SlideShare a Scribd company logo
GENERAL DEFICIENCIES
FOUND DURING
INSPECTION AND REMEDY
WITH CASE STUDIES
Introduction
Incidents of distress can be attributed to the
deficiency of planning, structural design,
hydraulic design, fabrication, erection,
operation and maintenance. Vibration,
cavitations, non-closure, corrosion, erosion
and aging problems, improper selection of
materials and neglect of lubrication of
components have resulted in mal-functioning
and even failures of gates in the past.
(1)Fig (1)
(1) Problem and Solution
Problem:
Washing away of the gate took place due to detachment of left side
trunnion girder
On inspection of all gates, the following deficiencies of gate
structures were observed:
1. Inadequate welding between trunnion girders and tie flats. In fact
the flats were welded only at flanges of trunnion girders.
2. Existence of substantial gaps of varying degree between tie flats
and webs of trunnion girders.
3. Eccentricity due to incorrect alignment of trunnion girders
4. Apprehensions about inadequacy, welding the insulated tie flats with
anchor girders
(1) Contd…
Solution:
1. An improvised scheme adopted to connect the webs of the trunnion
girders and tie flats by way of welding additional plates all along the
web of the trunnion girder on either side of each tie flat. (See Fig.)
2. In order to tackle eccentric transfer of load from trunnion bracket to
trunnion girder, additional plates of triangular shape were welded on
the flange plate of trunnion girder .
(1) Contd…
Solution:
3. In view of suspected deficiency of tie flat- anchor girder
junction, one tie flat near upstream flange of anchor girder
was exposed and it was revealed that the tie flats were
welded only to flanges and not to the webs of the anchor
girder.
4. The tie flats were welded only to flanges and not to the webs
of the anchor girder. Drive pins to connect the tie flats and
anchor girders and weld the pins to lock (See Fig). The
blockouts were then filled by epoxy mortar and epoxy grout.
(2) Failure of Radial Gate Leaf
Gate Features: 23nos. 12.941m x 9.85m and 2 nos. 4.877
x 9.85m spillway radial gates operated by rope drum hoists.
(2) Problem and Solution
Problem:
One of the end gates of smaller span failed while in closed position
at the the top right arm and horizontal girder. Failure of the
corresponding joint between bottom arm and horizontal girder and
also between the arm and trunnion hub, resulted in wrenching away
the arm assembly down the river. Skin plate assembly and
horizontal girders slid downstream and impacted on the trunnion
girders. On inspection the following observations were made:
 Webs of both the horizontal girders had twisted.
 End portions of skin plate beyond last vertical stiffeners had bent.
 Side guide rollers were jammed.
 End plates of trunnion hubs had bent.
Provision of spillway stoplogs as also of cat-walk bridge at trunnion
level had not been made.
(2) Contd…
Solution:
1. Provision of tie beams in between the end arms to take
care of side thrust of smaller gates. The Provision
existed for larger size gates.
2. Provision of bearing stiffeners and Drain Holes.
3. Stiffening of top cantilever portion of skin plates.
4. Strengthening of arm sections and their junctions.
(3) Difficulties encountered during
erection of Radial Gates
Gate features:18 nos. 15.00m x 14.565m
spillway radial gates operated by rope drum
hoists.
Fig (3)
(3) Problem and Solution
Problem:
  Distortion of tie flats: Tie flats (190 mm X 63 mm)
were procured in either single or two lengths. The pieces
procured in two lengths were butt welded. Maximum of
25mm kink was noticed close to the butt-welded joints .
4mm distortion was observed in a length of 130 to
300mm forming a maximum angle of deflection of the
order of 4 degrees due to distortion
 Fouling of tie flats with end arms : Arm hub connectors
were fouling with the exposed portions of embedded tie
flats restricting the lift of gate to 10.20m as against
designed lift of 14.565m.
(3) Solution
 The rectification of distorted tie flats was
carried out by welding additional plates of size
150mm x 10mm and 210mm x 8mm at the
location of kinks on the interior side
 In order to analyze stress pattern a finite
element computerized analysis on STAAD-III
was carried out.
 A proposal involving cutting & strengthening
Arm Hub Connector formulated.
(4) Distress of Radial Gate
Gate features:3 nos. 12.00m x 19m spillway
radial gates operated by rope drum hoists.
(4) Problem and Solution
Problem:
Lock nuts of trunnion cover plate were found sheared off. Trunnion
pin had rotated along with the hub/bush probably due to
development of friction /rust between bosh & pin. (Mat. : forged steel
with nickel chromium plating ). Rustoline was then injected, but
without success. Attempts to rotate the pin to make it free from the
hub bushing by jacks (12 capacity) but without success. Observed
that the Grease coming out from only half segment (downstream) of
trunnion.
Solution:
Suggestion was made to inject rustoline and castrol oil ( or any
Suitable lubricating medium ). It is now being envisaged to
rectify/replaced the trunnion assembly parts including pin and bush.
(5) Curtailment of height of radial gates
Gate features:26 nos. 15.00m x 15.24m spillway
radial gates operated by 2x115t hydraulic hoists.
Fig (5)
(5) Problems and Solution
Problem:
The work of design, manufacture and erection of all gates and
hoists, except erection of skin plate & vertical stiffener assemblies,
had been completed when it was ordered to restrict the storage level
to about >10 m head against the gates.
 
