NASA PM CHALLENGE 2009
JPL DESIGN AND FLIGHT PROJECT
          PRACTICES


           February 24, 2009


             Thomas R. Gavin
              Associate Director
     Flight Projects and Mission Success
NASA/JPL Project Lifecycle
JPL Flight Program/Mission Implementation
                                                   FORMULATION                       APPROVAL                                            IMPLEMENTATION
     Lifecycle
                           Pre-Phase A:        Phase A:               Phase B:                          Phase C:                   Phase D:                Phase E:                   Phase F:
     Phases                  Concept          Concept &          Preliminary Design                  Final Design &           System Assembly,            Operations &                Closeout
                             Studies         Technology            & Technology                        Fabrication            Integration & Test,         Sustainment
                                             Development             Completion                                                     Launch
              NASA
                                       KDP A               KDP B                         KDP C                       KDP D                      KDP E                         KDP F
              Decision
   ASSIGNED
   MISSIONS




              Points

              NASA
              Project
              Reviews                MCR1           SRR2 MDR1,2                         PDR1            CDR1         SIR1,3            ORR     FRR1 PLAR         CERR1,4                    DR

              NASA
                                    Down Select          Project Selection               KDP C                       KDP D                      KDP E                         KDP F
              Decision
              Points
  AO-DRIVEN
  MISSIONS




              NASA
              Project
              Reviews
                                                                                        PDR1            CDR1         SIR1,3            ORR    FRR1 PLAR         CERR1,4                     DR
                                   Step 1              Step 2
              JPL
              Project
                         Proposal Reviews      PIR Proposal Reviews PMSR1
              Reviews

                                                                                                                                                      MRB
    Other Reviews                                                                                                                                                                          Final
    and Events                                                                                                                    SMSR,                                   5           Archival of
                                                                                                                                                      Launch      EOPM
                                                                                                                                 LV LRR, LV FRR                                             Data

                 (1) Review is followed by a JPL CMC. If the review immediately precedes a KDP, a Mission Directorate and/or Agency PMC/GPMC, as appropriate, are required prior to the KDP.
  Notes          (2) The SRR and MDR may be combined
                 (3) SIR is a “soft gate”, project may initiate Phase D work immediately upon completion of Phase C work products, absent a notice of discontinuance from the Program Manager
                 (4) CERRs are established at the discretion of Program Offices.
                 (5) At the end of the prime mission, if an extended mission is approved, the extended mission is still in Phase E.
                 CDR – Critical Design Review                         LV FRR – Launch Vehicle Flight Readiness Review            PLAR – Post Launch Assessment Review
  Legend         CERR – Critical Events Readiness Review              LV LRR – Launch Vehicle Launch Readiness Review            PMC – Program Management Council
                 CMC – Center Management Council                      MCR – Mission Concept Review                               PMSR – Project Mission System Review
                 DR – Decommissioning Review                          MDR – Mission Definition Review                            SIR – System Integration Review
                 EOPM – End of Prime Mission                          MRB – Mission Readiness Briefing                           SMSR – Safety and Mission Success Review
                 FRR – Flight Readiness Review                        ORR – Operations Readiness Review                          SRR – System Requirements Review
                 GPMC – Governing Program Management Council          PDR – Preliminary Design Review
                 KDP – Key Decision Point                             PIR – Proposal Implementation Review                                                                              05.01.2007




                                                                                                                                                                                                     2
Design Principles:

                                      •   Applies to all flight designs, whether implemented in-house
                                          or at a contractor
                                      •   Specifies essential attributes of JPL flight designs
                                      •   Projects meet requirements, or get approval for
                                          deviation/exception
                                      •   Captures 40+ years of lessons learned
                                      •   Establishes robust design margins for high reliability
                                      •   Defines ample margins for management of development
                                          risk
                                      •   Requires a conservative approach to use of flight assets
                                      •   Prescribes a comprehensive approach to flight system V&V
                                      •   Compliance assessment is via the DP Compliance Matrix
                                      •   Deviations/Exceptions process engages management in
                                          discussion of risks being accepted
                                      •   Requires development of an Incompressible Test List and a
                                          Test as You Fly Exception List



       (Rules! DocID 43913)

                              Managing Projects at JPL                                      3
Design Principles: Content
Note: Sections 1 and 2 are Applicability and Introduction



