Summer 2017 Prepared by Supervised by
INFS7570 Applied Research Mohammad Balgoname Dr. John C. Turchek
Project Management Report
Green Computing Research Project
Document ID: 01
Version: 1.0
Release Date: May 15th
, 2017
Balgoname 2017
2
Table of Contents
1. Project Integration Management .............................................................................................................8
1.1 Definition of Green Computing...........................................................................................................8
1.3 Financial Analysis of Business case ...................................................................................................14
1.4 Project Charter..................................................................................................................................15
1.5 Integrated Project Change Control ...................................................................................................16
2. Project Scope Management....................................................................................................................20
2.1 Requirements Specifications.............................................................................................................20
2.1.1 Project Overview........................................................................................................................20
2.1.2 Purpose and Scope of this Specification....................................................................................20
2.1.3 Traceability Matrix.....................................................................................................................21
2.1.4 Questions for Project Sponsor...................................................................................................23
2.2 Project Scope Statement ..................................................................................................................23
2.3 Work Breakdown Structure 2.3.1 Work Breakdown Structure Table ..............................................24
2.3.2 Work Breakdown Structure Tree...............................................................................................26
2.4 Gantt Chart........................................................................................................................................27
3. Project Time Management .....................................................................................................................29
3.1 Review of WBS and Gantt Chart .......................................................................................................29
3.2 Project Milestones ............................................................................................................................30
3.3 Gantt Chart with Duration and Dependencies .................................................................................32
3.3.1 Gantt Chart.................................................................................................................................32
3.3.2 Network Diagram.......................................................................................................................32
3.4 Resource Assignment Matrix............................................................................................................33
4. Project Cost Management ......................................................................................................................36
4.1 Project Planned Cost Budget ............................................................................................................36
4.1.1 Weekly Budget...........................................................................................................................36
4.1.2 Resource Usage..........................................................................................................................38
4.2 Project BAC and Planned Value ........................................................................................................39
4.3 Earned Value Analysis.......................................................................................................................39
4.4 Corrective Actions.............................................................................................................................41
5. Project Quality Management..................................................................................................................43
5.1 Quality Management Requirements ................................................................................................43
5.1.1 Quality Management Approach.................................................................................................43
Balgoname 2017
3
5.1.2 Quality Objectives and Standards Identification .......................................................................43
5.1.3 Project Reviews and Assessments .............................................................................................44
5.1.4 Deliverable Acceptance Criteria.................................................................................................44
5.2 Seven Basic Tools of Quality .............................................................................................................45
5.3 Summary of High Quality Research Report ......................................................................................46
6. Project Human Resource Management..................................................................................................48
6.1 MBTI Types in Work Environments...................................................................................................48
6.1.1 MBTI Personality types ..............................................................................................................48
6.1.2 Introductory Email .....................................................................................................................50
6.2 Responsibility Assignment Matrix RACI ............................................................................................50
6.3 Human Resources Related Concerns................................................................................................52
7. Project Communication Management....................................................................................................55
7.1 Project Issue Log ...............................................................................................................................55
7.2 Applications of Wikis.........................................................................................................................56
7.3 Conflict Resolution............................................................................................................................57
8. Project Risk Management.......................................................................................................................60
8.1 Risk Register......................................................................................................................................60
8.2 Risk Assessment and Impact Matrix .................................................................................................61
8.3 Risk Response and Contingency Plans ..............................................................................................62
9. Project Procurement Management........................................................................................................64
9.1 Contract Agreement with Anne Consulting Firm..............................................................................64
9.2 Content of Research Report..............................................................................................................70
9.2.1 Executive Summary....................................................................................................................70
9.2.2 Table of Contents.......................................................................................................................70
9.3 Lesson Learned ...........................................................................................................................71
10. Periodic Reporting: Project Monitoring and Controlling ......................................................................73
10.1 Week 13 Work Progress..................................................................................................................73
10.1.1 Gantt Chart Update..................................................................................................................73
10.1.2 Network Diagram Update........................................................................................................74
10.1.3 Budget Report Update.............................................................................................................75
10.1.4 EVM Analysis............................................................................................................................75
10.1.5 Status Report ...........................................................................................................................76
10.2 Week 14 Work Progress..................................................................................................................77
Balgoname 2017
4
10.2.1 Gantt Chart Update..................................................................................................................77
10.2.2 Network Diagram Update........................................................................................................78
10.2.3 Budget Report Update.............................................................................................................79
10.2.4 EVM Analysis............................................................................................................................79
10.2.5 Status Report ...........................................................................................................................80
10.3 Week 15 Work Progress..................................................................................................................81
10.3.1 Gantt Chart Update..................................................................................................................81
10.3.2 Network Diagram Update........................................................................................................82
10.3.3 Budget Report Update.............................................................................................................83
10.3.4 EVM Analysis............................................................................................................................83
10.3.5 Status Report ...........................................................................................................................84
10.4 Week 16 Work Progress..................................................................................................................85
10.4.1 Gantt Chart Update..................................................................................................................85
10.4.2 Network Diagram Update........................................................................................................86
10.4.3 Budget Report Update.............................................................................................................87
10.4.4 EVM Analysis............................................................................................................................87
10.4.5 Status Report ...........................................................................................................................88
10.5 Week 17 Work Progress..................................................................................................................89
10.5.1 Gantt Chart Update..................................................................................................................89
10.5.2 Network Diagram Update........................................................................................................90
10.5.3 Budget Report Update.............................................................................................................91
10.5.4 EVM Analysis............................................................................................................................92
10.5.5 Status Report ...........................................................................................................................93
10.6 Week 18 Work Progress..................................................................................................................93
10.6.1 Gantt Chart Update..................................................................................................................93
10.6.2 Network Diagram Update........................................................................................................94
10.6.3 Budget Report Update.............................................................................................................95
10.6.4 EVM Analysis............................................................................................................................96
10.6.5 Status Report ...........................................................................................................................96
10.7 Week 19 Work Progress..................................................................................................................97
10.7.1 Gantt Chart Update..................................................................................................................97
10.7.2 Network Diagram Update........................................................................................................98
10.7.3 Budget Report Update.............................................................................................................99
Balgoname 2017
5
10.7.4 EVM Analysis............................................................................................................................99
10.7.5 Status Report .........................................................................................................................100
10.8 Week 20 Work Progress................................................................................................................101
10.8.1 Gantt Chart Update................................................................................................................101
10.8.2 Network Diagram Update......................................................................................................102
10.8.3 Budget Report Update...........................................................................................................103
10.8.4 EVM Analysis..........................................................................................................................103
10.8.5 Status Report .........................................................................................................................104
10.9 Week 21 Work Progress................................................................................................................105
10.9.1 Gantt Chart Update................................................................................................................105
10.9.2 Network Diagram Update......................................................................................................106
10.9.3 Budget Report Update...........................................................................................................107
10.9.4 EVM Analysis..........................................................................................................................107
10.9.5 Status Report .........................................................................................................................108
10.10 Week 22 Work Progress..............................................................................................................109
10.10.1 Gantt Chart Update..............................................................................................................109
10.10.2 Network Diagram Update....................................................................................................110
10.10.3 Budget Report Update.........................................................................................................111
10.10.4 EVM Analysis........................................................................................................................111
10.10.5 Status Report .......................................................................................................................112
10.11 Week 23 Work Progress..............................................................................................................113
10.11.1 Gantt Chart Update..............................................................................................................113
10.11.2 Network Diagram Update....................................................................................................114
10.11.3 Budget Report Update.........................................................................................................115
10.11.4 EVM Analysis........................................................................................................................115
10.11.5 Status Report .......................................................................................................................116
10.12 Week 24 Work Progress..............................................................................................................117
10.12.1 Gantt Chart Update..............................................................................................................117
10.12.2 Network Diagram Update....................................................................................................118
10.12.3 Budget Report Update.........................................................................................................119
10.12.4 EVM Analysis........................................................................................................................119
10.12.5 Status Report .......................................................................................................................120
10.13 Week 25 Work Progress..............................................................................................................121
Balgoname 2017
6
10.13.1 Gantt Chart Update..............................................................................................................121
10.13.2 Network Diagram Update....................................................................................................122
10.13.3 Budget Report Update.........................................................................................................123
10.13.4 EVM Analysis........................................................................................................................123
10.13.5 Status Report .......................................................................................................................124
10.14 Week 26 Work Progress..............................................................................................................125
10.14.1 Gantt Chart Update..............................................................................................................125
10.14.2 Network Diagram Update....................................................................................................126
10.14.3 Budget Report Update.........................................................................................................127
10.14.4 EVM Analysis........................................................................................................................127
10.14.5 Status Report .......................................................................................................................128
10.15 Week 27 Work Progress..............................................................................................................129
10.15.1 Gantt Chart Update..............................................................................................................129
10.15.2 Network Diagram Update....................................................................................................130
10.15.3 Budget Report Update.........................................................................................................131
10.15.4 EVM Analysis........................................................................................................................131
10.15.5 Status Report .......................................................................................................................132
Balgoname 2017
7
Part 1
Balgoname 2017
8
1. Project Integration Management
1.1 Definition of Green Computing
The concept of green computing has started to grow in the past few years, attaining
increasing popularity. Asides of the widespread sensitivity to ecological issues, such attention
also stems from economic needs, as both energy expenses and electrical requirements of IT
industry around the word show a continuously growing trend. This project aim is to define green
computing and provide actual application examples where green computing applications made a
positive impact.
The concept of green computing can be defined as "the environmentally responsible and
eco-friendly use of computers and their resources" (Techopedia, 2017). Green computing is also
defined as the examination of designing, manufacturing/engineering, utilizing and dumping of
computing devices in a way that lessens their environmental impact. Today, many IT
manufacturers and vendors are continually investing in designing energy efficient computing
devices, reducing the use of hazardous materials and encouraging the recyclability of digital
devices and papers. Recently, green computing concept expanded to include software code. The
advances of coding languages enabled the implementation of effective and efficient software
coding that saves power through making software less dependent on the use of hardware while
maintaining superior performance and less utilization of energy. (Singh & Vatta, 2016)
Green computing practices came into being in 1992 when the Environmental Protection
Agency (EPA) launched the Energy Star program - a government-backed labeling program that
helps individuals and organizations save money and reduce greenhouse gas emissions thought to
identify factories, office equipment, home appliances and electronics that have superior energy
efficiency. The EPA has more than 19,000 partner organizations across the United States to
Balgoname 2017
9
lessen emissions and achieve significant environmental and economic gains. EPA programs
prevent more that 416 million metric tons of U.S. GHG emissions. Also, reducing net energy
bills by more than $31 billion reductions in methane emissions by $7.7 billion in 2014 alone
(U.S. Environmental Protection Agency, 2016).
There are also other non-governmental organizations that support and apply green
computing concept throughout their organizations. One of these companies is VIA Technologies,
a Taiwanese company that manufactures motherboard chipsets, CPUs, and other computer
hardware. In 2001, VIA introduced an initiative for green computing that aims to design and
build efficient and effective hardware products that utilize less power. VIA's environmentally
friendly products are produced using a variety of clean-computing approaches. "In 2005, the VIA
launched its VIA C7-M and VIA C7 CPUs that have a maximum power consumption of 1W"
(Sultana, Suvarchala, & Ramay, 2016). These energy-efficient CPUs produced more than four
times less carbon during their operations and can be efficiently embedded in solar-powered
devices.
IBM is also one of the long supporters of green computing concept. In the 1960s, IBM
originated computer virtualization, which refers to the abstraction of computer resources, such as
the process of operating two or more logical computer systems on one set of physical hardware.
With virtualization capability, a system admin could merge many physical systems into virtual
machines on one single, robust system, thereby unplugging the original hardware and reducing
power and cooling consumption. Moreover, virtualization can assist in distributing work, so that
servers are either busy or put in a low-power sleep state.
Microsoft, Google, and Yahoo are addressing the environmental concerns about their
data center's carbon footprint, "the measure of the environmental impact of an individual or
Balgoname 2017
10
organization's lifestyle or operations, measured in units of carbon dioxide generated" (Rouse,
2010). In recent years, Microsoft and other corporations have built data centers in central
Washington to gain an advantage of the hydroelectric power produced by two dams in the
region. The Microsoft facility, which consumes up to 27 megawatts of energy at any given time,
is powered by hydroelectricity. Another Microsoft data center, located in Dublin, Ireland, that
started operation in 2009, thanks to Ireland's moderate climate, the 51,000-square-meter facility
is air cooled, making it 50& more energy-efficient than other comparable sized data warehouses.
(Kurp, 2008)
Google has committed to being carbon-neutral starting from 2007 and beyond, says Bill
Weihl, Google's director of energy strategy. According to Google, its data centers uses half the
industry's average amount of power. Google attributes this improved energy usage to the cooling
technologies, such as ultra-efficient evaporative cooling, that the company has customized for
itself. Yahoo’s data warehouses also went carbon-neutral, in part because of its use of carbon
offsets. (Kurp, 2008)
Many of industry-leading companies, such as Cisco Systems, Dell, Digital Reality,
Hewlett-Packard, IBM, and Intel to name few have joined efforts to reduce their carbon footprint
and promote the eco-friendlier environment through the establishment of a non-profit
organization called The Green Grid Association in 2007. The non-profit, open industry
consortium of information and communication technology (ICT) industry end-users, policy
makers, technology providers, facility architects have come together to improve data center and
IT resource efficiency globally, through sharing expertise and insights of best practices of
running data centers (The Green Grid, 2017). Overall green computing is a continuous non-
Balgoname 2017
11
endless innovation, and practices that make the use of hardware and software eco-friendlier and
saves energy and money. 1.2 Weighted Decision Matrix for Evaluation
The evaluation process of the project manager position of green computing research project
starts with identifying essential criteria that should be found in the nominees for this position.
After examining key characteristics of project manager, six criteria have been selected. Those
criteria are:
1. Project Management Experience
2. Knowledge level of IT
3. Leadership
4. Communication & Coordination
5. Analytical skills
6. Time Management
Each criterion is assigned by a rank of priority and weight factor which will be used to calculate
the final decision once candidates have been selected.
Table 1: Criteria selection
Once the priority has sorted, and weighted criteria, the process proceed to select candidates for
this position. Five candidates: Mia, Isabella, James, William, and Sophia nominated.
Balgoname 2017
12
Each candidate assigned points from a 1 – 10 scale. Then raw scores and weighted scores are
calculated to determine the rank of each candidate. The following chart shows the conclusion of
the decision matrix process.
Table 2: Decision Matrix
Based on the calculations that appear above, Mia has got the highest weighted score among other
candidates; therefore, she has been selected for this post. The following charts illustrate each
candidate weaknesses and straights. It also shows candidates total scores.
Balgoname 2017
13
Figure 2: Chart of total candidates’ scores
Figure 1: Chart of candidates’ straights and weaknesses
Balgoname 2017
14
1.3 Financial Analysis of Business case
Table 3: Project’s Financial Analysis
Balgoname 2017
15
1.4 Project Charter
PROJECT CHARTER
PROJECT NAME DATE AREA OF FOCUS
Green Computing Research 5/15/2017 Research and Development
BUSINESS CASE SCOPE
In line with our strategic goal, which is to help improve
the environment while increasing revenues and reducing
costs. The VP of Operations, Natalie called for starting a
green computing research project.
IN SCOPE OUT OF SCOPE
Thin client solutions Electronic waste disposal &
recycling
Development of green computing
solutions for internal use
Telecommuting Server resources virtualization Potential sale to other organizations
Open sources software Data center & Energy efficiency
MEASURABLE KEY DELIVERABLES
TARGET/GOAL DATE Financial analysis Standard work and reporting
Finalize Financial analysis 7/20/2017 Possible technologies to implement Orientation completion
Finalize recommended solutions 8/18/2017 Recommended Solutions
Finalize standard work and reporting 11/15/2017
SUCCESS FACTORS TIMELINE
Achieving scope of project ACTIONS/MILESTONES TARGET DATE/ STATUS
Meeting time constraint Development of high level requirements 5/18/2017
Execute project within budget Team job descriptions approval 5/21/2017
Achieving high quality processes Selection of team members 5/25/2017
STAKEHOLDERS FINANCIALS
NAME FUNCTION BUSINESS IMPACT INVESTMENT
Natalie VP of Operations The project shall provide environmental and financial
solutions that will save money and reduce the carbon
footprint of operating computers.
Total invested amount in the
project $356,000.00Ben CIO & project sponsor
Mia Project Manager
ASSUMPTIONS/ CONSTRAINTS RISK PLANNING
Project must complete in 6 moths Team members must be selected carefully as the project will be conducted online. Transacting
information among team members should be highly encrypted to assure the security.Team must be functioning by 5/15/2017
Work on project will be virtual (online
Sign-off:
VP of Operations: ……………… CIO & Project Sponsor: ……………… Project Manager: ………………
Balgoname 2017
16
1.5 Integrated Project Change Control
The principal focus of Integrated Change Control is to measure the impact of changes or
modifications on all project constraints. Changes to any component of the project might be
requested at any given time during the development of the project, especially during the project
executing & monitoring, or control phases. It is not essential to achieve all changes. In the
Perform Integrated Change Control, changes or modifications are accepted or rejected based on
their evaluation and impact to the project by the project Change Control Board (CCB).
Mainly, there are three reasons for change request which are: preventive actions, corrective
actions, and defect repair. Whenever a change is received, suggested, or identified, it will be
logged in the Change log of the project. Regardless of the size of the change or the impact of the
change, each and every change will be recorded in the Change Log. The project manager, Ms.
Mia, alone cannot do the impact analysis, inputs from the project team and if required from the
stakeholders are needed. In the impact analysis, the impact of the proposed change is analyzed