Solution:
 Curtailment of top of skin plate in the central portion at reduced
storage level and provision of ‘hood’ for directing wave splashes
away from the gate components.
 Discontinuation of vertical stiffeners in the central portion at top.
(5) Contd...
 Curtailment of primary shield to protect radial end arms at MWL in
the end
portions.
 Curtailment of secondary shield in the end portions to protect
ceramix coated piston rods of hydraulic cylinders.
 To provide electronic water level sensors to ensure raising of the
gate as soon water level reached the storage level.
(6) Failure of Barrage Gates
Gate features:17 nos. 17.678m span vertical
lift Barrage gates operated by rope drum
hoists.
(6) Problems and Solution
Problem:
 Overtopped by flash flood resulting in damages to 12
nos. of barrage gates. For want of provision of stoplogs,
no regular maintenance of gates could be carried out.
 The gate components were found very heavily rusted.
 The faulty fabrication was observed as the full depth
vertical splice joints from top to bottom were provided at
the centre line of the gate. During site inspection, it was
observed that the skin plate at the top of gate had
deflected and the top horizontal girder had apparently
failed in tension
(6) Contd…
Solution:
1. The existing gates were restored by welding and
strengthening.
2. Later on barrage gates were replaced with new ones with
modified sections so as to withstand higher heads due to over
topping.
3. The provision of stoplogs was introduced by cutting stoplogs
grooves along with a provision of new gantry crane.
4. In order to take care of increase in hoist capacity due to the
modifications, RCC counter weights on d/s of gate supported
on cross beams and pulleys attached to gantry girder were
introduced, thus bye-passing the existing hoist bridge..
(7) Refurbishment of barrage gates
Gate features :70 nos. 12.192m x 3.66m Stoney
type crest gates operated by chain hoists with
counter weight.
(7) Problems and Solution
Problem:
The gates erected in sixties and remained largely un-
attended as provision of regular stoplogs was not made.
However, provision of two nos. floating bulkheads was
introduced at a later date
Solution:
1. It was suggested that the existing gate leaves of bow
type girders be replaced by new gates (with plate
girders) with teflon cladded side seals. The provision of
gun metal bushes in roller train assemblies be replaced
by self lubricating bushes.
2. No. of Floating bulkheads be suitably increased.
(8) Overtopping of vertical lift spillway
gates
Gate features:33 nos. 12.83mx6.10m vertical
lift spillway gates operated by chain drum
hoists.
Fig (8)
(8) Problems and Solution
Problem:
Provision of free board over the gates was inadequate
resulting in exposure of top main horizontal girder and struts
to continued wetness and development of undesirable lateral
forces besides rusting and pitting of gate members. The
wave splashing also caused a loss of substantial storage .
Solution:
In order to prevent over topping of gates the following
alternative proposals were examined.
(1) Wave deflectors/Flow splitters
(2) Gate Hood
Provision of Gate Hood was finally suggested so as to direct
the flow away from the immediate downstream gate
components.
(9) Obstruction of bottom horizontal
girder of a wheeled gate with ogee
crest
Gate features: 2nos. 16.00mx7.80m emergency
gates of fixed wheel type operated by rope drum
hoists.
(9) Problems and Solution
Problem:
During erection of emergency gates, the bottom horizontal girder
flange of emergency gate was found to be obstructed by ogee crest
disabling seating of skin plate on the gate sill thus leaving a gap of
270mm between skin plate bottom and sill beam.
Solution:
1. After site inspection, a number of alternatives were considered.
2. Extension of skin plate at bottom by 80 mm along with suitable
stiffening of extended portion of gate bottom.
3. Reduction in depth of horizontal girder, along with provision of an
additional web plate.
4. Removal of bottom girder flanges from current location and
rewelding modified and strengthened bottom girder thus making an
‘l’ shaped girder instead of ‘I’ shaped.
(10) Non-closure of Silt Flushing Tunnel
Gate
Gate features:2nos. 1.50m x 2m high head silt
flushing fixed wheel gates operated by rope
drum hoists.
(10) Problems and Solution
Problem:
When one of the gates (with upstream skin plate & sealing) was
partially operated at high reservoir level, it was noticed that the gate
was not closing. The main cause was identified as impinging of
water jet on the bottom girder, thus creating upthrust on the gate
resulting in non-closure.
Solution:
1. Modification of gate bottom involving cutting of bottom inclined plate
such that the issuing jet was at about 45 degree to the horizontal.
2. Provision of 45 mm wide plate on the upstream side of the gate
causing additional down thrust on the gate thus facilitating gate
closure.
3. Replacement of rubber seals by teflon cladded seals.
(11) Jamming of Spherical Roller of Fixed
Wheel Gates
Gate features:8 nos. 18.00m x 5.35m fixed wheel
type under sluice gates operated by rope drum
hoists.
Fig (11)
(11) Problems and Solution
Problem:
Silt laden water entered into the spherical roller bearings causing
jamming of the bearings of wheels resulting in their sliding instead of
rolling. Bearing was in totally broken condition with dislocation of its
rollers and deposition of silt and clay inside the bearing. Oil seal on
one of the sides was oriented in the reverse manner and that the ‘O’
rings were located on the outside of the counter-head screws
thereby allowing water to enter into the bearings through the threads
of the screws. (See Fig.).
Solution:
Changing the location of O-rings and by fitment of oil seals in correct
orientation. Size of O-ring & no. of screws increased.
(12) Catapulting of Service Gate
Gate features:2nos. 3.30m x 4.20m vertical lift
fixed wheel type intake service hates operated
by 45t hydraulic hoists.
Fig (12)
(12) Problems and Solution
Problem:
The gate had catapulted to a height of 8.60m and lodged itself on the dogging
platform. The hoist stem rod completely buckled and guide shoes sheared.
Operating Criteria provides for balanced raising of gate achieved by crack
opening (Max. 150 mm)
During Balancing by Crack opening, the penstock portion between the gate and
turbine got filled up and the pressure nearly equal to reservoir head started
acting at the bottom side of the gate while the pressure at the top remained
equal to atmospheric pressure. It was also found that the gap between the gate
body and downstream wall was small thus restricting the flow of water through
this gap. The pressure developed at the bottom side of gate was of such a high
magnitude that the gate was catapulted.