   Section 3           Section 4             Section 5                                  Section 7             Section 8           Section 9
                                                                   Section 6                                                    Flight System
   Mission              Flight                Deleted                                    Flight             Flight System
                                                                   Managed                                                       Flight Ops
    Design              System               (was SW)                                   Scenario                V&V
                                                                   Margins                                                         Design
                        Design                                                           Design                Design




       4.1 General                                                                              8.1 General
       4.2 Mechanical Configuration/Systems           6.1 Deleted                               8.1.1 Min Op Times for Electronics
       4.3 Power/Pyrotechnics                         6.2 Mission Design Resource Margins       8.1.2 Handling & Test Constraints
       4.4 Information System                         6.2.1 Propellant                          8.2 Pre-delivery Verification
       4.5 Telecommunications System                  6.3 Flight System Technical               8.2.1 Subsystem and Assembly Level
       4.6 Guidance, Navigation & Control             Resource Margins                          8.2.2 Early Interface Testing
       4.7 Propulsion System                          6.3.1 General                             8.2.3 System Level
       4.8 System Thermal                             6.3.2 System Mass                         8.3 System Assembly, Integration & Test
       4.9 System Fault Protection                    6.3.3 System Power/Energy                 8.3.1 System Assembly
       4.10 System EMC/EMI                            6.3.4 Deleted                             8.3.2 System Integration
       4.11 Flight Software System                    6.3.5 Flight Software Margins             8.3.3 System Functional Verification
       4.12 Flight Electronics Hardware               6.3.6 Power/Pyro System Margins           8.3.4 Flight Sequence Verification
       System                                         6.3.7 Telecom System Margins              8.3.5 System Fault Protection
                                                      6.3.8 Flight Electronics H/W Margins      Verification
                                                      6.3.9 S/C Mechanisms Func Margins         8.3.6 System Stress Testing
                                                      6.3.10 Energy Margins for Cryo Sys        8.3.7 System Environmental Verification
                                                                                                8.3.8 Inter-system Verification
                                                                                                8.4 Launch Operations
                                                                                                8.4.1 Pre-mate Verification
                                                                                                8.4.2 Post-mate Verification
                                                                                                8.4.3 Launch-critical Support Equipment



                                                      Managing Projects at JPL                                                       4
Margin Management: Technical Margin


               Mass
                                                                                            2%
              Margin           30%            20%            10%             5%
               (%)                                                                        (Note 1)

               Power
              Margin
                (%)            30%            20%            15%             10%            10%
              (Note 2)
                                              Project
                               PMSR                                         ATLO
               Project                         PDR           Project                       Launch
                              (A-to-B                                      Readiness
              Milestone                     (B-to-C/D         CDR
                             Transition)                                    Review
                                            Transition)

Definitions:
Mass Margin = {(LV Allocation - CBE)/LV Allocation} x 100%
Power Margin = {(Available Power - CBE)/Available Power} x 100%
Notes:
1. Project Manager can specify other positive values, including zero
2. Power margins apply to mission critical and mission enabling modes, e.g., cruise, safing, etc.




                                       Managing Projects at JPL                                      5
Margin Management: Schedule Margins



           Schedule
                                                                                1 week/month
            Margin               1 month/year           2 months/year
                                                                              (2.8 months/year)
             Rate



            Flight                                   ATLO Start to
                             Implementation Start
           Missions/                              Ship to Launch Site/           Delivery to
                                to Delivery to
            Flight                                  Instrument I&T               Launch Site
                                    ATLO/
          Experiment                               Start to Delivery              to Launch
                               Instrument I&T
           Projects                                    To ATLO


Definitions:
Total Schedule = Planned Activities + Schedule Margin
Schedule Margin = No Planned Activities, but Funded Schedule
Schedule Margin Rate = Schedule Margin/(Planned Activity + Schedule Margin)



                                   Managing Projects at JPL                                    6
Margin Management: Budget Reserves


    Budget
   Reserves          30%             30%             25%             20%              20%         10%
     (%)



