SlideShare a Scribd company logo
ID
Task
Mode
Task Name
Duration
Start
Finish
Aug 20, '17
Sep 24, '17
Oct 29, '17
Dec 3, '17
Jan 7, '18
Feb 11, '18
Mar 18, '18
Apr 22, '18
May 27, '18
Jul 1, '18
Aug 5
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
1
PROJECT DESIGN
63 days
Mon 9/4/17 Wed 11/29/1
2
DEVELOP FUNCTIONAL SPECIFICATIONS
10 days
Mon 9/4/17 Fri 9/15/17
3
DEVELOP SYSTEM ARCHITECTURE
4
DEVELOP PRELIMANARY DESIGN SPECIFICATIONS
20 days
Mon
9/18/17
2.5 days
Mon
10/16/17
Fri 10/13/17
Wed
10/18/17
5
DEVELOP DETAILED DESIGN SPECIFICATIONS
6
DEVELOP ACCEPTANCE TEST PLAN
20 days
Wed
10/18/17
10.5 days
Wed
11/15/17
Wed
11/15/17
Wed
11/29/17
7
PROJECT DEVELOPMENT 157 days
Thu 11/30/1 Fri 7/6/18
8
DEVELOP COMPONENTS
60 days
Thu
11/30/17
Wed
2/21/18
9
PROCURE SOFTWARE
25 days
Thu 2/22/18 Wed 3/28/18
10
PROCURE HARDWARE 25 days
Thu 3/29/18 Wed 5/2/18
11
DEVELOPMENT ACCEPTANCE TEST PACKAGE
12
PERFORM UNIT/INTEGRATION TEST
25 days
Thu 5/3/18
Wed 6/6/18
22 days
Thu 6/7/18
Fri 7/6/18
13
PROJECT DELIVERY
9.5 days
Mon 7/9/18 Fri 7/20/18
14
INSTALL SYSTEM
2 days
Mon 7/9/18 Tue 7/10/18
Project: Web Based Tool
Date: Sun 7/23/17
Task
Split
Milestone
Project Summary
Inactive Task
Inactive Milestone
Manual Task
Duration-only
Manual Summary Rollup
Start-only
Finish-only
External Tasks
Deadline
Progress
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 1
ID
Task
Mode
Task Name
Duration
Start
Finish
Aug 20, '17
Sep 24, '17
Oct 29, '17
Dec 3, '17
Jan 7, '18
Feb 11, '18
Mar 18, '18
Apr 22, '18
May 27, '18
Jul 1, '18
Aug 5
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
15
TRAIN CUSTOMERS
1 day
Wed 7/11/18 Wed 7/11/18
16
PERFORM ACCEPTANCE 3 days
Thu 7/12/18 Mon
TEST
17
PERFORM POST PROJECT REVIEW
18
PROVIDE WARRANTY SUPPORT
7/16/18
3 days
Tue 7/17/18 Thu 7/19/18
1 day
Tue 7/17/18 Tue 7/17/18
19
ARCHIVE MATERIALS
0.5 days
Fri 7/20/18
Fri 7/20/18
Project: Web Based Tool
Date: Sun 7/23/17
Task
Split
Milestone
Project Summary
Inactive Task
Inactive Milestone
Manual Task
Duration-only
Manual Summary Rollup
Start-only
Finish-only
External Tasks
Deadline
Progress
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 2
7
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
BudgetNew Web Based Tool Budget EstimatePROJECT
TASKSLABOR HOURSLABOR COST ($)MATERIAL COST
($)OTHER COST ($)TOTAL PER TASKPROJECT
DESIGNDevelop Functional
Specifications80.0$3,100.00$2,499.00$750.00$6,429.00Develop
System
Architecture160.0$1,200.00$1,500.00$0.00$2,860.00Develop
Preliminary Design
Specification20.0$300.00$1,295.00$0.00$1,615.00Develop
Detailed Design
Specifications160.0$1,100.00$1,700.00$0.00$2,960.00Develop
Acceptance Test
Plan85.0$1,500.00$2,500.00$0.00$4,085.00Subtotal505.0$7,200
.00$9,494.00$750.00$17,949.00PROJECT
DEVELOPMENTDevelop
Components480.0$1,700.00$6,250.00$0.00$8,430.00Procure
Software (Capital
Equipment)200.0$400.00$15,500.00$0.00$16,100.00Procure
Hardware (Capital
Equipment)200.0$600.00$27,500.00$0.00$28,300.00Developme
nt Acceptance Test
Package200.0$1,200.00$1,000.00$0.00$2,400.00Perform
Unit/Integration Test
180.0$650.00$1,000.00$0.00$1,830.00Subtotal1,260.0$4,550.00
$51,250.00$0.00$57,060.00PROJECT
DELIVERYInstall
System16.0$320.00$1,750.00$500.00$2,586.00Train
Customers8.0$160.00$200.00$612.00$980.00Perform
Acceptance Test24.0$480.00$500.00$0.00$1,004.00Perform
Post Project Review24.0$480.00$0.00$0.00$504.00Provide
Warranty Support8.0$160.00$0.00$0.00$168.00Archive
Materials4.0$80.00$150.00$0.00$234.00Subtotal84.0$1,680.00$
2,600.00$1,112.00$5,476.00PROJECT
MANAGEMENTCustomer Progress
Meetings/Reports480.0$1,000.00$0.00$0.00$1,480.00Internal
Status
Meetings/Reports480.0$1,000.00$0.00$0.00$1,480.00Subcontra
ctors480.0$1,000.00$0.00$2,500.00$3,980.00Interface to Other
Internal
Departments480.0$1,000.00$0.00$0.00$1,480.00Configuration
Management480.0$1,000.00$0.00$0.00$1,480.00Quality
Assurance480.0$1,000.00$0.00$0.00$1,480.00Overall Project
Management480.0$1,000.00$0.00$0.00$1,480.00Subtotal3,360.
0$7,000.00$0.00$2,500.00$12,860.00OTHER
COSTTravel0.0$0.00$0.00$4,396.00$4,396.00Telecommunicati
ons0.0$0.00$0.00$1,759.00$1,759.00Documentation0.0$0.00$0.
00$500.00$500.00Subtotal0.0$0.00$0.00$6,655.00$6,655.00Tot
al Project Funding
Requirements5209.0$20,430.00$63,344.00$11,017.00$100,000.
00
Development & TestingDevelopment & Testing Report - New
Web Based Tool (testing results)Test Item Test Condition
Expected Result Procedure Pass/FailDefect ID#Browser /
DeviceBug Issue Description Owner CommentsSearch Form
1.aStable 5.00CompletePass325670.00Windows 8
(IE10)NoneJasmine McCordnavigation 1.aCritical
5.00Escallated to testing for fixFail325672.00Windows 8
(IE10)Cannot move mouse to menu area without it disappearing.
(See screenshot) Jasmine McCordnavigation 1.bCritical
5.00Escallated to testing for fixFail325673.00Windows 8
(IE10)Cannot scroll on pages 4, 6, 8Jasmine McCordsearch
form 1.bStable 5.00CompletePass325671.00Windows 8
(IE10)NoneJasmine McCordimage carousel 1-3.aCritical
5.00Escallated to testing for fixFail325674.00Windows 8
(IE10)The left and right arrows in box do nto scrollJasmine
McCordCustomer Support Field 1.aCritical 5.00Escallated to
testing for fixFail325675.00Windows 8 (IE10)Customer cannot
submit form unless all required fields are filled outJasmine
McCordNeed an extra 10 lead time for resolution Data Entry
Field (feedback)Critical 5.00Escallated to testing for
fixFail325676.00Windows 8 (IE10)Some fields get stuck when
data entered --> customer cannot get passed field without
restarting browserJasmine McCordNeed to resolve asap -
Priority level
Sheet2
Preliminary Project Charter Worksheet
CPMGT/305 Version 12
1
University of Phoenix Material
Preliminary Project Charter Worksheet
Complete this project charter worksheet according to the
instructions in section 4.1 of A Guide to the Project
Management Body of Knowledge.
Completed by: Learning Team A
Date: 7/22/2017
1. Project title: New Web Based Tool
2. High-level project scope ( fewer than 50 words)
A new performance management process will be created that
utilizes a web-based system; providing a convenient way to
document and track employee performance goals, provide
regularly updated status reports, and a vehicle for managerial
feedback. The system will use quantified data for salary/bonus
treatment at year’s end.
3. Problem to be solved or opportunity to be realized by this
project (fewer than 25 words)
The new performance management system will provide an
efficient way to quantify employee performance; providing a
fairer, more accurate system for performance appraisals.
4. Project purpose or justification including specific measurable
business impacts or results (fewer than 50 words)
The new performance management system is needed because of
the lack of accuracy in past employee performance reviews and
merit increases. The new system will provide both qualitative
and quantitative data metric data, which will result in providing
more precise analysis of employee work performance.
5. Measurable project objectives and related success criteria
including metrics (Provide three to four objectives with metrics)
· Determine which performance measuring criteria should be
implemented into the new system, and describe how the system
utilizes it.
· Develop performance management system platform
· Integrate system into company website
· Achieve increased employee performance of at least 15%
within 12 months of implementation.
6. High-level requirements (fewer than 100 words)
The performance management system project will require a
hand-selected project team with extensive background in human