On detailed inspection following observations were made:
1. Hoist links twisted
2. Gate Assemblies got twisted, Max. twist being 55mm.
3. Seals bases bent at centre about 4 mm.
4. Left Side guide shoe and lock plate of wheel assembly damaged.
(12) Contd…
Solution:
Rectification and strengthening measures carried
out on Gates. Hoist stem replaced.
Following Model studies recommended to arrive
at exact reason of the failure:
1. Relationship between the crack opening and gap
between the gate body and downstream wall.
2. Typical back of gate opening configuration.
3. Effects such as catapulting height, uplift forces
and pressures on the system during unbalanced
operation.
4. Effect of speed of opening of gate.
(13) Bulging of Gate Shaft Liners of Penstock
Gates
Gate features:2nos. 5.0mx9.0m fixed wheel type
penstock emergency hates operated by 500t
capacity hydraulic hoists.
Fig (13)
(13) Problems and Solution
Problem:
Emergency gate shaft got filled up to about 73 m head probably on
account of flow of water through the hole left un-plugged in the air
vent shaft while the gate was in closed position. Shaft again got
filled about 50m head. After Dewatering, crack of 15mm width at the
interface of 2nd and 3rd stage concrete in the bonnet chamber floor
on the U/s side of bonnet cover. U/s Welded joint of the bonnet
body has opened at a height of 1.30m above the gate upstream
liner had bulged towards downstream to a maximum of 146mm
causing profuse leakage.
(13) Contd…
Solution:
On site inspection, it was suggested that upstream bonnet plate be
replaced and damaged concrete backing (in particular 3rd
stage
concrete of 650 mm thickness) removed and recast after creating
dry conditions. The additional provisions of anchors in u/s body liner
and effective keying by angle stiffeners etc. were made from safety
considerations.
General guidelines:
1. Recheck the design of bonnet plates (with stiffeners in longitudinal
as well as transverse direction) for withstanding full external
pressure with permissible stress at 80 % Y.P.
2. Check adequacy of bonnet body anchorage with concrete with the
assumption that there will be hollows behind the liner in which water
can seep and exert water pressure.
3. Check whether the stiffening ribs are provided with large enough
(13) Contd…
4. Check provision of adequate grout holes in the bonnet plate to
grout any hollows that might be created during concreting
operation or subsequent shrinkage
5. Check provision of adequate dowel bars at suitable intervals
between second & third stage concrete.
6. Check that coarse/fine aggregates proposed to be used are non-
reactive in ASR.
7. Check that the concreting behind the liners is limited to the
maximum of
1.0m in a single lift.
8. The floor of bonnet chamber be made water tight.
(14) Modification of Gate Bottom
Shapes
Gate features:2 nos. 1.829mx3.658m vertical lift
fixed wheel type service and emergency gates
operated by electric hoists
Fig (14)
(14) Problems and Solution
Problem:
The service gates are provided with upstream sealing and skin plate
whereas the emergency gates are having downstream sealing and
skin plates. It was reported that the gates create difficulty in closing
besides vibrations, cavitation problems and profuse leakage past the
gates.
Solution:
Redesign the bottom lip slope of the service gate , an angle of 35
degrees or more with the horizontal between the controlling edge of
the gate and downstream edge of bottom-most girder (See Fig ).
Likewise for emergency gate, the bottom lip shape was proposed to
be modified to provide for flow convergence of to flow passage so as
to achieve positive pressure on gate bottom.
(15) Mal-functioning of Fixed Wheel
Service gate
9nos. 3.050m x 4.575m high head vertical lift fixed
wheel type service gates operated by rope drum
hoists.
(15) Problems and Solution
Problem:
The gates were not self-closing even at low reservoir levels. It was
observed that the stainless steel cladding of rubber seals had
peeled off at certain locations and wheels were not rotating freely
and bulging of stainless steel plate of liner of breast wall had taken
place..
Solution:
1. The seal seats and breast liner plates cladded with 1.25 to 5mm
stainless steel plates be removed fully as it was damaging the seals
and obstructions to movement of gate.
2. Stainless steel cladded seals be replaced with Teflon cladded seals
3. The Bottom Shape of gate be modified by reducing the depth of
girder, while maintaining a lip angle of not less than 32 degrees.
(16) LESSONS LEARNT
1. Corrosion of structural members
2. Lubrication of machinery components should be attended regularly
3. Provision of stoplogs meant for maintenance of main gates.
4. The brass/ bronze/stainless steel cladding has peeled off. Use of
such cladded seals be discontinued and these should be replaced
by teflon cladded seals
5. The sealing arrangement for spherical roller bearing of wheel
assemblies should be designed and maintained with extreme care.
Any slip up can result in jamming of wheels .
6. In case of gates used for balancing of water pressure by crack
opening, care should be taken to ensure that the area of crack
opening is smaller than the area between down stream edge of
the gate and the shaft (slot) normally designed as “ back of gate
orifice” which could otherwise cause catapulting of the gate.
(16) LESSONS LEARNT
7. Overtopping of gates should be suitably
protected. It can lead to vibrations and corrosion
in the gate structure.
8. Special attention should be accorded to the
bottom shapes of the gates. The geometry of
gate bottom may have to be established from
hydraulic model studies particularly for high
heads unless data for similar installation is
available.
9. While planning the fabrication activities of the
gate, the vertical joints should not be located at
the centre of gate, instead these should be
planned at the least possible bending moment
location. Also splice joints should be suitably
staggered.
(16) LESSONS LEARNT
10. The project authorities should formulate suitable
guidelines for inspection, operation and maintenance of all
gates and hoist structures. Suitable training should be
imparted to operating staff. A logbook of operation,
inspection, maintenance and repairs for each gate
structure should be maintained at the project site.
11. The provision of suitably designed dowel bars between
different stages of concrete is essential for safety and
performance of the structure. The surfaces of previous
stages of concrete should be thoroughly roughened and
treated before laying the next stage. Adequate grouting
measures should be provided for concreting behind the
steel liners in order to grout any hollows that might be
created during concreting operation or subsequent
shrinkage.
THANK YOU