    Flight        Proposals—     Proposals-          Project/                         Start      Ship to
   Missions/       Step-1 &/or   Step-2 &/or       Instrument        Project/           of       Launch
    Flight       Instrument AO Instrument AO          PDR          Instrument        ATLO/        Site/
  Experiment      (Pre-A-to-A      (A-to-B         (B-to-C/D          CDR          Instrument   Deliver to
   Projects        Transition)   Transition)       Transition)                        I&T        ATLO


 Definitions:
 Budget Reserve = {Unencumbered Budget Reserve/Estimated Cost to Go} x 100%
 Total Budget = Estimated Cost to Go + Unencumbered Budget Reserve
 Notes:
 1. Cost to Go includes the funded schedule margin, but excludes the launch vehicle costs




                                    Managing Projects at JPL                                      7
Cost Risk Subfactors
                 COST RISK SUBFACTORS                                                      COST RISK SUBFACTORS
MISSION COMPLEXITY                                                       SYSTEM ARCHITECTURE
 1. Mission with multiple flight elements (P)                             1. New system architecture (P)

  2. Mission with multiple objectives                                     2. System architecture applied to new environment and technology
  3. Precision lander mission                                             3. Level 1 Requirements not well defined in formulation phase (P)
  4. Operation in harsh environments (P)                                  4. System with many ACS modes
SIGNIFICANT TECHNICAL DEVELOPMENT                                         5. System with many deployments
  1. Mission enabling spacecraft technology with TRL<5 (P)                6. Excessive reliability requirements (P)
  2. Mission critical instrument technology with TRL<5                    7.Pointing control stability requirements beyond state of art
  3. Lack of fallback option for mission critical technology             CONTRACTOR CAPABILITIES MATCH
  4. Multiple interfaces affected by mission critical technology          1. Contractor inexperienced in mission application (P)
NEW SOFTWARE OR UNVALIDATED SOFTWARE                                      2. Foreign Partner delivering hardware that is mission critical or on
INHERITANCE                                                               critical path
  1. New software architecture                                            3. Not enough experienced personnel available.
  2. New fault protection                                                PROGRAMMATIC /COST &SCHEDULE MARGIN
  3. New software team                                                    1. Less then 12-month Phase A/B
  4. Undocumented software inheritance without the same
  development team                                                         2. Less than 30-month Phase C/D
TECHNICAL MARGINS                                                          3. Schedule margins below guidelines (P)
  1. New design with multiple parameters not meeting the margin
  requirements specified in the design principles (P)                      4. Multiple programmatic interfaces
  2. Inherited hardware with any single technical parameter not
  meeting the technical margin requirements specified in the
  design principles                                                      MANAGEMENT AND ORGANIZATION
                                                                          1. Inadequate team and management experience (P)
                                                                          2. Insufficient workforce
                                                                          3. Risk mitigation plan not completed during formulation phase
                                                                          4. Selection of science instruments late in phase B (P)


(P) = Primary risk subfactors; All others (S) = Secondary risk subfactors. Required budget reserve % = 20% + 5(number of P's)% + 2(number of S's)%




                                                        Managing Projects at JPL                                                                  8
Flight Project Practices

                                     • Applies to all projects regardless of
                                       implementation mode
                                     • Specifies what projects are required to do
                                     • Projects meet requirements, or get approval
                                       for deviation/exception
                                     • Communicates the JPL way of doing business,
                                       both internally and externally, e.g. to sponsors
                                     • Provides for projects the JPL implementation
                                       of 7120.5D
                                     • Provides for flowdown of requirements in the
                                       JPL prime contract
                                     • Establishes standards of uniformity
                                     • Compliance assessment is via the FPP
                                       Compliance Matrix
                                     • Deviations/Exceptions/Waiver process
                                       engages management in discussion of risks
                                       being accepted
                                     • Project and Engineering Management
                                       Committee (PEMC) provides the change
                                       authority
(Rules! DocID 58032)

                       Managing Projects at JPL                                9
Flight Project Practices: Content
Note: Sections 1-4 are Applicability, Purpose, Implementation, and Approval/Change Authority

                  Section 5                                   Section 6                                   Section 7
                 Management                                  Engineering                              Safety & Mission
                  Practices                                   Practices                                  Assurance
                                                                                                          Practices