resources and supervisory management. Two human resource
clerks will participate, in addition to a single project manager.
The team will also require the services of a software
development consultant and her team of two software engineers.
The project will be staged in a small suite of offices on the
third-floor of the downtown Seattle office. The project will
require the purchase of a new web server, and dedicated internet
connection during preliminary stages prior to implementation in
a production environment.
7. High-level risks (fewer than 100 words)
Some high-level risks include: developmental delays, scope
creep, excessive change requests, technical difficulties, lack of
employee enthusiasm for new performance system.
8. Summary of high-level milestones schedule (identify the
major deliverables and subtasks)
1. Develop Employee Performance Grading System
· Analyze industry standards, averages
· Create methodology for quantifying performance goals/results
· Develop template for employee performance status reports
· Create grading matrix for salary/bonus criteria
2. Develop software platform for Performance Grading System
· Develop outline for software development
· Create software for Performance Grading System
· Pilot test group prior to production rollout
· Work out bugs, smooth out feature set
· Implementation
3. Company Intranet Integration
· Implement Performance Management software into Web space
· Develop supervisor feedback system that integrates with PMS
· Test and Troubleshoot
· Pilot software platform/web site
· Full implementation
9. Summary of high-level budget including expense dollars,
capital dollars, and headcount (identify costs for major
deliverables and tasks identified in the preceding milestone
schedule)
Deliverables
Estimated Cost
Due Date
DEVELOP FUNCTIONAL SPECIFICATIONS
Labor Costs = $7,200
September 9th, 2017
DEVELOP SYSTEM ARCHITECTURE
Labor Costs = $7,000
October 15th, 2017
DEVELOP PRELIMANARY DESIGN SPECIFICATIONS
Labor Costs = $4,500
October 18th, 2017
DEVELOP DETAILED DESIGN SPECIFICATIONS
Labor Costs = $1,100
November 15th, 2017
DEVELOP COMPONENTS
Labor Costs = $600
August 22th, 2017
PROCURE SOFTWARE
Labor Costs = $7,200
March 28, 2017
DEVELOPMENT ACCEPTANCE TEST PACKAGE
Labor Costs = $1,680
June 6th, 2018
PERFORM UNIT/INTEGRATION TEST
Labor Costs = $7,000
July 6th, 2018
INSTALL SYSTEM
Labor Costs = $3,200
July 10th, 2018
1
PROJECT PLAN OVERVIEW & PRELIMINARY PROJECT
PLANProject Plan Overview & Preliminary Project Plan
Team A:
Project Selection Criterion
One of the biggest decisions an organization makes is what
projects to take on. Once a scope of work, bids or a proposal
has been presented as project material, there are many factors to
consider. The most valuable options should be chosen as well
as considering goals and objectives of the portfolio of the
organization. The benefits of the project as well as objectives
are the main reason for choosing a project. Another thing to
consider would be the feasibility, what is the likelihood of this
project getting off the ground to completion. Timing must be
well-thought-out for each project. Some projects are conducted
in an emergency state, whereas, some are planned out far in
advance. Budget is one of biggest reasons for a project to fail
or be successful. A chosen project must maintain allocated
funding from stakeholders.
The first step for project selection is defining the project and
the criteria thereof. The second step is to score the project for
where it stands before other projects. The last step inform
stakeholders for approvals For this particular project the
criteria behind this project being chosen was the sales force
needed a web-based tool that could help in managing client
accounts, track sales and maintain customer proposals. It was
chosen due to the value of customer satisfaction verses budget
constraints. The benefits to cost ratio was analyzed and found
to be a profitable advantage for the sales team and their
customers. The payback period was examined; the findings
were that within a five year period the payback would be higher
than cost of project.
As the sales team begin to manage their customers with a more
organized position, they can take on more customers and keep
satisfaction and personable service while maintaining
production. Stakeholders chose this project for growth of
clients. Another criteria for selection was time management.
With the purchase and implementation of this web-based tool,
the sales force will have the tools to preserve client accounts in
a timely fashion. The web-based tool has the ability to notify
sales and clients when their products are low. The tool is also
has the ability to perform data-based functions. The sales team
inputs what products the client has. The client uses the tool for
production accountability. When stock gets low, the tool sends
notification to that client’s sales person for further ordering
direction. This cost value and customer satisfaction was criteria
for stakeholder decision Overview
The nature and scope of this project is to develop a web based
tool for a client organization. Team A works for an information
technology organization. A client has asked our organization to
help build and implement a new web-based internal management
system for their sales department to manage their customer
accounts. Our client’s sales managers and sales executives will
use this tool to develop account plans for their customers and to
track their own sales results and be able to extract a sales report
for each sales representative at each quarter. The focus of this
project is to be able to deliver a program that sales
representatives can manage easily anywhere and be able to pull
statistical information about their clients and themselves and
sales criteria.
The purpose of this internal management system implementation
is to help our clients sales department get more organized and
be able to input their client’s information and be able to build
programs specific to the needs of their clients. This
implementation will also allow the sales representatives to be
able to manage their client base much easier and be able to
track their clients progress and also be able to keep up to date
statistical information in their systems about their clients as
well. This system is being customized and developed
specifically to fit the needs of our client and requirements to
meet the client’s needs internally. The long term goal is for our
client to be able to manage their clients much better and be able
to address their needs in a more specific fashion.
We will be developing the project based on the following
criteria;
· A description of your internal client's requirements for this
sales and account management system.
· Identification and engagement of the appropriate stakeholders
to define the requirements for the new system.
· Development and testing of the system.
· Implementation of the system.
· A method for obtaining client feedback.
Task
Project Manager
Due Date
Owner
A description of your internal client’s requirements for this sale
and account management system
TBD
August 14, 2017
TBD
Identification and engagement of the appropriate stakeholders to
define the requirements for the new system.
TBD
August 14, 2017
TBD
Development & Testing for the system
TBD
August 14, 2017
TBD
A Method for obtaining client feedback
TBD
August 14, 2017
TBD
Preliminary Project Schedule
Preliminary Budgetary Plan
Reference
PMI (2013) Project Management Institute. A Guide to the
Project Management Body of Knowledge (PMBOK Guide) - 5th
Edition