More Related Content

What's hot

Various types of gates, their important components
Various types of gates, their important components Various types of gates, their important components
Various types of gates, their important components
EEMayurakshiEMDivisi
 
Dam design
Dam designDam design
Dam design
Mohammed Maina
 
hydro power energy water conveyance system
hydro power energy water conveyance system   hydro power energy water conveyance system
hydro power energy water conveyance system
khabat shekhany
 
Embankment lecture 2
Embankment lecture 2Embankment lecture 2
Embankment lecture 2
Vidhi Khokhani
 
91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...
91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...
91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...
Rama Krishna Varanasi
 
Snubbing BOP, Snubbing Bop Stack - Worldwide Oilfield Machine
Snubbing BOP, Snubbing Bop Stack - Worldwide Oilfield MachineSnubbing BOP, Snubbing Bop Stack - Worldwide Oilfield Machine
Snubbing BOP, Snubbing Bop Stack - Worldwide Oilfield Machine
womgroup
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
Mohamed Gaafar
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe ppt
zafaralam7868
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
SAGAR RAUT
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
ahsanrabbani
 
Spillway and gates
Spillway and gatesSpillway and gates
Spillway and gates
holegajendra
 
4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf
DEVNAIK7
 
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
India Water Portal
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_projectSouhail Zraoura
 
Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.
Raj Bisen
 
design of weirs
design of weirsdesign of weirs
design of weirs
SANJEEV Wazir
 
Embankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadEmbankment dam civil 5 th sem upload
Embankment dam civil 5 th sem upload
Meet Soni
 
REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...
REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...
REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...
Yimmy Joel Ibarra Vera
 
Dam outlet works lecture 1
Dam outlet works lecture 1Dam outlet works lecture 1
Dam outlet works lecture 1
Vidhi Khokhani
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailraceRakesh Sunari Magar
 

What's hot (20)

Various types of gates, their important components
Various types of gates, their important components Various types of gates, their important components
Various types of gates, their important components
 
Dam design
Dam designDam design
Dam design
 
hydro power energy water conveyance system
hydro power energy water conveyance system   hydro power energy water conveyance system
hydro power energy water conveyance system
 
Embankment lecture 2
Embankment lecture 2Embankment lecture 2
Embankment lecture 2
 
91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...
91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...
91160763 design-of-hydraulic-structures-be-civil-books-bis-codes-and-useful-l...
 
Snubbing BOP, Snubbing Bop Stack - Worldwide Oilfield Machine
Snubbing BOP, Snubbing Bop Stack - Worldwide Oilfield MachineSnubbing BOP, Snubbing Bop Stack - Worldwide Oilfield Machine
Snubbing BOP, Snubbing Bop Stack - Worldwide Oilfield Machine
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe ppt
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Spillway and gates
Spillway and gatesSpillway and gates
Spillway and gates
 
4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf
 
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project
 
Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
Embankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadEmbankment dam civil 5 th sem upload
Embankment dam civil 5 th sem upload
 
REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...
REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...
REPARACION DE PILOTES HINCADOS EN EL MAR, UTILIZANDO ADITIVOS PARA PROLONGAR ...
 
Dam outlet works lecture 1
Dam outlet works lecture 1Dam outlet works lecture 1
Dam outlet works lecture 1
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 

Similar to General deficiencies found during inspection of gates and remedy with case studies

IRJET- The Rehabilitation Techniques for Irwin Bridge
IRJET-  	  The Rehabilitation Techniques for Irwin BridgeIRJET-  	  The Rehabilitation Techniques for Irwin Bridge
IRJET- The Rehabilitation Techniques for Irwin Bridge
IRJET Journal
 
Emeca SPE-USA Pile Joint Product
Emeca SPE-USA Pile Joint ProductEmeca SPE-USA Pile Joint Product
Emeca SPE-USA Pile Joint Product
pdewit
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
Mahesh Sontyal
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
David H Moloney
 
A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...
nasina balasubrahmayam
 
Final Presentation
Final PresentationFinal Presentation
Final PresentationMonique F M
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
Safdar Ali
 
Presentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergencyPresentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergency
Super Arc Consultant
 
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOADBriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOADmichael mabrouk
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster PresentationPaul Trofimov
 
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Rais Uddin
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
GPT Stvd
 
Debonding techniques and enamel fracture patterns /certified fixed orthodonti...
Debonding techniques and enamel fracture patterns /certified fixed orthodonti...Debonding techniques and enamel fracture patterns /certified fixed orthodonti...
Debonding techniques and enamel fracture patterns /certified fixed orthodonti...
Indian dental academy
 
EC3 design
EC3 designEC3 design
EC3 design
Maria João Espada
 
Uni rail system presentation
Uni rail system presentationUni rail system presentation
Uni rail system presentation
TRABALHO VERTICAL
 
Prefabricated panels
Prefabricated panelsPrefabricated panels
Prefabricated panels
Moldtech SL
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case studyMD.Suresh Kumar
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 

Similar to General deficiencies found during inspection of gates and remedy with case studies (20)

IRJET- The Rehabilitation Techniques for Irwin Bridge
IRJET-  	  The Rehabilitation Techniques for Irwin BridgeIRJET-  	  The Rehabilitation Techniques for Irwin Bridge
IRJET- The Rehabilitation Techniques for Irwin Bridge
 
Ship failure
Ship failureShip failure
Ship failure
 
Emeca SPE-USA Pile Joint Product
Emeca SPE-USA Pile Joint ProductEmeca SPE-USA Pile Joint Product
Emeca SPE-USA Pile Joint Product
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 
A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
Presentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergencyPresentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergency
 
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOADBriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster Presentation
 
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
Debonding techniques and enamel fracture patterns /certified fixed orthodonti...
Debonding techniques and enamel fracture patterns /certified fixed orthodonti...Debonding techniques and enamel fracture patterns /certified fixed orthodonti...
Debonding techniques and enamel fracture patterns /certified fixed orthodonti...
 
