SlideShare a Scribd company logo
Risk and Reliability response:
Blow Out Preventer Pull or No-pull decision support
• Pieter van Asten
• Decem ber 3rd
2014; Aberdeen
• IADC Well Control Europe Conference
Lloyd’s Register Energy - Drilling
Innovation comes after denial and before success
Pieter van Asten 2013
• The BOP risk m odel background
• why was it m ade and for what purpose?
• The project
• how was it done and by whom ?
• The solution
• what is the result and how is it used?
• The conclusion
• The Future
• continuous innovation: the way forward in
progress
Background
project
Solution
Conclusion
Future
Background
project
Solution
Conclusion
Society ….is all of us,
and our biggest stake is the safety of life and
environm ent for ourselves and our dear-ones.
ISO –IEC guide 51:
Safety is the freedom
of unacceptable risk
The tragic accident in April 2010 in the Gulf of Mexico can be
m arked as the m om ent that confirm ed the idea for m aking a
subsea BOP (Blow Out Preventer) risk m odel.
It showed that society, enabled by
(social-)m edia, is our biggest stakeholder
with its own risk acceptance perception.
Future
Background
project
Solution
Conclusion
Societal risk awareness and its (non-) acceptance created the need to
m anage these risks and becam e the foundation for the dem and for a
solution to enable this.
•The industry was faced with a very conservative
approach to BOP component failure.
•This conservatism was fed by the fear that
something could go as wrong as we all saw
happening but was also very costly.
A focal point of attention and contribution to what
happened in April 2010 becam e the subsea BOP.
Future
Background
project
Solution
Conclusion
With our stakeholder’s biggest concerns in focus, the objective of the
requested solution to us becam e:
“enable assistance in decision making if a
BOP needs to be pulled or not by means of
risk based consistent component failure
investigation and effect modelling and due
communication”
A subsea BOP is a special system and am ong few
system s com bining m ultiple functions:
•(drilling) operations control
•risk prevention tool (preventer)
•em ergency response tool
Future
A subsea BOP is also
•highly regulated
•not visible or well accessible when operational
These com binations m ean sim ple com ponent failures
can cause severe risk exposure and non-com pliance.
Background
project
Solution
Conclusion
But what to do when a com ponent m ay have or has failed?
Objective assessm ent and consistent com m unication about the
risk of a BOP com ponent to decide to continue or suspend
operations has proven to be challenging.
Future
Nowadays drilling operations are always balancing between
conflicting factors:
NPT (Costs) – Risk (Safety) - Com pliance
The challenge we faced only allowed for a truly
innovative approach.
Background
project
Solution
Conclusion
Future
•high (society and industry) stakes
•a joined effort with five involved parties
•no route-m ap but the m ain objectives
•an industry looking at us
Background
project
Solution
Conclusion
I worked with people that were involved in the extrem e
circum stances after the accident and who lost
colleagues
That m ade m e very hum ble and realizing we just could
not fail: there was too m uch at stake: safety and lives.
I worked with a wonderful team and this team effort,
including our client, was the one of the m ost
contributing factors for our success.
I am proud on what we did,
how we did it and what we achieved.
What made it succeed?
Future
Background
project
Solution
Conclusion
How is all this inform ation com bined
to becom e a Risk Model?
The total risk m odel is like a three dim ensional cube with six
sides that input and affect the outcom e and each other.
The cube’s three dim ensions represent
the com plexity and interaction of all aspects
of a com plete BOP risk m odel.
Future
Background
project
Solution
Conclusion
A BOP risk m odel assesses the effect of com ponent
failure taking regulations, specifications and
operational procedures into account.
Risk levels of the whole BOP, a subsystem or
com ponent are expressed in a color-coding traffic-
light alike.
•Red
•Orange
•Yellow
•Green
Future
Background
project
Solution
Conclusion
BOP risk m odel solution:
• Risk-based approach in balancing
the conflicting factors
• Consistent, transparent pull or no pull
decision assistance and m otivated
decision reporting all stakeholders
• Better prioritization of m aintenance
• Industry credit: done with a m ajor
drilling contractor
• Regulator agreem ent on
m ethodology (BSEE)
• Does not take away or replace thinking, com petence
or responsibility
• Enables training and can m ake what-ifs: play with
different failure scenarios
Future
Background
project
Solution
Conclusion The BOP risk m odel is a m ajor and
innovative first step towards a risk based
and transparent pull or no-pull decision
and com m unication to all stakeholders in
case of a subsea BOP com ponent failure.
Preventing one unnecessary BOPpull proves the value of a
BOPriskmodel.
Saving one life with a BOPriskmodel makes it invaluable
Being able to asses the risk of component failure is one
thing…..what about preventing that component from failing and
exposure to the risk of failure?
Future
Background
project
Solution
Conclusion
Future
Thankyoufor your attention.