More Related Content

Similar to IDTaskModeTask NameDurationStartFinishAug 20.docx

Madhura Kulkarni Resume
Madhura Kulkarni ResumeMadhura Kulkarni Resume
Madhura Kulkarni Resume
Madhura Kulkarni
 
Software requirements engineering lecture 01
Software requirements engineering   lecture 01Software requirements engineering   lecture 01
Software requirements engineering lecture 01
Abdul Basit
 
Software requirements engineering
Software requirements engineeringSoftware requirements engineering
Software requirements engineering
Abdul Basit
 
IBM Cognos 10 Framework Manager Metadata Modeling: Tips and Tricks
IBM Cognos 10 Framework Manager Metadata Modeling: Tips and TricksIBM Cognos 10 Framework Manager Metadata Modeling: Tips and Tricks
IBM Cognos 10 Framework Manager Metadata Modeling: Tips and Tricks
Senturus
 
Turbocharge Your Automation Framework to Shorten Regression Execution Time
Turbocharge Your Automation Framework to Shorten Regression Execution TimeTurbocharge Your Automation Framework to Shorten Regression Execution Time
Turbocharge Your Automation Framework to Shorten Regression Execution Time
Josiah Renaudin
 
Mercury Testdirector8.0 using Slides
Mercury Testdirector8.0 using SlidesMercury Testdirector8.0 using Slides
Mercury Testdirector8.0 using Slides
telab
 
Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...
Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...
Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...
Curiosity Software Ireland
 
Enhancing Software Quality
Enhancing Software QualityEnhancing Software Quality
Enhancing Software Quality
Anand Prabhala
 
STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
Anna Russo
 
CV_Sanjay
CV_SanjayCV_Sanjay
CV_Sanjay
sanjay DS
 
CV_Sachin_11Years_Automation_Performance
CV_Sachin_11Years_Automation_PerformanceCV_Sachin_11Years_Automation_Performance
CV_Sachin_11Years_Automation_Performance
Sachin Kodagali
 
STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
Anna Russo
 
Chandan_3.7 Years of Experience_Oracle
Chandan_3.7 Years of Experience_OracleChandan_3.7 Years of Experience_Oracle
Chandan_3.7 Years of Experience_Oracle
Chandan Jai
 
Improving Software Quality- 2-day Tester Training
Improving Software Quality- 2-day Tester TrainingImproving Software Quality- 2-day Tester Training
Improving Software Quality- 2-day Tester Training
Anna Russo
 
Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015 Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015
deepti Debnath
 
Vishal Jadhav
Vishal JadhavVishal Jadhav
Resume_Sahida Sultana
Resume_Sahida SultanaResume_Sahida Sultana
Resume_Sahida Sultana
Sahida Sultana
 
Resume
ResumeResume
Ashish Baraiya
Ashish BaraiyaAshish Baraiya
Ashish Baraiya
Ashish Baraiya
 
yourfirstcodedui-121217152431-phpapp02.pdf
yourfirstcodedui-121217152431-phpapp02.pdfyourfirstcodedui-121217152431-phpapp02.pdf
yourfirstcodedui-121217152431-phpapp02.pdf
Patiento Del Mar
 

Similar to IDTaskModeTask NameDurationStartFinishAug 20.docx (20)

Madhura Kulkarni Resume
Madhura Kulkarni ResumeMadhura Kulkarni Resume
Madhura Kulkarni Resume
 
Software requirements engineering lecture 01
Software requirements engineering   lecture 01Software requirements engineering   lecture 01
Software requirements engineering lecture 01
 
Software requirements engineering
Software requirements engineeringSoftware requirements engineering
Software requirements engineering
 
IBM Cognos 10 Framework Manager Metadata Modeling: Tips and Tricks
IBM Cognos 10 Framework Manager Metadata Modeling: Tips and TricksIBM Cognos 10 Framework Manager Metadata Modeling: Tips and Tricks
IBM Cognos 10 Framework Manager Metadata Modeling: Tips and Tricks
 
Turbocharge Your Automation Framework to Shorten Regression Execution Time
Turbocharge Your Automation Framework to Shorten Regression Execution TimeTurbocharge Your Automation Framework to Shorten Regression Execution Time
Turbocharge Your Automation Framework to Shorten Regression Execution Time
 
Mercury Testdirector8.0 using Slides
Mercury Testdirector8.0 using SlidesMercury Testdirector8.0 using Slides
Mercury Testdirector8.0 using Slides
 
Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...
Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...
Curiosity and Infuse Consulting Present: Sustainable Test Automation Strategi...
 
Enhancing Software Quality
Enhancing Software QualityEnhancing Software Quality
Enhancing Software Quality
 
STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STAREAST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
 
CV_Sanjay
CV_SanjayCV_Sanjay
CV_Sanjay
 
CV_Sachin_11Years_Automation_Performance
CV_Sachin_11Years_Automation_PerformanceCV_Sachin_11Years_Automation_Performance
CV_Sachin_11Years_Automation_Performance
 
STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
STARWEST 2011 - 7 Steps To Improving Software Quality using Microsoft Test Ma...
 
Chandan_3.7 Years of Experience_Oracle
Chandan_3.7 Years of Experience_OracleChandan_3.7 Years of Experience_Oracle
Chandan_3.7 Years of Experience_Oracle
 
Improving Software Quality- 2-day Tester Training
Improving Software Quality- 2-day Tester TrainingImproving Software Quality- 2-day Tester Training
Improving Software Quality- 2-day Tester Training
 
Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015 Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015
 
Vishal Jadhav
Vishal JadhavVishal Jadhav
Vishal Jadhav
 
Resume_Sahida Sultana
Resume_Sahida SultanaResume_Sahida Sultana
Resume_Sahida Sultana
 
Resume
ResumeResume
Resume
 
Ashish Baraiya
Ashish BaraiyaAshish Baraiya
Ashish Baraiya
 
yourfirstcodedui-121217152431-phpapp02.pdf
yourfirstcodedui-121217152431-phpapp02.pdfyourfirstcodedui-121217152431-phpapp02.pdf
yourfirstcodedui-121217152431-phpapp02.pdf
 

More from wilcockiris

Barbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docx
Barbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docxBarbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docx
Barbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docx
wilcockiris
 
BARGAIN CITY Your career is moving along faster than you e.docx
BARGAIN CITY Your career is moving along faster than you e.docxBARGAIN CITY Your career is moving along faster than you e.docx
BARGAIN CITY Your career is moving along faster than you e.docx
wilcockiris
 
Barbara schedules a meeting with a core group of clinic  managers. T.docx
Barbara schedules a meeting with a core group of clinic  managers. T.docxBarbara schedules a meeting with a core group of clinic  managers. T.docx
Barbara schedules a meeting with a core group of clinic  managers. T.docx
wilcockiris
 
Barbara schedules a meeting with a core group of clinic managers.docx
Barbara schedules a meeting with a core group of clinic managers.docxBarbara schedules a meeting with a core group of clinic managers.docx
Barbara schedules a meeting with a core group of clinic managers.docx
wilcockiris
 
Barbara schedules a meeting with a core group of clinic managers. Th.docx
Barbara schedules a meeting with a core group of clinic managers. Th.docxBarbara schedules a meeting with a core group of clinic managers. Th.docx
Barbara schedules a meeting with a core group of clinic managers. Th.docx
wilcockiris
 
Barbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docx
Barbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docxBarbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docx
Barbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docx
wilcockiris
 
BARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docx
BARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docxBARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docx
BARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docx
wilcockiris
 
Banks 5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docx
Banks    5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docxBanks    5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docx
Banks 5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docx
wilcockiris
 