EC3 design
EC3 designEC3 design
EC3 design
 
Uni rail system presentation
Uni rail system presentationUni rail system presentation
Uni rail system presentation
 
Prefabricated panels
Prefabricated panelsPrefabricated panels
Prefabricated panels
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case study
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 

More from IEI GSC

DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...
DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...
DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...
IEI GSC
 
Flexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beamsFlexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beams
IEI GSC
 
MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...
MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...
MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...
IEI GSC
 
COMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONS
COMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONSCOMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONS
COMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONS
IEI GSC
 
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
IEI GSC
 
ENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRC
ENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRCENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRC
ENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRC
IEI GSC
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
IEI GSC
 
Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...
IEI GSC
 
Precast infastructure
Precast infastructurePrecast infastructure
Precast infastructure
IEI GSC
 
Advances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forwardAdvances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forward
IEI GSC
 
Effect of Waste Foundry Sand on Durability Properties of Concrete
Effect of Waste Foundry Sand on Durability Properties of ConcreteEffect of Waste Foundry Sand on Durability Properties of Concrete
Effect of Waste Foundry Sand on Durability Properties of Concrete
IEI GSC
 
Flexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beamsFlexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beams
IEI GSC
 
Future of civil engineering
Future of civil engineering Future of civil engineering
Future of civil engineering
IEI GSC
 
Dr. Jaikrishna Memorial Lecture on Evolution of Bridges
Dr. Jaikrishna Memorial Lecture on Evolution of BridgesDr. Jaikrishna Memorial Lecture on Evolution of Bridges
Dr. Jaikrishna Memorial Lecture on Evolution of Bridges
IEI GSC
 
Structural Safety in India
Structural Safety in India Structural Safety in India
Structural Safety in India
IEI GSC
 
GEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGION
GEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGIONGEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGION
GEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGION
IEI GSC
 
Use of GeoTextiles in Civil Engineering : Work on NH 150, Manipur
Use of GeoTextiles in Civil Engineering : Work on NH 150, ManipurUse of GeoTextiles in Civil Engineering : Work on NH 150, Manipur
Use of GeoTextiles in Civil Engineering : Work on NH 150, Manipur
IEI GSC
 
Textiles & GeoTextile Composites
Textiles & GeoTextile CompositesTextiles & GeoTextile Composites
Textiles & GeoTextile Composites
IEI GSC
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
IEI GSC
 
Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...
Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...
Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...
IEI GSC
 

More from IEI GSC (20)

DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...
DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...
DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJAR...
 
Flexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beamsFlexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beams
 
MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...
MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...
MIXTURE DESIGN OF FLY ASH & SLAG BASED ALKALI ACTIVATED CONCRETE FOR PRECAST ...
 
COMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONS
COMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONSCOMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONS
COMPARATIVE STUDY OF OUTRIGGER STRUCTURE WITH DIFFERENT CONFIGURATIONS
 
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
 
ENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRC
ENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRCENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRC
ENHANCEMENT OF SEISMIC PERFORMANCE OF STRUCTURES USING HyFRC
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
 
Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...
 
Precast infastructure
Precast infastructurePrecast infastructure
Precast infastructure
 
Advances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forwardAdvances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forward
 
Effect of Waste Foundry Sand on Durability Properties of Concrete
Effect of Waste Foundry Sand on Durability Properties of ConcreteEffect of Waste Foundry Sand on Durability Properties of Concrete
Effect of Waste Foundry Sand on Durability Properties of Concrete
 
Flexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beamsFlexure Behaviour of Ferrocement Strengthened RC beams
Flexure Behaviour of Ferrocement Strengthened RC beams
 
Future of civil engineering
Future of civil engineering Future of civil engineering
Future of civil engineering
 
Dr. Jaikrishna Memorial Lecture on Evolution of Bridges
Dr. Jaikrishna Memorial Lecture on Evolution of BridgesDr. Jaikrishna Memorial Lecture on Evolution of Bridges
Dr. Jaikrishna Memorial Lecture on Evolution of Bridges
 
Structural Safety in India
Structural Safety in India Structural Safety in India
Structural Safety in India
 
GEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGION
GEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGIONGEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGION
GEO TEXTILES FOR DEVELOPMENT OF NORTH EASTERN REGION
 
Use of GeoTextiles in Civil Engineering : Work on NH 150, Manipur
Use of GeoTextiles in Civil Engineering : Work on NH 150, ManipurUse of GeoTextiles in Civil Engineering : Work on NH 150, Manipur
Use of GeoTextiles in Civil Engineering : Work on NH 150, Manipur
 
Textiles & GeoTextile Composites
Textiles & GeoTextile CompositesTextiles & GeoTextile Composites
Textiles & GeoTextile Composites
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...
Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...
Presentation: Comparative Evaluation Of Epoxy Treated Reinforcement And Ename...
 