on all project constraints scope, cost, schedule, quality, or any other dimension. This is a critical
step in the process as impact analysis will be regarded as input for the change request’s rejection
or approval. Once the impact analysis is done, it should be provided to the CCB along with
change request for the decision of approval, postponed, or rejected.
In case the change request is approved, the work associated to change request becomes part of
the project, and all associated project documents, plans, and charter get updated. If the change or
modification request is postponed or rejected, the CCB will send to the project sponsor the
reasons of postponed or rejection. Finally, the Change Log will be updated for all details
regarding change request such as the decision that has been taken on, reasons for postponed, or
rejection, and if accepted follow-up steps.
Balgoname 2017
17
Figure 3: Flowchart of Change Request Process
Balgoname 2017
18
Change Request Form
Project Name Project Sponsor
S
T
E
P
1
Urgency
Change Request # Originator Change Requested by Date Requested
JUSTIFICATION
Description of Change Request #
Reason for Change
Proposed Approach to Resolve
PROJECT PLAN AREA IMPACT OF PROPOSED CHANGE(S)
S
T
E
P
2
IMPACT
Impact on Scope
Impact on Schedule
Impact on Spending
Impact on Risk
Other
APPROVALS TO PROCEED
S
T
E
P
3
Originator/ Date Project Manager Sponsor/ Date Customer/ Date
Table 4: Change Request Form
Balgoname 2017
19
Part 2
Balgoname 2017
20
2. Project Scope Management
2.1 Requirements Specifications
2.1.1 Project Overview
The project calls for researching possible eco-friendly technologies that reduce carbon footprint
to reduce global warming and save money to reduce the financial burden of the organization.
2.1.2 Purpose and Scope of this Specification
This requirements specification document describes the functions and requirements specified for
green computing research project. The purpose of the specification document is to apply
constraints to what and what not is included in the scope of the research. There are several
requirements for this project, including but not limited to the establishment of project charter,
plan, scope baseline, cost baseline, and activity plan.
In Scope
❖ Thin client solutions
❖ Electronic waste disposal & recycling
❖ Telecommuting
❖ Server resources virtualization
❖ Open sources software, and
❖ Data center & energy efficiency technologies
Out of Scope
❖ Development of green computing solutions for internal use
❖ Potential sale to other organizations
Balgoname 2017
21
2.1.3 Traceability Matrix
Requirements Traceability Matrix
Project Name: Green Computing Research Project
Cost Center: Environmental Technologies Program
Project Description: Researching possible green computing applications
ID Associated ID
Requirements
Description
Business Needs,
Opportunities, Goals,
Objectives
WBS
Deliverables
Owner Source Status
001
1.0 Project Charter Project Justifications Project Charter
Project
Sponsor
Business Case Accomplished
1.1 Team Selection Candidates screening and evaluation
Project Team
Formation
Project
Manager
Project Charter Ongoing
1.2 Project Management Plan
Project execution and control guide
documentation
Project
Management Plan
Project
Manager
Project Charter Ongoing
1.2.1 Scope Management Plan Collection of all project's processes Project Statement
Project
Manager
Project Charter Pending
1.2.2
Requirements Management
Plan
Documentation of project's
requirements
Project
Management Plan
Project
Manager
Project
Management Plan
Pending
1.2.2.1
Requirements
Documentation
Project’s definition, traceability
matrix, and deliverables
Requirements
Management Plan
Project
Manager
Requirements
Management Plan
Ongoing
Balgoname 2017
22
002
2.0 Develop WBS
Organizes team's work into
manageable sections
WBS
Project
Manager
Scope
Management Plan
Pending
2.1 Scope Baseline
Finalized WBS, WBS dictionary, and
the project scope statement
Scope
Management Plan
Project
Team
Scope
Management Plan
Pending
003
3.0 Schedule Management Plan
Establish policies and procedures used
to develop, execute, monitor and
control the project schedule
Schedule
Management Plan
Project
Team
Project
Management plan
Pending
3.1 Activity Plan
Develop detailed list of all project’s
activities
List of Activities
Project
Team
Project
Management plan
Pending
3.2 Schedule Baseline
Establish fixed timeline measurement
for accomplishment of project tasks
Schedule Baseline
Project
Manager
Schedule
Management Plan
Pending
004 4.0 Cost Baseline
Develop time-phased spending plan
for the project
Cost Baseline
Project
Manager
Cost Management
Plan
Pending
005 5.0
Stakeholder Management
Plan
Develop management strategies to
engage stakeholders effectively
Stakeholders
Registration
Project
Manager
Project
Management Plan
Pending
Table 5: Requirements Traceability Matrix
Balgoname 2017
23
2.1.4 Questions for Project Sponsor
▪ What is the project context, including organization's political considerations?
▪ What do you regard the main functions and features to be?
▪ What are your expectations of schedule and budget?
▪ What are the tradeoffs that will have to be made?
▪ What could be a high-level potential risk?
2.2 Project Scope Statement
Scope Statement
Project Name Green Computing Research Project
Project Manager Mia
Date 05/23/2017
Version History
Version Date Comments
1.0 05/16/2017 Preliminary Scope statement
2.0 5/23/2017 Finalized Scope Statement
Project Justifications
As a strategic goal for the Environmental Technologies program at the organization, this
project will help to improve the environment, while at the same time increase corporate
revenues and decrease computers operational costs. It also helps to promote a positive
corporate image and shows social responsibility.
Project Scope
To produce a comprehensive research report including detailed financial analysis and
recommendations on what green computing technologies can be applied internally and
potentially sold to other organization.
Project Deliverables
Financial analysis Recommended Solutions Orientation completion
Possible technologies to
implement
Standard work and reporting
Project Budget
Total invested amount in the project $356,000.00
Project Deadline
6 Months starting form 05/15/2017
Table 6: Scope Statement
Balgoname 2017
24
2.3 Work Breakdown Structure 2.3.1 Work Breakdown Structure Table
Work Breakdown Structure
Project Name Green Computing Research Project Project # 2
Project Manager Mia Sponsor Ben
Project Artifacts Business Case, and Risk Assessment Version 1.0
ID Task
Depen-
dencies
Status Cost Start Date
Planned
Completion
Estimate to
Completion
Actual
Completion
Resou-
rces
1 Project Initiation 1.0 Completed $21,747.00 05/15/2017 11 Mia, Ben
2 Team Member Selection 1.1 Completed 5,931.00 05/15/2017 3
3 Stakeholders Meeting 1.2 Completed 1,977.00 05/17/2017 1
4 Project Management Plan 1.3 Completed 7,908.00 05/18/2017 4
5 Project Scope Statement 1.4 Completed 1,977.00 05/21/2017 1
6 Project Change Control 1.4.1 Completed 1,977.00 05/21/2017 1
7 Charter Signed 1.4.1.1 Completed 1,977.00 05/22/2017 1
8 Planning 2.0 Ongoing $108,735.00 05/23/2017 55
Mia,
Project
Team
9 Project Kick-Off Meeting 2.1 Ongoing 1,977.00 05/23/2017 1
10 Develop Work Plan 2.2 Ongoing 59,310.00 05/24/2017 30
11 Develop Project Control Plan 2.3 Ongoing 39,540.00 06/23/2017 20
12 Finalize Project Plan 2.4 Ongoing 5,931.00 07/15/2017 3
13 Gain Approvals 2.5 Ongoing 1977.00 07/16/2017 1
15 Execution 3.0 Pending $205,608.00 07/17/2017 104
Mia,
Project
Team
16 Survey Analogous Researches 3.1 Pending 45,471.00 07/17/2017 23
17 Conduct Research 3.2 Pending 108,735.00 08/09/2017 55
18 Technologies Examination 3.2.1 Pending 39,540.00 10/4/2017 20
19 Analyze Findings 3.2.1.1 Pending 9,885.00 10/25/2017 5
20 Report Findings 3.3 Pending 1,977.00 10/30/2017 1
21 Monitoring and Controlling 4.0 Pending $2,117.00 11/01/2017 1 Mia
Balgoname 2017
25
24 Performance Reporting 4.1 Pending 2,117.00 11/01/2017 1
25 Closing 5.0 Pending $17,793.00 11/01/2017 9
Mia,
Project
Team
26 Conduct Post Project Review 5.1 Pending 15,816.00 11/4/2017 8
27 Approve Project Closeout 5.2 Pending 1,97700 11/14/2017 1
Total $356,000.00 180
Table 7: Work Breakdown Structure table
Balgoname 2017
26
2.3.2 Work Breakdown Structure Tree
Figure 4: Work Breakdown Structure Diagram
Balgoname 2017
27
2.4 Gantt Chart
Figure 5: Gantt Chart of the Project
Balgoname 2017
28
Part 3
Balgoname 2017
29
3. Project Time Management
3.1 Review of WBS and Gantt Chart
Figure 6: An updated WBS and Gant Chart
Shown above, an up-to-date picture of the WBS and Gantt chart. It includes all the dependencies,
milestones, and timeline. There are, however, few tasks that suggested to be added to the project.
Three tasks to be exact.
The first task is quality control monitoring. Since the scope of this project revolves around
research, there should be a quantitative and qualitative quality metrics that measure the processes
Balgoname 2017
30
of the project and its procedures. The role of this task is to assure that the work is not only done
as planned, but also in accordance with national and international quality standards.
The second suggested task is to establish a knowledge management (KM) logging to aid the
project team along the way. The KM log has short and long-term benefits to the project team and
the organization. When utilized correctly, it enables sharing of tacit knowledge among the
project team, which shorten the time required to perform tasks. It also benefits the organization
as its quality increase the more knowledge is logged.
The last suggested task for the project is communication coordination tool. Since two of the
project team are working remotely. It is important to facilitate the communication among the
project team systematically. Without such a tool, the work might get delayed, or done
incorrectly.
3.2 Project Milestones
The project has four milestones. Each milestone signifies a major achievement of the project's
components. The process of selecting project's milestones is based on SMART, which is an
acronym of four words that was created by Peter Drucker's Management by Objectives concepts.
Those four words are Specific, Measurable, Achievable, Relevant, and Time-bound (Drucker,
1954). Each of the three milestones is carefully selected to assure that it meets the criteria of
SMART. If one of these three milestones did not meet the constraints, it would cause problems
later the project life cycle.
The first milestone of green computing research project is the signature of the project charter. It
is chosen as the first milestone, due to the importance of this task. The signature of the project
charter means that everything that is required for the project to go is in place, including scope
Balgoname 2017
31
and time management, and budget. The second milestone is gaining the approval of the planning
phase. This milestone is of high importance due to the sensitivity of the entire planning phase. It
is known that during the planning phase, all the procedures, requirements, and tools get selected;
therefore, a successful planning shall increase the possibility of having a successful project.
The third milestone of this project is report the findings process, which is the final stage of the
research processes. This process has been selected as a milestone because it is the fruit of the
project and the final outcome. The last milestone of green computing research project is
conducting post review of the project. This task has been selected as a milestone due to the
importance of work review. No work is complete without its been reviewed. The rest of the
project procedures and tasks are not as important as the mentioned three processes; furthermore,
most of the tasks are pre-requisite for meeting the project's three milestones.
Balgoname 2017
32
Figure 7: Gantt Chart with milestones, and duration
3.3 Gantt Chart with Duration and Dependencies
3.3.1 Gantt Chart
3.3.2 Network Diagram
Figure 8: Network diagram of the project dependencies, and tasks
Balgoname 2017
33
3.4 Resource Assignment Matrix
Table 7: Resource Assignment Matrix
Shown above, is an assignment matrix of the project resources. As explained in the case, the
team consists of five team members including the project manager. Assumptions made while
assigning the resources matrix:
❖ The project sponsor and manager are responsible for selecting team members
❖ Full-time engagement in the project means 8 hours a day and six months commitment
Balgoname 2017
34
Three members of the team, the project manager, James, and Teresa are available 100% to
engage in the project. While two of members, Matt, and Lee are available 50% to engage in the
project. The project manager is responsible for monitoring and coordinating the project and team
members. She is also responsible for reporting performance of the team members. Meanwhile,
the remaining four members, Teresa, Matt, James, and Lee are responsible for executing the
research. They are also responsible for conducting the post-project review before the final
submission of the project. According to the case, attention should be drawn that, one of the team
members, Lee, will not be available to work on the project the first four weeks. He will join the
team during the planning phase and beyond. Outsourced labor are requested based on specific
tasks that require extra manpower, or certain expertise that is not available in the project
resources.
Balgoname 2017
35
Part 4
Balgoname 2017
36
4. Project Cost Management
4.1 Project Planned Cost Budget
4.1.1 Weekly Budget
Year Quarter Week Budget Cost
Baseline
Cost
Cost Actual Cost
2017
Q2
Week
17
4282.00
4282.00
4282.00 4282.00
Week
18
7980.00 8190.00 8190.00 8190.00
Week
19
4956.00 5005.00 5005.00 5005.00
Week
20
4956.00 5005.00 5005.00 5005.00
Week
21
4956.00 5005.00 5005.00 5005.00
Week
22
4956.00 5005.00 5005.00 5005.00
Week
23
4956.00 5005.00 5005.00 5005.00
Week
24
4100.00 4004.00 4004.00 4004.00
Q2 Total $41,142.00 $41,501.00 $41,501.00 $41,501.00
Q3
Week
25
7150.00 7260.00 7260.00 7260.00
Week
26
7150.00 7260.00 7260.00 7260.00
Week
27
7150.00 7260.00 7260.00 7260.00
Week
28
7150.00 7260.00 7260.00 7260.00
Week
29
12149.00 12251.00 12251.00 0.00
Week
30
16290.00 17300.00 17300.00 0.00
Week
31
16290.00 17300.00 17300.00 0.00
Week
32
16290.00 17300.00 17300.00 0.00
Week
33
16300.00 17300.00 17300.00 0.00
Week
34
13142.00 13284.00 13284.00 0.00
Balgoname 2017
37
Week
35
14430.00 14520.00 14520.00 0.00
Week
36
7150.00 7260.00 7260.00 0.00
Q 3 Total $140,641.00 $145,555.00 $145,555.00 $29,040.00
Q4
Week
37
7260.00 7260.00 7260.00 0.00
Week
38
7260.00 7260.00 7260.00 0.00
Week
39
7260.00 7260.00 7260.00 0.00
Week
40
7150.00 7260.00 7260.00 0.00
Week
41
7260.00 7260.00 7260.00 0.00
Week
42
7150.00 7260.00 7260.00 0.00
Week
43
7150.00 7260.00 7260.00 0.00
Week
44
7260.00 7260.00 7260.00 0.00
Week
45
8852.00 8952.00 8952.00 0.00
Week
46
14479.00 15975.00 15975.00 0.00
Week
47
18745.00 19475.00 19475.00 0.00
Week
48
18745.00 19475.00 19475.00 0.00
Q 4 Total $118,571.00 $121,957.00 $121,957.00 $-
2017 Total $300,354.00 $309,013.00 $309,013.00 $70,541.00
2018
Q1
Week
1
0.00 0.00 17153.00 0.00
Week
2
0.00 0.00 12078.00 0.00
Week
3
0.00 0.00 10090.00 0.00
Week
4
0.00 0.00 4036.00 0.00
Week
5
0.00 0.00 0.00 0.00
Week
6
0.00 0.00 0.00 0.00
Balgoname 2017
38
Week
7
0.00 0.00 0.00 0.00
Week
8
0.00 0.00 0.00 0.00
Week
9
0.00 0.00 0.00 0.00
Week
10
0.00 0.00 0.00 0.00
Week
11
0.00 0.00 0.00 0.00
Week
12
0.00 0.00 0.00 0.00
Q 1 Total $- $- $43,357.00 $-
2018 Total $- $- $43,357.00 $-
Grand Total $300,354.00 $309,013.00 $352,370.00 $70,541.00
Table 8: Weekly Budget
4.1.2 Resource Usage
Balgoname 2017
39
Figure 9: Gantt chart shows resource usage
Table 9: Resource usage total hours and cost
4.2 Project BAC and Planned Value
Budget at Completion and Planned Value
BAC $356,000.00
Planned Value
End of Week 4 (BAC x 0.10) $35,000.00
End of Week 8 (BAC x 0.25) $89,000.00
End of Week 12 (BAC x 0.50) $178,000.00
End of Week 15 (BAC x 0.60) $213,600.00
Table 10: BAC and PV values
4.3 Earned Value Analysis
Given
BAC $366,000.00
PV $180,500.00
EV $191,500.00
AC $206,500.00
Part (A)
CV = EV – AC = $ (15,000.00)
SV = EV – PV = $11,000.00
Balgoname 2017
40
CPI = EV / AC = 0.93
SPI = EV / PV = 1.06
Part (B)
EAC = BAC / CPI = $394,668.41
Table 11: Budget analysis
Figure 10: Earned Value Chart
Shown above, a chart for the earned value (EV) for the given problem. The five indexes, PV,
EV, AC, EAC, and BAC that have been utilized examines the Budget at Completion (BAC)
against the Variance at Completion (EAC). This project has a variance $28,668 from the planned
budget. This overspending occurred due to low-cost performance index (CPI) of this project at
0.93. The project is also behind schedule as the CPI and SPI indexes illustrate. This analysis, is
an alarming benchmark. The sponsor, and manager of this project have to take actions to return
this project on track to assure its successfulness.
$366,000.00
$180,500.00
$191,500.00
$206,500.00
$394,668.41
0
200000
400000
600000
800000
1000000
1200000
1400000
1600000
1 2 3 4 5 6
Earned Value Chart
EAC
AC
EV
PV
BAC
Timeline
Balgoname 2017
41
4.4 Corrective Actions
Many corrective actions can be made for this given problem to overcome it. First, before hiring
consultancy, the project manager has to ensure that he or she have clear specification
requirements documentation. The purpose of this document that it specifies in in-depth details
the processes and procedures to conduct the project. Any confusion this document causes will
cause defects, and errors, that eventually causes delays or complete failure of the project.
Another method that assures good outcomes is through measurable quality indexes. These
indexes are pre-determined by the project management office or the organization, which reflect
what work is considered meets the quality of a certain entity.
Lastly, while considering assigning consultant, it is better to test the company through the
Capability Maturity Model (CMM). This model is a ranking system consists of five ranks. A
company with level one is considered chaotic, while companies with level five considered well
established and provide quality work.
In this light, and when having good specification requirements, the project team or consultant is
closer to achieve better outcomes. A good specification requirement is a road map that illustrates
the details of the project including costs. A good quality matrix protects the project from any
creeps in scope or budget. Finally, selecting project team including consultants should be
systematic and using models such as CMM which identify good from bad consultant to assign.
Balgoname 2017
42
Part 5
Balgoname 2017
43
5. Project Quality Management
5.1 Quality Management Requirements
5.1.1 Quality Management Approach
The objectives of quality management for Green Computing Research Project are to assure:
❖ Project deliverable meet their standards
❖ Project management processes are appropriately developed.
Quality management is performed throughout the entire project lifecycle with attention to:
1. Quality Planning
2. Quality Assurance
3. Quality Control
4. Independent Verification and Validation (IV&V)
Quality management planning determines quality policies and procedures relevant to the project
for both project deliverables and project processes, defines who is responsible for what, and
documents compliance.
Key Component of Quality Management Plan
Objects of quality review Quality Measure Quality Evaluation Method
Project Deliverables Deliverables Quality Standards
Customers Satisfaction
Quality Control Activities
Project Processes Processes Quality Standards
Stakeholders Expectations
Quality Assurance Activities
Table 12: Components of QMP
5.1.2 Quality Objectives and Standards Identification
5.1.2.1 Project Deliverables
❖ The research should be well formulated, and the purpose of the study should be clear
❖ The research should be well designed and executed
❖ The research should demonstrate an understanding of related studies
❖ The research should utilize best available data and information
❖ The research assumptions should be explicit and justified
❖ The findings should advance knowledge and bear on important policy issues
❖ Implications and suggestions should be logical, warranted by the findings, and explained
thoroughly, with appropriate caveats
❖ Documentations should be accurate, understandable, clearly structured, and temperate in
tone
❖ The research should be compelling, useful, and relevant to stakeholders and decision
makers
❖ The research should be objective, independent, and balanced
5.1.2.2 Project Processes
❖ The PDCA Cycle
❖ Cause and Effect Diagram
Balgoname 2017
44
❖ Pareto Charts;
❖ Control Charts
❖ Maturity Models
5.1.3 Project Reviews and Assessments
Review Type Frequency Tools Reviewer Reports
Project Charter Constant reviews until
approval of charter
ISO, IEEE
Project
Manager
Attach finalized
reports of all reviews
conducted under the
project quality
management
document
Project Management Plan
Scope Management Plan
Requirements Management
Plan
Requirements Documentation Once after completion
WBS
Constant reviews
Microsoft
Project
Scope Baseline Microsoft
Project,
Microsoft
Excel
Schedule Management Plan
Activity Plan
Schedule Baseline
Cost Baseline
Stakeholder Management Plan Once after completion ISO, IEEE
Table 13: project reviews and assessments table
5.1.4 Deliverable Acceptance Criteria
Deliverable Final Approval Process Stakeholder Acceptance Criteria
Financial analysis Ongoing Proper mathematical calculations
Recommended Solutions Ongoing Based on logical comprehension
approachOrientation completion Ongoing
Possible technologies to implement Ongoing
Standard work and reporting Ongoing Follow American reporting and
citation standards
Table 14: project deliverable acceptation criteria table
Balgoname 2017
45
5.2 Seven Basic Tools of Quality
The Project Management Institute (PMI), references the seven basic tools in a guide to the
Project Management Body of Knowledge (PMBOK), as an example of a set of general tools
useful for planning or controlling project quality. The Seven Basic Tools of Quality is a name
given to a set of graphical models, which are identified as being most helpful in troubleshooting
issues related to quality. Since they are basic, they are easy to utilize as they require little formal
training in statistics. Also, they can be used to solve most of, much of quality related issues.
(Project Management Institute, 2013)
The seven tools are the following:
❖ Cause-and-effect diagram also known as the "Ishikawa diagram" or "fishbone"
❖ Control Chat
❖ Check sheet
❖ Pareto chart
❖ Histogram
❖ Scatter diagram
❖ Stratification (alternately, flow chart or run chart)
The Cause and Effect diagram can be utilized in Green Computing research to examines why
something happened or might happen by potential causes into smaller categories. It also can be
useful for showing the relationship between contributing factors. Another useful tool is the
histogram, which is a graphical depiction of how many times different, mutually exclusive
events are inspected in an experiment. The two explained tools and all other seven tools have to
be utilized in the project to guarantee more high level of quality.
Balgoname 2017
46
5.3 Summary of High Quality Research Report
In 2014, the Journal of Chemical and Pharmaceutical Sciences (JCHPS), published a report by
Namburi Anupama concerning green computing. Mr. Anupama has done phenomenal work in
explaining green computing. The report describes and defines in depth green computing and its
implications.
The paper aims to urge organizations to apply green computing through many practices, such as
saving energy during idle operation, using eco-friendly sources of energy, reducing harmful
effects of computing resources, and reducing computing wastes. Furthermore, the author
provided tangible examples where green computing practices have positively impacted
organization financially, environmentally, and socially.
For instance, one of the programs that were mentioned in this paper is about cooling database
centers through the leveraging of local climate to cool down data center instead of using air
conditions to do so. The program was effective and shown tremendous financial and
environmental benefits. (Anupama, 2014)
This paper is of high-quality sources that would aid the team in conducting the research due to
many facts. First, this paper has been revised by academic researchers and published in a
scientific journal. Second, the author has provided an excellent definition of green computing,
and its practices in the organization. Third, this report contains many useful sources that; when
considering, it will enlighten the project team to enrich their work further. Due to these reasons, I
believe this paper must be one of the sources that will be used to build upon out green computing
research.
Balgoname 2017
47
Part 6
Balgoname 2017
48
6. Project Human Resource Management
6.1 MBTI Types in Work Environments
6.1.1 MBTI Personality types
MBTI stands for The Myers-Briggs Type Indicator. MBTI was designed by Carl Jung’s theory
of psychological type. It indicates individuals’ personality preferences in four dimensions:
❖ Where individual focus his/her attention - Extraversion (E) or Introversion (I)
❖ The way individual take information - Sensing (S) or Intuition (N)
❖ How individual makes decisions - Thinking (T) or Feeling (F)
❖ How individual deal with the world - Judging (J) or Perceiving (P)
There are 16 unique MBTI personalities:
• ISTJ
• ISFJ
• INFJ
• INTJ
• ISTP
• ISFP
• INFP
• INTP
• ESTP
• ESFP
• ENFP
• ENTP
• ESTJ
• ESFJ
• ENFJ
• ENTJ
Each four letters make up individuals personality type. When individuals know their personality
type, it can help them understand their behavior and interacting with others better. While there
are no personalities better than others; there are, however, a preference to certain personality
types based on the nature of this project that requires the ability to conduct research. To narrow
the search scope of the preferred personality types. (Jung, 1971)
The 16 personality types can be break into four sub-sets:
Analysts
This group of personality type contains four personalities all of which revolve around analytical
skills. Those four personality types are: INTJ, INTP, ENTJ, and ENTP. The first personality
INTJ individual is an imaginative and strategic thinker. While INTP individual is an inventor
with a thirst for knowledge. The ENTJ personality individual is bold, imaginative and strong-
Balgoname 2017
49
willed leader, and always trying to find a way or solution to a certain problem. Lastly, ENTP
personality individual is a smart and curious thinker who cannot resist an intellectual challenge.
Diplomats
This group also contains four personality types whom skills lean toward diplomacy. Those four
types are INFJ, INFP, ENFJ, and ENFP. The INFJ individual is a quiet and mystical person, yet
very inspiring and tireless idealists. An individual with INFP personality type is a poetic, kind
and altruistic person, always eager to help a good cause. The ENFJ individual is charismatic and
inspiring leaders, and able to mesmerize their listeners. Lastly, the ENFP individual is
enthusiastic, creative and sociable free spirit, who can always find a reason to smile.
Sentinels
This four personality types group consists of ISTJ, ISFJ, ESTJ, and ESFJ. The first type ISTJ
individual is a rational and fact-minded individual, whose reliability cannot be doubted. The
second personality individual ISFJ is very dedicated and warm protector, and always ready to
defend their interests. The third personality individual, ESTJ is an excellent administrator, and
unsurpassed at managing things, or people. Finally, the ESFJ individual is an extraordinarily
caring, social, and accessible person and always eager to help.
Explorers
This group of four personality types consists of ISTP, ISFP, ESTP, and ESFP all of which have
skills related to exploration. The ISTP personality individual is a bold and practical
experimenter, and master of all kinds of tools. The ISFP individual is a flexible and charming
artist, and always ready to explore and experience something new. An individual with ESTP
personality type is a smart, energetic, and very perceptive person, who truly enjoy living on the
Balgoname 2017
50
edge. Lastly, ESFP individual is a spontaneous, energetic, and enthusiastic person, who is
admired by his peers. (Meade, 2017)
6.1.2 Introductory Email
Project team,
Myself and on behalf the project sponsor, I am delighted to welcome you to the Green
Computing Research Project. As you may all know that our project is a high priority to our
organization, as it will provide solutions to overcome the consumption of energy problem and
reduce the bad impact on our environment. Dear team members, I am fully confident in your
abilities to make this project reality. You all have shown good competencies and you have been
selected among others according to this fact. Thank you for being part of our team and I hope our
project with your participation and cooperation sees the light.
Best regards,
Project Manager
6.2 Responsibility Assignment Matrix RACI
The Responsibility Assignment Matrix (RAM), or Linear Responsibility Chart (LRC), represents
the participation by different duties in achieving tasks or deliverables for a project or business
process. It is valuable in defining duties and obligations in cross-functional/ departmental
projects and processes.
Assumptions for the RAM
The RACI acronym is derived from four key responsibilities most typically used:
❖ Responsible - Individuals who do the work to achieve the task
Balgoname 2017
51
❖ Accountable - The ultimately responsible person for the correct and thorough completion
of the deliverable or tasks
❖ Consulted - Individuals whose opinions are sought, typically subject matter experts
❖ Informed - Individuals who are kept up-to-date on progress
Table 15: Resources Assignment Matrix (RAM) with RACI responsibilities.
Balgoname 2017
52
6.3 Human Resources Related Concerns
Human resources are the most important element of any work. They are the real asset and
working power of any organization or organized work. The influence of human resources is so
powerful and reflects, either positively or negatively on their work based on the challenges and
circumstances. This paper spotlight some of the challenges and concerns that might encounter a
project's human resources.
There are many human resources contributing factors for project failure, such as stakeholders,
motivation, diversity in (culture, ethnicity, and protected groups), work environment. One factor
that contributes to project failure is related to the lack of project management expertise in an
organization. When a project team's risks are given little or no prominence, it creates resistance,
apathy, and lack of engagement, which have a significant impact on the procedures and timelines
of the project plan.
The project's human resource management is a multifaceted process. The project manager is
solely responsible for lead, direct and orchestrate the project team, customers, contributors,
partners, and any other stakeholders to achieve the desired results for the project's purpose,
which is a huge challenge and subject to wrong personal judgment. Therefore, throughout the
project, the project manager has to address project team retention, labor relations, and
performance appraisal and depending on the nature of the project work, health and safety
concerns.
The number of stakeholders in the project sometimes change; therefore, the project manager and
project team need to be aware of the incoming flux of interested parties and how this shift may