Banking industry•Databases that storeocorporate sensiti.docx
Banking industry•Databases that storeocorporate sensiti.docxBanking industry•Databases that storeocorporate sensiti.docx
Banking industry•Databases that storeocorporate sensiti.docx
wilcockiris
 
BAOL 531 Managerial AccountingWeek Three Article Research Pape.docx
BAOL 531 Managerial AccountingWeek Three Article Research Pape.docxBAOL 531 Managerial AccountingWeek Three Article Research Pape.docx
BAOL 531 Managerial AccountingWeek Three Article Research Pape.docx
wilcockiris
 
bankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docx
bankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docxbankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docx
bankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docx
wilcockiris
 
Barbara and Judi entered into a contract with Linda, which provi.docx
Barbara and Judi entered into a contract with Linda, which provi.docxBarbara and Judi entered into a contract with Linda, which provi.docx
Barbara and Judi entered into a contract with Linda, which provi.docx
wilcockiris
 
bappsum.indd 614 182014 30258 PMHuman Reso.docx
bappsum.indd   614 182014   30258 PMHuman Reso.docxbappsum.indd   614 182014   30258 PMHuman Reso.docx
bappsum.indd 614 182014 30258 PMHuman Reso.docx
wilcockiris
 
Bank ReservesSuppose that the reserve ratio is .25, and that a b.docx
Bank ReservesSuppose that the reserve ratio is .25, and that a b.docxBank ReservesSuppose that the reserve ratio is .25, and that a b.docx
Bank ReservesSuppose that the reserve ratio is .25, and that a b.docx
wilcockiris
 
Bank Services, Grading GuideFIN366 Version 21Individual.docx
Bank Services, Grading GuideFIN366 Version 21Individual.docxBank Services, Grading GuideFIN366 Version 21Individual.docx
Bank Services, Grading GuideFIN366 Version 21Individual.docx
wilcockiris
 
Baldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docx
Baldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docxBaldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docx
Baldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docx
wilcockiris
 
Bank confirmations are critical to the cash audit. What information .docx
Bank confirmations are critical to the cash audit. What information .docxBank confirmations are critical to the cash audit. What information .docx
Bank confirmations are critical to the cash audit. What information .docx
wilcockiris
 
BalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docx
BalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docxBalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docx
BalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docx
wilcockiris
 
BAM 515 - Organizational Behavior(Enter your answers on th.docx
BAM 515 - Organizational Behavior(Enter your answers on th.docxBAM 515 - Organizational Behavior(Enter your answers on th.docx
BAM 515 - Organizational Behavior(Enter your answers on th.docx
wilcockiris
 
BalanchineGeorge Balanchine is an important figure in the histor.docx
BalanchineGeorge Balanchine is an important figure in the histor.docxBalanchineGeorge Balanchine is an important figure in the histor.docx
BalanchineGeorge Balanchine is an important figure in the histor.docx
wilcockiris
 

More from wilcockiris (20)

Barbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docx
Barbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docxBarbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docx
Barbara Silva is the CIO for Peachtree Community Hospital in Atlanta.docx
 
BARGAIN CITY Your career is moving along faster than you e.docx
BARGAIN CITY Your career is moving along faster than you e.docxBARGAIN CITY Your career is moving along faster than you e.docx
BARGAIN CITY Your career is moving along faster than you e.docx
 
Barbara schedules a meeting with a core group of clinic  managers. T.docx
Barbara schedules a meeting with a core group of clinic  managers. T.docxBarbara schedules a meeting with a core group of clinic  managers. T.docx
Barbara schedules a meeting with a core group of clinic  managers. T.docx
 
Barbara schedules a meeting with a core group of clinic managers.docx
Barbara schedules a meeting with a core group of clinic managers.docxBarbara schedules a meeting with a core group of clinic managers.docx
Barbara schedules a meeting with a core group of clinic managers.docx
 
Barbara schedules a meeting with a core group of clinic managers. Th.docx
Barbara schedules a meeting with a core group of clinic managers. Th.docxBarbara schedules a meeting with a core group of clinic managers. Th.docx
Barbara schedules a meeting with a core group of clinic managers. Th.docx
 
Barbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docx
Barbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docxBarbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docx
Barbara Rosenwein, A Short History of the Middle Ages 4th edition (U.docx
 
BARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docx
BARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docxBARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docx
BARBARA NGAM, MPAShoreline, WA 98155 ▪ 801.317.5999 ▪ [email pro.docx
 
Banks 5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docx
Banks    5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docxBanks    5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docx
Banks 5Maya BanksProfessor Debra MartinEN106DLGU1A2018.docx
 
Banking industry•Databases that storeocorporate sensiti.docx
Banking industry•Databases that storeocorporate sensiti.docxBanking industry•Databases that storeocorporate sensiti.docx
Banking industry•Databases that storeocorporate sensiti.docx
 
BAOL 531 Managerial AccountingWeek Three Article Research Pape.docx
BAOL 531 Managerial AccountingWeek Three Article Research Pape.docxBAOL 531 Managerial AccountingWeek Three Article Research Pape.docx
BAOL 531 Managerial AccountingWeek Three Article Research Pape.docx
 
bankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docx
bankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docxbankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docx
bankCustomer1223333SmithJamesbbbbbb12345 Abrams Rd Dallas TX 75043.docx
 
Barbara and Judi entered into a contract with Linda, which provi.docx
Barbara and Judi entered into a contract with Linda, which provi.docxBarbara and Judi entered into a contract with Linda, which provi.docx
Barbara and Judi entered into a contract with Linda, which provi.docx
 
bappsum.indd 614 182014 30258 PMHuman Reso.docx
bappsum.indd   614 182014   30258 PMHuman Reso.docxbappsum.indd   614 182014   30258 PMHuman Reso.docx
bappsum.indd 614 182014 30258 PMHuman Reso.docx
 