More Related Content

Similar to IADC Aberdeen 2014 BOP presentation 0.1

Environmental Management_LEC04.pptx
Environmental Management_LEC04.pptxEnvironmental Management_LEC04.pptx
Environmental Management_LEC04.pptx
MonirulIslamEstiak
 
module_3b_eiaempcra_-_mar_2019.pptx
module_3b_eiaempcra_-_mar_2019.pptxmodule_3b_eiaempcra_-_mar_2019.pptx
module_3b_eiaempcra_-_mar_2019.pptx
AshishSingh140031
 
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Tim Christ Executive Leadership
 
3rd EIA Law, Policy and Institutional Arrangements.pptx
3rd EIA Law, Policy and Institutional Arrangements.pptx3rd EIA Law, Policy and Institutional Arrangements.pptx
3rd EIA Law, Policy and Institutional Arrangements.pptx
Abdiwali Abdullahi
 
Bridge RectifierPre-Lab InformationRectifiers are widely used .docx
Bridge RectifierPre-Lab InformationRectifiers are widely used .docxBridge RectifierPre-Lab InformationRectifiers are widely used .docx
Bridge RectifierPre-Lab InformationRectifiers are widely used .docx
AASTHA76
 
Risk.pdf
Risk.pdfRisk.pdf
Risk.pdf
hasan752746
 
Technology assessment
Technology assessmentTechnology assessment
Technology assessment
Lassonde School of Engineering
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
thanga2
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
thanga2
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Association for Project Management
 
PreventionMitigation_Philadelphia_Breakout.ppt
PreventionMitigation_Philadelphia_Breakout.pptPreventionMitigation_Philadelphia_Breakout.ppt
PreventionMitigation_Philadelphia_Breakout.ppt
JessaEraldinOrigines
 
eia.ppt
eia.ppteia.ppt
eia.ppt
eia.ppteia.ppt
eia.ppt
ssuser9035501
 
Mitigating operational impacts of developments - Stephen Inch
Mitigating operational impacts of developments - Stephen InchMitigating operational impacts of developments - Stephen Inch
Mitigating operational impacts of developments - Stephen Inch
IES / IAQM
 
Contemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentContemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessment
Nasiru Ibrahim Barda
 
4th EIA PROCESS.pptx
4th EIA PROCESS.pptx4th EIA PROCESS.pptx
4th EIA PROCESS.pptx
Abdiwali Abdullahi
 
Webinar - Using six sigma tools to analyze ehs performance metrics
Webinar - Using six sigma tools to analyze ehs performance metricsWebinar - Using six sigma tools to analyze ehs performance metrics
Webinar - Using six sigma tools to analyze ehs performance metrics
ProcessMAP Corporation
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
School of planning and architecture
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Song Love
 
Claims club, Exeter - September 2016
Claims club, Exeter - September 2016Claims club, Exeter - September 2016
Claims club, Exeter - September 2016
Browne Jacobson LLP
 

Similar to IADC Aberdeen 2014 BOP presentation 0.1 (20)

Environmental Management_LEC04.pptx
Environmental Management_LEC04.pptxEnvironmental Management_LEC04.pptx
Environmental Management_LEC04.pptx
 
module_3b_eiaempcra_-_mar_2019.pptx
module_3b_eiaempcra_-_mar_2019.pptxmodule_3b_eiaempcra_-_mar_2019.pptx
module_3b_eiaempcra_-_mar_2019.pptx
 
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
 
3rd EIA Law, Policy and Institutional Arrangements.pptx
3rd EIA Law, Policy and Institutional Arrangements.pptx3rd EIA Law, Policy and Institutional Arrangements.pptx
3rd EIA Law, Policy and Institutional Arrangements.pptx
 
Bridge RectifierPre-Lab InformationRectifiers are widely used .docx
Bridge RectifierPre-Lab InformationRectifiers are widely used .docxBridge RectifierPre-Lab InformationRectifiers are widely used .docx
Bridge RectifierPre-Lab InformationRectifiers are widely used .docx
 
Risk.pdf
Risk.pdfRisk.pdf
Risk.pdf
 
Technology assessment
Technology assessmentTechnology assessment
Technology assessment
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
 
PreventionMitigation_Philadelphia_Breakout.ppt
PreventionMitigation_Philadelphia_Breakout.pptPreventionMitigation_Philadelphia_Breakout.ppt
PreventionMitigation_Philadelphia_Breakout.ppt
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
Mitigating operational impacts of developments - Stephen Inch
Mitigating operational impacts of developments - Stephen InchMitigating operational impacts of developments - Stephen Inch
Mitigating operational impacts of developments - Stephen Inch
 
Contemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentContemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessment
 
4th EIA PROCESS.pptx
4th EIA PROCESS.pptx4th EIA PROCESS.pptx
4th EIA PROCESS.pptx
 