affect the dynamics of the project work and the project team. One approach to project human
Balgoname 2017
53
resources may work well in one phase of the project, yet it might not work in another phase due
to the stakeholders who involve. Since individuals drive processes, it is logical to build
competencies in employees’ management skills as well as in quantitative and analytical process
management. The project manager may have to pull together teams of employees who do not
work for the same organization. For instance, contractors view themselves as peers or colleagues
and where they must be managed differently from the organization's employees.
The workforce is diverse more than ever before, not only culturally and ethnically, but also in
other ways as well. It includes older workers, women, disabled individuals and other protected
groups by law from discrimination. Moreover, with the demands for skilled, high-tech workers at
all levels, employees’ searches span the globe and cross-cultural barriers. In project work
environment, organizations cannot offer permanent employment, nor can they guarantee raises,
benefits, job definition, management stability. Moreover, they cannot repay loyalty with loyalty
or hard work with compensation. Thus, the challenges of motivating employees go beyond their
abilities.
A stressful work environment results in stressed employees, and when employees are stressed,
they are more likely to make mistakes and perform at less than their optimal levels. The more
mistakes employees make, the worse they feel about their jobs and themselves, and the more
likely they are experience burnout. A high burnout rate leads to a high turnover rate, and
eventually, more time for a project manager spent on rehiring and retraining.
Staying within time and budget limits goes a long way toward stress-free project management
within the process and human resources issues that come with the job. Many problems can
happen to throw project processes off schedule; however, managing personnel matters properly
can do a great deal towards maintaining the project running smoothly.
Balgoname 2017
54
Part 7
Balgoname 2017
55
7. Project Communication Management
7.1 Project Issue Log
Project Green Computing Research Project
Project Manager Mia
Project Description Research possible green computing application for
internal use and possible sale to other organizations
ID Status Priority
(L/M/H)
Issue Disruption Assigned
to
Expected
Resolution
Date
Escalation
Required
(Y/N)
Impact Summary
1
Work in progress H Couple of team members do not
use the share site to post their
work and use e-mails instead.
Teressa 6/20/2017 Yes This issue hinders the progress
of work as it requires more time
to check on work done and
provide feedback though wiki
tools.
2 Open
M Some of team members are not
using webcams during conference
calls.
Matt 7/17/2017 Yes This issue prevents visualized
meetings, which enhance the
team meeting experience. It
also hinders the credibility to
participation.
3 Closed
L Lack of time commitment during
team meetings. Meeting times
goes beyond what is planned.
Project
Manager
7/20/2017 No This issue consumes some of
the team members time, which
can be spent on other
necessary work.
4
Open H Lack of enough date.
Recommendation deliverable is
behind schedule.
Teressa 7/28/2017 Yes This issue might cause possible
delay to the project as it part of
the project core.
Table 16: Issue Log
Balgoname 2017
56
7.2 Applications of Wikis
Wiki is one of the most common buzzwords on the internet. The term wiki means quick in
Hawaiian, and it also defined as a website tool that enables collaborative editing of its content
and structure by its users. What makes wiki a useful instrument in the project work, is it
collaborative editing environment that allows brainstorming, and discussion of various ideas
without the need of having the participants in one place. Wiki is widely adapted in many
organization today, due to its swiftness, and effectiveness of allowing participants to generate
contents. (LeBar, 2017)
Some of the project team members have concerns about using wiki because they do not want
other team members to change, or edit their work; therefore, they are not using the wiki tool to
post their work. They instead use the email to send their work, which consumes a precious time
for the rest of the team. The use of wiki can be very chaotic or very organized. If there are rules
and policies of using wikis, the tool is organized and fruitful; on another hand, if there are no
rules or policies on who do what, the tool is causing chaos. Having rules and policies of using
wiki will satisfy the concerns of some of the team members and assure the effectiveness of
utilizing the tool.
In conclusion, wiki is very valuable tool, given the nature of the project is heavily research. It
will allow team members to brainstorm and share their ideas, which will positively reflect on the
work. The fact, that wiki is a tool that allow participant to share and edit the content, made some
of the project members withdrawal from participating and preferred traditional communication
method – the e-mails. However, if there are rules and polices of the way participant generate,
edit, and share content, the team members’ concerns are solved.
Balgoname 2017
57
7.3 Conflict Resolution
As part of the project management, there must be a method to approach conflict and control it in
a way that limits the negative impact on the project and the team. Conflict management is the
means of limiting the adverse aspects of conflict while increasing the positive side of the
conflict. The purpose of conflict management is to enhance learning and group outcomes,
including effectiveness or performance in an organization setting. When conflicts managed
properly, it can improve team results and reduces the negative impact
Conflict resolution is a method for two or more parties to find a peaceful solution to
disagreement among them, due to personal, financial, political, or emotional reasons. Conflict
resolution conceptualized as the method and processes implicated in facilitating the peaceful
ending of conflict. A project manager can attempt to resolve a conflict by communicating about
conflicting ideologies, or motives to the individual(s), and by involving in bilateral negotiation.
There are procedures for addressing conflicts, including negotiation, mediation, and arbitration. .
(Afzalur Rahim, 2002)
For the Green Computing Research Project, the aim of conflict resolution is to solve a problem
through negotiation immediately, once a problem or conflict occurs. By doing so, most of the
conflicts would not escalate to require mediation and or arbitration. the project, few conflicts
occurred among the project team in the communication management. Here are some of these
issues and how they can be solved.
First, James and other team members did not seem uncomfortable using collaboration tools to
post their work, arguing that other team members might change, or edit their work, which
eventually leads to delaying the work and impedes the progress of the project. Solving this issue
requires knowing that one's enemy is unknowingness; in this case, it is possible that the team
members are not aware of how to use the wiki tool and control it in a way that allows only
authorized an individual to edit a certain post. It is also recommended during the training
Balgoname 2017
58
sessions to explain how to use wiki tool efficiently and adequately and at the same time
emphasize the benefits that it brings to the project and its team members from agility, flexibility,
and security.
Another conflict arose while in project management was that some team members failed to use
webcams during team meetings. In this case, the project manager should stress the importance of
having webcam during video conferences. Since few of the project team are working remotely, it
makes them feel isolated from the work environment and lead to losing their motivation to work.
Having a webcam during conferences stimulates the team members to work better because they
are metaphorically meeting face-to-face with their peers and it also increases the participant's
seriousness to share their arguments and inputs.
Another issue that arose was that during meetings the team did not adhere to the predetermined
meeting time, which affects other team members because they are occupied with other important
matters. The project manager should state three important policies at the beginning of each
meeting to increase the effectiveness of meetings. First, the manager should indicate the subject
of the meeting, what and what not it includes for discussion during the meeting. The project
manager also must remind the team of the meeting time boundaries, when it starts, and when it
ends. Finally, it is important that the project manager state what he or she is looking forward to
accomplishing by the end of the meeting.
Overall, conflicts are an inevitable matter. It could be caused for legitimate or illegitimate
reasons, and it might happen anytime. The ability to deal with conflict and manage it is
extremely important to assure a steady progress of the work. There are many approaches to
achieving conflict resolution such as negotiation, mediation, and arbitration. The leader's ability
to encounter conflicts and solve them are a pivotal point that can sway the dispute to an end or an
escalation.
Balgoname 2017
59
Part 8
Balgoname 2017
60
8. Project Risk Management
8.1 Risk Register
Table 17: Risk register table contacting seven possible risks for Green Computing Project
Balgoname 2017
61
8.2 Risk Assessment and Impact Matrix
Table 18: Risk Assessment and Impact matrix
Balgoname 2017
62
Table 19: Risk Response and Contingency Plans
8.3 Risk Response and Contingency Plans
Balgoname 2017
63
Part 9
Balgoname 2017
64
9. Project Procurement Management
9.1 Contract Agreement with Anne Consulting Firm
Service Contract Agreement
THIS SERVICE AGREEMENT (the “Agreement”) dated this 5th
day of July, 2017
BETWEEN:
We Are Big, Inc.
(the “Client”)
-AND-
Anne Consulting
(the “Contractor”).
BACKGROUND:
A. The Client is of the evaluation that the Contractor has the required experience, abilities,
and qualifications to provide services to the Client.
B. The Contractor is amenable to granting such services to the Client on the conditions and
terms set out in this Agreement.
IN CONSIDERATION OF the matters explained above and of the mutual benefits and
commitment outlined in this Agreement, the receipt and sufficiency of which consideration is
hereby acknowledged, the Client and the Contractor (independently the “Party” and collectively
the “Parties” to this Agreement) agree as follows:
Services Provided
1. The Client hereby accepts to engage the Contractor to provide the Client with the
following services (the “Services”):
• Support project team in research work to generate ideas for green computing
• Provide consultants for the project as per need for the project
2. The Services will include any other duties which the Parties shall agree on. The
Contractor hereby consents to provide such Services to the Client.
Balgoname 2017
65
Term of Agreement.
3. The term in this Agreement (the “Term”) will be effective on the date of this Agreement
and will abide in full force effect until the completion of the Services, subject to earlier
termination as provided in this Agreement. The Term of this Agreement may be extended
with the written consent of the Parties.
4. In the event that either Party violates an article provision under this Agreement, the non-
defaulting Party against all reasonable damages.
Performance
5. The Parties consent to do everything necessary to ensure that the terms of this Agreement
take effect.
6. Except as otherwise granted in this Agreement, all monetary amounts indicated to in this
Agreement are in US Dollars (USD).
Compensation
7. The Contractor will charge the Client an hourly rate of $190.00 for Anne’s Services. The
Contractor will also charge the Client $150.00 per hour for any other consultants that is
subject to a maximum of 100 hours (the “Compensation”).
8. The Client will be billed when the Services are finished.
9. Invoices handed by the Contractor to the Client are due within 30 days of submission.
10. In the event that the Client ended this Agreement prior to completion of the Services, but
where the Services have been partly performed, the Contractor will be entitled to pro rata
payment of the Compensation to the date of end provided that there has been no breach of
contract on the part of the Contractor.
11. The Compensation as declared in this Agreement does not include sales tax or other
applicable duties as may be required by law. Any charges and sales tax required by law
will be charged to the Client in addition to the Compensation.
Reimbursement of Expenses
12. The Contractor will be repaid from time to time for reasonable and necessary expenses
incurred by the Contractor in relation to providing the Services.
Balgoname 2017
66
13. All expenditures must be previously approved by the Client.
Confidentiality
14. Confidential information (the “Confidential Information”) attributes to any data or
information relating to the business of the Client that would reasonably be considered to
be proprietary to the Client including, but not limited to, business processes, accounting
records, and client records and that is not generally known in the industry of the Client
and wherever the reveal of that Confidential Information could reasonably be expected to
cause harm to the Client.
15. The Contactor agrees that they will not disclose, divulge reveal, report or use for any
purpose, any confidential information that the Contractor has obtained, except as
authorized by the Client or as required by law. The responsibilities of confidentiality will
apply during the term of this Agreement and will survive indefinitely upon termination of
this Agreement.
16. All oral and written information and materials disclosed or provided by the Client to the
Contractor under this Agreement are Confidential Information despite whether it was
provided before or after the date of this Agreement or how it was presented to the
Contractor.
Ownership of Intellectual Property
17. All intellectual property and associated material, including any trade secret, moral rights,
goodwill, relevant registrations or applications for registration, and rights in any
copyright, patent, trademark, trade dress, industrial design and trade name (the
“Intellectual Property”) that is produced or developed under this Agreement, is a “work
made for hire” and will be the individual property of the Client. The utilize of the
Intellectual Property by the Client will not be bound in any way.
18. The Contractor may not utilize the Intellectual Property for any purpose other than that
contracted for in this Agreement except with the written agreement of the Client. The
Contractor will be liable for any and all damages occurring from the unauthorized
utilization of the Intellectual Property.
Return of Property
Balgoname 2017
67
19. Upon the expiration or termination of this Agreement, the Contractor will return to the
Client any property, records, documentation, or Confidential Information which is the
property of the Client.
Capacity/Independent Contractor
20. In providing the Services in accordance with this Agreement, it is expressly agreed that
the Contractor is acting as an autonomous contractor and not as an employee. The
Contractor and the Client reckon that this Agreement does not constitute a joint venture
or partnership between them, and is solely a contract for service. The Client is not
required to pay, or make any contributions to, any social security, local, state or federal
tax, unemployment compensation, workers’ compensations, insurance premium, profit-
sharing, pension or any other employee benefit for the Contractor during the Term. The
Contractor is obligated for paying and complying with reporting requirements for, all
local, state and federal taxes associated with payments made to the Contractor under this
Agreement.
Notice
21. All notices, requests, demands or other communications required or permitted by the
terms of this Agreement will be given in writing and hand over to the Parties at the
following addresses:
• 700 Liberty Ave, Pittsburgh, PA 15222
• 201 Fifth Ave, Pittsburgh, PA 15222
Or to other address as either Party shall notify the other, and will be deemed to be
properly hand over (a) immediately upon being served personally, (b) two days after
being deposited with the postal service is served by registered mail, or (c) the following
day after being deposited with an overnight courier.
Indemnification
22. Except to the amount paid in settlement from any applicable insurance policies, and to
the extent permitted by applicable law, each Party accepts to indemnify and hold
harmless the other Party, and its respective employees, officers, agents, affiliates,
Balgoname 2017
68
officers, and permitted successors and assigns against any and all claims, damages,
losses, penalties, liabilities, punitive damages, expenses, reasonable legal fees and costs
of any kind or amount whatsoever, which arise or result from out of any act or omission
of the indemnifying party, its own affiliates, officers, agents, employees, and permitted
successors and assigns that occurs in connection with this Agreement.
Modification of Agreement
23. Any amendment or modification of this Agreement or additional obligation assumed by
either Party in connection with this Agreement will only be obligated if evidenced in
writing signed by each Party or an authorized representative of each Party.
Time of the Essence
24. Time is the essence in this Agreement. No variation or extension of this Agreement will
operate as a waiver of this provision.
Assignment
25. The Contractor will not willingly, or by operation of law, assign or otherwise transfer its
obligations under this Agreement without the prior written approval of the Client.
Entire Agreement
26. It is agreed that there is no representation, warranty, collateral agreement or condition
affecting this Agreement except as expressly provided in this Agreement.
Enurement
27. This Agreement will guarantee to the benefit of and be binding upon the Parties and their
respective administrators, executors, heirs, and permitted successors and assigns.
Titles/Headings
28. Headings are inserted for the convenience of the Parties only and are not to be considered
when interpreting this Agreement.
Gender
Balgoname 2017
69
29. Words in the plural mean and include the singular and vice versa. Words in the masculine
mean and include the feminine and vice versa.
Governing Law
30. This Agreement will be ruled by and construed in accordance with the law of the State of
Pennsylvania.
Severability
31. In the event where any of the terms of this Agreement are held to be unenforceable or
invalid in whole or in part, all other terms will nevertheless continue to be enforceable
and valid with the invalid or unenforceable parts severed from the remainder of this
Agreement.
Waiver
32. The waiver by either Party of a delay, breach, default, or omission of any of the
provisions of this Agreement by the opposite Party will not be construed as a waiver of
any following breach of the same or other provisions.
IN WITNESS OF THIS the Parties have duly affixed their signatures under hand and seal on
this 5th
day of July 2017
___We Are Big, Inc._________________
____________________________(Client)
__Anne Consulting__________________
________________________(Contractor)
Balgoname 2017
70
9.2 Content of Research Report
9.2.1 Executive Summary
This project was commissioned by the Environment Technologies Program of We Are Big, Inc.
The project aims to find possible green computing technologies that reduces energy consumption
and increases the efficiency of computing power. Green computing or eco-friendly computing is
a term that refers to the environmental responsibility use of computers and their resources, where
the designing, engineering, manufacturing, and disposing of computing devices have minimal
impact on the environment. Through researching, the project team will work to generate ideas,
methods, and technologies that work in accordance with the definition of green computing and
based on the financial analysis. The prospect outcomes will help the We Are Big, Inc. to
rationalize energy consumption, which would reflect on savings of budget money. Once the
technology proves effective, the company aims to provide its expertise and technologies to other
company to harvest the benefits of green computing.
9.2.2 Table of Contents
Preface …………………………………………………………………………………………. 2
Executive Summary ……………………………………………………………………………. 3
Table of Content ………………………………….……………………………………….……. 4
Introduction ……………………………………………………………………………………... 5
Green computing Solutions …………………………………………………………………..…. 8
Financial Analysis …………………………………………………………………………….... 10
Conclusion ……………………………………………………………………………………... 12
Balgoname 2017
71
9.3Lesson Learned
1. Having a realistic financial planning will allow the project manager to avoid spending issues
during the span of project life cycle.
2. The quality of the project is how it is defined; therefore, it is important to search for best
standards, and practices to guarantee optimum results.
3. Outsourced labors do overcome workers shortages; however, it is tough to control the work
quality.
4. Conflicts among team members are inevitable, therefore, the project manager ability to
resolve conflicts is very crucial to maintain the progress of the project and avoid expensive
costs.
Balgoname 2017
72
Part 10
Balgoname 2017
73
10. Periodic Reporting: Project Monitoring and Controlling
10.1 Week 13 Work Progress
10.1.1 Gantt Chart Update
Balgoname 2017
74
10.1.2 Network Diagram Update
Balgoname 2017
75
10.1.3 Budget Report Update
10.1.4 EVM Analysis
Balgoname 2017
76
10.1.5 Status Report
Week 13 goes as planned with work and budget. Currently, the project team has successfully
finished the first two phases – initiation, and planning. We are waiting for the approval to
proceed with the project execution. The indexes of schedule performance (SPI) and cost
performance (CPI) are showing a positive performance of the project processes.
Balgoname 2017
77
10.2 Week 14 Work Progress
10.2.1 Gantt Chart Update
Balgoname 2017
78
10.2.2 Network Diagram Update
Balgoname 2017
79
10.2.3 Budget Report Update
10.2.4 EVM Analysis
Balgoname 2017
80
10.2.5 Status Report
Week 14 goes as planned with work but with a variance of actual spending that is less than
budget by $6,250. So far, the project team has successfully finished the processes of the second
phases – planning. We are currently waiting for the sponsor approval to proceed with the project
execution. The project Schedule Performance Index (SPI) is indicating a normal progress, while
Cost Performance Index (CPI) is showing a positive performance due to the cost variance.
Balgoname 2017
81
10.3 Week 15 Work Progress
10.3.1 Gantt Chart Update
Balgoname 2017
82
10.3.2 Network Diagram Update
Balgoname 2017
83
10.3.3 Budget Report Update
10.3.4 EVM Analysis
Balgoname 2017
84
10.3.5 Status Report
Week 15 goes as planned with work and budget. Currently, the project team has successfully
finished the first two phases – initiation, and planning. The project team received the approval to
proceed with the project execution. The indexes of schedule performance (SPI) and cost
performance (CPI) are showing a positive performance of the project processes.
Balgoname 2017
85
10.4 Week 16 Work Progress
10.4.1 Gantt Chart Update
Balgoname 2017
86
10.4.2 Network Diagram Update
Balgoname 2017
87
10.4.3 Budget Report Update
10.4.4 EVM Analysis
Balgoname 2017
88
10.4.5 Status Report
Week 16 goes as planned with work but with a positive variance of actual spending that is more
than budget by $6,250. So far, the project team has successfully finished the processes of the
second phases – planning. Currently, the project team are executing the first task of the project’s
WBS. The project Schedule Performance Index (SPI) and Cost Performance Index (CPI) are
showing a normal progress.
Balgoname 2017
89
10.5 Week 17 Work Progress
10.5.1 Gantt Chart Update
Balgoname 2017
90
10.5.2 Network Diagram Update
Balgoname 2017
91
10.5.3 Budget Report Update
Balgoname 2017
92
10.5.4 EVM Analysis
Balgoname 2017
93
10.5.5 Status Report
Week 17 goes as planned with work and budget. Currently, the project team has successfully
finished the first two phases – initiation, and planning. The project team has successfully finished
the processes of the first task of the execution phases – survey analogues researches and
currently, they are executing the second task of the project’s WBS. The indexes of schedule
performance (SPI) and cost performance (CPI) are showing a positive performance of the project
processes.
10.6 Week 18 Work Progress
10.6.1 Gantt Chart Update
Balgoname 2017
94
10.6.2 Network Diagram Update
Balgoname 2017
95
10.6.3 Budget Report Update
Balgoname 2017
96
10.6.4 EVM Analysis
10.6.5 Status Report
Week 18 went as planned schedule and budget. Both cost and schedule performance indexes are
indicating a normal to positive work progress
Balgoname 2017
97
10.7 Week 19 Work Progress
10.7.1 Gantt Chart Update
Balgoname 2017
98
10.7.2 Network Diagram Update
Balgoname 2017
99
10.7.3 Budget Report Update
10.7.4 EVM Analysis
Balgoname 2017
100
10.7.5 Status Report
Only 50% of scheduled work has been done while planned budget has been consumed. Both
schedule and cost performance indexes are showing a negative progress.
Balgoname 2017
101
10.8 Week 20 Work Progress
10.8.1 Gantt Chart Update
Balgoname 2017
102
10.8.2 Network Diagram Update
Balgoname 2017
103
10.8.3 Budget Report Update
10.8.4 EVM Analysis
Balgoname 2017
104
10.8.5 Status Report
Only one-half of what was planned got completed, but spend all the budget on the tasks
scheduled for week 20. We have not expected any delays as we have rescheduled delayed work
to meet the deadline. Based on the schedule and cost performance indexes, during weeks 5, and 6
work was ahead of what was scheduled, which will substitute to the delays occurred week 20.
Balgoname 2017
105
10.9 Week 21 Work Progress
10.9.1 Gantt Chart Update
Balgoname 2017
106
10.9.2 Network Diagram Update
Balgoname 2017
107
10.9.3 Budget Report Update
10.9.4 EVM Analysis
Balgoname 2017
108
10.9.5 Status Report
Week 21 went as planned. The delays occurred during week 20 has been taken care of and work
is gradually moving to planned schedule thanks to the actions that have been taken to overcome
the schedule issues.
Balgoname 2017
109
10.10 Week 22 Work Progress
10.10.1 Gantt Chart Update
Balgoname 2017
110
10.10.2 Network Diagram Update
Balgoname 2017
111
10.10.3 Budget Report Update
10.10.4 EVM Analysis
Balgoname 2017
112
10.10.5 Status Report
Total work planned is completed for this stage of the project and budget meets the original
budget for week 22. Based on the schedule and cost performance indexes, the project is
progressing as scheduled with no positive or negative variance of the budgeted costs.
Balgoname 2017
113
10.11 Week 23 Work Progress
10.11.1 Gantt Chart Update
Balgoname 2017
114
10.11.2 Network Diagram Update
Balgoname 2017
115
10.11.3 Budget Report Update
10.11.4 EVM Analysis
Balgoname 2017
116
10.11.5 Status Report
Only one-half of scheduled work has been achieved during week 23. We have experienced a
positive variance of budgeted costs by $7,000 more. The project manager with the project team
has met to discuss options that can be taken to overcome this problem.
Balgoname 2017
117
10.12 Week 24 Work Progress
10.12.1 Gantt Chart Update
Balgoname 2017
118
10.12.2 Network Diagram Update
Balgoname 2017
119
10.12.3 Budget Report Update
10.12.4 EVM Analysis
Balgoname 2017
120
10.12.5 Status Report
Week 24 went as planned with schedule and budget. Based on the cost and schedule performance
indexes for this week, the project has been affected by week’s 23 delays and over spending. The
project manager is assessing the possibility of eliminating some of executable tasks of the project
if the schedule performance does not meet the planned schedule time by week 26.
Balgoname 2017
121
10.13 Week 25 Work Progress
10.13.1 Gantt Chart Update
Balgoname 2017
122
10.13.2 Network Diagram Update
Balgoname 2017
123
10.13.3 Budget Report Update
10.13.4 EVM Analysis
Balgoname 2017
124
10.13.5 Status Report
Week 25 went as planned with budget and schedule.
Balgoname 2017
125
10.14 Week 26 Work Progress
10.14.1 Gantt Chart Update
Balgoname 2017
126
10.14.2 Network Diagram Update
Balgoname 2017
127
10.14.3 Budget Report Update
10.14.4 EVM Analysis
Balgoname 2017
128
10.14.5 Status Report
By the end of week 26 work and budget wet as planned.
Balgoname 2017
129
10.15 Week 27 Work Progress
10.15.1 Gantt Chart Update
Balgoname 2017
130
10.15.2 Network Diagram Update
Balgoname 2017
131
10.15.3 Budget Report Update
10.15.4 EVM Analysis
Balgoname 2017
132
10.15.5 Status Report
All the work planned for week 27 have been completed on planned schedule. The project
experienced a positive variance of actual cost by $5,500 more. The project cost performance is
showing a negative performance while the schedule performance index is still maintaining a
normal performance. As the project continues the project manager might take necessary actions
to maintain an actual spending based on what is budgeted.
Balgoname 2017
133
References
Afzalur Rahim, M. (2002). Toward A Theory of Managing Organizational Conflict. The International
Journal of Conflict Management, Vol. 13(No. 3), pp. 206-235.
Anupama, N. (2014, October). Green Computing, A Smart Computing. Journal of Chemical and
Pharmaceutical Sciences, 1(3), 170-171. Retrieved from
http://jchps.com/specialissues/Special%20issue3/40%20jchps%20si3%20addn%20anupama%20
170-171.pdf
Drucker, P. F. (1954). The Practice of Management. New York, NY: Harper Collins Inc. . Retrieved May 30,
2017
Jung, C. G. (1971, August 1). Psychological Types. Collected Wrks of C.G. Jung, Vol. 6.
Kurp, P. (2008, October 1). Green Computing. Communications Of The ACM, Vol. 51(No. 10), pp. 11-13.
LeBar, Z. (2017, April 3). What Are Wikis, and Why Should You Use Them? Retrieved June 18, 2017, from
Envato Tuts+: https://business.tutsplus.com/tutorials/what-are-wikis-and-why-should-you-use-
them--cms-19540
Meade, J. (2017, April 13). This Is Why People Are Intimidated By You, Based On Your Personality Type.
Retrieved from http://thoughtcatalog.com: http://thoughtcatalog.com/jennifer-
meade/2017/04/this-is-why-people-are-intimidated-by-you-based-on-your-personality-type/
Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK
guide). Newtown Square, PA, USA: Project Management Institute.
Rouse, M. (2010, March 4). Carbon Footprint. Retrieved from Tech Target:
http://whatis.techtarget.com/definition/carbon-footprint
Singh, J. V., & Vatta, S. (2016, January-February 1). Green Computing: Eco Friendly Technology.
International Journal of Engineering Research and General Science, Vol. 4(No. 1), pp. 280-283.
Sultana, A., Suvarchala, C., & Ramay, A. (2016, January 10). A Study on Green Computing: The Future
Computing and Eco-Friendly Technology. International Journal of Innovation Research &
Development, Vol. 5(No. 2), pp. 35-39.
Techopedia. (2017, May 5). Green Computing Definition . Retrieved from
https://www.techopedia.com/definition/14753/green-computing
The Green Grid. (2017, May 6). About. Retrieved from The Green Grid:
https://www.thegreengrid.org/en/about-us
U.S. Environmental Protection Agency. (2016). Climate Protection Partnerships 2014 Reprot. Washington
D.C. : Office of Atmospheric Programs.

