, providing seedlings & livestock, capacity building, health care , enhance awareness to APs for new life REMDP
  • 17. Implementation in progress • Conducting DMS and Selection of Resettlement Site with participation of local APs especially women. • Public Disclosure of Matrix Design and Planning . • Gathering feedback and comment for revision. Woman participates in DMS at field Inventory Asset on Land Public Disclosure at Village
  • 18. • Selection of resettlement Site and Production land • Site clearance and Monitoring from APs • Access to forest for hunting, foods and NTP collection. Implementation in progress Woman participates construction monitoring Combined Team in the forest New RS under Clearance
  • 19. Implementation in progress Disclosure on compensation in participation of men and women AP gathers up for consultation Seeking for Expected Resettled Sites Reaching final agreement
  • 20. • Compensation and Support Payment. • Advising APs to put monies at Bank for saving. • Both wife and husband’s name appears in all papers Implementation in progress Woman opens separate bank account Get compensated in spouses Papers in the name of husband and wife
  • 21. • Construction of Public Facilities including health care station, school, power supply, access road, domestic water system… Implementation in progress School at new RS School under construction Health Center at new RS Weekly meeting in RS including VRDG, SB4, Contractor, ADB consultant
  • 22. After Relocation Individual house at new RS Community Hall for Public Activities Overview to a village. • APs build their own house and Guol house under their choice & traditional style. • Land Use Certificate under name of spouse.
  • 23. A new life begins A view at New Resettlement Site Traditional Guol and Community Court Typical new house built by AP Collection of rattanVehicle accessible
  • 24. Restoration After Relocation Wet rice development Traditional Knitting at home Fish Pond House Gardening
  • 25. Emerging of Challenges • Conflict of interest within family. • Abuse of Alcohol; Driving motorbike; Using modern home appliances and facilities. • More vulnerable by social impacts from contacting with outer world. • Long term financial management • Maintaining traditional culture. • Stable restoration of livelihood activities. PMB is continuing with APs for sustainable development by extending more efforts on:  Training AP towards new life and career.  Providing further supports.  Improving APs awareness and capacity.  Sharing knowledge and benefit…
  • 26. Respecting and maintaining locally social and cultural characteristic. Well preparation with design factoring much traditionally cultural settings and tailoring to AP’s expectation. Encouraging and Empowering APs to actively participating throughout all stages. Applying bottom up approach and making APs core part of Project in a long run. High consensus from AP towards project objectives by Working with Affected People. C. LESSON LEARNED
  • 27. THANK YOU FOR ATTENTION . . . , .
  • 28. Song Bung 4 Hydropower Project Takafumi Kadono, ADB Tran Trung Tuyen, SB4HPMB 23 May 2013 Resettlement Livelihood Improvement (JFPR) Civil Society Organization Collaboration Basin Sustainability
  • 30. Song Bung 4 HPP Land Acquisition and Resettlement Process • Mobilizing and empowering APs from early stages; continuous involvement. • Meaningful consultation – not just ticking the box. – Selection of resettlement site – Design of resettlement site and own houses – Discussion on livelihood restoration activities – Bottom-up approach • Community mobilization & additional livelihood restoration support funded by Japan Fund for Poverty Reduction (JFPR) 29
  • 31. Song Bung 4 HPP Land Acquisition and Resettlement Process 30 Old House Old House New House New Concrete House in A Vuong HPP Old Classroom New Classroom
  • 32. Song Bung 4 HPP Land Acquisition and Resettlement Process • Gender-responsive. – Women have been empowered to participate in consultation, resettlement site selection and planning, DMS, compensation payment – Half of VRDG members and extension workers are women – Female village extension workers – Livelihood restoration programs for women – Farm and non-farm skills training for women (para-vet, plumbing, etc.) – Improved maternal health care – Separate bank accounts for men and women • Application of ADB policies. • ADB staff dedicated to LAR. • Capacity building of PMB and local authorities. 31
  • 33. JFPR 9120-VIE:Livelihood Improvement of Vulnerable Ethnic Minority Communities Affected by the Song Bung 4 Hydropower Project in Quang Nam Province Japan Fund for Poverty Reduction
  • 34. Objective and Activities • Japan Fund for Poverty Reduction grant ($2 million) to complement income restoration and for social preparation. • Village Resettlement Development Group (2009) – Consisting of representatives of affected persons (44% women). – To develop awareness about entitlement, resettlement activities, grievance redress mechanism, plan & implement resettlement, design and implement livelihood programs. – Meet every 2 weeks and monthly. – Supported by JFPR Community Mobilizer. • Village Extension Worker – Community facilitator, village para-vet, agriculture, fishery, health. – All both man and woman. 33
  • 35. Objective and Activities • Training and awareness program – Health awareness, immunization, treatment of mosquito net, etc. – Traffic safety – HIV/AIDS and human trafficking – Water management, irrigation, plumbing, forest protection – Build awareness on use and maintenance of village infrastructure • Livelihood Activities - Diversification – Livestock (pig, chicken, duck, buffalo…) – Agriculture (home garden, wet rice, improve traditional upland farming…) – Fishery, agro-forestry, industrial trees – Non-farm income generating activities 34