Webinar - Using six sigma tools to analyze ehs performance metrics
Webinar - Using six sigma tools to analyze ehs performance metricsWebinar - Using six sigma tools to analyze ehs performance metrics
Webinar - Using six sigma tools to analyze ehs performance metrics
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
 
Claims club, Exeter - September 2016
Claims club, Exeter - September 2016Claims club, Exeter - September 2016
Claims club, Exeter - September 2016
 

IADC Aberdeen 2014 BOP presentation 0.1

  • 1. Risk and Reliability response: Blow Out Preventer Pull or No-pull decision support • Pieter van Asten • Decem ber 3rd 2014; Aberdeen • IADC Well Control Europe Conference Lloyd’s Register Energy - Drilling
  • 2. Innovation comes after denial and before success Pieter van Asten 2013
  • 3. • The BOP risk m odel background • why was it m ade and for what purpose? • The project • how was it done and by whom ? • The solution • what is the result and how is it used? • The conclusion • The Future • continuous innovation: the way forward in progress Background project Solution Conclusion Future
  • 4. Background project Solution Conclusion Society ….is all of us, and our biggest stake is the safety of life and environm ent for ourselves and our dear-ones. ISO –IEC guide 51: Safety is the freedom of unacceptable risk The tragic accident in April 2010 in the Gulf of Mexico can be m arked as the m om ent that confirm ed the idea for m aking a subsea BOP (Blow Out Preventer) risk m odel. It showed that society, enabled by (social-)m edia, is our biggest stakeholder with its own risk acceptance perception. Future
  • 5. Background project Solution Conclusion Societal risk awareness and its (non-) acceptance created the need to m anage these risks and becam e the foundation for the dem and for a solution to enable this. •The industry was faced with a very conservative approach to BOP component failure. •This conservatism was fed by the fear that something could go as wrong as we all saw happening but was also very costly. A focal point of attention and contribution to what happened in April 2010 becam e the subsea BOP. Future
  • 6. Background project Solution Conclusion With our stakeholder’s biggest concerns in focus, the objective of the requested solution to us becam e: “enable assistance in decision making if a BOP needs to be pulled or not by means of risk based consistent component failure investigation and effect modelling and due communication” A subsea BOP is a special system and am ong few system s com bining m ultiple functions: •(drilling) operations control •risk prevention tool (preventer) •em ergency response tool Future
  • 7. A subsea BOP is also •highly regulated •not visible or well accessible when operational These com binations m ean sim ple com ponent failures can cause severe risk exposure and non-com pliance. Background project Solution Conclusion But what to do when a com ponent m ay have or has failed? Objective assessm ent and consistent com m unication about the risk of a BOP com ponent to decide to continue or suspend operations has proven to be challenging. Future
  • 8. Nowadays drilling operations are always balancing between conflicting factors: NPT (Costs) – Risk (Safety) - Com pliance The challenge we faced only allowed for a truly innovative approach. Background project Solution Conclusion Future •high (society and industry) stakes •a joined effort with five involved parties •no route-m ap but the m ain objectives •an industry looking at us
  • 9. Background project Solution Conclusion I worked with people that were involved in the extrem e circum stances after the accident and who lost colleagues That m ade m e very hum ble and realizing we just could not fail: there was too m uch at stake: safety and lives. I worked with a wonderful team and this team effort, including our client, was the one of the m ost contributing factors for our success. I am proud on what we did, how we did it and what we achieved. What made it succeed? Future
  • 10. Background project Solution Conclusion How is all this inform ation com bined to becom e a Risk Model? The total risk m odel is like a three dim ensional cube with six sides that input and affect the outcom e and each other. The cube’s three dim ensions represent the com plexity and interaction of all aspects of a com plete BOP risk m odel. Future
  • 11. Background project Solution Conclusion A BOP risk m odel assesses the effect of com ponent failure taking regulations, specifications and operational procedures into account. Risk levels of the whole BOP, a subsystem or com ponent are expressed in a color-coding traffic- light alike. •Red •Orange •Yellow •Green Future
  • 12. Background project Solution Conclusion BOP risk m odel solution: • Risk-based approach in balancing the conflicting factors • Consistent, transparent pull or no pull decision assistance and m otivated decision reporting all stakeholders • Better prioritization of m aintenance • Industry credit: done with a m ajor drilling contractor • Regulator agreem ent on m ethodology (BSEE) • Does not take away or replace thinking, com petence or responsibility • Enables training and can m ake what-ifs: play with different failure scenarios Future
  • 13. Background project Solution Conclusion The BOP risk m odel is a m ajor and innovative first step towards a risk based and transparent pull or no-pull decision and com m unication to all stakeholders in case of a subsea BOP com ponent failure. Preventing one unnecessary BOPpull proves the value of a BOPriskmodel. Saving one life with a BOPriskmodel makes it invaluable Being able to asses the risk of component failure is one thing…..what about preventing that component from failing and exposure to the risk of failure? Future