      5.1 Life Cycle                             6.1 Mission Design                            7.1 Mission Assurance Management
      5.2 Planning                               6.2 Telecommunications Design                 7.2 Reliability Engineering
      5.3 Science                                6.3 Mission Operations                        7.3 Quality Assurance
      5.4 Project Organization, Roles &          6.4 System Engineering                        7.4 Software IV&V
      Responsibilities, Etc.                     6.5 Launch Services                           7.5 Electronic Parts Reliability,
      5.5 Work Breakdown Structure               6.6 Inheritance                               Application and Acquisition
      5.6 NEPA Compliance & Lnch Appvl           6.7 Planetary Protection                      7.6 Problem Reporting
      5.7 Spares, Testbeds, and Models           6.8 Flt Sys Fault Tolerance/Redundancy        7.7 Mission Operations Assurance
      5.8 Make-or-Buy Decisions                  6.9 Flight Hardware Logistics                 7.8 Systems Safety
      5.9 Scheduling, Cost Estimating, Etc       6.10 Materials, Processes, and
      5.10 Information Mgrt & IT                 Contamination Control
      5.11 Level 1 Scope Margin                  6.11 Software Development
      5.12 Project Staffing & Destaffing         6.12 Protection & Security of Flt H/W
      5.13 Project Priorities/Competing Char     6.13 Design & Verification for
      5.14 Acquisition & Surveillance            Environmental Compatibility
      5.15 Project & Institutional Reporting     6.14 Proj & Sys Level Functional V&V
      5.16 Reviews                               6.15 Configuration Management
      5.17 Risk Management                       6.16 Orbital Debris
      5.18 Waivers                               6.17 Hardware Development
      5.19 Crisis Response                       6.17 Mission Ops System Development
      5.20 Science Data Management
      5.21 Ext Comm & Public Engagement
      5.21 Lessons Learned
      5.22 Margins & Margin Mgt
      5.24 Export Control
      5.25 Technology
      5.26 Project Close-out
                                                Managing Projects at JPL                                                           10
Certification of Flight Readiness (CoFR)
• The objective of the CoFR process is to formally document and
  capture the processes and products that, when completed, constitute
  a system certified as flight ready.
    – Applies to all flight missions and instruments
    – Maximizes use of processes that we already do (minimal new work needs to be done)
    – Document is tailorable to specific missions or instruments (to be worked with OCE, SMA,
      Assoc. Dir.)
    – Process should be completed by the Mission Readiness Review (some open items
      extending to the flight readiness review are expected)

• Two areas are covered:
    – Products that document the project's adherence to JPL flight/mission development
      practices.
    – Tasks and products that document the project's residual risk to mission success.

• CoFR process part of Project Life Cycle
    – Organize libraries with later CoFR processes in mind, update library pointers continually
    – Use in reviews (SIR, FRR etc.) to show work being done
    – Compliance verified by audit (OCE, SMA, Assoc. Dir.) at earlier reviews
    – Start signature process within the Project well before FRR


                                    Managing Projects at JPL                                      11

More Related Content

What's hot

Oberhettinger
OberhettingerOberhettinger
OberhettingerNASAPMC
 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephenNASAPMC
 
Costello kenneth
Costello kennethCostello kenneth
Costello kennethNASAPMC
 
Fwd thinking
Fwd thinkingFwd thinking
Fwd thinkingmecocca5
 
Friedenthal.sandford
Friedenthal.sandfordFriedenthal.sandford
Friedenthal.sandfordNASAPMC
 
Designing at 2x nanometers Some New Problems Appear & Some Old Ones Remain
Designing at 2x nanometers Some New Problems Appear & Some Old Ones RemainDesigning at 2x nanometers Some New Problems Appear & Some Old Ones Remain
Designing at 2x nanometers Some New Problems Appear & Some Old Ones Remainchiportal
 
Unger massey
Unger masseyUnger massey
Unger masseyNASAPMC
 
Lawrence.jim
Lawrence.jimLawrence.jim
Lawrence.jimNASAPMC
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paulNASAPMC
 
SPL FDA ESG Green Belt Project
SPL FDA ESG Green Belt ProjectSPL FDA ESG Green Belt Project
SPL FDA ESG Green Belt ProjectJay Prakash
 