More Related Content

What's hot

Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeTheodore Van Patten, Jr.
 
Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...
Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...
Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...
Công Ty Cổ Phần Tư Vấn Đầu Tư Dự Án Việt
 
The Relationship between Competition and Innovation – OECD Secretariat – June...
The Relationship between Competition and Innovation – OECD Secretariat – June...The Relationship between Competition and Innovation – OECD Secretariat – June...
The Relationship between Competition and Innovation – OECD Secretariat – June...
OECD Directorate for Financial and Enterprise Affairs
 
Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...
Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...
Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...
Công Ty Cổ Phần Tư Vấn Đầu Tư Dự Án Việt
 
Dự án Nhà máy sản xuất sợi dệt kết hợp
Dự án Nhà máy sản xuất sợi dệt kết hợpDự án Nhà máy sản xuất sợi dệt kết hợp
Dự án Nhà máy sản xuất sợi dệt kết hợp
LẬP DỰ ÁN VIỆT
 
Matrix III Volume One By Val Valerian
Matrix III Volume One By Val Valerian  Matrix III Volume One By Val Valerian
Matrix III Volume One By Val Valerian
528Hz TRUTH
 
Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...
Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...
Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...
Công Ty Cổ Phần Tư Vấn Đầu Tư Dự Án Việt
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-StatementJeremy Heady
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyTimothy Cochran
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
Sadia Sharmin
 
HD AFLEVERING Valdemar Stilling, Final
HD AFLEVERING Valdemar Stilling, FinalHD AFLEVERING Valdemar Stilling, Final
HD AFLEVERING Valdemar Stilling, FinalValdemar Stilling
 
Dự án Khu du lịch sinh thái Bình An 0903034381
Dự án Khu du lịch sinh thái Bình An 0903034381Dự án Khu du lịch sinh thái Bình An 0903034381
Dự án Khu du lịch sinh thái Bình An 0903034381
CTY CP TƯ VẤN ĐẦU TƯ THẢO NGUYÊN XANH
 
Nong Trai Giao Duc
Nong Trai Giao DucNong Trai Giao Duc
Nong Trai Giao Duc
LẬP DỰ ÁN VIỆT
 
Celonis Snap Presentation Final Ramadan SANLI.pdf
Celonis Snap Presentation Final Ramadan SANLI.pdfCelonis Snap Presentation Final Ramadan SANLI.pdf
Celonis Snap Presentation Final Ramadan SANLI.pdf
Ramadan ŞANLI
 

What's hot (20)

Project management-plan
Project management-planProject management-plan
Project management-plan
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...
Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...
Thuyết minh dự án đầu tư xây dựng Khu chế biến nông sản theo tiêu chuẩn EU | ...
 
The Relationship between Competition and Innovation – OECD Secretariat – June...
The Relationship between Competition and Innovation – OECD Secretariat – June...The Relationship between Competition and Innovation – OECD Secretariat – June...
The Relationship between Competition and Innovation – OECD Secretariat – June...
 
Business Plan
Business PlanBusiness Plan
Business Plan
 
Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...
Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...
Dự án báo cáo nghiên cứu tiền khả thi trang trại nông nghiệp công nghệ cao kế...
 
P2440pl
P2440plP2440pl
P2440pl
 
Project charter template
Project charter templateProject charter template
Project charter template
 
Feasibility Study
Feasibility StudyFeasibility Study
Feasibility Study
 
Dự án Nhà máy sản xuất sợi dệt kết hợp
Dự án Nhà máy sản xuất sợi dệt kết hợpDự án Nhà máy sản xuất sợi dệt kết hợp
Dự án Nhà máy sản xuất sợi dệt kết hợp
 
Matrix III Volume One By Val Valerian
Matrix III Volume One By Val Valerian  Matrix III Volume One By Val Valerian
Matrix III Volume One By Val Valerian
 
Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...
Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...
Khu nông nghiệp công nghệ cao kết hợp du lịch Green Stars Phú Quốc - www.duan...
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-Statement
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the Company
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
HD AFLEVERING Valdemar Stilling, Final
HD AFLEVERING Valdemar Stilling, FinalHD AFLEVERING Valdemar Stilling, Final
HD AFLEVERING Valdemar Stilling, Final
 
Dự án Khu du lịch sinh thái Bình An 0903034381
Dự án Khu du lịch sinh thái Bình An 0903034381Dự án Khu du lịch sinh thái Bình An 0903034381
Dự án Khu du lịch sinh thái Bình An 0903034381
 
Nong Trai Giao Duc
Nong Trai Giao DucNong Trai Giao Duc
Nong Trai Giao Duc
 
Celonis Snap Presentation Final Ramadan SANLI.pdf
Celonis Snap Presentation Final Ramadan SANLI.pdfCelonis Snap Presentation Final Ramadan SANLI.pdf
Celonis Snap Presentation Final Ramadan SANLI.pdf
 
EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3
 

Viewers also liked

MANAGEMENT RESEARCH PROJECT
MANAGEMENT RESEARCH PROJECTMANAGEMENT RESEARCH PROJECT
MANAGEMENT RESEARCH PROJECTERICK MAINA
 
Project report on Wealth Management
Project report on Wealth ManagementProject report on Wealth Management
Project report on Wealth Management
Khushbu Malara
 
CRM IN TELESHOPPING INDUSTRY
CRM IN TELESHOPPING INDUSTRYCRM IN TELESHOPPING INDUSTRY
CRM IN TELESHOPPING INDUSTRY
Shriyansh Gupta
 
Telecom Order Management Solution Research Project
Telecom Order Management Solution Research ProjectTelecom Order Management Solution Research Project
Telecom Order Management Solution Research Project
Shailendra Shankar
 
A study on perception of customers towards tata indica v2 project report mba ...
A study on perception of customers towards tata indica v2 project report mba ...A study on perception of customers towards tata indica v2 project report mba ...
A study on perception of customers towards tata indica v2 project report mba ...
Babasab Patil
 
MANAGEMENT RESEARCH PAPER (MRP) PROJECT
MANAGEMENT RESEARCH PAPER (MRP) PROJECTMANAGEMENT RESEARCH PAPER (MRP) PROJECT
MANAGEMENT RESEARCH PAPER (MRP) PROJECTGodwin Kinoti
 
Transport Research Project Final Report
Transport Research Project Final ReportTransport Research Project Final Report
Transport Research Project Final Report
Kartik Tiwari
 
Masters Project CThornhill v2 final
Masters Project CThornhill v2 finalMasters Project CThornhill v2 final
Masters Project CThornhill v2 finalCecil Thornhill
 
MANAGEMENT RESEARCH PROJECT
MANAGEMENT RESEARCH  PROJECTMANAGEMENT RESEARCH  PROJECT
MANAGEMENT RESEARCH PROJECT
Allcance Digital
 
LinkedTV D6.4 Scenario Demonstrators v2
LinkedTV D6.4 Scenario Demonstrators v2LinkedTV D6.4 Scenario Demonstrators v2
LinkedTV D6.4 Scenario Demonstrators v2
LinkedTV
 
Market Research on Distribution System of Pepsi Project Report
Market Research on Distribution System of Pepsi Project ReportMarket Research on Distribution System of Pepsi Project Report
Market Research on Distribution System of Pepsi Project ReportAbhishek Keshri
 

Viewers also liked (11)

MANAGEMENT RESEARCH PROJECT
MANAGEMENT RESEARCH PROJECTMANAGEMENT RESEARCH PROJECT
MANAGEMENT RESEARCH PROJECT
 
Project report on Wealth Management
Project report on Wealth ManagementProject report on Wealth Management
Project report on Wealth Management
 
CRM IN TELESHOPPING INDUSTRY
CRM IN TELESHOPPING INDUSTRYCRM IN TELESHOPPING INDUSTRY
CRM IN TELESHOPPING INDUSTRY
 
Telecom Order Management Solution Research Project
Telecom Order Management Solution Research ProjectTelecom Order Management Solution Research Project
Telecom Order Management Solution Research Project
 
A study on perception of customers towards tata indica v2 project report mba ...
A study on perception of customers towards tata indica v2 project report mba ...A study on perception of customers towards tata indica v2 project report mba ...
A study on perception of customers towards tata indica v2 project report mba ...
 