Recently uploaded

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 

General deficiencies found during inspection of gates and remedy with case studies

  • 1. GENERAL DEFICIENCIES FOUND DURING INSPECTION AND REMEDY WITH CASE STUDIES
  • 2. Introduction Incidents of distress can be attributed to the deficiency of planning, structural design, hydraulic design, fabrication, erection, operation and maintenance. Vibration, cavitations, non-closure, corrosion, erosion and aging problems, improper selection of materials and neglect of lubrication of components have resulted in mal-functioning and even failures of gates in the past.
  • 3.
  • 5. (1) Problem and Solution Problem: Washing away of the gate took place due to detachment of left side trunnion girder On inspection of all gates, the following deficiencies of gate structures were observed: 1. Inadequate welding between trunnion girders and tie flats. In fact the flats were welded only at flanges of trunnion girders. 2. Existence of substantial gaps of varying degree between tie flats and webs of trunnion girders. 3. Eccentricity due to incorrect alignment of trunnion girders 4. Apprehensions about inadequacy, welding the insulated tie flats with anchor girders
  • 6. (1) Contd… Solution: 1. An improvised scheme adopted to connect the webs of the trunnion girders and tie flats by way of welding additional plates all along the web of the trunnion girder on either side of each tie flat. (See Fig.) 2. In order to tackle eccentric transfer of load from trunnion bracket to trunnion girder, additional plates of triangular shape were welded on the flange plate of trunnion girder .
  • 7. (1) Contd… Solution: 3. In view of suspected deficiency of tie flat- anchor girder junction, one tie flat near upstream flange of anchor girder was exposed and it was revealed that the tie flats were welded only to flanges and not to the webs of the anchor girder. 4. The tie flats were welded only to flanges and not to the webs of the anchor girder. Drive pins to connect the tie flats and anchor girders and weld the pins to lock (See Fig). The blockouts were then filled by epoxy mortar and epoxy grout.
  • 8. (2) Failure of Radial Gate Leaf Gate Features: 23nos. 12.941m x 9.85m and 2 nos. 4.877 x 9.85m spillway radial gates operated by rope drum hoists.
  • 9. (2) Problem and Solution Problem: One of the end gates of smaller span failed while in closed position at the the top right arm and horizontal girder. Failure of the corresponding joint between bottom arm and horizontal girder and also between the arm and trunnion hub, resulted in wrenching away the arm assembly down the river. Skin plate assembly and horizontal girders slid downstream and impacted on the trunnion girders. On inspection the following observations were made:  Webs of both the horizontal girders had twisted.  End portions of skin plate beyond last vertical stiffeners had bent.  Side guide rollers were jammed.  End plates of trunnion hubs had bent. Provision of spillway stoplogs as also of cat-walk bridge at trunnion level had not been made.
  • 10. (2) Contd… Solution: 1. Provision of tie beams in between the end arms to take care of side thrust of smaller gates. The Provision existed for larger size gates. 2. Provision of bearing stiffeners and Drain Holes. 3. Stiffening of top cantilever portion of skin plates. 4. Strengthening of arm sections and their junctions.
  • 11. (3) Difficulties encountered during erection of Radial Gates Gate features:18 nos. 15.00m x 14.565m spillway radial gates operated by rope drum hoists.
  • 13. (3) Problem and Solution Problem:   Distortion of tie flats: Tie flats (190 mm X 63 mm) were procured in either single or two lengths. The pieces procured in two lengths were butt welded. Maximum of 25mm kink was noticed close to the butt-welded joints . 4mm distortion was observed in a length of 130 to 300mm forming a maximum angle of deflection of the order of 4 degrees due to distortion  Fouling of tie flats with end arms : Arm hub connectors were fouling with the exposed portions of embedded tie flats restricting the lift of gate to 10.20m as against designed lift of 14.565m.
  • 14. (3) Solution  The rectification of distorted tie flats was carried out by welding additional plates of size 150mm x 10mm and 210mm x 8mm at the location of kinks on the interior side  In order to analyze stress pattern a finite element computerized analysis on STAAD-III was carried out.  A proposal involving cutting & strengthening Arm Hub Connector formulated.
  • 15. (4) Distress of Radial Gate Gate features:3 nos. 12.00m x 19m spillway radial gates operated by rope drum hoists.
  • 16. (4) Problem and Solution Problem: Lock nuts of trunnion cover plate were found sheared off. Trunnion pin had rotated along with the hub/bush probably due to development of friction /rust between bosh & pin. (Mat. : forged steel with nickel chromium plating ). Rustoline was then injected, but without success. Attempts to rotate the pin to make it free from the hub bushing by jacks (12 capacity) but without success. Observed that the Grease coming out from only half segment (downstream) of trunnion. Solution: Suggestion was made to inject rustoline and castrol oil ( or any Suitable lubricating medium ). It is now being envisaged to rectify/replaced the trunnion assembly parts including pin and bush.
  • 17. (5) Curtailment of height of radial gates Gate features:26 nos. 15.00m x 15.24m spillway radial gates operated by 2x115t hydraulic hoists.
  • 19. (5) Problems and Solution Problem: The work of design, manufacture and erection of all gates and hoists, except erection of skin plate & vertical stiffener assemblies, had been completed when it was ordered to restrict the storage level to about >10 m head against the gates.   Solution:  Curtailment of top of skin plate in the central portion at reduced storage level and provision of ‘hood’ for directing wave splashes away from the gate components.  Discontinuation of vertical stiffeners in the central portion at top.
  • 20. (5) Contd...  Curtailment of primary shield to protect radial end arms at MWL in the end portions.  Curtailment of secondary shield in the end portions to protect ceramix coated piston rods of hydraulic cylinders.  To provide electronic water level sensors to ensure raising of the gate as soon water level reached the storage level.
  • 21. (6) Failure of Barrage Gates Gate features:17 nos. 17.678m span vertical lift Barrage gates operated by rope drum hoists.