Bank ReservesSuppose that the reserve ratio is .25, and that a b.docx
Bank ReservesSuppose that the reserve ratio is .25, and that a b.docxBank ReservesSuppose that the reserve ratio is .25, and that a b.docx
Bank ReservesSuppose that the reserve ratio is .25, and that a b.docx
 
Bank Services, Grading GuideFIN366 Version 21Individual.docx
Bank Services, Grading GuideFIN366 Version 21Individual.docxBank Services, Grading GuideFIN366 Version 21Individual.docx
Bank Services, Grading GuideFIN366 Version 21Individual.docx
 
Baldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docx
Baldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docxBaldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docx
Baldwins Kentucky Revised Statutes AnnotatedTitle XXXV. Domesti.docx
 
Bank confirmations are critical to the cash audit. What information .docx
Bank confirmations are critical to the cash audit. What information .docxBank confirmations are critical to the cash audit. What information .docx
Bank confirmations are critical to the cash audit. What information .docx
 
BalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docx
BalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docxBalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docx
BalShtBalance SheetBalance SheetBalance SheetBalance SheetThe Fran.docx
 
BAM 515 - Organizational Behavior(Enter your answers on th.docx
BAM 515 - Organizational Behavior(Enter your answers on th.docxBAM 515 - Organizational Behavior(Enter your answers on th.docx
BAM 515 - Organizational Behavior(Enter your answers on th.docx
 
BalanchineGeorge Balanchine is an important figure in the histor.docx
BalanchineGeorge Balanchine is an important figure in the histor.docxBalanchineGeorge Balanchine is an important figure in the histor.docx
BalanchineGeorge Balanchine is an important figure in the histor.docx
 

Recently uploaded

RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience
Wahiba Chair Training & Consulting
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
HajraNaeem15
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
สมใจ จันสุกสี
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
Celine George
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
Nguyen Thanh Tu Collection
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
PsychoTech Services
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
math operations ued in python and all used
math operations ued in python and all usedmath operations ued in python and all used
math operations ued in python and all used
ssuser13ffe4
 

Recently uploaded (20)

RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
math operations ued in python and all used
math operations ued in python and all usedmath operations ued in python and all used
math operations ued in python and all used
 