MANAGEMENT RESEARCH PAPER (MRP) PROJECT
MANAGEMENT RESEARCH PAPER (MRP) PROJECTMANAGEMENT RESEARCH PAPER (MRP) PROJECT
MANAGEMENT RESEARCH PAPER (MRP) PROJECT
 
Transport Research Project Final Report
Transport Research Project Final ReportTransport Research Project Final Report
Transport Research Project Final Report
 
Masters Project CThornhill v2 final
Masters Project CThornhill v2 finalMasters Project CThornhill v2 final
Masters Project CThornhill v2 final
 
MANAGEMENT RESEARCH PROJECT
MANAGEMENT RESEARCH  PROJECTMANAGEMENT RESEARCH  PROJECT
MANAGEMENT RESEARCH PROJECT
 
LinkedTV D6.4 Scenario Demonstrators v2
LinkedTV D6.4 Scenario Demonstrators v2LinkedTV D6.4 Scenario Demonstrators v2
LinkedTV D6.4 Scenario Demonstrators v2
 
Market Research on Distribution System of Pepsi Project Report
Market Research on Distribution System of Pepsi Project ReportMarket Research on Distribution System of Pepsi Project Report
Market Research on Distribution System of Pepsi Project Report
 

Similar to Green Computing Research: Project management report

Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Chris Delepierre
 
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Saide OER Africa
 
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Saide OER Africa
 
ala_harabi-4 presentation d une platform web
ala_harabi-4 presentation d une platform webala_harabi-4 presentation d une platform web
ala_harabi-4 presentation d une platform web
mohamedjawharchahed
 
RDGB Corporate Profile
RDGB Corporate ProfileRDGB Corporate Profile
RDGB Corporate Profile
Rejaul Islam
 
Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementation
Dejened
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Joy Irman
 
Final Report Pengembangan Produk
Final Report Pengembangan ProdukFinal Report Pengembangan Produk
Final Report Pengembangan Produk
lan_jut
 
Digital Interventions for Health Systems Strengthening
Digital Interventions for Health Systems Strengthening Digital Interventions for Health Systems Strengthening
Digital Interventions for Health Systems Strengthening
Prof. Rajendra Pratap Gupta
 
Name Thistle Anderson Phone ext. 2927 Email [email.docx
 Name Thistle Anderson  Phone ext. 2927  Email [email.docx Name Thistle Anderson  Phone ext. 2927  Email [email.docx
Name Thistle Anderson Phone ext. 2927 Email [email.docx
MARRY7
 
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...Jason Cheung
 
RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...
RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...
RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...
Ayda.N Mazlan
 
Guidelines of osh in ci management v3_final for public comment
Guidelines of osh in ci management v3_final for public commentGuidelines of osh in ci management v3_final for public comment
Guidelines of osh in ci management v3_final for public comment
Dr. Mohammad Anati
 
Systems Analysis And Design Methodology And Supporting Processes
Systems Analysis And Design Methodology And Supporting ProcessesSystems Analysis And Design Methodology And Supporting Processes
Systems Analysis And Design Methodology And Supporting ProcessesAlan McSweeney
 
SBEP Procurement Manual
SBEP Procurement ManualSBEP Procurement Manual
SBEP Procurement Manual
Zeeshan Shahid
 
1310 feasibility compost_coffee and climate_soil and more final
1310 feasibility compost_coffee and climate_soil and more final1310 feasibility compost_coffee and climate_soil and more final
1310 feasibility compost_coffee and climate_soil and more final
Anurag Sinha
 
Factors affect taking charge at Vingroup Corporation
Factors affect taking charge at Vingroup CorporationFactors affect taking charge at Vingroup Corporation
Factors affect taking charge at Vingroup Corporation
Nguyễn Hà
 

Similar to Green Computing Research: Project management report (20)

Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
 
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
 
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
 
Unilever_PM_Hndbk
Unilever_PM_HndbkUnilever_PM_Hndbk
Unilever_PM_Hndbk
 
ala_harabi-4 presentation d une platform web
ala_harabi-4 presentation d une platform webala_harabi-4 presentation d une platform web
ala_harabi-4 presentation d une platform web
 
896405 - HSSE_v03
896405 - HSSE_v03896405 - HSSE_v03
896405 - HSSE_v03
 
RDGB Corporate Profile
RDGB Corporate ProfileRDGB Corporate Profile
RDGB Corporate Profile
 
Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementation
 
Vekony & Korneliussen (2016)
Vekony & Korneliussen (2016)Vekony & Korneliussen (2016)
Vekony & Korneliussen (2016)
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
 
Final Report Pengembangan Produk
Final Report Pengembangan ProdukFinal Report Pengembangan Produk
Final Report Pengembangan Produk
 
Digital Interventions for Health Systems Strengthening
Digital Interventions for Health Systems Strengthening Digital Interventions for Health Systems Strengthening
Digital Interventions for Health Systems Strengthening
 
Name Thistle Anderson Phone ext. 2927 Email [email.docx
 Name Thistle Anderson  Phone ext. 2927  Email [email.docx Name Thistle Anderson  Phone ext. 2927  Email [email.docx
Name Thistle Anderson Phone ext. 2927 Email [email.docx
 
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
 
RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...
RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...
RAPID RURAL APPRAISAL (RRA) AND PARTICIPATORY RURAL APPRAISAL (PRE) - A MANUA...
 
Guidelines of osh in ci management v3_final for public comment
Guidelines of osh in ci management v3_final for public commentGuidelines of osh in ci management v3_final for public comment
Guidelines of osh in ci management v3_final for public comment
 
Systems Analysis And Design Methodology And Supporting Processes
Systems Analysis And Design Methodology And Supporting ProcessesSystems Analysis And Design Methodology And Supporting Processes
Systems Analysis And Design Methodology And Supporting Processes
 
SBEP Procurement Manual
SBEP Procurement ManualSBEP Procurement Manual
SBEP Procurement Manual
 
1310 feasibility compost_coffee and climate_soil and more final
1310 feasibility compost_coffee and climate_soil and more final1310 feasibility compost_coffee and climate_soil and more final
1310 feasibility compost_coffee and climate_soil and more final
 
Factors affect taking charge at Vingroup Corporation
Factors affect taking charge at Vingroup CorporationFactors affect taking charge at Vingroup Corporation
Factors affect taking charge at Vingroup Corporation
 

Recently uploaded

Explore Modern SharePoint Templates for 2024
Explore Modern SharePoint Templates for 2024Explore Modern SharePoint Templates for 2024
Explore Modern SharePoint Templates for 2024
Sharepoint Designs
 
A Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdfA Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdf
kalichargn70th171
 
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...
Globus
 
SOCRadar Research Team: Latest Activities of IntelBroker
SOCRadar Research Team: Latest Activities of IntelBrokerSOCRadar Research Team: Latest Activities of IntelBroker
SOCRadar Research Team: Latest Activities of IntelBroker
SOCRadar
 
GlobusWorld 2024 Opening Keynote session
GlobusWorld 2024 Opening Keynote sessionGlobusWorld 2024 Opening Keynote session
GlobusWorld 2024 Opening Keynote session
Globus
 
BoxLang: Review our Visionary Licenses of 2024
BoxLang: Review our Visionary Licenses of 2024BoxLang: Review our Visionary Licenses of 2024
BoxLang: Review our Visionary Licenses of 2024
Ortus Solutions, Corp
 
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoamOpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
takuyayamamoto1800
 
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERRORTROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
Tier1 app
 
Dominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdf
Dominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdfDominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdf
Dominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdf
AMB-Review
 
Globus Compute Introduction - GlobusWorld 2024
Globus Compute Introduction - GlobusWorld 2024Globus Compute Introduction - GlobusWorld 2024
Globus Compute Introduction - GlobusWorld 2024
Globus
 
Strategies for Successful Data Migration Tools.pptx
Strategies for Successful Data Migration Tools.pptxStrategies for Successful Data Migration Tools.pptx
Strategies for Successful Data Migration Tools.pptx
varshanayak241
 
First Steps with Globus Compute Multi-User Endpoints
First Steps with Globus Compute Multi-User EndpointsFirst Steps with Globus Compute Multi-User Endpoints
First Steps with Globus Compute Multi-User Endpoints
Globus
 
Understanding Globus Data Transfers with NetSage
Understanding Globus Data Transfers with NetSageUnderstanding Globus Data Transfers with NetSage
Understanding Globus Data Transfers with NetSage
Globus
 
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...
Globus
 
Globus Compute wth IRI Workflows - GlobusWorld 2024
Globus Compute wth IRI Workflows - GlobusWorld 2024Globus Compute wth IRI Workflows - GlobusWorld 2024
Globus Compute wth IRI Workflows - GlobusWorld 2024
Globus
 
Beyond Event Sourcing - Embracing CRUD for Wix Platform - Java.IL
Beyond Event Sourcing - Embracing CRUD for Wix Platform - Java.ILBeyond Event Sourcing - Embracing CRUD for Wix Platform - Java.IL
Beyond Event Sourcing - Embracing CRUD for Wix Platform - Java.IL
Natan Silnitsky
 
top nidhi software solution freedownload
top nidhi software solution freedownloadtop nidhi software solution freedownload
top nidhi software solution freedownload
vrstrong314
 
Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...
Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...
Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...
informapgpstrackings
 
Accelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with PlatformlessAccelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with Platformless
WSO2
 
Prosigns: Transforming Business with Tailored Technology Solutions
Prosigns: Transforming Business with Tailored Technology SolutionsProsigns: Transforming Business with Tailored Technology Solutions
Prosigns: Transforming Business with Tailored Technology Solutions
Prosigns
 

Recently uploaded (20)

Explore Modern SharePoint Templates for 2024
Explore Modern SharePoint Templates for 2024Explore Modern SharePoint Templates for 2024
Explore Modern SharePoint Templates for 2024
 
A Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdfA Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdf
 
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...
 
SOCRadar Research Team: Latest Activities of IntelBroker
SOCRadar Research Team: Latest Activities of IntelBrokerSOCRadar Research Team: Latest Activities of IntelBroker
SOCRadar Research Team: Latest Activities of IntelBroker
 
GlobusWorld 2024 Opening Keynote session
GlobusWorld 2024 Opening Keynote sessionGlobusWorld 2024 Opening Keynote session
GlobusWorld 2024 Opening Keynote session
 
BoxLang: Review our Visionary Licenses of 2024
BoxLang: Review our Visionary Licenses of 2024BoxLang: Review our Visionary Licenses of 2024
BoxLang: Review our Visionary Licenses of 2024
 
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoamOpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
 
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERRORTROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
 
Dominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdf
Dominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdfDominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdf
Dominate Social Media with TubeTrivia AI’s Addictive Quiz Videos.pdf
 
Globus Compute Introduction - GlobusWorld 2024
Globus Compute Introduction - GlobusWorld 2024Globus Compute Introduction - GlobusWorld 2024
Globus Compute Introduction - GlobusWorld 2024
 
Strategies for Successful Data Migration Tools.pptx
Strategies for Successful Data Migration Tools.pptxStrategies for Successful Data Migration Tools.pptx
Strategies for Successful Data Migration Tools.pptx
 
First Steps with Globus Compute Multi-User Endpoints
First Steps with Globus Compute Multi-User EndpointsFirst Steps with Globus Compute Multi-User Endpoints
First Steps with Globus Compute Multi-User Endpoints
 
Understanding Globus Data Transfers with NetSage
Understanding Globus Data Transfers with NetSageUnderstanding Globus Data Transfers with NetSage
Understanding Globus Data Transfers with NetSage
 
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...
 
Globus Compute wth IRI Workflows - GlobusWorld 2024
Globus Compute wth IRI Workflows - GlobusWorld 2024Globus Compute wth IRI Workflows - GlobusWorld 2024
Globus Compute wth IRI Workflows - GlobusWorld 2024
 
Beyond Event Sourcing - Embracing CRUD for Wix Platform - Java.IL
Beyond Event Sourcing - Embracing CRUD for Wix Platform - Java.ILBeyond Event Sourcing - Embracing CRUD for Wix Platform - Java.IL
Beyond Event Sourcing - Embracing CRUD for Wix Platform - Java.IL
 
top nidhi software solution freedownload
top nidhi software solution freedownloadtop nidhi software solution freedownload
top nidhi software solution freedownload
 
Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...
Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...
Field Employee Tracking System| MiTrack App| Best Employee Tracking Solution|...
 
Accelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with PlatformlessAccelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with Platformless
 
Prosigns: Transforming Business with Tailored Technology Solutions
Prosigns: Transforming Business with Tailored Technology SolutionsProsigns: Transforming Business with Tailored Technology Solutions
Prosigns: Transforming Business with Tailored Technology Solutions
 