Mitchell.michael
Mitchell.michaelMitchell.michael
Mitchell.michaelNASAPMC
 
D4.5 A package of calibration procedures linked to SWAT through a generic pla...
D4.5 A package of calibration procedures linked to SWAT through a generic pla...D4.5 A package of calibration procedures linked to SWAT through a generic pla...
D4.5 A package of calibration procedures linked to SWAT through a generic pla...envirogrids-blacksee
 
Schaible.dawn
Schaible.dawnSchaible.dawn
Schaible.dawnNASAPMC
 
Kapruch steve
Kapruch steveKapruch steve
Kapruch steveNASAPMC
 
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...grssieee
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 

What's hot (19)

Oberhettinger
OberhettingerOberhettinger
Oberhettinger
 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephen
 
Costello kenneth
Costello kennethCostello kenneth
Costello kenneth
 
Fwd thinking
Fwd thinkingFwd thinking
Fwd thinking
 
Friedenthal.sandford
Friedenthal.sandfordFriedenthal.sandford
Friedenthal.sandford
 
Designing at 2x nanometers Some New Problems Appear & Some Old Ones Remain
Designing at 2x nanometers Some New Problems Appear & Some Old Ones RemainDesigning at 2x nanometers Some New Problems Appear & Some Old Ones Remain
Designing at 2x nanometers Some New Problems Appear & Some Old Ones Remain
 
Unger massey
Unger masseyUnger massey
Unger massey
 
Lawrence.jim
Lawrence.jimLawrence.jim
Lawrence.jim
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paul
 
SPL FDA ESG Green Belt Project
SPL FDA ESG Green Belt ProjectSPL FDA ESG Green Belt Project
SPL FDA ESG Green Belt Project
 
Mitchell.michael
Mitchell.michaelMitchell.michael
Mitchell.michael
 
9797v00 Boeing Smv Roi
9797v00 Boeing Smv Roi9797v00 Boeing Smv Roi
9797v00 Boeing Smv Roi
 
D4.5 A package of calibration procedures linked to SWAT through a generic pla...
D4.5 A package of calibration procedures linked to SWAT through a generic pla...D4.5 A package of calibration procedures linked to SWAT through a generic pla...
D4.5 A package of calibration procedures linked to SWAT through a generic pla...
 
Schaible.dawn
Schaible.dawnSchaible.dawn
Schaible.dawn
 
Kapruch steve
Kapruch steveKapruch steve
Kapruch steve
 
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
 
D081073[1]
D081073[1]D081073[1]
D081073[1]
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 

Similar to Gavin.tom

Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbainNASAPMC
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randallNASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leisingNASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leisingNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Fred.ouellette
Fred.ouelletteFred.ouellette
Fred.ouelletteNASAPMC
 
Fred.ouellette
Fred.ouelletteFred.ouellette
Fred.ouelletteNASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
Chen.tim
Chen.timChen.tim
Chen.timNASAPMC
 
Majerowicz
MajerowiczMajerowicz
MajerowiczNASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
 
Kelly crumbley
Kelly crumbleyKelly crumbley
Kelly crumbleyNASAPMC
 
Kelly crumbley
Kelly crumbleyKelly crumbley
Kelly crumbleyNASAPMC
 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.cNASAPMC
 

Similar to Gavin.tom (20)

Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Fred.ouellette
Fred.ouelletteFred.ouellette
Fred.ouellette
 
Fred.ouellette
Fred.ouelletteFred.ouellette
Fred.ouellette
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Chen.tim
Chen.timChen.tim
Chen.tim
 
Majerowicz
MajerowiczMajerowicz
Majerowicz
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Eosp fall 2010
Eosp fall 2010Eosp fall 2010
Eosp fall 2010
 
Kelly crumbley
Kelly crumbleyKelly crumbley
Kelly crumbley
 
Kelly crumbley
Kelly crumbleyKelly crumbley
Kelly crumbley
 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.c
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetEnjoy Anytime
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 

Recently uploaded (20)

Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 

Gavin.tom

  • 1. NASA PM CHALLENGE 2009 JPL DESIGN AND FLIGHT PROJECT PRACTICES February 24, 2009 Thomas R. Gavin Associate Director Flight Projects and Mission Success
  • 2. NASA/JPL Project Lifecycle JPL Flight Program/Mission Implementation FORMULATION APPROVAL IMPLEMENTATION Lifecycle Pre-Phase A: Phase A: Phase B: Phase C: Phase D: Phase E: Phase F: Phases Concept Concept & Preliminary Design Final Design & System Assembly, Operations & Closeout Studies Technology & Technology Fabrication Integration & Test, Sustainment Development Completion Launch NASA KDP A KDP B KDP C KDP D KDP E KDP F Decision ASSIGNED MISSIONS Points NASA Project Reviews MCR1 SRR2 MDR1,2 PDR1 CDR1 SIR1,3 ORR FRR1 PLAR CERR1,4 DR NASA Down Select Project Selection KDP C KDP D KDP E KDP F Decision Points AO-DRIVEN MISSIONS NASA Project Reviews PDR1 CDR1 SIR1,3 ORR FRR1 PLAR CERR1,4 DR Step 1 Step 2 JPL Project Proposal Reviews PIR Proposal Reviews PMSR1 Reviews MRB Other Reviews Final and Events SMSR, 5 Archival of Launch EOPM LV LRR, LV FRR Data (1) Review is followed by a JPL CMC. If the review immediately precedes a KDP, a Mission Directorate and/or Agency PMC/GPMC, as appropriate, are required prior to the KDP. Notes (2) The SRR and MDR may be combined (3) SIR is a “soft gate”, project may initiate Phase D work immediately upon completion of Phase C work products, absent a notice of discontinuance from the Program Manager (4) CERRs are established at the discretion of Program Offices. (5) At the end of the prime mission, if an extended mission is approved, the extended mission is still in Phase E. CDR – Critical Design Review LV FRR – Launch Vehicle Flight Readiness Review PLAR – Post Launch Assessment Review Legend CERR – Critical Events Readiness Review LV LRR – Launch Vehicle Launch Readiness Review PMC – Program Management Council CMC – Center Management Council MCR – Mission Concept Review PMSR – Project Mission System Review DR – Decommissioning Review MDR – Mission Definition Review SIR – System Integration Review EOPM – End of Prime Mission MRB – Mission Readiness Briefing SMSR – Safety and Mission Success Review FRR – Flight Readiness Review ORR – Operations Readiness Review SRR – System Requirements Review GPMC – Governing Program Management Council PDR – Preliminary Design Review KDP – Key Decision Point PIR – Proposal Implementation Review 05.01.2007 2
  • 3. Design Principles: • Applies to all flight designs, whether implemented in-house or at a contractor • Specifies essential attributes of JPL flight designs • Projects meet requirements, or get approval for deviation/exception • Captures 40+ years of lessons learned • Establishes robust design margins for high reliability • Defines ample margins for management of development risk • Requires a conservative approach to use of flight assets • Prescribes a comprehensive approach to flight system V&V • Compliance assessment is via the DP Compliance Matrix • Deviations/Exceptions process engages management in discussion of risks being accepted • Requires development of an Incompressible Test List and a Test as You Fly Exception List (Rules! DocID 43913) Managing Projects at JPL 3
  • 4. Design Principles: Content Note: Sections 1 and 2 are Applicability and Introduction Section 3 Section 4 Section 5 Section 7 Section 8 Section 9 Section 6 Flight System Mission Flight Deleted Flight Flight System Managed Flight Ops Design System (was SW) Scenario V&V Margins Design Design Design Design 4.1 General 8.1 General 4.2 Mechanical Configuration/Systems 6.1 Deleted 8.1.1 Min Op Times for Electronics 4.3 Power/Pyrotechnics 6.2 Mission Design Resource Margins 8.1.2 Handling & Test Constraints 4.4 Information System 6.2.1 Propellant 8.2 Pre-delivery Verification 4.5 Telecommunications System 6.3 Flight System Technical 8.2.1 Subsystem and Assembly Level 4.6 Guidance, Navigation & Control Resource Margins 8.2.2 Early Interface Testing 4.7 Propulsion System 6.3.1 General 8.2.3 System Level 4.8 System Thermal 6.3.2 System Mass 8.3 System Assembly, Integration & Test 4.9 System Fault Protection 