IDTaskModeTask NameDurationStartFinishAug 20.docx

  • 1. ID Task Mode Task Name Duration Start Finish Aug 20, '17 Sep 24, '17 Oct 29, '17 Dec 3, '17 Jan 7, '18 Feb 11, '18 Mar 18, '18 Apr 22, '18 May 27, '18 Jul 1, '18 Aug 5 S M T W T F S S M T W T
  • 2. F S S M T W T F S S M T 1 PROJECT DESIGN 63 days Mon 9/4/17 Wed 11/29/1 2 DEVELOP FUNCTIONAL SPECIFICATIONS 10 days Mon 9/4/17 Fri 9/15/17 3 DEVELOP SYSTEM ARCHITECTURE 4 DEVELOP PRELIMANARY DESIGN SPECIFICATIONS 20 days Mon 9/18/17 2.5 days Mon
  • 3. 10/16/17 Fri 10/13/17 Wed 10/18/17 5 DEVELOP DETAILED DESIGN SPECIFICATIONS 6 DEVELOP ACCEPTANCE TEST PLAN 20 days Wed 10/18/17 10.5 days Wed 11/15/17 Wed 11/15/17 Wed 11/29/17 7 PROJECT DEVELOPMENT 157 days Thu 11/30/1 Fri 7/6/18 8 DEVELOP COMPONENTS 60 days
  • 4. Thu 11/30/17 Wed 2/21/18 9 PROCURE SOFTWARE 25 days Thu 2/22/18 Wed 3/28/18 10 PROCURE HARDWARE 25 days Thu 3/29/18 Wed 5/2/18 11 DEVELOPMENT ACCEPTANCE TEST PACKAGE 12 PERFORM UNIT/INTEGRATION TEST 25 days Thu 5/3/18 Wed 6/6/18 22 days Thu 6/7/18 Fri 7/6/18 13 PROJECT DELIVERY 9.5 days Mon 7/9/18 Fri 7/20/18 14 INSTALL SYSTEM 2 days Mon 7/9/18 Tue 7/10/18
  • 5. Project: Web Based Tool Date: Sun 7/23/17 Task Split Milestone Project Summary Inactive Task Inactive Milestone Manual Task Duration-only Manual Summary Rollup Start-only Finish-only External Tasks Deadline Progress Manual Progress Summary
  • 6. Inactive Summary Manual Summary External Milestone Page 1 ID Task Mode Task Name Duration Start Finish Aug 20, '17 Sep 24, '17 Oct 29, '17 Dec 3, '17 Jan 7, '18 Feb 11, '18 Mar 18, '18 Apr 22, '18 May 27, '18 Jul 1, '18 Aug 5 S M T W T F
  • 7. S S M T W T F S S M T W T F S S M T 15 TRAIN CUSTOMERS 1 day Wed 7/11/18 Wed 7/11/18 16 PERFORM ACCEPTANCE 3 days Thu 7/12/18 Mon TEST 17 PERFORM POST PROJECT REVIEW 18 PROVIDE WARRANTY SUPPORT 7/16/18 3 days
  • 8. Tue 7/17/18 Thu 7/19/18 1 day Tue 7/17/18 Tue 7/17/18 19 ARCHIVE MATERIALS 0.5 days Fri 7/20/18 Fri 7/20/18 Project: Web Based Tool Date: Sun 7/23/17 Task Split Milestone Project Summary Inactive Task Inactive Milestone Manual Task Duration-only Manual Summary Rollup Start-only Finish-only External Tasks
  • 9. Deadline Progress Manual Progress Summary Inactive Summary Manual Summary External Milestone Page 2 7 � � � �
  • 23. � � � � BudgetNew Web Based Tool Budget EstimatePROJECT TASKSLABOR HOURSLABOR COST ($)MATERIAL COST ($)OTHER COST ($)TOTAL PER TASKPROJECT DESIGNDevelop Functional Specifications80.0$3,100.00$2,499.00$750.00$6,429.00Develop System Architecture160.0$1,200.00$1,500.00$0.00$2,860.00Develop Preliminary Design Specification20.0$300.00$1,295.00$0.00$1,615.00Develop Detailed Design Specifications160.0$1,100.00$1,700.00$0.00$2,960.00Develop Acceptance Test Plan85.0$1,500.00$2,500.00$0.00$4,085.00Subtotal505.0$7,200
  • 24. .00$9,494.00$750.00$17,949.00PROJECT DEVELOPMENTDevelop Components480.0$1,700.00$6,250.00$0.00$8,430.00Procure Software (Capital Equipment)200.0$400.00$15,500.00$0.00$16,100.00Procure Hardware (Capital Equipment)200.0$600.00$27,500.00$0.00$28,300.00Developme nt Acceptance Test Package200.0$1,200.00$1,000.00$0.00$2,400.00Perform Unit/Integration Test 180.0$650.00$1,000.00$0.00$1,830.00Subtotal1,260.0$4,550.00 $51,250.00$0.00$57,060.00PROJECT DELIVERYInstall System16.0$320.00$1,750.00$500.00$2,586.00Train Customers8.0$160.00$200.00$612.00$980.00Perform Acceptance Test24.0$480.00$500.00$0.00$1,004.00Perform Post Project Review24.0$480.00$0.00$0.00$504.00Provide Warranty Support8.0$160.00$0.00$0.00$168.00Archive Materials4.0$80.00$150.00$0.00$234.00Subtotal84.0$1,680.00$ 2,600.00$1,112.00$5,476.00PROJECT MANAGEMENTCustomer Progress Meetings/Reports480.0$1,000.00$0.00$0.00$1,480.00Internal Status Meetings/Reports480.0$1,000.00$0.00$0.00$1,480.00Subcontra ctors480.0$1,000.00$0.00$2,500.00$3,980.00Interface to Other Internal Departments480.0$1,000.00$0.00$0.00$1,480.00Configuration Management480.0$1,000.00$0.00$0.00$1,480.00Quality Assurance480.0$1,000.00$0.00$0.00$1,480.00Overall Project Management480.0$1,000.00$0.00$0.00$1,480.00Subtotal3,360. 0$7,000.00$0.00$2,500.00$12,860.00OTHER COSTTravel0.0$0.00$0.00$4,396.00$4,396.00Telecommunicati ons0.0$0.00$0.00$1,759.00$1,759.00Documentation0.0$0.00$0. 00$500.00$500.00Subtotal0.0$0.00$0.00$6,655.00$6,655.00Tot al Project Funding
  • 25. Requirements5209.0$20,430.00$63,344.00$11,017.00$100,000. 00 Development & TestingDevelopment & Testing Report - New Web Based Tool (testing results)Test Item Test Condition Expected Result Procedure Pass/FailDefect ID#Browser / DeviceBug Issue Description Owner CommentsSearch Form 1.aStable 5.00CompletePass325670.00Windows 8 (IE10)NoneJasmine McCordnavigation 1.aCritical 5.00Escallated to testing for fixFail325672.00Windows 8 (IE10)Cannot move mouse to menu area without it disappearing. (See screenshot) Jasmine McCordnavigation 1.bCritical 5.00Escallated to testing for fixFail325673.00Windows 8 (IE10)Cannot scroll on pages 4, 6, 8Jasmine McCordsearch form 1.bStable 5.00CompletePass325671.00Windows 8 (IE10)NoneJasmine McCordimage carousel 1-3.aCritical 5.00Escallated to testing for fixFail325674.00Windows 8 (IE10)The left and right arrows in box do nto scrollJasmine McCordCustomer Support Field 1.aCritical 5.00Escallated to testing for fixFail325675.00Windows 8 (IE10)Customer cannot submit form unless all required fields are filled outJasmine McCordNeed an extra 10 lead time for resolution Data Entry Field (feedback)Critical 5.00Escallated to testing for fixFail325676.00Windows 8 (IE10)Some fields get stuck when data entered --> customer cannot get passed field without restarting browserJasmine McCordNeed to resolve asap - Priority level Sheet2 Preliminary Project Charter Worksheet CPMGT/305 Version 12 1 University of Phoenix Material Preliminary Project Charter Worksheet
  • 26. Complete this project charter worksheet according to the instructions in section 4.1 of A Guide to the Project Management Body of Knowledge. Completed by: Learning Team A Date: 7/22/2017 1. Project title: New Web Based Tool 2. High-level project scope ( fewer than 50 words) A new performance management process will be created that utilizes a web-based system; providing a convenient way to document and track employee performance goals, provide regularly updated status reports, and a vehicle for managerial feedback. The system will use quantified data for salary/bonus treatment at year’s end. 3. Problem to be solved or opportunity to be realized by this project (fewer than 25 words) The new performance management system will provide an efficient way to quantify employee performance; providing a fairer, more accurate system for performance appraisals. 4. Project purpose or justification including specific measurable business impacts or results (fewer than 50 words) The new performance management system is needed because of the lack of accuracy in past employee performance reviews and merit increases. The new system will provide both qualitative and quantitative data metric data, which will result in providing more precise analysis of employee work performance. 5. Measurable project objectives and related success criteria including metrics (Provide three to four objectives with metrics) · Determine which performance measuring criteria should be implemented into the new system, and describe how the system utilizes it.