Green Computing Research: Project management report

  • 1. Summer 2017 Prepared by Supervised by INFS7570 Applied Research Mohammad Balgoname Dr. John C. Turchek Project Management Report Green Computing Research Project Document ID: 01 Version: 1.0 Release Date: May 15th , 2017
  • 2. Balgoname 2017 2 Table of Contents 1. Project Integration Management .............................................................................................................8 1.1 Definition of Green Computing...........................................................................................................8 1.3 Financial Analysis of Business case ...................................................................................................14 1.4 Project Charter..................................................................................................................................15 1.5 Integrated Project Change Control ...................................................................................................16 2. Project Scope Management....................................................................................................................20 2.1 Requirements Specifications.............................................................................................................20 2.1.1 Project Overview........................................................................................................................20 2.1.2 Purpose and Scope of this Specification....................................................................................20 2.1.3 Traceability Matrix.....................................................................................................................21 2.1.4 Questions for Project Sponsor...................................................................................................23 2.2 Project Scope Statement ..................................................................................................................23 2.3 Work Breakdown Structure 2.3.1 Work Breakdown Structure Table ..............................................24 2.3.2 Work Breakdown Structure Tree...............................................................................................26 2.4 Gantt Chart........................................................................................................................................27 3. Project Time Management .....................................................................................................................29 3.1 Review of WBS and Gantt Chart .......................................................................................................29 3.2 Project Milestones ............................................................................................................................30 3.3 Gantt Chart with Duration and Dependencies .................................................................................32 3.3.1 Gantt Chart.................................................................................................................................32 3.3.2 Network Diagram.......................................................................................................................32 3.4 Resource Assignment Matrix............................................................................................................33 4. Project Cost Management ......................................................................................................................36 4.1 Project Planned Cost Budget ............................................................................................................36 4.1.1 Weekly Budget...........................................................................................................................36 4.1.2 Resource Usage..........................................................................................................................38 4.2 Project BAC and Planned Value ........................................................................................................39 4.3 Earned Value Analysis.......................................................................................................................39 4.4 Corrective Actions.............................................................................................................................41 5. Project Quality Management..................................................................................................................43 5.1 Quality Management Requirements ................................................................................................43 5.1.1 Quality Management Approach.................................................................................................43
  • 3. Balgoname 2017 3 5.1.2 Quality Objectives and Standards Identification .......................................................................43 5.1.3 Project Reviews and Assessments .............................................................................................44 5.1.4 Deliverable Acceptance Criteria.................................................................................................44 5.2 Seven Basic Tools of Quality .............................................................................................................45 5.3 Summary of High Quality Research Report ......................................................................................46 6. Project Human Resource Management..................................................................................................48 6.1 MBTI Types in Work Environments...................................................................................................48 6.1.1 MBTI Personality types ..............................................................................................................48 6.1.2 Introductory Email .....................................................................................................................50 6.2 Responsibility Assignment Matrix RACI ............................................................................................50 6.3 Human Resources Related Concerns................................................................................................52 7. Project Communication Management....................................................................................................55 7.1 Project Issue Log ...............................................................................................................................55 7.2 Applications of Wikis.........................................................................................................................56 7.3 Conflict Resolution............................................................................................................................57 8. Project Risk Management.......................................................................................................................60 8.1 Risk Register......................................................................................................................................60 8.2 Risk Assessment and Impact Matrix .................................................................................................61 8.3 Risk Response and Contingency Plans ..............................................................................................62 9. Project Procurement Management........................................................................................................64 9.1 Contract Agreement with Anne Consulting Firm..............................................................................64 9.2 Content of Research Report..............................................................................................................70 9.2.1 Executive Summary....................................................................................................................70 9.2.2 Table of Contents.......................................................................................................................70 9.3 Lesson Learned ...........................................................................................................................71 10. Periodic Reporting: Project Monitoring and Controlling ......................................................................73 10.1 Week 13 Work Progress..................................................................................................................73 10.1.1 Gantt Chart Update..................................................................................................................73 10.1.2 Network Diagram Update........................................................................................................74 10.1.3 Budget Report Update.............................................................................................................75 10.1.4 EVM Analysis............................................................................................................................75 10.1.5 Status Report ...........................................................................................................................76 10.2 Week 14 Work Progress..................................................................................................................77
  • 4. Balgoname 2017 4 10.2.1 Gantt Chart Update..................................................................................................................77 10.2.2 Network Diagram Update........................................................................................................78 10.2.3 Budget Report Update.............................................................................................................79 10.2.4 EVM Analysis............................................................................................................................79 10.2.5 Status Report ...........................................................................................................................80 10.3 Week 15 Work Progress..................................................................................................................81 10.3.1 Gantt Chart Update..................................................................................................................81 10.3.2 Network Diagram Update........................................................................................................82 10.3.3 Budget Report Update.............................................................................................................83 10.3.4 EVM Analysis............................................................................................................................83 10.3.5 Status Report ...........................................................................................................................84 10.4 Week 16 Work Progress..................................................................................................................85 10.4.1 Gantt Chart Update..................................................................................................................85 10.4.2 Network Diagram Update........................................................................................................86 10.4.3 Budget Report Update.............................................................................................................87 10.4.4 EVM Analysis............................................................................................................................87 10.4.5 Status Report ...........................................................................................................................88 10.5 Week 17 Work Progress..................................................................................................................89 10.5.1 Gantt Chart Update..................................................................................................................89 10.5.2 Network Diagram Update........................................................................................................90 10.5.3 Budget Report Update.............................................................................................................91 10.5.4 EVM Analysis............................................................................................................................92 10.5.5 Status Report ...........................................................................................................................93 10.6 Week 18 Work Progress..................................................................................................................93 10.6.1 Gantt Chart Update..................................................................................................................93 10.6.2 Network Diagram Update........................................................................................................94 10.6.3 Budget Report Update.............................................................................................................95 10.6.4 EVM Analysis............................................................................................................................96 10.6.5 Status Report ...........................................................................................................................96 10.7 Week 19 Work Progress..................................................................................................................97 10.7.1 Gantt Chart Update..................................................................................................................97 10.7.2 Network Diagram Update........................................................................................................98 10.7.3 Budget Report Update.............................................................................................................99
  • 5. Balgoname 2017 5 10.7.4 EVM Analysis............................................................................................................................99 10.7.5 Status Report .........................................................................................................................100 10.8 Week 20 Work Progress................................................................................................................101 10.8.1 Gantt Chart Update................................................................................................................101 10.8.2 Network Diagram Update......................................................................................................102 10.8.3 Budget Report Update...........................................................................................................103 10.8.4 EVM Analysis..........................................................................................................................103 10.8.5 Status Report .........................................................................................................................104 10.9 Week 21 Work Progress................................................................................................................105 10.9.1 Gantt Chart Update................................................................................................................105 10.9.2 Network Diagram Update......................................................................................................106 10.9.3 Budget Report Update...........................................................................................................107 10.9.4 EVM Analysis..........................................................................................................................107 10.9.5 Status Report .........................................................................................................................108 10.10 Week 22 Work Progress..............................................................................................................109 10.10.1 Gantt Chart Update..............................................................................................................109 10.10.2 Network Diagram Update....................................................................................................110 10.10.3 Budget Report Update.........................................................................................................111 10.10.4 EVM Analysis........................................................................................................................111 10.10.5 Status Report .......................................................................................................................112 10.11 Week 23 Work Progress..............................................................................................................113 10.11.1 Gantt Chart Update..............................................................................................................113 10.11.2 Network Diagram Update....................................................................................................114 10.11.3 Budget Report Update.........................................................................................................115 10.11.4 EVM Analysis........................................................................................................................115 10.11.5 Status Report .......................................................................................................................116 10.12 Week 24 Work Progress..............................................................................................................117 10.12.1 Gantt Chart Update..............................................................................................................117 10.12.2 Network Diagram Update....................................................................................................118 10.12.3 Budget Report Update.........................................................................................................119 10.12.4 EVM Analysis........................................................................................................................119 10.12.5 Status Report .......................................................................................................................120 10.13 Week 25 Work Progress..............................................................................................................121
  • 6. Balgoname 2017 6 10.13.1 Gantt Chart Update..............................................................................................................121 10.13.2 Network Diagram Update....................................................................................................122 10.13.3 Budget Report Update.........................................................................................................123 10.13.4 EVM Analysis........................................................................................................................123 10.13.5 Status Report .......................................................................................................................124 10.14 Week 26 Work Progress..............................................................................................................125 10.14.1 Gantt Chart Update..............................................................................................................125 10.14.2 Network Diagram Update....................................................................................................126 10.14.3 Budget Report Update.........................................................................................................127 10.14.4 EVM Analysis........................................................................................................................127 10.14.5 Status Report .......................................................................................................................128 10.15 Week 27 Work Progress..............................................................................................................129 10.15.1 Gantt Chart Update..............................................................................................................129 10.15.2 Network Diagram Update....................................................................................................130 10.15.3 Budget Report Update.........................................................................................................131 10.15.4 EVM Analysis........................................................................................................................131 10.15.5 Status Report .......................................................................................................................132
  • 8. Balgoname 2017 8 1. Project Integration Management 1.1 Definition of Green Computing The concept of green computing has started to grow in the past few years, attaining increasing popularity. Asides of the widespread sensitivity to ecological issues, such attention also stems from economic needs, as both energy expenses and electrical requirements of IT industry around the word show a continuously growing trend. This project aim is to define green computing and provide actual application examples where green computing applications made a positive impact. The concept of green computing can be defined as "the environmentally responsible and eco-friendly use of computers and their resources" (Techopedia, 2017). Green computing is also defined as the examination of designing, manufacturing/engineering, utilizing and dumping of computing devices in a way that lessens their environmental impact. Today, many IT manufacturers and vendors are continually investing in designing energy efficient computing devices, reducing the use of hazardous materials and encouraging the recyclability of digital devices and papers. Recently, green computing concept expanded to include software code. The advances of coding languages enabled the implementation of effective and efficient software coding that saves power through making software less dependent on the use of hardware while maintaining superior performance and less utilization of energy. (Singh & Vatta, 2016) Green computing practices came into being in 1992 when the Environmental Protection Agency (EPA) launched the Energy Star program - a government-backed labeling program that helps individuals and organizations save money and reduce greenhouse gas emissions thought to identify factories, office equipment, home appliances and electronics that have superior energy efficiency. The EPA has more than 19,000 partner organizations across the United States to
  • 9. Balgoname 2017 9 lessen emissions and achieve significant environmental and economic gains. EPA programs prevent more that 416 million metric tons of U.S. GHG emissions. Also, reducing net energy bills by more than $31 billion reductions in methane emissions by $7.7 billion in 2014 alone (U.S. Environmental Protection Agency, 2016). There are also other non-governmental organizations that support and apply green computing concept throughout their organizations. One of these companies is VIA Technologies, a Taiwanese company that manufactures motherboard chipsets, CPUs, and other computer hardware. In 2001, VIA introduced an initiative for green computing that aims to design and build efficient and effective hardware products that utilize less power. VIA's environmentally friendly products are produced using a variety of clean-computing approaches. "In 2005, the VIA launched its VIA C7-M and VIA C7 CPUs that have a maximum power consumption of 1W" (Sultana, Suvarchala, & Ramay, 2016). These energy-efficient CPUs produced more than four times less carbon during their operations and can be efficiently embedded in solar-powered devices. IBM is also one of the long supporters of green computing concept. In the 1960s, IBM originated computer virtualization, which refers to the abstraction of computer resources, such as the process of operating two or more logical computer systems on one set of physical hardware. With virtualization capability, a system admin could merge many physical systems into virtual machines on one single, robust system, thereby unplugging the original hardware and reducing power and cooling consumption. Moreover, virtualization can assist in distributing work, so that servers are either busy or put in a low-power sleep state. Microsoft, Google, and Yahoo are addressing the environmental concerns about their data center's carbon footprint, "the measure of the environmental impact of an individual or
  • 10. Balgoname 2017 10 organization's lifestyle or operations, measured in units of carbon dioxide generated" (Rouse, 2010). In recent years, Microsoft and other corporations have built data centers in central Washington to gain an advantage of the hydroelectric power produced by two dams in the region. The Microsoft facility, which consumes up to 27 megawatts of energy at any given time, is powered by hydroelectricity. Another Microsoft data center, located in Dublin, Ireland, that started operation in 2009, thanks to Ireland's moderate climate, the 51,000-square-meter facility is air cooled, making it 50& more energy-efficient than other comparable sized data warehouses. (Kurp, 2008) Google has committed to being carbon-neutral starting from 2007 and beyond, says Bill Weihl, Google's director of energy strategy. According to Google, its data centers uses half the industry's average amount of power. Google attributes this improved energy usage to the cooling technologies, such as ultra-efficient evaporative cooling, that the company has customized for itself. Yahoo’s data warehouses also went carbon-neutral, in part because of its use of carbon offsets. (Kurp, 2008) Many of industry-leading companies, such as Cisco Systems, Dell, Digital Reality, Hewlett-Packard, IBM, and Intel to name few have joined efforts to reduce their carbon footprint and promote the eco-friendlier environment through the establishment of a non-profit organization called The Green Grid Association in 2007. The non-profit, open industry consortium of information and communication technology (ICT) industry end-users, policy makers, technology providers, facility architects have come together to improve data center and IT resource efficiency globally, through sharing expertise and insights of best practices of running data centers (The Green Grid, 2017). Overall green computing is a continuous non-
  • 11. Balgoname 2017 11 endless innovation, and practices that make the use of hardware and software eco-friendlier and saves energy and money. 1.2 Weighted Decision Matrix for Evaluation The evaluation process of the project manager position of green computing research project starts with identifying essential criteria that should be found in the nominees for this position. After examining key characteristics of project manager, six criteria have been selected. Those criteria are: 1. Project Management Experience 2. Knowledge level of IT 3. Leadership 4. Communication & Coordination 5. Analytical skills 6. Time Management Each criterion is assigned by a rank of priority and weight factor which will be used to calculate the final decision once candidates have been selected. Table 1: Criteria selection Once the priority has sorted, and weighted criteria, the process proceed to select candidates for this position. Five candidates: Mia, Isabella, James, William, and Sophia nominated.
  • 12. Balgoname 2017 12 Each candidate assigned points from a 1 – 10 scale. Then raw scores and weighted scores are calculated to determine the rank of each candidate. The following chart shows the conclusion of the decision matrix process. Table 2: Decision Matrix Based on the calculations that appear above, Mia has got the highest weighted score among other candidates; therefore, she has been selected for this post. The following charts illustrate each candidate weaknesses and straights. It also shows candidates total scores.
  • 13. Balgoname 2017 13 Figure 2: Chart of total candidates’ scores Figure 1: Chart of candidates’ straights and weaknesses
  • 14. Balgoname 2017 14 1.3 Financial Analysis of Business case Table 3: Project’s Financial Analysis
  • 15. Balgoname 2017 15 1.4 Project Charter PROJECT CHARTER PROJECT NAME DATE AREA OF FOCUS Green Computing Research 5/15/2017 Research and Development BUSINESS CASE SCOPE In line with our strategic goal, which is to help improve the environment while increasing revenues and reducing costs. The VP of Operations, Natalie called for starting a green computing research project. IN SCOPE OUT OF SCOPE Thin client solutions Electronic waste disposal & recycling Development of green computing solutions for internal use Telecommuting Server resources virtualization Potential sale to other organizations Open sources software Data center & Energy efficiency MEASURABLE KEY DELIVERABLES TARGET/GOAL DATE Financial analysis Standard work and reporting Finalize Financial analysis 7/20/2017 Possible technologies to implement Orientation completion Finalize recommended solutions 8/18/2017 Recommended Solutions Finalize standard work and reporting 11/15/2017 SUCCESS FACTORS TIMELINE Achieving scope of project ACTIONS/MILESTONES TARGET DATE/ STATUS Meeting time constraint Development of high level requirements 5/18/2017 Execute project within budget Team job descriptions approval 5/21/2017 Achieving high quality processes Selection of team members 5/25/2017 STAKEHOLDERS FINANCIALS NAME FUNCTION BUSINESS IMPACT INVESTMENT Natalie VP of Operations The project shall provide environmental and financial solutions that will save money and reduce the carbon footprint of operating computers. Total invested amount in the project $356,000.00Ben CIO & project sponsor Mia Project Manager ASSUMPTIONS/ CONSTRAINTS RISK PLANNING Project must complete in 6 moths Team members must be selected carefully as the project will be conducted online. Transacting information among team members should be highly encrypted to assure the security.Team must be functioning by 5/15/2017 Work on project will be virtual (online Sign-off: VP of Operations: ……………… CIO & Project Sponsor: ……………… Project Manager: ………………