  • 22. (6) Problems and Solution Problem:  Overtopped by flash flood resulting in damages to 12 nos. of barrage gates. For want of provision of stoplogs, no regular maintenance of gates could be carried out.  The gate components were found very heavily rusted.  The faulty fabrication was observed as the full depth vertical splice joints from top to bottom were provided at the centre line of the gate. During site inspection, it was observed that the skin plate at the top of gate had deflected and the top horizontal girder had apparently failed in tension
  • 23. (6) Contd… Solution: 1. The existing gates were restored by welding and strengthening. 2. Later on barrage gates were replaced with new ones with modified sections so as to withstand higher heads due to over topping. 3. The provision of stoplogs was introduced by cutting stoplogs grooves along with a provision of new gantry crane. 4. In order to take care of increase in hoist capacity due to the modifications, RCC counter weights on d/s of gate supported on cross beams and pulleys attached to gantry girder were introduced, thus bye-passing the existing hoist bridge..
  • 24. (7) Refurbishment of barrage gates Gate features :70 nos. 12.192m x 3.66m Stoney type crest gates operated by chain hoists with counter weight.
  • 25. (7) Problems and Solution Problem: The gates erected in sixties and remained largely un- attended as provision of regular stoplogs was not made. However, provision of two nos. floating bulkheads was introduced at a later date Solution: 1. It was suggested that the existing gate leaves of bow type girders be replaced by new gates (with plate girders) with teflon cladded side seals. The provision of gun metal bushes in roller train assemblies be replaced by self lubricating bushes. 2. No. of Floating bulkheads be suitably increased.
  • 26. (8) Overtopping of vertical lift spillway gates Gate features:33 nos. 12.83mx6.10m vertical lift spillway gates operated by chain drum hoists.
  • 28. (8) Problems and Solution Problem: Provision of free board over the gates was inadequate resulting in exposure of top main horizontal girder and struts to continued wetness and development of undesirable lateral forces besides rusting and pitting of gate members. The wave splashing also caused a loss of substantial storage . Solution: In order to prevent over topping of gates the following alternative proposals were examined. (1) Wave deflectors/Flow splitters (2) Gate Hood Provision of Gate Hood was finally suggested so as to direct the flow away from the immediate downstream gate components.
  • 29. (9) Obstruction of bottom horizontal girder of a wheeled gate with ogee crest Gate features: 2nos. 16.00mx7.80m emergency gates of fixed wheel type operated by rope drum hoists.
  • 30. (9) Problems and Solution Problem: During erection of emergency gates, the bottom horizontal girder flange of emergency gate was found to be obstructed by ogee crest disabling seating of skin plate on the gate sill thus leaving a gap of 270mm between skin plate bottom and sill beam. Solution: 1. After site inspection, a number of alternatives were considered. 2. Extension of skin plate at bottom by 80 mm along with suitable stiffening of extended portion of gate bottom. 3. Reduction in depth of horizontal girder, along with provision of an additional web plate. 4. Removal of bottom girder flanges from current location and rewelding modified and strengthened bottom girder thus making an ‘l’ shaped girder instead of ‘I’ shaped.
  • 31. (10) Non-closure of Silt Flushing Tunnel Gate Gate features:2nos. 1.50m x 2m high head silt flushing fixed wheel gates operated by rope drum hoists.
  • 32. (10) Problems and Solution Problem: When one of the gates (with upstream skin plate & sealing) was partially operated at high reservoir level, it was noticed that the gate was not closing. The main cause was identified as impinging of water jet on the bottom girder, thus creating upthrust on the gate resulting in non-closure. Solution: 1. Modification of gate bottom involving cutting of bottom inclined plate such that the issuing jet was at about 45 degree to the horizontal. 2. Provision of 45 mm wide plate on the upstream side of the gate causing additional down thrust on the gate thus facilitating gate closure. 3. Replacement of rubber seals by teflon cladded seals.
  • 33. (11) Jamming of Spherical Roller of Fixed Wheel Gates Gate features:8 nos. 18.00m x 5.35m fixed wheel type under sluice gates operated by rope drum hoists.
  • 35. (11) Problems and Solution Problem: Silt laden water entered into the spherical roller bearings causing jamming of the bearings of wheels resulting in their sliding instead of rolling. Bearing was in totally broken condition with dislocation of its rollers and deposition of silt and clay inside the bearing. Oil seal on one of the sides was oriented in the reverse manner and that the ‘O’ rings were located on the outside of the counter-head screws thereby allowing water to enter into the bearings through the threads of the screws. (See Fig.). Solution: Changing the location of O-rings and by fitment of oil seals in correct orientation. Size of O-ring & no. of screws increased.
  • 36. (12) Catapulting of Service Gate Gate features:2nos. 3.30m x 4.20m vertical lift fixed wheel type intake service hates operated by 45t hydraulic hoists.
  • 38. (12) Problems and Solution Problem: The gate had catapulted to a height of 8.60m and lodged itself on the dogging platform. The hoist stem rod completely buckled and guide shoes sheared. Operating Criteria provides for balanced raising of gate achieved by crack opening (Max. 150 mm) During Balancing by Crack opening, the penstock portion between the gate and turbine got filled up and the pressure nearly equal to reservoir head started acting at the bottom side of the gate while the pressure at the top remained equal to atmospheric pressure. It was also found that the gap between the gate body and downstream wall was small thus restricting the flow of water through this gap. The pressure developed at the bottom side of gate was of such a high magnitude that the gate was catapulted. On detailed inspection following observations were made: 1. Hoist links twisted 2. Gate Assemblies got twisted, Max. twist being 55mm. 3. Seals bases bent at centre about 4 mm. 4. Left Side guide shoe and lock plate of wheel assembly damaged.