  • 27. · Develop performance management system platform · Integrate system into company website · Achieve increased employee performance of at least 15% within 12 months of implementation. 6. High-level requirements (fewer than 100 words) The performance management system project will require a hand-selected project team with extensive background in human resources and supervisory management. Two human resource clerks will participate, in addition to a single project manager. The team will also require the services of a software development consultant and her team of two software engineers. The project will be staged in a small suite of offices on the third-floor of the downtown Seattle office. The project will require the purchase of a new web server, and dedicated internet connection during preliminary stages prior to implementation in a production environment. 7. High-level risks (fewer than 100 words) Some high-level risks include: developmental delays, scope creep, excessive change requests, technical difficulties, lack of employee enthusiasm for new performance system. 8. Summary of high-level milestones schedule (identify the major deliverables and subtasks) 1. Develop Employee Performance Grading System · Analyze industry standards, averages · Create methodology for quantifying performance goals/results · Develop template for employee performance status reports
  • 28. · Create grading matrix for salary/bonus criteria 2. Develop software platform for Performance Grading System · Develop outline for software development · Create software for Performance Grading System · Pilot test group prior to production rollout · Work out bugs, smooth out feature set · Implementation 3. Company Intranet Integration · Implement Performance Management software into Web space · Develop supervisor feedback system that integrates with PMS · Test and Troubleshoot · Pilot software platform/web site · Full implementation 9. Summary of high-level budget including expense dollars, capital dollars, and headcount (identify costs for major deliverables and tasks identified in the preceding milestone schedule) Deliverables Estimated Cost Due Date DEVELOP FUNCTIONAL SPECIFICATIONS Labor Costs = $7,200
  • 29. September 9th, 2017 DEVELOP SYSTEM ARCHITECTURE Labor Costs = $7,000 October 15th, 2017 DEVELOP PRELIMANARY DESIGN SPECIFICATIONS Labor Costs = $4,500 October 18th, 2017 DEVELOP DETAILED DESIGN SPECIFICATIONS Labor Costs = $1,100 November 15th, 2017 DEVELOP COMPONENTS Labor Costs = $600 August 22th, 2017 PROCURE SOFTWARE Labor Costs = $7,200 March 28, 2017 DEVELOPMENT ACCEPTANCE TEST PACKAGE Labor Costs = $1,680 June 6th, 2018 PERFORM UNIT/INTEGRATION TEST Labor Costs = $7,000 July 6th, 2018 INSTALL SYSTEM Labor Costs = $3,200 July 10th, 2018 1 PROJECT PLAN OVERVIEW & PRELIMINARY PROJECT PLANProject Plan Overview & Preliminary Project Plan Team A: Project Selection Criterion One of the biggest decisions an organization makes is what projects to take on. Once a scope of work, bids or a proposal
  • 30. has been presented as project material, there are many factors to consider. The most valuable options should be chosen as well as considering goals and objectives of the portfolio of the organization. The benefits of the project as well as objectives are the main reason for choosing a project. Another thing to consider would be the feasibility, what is the likelihood of this project getting off the ground to completion. Timing must be well-thought-out for each project. Some projects are conducted in an emergency state, whereas, some are planned out far in advance. Budget is one of biggest reasons for a project to fail or be successful. A chosen project must maintain allocated funding from stakeholders. The first step for project selection is defining the project and the criteria thereof. The second step is to score the project for where it stands before other projects. The last step inform stakeholders for approvals For this particular project the criteria behind this project being chosen was the sales force needed a web-based tool that could help in managing client accounts, track sales and maintain customer proposals. It was chosen due to the value of customer satisfaction verses budget constraints. The benefits to cost ratio was analyzed and found to be a profitable advantage for the sales team and their customers. The payback period was examined; the findings were that within a five year period the payback would be higher than cost of project. As the sales team begin to manage their customers with a more organized position, they can take on more customers and keep satisfaction and personable service while maintaining production. Stakeholders chose this project for growth of clients. Another criteria for selection was time management. With the purchase and implementation of this web-based tool, the sales force will have the tools to preserve client accounts in a timely fashion. The web-based tool has the ability to notify sales and clients when their products are low. The tool is also has the ability to perform data-based functions. The sales team
  • 31. inputs what products the client has. The client uses the tool for production accountability. When stock gets low, the tool sends notification to that client’s sales person for further ordering direction. This cost value and customer satisfaction was criteria for stakeholder decision Overview The nature and scope of this project is to develop a web based tool for a client organization. Team A works for an information technology organization. A client has asked our organization to help build and implement a new web-based internal management system for their sales department to manage their customer accounts. Our client’s sales managers and sales executives will use this tool to develop account plans for their customers and to track their own sales results and be able to extract a sales report for each sales representative at each quarter. The focus of this project is to be able to deliver a program that sales representatives can manage easily anywhere and be able to pull statistical information about their clients and themselves and sales criteria. The purpose of this internal management system implementation is to help our clients sales department get more organized and be able to input their client’s information and be able to build programs specific to the needs of their clients. This implementation will also allow the sales representatives to be able to manage their client base much easier and be able to track their clients progress and also be able to keep up to date statistical information in their systems about their clients as well. This system is being customized and developed specifically to fit the needs of our client and requirements to meet the client’s needs internally. The long term goal is for our client to be able to manage their clients much better and be able to address their needs in a more specific fashion. We will be developing the project based on the following criteria; · A description of your internal client's requirements for this sales and account management system. · Identification and engagement of the appropriate stakeholders
  • 32. to define the requirements for the new system. · Development and testing of the system. · Implementation of the system. · A method for obtaining client feedback. Task Project Manager Due Date Owner A description of your internal client’s requirements for this sale and account management system TBD August 14, 2017 TBD Identification and engagement of the appropriate stakeholders to define the requirements for the new system. TBD August 14, 2017 TBD Development & Testing for the system TBD August 14, 2017 TBD A Method for obtaining client feedback TBD August 14, 2017 TBD Preliminary Project Schedule Preliminary Budgetary Plan Reference PMI (2013) Project Management Institute. A Guide to the
  • 33. Project Management Body of Knowledge (PMBOK Guide) - 5th Edition