  • 37. Safeguard Policy Statement (2009) • Effective on 20 Jan 2010 • Consolidation of Previous Policies: – Environment Policy (2002) – Indigenous Peoples Policy (1998) – Involuntary Resettlement Policy (1995) • Ambiguities clarified • Consistent with WB and IFC’s approaches • Requirements tailored appropriately to different financing modalities • Strengthened monitoring and supervision • Country Safeguard Systems (CSS) • Emphasis on capacity development in DMCs 36
  • 38. Safeguard Policy Statement (2009) • Overarching Objectives: – Avoid adverse impacts of projects on the environment and affected people, where possible; – Minimize, mitigate, and/or compensate for adverse project impacts on the environment and affected people when avoidance is not possible; and – Help borrowers/clients to strengthen their safeguard systems and develop the capacity to manage environmental and social risks. 37
  • 39. Major Difference: Environmental Safeguards Previous SPS o Includes explicit requirements on (i) environmental assessment process o No equivalent requirements on (ii)- (v), while environmental assessment reports examine these issues in practice but often in an ad hoc manner Includes explicit policy principles and requirements on: i. environmental assessment process ii. biodiversity protection and natural resources management iii. pollution prevention and abatement iv. occupational and community health and safety v. physical cultural resources
  • 40. Major Difference: Involuntary Resettlement Safeguards Previous SPS o The 1995 Policy does not clearly define policy scope and triggers The IR safeguards cover physical displacements (relocation, loss of residential land, or loss of shelter) and economic displacements (loss of land, assets, access to assets, income sources and means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.
  • 41. Major Difference: Involuntary Resettlement Safeguards Previous SPS o No equivalent provision If potential adverse economic, social, or environmental impacts from project activities other than land acquisition are identified, they will be avoided, or at least minimized, mitigated, or compensated for, through the environmental assessment process. If these impacts are found to be significantly adverse at any stage of the project, the borrower/client will be required to develop and implement a management plan to restore the livelihood of affected persons to at least pre- project levels or better.
  • 42. Major Difference: Indigenous Peoples Safeguards Previous SPS o For projects involving Indigenous Peoples, initiatives should be conceived, planned, and implemented, to the maximum extent possible, with the informed consent of affected communities. However, no specific provisions on how to operationalize this concept. The borrower and ADB will ascertain the consent of affected IP communities to the following three types of project activities: o commercial development of the cultural resources and knowledge of IP; o physical displacement from traditional or customary lands; and o commercial development of natural resources within customary lands under use that would impact the livelihoods or the cultural, ceremonial, or spiritual uses that define the identity and community of IP.
  • 43. Major Difference: Indigenous Peoples Safeguards Previous SPS o No equivalent provision o The consent of affected Indigenous Peoples communities refers to a collective expression by the affected Indigenous Peoples communities, through individuals and/or their recognized representatives, of broad community support for such project activities. Broad community support may exist even if some individuals or groups object to the project activities. o ADB will assure that broad community support is demonstrated. ADB will not finance the project if such broad support does not exist.
  • 45. Collaboration with CSO Collaboration between ADB and CSO • Policy level • Country Partnership Strategy level • Project level Collaboration indicated in: • Strategy 2020 • Public Communications Policy • Accountability Mechanism • Safeguard Policy Statement, etc. 44
  • 46. Collaboration with CSO Roles Performed by CSO • Policy design and review • Advocacy across a range of issues • Information provider • Consultation during project design • Beneficiaries and stakeholders • Co-financer • Technical expert and trainers • Implementing agency • Monitoring and evaluation 45
  • 47. CSO in Song Bung 4 HPP • Service provider for livelihood development under JFPR 9120-VIE. • Independent monitoring. 46 Workshop organized by Vietnam Rivers Network
  • 48. Basin Sustainability Vu Gia – Thu Bon River Basin
  • 49. Payment for Ecosystem Services (PfES) • Benefit Sharing Mechanism supported through ADB TA 4689-VIE; piloted in A Vuong HPP – same Vu Gia - Thu Bon basin as Song Bung 4 HPP. • Suggested 2% of gross generation to finance Benefit Sharing Fund for livelihood development. • Decree 99 on PFES approved 2010. • Hydropower plants pay VND20/kWh (¢0.1/kWh) • $26 million collected in 2012, but disbursement to households and monitoring challenging. • ADB TA 6422-REG promotes (i) “household groups” and (ii) GIS & remote sensing. 48
  • 50. Rapid Basin-wide Hydropower Sustainability Assessment Tool (RSAT) • Developed by ADB, MRC, WWF. • Assess hydropower sustainability issues in a basin wide, multiple project context. • Assessment by stakeholders. • Action orientated. • Multi-criteria gap analysis. • Scheduled for piloting in Vu Gia - Thu Bon river basin (July). (To be financed by Water Financing Partnership Facility: WFPF) 49
  • 51. Hydropower Operation Rules • MoNRE tasked to prepare dry season operating rules for hydropower reservoirs in the Vu Gia - Thu Bon river basin. • ADB providing support (financed by WFPF) • ADB also supporting study on minimum flow requirements. 50