  • 16. Balgoname 2017 16 1.5 Integrated Project Change Control The principal focus of Integrated Change Control is to measure the impact of changes or modifications on all project constraints. Changes to any component of the project might be requested at any given time during the development of the project, especially during the project executing & monitoring, or control phases. It is not essential to achieve all changes. In the Perform Integrated Change Control, changes or modifications are accepted or rejected based on their evaluation and impact to the project by the project Change Control Board (CCB). Mainly, there are three reasons for change request which are: preventive actions, corrective actions, and defect repair. Whenever a change is received, suggested, or identified, it will be logged in the Change log of the project. Regardless of the size of the change or the impact of the change, each and every change will be recorded in the Change Log. The project manager, Ms. Mia, alone cannot do the impact analysis, inputs from the project team and if required from the stakeholders are needed. In the impact analysis, the impact of the proposed change is analyzed on all project constraints scope, cost, schedule, quality, or any other dimension. This is a critical step in the process as impact analysis will be regarded as input for the change request’s rejection or approval. Once the impact analysis is done, it should be provided to the CCB along with change request for the decision of approval, postponed, or rejected. In case the change request is approved, the work associated to change request becomes part of the project, and all associated project documents, plans, and charter get updated. If the change or modification request is postponed or rejected, the CCB will send to the project sponsor the reasons of postponed or rejection. Finally, the Change Log will be updated for all details regarding change request such as the decision that has been taken on, reasons for postponed, or rejection, and if accepted follow-up steps.
  • 17. Balgoname 2017 17 Figure 3: Flowchart of Change Request Process
  • 18. Balgoname 2017 18 Change Request Form Project Name Project Sponsor S T E P 1 Urgency Change Request # Originator Change Requested by Date Requested JUSTIFICATION Description of Change Request # Reason for Change Proposed Approach to Resolve PROJECT PLAN AREA IMPACT OF PROPOSED CHANGE(S) S T E P 2 IMPACT Impact on Scope Impact on Schedule Impact on Spending Impact on Risk Other APPROVALS TO PROCEED S T E P 3 Originator/ Date Project Manager Sponsor/ Date Customer/ Date Table 4: Change Request Form
  • 20. Balgoname 2017 20 2. Project Scope Management 2.1 Requirements Specifications 2.1.1 Project Overview The project calls for researching possible eco-friendly technologies that reduce carbon footprint to reduce global warming and save money to reduce the financial burden of the organization. 2.1.2 Purpose and Scope of this Specification This requirements specification document describes the functions and requirements specified for green computing research project. The purpose of the specification document is to apply constraints to what and what not is included in the scope of the research. There are several requirements for this project, including but not limited to the establishment of project charter, plan, scope baseline, cost baseline, and activity plan. In Scope ❖ Thin client solutions ❖ Electronic waste disposal & recycling ❖ Telecommuting ❖ Server resources virtualization ❖ Open sources software, and ❖ Data center & energy efficiency technologies Out of Scope ❖ Development of green computing solutions for internal use ❖ Potential sale to other organizations
  • 21. Balgoname 2017 21 2.1.3 Traceability Matrix Requirements Traceability Matrix Project Name: Green Computing Research Project Cost Center: Environmental Technologies Program Project Description: Researching possible green computing applications ID Associated ID Requirements Description Business Needs, Opportunities, Goals, Objectives WBS Deliverables Owner Source Status 001 1.0 Project Charter Project Justifications Project Charter Project Sponsor Business Case Accomplished 1.1 Team Selection Candidates screening and evaluation Project Team Formation Project Manager Project Charter Ongoing 1.2 Project Management Plan Project execution and control guide documentation Project Management Plan Project Manager Project Charter Ongoing 1.2.1 Scope Management Plan Collection of all project's processes Project Statement Project Manager Project Charter Pending 1.2.2 Requirements Management Plan Documentation of project's requirements Project Management Plan Project Manager Project Management Plan Pending 1.2.2.1 Requirements Documentation Project’s definition, traceability matrix, and deliverables Requirements Management Plan Project Manager Requirements Management Plan Ongoing
  • 22. Balgoname 2017 22 002 2.0 Develop WBS Organizes team's work into manageable sections WBS Project Manager Scope Management Plan Pending 2.1 Scope Baseline Finalized WBS, WBS dictionary, and the project scope statement Scope Management Plan Project Team Scope Management Plan Pending 003 3.0 Schedule Management Plan Establish policies and procedures used to develop, execute, monitor and control the project schedule Schedule Management Plan Project Team Project Management plan Pending 3.1 Activity Plan Develop detailed list of all project’s activities List of Activities Project Team Project Management plan Pending 3.2 Schedule Baseline Establish fixed timeline measurement for accomplishment of project tasks Schedule Baseline Project Manager Schedule Management Plan Pending 004 4.0 Cost Baseline Develop time-phased spending plan for the project Cost Baseline Project Manager Cost Management Plan Pending 005 5.0 Stakeholder Management Plan Develop management strategies to engage stakeholders effectively Stakeholders Registration Project Manager Project Management Plan Pending Table 5: Requirements Traceability Matrix
  • 23. Balgoname 2017 23 2.1.4 Questions for Project Sponsor ▪ What is the project context, including organization's political considerations? ▪ What do you regard the main functions and features to be? ▪ What are your expectations of schedule and budget? ▪ What are the tradeoffs that will have to be made? ▪ What could be a high-level potential risk? 2.2 Project Scope Statement Scope Statement Project Name Green Computing Research Project Project Manager Mia Date 05/23/2017 Version History Version Date Comments 1.0 05/16/2017 Preliminary Scope statement 2.0 5/23/2017 Finalized Scope Statement Project Justifications As a strategic goal for the Environmental Technologies program at the organization, this project will help to improve the environment, while at the same time increase corporate revenues and decrease computers operational costs. It also helps to promote a positive corporate image and shows social responsibility. Project Scope To produce a comprehensive research report including detailed financial analysis and recommendations on what green computing technologies can be applied internally and potentially sold to other organization. Project Deliverables Financial analysis Recommended Solutions Orientation completion Possible technologies to implement Standard work and reporting Project Budget Total invested amount in the project $356,000.00 Project Deadline 6 Months starting form 05/15/2017 Table 6: Scope Statement
  • 24. Balgoname 2017 24 2.3 Work Breakdown Structure 2.3.1 Work Breakdown Structure Table Work Breakdown Structure Project Name Green Computing Research Project Project # 2 Project Manager Mia Sponsor Ben Project Artifacts Business Case, and Risk Assessment Version 1.0 ID Task Depen- dencies Status Cost Start Date Planned Completion Estimate to Completion Actual Completion Resou- rces 1 Project Initiation 1.0 Completed $21,747.00 05/15/2017 11 Mia, Ben 2 Team Member Selection 1.1 Completed 5,931.00 05/15/2017 3 3 Stakeholders Meeting 1.2 Completed 1,977.00 05/17/2017 1 4 Project Management Plan 1.3 Completed 7,908.00 05/18/2017 4 5 Project Scope Statement 1.4 Completed 1,977.00 05/21/2017 1 6 Project Change Control 1.4.1 Completed 1,977.00 05/21/2017 1 7 Charter Signed 1.4.1.1 Completed 1,977.00 05/22/2017 1 8 Planning 2.0 Ongoing $108,735.00 05/23/2017 55 Mia, Project Team 9 Project Kick-Off Meeting 2.1 Ongoing 1,977.00 05/23/2017 1 10 Develop Work Plan 2.2 Ongoing 59,310.00 05/24/2017 30 11 Develop Project Control Plan 2.3 Ongoing 39,540.00 06/23/2017 20 12 Finalize Project Plan 2.4 Ongoing 5,931.00 07/15/2017 3 13 Gain Approvals 2.5 Ongoing 1977.00 07/16/2017 1 15 Execution 3.0 Pending $205,608.00 07/17/2017 104 Mia, Project Team 16 Survey Analogous Researches 3.1 Pending 45,471.00 07/17/2017 23 17 Conduct Research 3.2 Pending 108,735.00 08/09/2017 55 18 Technologies Examination 3.2.1 Pending 39,540.00 10/4/2017 20 19 Analyze Findings 3.2.1.1 Pending 9,885.00 10/25/2017 5 20 Report Findings 3.3 Pending 1,977.00 10/30/2017 1 21 Monitoring and Controlling 4.0 Pending $2,117.00 11/01/2017 1 Mia
  • 25. Balgoname 2017 25 24 Performance Reporting 4.1 Pending 2,117.00 11/01/2017 1 25 Closing 5.0 Pending $17,793.00 11/01/2017 9 Mia, Project Team 26 Conduct Post Project Review 5.1 Pending 15,816.00 11/4/2017 8 27 Approve Project Closeout 5.2 Pending 1,97700 11/14/2017 1 Total $356,000.00 180 Table 7: Work Breakdown Structure table
  • 26. Balgoname 2017 26 2.3.2 Work Breakdown Structure Tree Figure 4: Work Breakdown Structure Diagram
  • 27. Balgoname 2017 27 2.4 Gantt Chart Figure 5: Gantt Chart of the Project
  • 29. Balgoname 2017 29 3. Project Time Management 3.1 Review of WBS and Gantt Chart Figure 6: An updated WBS and Gant Chart Shown above, an up-to-date picture of the WBS and Gantt chart. It includes all the dependencies, milestones, and timeline. There are, however, few tasks that suggested to be added to the project. Three tasks to be exact. The first task is quality control monitoring. Since the scope of this project revolves around research, there should be a quantitative and qualitative quality metrics that measure the processes
  • 30. Balgoname 2017 30 of the project and its procedures. The role of this task is to assure that the work is not only done as planned, but also in accordance with national and international quality standards. The second suggested task is to establish a knowledge management (KM) logging to aid the project team along the way. The KM log has short and long-term benefits to the project team and the organization. When utilized correctly, it enables sharing of tacit knowledge among the project team, which shorten the time required to perform tasks. It also benefits the organization as its quality increase the more knowledge is logged. The last suggested task for the project is communication coordination tool. Since two of the project team are working remotely. It is important to facilitate the communication among the project team systematically. Without such a tool, the work might get delayed, or done incorrectly. 3.2 Project Milestones The project has four milestones. Each milestone signifies a major achievement of the project's components. The process of selecting project's milestones is based on SMART, which is an acronym of four words that was created by Peter Drucker's Management by Objectives concepts. Those four words are Specific, Measurable, Achievable, Relevant, and Time-bound (Drucker, 1954). Each of the three milestones is carefully selected to assure that it meets the criteria of SMART. If one of these three milestones did not meet the constraints, it would cause problems later the project life cycle. The first milestone of green computing research project is the signature of the project charter. It is chosen as the first milestone, due to the importance of this task. The signature of the project charter means that everything that is required for the project to go is in place, including scope
  • 31. Balgoname 2017 31 and time management, and budget. The second milestone is gaining the approval of the planning phase. This milestone is of high importance due to the sensitivity of the entire planning phase. It is known that during the planning phase, all the procedures, requirements, and tools get selected; therefore, a successful planning shall increase the possibility of having a successful project. The third milestone of this project is report the findings process, which is the final stage of the research processes. This process has been selected as a milestone because it is the fruit of the project and the final outcome. The last milestone of green computing research project is conducting post review of the project. This task has been selected as a milestone due to the importance of work review. No work is complete without its been reviewed. The rest of the project procedures and tasks are not as important as the mentioned three processes; furthermore, most of the tasks are pre-requisite for meeting the project's three milestones.
  • 32. Balgoname 2017 32 Figure 7: Gantt Chart with milestones, and duration 3.3 Gantt Chart with Duration and Dependencies 3.3.1 Gantt Chart 3.3.2 Network Diagram Figure 8: Network diagram of the project dependencies, and tasks
  • 33. Balgoname 2017 33 3.4 Resource Assignment Matrix Table 7: Resource Assignment Matrix Shown above, is an assignment matrix of the project resources. As explained in the case, the team consists of five team members including the project manager. Assumptions made while assigning the resources matrix: ❖ The project sponsor and manager are responsible for selecting team members ❖ Full-time engagement in the project means 8 hours a day and six months commitment
  • 34. Balgoname 2017 34 Three members of the team, the project manager, James, and Teresa are available 100% to engage in the project. While two of members, Matt, and Lee are available 50% to engage in the project. The project manager is responsible for monitoring and coordinating the project and team members. She is also responsible for reporting performance of the team members. Meanwhile, the remaining four members, Teresa, Matt, James, and Lee are responsible for executing the research. They are also responsible for conducting the post-project review before the final submission of the project. According to the case, attention should be drawn that, one of the team members, Lee, will not be available to work on the project the first four weeks. He will join the team during the planning phase and beyond. Outsourced labor are requested based on specific tasks that require extra manpower, or certain expertise that is not available in the project resources.
  • 36. Balgoname 2017 36 4. Project Cost Management 4.1 Project Planned Cost Budget 4.1.1 Weekly Budget Year Quarter Week Budget Cost Baseline Cost Cost Actual Cost 2017 Q2 Week 17 4282.00 4282.00 4282.00 4282.00 Week 18 7980.00 8190.00 8190.00 8190.00 Week 19 4956.00 5005.00 5005.00 5005.00 Week 20 4956.00 5005.00 5005.00 5005.00 Week 21 4956.00 5005.00 5005.00 5005.00 Week 22 4956.00 5005.00 5005.00 5005.00 Week 23 4956.00 5005.00 5005.00 5005.00 Week 24 4100.00 4004.00 4004.00 4004.00 Q2 Total $41,142.00 $41,501.00 $41,501.00 $41,501.00 Q3 Week 25 7150.00 7260.00 7260.00 7260.00 Week 26 7150.00 7260.00 7260.00 7260.00 Week 27 7150.00 7260.00 7260.00 7260.00 Week 28 7150.00 7260.00 7260.00 7260.00 Week 29 12149.00 12251.00 12251.00 0.00 Week 30 16290.00 17300.00 17300.00 0.00 Week 31 16290.00 17300.00 17300.00 0.00 Week 32 16290.00 17300.00 17300.00 0.00 Week 33 16300.00 17300.00 17300.00 0.00 Week 34 13142.00 13284.00 13284.00 0.00
  • 37. Balgoname 2017 37 Week 35 14430.00 14520.00 14520.00 0.00 Week 36 7150.00 7260.00 7260.00 0.00 Q 3 Total $140,641.00 $145,555.00 $145,555.00 $29,040.00 Q4 Week 37 7260.00 7260.00 7260.00 0.00 Week 38 7260.00 7260.00 7260.00 0.00 Week 39 7260.00 7260.00 7260.00 0.00 Week 40 7150.00 7260.00 7260.00 0.00 Week 41 7260.00 7260.00 7260.00 0.00 Week 42 7150.00 7260.00 7260.00 0.00 Week 43 7150.00 7260.00 7260.00 0.00 Week 44 7260.00 7260.00 7260.00 0.00 Week 45 8852.00 8952.00 8952.00 0.00 Week 46 14479.00 15975.00 15975.00 0.00 Week 47 18745.00 19475.00 19475.00 0.00 Week 48 18745.00 19475.00 19475.00 0.00 Q 4 Total $118,571.00 $121,957.00 $121,957.00 $- 2017 Total $300,354.00 $309,013.00 $309,013.00 $70,541.00 2018 Q1 Week 1 0.00 0.00 17153.00 0.00 Week 2 0.00 0.00 12078.00 0.00 Week 3 0.00 0.00 10090.00 0.00 Week 4 0.00 0.00 4036.00 0.00 Week 5 0.00 0.00 0.00 0.00 Week 6 0.00 0.00 0.00 0.00
  • 38. Balgoname 2017 38 Week 7 0.00 0.00 0.00 0.00 Week 8 0.00 0.00 0.00 0.00 Week 9 0.00 0.00 0.00 0.00 Week 10 0.00 0.00 0.00 0.00 Week 11 0.00 0.00 0.00 0.00 Week 12 0.00 0.00 0.00 0.00 Q 1 Total $- $- $43,357.00 $- 2018 Total $- $- $43,357.00 $- Grand Total $300,354.00 $309,013.00 $352,370.00 $70,541.00 Table 8: Weekly Budget 4.1.2 Resource Usage
  • 39. Balgoname 2017 39 Figure 9: Gantt chart shows resource usage Table 9: Resource usage total hours and cost 4.2 Project BAC and Planned Value Budget at Completion and Planned Value BAC $356,000.00 Planned Value End of Week 4 (BAC x 0.10) $35,000.00 End of Week 8 (BAC x 0.25) $89,000.00 End of Week 12 (BAC x 0.50) $178,000.00 End of Week 15 (BAC x 0.60) $213,600.00 Table 10: BAC and PV values 4.3 Earned Value Analysis Given BAC $366,000.00 PV $180,500.00 EV $191,500.00 AC $206,500.00 Part (A) CV = EV – AC = $ (15,000.00) SV = EV – PV = $11,000.00
  • 40. Balgoname 2017 40 CPI = EV / AC = 0.93 SPI = EV / PV = 1.06 Part (B) EAC = BAC / CPI = $394,668.41 Table 11: Budget analysis Figure 10: Earned Value Chart Shown above, a chart for the earned value (EV) for the given problem. The five indexes, PV, EV, AC, EAC, and BAC that have been utilized examines the Budget at Completion (BAC) against the Variance at Completion (EAC). This project has a variance $28,668 from the planned budget. This overspending occurred due to low-cost performance index (CPI) of this project at 0.93. The project is also behind schedule as the CPI and SPI indexes illustrate. This analysis, is an alarming benchmark. The sponsor, and manager of this project have to take actions to return this project on track to assure its successfulness. $366,000.00 $180,500.00 $191,500.00 $206,500.00 $394,668.41 0 200000 400000 600000 800000 1000000 1200000 1400000 1600000 1 2 3 4 5 6 Earned Value Chart EAC AC EV PV BAC Timeline
  • 41. Balgoname 2017 41 4.4 Corrective Actions Many corrective actions can be made for this given problem to overcome it. First, before hiring consultancy, the project manager has to ensure that he or she have clear specification requirements documentation. The purpose of this document that it specifies in in-depth details the processes and procedures to conduct the project. Any confusion this document causes will cause defects, and errors, that eventually causes delays or complete failure of the project. Another method that assures good outcomes is through measurable quality indexes. These indexes are pre-determined by the project management office or the organization, which reflect what work is considered meets the quality of a certain entity. Lastly, while considering assigning consultant, it is better to test the company through the Capability Maturity Model (CMM). This model is a ranking system consists of five ranks. A company with level one is considered chaotic, while companies with level five considered well established and provide quality work. In this light, and when having good specification requirements, the project team or consultant is closer to achieve better outcomes. A good specification requirement is a road map that illustrates the details of the project including costs. A good quality matrix protects the project from any creeps in scope or budget. Finally, selecting project team including consultants should be systematic and using models such as CMM which identify good from bad consultant to assign.
  • 43. Balgoname 2017 43 5. Project Quality Management 5.1 Quality Management Requirements 5.1.1 Quality Management Approach The objectives of quality management for Green Computing Research Project are to assure: ❖ Project deliverable meet their standards ❖ Project management processes are appropriately developed. Quality management is performed throughout the entire project lifecycle with attention to: 1. Quality Planning 2. Quality Assurance 3. Quality Control 4. Independent Verification and Validation (IV&V) Quality management planning determines quality policies and procedures relevant to the project for both project deliverables and project processes, defines who is responsible for what, and documents compliance. Key Component of Quality Management Plan Objects of quality review Quality Measure Quality Evaluation Method Project Deliverables Deliverables Quality Standards Customers Satisfaction Quality Control Activities Project Processes Processes Quality Standards Stakeholders Expectations Quality Assurance Activities Table 12: Components of QMP 5.1.2 Quality Objectives and Standards Identification 5.1.2.1 Project Deliverables ❖ The research should be well formulated, and the purpose of the study should be clear ❖ The research should be well designed and executed ❖ The research should demonstrate an understanding of related studies ❖ The research should utilize best available data and information ❖ The research assumptions should be explicit and justified ❖ The findings should advance knowledge and bear on important policy issues ❖ Implications and suggestions should be logical, warranted by the findings, and explained thoroughly, with appropriate caveats ❖ Documentations should be accurate, understandable, clearly structured, and temperate in tone ❖ The research should be compelling, useful, and relevant to stakeholders and decision makers ❖ The research should be objective, independent, and balanced 5.1.2.2 Project Processes ❖ The PDCA Cycle ❖ Cause and Effect Diagram
  • 44. Balgoname 2017 44 ❖ Pareto Charts; ❖ Control Charts ❖ Maturity Models 5.1.3 Project Reviews and Assessments Review Type Frequency Tools Reviewer Reports Project Charter Constant reviews until approval of charter ISO, IEEE Project Manager Attach finalized reports of all reviews conducted under the project quality management document Project Management Plan Scope Management Plan Requirements Management Plan Requirements Documentation Once after completion WBS Constant reviews Microsoft Project Scope Baseline Microsoft Project, Microsoft Excel Schedule Management Plan Activity Plan Schedule Baseline Cost Baseline Stakeholder Management Plan Once after completion ISO, IEEE Table 13: project reviews and assessments table 5.1.4 Deliverable Acceptance Criteria Deliverable Final Approval Process Stakeholder Acceptance Criteria Financial analysis Ongoing Proper mathematical calculations Recommended Solutions Ongoing Based on logical comprehension approachOrientation completion Ongoing Possible technologies to implement Ongoing Standard work and reporting Ongoing Follow American reporting and citation standards Table 14: project deliverable acceptation criteria table
  • 45. Balgoname 2017 45 5.2 Seven Basic Tools of Quality The Project Management Institute (PMI), references the seven basic tools in a guide to the Project Management Body of Knowledge (PMBOK), as an example of a set of general tools useful for planning or controlling project quality. The Seven Basic Tools of Quality is a name given to a set of graphical models, which are identified as being most helpful in troubleshooting issues related to quality. Since they are basic, they are easy to utilize as they require little formal training in statistics. Also, they can be used to solve most of, much of quality related issues. (Project Management Institute, 2013) The seven tools are the following: ❖ Cause-and-effect diagram also known as the "Ishikawa diagram" or "fishbone" ❖ Control Chat ❖ Check sheet ❖ Pareto chart ❖ Histogram ❖ Scatter diagram ❖ Stratification (alternately, flow chart or run chart) The Cause and Effect diagram can be utilized in Green Computing research to examines why something happened or might happen by potential causes into smaller categories. It also can be useful for showing the relationship between contributing factors. Another useful tool is the histogram, which is a graphical depiction of how many times different, mutually exclusive events are inspected in an experiment. The two explained tools and all other seven tools have to be utilized in the project to guarantee more high level of quality.
  • 46. Balgoname 2017 46 5.3 Summary of High Quality Research Report In 2014, the Journal of Chemical and Pharmaceutical Sciences (JCHPS), published a report by Namburi Anupama concerning green computing. Mr. Anupama has done phenomenal work in explaining green computing. The report describes and defines in depth green computing and its implications. The paper aims to urge organizations to apply green computing through many practices, such as saving energy during idle operation, using eco-friendly sources of energy, reducing harmful effects of computing resources, and reducing computing wastes. Furthermore, the author provided tangible examples where green computing practices have positively impacted organization financially, environmentally, and socially. For instance, one of the programs that were mentioned in this paper is about cooling database centers through the leveraging of local climate to cool down data center instead of using air conditions to do so. The program was effective and shown tremendous financial and environmental benefits. (Anupama, 2014) This paper is of high-quality sources that would aid the team in conducting the research due to many facts. First, this paper has been revised by academic researchers and published in a scientific journal. Second, the author has provided an excellent definition of green computing, and its practices in the organization. Third, this report contains many useful sources that; when considering, it will enlighten the project team to enrich their work further. Due to these reasons, I believe this paper must be one of the sources that will be used to build upon out green computing research.
  • 48. Balgoname 2017 48 6. Project Human Resource Management 6.1 MBTI Types in Work Environments 6.1.1 MBTI Personality types MBTI stands for The Myers-Briggs Type Indicator. MBTI was designed by Carl Jung’s theory of psychological type. It indicates individuals’ personality preferences in four dimensions: ❖ Where individual focus his/her attention - Extraversion (E) or Introversion (I) ❖ The way individual take information - Sensing (S) or Intuition (N) ❖ How individual makes decisions - Thinking (T) or Feeling (F) ❖ How individual deal with the world - Judging (J) or Perceiving (P) There are 16 unique MBTI personalities: • ISTJ • ISFJ • INFJ • INTJ • ISTP • ISFP • INFP • INTP • ESTP • ESFP • ENFP • ENTP • ESTJ • ESFJ • ENFJ • ENTJ Each four letters make up individuals personality type. When individuals know their personality type, it can help them understand their behavior and interacting with others better. While there are no personalities better than others; there are, however, a preference to certain personality types based on the nature of this project that requires the ability to conduct research. To narrow the search scope of the preferred personality types. (Jung, 1971) The 16 personality types can be break into four sub-sets: Analysts This group of personality type contains four personalities all of which revolve around analytical skills. Those four personality types are: INTJ, INTP, ENTJ, and ENTP. The first personality INTJ individual is an imaginative and strategic thinker. While INTP individual is an inventor with a thirst for knowledge. The ENTJ personality individual is bold, imaginative and strong-
  • 49. Balgoname 2017 49 willed leader, and always trying to find a way or solution to a certain problem. Lastly, ENTP personality individual is a smart and curious thinker who cannot resist an intellectual challenge. Diplomats This group also contains four personality types whom skills lean toward diplomacy. Those four types are INFJ, INFP, ENFJ, and ENFP. The INFJ individual is a quiet and mystical person, yet very inspiring and tireless idealists. An individual with INFP personality type is a poetic, kind and altruistic person, always eager to help a good cause. The ENFJ individual is charismatic and inspiring leaders, and able to mesmerize their listeners. Lastly, the ENFP individual is enthusiastic, creative and sociable free spirit, who can always find a reason to smile. Sentinels This four personality types group consists of ISTJ, ISFJ, ESTJ, and ESFJ. The first type ISTJ individual is a rational and fact-minded individual, whose reliability cannot be doubted. The second personality individual ISFJ is very dedicated and warm protector, and always ready to defend their interests. The third personality individual, ESTJ is an excellent administrator, and unsurpassed at managing things, or people. Finally, the ESFJ individual is an extraordinarily caring, social, and accessible person and always eager to help. Explorers This group of four personality types consists of ISTP, ISFP, ESTP, and ESFP all of which have skills related to exploration. The ISTP personality individual is a bold and practical experimenter, and master of all kinds of tools. The ISFP individual is a flexible and charming artist, and always ready to explore and experience something new. An individual with ESTP personality type is a smart, energetic, and very perceptive person, who truly enjoy living on the
  • 50. Balgoname 2017 50 edge. Lastly, ESFP individual is a spontaneous, energetic, and enthusiastic person, who is admired by his peers. (Meade, 2017) 6.1.2 Introductory Email Project team, Myself and on behalf the project sponsor, I am delighted to welcome you to the Green Computing Research Project. As you may all know that our project is a high priority to our organization, as it will provide solutions to overcome the consumption of energy problem and reduce the bad impact on our environment. Dear team members, I am fully confident in your abilities to make this project reality. You all have shown good competencies and you have been selected among others according to this fact. Thank you for being part of our team and I hope our project with your participation and cooperation sees the light. Best regards, Project Manager 6.2 Responsibility Assignment Matrix RACI The Responsibility Assignment Matrix (RAM), or Linear Responsibility Chart (LRC), represents the participation by different duties in achieving tasks or deliverables for a project or business process. It is valuable in defining duties and obligations in cross-functional/ departmental projects and processes. Assumptions for the RAM The RACI acronym is derived from four key responsibilities most typically used: ❖ Responsible - Individuals who do the work to achieve the task
  • 51. Balgoname 2017 51 ❖ Accountable - The ultimately responsible person for the correct and thorough completion of the deliverable or tasks ❖ Consulted - Individuals whose opinions are sought, typically subject matter experts ❖ Informed - Individuals who are kept up-to-date on progress Table 15: Resources Assignment Matrix (RAM) with RACI responsibilities.
  • 52. Balgoname 2017 52 6.3 Human Resources Related Concerns Human resources are the most important element of any work. They are the real asset and working power of any organization or organized work. The influence of human resources is so powerful and reflects, either positively or negatively on their work based on the challenges and circumstances. This paper spotlight some of the challenges and concerns that might encounter a project's human resources. There are many human resources contributing factors for project failure, such as stakeholders, motivation, diversity in (culture, ethnicity, and protected groups), work environment. One factor that contributes to project failure is related to the lack of project management expertise in an organization. When a project team's risks are given little or no prominence, it creates resistance, apathy, and lack of engagement, which have a significant impact on the procedures and timelines of the project plan. The project's human resource management is a multifaceted process. The project manager is solely responsible for lead, direct and orchestrate the project team, customers, contributors, partners, and any other stakeholders to achieve the desired results for the project's purpose, which is a huge challenge and subject to wrong personal judgment. Therefore, throughout the project, the project manager has to address project team retention, labor relations, and performance appraisal and depending on the nature of the project work, health and safety concerns. The number of stakeholders in the project sometimes change; therefore, the project manager and project team need to be aware of the incoming flux of interested parties and how this shift may affect the dynamics of the project work and the project team. One approach to project human