6.3.3 System Power/Energy 8.3.1 System Assembly 4.10 System EMC/EMI 6.3.4 Deleted 8.3.2 System Integration 4.11 Flight Software System 6.3.5 Flight Software Margins 8.3.3 System Functional Verification 4.12 Flight Electronics Hardware 6.3.6 Power/Pyro System Margins 8.3.4 Flight Sequence Verification System 6.3.7 Telecom System Margins 8.3.5 System Fault Protection 6.3.8 Flight Electronics H/W Margins Verification 6.3.9 S/C Mechanisms Func Margins 8.3.6 System Stress Testing 6.3.10 Energy Margins for Cryo Sys 8.3.7 System Environmental Verification 8.3.8 Inter-system Verification 8.4 Launch Operations 8.4.1 Pre-mate Verification 8.4.2 Post-mate Verification 8.4.3 Launch-critical Support Equipment Managing Projects at JPL 4
  • 5. Margin Management: Technical Margin Mass 2% Margin 30% 20% 10% 5% (%) (Note 1) Power Margin (%) 30% 20% 15% 10% 10% (Note 2) Project PMSR ATLO Project PDR Project Launch (A-to-B Readiness Milestone (B-to-C/D CDR Transition) Review Transition) Definitions: Mass Margin = {(LV Allocation - CBE)/LV Allocation} x 100% Power Margin = {(Available Power - CBE)/Available Power} x 100% Notes: 1. Project Manager can specify other positive values, including zero 2. Power margins apply to mission critical and mission enabling modes, e.g., cruise, safing, etc. Managing Projects at JPL 5
  • 6. Margin Management: Schedule Margins Schedule 1 week/month Margin 1 month/year 2 months/year (2.8 months/year) Rate Flight ATLO Start to Implementation Start Missions/ Ship to Launch Site/ Delivery to to Delivery to Flight Instrument I&T Launch Site ATLO/ Experiment Start to Delivery to Launch Instrument I&T Projects To ATLO Definitions: Total Schedule = Planned Activities + Schedule Margin Schedule Margin = No Planned Activities, but Funded Schedule Schedule Margin Rate = Schedule Margin/(Planned Activity + Schedule Margin) Managing Projects at JPL 6
  • 7. Margin Management: Budget Reserves Budget Reserves 30% 30% 25% 20% 20% 10% (%) Flight Proposals— Proposals- Project/ Start Ship to Missions/ Step-1 &/or Step-2 &/or Instrument Project/ of Launch Flight Instrument AO Instrument AO PDR Instrument ATLO/ Site/ Experiment (Pre-A-to-A (A-to-B (B-to-C/D CDR Instrument Deliver to Projects Transition) Transition) Transition) I&T ATLO Definitions: Budget Reserve = {Unencumbered Budget Reserve/Estimated Cost to Go} x 100% Total Budget = Estimated Cost to Go + Unencumbered Budget Reserve Notes: 1. Cost to Go includes the funded schedule margin, but excludes the launch vehicle costs Managing Projects at JPL 7
  • 8. Cost Risk Subfactors COST RISK SUBFACTORS COST RISK SUBFACTORS MISSION COMPLEXITY SYSTEM ARCHITECTURE 1. Mission with multiple flight elements (P) 1. New system architecture (P) 2. Mission with multiple objectives 2. System architecture applied to new environment and technology 3. Precision lander mission 3. Level 1 Requirements not well defined in formulation phase (P) 4. Operation in harsh environments (P) 4. System with many ACS modes SIGNIFICANT TECHNICAL DEVELOPMENT 5. System with many deployments 1. Mission enabling spacecraft technology with TRL<5 (P) 6. Excessive reliability requirements (P) 2. Mission critical instrument technology with TRL<5 7.Pointing control stability requirements beyond state of art 3. Lack of fallback option for mission critical technology CONTRACTOR CAPABILITIES MATCH 4. Multiple interfaces affected by mission critical technology 1. Contractor inexperienced in mission application (P) NEW SOFTWARE OR UNVALIDATED SOFTWARE 2. Foreign Partner delivering hardware that is mission critical or on INHERITANCE critical path 1. New software architecture 3. Not enough experienced personnel available. 2. New fault protection PROGRAMMATIC /COST &SCHEDULE MARGIN 3. New software team 1. Less then 12-month Phase A/B 4. Undocumented software inheritance without the same development team 2. Less than 30-month Phase C/D TECHNICAL MARGINS 3. Schedule margins below guidelines (P) 1. New design with multiple parameters not meeting the margin requirements specified in the design principles (P) 4. Multiple programmatic interfaces 2. Inherited hardware with any single technical parameter not meeting the technical margin requirements specified in the design principles MANAGEMENT AND ORGANIZATION 1. Inadequate team and management experience (P) 2. Insufficient workforce 3. Risk mitigation plan not completed during formulation phase 4. Selection of science instruments late in phase B (P) (P) = Primary risk subfactors; All others (S) = Secondary risk subfactors. Required budget reserve % = 20% + 5(number of P's)% + 2(number of S's)% Managing Projects at JPL 8