  • 39. (12) Contd… Solution: Rectification and strengthening measures carried out on Gates. Hoist stem replaced. Following Model studies recommended to arrive at exact reason of the failure: 1. Relationship between the crack opening and gap between the gate body and downstream wall. 2. Typical back of gate opening configuration. 3. Effects such as catapulting height, uplift forces and pressures on the system during unbalanced operation. 4. Effect of speed of opening of gate.
  • 40. (13) Bulging of Gate Shaft Liners of Penstock Gates Gate features:2nos. 5.0mx9.0m fixed wheel type penstock emergency hates operated by 500t capacity hydraulic hoists.
  • 42. (13) Problems and Solution Problem: Emergency gate shaft got filled up to about 73 m head probably on account of flow of water through the hole left un-plugged in the air vent shaft while the gate was in closed position. Shaft again got filled about 50m head. After Dewatering, crack of 15mm width at the interface of 2nd and 3rd stage concrete in the bonnet chamber floor on the U/s side of bonnet cover. U/s Welded joint of the bonnet body has opened at a height of 1.30m above the gate upstream liner had bulged towards downstream to a maximum of 146mm causing profuse leakage.
  • 43. (13) Contd… Solution: On site inspection, it was suggested that upstream bonnet plate be replaced and damaged concrete backing (in particular 3rd stage concrete of 650 mm thickness) removed and recast after creating dry conditions. The additional provisions of anchors in u/s body liner and effective keying by angle stiffeners etc. were made from safety considerations. General guidelines: 1. Recheck the design of bonnet plates (with stiffeners in longitudinal as well as transverse direction) for withstanding full external pressure with permissible stress at 80 % Y.P. 2. Check adequacy of bonnet body anchorage with concrete with the assumption that there will be hollows behind the liner in which water can seep and exert water pressure. 3. Check whether the stiffening ribs are provided with large enough
  • 44. (13) Contd… 4. Check provision of adequate grout holes in the bonnet plate to grout any hollows that might be created during concreting operation or subsequent shrinkage 5. Check provision of adequate dowel bars at suitable intervals between second & third stage concrete. 6. Check that coarse/fine aggregates proposed to be used are non- reactive in ASR. 7. Check that the concreting behind the liners is limited to the maximum of 1.0m in a single lift. 8. The floor of bonnet chamber be made water tight.
  • 45. (14) Modification of Gate Bottom Shapes Gate features:2 nos. 1.829mx3.658m vertical lift fixed wheel type service and emergency gates operated by electric hoists
  • 47. (14) Problems and Solution Problem: The service gates are provided with upstream sealing and skin plate whereas the emergency gates are having downstream sealing and skin plates. It was reported that the gates create difficulty in closing besides vibrations, cavitation problems and profuse leakage past the gates. Solution: Redesign the bottom lip slope of the service gate , an angle of 35 degrees or more with the horizontal between the controlling edge of the gate and downstream edge of bottom-most girder (See Fig ). Likewise for emergency gate, the bottom lip shape was proposed to be modified to provide for flow convergence of to flow passage so as to achieve positive pressure on gate bottom.
  • 48. (15) Mal-functioning of Fixed Wheel Service gate 9nos. 3.050m x 4.575m high head vertical lift fixed wheel type service gates operated by rope drum hoists.
  • 49. (15) Problems and Solution Problem: The gates were not self-closing even at low reservoir levels. It was observed that the stainless steel cladding of rubber seals had peeled off at certain locations and wheels were not rotating freely and bulging of stainless steel plate of liner of breast wall had taken place.. Solution: 1. The seal seats and breast liner plates cladded with 1.25 to 5mm stainless steel plates be removed fully as it was damaging the seals and obstructions to movement of gate. 2. Stainless steel cladded seals be replaced with Teflon cladded seals 3. The Bottom Shape of gate be modified by reducing the depth of girder, while maintaining a lip angle of not less than 32 degrees.
  • 50. (16) LESSONS LEARNT 1. Corrosion of structural members 2. Lubrication of machinery components should be attended regularly 3. Provision of stoplogs meant for maintenance of main gates. 4. The brass/ bronze/stainless steel cladding has peeled off. Use of such cladded seals be discontinued and these should be replaced by teflon cladded seals 5. The sealing arrangement for spherical roller bearing of wheel assemblies should be designed and maintained with extreme care. Any slip up can result in jamming of wheels . 6. In case of gates used for balancing of water pressure by crack opening, care should be taken to ensure that the area of crack opening is smaller than the area between down stream edge of the gate and the shaft (slot) normally designed as “ back of gate orifice” which could otherwise cause catapulting of the gate.
  • 51. (16) LESSONS LEARNT 7. Overtopping of gates should be suitably protected. It can lead to vibrations and corrosion in the gate structure. 8. Special attention should be accorded to the bottom shapes of the gates. The geometry of gate bottom may have to be established from hydraulic model studies particularly for high heads unless data for similar installation is available. 9. While planning the fabrication activities of the gate, the vertical joints should not be located at the centre of gate, instead these should be planned at the least possible bending moment location. Also splice joints should be suitably staggered.
  • 52. (16) LESSONS LEARNT 10. The project authorities should formulate suitable guidelines for inspection, operation and maintenance of all gates and hoist structures. Suitable training should be imparted to operating staff. A logbook of operation, inspection, maintenance and repairs for each gate structure should be maintained at the project site. 11. The provision of suitably designed dowel bars between different stages of concrete is essential for safety and performance of the structure. The surfaces of previous stages of concrete should be thoroughly roughened and treated before laying the next stage. Adequate grouting measures should be provided for concreting behind the steel liners in order to grout any hollows that might be created during concreting operation or subsequent shrinkage.