  • 53. Balgoname 2017 53 resources may work well in one phase of the project, yet it might not work in another phase due to the stakeholders who involve. Since individuals drive processes, it is logical to build competencies in employees’ management skills as well as in quantitative and analytical process management. The project manager may have to pull together teams of employees who do not work for the same organization. For instance, contractors view themselves as peers or colleagues and where they must be managed differently from the organization's employees. The workforce is diverse more than ever before, not only culturally and ethnically, but also in other ways as well. It includes older workers, women, disabled individuals and other protected groups by law from discrimination. Moreover, with the demands for skilled, high-tech workers at all levels, employees’ searches span the globe and cross-cultural barriers. In project work environment, organizations cannot offer permanent employment, nor can they guarantee raises, benefits, job definition, management stability. Moreover, they cannot repay loyalty with loyalty or hard work with compensation. Thus, the challenges of motivating employees go beyond their abilities. A stressful work environment results in stressed employees, and when employees are stressed, they are more likely to make mistakes and perform at less than their optimal levels. The more mistakes employees make, the worse they feel about their jobs and themselves, and the more likely they are experience burnout. A high burnout rate leads to a high turnover rate, and eventually, more time for a project manager spent on rehiring and retraining. Staying within time and budget limits goes a long way toward stress-free project management within the process and human resources issues that come with the job. Many problems can happen to throw project processes off schedule; however, managing personnel matters properly can do a great deal towards maintaining the project running smoothly.
  • 55. Balgoname 2017 55 7. Project Communication Management 7.1 Project Issue Log Project Green Computing Research Project Project Manager Mia Project Description Research possible green computing application for internal use and possible sale to other organizations ID Status Priority (L/M/H) Issue Disruption Assigned to Expected Resolution Date Escalation Required (Y/N) Impact Summary 1 Work in progress H Couple of team members do not use the share site to post their work and use e-mails instead. Teressa 6/20/2017 Yes This issue hinders the progress of work as it requires more time to check on work done and provide feedback though wiki tools. 2 Open M Some of team members are not using webcams during conference calls. Matt 7/17/2017 Yes This issue prevents visualized meetings, which enhance the team meeting experience. It also hinders the credibility to participation. 3 Closed L Lack of time commitment during team meetings. Meeting times goes beyond what is planned. Project Manager 7/20/2017 No This issue consumes some of the team members time, which can be spent on other necessary work. 4 Open H Lack of enough date. Recommendation deliverable is behind schedule. Teressa 7/28/2017 Yes This issue might cause possible delay to the project as it part of the project core. Table 16: Issue Log
  • 56. Balgoname 2017 56 7.2 Applications of Wikis Wiki is one of the most common buzzwords on the internet. The term wiki means quick in Hawaiian, and it also defined as a website tool that enables collaborative editing of its content and structure by its users. What makes wiki a useful instrument in the project work, is it collaborative editing environment that allows brainstorming, and discussion of various ideas without the need of having the participants in one place. Wiki is widely adapted in many organization today, due to its swiftness, and effectiveness of allowing participants to generate contents. (LeBar, 2017) Some of the project team members have concerns about using wiki because they do not want other team members to change, or edit their work; therefore, they are not using the wiki tool to post their work. They instead use the email to send their work, which consumes a precious time for the rest of the team. The use of wiki can be very chaotic or very organized. If there are rules and policies of using wikis, the tool is organized and fruitful; on another hand, if there are no rules or policies on who do what, the tool is causing chaos. Having rules and policies of using wiki will satisfy the concerns of some of the team members and assure the effectiveness of utilizing the tool. In conclusion, wiki is very valuable tool, given the nature of the project is heavily research. It will allow team members to brainstorm and share their ideas, which will positively reflect on the work. The fact, that wiki is a tool that allow participant to share and edit the content, made some of the project members withdrawal from participating and preferred traditional communication method – the e-mails. However, if there are rules and polices of the way participant generate, edit, and share content, the team members’ concerns are solved.
  • 57. Balgoname 2017 57 7.3 Conflict Resolution As part of the project management, there must be a method to approach conflict and control it in a way that limits the negative impact on the project and the team. Conflict management is the means of limiting the adverse aspects of conflict while increasing the positive side of the conflict. The purpose of conflict management is to enhance learning and group outcomes, including effectiveness or performance in an organization setting. When conflicts managed properly, it can improve team results and reduces the negative impact Conflict resolution is a method for two or more parties to find a peaceful solution to disagreement among them, due to personal, financial, political, or emotional reasons. Conflict resolution conceptualized as the method and processes implicated in facilitating the peaceful ending of conflict. A project manager can attempt to resolve a conflict by communicating about conflicting ideologies, or motives to the individual(s), and by involving in bilateral negotiation. There are procedures for addressing conflicts, including negotiation, mediation, and arbitration. . (Afzalur Rahim, 2002) For the Green Computing Research Project, the aim of conflict resolution is to solve a problem through negotiation immediately, once a problem or conflict occurs. By doing so, most of the conflicts would not escalate to require mediation and or arbitration. the project, few conflicts occurred among the project team in the communication management. Here are some of these issues and how they can be solved. First, James and other team members did not seem uncomfortable using collaboration tools to post their work, arguing that other team members might change, or edit their work, which eventually leads to delaying the work and impedes the progress of the project. Solving this issue requires knowing that one's enemy is unknowingness; in this case, it is possible that the team members are not aware of how to use the wiki tool and control it in a way that allows only authorized an individual to edit a certain post. It is also recommended during the training
  • 58. Balgoname 2017 58 sessions to explain how to use wiki tool efficiently and adequately and at the same time emphasize the benefits that it brings to the project and its team members from agility, flexibility, and security. Another conflict arose while in project management was that some team members failed to use webcams during team meetings. In this case, the project manager should stress the importance of having webcam during video conferences. Since few of the project team are working remotely, it makes them feel isolated from the work environment and lead to losing their motivation to work. Having a webcam during conferences stimulates the team members to work better because they are metaphorically meeting face-to-face with their peers and it also increases the participant's seriousness to share their arguments and inputs. Another issue that arose was that during meetings the team did not adhere to the predetermined meeting time, which affects other team members because they are occupied with other important matters. The project manager should state three important policies at the beginning of each meeting to increase the effectiveness of meetings. First, the manager should indicate the subject of the meeting, what and what not it includes for discussion during the meeting. The project manager also must remind the team of the meeting time boundaries, when it starts, and when it ends. Finally, it is important that the project manager state what he or she is looking forward to accomplishing by the end of the meeting. Overall, conflicts are an inevitable matter. It could be caused for legitimate or illegitimate reasons, and it might happen anytime. The ability to deal with conflict and manage it is extremely important to assure a steady progress of the work. There are many approaches to achieving conflict resolution such as negotiation, mediation, and arbitration. The leader's ability to encounter conflicts and solve them are a pivotal point that can sway the dispute to an end or an escalation.
  • 60. Balgoname 2017 60 8. Project Risk Management 8.1 Risk Register Table 17: Risk register table contacting seven possible risks for Green Computing Project
  • 61. Balgoname 2017 61 8.2 Risk Assessment and Impact Matrix Table 18: Risk Assessment and Impact matrix
  • 62. Balgoname 2017 62 Table 19: Risk Response and Contingency Plans 8.3 Risk Response and Contingency Plans
  • 64. Balgoname 2017 64 9. Project Procurement Management 9.1 Contract Agreement with Anne Consulting Firm Service Contract Agreement THIS SERVICE AGREEMENT (the “Agreement”) dated this 5th day of July, 2017 BETWEEN: We Are Big, Inc. (the “Client”) -AND- Anne Consulting (the “Contractor”). BACKGROUND: A. The Client is of the evaluation that the Contractor has the required experience, abilities, and qualifications to provide services to the Client. B. The Contractor is amenable to granting such services to the Client on the conditions and terms set out in this Agreement. IN CONSIDERATION OF the matters explained above and of the mutual benefits and commitment outlined in this Agreement, the receipt and sufficiency of which consideration is hereby acknowledged, the Client and the Contractor (independently the “Party” and collectively the “Parties” to this Agreement) agree as follows: Services Provided 1. The Client hereby accepts to engage the Contractor to provide the Client with the following services (the “Services”): • Support project team in research work to generate ideas for green computing • Provide consultants for the project as per need for the project 2. The Services will include any other duties which the Parties shall agree on. The Contractor hereby consents to provide such Services to the Client.
  • 65. Balgoname 2017 65 Term of Agreement. 3. The term in this Agreement (the “Term”) will be effective on the date of this Agreement and will abide in full force effect until the completion of the Services, subject to earlier termination as provided in this Agreement. The Term of this Agreement may be extended with the written consent of the Parties. 4. In the event that either Party violates an article provision under this Agreement, the non- defaulting Party against all reasonable damages. Performance 5. The Parties consent to do everything necessary to ensure that the terms of this Agreement take effect. 6. Except as otherwise granted in this Agreement, all monetary amounts indicated to in this Agreement are in US Dollars (USD). Compensation 7. The Contractor will charge the Client an hourly rate of $190.00 for Anne’s Services. The Contractor will also charge the Client $150.00 per hour for any other consultants that is subject to a maximum of 100 hours (the “Compensation”). 8. The Client will be billed when the Services are finished. 9. Invoices handed by the Contractor to the Client are due within 30 days of submission. 10. In the event that the Client ended this Agreement prior to completion of the Services, but where the Services have been partly performed, the Contractor will be entitled to pro rata payment of the Compensation to the date of end provided that there has been no breach of contract on the part of the Contractor. 11. The Compensation as declared in this Agreement does not include sales tax or other applicable duties as may be required by law. Any charges and sales tax required by law will be charged to the Client in addition to the Compensation. Reimbursement of Expenses 12. The Contractor will be repaid from time to time for reasonable and necessary expenses incurred by the Contractor in relation to providing the Services.
  • 66. Balgoname 2017 66 13. All expenditures must be previously approved by the Client. Confidentiality 14. Confidential information (the “Confidential Information”) attributes to any data or information relating to the business of the Client that would reasonably be considered to be proprietary to the Client including, but not limited to, business processes, accounting records, and client records and that is not generally known in the industry of the Client and wherever the reveal of that Confidential Information could reasonably be expected to cause harm to the Client. 15. The Contactor agrees that they will not disclose, divulge reveal, report or use for any purpose, any confidential information that the Contractor has obtained, except as authorized by the Client or as required by law. The responsibilities of confidentiality will apply during the term of this Agreement and will survive indefinitely upon termination of this Agreement. 16. All oral and written information and materials disclosed or provided by the Client to the Contractor under this Agreement are Confidential Information despite whether it was provided before or after the date of this Agreement or how it was presented to the Contractor. Ownership of Intellectual Property 17. All intellectual property and associated material, including any trade secret, moral rights, goodwill, relevant registrations or applications for registration, and rights in any copyright, patent, trademark, trade dress, industrial design and trade name (the “Intellectual Property”) that is produced or developed under this Agreement, is a “work made for hire” and will be the individual property of the Client. The utilize of the Intellectual Property by the Client will not be bound in any way. 18. The Contractor may not utilize the Intellectual Property for any purpose other than that contracted for in this Agreement except with the written agreement of the Client. The Contractor will be liable for any and all damages occurring from the unauthorized utilization of the Intellectual Property. Return of Property
  • 67. Balgoname 2017 67 19. Upon the expiration or termination of this Agreement, the Contractor will return to the Client any property, records, documentation, or Confidential Information which is the property of the Client. Capacity/Independent Contractor 20. In providing the Services in accordance with this Agreement, it is expressly agreed that the Contractor is acting as an autonomous contractor and not as an employee. The Contractor and the Client reckon that this Agreement does not constitute a joint venture or partnership between them, and is solely a contract for service. The Client is not required to pay, or make any contributions to, any social security, local, state or federal tax, unemployment compensation, workers’ compensations, insurance premium, profit- sharing, pension or any other employee benefit for the Contractor during the Term. The Contractor is obligated for paying and complying with reporting requirements for, all local, state and federal taxes associated with payments made to the Contractor under this Agreement. Notice 21. All notices, requests, demands or other communications required or permitted by the terms of this Agreement will be given in writing and hand over to the Parties at the following addresses: • 700 Liberty Ave, Pittsburgh, PA 15222 • 201 Fifth Ave, Pittsburgh, PA 15222 Or to other address as either Party shall notify the other, and will be deemed to be properly hand over (a) immediately upon being served personally, (b) two days after being deposited with the postal service is served by registered mail, or (c) the following day after being deposited with an overnight courier. Indemnification 22. Except to the amount paid in settlement from any applicable insurance policies, and to the extent permitted by applicable law, each Party accepts to indemnify and hold harmless the other Party, and its respective employees, officers, agents, affiliates,
  • 68. Balgoname 2017 68 officers, and permitted successors and assigns against any and all claims, damages, losses, penalties, liabilities, punitive damages, expenses, reasonable legal fees and costs of any kind or amount whatsoever, which arise or result from out of any act or omission of the indemnifying party, its own affiliates, officers, agents, employees, and permitted successors and assigns that occurs in connection with this Agreement. Modification of Agreement 23. Any amendment or modification of this Agreement or additional obligation assumed by either Party in connection with this Agreement will only be obligated if evidenced in writing signed by each Party or an authorized representative of each Party. Time of the Essence 24. Time is the essence in this Agreement. No variation or extension of this Agreement will operate as a waiver of this provision. Assignment 25. The Contractor will not willingly, or by operation of law, assign or otherwise transfer its obligations under this Agreement without the prior written approval of the Client. Entire Agreement 26. It is agreed that there is no representation, warranty, collateral agreement or condition affecting this Agreement except as expressly provided in this Agreement. Enurement 27. This Agreement will guarantee to the benefit of and be binding upon the Parties and their respective administrators, executors, heirs, and permitted successors and assigns. Titles/Headings 28. Headings are inserted for the convenience of the Parties only and are not to be considered when interpreting this Agreement. Gender
  • 69. Balgoname 2017 69 29. Words in the plural mean and include the singular and vice versa. Words in the masculine mean and include the feminine and vice versa. Governing Law 30. This Agreement will be ruled by and construed in accordance with the law of the State of Pennsylvania. Severability 31. In the event where any of the terms of this Agreement are held to be unenforceable or invalid in whole or in part, all other terms will nevertheless continue to be enforceable and valid with the invalid or unenforceable parts severed from the remainder of this Agreement. Waiver 32. The waiver by either Party of a delay, breach, default, or omission of any of the provisions of this Agreement by the opposite Party will not be construed as a waiver of any following breach of the same or other provisions. IN WITNESS OF THIS the Parties have duly affixed their signatures under hand and seal on this 5th day of July 2017 ___We Are Big, Inc._________________ ____________________________(Client) __Anne Consulting__________________ ________________________(Contractor)
  • 70. Balgoname 2017 70 9.2 Content of Research Report 9.2.1 Executive Summary This project was commissioned by the Environment Technologies Program of We Are Big, Inc. The project aims to find possible green computing technologies that reduces energy consumption and increases the efficiency of computing power. Green computing or eco-friendly computing is a term that refers to the environmental responsibility use of computers and their resources, where the designing, engineering, manufacturing, and disposing of computing devices have minimal impact on the environment. Through researching, the project team will work to generate ideas, methods, and technologies that work in accordance with the definition of green computing and based on the financial analysis. The prospect outcomes will help the We Are Big, Inc. to rationalize energy consumption, which would reflect on savings of budget money. Once the technology proves effective, the company aims to provide its expertise and technologies to other company to harvest the benefits of green computing. 9.2.2 Table of Contents Preface …………………………………………………………………………………………. 2 Executive Summary ……………………………………………………………………………. 3 Table of Content ………………………………….……………………………………….……. 4 Introduction ……………………………………………………………………………………... 5 Green computing Solutions …………………………………………………………………..…. 8 Financial Analysis …………………………………………………………………………….... 10 Conclusion ……………………………………………………………………………………... 12
  • 71. Balgoname 2017 71 9.3Lesson Learned 1. Having a realistic financial planning will allow the project manager to avoid spending issues during the span of project life cycle. 2. The quality of the project is how it is defined; therefore, it is important to search for best standards, and practices to guarantee optimum results. 3. Outsourced labors do overcome workers shortages; however, it is tough to control the work quality. 4. Conflicts among team members are inevitable, therefore, the project manager ability to resolve conflicts is very crucial to maintain the progress of the project and avoid expensive costs.
  • 73. Balgoname 2017 73 10. Periodic Reporting: Project Monitoring and Controlling 10.1 Week 13 Work Progress 10.1.1 Gantt Chart Update
  • 75. Balgoname 2017 75 10.1.3 Budget Report Update 10.1.4 EVM Analysis
  • 76. Balgoname 2017 76 10.1.5 Status Report Week 13 goes as planned with work and budget. Currently, the project team has successfully finished the first two phases – initiation, and planning. We are waiting for the approval to proceed with the project execution. The indexes of schedule performance (SPI) and cost performance (CPI) are showing a positive performance of the project processes.
  • 77. Balgoname 2017 77 10.2 Week 14 Work Progress 10.2.1 Gantt Chart Update
  • 79. Balgoname 2017 79 10.2.3 Budget Report Update 10.2.4 EVM Analysis
  • 80. Balgoname 2017 80 10.2.5 Status Report Week 14 goes as planned with work but with a variance of actual spending that is less than budget by $6,250. So far, the project team has successfully finished the processes of the second phases – planning. We are currently waiting for the sponsor approval to proceed with the project execution. The project Schedule Performance Index (SPI) is indicating a normal progress, while Cost Performance Index (CPI) is showing a positive performance due to the cost variance.
  • 81. Balgoname 2017 81 10.3 Week 15 Work Progress 10.3.1 Gantt Chart Update
  • 83. Balgoname 2017 83 10.3.3 Budget Report Update 10.3.4 EVM Analysis
  • 84. Balgoname 2017 84 10.3.5 Status Report Week 15 goes as planned with work and budget. Currently, the project team has successfully finished the first two phases – initiation, and planning. The project team received the approval to proceed with the project execution. The indexes of schedule performance (SPI) and cost performance (CPI) are showing a positive performance of the project processes.
  • 85. Balgoname 2017 85 10.4 Week 16 Work Progress 10.4.1 Gantt Chart Update
  • 87. Balgoname 2017 87 10.4.3 Budget Report Update 10.4.4 EVM Analysis
  • 88. Balgoname 2017 88 10.4.5 Status Report Week 16 goes as planned with work but with a positive variance of actual spending that is more than budget by $6,250. So far, the project team has successfully finished the processes of the second phases – planning. Currently, the project team are executing the first task of the project’s WBS. The project Schedule Performance Index (SPI) and Cost Performance Index (CPI) are showing a normal progress.
  • 89. Balgoname 2017 89 10.5 Week 17 Work Progress 10.5.1 Gantt Chart Update
  • 93. Balgoname 2017 93 10.5.5 Status Report Week 17 goes as planned with work and budget. Currently, the project team has successfully finished the first two phases – initiation, and planning. The project team has successfully finished the processes of the first task of the execution phases – survey analogues researches and currently, they are executing the second task of the project’s WBS. The indexes of schedule performance (SPI) and cost performance (CPI) are showing a positive performance of the project processes. 10.6 Week 18 Work Progress 10.6.1 Gantt Chart Update
  • 96. Balgoname 2017 96 10.6.4 EVM Analysis 10.6.5 Status Report Week 18 went as planned schedule and budget. Both cost and schedule performance indexes are indicating a normal to positive work progress
  • 97. Balgoname 2017 97 10.7 Week 19 Work Progress 10.7.1 Gantt Chart Update
  • 99. Balgoname 2017 99 10.7.3 Budget Report Update 10.7.4 EVM Analysis
  • 100. Balgoname 2017 100 10.7.5 Status Report Only 50% of scheduled work has been done while planned budget has been consumed. Both schedule and cost performance indexes are showing a negative progress.
  • 101. Balgoname 2017 101 10.8 Week 20 Work Progress 10.8.1 Gantt Chart Update
  • 103. Balgoname 2017 103 10.8.3 Budget Report Update 10.8.4 EVM Analysis
  • 104. Balgoname 2017 104 10.8.5 Status Report Only one-half of what was planned got completed, but spend all the budget on the tasks scheduled for week 20. We have not expected any delays as we have rescheduled delayed work to meet the deadline. Based on the schedule and cost performance indexes, during weeks 5, and 6 work was ahead of what was scheduled, which will substitute to the delays occurred week 20.
  • 105. Balgoname 2017 105 10.9 Week 21 Work Progress 10.9.1 Gantt Chart Update
  • 107. Balgoname 2017 107 10.9.3 Budget Report Update 10.9.4 EVM Analysis
  • 108. Balgoname 2017 108 10.9.5 Status Report Week 21 went as planned. The delays occurred during week 20 has been taken care of and work is gradually moving to planned schedule thanks to the actions that have been taken to overcome the schedule issues.
  • 109. Balgoname 2017 109 10.10 Week 22 Work Progress 10.10.1 Gantt Chart Update
  • 111. Balgoname 2017 111 10.10.3 Budget Report Update 10.10.4 EVM Analysis
  • 112. Balgoname 2017 112 10.10.5 Status Report Total work planned is completed for this stage of the project and budget meets the original budget for week 22. Based on the schedule and cost performance indexes, the project is progressing as scheduled with no positive or negative variance of the budgeted costs.
  • 113. Balgoname 2017 113 10.11 Week 23 Work Progress 10.11.1 Gantt Chart Update
  • 115. Balgoname 2017 115 10.11.3 Budget Report Update 10.11.4 EVM Analysis
  • 116. Balgoname 2017 116 10.11.5 Status Report Only one-half of scheduled work has been achieved during week 23. We have experienced a positive variance of budgeted costs by $7,000 more. The project manager with the project team has met to discuss options that can be taken to overcome this problem.
  • 117. Balgoname 2017 117 10.12 Week 24 Work Progress 10.12.1 Gantt Chart Update
  • 119. Balgoname 2017 119 10.12.3 Budget Report Update 10.12.4 EVM Analysis
  • 120. Balgoname 2017 120 10.12.5 Status Report Week 24 went as planned with schedule and budget. Based on the cost and schedule performance indexes for this week, the project has been affected by week’s 23 delays and over spending. The project manager is assessing the possibility of eliminating some of executable tasks of the project if the schedule performance does not meet the planned schedule time by week 26.
  • 121. Balgoname 2017 121 10.13 Week 25 Work Progress 10.13.1 Gantt Chart Update
  • 123. Balgoname 2017 123 10.13.3 Budget Report Update 10.13.4 EVM Analysis
  • 124. Balgoname 2017 124 10.13.5 Status Report Week 25 went as planned with budget and schedule.
  • 125. Balgoname 2017 125 10.14 Week 26 Work Progress 10.14.1 Gantt Chart Update
  • 127. Balgoname 2017 127 10.14.3 Budget Report Update 10.14.4 EVM Analysis
  • 128. Balgoname 2017 128 10.14.5 Status Report By the end of week 26 work and budget wet as planned.
  • 129. Balgoname 2017 129 10.15 Week 27 Work Progress 10.15.1 Gantt Chart Update
  • 131. Balgoname 2017 131 10.15.3 Budget Report Update 10.15.4 EVM Analysis
  • 132. Balgoname 2017 132 10.15.5 Status Report All the work planned for week 27 have been completed on planned schedule. The project experienced a positive variance of actual cost by $5,500 more. The project cost performance is showing a negative performance while the schedule performance index is still maintaining a normal performance. As the project continues the project manager might take necessary actions to maintain an actual spending based on what is budgeted.
  • 133. Balgoname 2017 133 References Afzalur Rahim, M. (2002). Toward A Theory of Managing Organizational Conflict. The International Journal of Conflict Management, Vol. 13(No. 3), pp. 206-235. Anupama, N. (2014, October). Green Computing, A Smart Computing. Journal of Chemical and Pharmaceutical Sciences, 1(3), 170-171. Retrieved from http://jchps.com/specialissues/Special%20issue3/40%20jchps%20si3%20addn%20anupama%20 170-171.pdf Drucker, P. F. (1954). The Practice of Management. New York, NY: Harper Collins Inc. . Retrieved May 30, 2017 Jung, C. G. (1971, August 1). Psychological Types. Collected Wrks of C.G. Jung, Vol. 6. Kurp, P. (2008, October 1). Green Computing. Communications Of The ACM, Vol. 51(No. 10), pp. 11-13. LeBar, Z. (2017, April 3). What Are Wikis, and Why Should You Use Them? Retrieved June 18, 2017, from Envato Tuts+: https://business.tutsplus.com/tutorials/what-are-wikis-and-why-should-you-use- them--cms-19540 Meade, J. (2017, April 13). This Is Why People Are Intimidated By You, Based On Your Personality Type. Retrieved from http://thoughtcatalog.com: http://thoughtcatalog.com/jennifer- meade/2017/04/this-is-why-people-are-intimidated-by-you-based-on-your-personality-type/ Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide). Newtown Square, PA, USA: Project Management Institute. Rouse, M. (2010, March 4). Carbon Footprint. Retrieved from Tech Target: http://whatis.techtarget.com/definition/carbon-footprint Singh, J. V., & Vatta, S. (2016, January-February 1). Green Computing: Eco Friendly Technology. International Journal of Engineering Research and General Science, Vol. 4(No. 1), pp. 280-283. Sultana, A., Suvarchala, C., & Ramay, A. (2016, January 10). A Study on Green Computing: The Future Computing and Eco-Friendly Technology. International Journal of Innovation Research & Development, Vol. 5(No. 2), pp. 35-39. Techopedia. (2017, May 5). Green Computing Definition . Retrieved from https://www.techopedia.com/definition/14753/green-computing The Green Grid. (2017, May 6). About. Retrieved from The Green Grid: https://www.thegreengrid.org/en/about-us U.S. Environmental Protection Agency. (2016). Climate Protection Partnerships 2014 Reprot. Washington D.C. : Office of Atmospheric Programs.