  • 9. Flight Project Practices • Applies to all projects regardless of implementation mode • Specifies what projects are required to do • Projects meet requirements, or get approval for deviation/exception • Communicates the JPL way of doing business, both internally and externally, e.g. to sponsors • Provides for projects the JPL implementation of 7120.5D • Provides for flowdown of requirements in the JPL prime contract • Establishes standards of uniformity • Compliance assessment is via the FPP Compliance Matrix • Deviations/Exceptions/Waiver process engages management in discussion of risks being accepted • Project and Engineering Management Committee (PEMC) provides the change authority (Rules! DocID 58032) Managing Projects at JPL 9
  • 10. Flight Project Practices: Content Note: Sections 1-4 are Applicability, Purpose, Implementation, and Approval/Change Authority Section 5 Section 6 Section 7 Management Engineering Safety & Mission Practices Practices Assurance Practices 5.1 Life Cycle 6.1 Mission Design 7.1 Mission Assurance Management 5.2 Planning 6.2 Telecommunications Design 7.2 Reliability Engineering 5.3 Science 6.3 Mission Operations 7.3 Quality Assurance 5.4 Project Organization, Roles & 6.4 System Engineering 7.4 Software IV&V Responsibilities, Etc. 6.5 Launch Services 7.5 Electronic Parts Reliability, 5.5 Work Breakdown Structure 6.6 Inheritance Application and Acquisition 5.6 NEPA Compliance & Lnch Appvl 6.7 Planetary Protection 7.6 Problem Reporting 5.7 Spares, Testbeds, and Models 6.8 Flt Sys Fault Tolerance/Redundancy 7.7 Mission Operations Assurance 5.8 Make-or-Buy Decisions 6.9 Flight Hardware Logistics 7.8 Systems Safety 5.9 Scheduling, Cost Estimating, Etc 6.10 Materials, Processes, and 5.10 Information Mgrt & IT Contamination Control 5.11 Level 1 Scope Margin 6.11 Software Development 5.12 Project Staffing & Destaffing 6.12 Protection & Security of Flt H/W 5.13 Project Priorities/Competing Char 6.13 Design & Verification for 5.14 Acquisition & Surveillance Environmental Compatibility 5.15 Project & Institutional Reporting 6.14 Proj & Sys Level Functional V&V 5.16 Reviews 6.15 Configuration Management 5.17 Risk Management 6.16 Orbital Debris 5.18 Waivers 6.17 Hardware Development 5.19 Crisis Response 6.17 Mission Ops System Development 5.20 Science Data Management 5.21 Ext Comm & Public Engagement 5.21 Lessons Learned 5.22 Margins & Margin Mgt 5.24 Export Control 5.25 Technology 5.26 Project Close-out Managing Projects at JPL 10
  • 11. Certification of Flight Readiness (CoFR) • The objective of the CoFR process is to formally document and capture the processes and products that, when completed, constitute a system certified as flight ready. – Applies to all flight missions and instruments – Maximizes use of processes that we already do (minimal new work needs to be done) – Document is tailorable to specific missions or instruments (to be worked with OCE, SMA, Assoc. Dir.) – Process should be completed by the Mission Readiness Review (some open items extending to the flight readiness review are expected) • Two areas are covered: – Products that document the project's adherence to JPL flight/mission development practices. – Tasks and products that document the project's residual risk to mission success. • CoFR process part of Project Life Cycle – Organize libraries with later CoFR processes in mind, update library pointers continually – Use in reviews (SIR, FRR etc.) to show work being done – Compliance verified by audit (OCE, SMA, Assoc. Dir.) at earlier reviews – Start signature process within the Project well before FRR Managing Projects at JPL 11